January 13, 2010 Laura Lewallen Pb2 Architecture & Engineering 710 West Roselawn Drive Rogers, AR 72756 WAL-MART #1599 REMODEL, 11701 METCALF, OVERLAND PARK, KANSAS, PLAN REVIEW NUMBER PRS2009-00470 The Planning and Development Services Department reviewed the plans submitted on December 21, 2009. The following comments are from various divisions within the Planning and Development Services Department. When resubmitting your plans, include a cover letter complete with project name, address, and plan review number, and indicate how you have addressed each plan review comment. Please refer to the enclosed guidelines (Attachment A) and sample cover letter (Attachment B). Building Safety Division - Plan Review The following comments are from the Building Safety Division-Plan Review. Direct any questions regarding these issues to Gregory Maggiore M.C.P. at (913) 895-6248. Code references for this review: 2006 International Building Code ............................................ 2006 IBC 2006 International Fire Code .................................................. 2006 IFC 2006 International Plumbing Code .......................................... 2006 IPC 2006 International Mechanical Code ...................................... 2006 IMC 2006 International Fuel Gas Code .......................................... 2006 IFGC 2006 International Energy Conservation Code ....................... 2006 IECC 2005 National Electric Code ................................................... 2005 NEC Americans with Disabilities Act Accessibility Guidelines ......... ADAAG Overland Park Municipal Code ............................................... OPMC Building Safety Division/Plan Review 913/895-6205 Fax 913/895-5016 Laura Lewallen January 13, 2010 Page 2 of 5 1. Sheet D1 shows areas of demolition. Sheet D1.1 shows construction details of proposed dust barriers and proposed security enclosure. Please provide information for the placement and staging of these structures so as to not create means of egress deficiencies as per 2006 IBC Chapter 10 and cause a deficiency in fire sprinkler coverage as per NFPA 13. 2. Sheet D1 shows front entry doors 098A and 099A to be removed. Please clarify what exits, egress, and accessible means of egress will be maintained during this part of the project as required by Chapter 10 and 11 of the 2006 IBC. How will patrons and employees enter and exit the store? 3. Sheet A1 shows front entry doors 098A/B and 099A/B to egress an unconditioned vestibule. The Door Schedule on Sheet A8 does not specify tempered thermal glass with a U Value of .85 or better as required by Table 502.3 of the 2006 IECC; please clarify. 4. Sheet A1 and A8 show front entry doors 098A and 099A with glazing over head. Please clarify what type of glazing will be used in this location in compliance with Chapter 24 of the 2006 IBC and Table 502.3. 5. Please clarify where Temporary Dust Partition D shown on Sheet TC1 will be implemented to separate adjacent conditioned space to maintain 68F at 3 feet above floor as required by 2006 IMC (B) 309.1. 6. Sheet TC1 details call for plywood, wood studs and polyethylene plastic. This proposed structure is incongruous with Section 603 of the 2006 IBC; please clarify. 7. Sheet D1 Demolition Plan shows public toilet facilities to be removed. Please provide information on how patrons and employees will be provided with adequate toilets and accessible toilet facilities. Specification 01500 lacks information requiring accessible toilets; please clarify. 8. Sheet SP1 and SP2 show new ramps to be constructed. Please provide high point and low point elevation dimensions to verify no ramp exceeds 30” in height as required by Section 106.1.1 of the 2006 IBC and Section 4.8.2 of the ADAAG. 9. Sheet SP2 Details show hand rail extensions at the bottom of the ramps and stairs (not attach to building). The details do not provide the 27” maximum from the bottom of the hand rail extension to the top of landing as required by Section 4.8.5 Fig 27 of the ADAAG. The delineation shown is mathematically correct, however not showing the 27” can lead to confusion in the field and require revision by Section 106.1.1 of the 2006 IBC. Laura Lewallen January 13, 2010 Page 3 of 5 10. Sheet SP2 Details show a 4” gap between the bottom of handrail/guard and the top of the ramp and top of the landing. Ramps and landings with a drop off are required to have a minimum 2” edge protection as required by Section 4.8.7, Fig. 27 of the ADAAG. 11. Sheet A1 Partition Legend calls for plywood wainscot in various locations. This proposed construction is incongruous with Section 603 of the 2006 IBC; please clarify. 12. Sheet A1 and Door Schedule on A8 show new roll up doors to be installed in various locations. Neither Division 8 (08332) in the specifications or the drawings required the roll up doors to comply with DASMA 107 (a 90 MPH rated door) as required by Section 2603.4.1.9 of the 2006 IBC; please clarify. 13. Sheet A4.1 calls for installing a new roofing system over the existing roof. This application is not permitted under Section 1510.3 of the 2006 IBC with exceptions; please clarify. 14. Sheet A4.1 calls for installing a new roofing system over the existing roof. Please verify the existing structure is structurally capable to with stand the additional dead load as required by Section 1510.2 of the 2006 IBC. 15. Sheet A5.1 shows new Vestibule 711 with incomplete dimensions. Please provide complete dimensions for this space as required by Section 106.1.1 of the 2006 IBC. 16. Vestibule Doors 711 A and 711 B egress an unconditioned vestibule. The Door Schedule on Sheet A8 does not specify tempered thermal glass with a U Value of .85 or better as required by Table 502.3 of the 2006 IECC. 17. Sheet PH1.1 shows a 4” (B9) base in Toilet 301. Please revise to provide a 6” high base as required by Section 1210.1 of the 2006 IBC. 18. Please provide information that the wall materials with in 24" and 48” AFF adjacent to the water closets are to be constructed of materials (and substrate that clad the studs) that is not adversely affected by moisture as required by Section 1210.2 of the 2006 IBC for new toilet rooms. 19. The Bath Room Elevations and Finish Schedule on Sheet A7 call for NRP1 paint on walls behind and adjacent to toilets. Please provide information on paint to be used in theses locations that comply with the requirements of Section 1210.2 of the 2006 IBC. Laura Lewallen January 13, 2010 Page 4 of 5 20. Sheet S1.1 Slab Plan calls for a vapor barrier to match existing which is incongruous with other notes requiring a 6 mil Polyethylene vapor retarder. Please revise all notes to provide a 6 mil Polyethylene vapor retarder in compliance with Section 1910 of the 2006 IBC. 21. Sheet S1.1 calls out the FF EL = 100’-0” and Civil Drawings Sheet 6000 series calls out the finished floor elevation as 992.0. Please coordinate drawings as required by Section 106.1.1 of the 2006 IBC. (Sheet P1 notes condition.) 22. Sheet S6 calls out ½” Plywood Sheathing on Pharmacy Framing Plan. This proposed construction is incongruous with Section 603 of the 2006 IBC; please clarify. 23. Sheet E1.2 shows that there will be new exterior lighting. Please provide information that exterior lighting is in compliance with Section 505.6.2 of the 2006 IECC. 24. Electrical Drawings and Section 16100 2.2 E calls out for allowed conductors such as THHN conductors to be installed underground or under concrete slabs which the NEC designates as wet locations. THHN is not rated to be installed in a wet location as per Table 310.13 of the 2005 NEC; please clarify. 25. Civil Drawings show an accessible parking space that is not van accessible in the separate parking lot next to the garden center. This space is required to be van accessible by Section 1106.5 of the 2006 IBC. 26. Civil Drawings show an accessible parking space that is not van accessible in the separate parking lot next to the Garden Center. Please show the grades and slopes of this required accessible parking and the accessible rout to the entrance as required by Section 4.6 of the ADAAG. 27. Obtain a building sewer and connection permit from the Johnson County Wastewater Offices, 11811 South Sunset Drive, Suite 2500, Olathe, Kansas; or provide information that such a permit is not required. You may reach the Johnson County Wastewater Offices at (913) 715-8500. Current Planning Division The following comments are from the Current Planning Division. Questions regarding these issues should be directed to David Dalecky at (913) 895-6218. 1. Sheet A-2 - The elevation drawing calls for the glazed tile material to be painted. The Planning Commission did not approve of this material to be painted when the proposed renovations were reviewed and approved by the commission on October 26, 2009. Coordinate any proposed color changes and materials Laura Lewallen January 13, 2010 Page 5 of 5 changes with the Planning Department staff prior to implementing material changes to the building. Provide a general description (color name) of the unique colors, i.e. what is a common color name for the “Domino”. 2. Sheet A 2.2 - No signage is approved with the building permit drawings. Separate sing permits shall be submitted for review and approval by the code enforcement specialist. Engineering Services Division The following comment is from the Engineering Services Division. Questions regarding this issue should be directed to Mark Stuecheli at (913) 895-6026. 1. As was discussed in a 12/22/09 telephone conversation with Jeff Laubach of Phelps Engineering, increase from 25 feet to at least 30 feet the radius on the curb return that is proposed to be reconstructed at the southwest corner of the site where the main western drive intersects the shopping center loop road. That change will add an extra margin of safety to the effort to increase the effective width to the driveway to hopefully prevent the rutting in the island that currently occurs. If you have questions or alternatives to discuss on the above-mentioned items, please contact the appropriate person above, or contact me at this office, (913) 895-6248. Gregory Maggiore, M.C.P. gmz/cdm Enclosure c: Wal-mart Retail Trust III, 2001 SE 10th Street, Bentonville, AR 72712