Minutes 27 June 2013 Bath Flood Management – Optioneering Workshop Meeting 26th June 2013 Present Richard Quarry - Capita Symonds Simon Martin - B&NES Major Projects Val Dawes - B&NES Major Projects Richard Jones - Black & Veatch Nigel Rushmer - Gleeds, Neil Swanson - Landscape Projects John Southwell – Environment Agency Ed Lockington – Environment Agency Nigel Smith – Environment Agency Mark Minkley (B&NES) Tim Hewitt (B&NES) Lucy Corner (B&NES) Apologies Derek Quilter B&NES) 1.0 Introductions 1.1 The parties around the table introduced themselves 1.2 EL advised that JS involvement from the EA perspective in the scheme would transfer to NS on a day to day basis 2.0 Purpose of the Meeting 2.1 SM introduced the scheme advising that the project is a joint delivery between B&NES and the Environment Agency. The B&NES Place Directorate is the Client. 2.2 SM and JS advised that the project has two interwoven objectives. The first being to offer flood relief mitigation and the second being to enable development to key sites around the central area. The project also feeds into the LEP with the ultimate objective of regeneration and job creation. The Flood Risk Assessment also supports the core strategy. 2.3 It was stated that the outcomes of this meeting would be fed into the Comms Plan. It was stated that there are two levels of options. The first is the strategic option which has resulted in the current engineering proposal. This is not intended to be further reviewed other than to advise on the process already Quays Office Park, Conference Avenue, Portishead, Bristol, BS20 7LZ Tel +44 (0)1275 840840 Fax +44 (0)1275 840830 www.capitasymonds.co.uk Capita Symonds Ltd Registered office: 71 Victoria Street, Westminster, London SW1H 0XA. Registered in England No. 2018542 Part of Capita plc www.capita.co.uk Action undertaken. The second level of options relates to the detail elements of the engineering proposal. 3.0 3.1 Contextual Background . It was advised that a considerable amount of work had already been undertaken to determine the strategic objective of the scheme. JS advised that a series of detailed studies have been undertaken. In 2005 Capita undertook a study of flood risk implications. This was followed by an Atkins study which focused upon linking flood relief works with a growth agenda in respect of brownfield sites .There was also a further report undertaken by White Young Green. JS advised that the Atkins report included stakeholder workshops and detailed feedback. It was agreed that this information would be obtained and reviwed in respect of the current project. 3.2 JS advised that the Atkins study was inconclusive in respect of flood attenuation at Bath Easton. 3.3 RJ advised that a full EIA is required and that part of this process requires demonstration that all options have been duly considered. SM reiterated that the current scheme provides most economic benefit and fulfills the requirements of the Council’s Place Agenda. There is also the benefit of much of the land ownership of the scheme is in the ownership of the Council. 3.4 JS advised that the impact of the proposed Twerton scheme would not impact in anyway upon this scheme. The flood gate opens anyway and as such the EA consider that the Twerton scheme does not stack up technically. 3.5 RJ stated that the current engineering proposal incorporates 20% allowance for Increase in river levels. 4.0 Option Review of the Current Engineered Proposal 4.1 A series of high level option proposals produced by Black & Veatch were presented to the meeting. 4.2 The removal of the mature trees and the options surrounding this key issue were the first item to discuss. 4.3 The option of forming a channel to create an island thus maintaining the trees was tabled. It was determined that there were in fact two options, the first being to form a bunded channel And the second to form a channel with water flowing through it which could either be open or culverted. 4.4 NS advised that the trees were not of good stock and had a short life expectancy. It was agreed that there are much more suitable tree species which could be replanted which would offer better ecological and aesthetically properties. It was ascertained that the Poplars were originally planted to provide a wind break. The meeting was advised that bat surveys were due to be conducted. Overall it was agreed that new planting would solve many of the current issues with the trees. Page 2 RJ 4.5 The issue of SUDS was discussed. SM advised that this has little impact in the city centre. The future developers would provide SUDS as part of future development proposals. The new proposed pumping station is only to be operational in times of peak flood. 4.6 It was stated that further dialogue on environmental mitigation measures will be required involving Canals & Rivers Trust and the River Regeneration Trust. SM advised that it is also key the Council’s Green Streets strategy is reflected in the scheme. 4.7 The meeting discussed the channel option and considered that this would make an inaccessible area and may damage the trees in any event. The cost impact of a channel or culverted scheme needs also to be considered. A culvert may also constrain development. It was also accepted that both the water corridor and bund/marshy corridor option would involve more land take. 4.8 There was dialogue in respect of dredging. JS advised that this is not an option as the weirs Merely nullify the impact. 4.9 There was discussion regarding the use of Green Park to form a conveyance area, thus avoiding the need to remove the mature trees and to potentially allow for the requirement of a new pedestrian footbridge. NS advised that there could be some intrinsic benefit in returning the park to its original condition which may increase usage. There would be requirement for sheet piling if this option were to go ahead. It was advised that Green Park is a risk in respect of residents. 4.10 The option to replant the existing trees was discussed. It was stated that there was no guarantee that the trees would survive and that these species are of little merit anyway 4.10 The second key option to be explored related to the sheet piled wall to the South Bank. It was suggested that this could be left to the individual developers. SM stated that this Was not an option as it was key to facilitating a marginal site. RJ advised that the extreme option would be to construct a new road bridge linking north and south banks thus eliminating the need to protect Lower Bristol Road from flood. This was discounted on grounds of land take and cost.. 4.11 There was discussion regarding mitigating environmental impacts in respect of the aesthetics of the sheet piled wall. The suggestion of floating pontoons with rushes and the potential of a green wall to the vertical sheet piles was discussed. A further option may be to create a 4m wide shelf at river level. 4.12 The current option regarding temporary flood works to the South Bank was discussed. There was discussion as to whether the demolition of Building 8a could be brought forward. SM stated that further planning advise is needed. SM 4.13 The next option to be discussed was the lighting. This has yet to be design but it was agreed That cognizance needs to be paid to ecological impacts and that a consistent approach is required. 4.14 There was discussion surrounding the flood barriers required to existing buildings on Lower Bristol Road. It was agreed that the EA will lead discussions with owners. EA do not favour direct intervention but do have this as an option. Flood jackets could be an alternative to fixed barriers. The option of the flood wall along Lower Bristol Road Page 3 was discussed, though this may have detrimental impact on carriage width which may not be agreed with Highways. However, both this option and that of the footbridge provide options for discussion with landowners to avoid being ransomed. The meeting agreed that the current proposed of flood boards is the most feasible. 5.0 Any Other Business 5.1 There was discussion on funding. B&NES will draw funding from RIF and have capacity to deliver the project without the EA grant which will drawn down at separate timescales. 5.2 RQ to forward details of Design Team Meeting minutes, risk register and programme to EA. 6.0 Next Meeting 8.1 It was agreed that a further meeting is required between the Design Team and the EA. The date of this will be confirmed once design is further developed. Page 4 RQ