Surface Treatment & Testing of 4R Cavity March 30, 2012 (Updated, Oct 31, 2012) 1 MOTIVATION This document summarizes the surface treatment and cold testing of the 4-rod UK cavity potentially take place at CERN. The cavity will operate at 400 MHz and be tested at 4K and 2K for validation of deflecting fields in a Niobium cavity. 2 TEST LOCATION AND TIMELINE The cavity will undergo heavy BCP at Niowave in the U.S. under the contract from Lancaster University and shipped to CERN. Additional surface treatment will be needed at CERN. Following chemistry, high temperature bake and HPR, vertical testing could take place at CERN. The SM18 tests will have to take place latest by August to finish testing before the refurbishment of the cryoline estimated for September 2012. Else, testing will have to take place early 2012. After refurbishment, a dedicated 2K cryostat will be available for testing. Checklist: 1. Leak tightness for the cavity (done by Niowave). Details to be provided by Niowave to CERN. In addition complete details of EDM and EB-welding is also required for the purposes of tracking the cavity performance through the treatment and test cycles at CERN. Optical inspection, endoscopic or x-ray will be done upon reception at CERN. 2. Heavy BCP to be performed at Niowave (150 microns removal) using acid flow. The cavity can be expected at CERN by mid or end of July. Recipe to be checked with Jlab on cavities made of solid Nb. 3. Special flanges (see BCP section for link) with degassing capability to be made for BCP to protect NbTi flanges and ports. Niowave will employ a vertical setup with chillers to control the temperature. 4. Sketch of the CERN BCP setup, flanges, material specs, piping, water tank and other equipment is shown in BCP section. All parts that can be adapted to the CERN systems should be recuperated, awaiting Niowave quote. 5. Degreasing, inspection and High temp bake at 600-800 deg C for hydrogen degassing will has been completed before a light BCP. HPR system available at CERN will be used after the light BCP and dried by pumping. 6. Beam pipe flanges with external SS are compatible with NbTi cavity flanges using copper gaskets. The thickness of the seal should be checked with CERN. It is strongly recommended to add NbTi flanges to cavity ports with high fields. 7. Collar for attachment to CERN support structure (both for BCP & Testing manipulation) should be made from SS316. CAD model of the structure is designed by LU engineers. Fabrication should be performed LU/Niowave 8. The input and pickup antenna geometry and exact penetration were defined and the antenna’s not available at CERN will be fabricated by LU/CERN. Pickup probes, two available at CERN, but need a change to the antenna shape to an L-shape. Ceramic material details for Q calculations were provided by CERN. 9. Two hybrid flanges, one for the beam pipe port to be used for pickup (CF100 to CF16) and second for top input coupler port (CF63 to CF16). One hybrid flange for the bottom beam pipe port (CF100 to CF35) for pumping port/gate valve 10. Test support structure used for SPL cavities (2.4m total length) can be used with a modification to the pumping port. Mathieu confirms that it fits but with very little clearance. Therefore, 2K helium level should be actively monitored to ensure proper level. If tested at 4.2K, removal of bubbles from the void of bottom side of rods should be conceived. 2.1 CAVITY ASSEMBLY A test program of the 4R cavity in the SM18 facility at CERN will potentially imply a surface treated and vacuum sealed cavity assembly. Clean room facilities are available in case of reassembly but it is preferred not to open the cavity vacuum processing and baking in a clean room. Therefore, input and all pickup probes are to be prepared in advance for assembly immediately after the cavity processing at the same site. Probes from the LHC 400 MHZ main RF cavities can be recuperated for these tests if there are not provided with the cavity assembly. Cavity assembly after the HPR can be performed in class 100 with laminar flow. Cavity Weight 35 kg Total Length (Flange-to-Flange) 800 mm Total Width (Flange-to-Flange) 322.5 mm Beam pipe diameter Beam Pipe Flange 84 mm 6 inches (100 CF, 152 mm) Side pickup ports diameter 64 mm Top pick up port diameter 40 mm Pickup port flanges 4.5 inches (63 CF, 113.5 mm) A schematic of the cavity profile (top and cross sectional view) are shown below with associated dimension in mm and inches. The total flange to flange length is 800mm. The cavity width with side ports is 322.5 mm. The beam pipe ports are 84mm in diameter with a 152 mm 100CF flange. The three ports on the cavity body have a port diameter of 64 mm on the side and 40mm on the top with a 113.5mm 63CF flange. All cavity flanges are made of NbTi and will be blanked off with stainless with copper gaskets. The exterior flanges will be coated with Niobium or copper at CERN for testing. 2.2 SURFACE TREATMENT & BAKING Due to the complexity of the structure and lack of experience on such devices, especially with EDM on solid Nb, it is believed that a significant amount of material needs to be etched for reaching high performance. The cavity is to undergo heavy BCP at Niowave. An initial degreasing with ultrasonic de-ionized water will take place before a surface treatment for degreasing and surface residue. The standard chemical mixture of HF+H2NO3+Phosphoric acid (1:1:2) can be used with the phosphoric acid as the buffer to stabilize the rate reaction. An initial etching of the surface of approximately 150 microns using some rotational mechanism could be used to ensure uniform removal of material on the surface. It should be noted that approximately 50 microns were already removed from the 4rod portions prior to welding according to Niowave. Frequency tracking during the removal and weighting the cavity before and after should be performed. If available, ultrasonic measurements from point to point should be carried out according to JLab suggestion. The cavity will be vertically oriented with acid flow rate of approximately 5 gallons/min and it might be reduced to 2gallons/min to further slow the material removal. The cavity will be cooled with external chiller sprayed on to the surface acting a heat exchanger with temperature kept between 5-9 degrees centigrade. The BCP is performed in one complete go. All flanges will be covered with standard plastic (viton) material and appropriate seals. After the chemistry, the cavity will undergo an ultra clean water rinse and a leak tightness of about 10-10 torr. The cavity surface fields (Left: Electric & Right: Magnetic) are shown below for input to chemistry experts and also placement of thermal sensors for testing. Note that the peak electric field is located between the rods facing each other along the beam direction and the peak magnetic field is located at the base of each rod slightly offset from the beam pipe region. Electric Field Magnetic Field Upon reception of the cavity at CERN, a degreasing with ultra pure water and endoscopic inspection will take place to note the surface features as received from Niowave after heavy BCP. A high temp bake at 600 deg C for hydrogen degassing has been performed in the UHV furnace of the bare cavity (see pictures below). This step should help alleviate the Q-disease and a generally accepted step in the SRF community. The exact temperature and time period is variable but past experience show 600 deg of approx 48 hours or more is sufficient. The cavity will then undergo an additional light chemical etching of 20-50 microns and rinsing. Following this light removal of the surface, a high pressure rinse with de-ionized water should follow to remove all impurities help improve the Q-slope at high fields and improve field emission properties. An additional UHV bake of at 120 deg for approx 48 hrs should take place either which is believed to help with high field slope. Safety aspects should be studied in detail with careful planning to avoid overlap with other chemistry activities. The chemistry team will require additional equipment to adapt the cavity to the BCP system at CERN (see schematic below). Any equipment used at Niowave to treat the cavity could be recuperated if it can be directly adapted to the CERN chemistry facility. This includes all plastic flange material, piping, water tank, and the support system to manipulate the cavity. Niowave will provide an estimate to procure this material. The plastic material specification can be similar to that given in the link below: www.es-technologies.com/pdfs/ENCM2080.pdf Information on the EB welding is also vital to avoid accidents that may damage the cavity during chemistry if the leak tightness of the weld is not adequate. A thorough inspection at CERN via optical and x-ray will take place to ensure all welds are adequate. A recipe as an initial place holder is described. This recipe can be replaced with a one after consultation from JLab. Niowave has informed that the EB-welding is 100% penetration. 2.3 CAVITY PICKUP PROBES A picture of in input probe used for the tests of the LHC main RF cavities. Two such probes exists which are mounted on a CF16 flange (see picture below). Either these pickup probes can be mounted on the 4R cavity assembly or similar probes be made to adapt to the existing flanges on the 4R cavity. The Qext for the measurements have to calculated and also measured with a network analyzer for calibration immediately after the cavity assembly. The appropriate Qext for a maximum amplifier power of 200 W and preferably well below this value to reach the deflecting gradient of 3 MV must be specified. The lengths of the antennas have been calculated for critical coupling at 2K both for the pickup (left picture below) and input (right picture below). The pickup and input have a calculated Qext of 6x1010 and 1.4x108 respectively. The antennas are approximately 7mm in diameter and are made of stainless steel. The orientation of pickup probe with a hook shape should be approximately -450 in the z-y plane which is sketched below. The flange has 6 anchors giving a freedom of approx. 600 per bolt, so the orientation of the pickup probe will only be approximate. -45 deg 2.4 TRANSPORT, MANIPULATION & TEST STRUCTURE Since the cavity body is prone to deformation, four stubs on the top and the bottom as shown in figure below is needed to ensure rigid support which is attached to two racetrack collars. A rotational degree of freedom is added for transport and manipulation of the cavity from the different stations. Lever arms to the same specification of the HIE-ISOLDE support structure will be designed to use the same transport carts between the different stations. The overall dimensions are shown below. All parts of the support structure should be made of SS316 non-magnetic material. 350 mm 802.54 mm 409 mm Since the contraction of SS and Nb are vastly different during cool down, a modification of this structure maybe needed to relieve any stresses on the cavity from differential contraction. A simple clamp structure on the beam pipe will be used for test purposes to avoid the issue of the differential contraction. The support structure used for the recent SPL cavity tests could be adapted for the UK 4-rod cavity for the insertion into the cryostat. A picture of the thermal shielding and the support structure is shown below. The exact fixation to the support has to conceived and fabricated for rigid support of the cavity. See for example the collar design used for the anchoring the ISOLDE cavity with the same support structure. The pumping ports should be located at the bottom ends of the beam pipe with a gate valve at the bottom which will enable the connection to the pumping system of the cryostat insert. A minor modification this support structure will be required to allow for pumping from the bottom of the cavity. This will also allow for the cavity to be transported directly from the rinsing facility, dried to the testing w/o opening the cavity vacuum. The test collar and support structure with the cross section is shown below. The integration into the cryostat is verified without any issues. Four transducers facing at an angle of approximately 45 deg at the top and bottom of the faces of the cavity will be used to record any second sound effects from cavity quench. Additional resistors maybe attached to the cavity surface to record the temperature during the tests. If the shutdown schedule doesn’t permit the testing at CERN in 2012, the test will take place in SM18 early 2013 in a dedicated 2K cryostat planned to be fitted during the SM18 shutdown. 2.5 RF POWER AND CONTROLS Amplifiers from the LHC 400 MHz cavities can be used to power the cavity. The power requirements from the coupling should be verified as the available power is limited to 200W. A new power supply with 500W capability is purchased and should be available for tests in 2013. Higher power would require modification of input adapters for power compatibility if string multipacting barriers limit the maximum the cavity field with the existing 200 W input power. Check the RF wiring for power transport. 2.6 CRYOGENICS AND TEMPERATURE MONITORING Thermal sensors are already available (how many) on the support structure. The placement of these sensors is likely to be on the lateral beam pipe region close to the rods where the magnetic fields are maximum. Four such sensors should suffice, but some additional sensors if available could be placed on the cavity body for additional temperature measurements during the measurements. Second sound acoustic transducers could also be used for quench detection. Such sensors are already used in the cryolab setup. Kitty has placed the order for the use 2nd sound equipment in the SM18 cryostat for 4R cavity testing. The T-mapping system however requires additional work which is not foreseen at CERN. Therefore, if this is required, LU should take the responsibility of fabrication of the T-mapping flexible tapes to be fitted for testing. 2.7 VACUUM AND ANCILLARIES The cavity after the surface treatment and UHV baking will undergo a high pressure rinse with all coupler probes, flanges and valves installed. The drying is done with active pumping and therefore can be directly connected to the cryostat support structure via the bottom valve for testing without opening the cavity vacuum. Pictures of the pumping port valve used to be used for the crab cavities are shown below. The appropriate hybrid flanges are made for mating CF100 on the beam pipe port to that of the pumping port setup and the integration into the cryostat was also verified without any issues. 3 SCHEDULE OF THE TEST PROGRAM 3.1 CAVITY RECEPTION & INSPECTION Since a light surface treatment and testing is foreseen at CERN, an optical inspection at various stages of the cavity processing is desired. A minimum of three inspections, one at reception, one after main BCP and the third after the UHV bake is highly desired. AS the cavity will undergo heavy chemistry at outside CERN, it is strongly recommended to assemble all flanges with appropriate blanks to minimize the cavity contamination during transport. The coupler probes and the pumping port valves will be assembled at CERN immediately after the final HPR. The cavity can be assembled to the support collar and transported directly to the SM18 facility where it can be tested. 3.2 CRYOGENIC TESTING All testing should be foreseen before the end of August 2012 to avoid conflicts with other testing and upgrade of the cryo line foreseen for September 2012. If all ancillary parts are fabricated and delivered to CERN with the cavity by mid-July, a surface treatment and cryogenic testing could be foreseen before the end of August or early August. However, this schedule doesn’t take into account any conflicts with other testing ongoing already at SM18 which may affect the planning. 4 RESOURCES & REQUESTS 4.1 MANPOWER All activities foreseen to take place at CERN will be coordinated and organized within the RF group and the vacuum group. Support from engineering for finalizing the structure support and additional clamps for cold testing will be required. Participation of a student/fellow during cold testing in SM18 from LU/DL is foreseen. 4.2 MATERIAL AND SUPPLIES The cavity and its support structure will be provided by LU/Niowave to the appropriate design specifications given by CERN. All support structures should be constructed out of non-magnetic SS-316. The cavity EB-welding and leak tightness information from Niowave should be transmitted to CERN with the cavity. Prior to BCP, the cavity should be welded with stiffeners to guarantee its structure integrity throughout the test cycle. CERN will be able to provide a limited amount of resources upon approval for the addition of stiffeners. The support structure rods on the exterior maybe threaded at the extremeties to allow for bolting on to the support plate of the test stand if this structure is used. All BCP related items that can be adapted to the CERN chemistry facility will be recuperated from Niowave. The exact list of items is pending a quote from Niowave. Additional equipment required both for chemistry and testing will be procured by CERN. All flanges and hybrids adapters for probes is foreseen to be procured from Niowave. Any additional flanges and adaptors required can be used from the CERN inventory. It is highly recommended to use NbTi flanges on the port of the cavity body to minimize the heat losses due to high fields. The flanges on the beam ports can be of stainless steel. 4.3 PLANNING Based on the Jun 30 meeting at CERN with the LU, an optimisitic planning is outlined. But delay in delivery anticipated due to addition of stiffeners (2 weeks) according to Niowave which will push the above schedule 3-4 weeks. Conflicts at the chemistry and testing are also taken into account and a new schedule is given below. New Planning as of Oct 19, 2012 Aug 31: Cavity arrives at CERN Sep 13-20: Vacuum H2 outgassing (48 Hrs, 600 deg C), no degreasing as Niowave confirmed that the cavity was degreased and packed in class100 clean room. Sep 23-Oct 23 (Weeks 39-42): Cavity inspection, Flanges and seal fixed on the cavity, RF measurements, leak tightness, optical/endoscopic measurements Oct 24-Nov 2 (Week 43-44): Light BCP, high pressure rinsing and handing to RF Nov 5- Nov 12 (Week 45): Transport, RF test stand preparation, vaccum & cooldown Nov 12- Nov 23 (Week 46-47): First RF tests at 2K Old June 30 Planning: Obsolete, see below for current planning Jul 16: Cavity arrives at CERN (Arrived Aug 31, 2012 due to delays) Jul 16-20: Cavity inspection, leak tightness, optical/endoscopic measurements Jul 23-27: Cavity degreasing (if needed), preparation of vacuum H2 outgassing Jul 30-Aug3: Light BCP, high pressure rinsing and handing to RF Aug 6-10: Transport, RF test stand preparation, vaccum & cooldown Aug 13-17: First RF tests at 2K