PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Project Name Region Sector Project ID Borrower(s) Report No.:73197 Emergency Infrastructure Preservation & Vulnerability Reduction Project AFRICA Roads and highways (50%); Other social services (25%); Irrigation and drainage (15%); General water, sanitation and flood protection sector (10%) P132101 Republic of Madagascar Ministry of Finance Mrs. Andriambololona Vonintsalama, Secretary-General Telephone No.: +(261) 34 04 063 08 or +(261) 20 22 336 30 Email: secretairesg@mefb.gov.mg Implementing Agency Environment Category Date PID Prepared Estimated Date of Appraisal Authorization Estimated Date of Board Approval ARM Madagascar M. Jean Pascal Ramanamisata Directeur Général Autorité Routière de Madagascar Telephone #: +(261) 33 11 688 30 e-mail: "Ramanamisata Jean Pascal" <pascal.r-misata@arm.mg>, BN BVPI Madagascar [ ] A [X] B [ ] C [ ] FI [ ] TBD (to be determined) September 26, 2012 August 27, 2012 November 20, 2012 1. Key development issues and rationale for Bank involvement Introduction 1. This Project Paper proposes the financing of an Emergency Infrastructure Preservation and Vulnerability Reduction Project (the proposed Project) in the amount of SDR XX (US$102.0 million equivalent) to the Republic of Madagascar. 2. Following an unconstitutional change of government in early 2009, Madagascar has been experiencing a prolonged and severe political crisis, which has caused major economic and social impacts that have been exacerbated by a series of external shocks, and a withdrawal of most external funding. These concomitant events have caused a dramatic increase in the incidence of poverty, especially on the most vulnerable population, with a reduction of social protection safety nets and income-earning opportunities. The same events also caused a severe reduction in public investments and the maintenance of lifeline infrastructure1 including roads, agricultural and social infrastructure, resulting in their deterioration and decreased resilience to natural disasters such as cyclones and droughts, as well as a sharp decline in basic social service delivery. 3. As a result of the political events that led to the departure of the former President of the Republic in early 2009, preparation and approval of new lending and disbursements under the Madagascar portfolio were put on hold in March 2009 in accordance with OP/BP 7.30, Dealing with De Facto Governments. At the end of 2009, disbursements for the existing portfolio resumed progressively to preserve the projects’ human and physical assets and minimize risks. The full resumption of disbursements in May 2011 facilitated the initiation of a major portfolio restructuring which is almost completed. The restructuring aimed to enhance the portfolio’s impact through greater spatial concentration while exiting from activities that have become unviable in the present context or that are at risk of political interference. These actions will also ensure that the World Bank is better positioned to address the priority needs of the population, but with the portfolio aging and the amount of undisbursed resources dwindling, it is becoming increasingly difficult to make a meaningful impact. 4. The proposed Project, prepared in close coordination with other Development Partners, is part of a coordinated two-project International Development Association (IDA) response to address the emergency needs due to the crisis and external shocks cited above. Initially, most of the main Development Partners, including IDA, responded to the unconstitutional change in government by freezing disbursements and suspending direct communication with the de-facto authorities. However, as evidence emerged that the abrupt scaling back of many Development Partners-supported programs was contributing to a rise in poverty and a marked decline in human development indicators, all Development Partners resumed disbursements of some ongoing operations, provided they had a clear humanitarian focus and could be implemented through civil society organizations or semi-autonomous agencies not directly situated within mainstream line ministries. The European Union (EU) and African Development Bank (AfdB) are considering emergency support operations similar to the two projects proposed by the World Bank (the Bank). 5. The integrated, multi-sectorial approach that is being used for both proposed projects is designed to take advantage of natural synergies between sectors, in contrast to a more traditional approach that would involve the preparation of multiple stand-alone operations. The two proposed projects have been designed to target the most vulnerable populations and preserve critical institutional capacity whose collapse would lead to greater human suffering in the short term and raise the cost of re-engagement once the crisis has passed. 6. The Emergency Support to Critical Education, Health and Services Project (P131945, or Human Development Project), which is being prepared concurrently with the proposed Project, seeks to preserve critical education, health and nutrition service delivery in targeted vulnerable Infrastructure that is crucial to the populations’ economic and social life is considered as lifeline infrastructure. This includes transport infrastructure (especially, roads, for domestic transport, and ports, for both domestic and international transport), agricultural infrastructure (especially water control structures needed for irrigated agriculture), and social infrastructure (especially schools and health centers). 1 areas. It would primarily target regions where the negative impacts of the crises on human development indicators have been severe, where the additional resources complement those of other Development Partners and the government, and where existing implementation mechanisms are already in place for faster impact. 7. The proposed Project would contribute to preserve key lifeline infrastructure and reduce household vulnerability in targeted areas. It would restore all-weather access on key national roads through the spot rehabilitation of selected road sections, rehabilitate basic infrastructure for communities like primary schools and health centers, preserve agricultural capacity and provide short-term employment opportunities to vulnerable households in severely affected areas. It would also build resilience to further shocks through the provision of disaster risk management activities. In order to maximize synergies across activities and projects, feeder roads and agricultural activities would be mostly implemented along the key national roads rehabilitated under the proposed Project while the rehabilitation of health facilities, nutrition sites and schools would be implemented in the regions of intervention of the Human Development Project. Disaster risk management activities would be integrated in all activities. 8. The design of the proposed Project has been largely guided by past and on-going projects in Madagascar. The Project proposes to selectively continue those activities which are already implemented as part of the existing portfolio, are the most critical for the preservation of human capital and lifeline infrastructure and are readily implementable. For example, the cash-for-work sub-component proposed under the Project would scale up the cash-for-work program currently successfully implemented under the IDA-financed Emergency Food Security and Reconstruction Project (P120631). Likewise, in the transport sector, the proposed Project would continue similar activities financed under a series of three Adaptable Program Loans (APLs) 2 which started in early 2000 with thorough sectorial institutional reforms to support the policy of the Government to divest from operational activities, including the creation of the Road Authority (ARM) whose preservation would be supported by the proposed project. In the agricultural sector, the Project also proposes to continue activities which are currently successfully implemented under the Irrigation and Watershed Management Project (P074086). Last, the Global Facility for Disaster Reduction and Recovery (GFDRR) funded Track II technical assistance project is supporting the development of tools for improved disaster response planning and coordination. 9. The design of the proposed Project incorporates mitigation measures that reduce considerably any risk of political capture. Cognizant of the fact that the risk of political capture is especially high at the eve of the upcoming election cycle, mitigation measures have been embedded in the proposed Project including: (i) identification during Project preparation of the infrastructures (roads, schools, etc.) to be rehabilitated during the first year; (ii) allocation of resources and selection of beneficiaries for the cash-for-work program driven by formulas based on poverty data and household characteristics; (iii) incorporation of social accountability mechanisms at community level; and (iv) enhanced supervision to monitor project implementation and prevent political interference. Also, the strong IDA country presence would provide continual monitoring and surveillance of project activities while the recently created 2 APL1: Transport Sector Reform and Rehabilitation Project (P052208), 2000-2005, APL2: Rural Transport Project (P073689), 2003-2012, and APL3: Transport Infrastructure Investment Project (P082806), 2004-2012. Global Center on Conflict, Security and Development located in Nairobi, Kenya would provide incremental support and expertise for enhanced supervision. 10. The two IDA proposed Projects are being processed under emergency OP/BP 8.00 procedures to ensure a rapid focused response to critical needs. By maintaining sectorial dialogue with the Government and other partners and maintaining existing implementation systems, the proposed interventions would pave the way towards a fuller re-engagement with the Government of Madagascar once the situation permits. Rationale for the Proposed Bank Emergency Project 11. In the present context of deteriorating infrastructure and increased household vulnerability, the proposed Project aims to preserve lifeline infrastructure in critical sectors (notably transport, agriculture, health, and education) and to reduce vulnerability by creating short-term employment and income opportunities for poor households in targeted areas, through the provision of cash-for-work programs and agricultural intensification schemes. The objective of these interventions is to preserve the country’s key domestic and international economic activities, the capacity of disadvantaged segments of the population to carry out vital economic activities and improve their access to stable income-earning opportunities. The project also aims to increase the DRM capacity of the Government to anticipate and respond to natural disasters, and establishes a contingency financing mechanism to allow reallocation of project funds to respond to natural disasters. 12. The interventions to be supported under the proposed Project have been selected based on three criteria: (i) their potential to contribute to the preservation of critical lifeline infrastructure, the preservation of incomes and the reduction of vulnerability; (ii) the ability to be implemented quickly and to achieve rapid results on the ground; and (iii) the absence of alternatives means of supporting the intervention. Rehabilitation of key lifeline infrastructure, would help to slow, and hopefully reverse, part of the sustained decline in economic activity. Investments in agricultural intensification activities and cash-for-work programs would provide households with incomeearning opportunities to compensate for the nation’s depleted safety nets. Support provided to improving preparedness for natural disasters would help build resilience in the face of future weather-related shocks, and support to the ARM would help in further preserving both institutional and road assets. 13. The Bank has a demonstrated record of delivering results in the areas of focus supported by the proposed Project, as well as the knowledge needed for planning effective interventions and established implementation capacity. In the transport sector, the Bank has financed a series of successful lending operations that have played a major role in preserving, upgrading and expanding the national road and rail networks, as well as in preserving ports infrastructure. In the agricultural sector, the Bank has financed successful rural development projects that constitute the centerpiece of the national agricultural development strategy. In the social protection sector, the Bank has pioneered innovative cash-for-work programs that have made a significant impact in boosting the revenues of targeted groups in the population. With respect to disaster risk management, the Bank has led important trust-funded analytical work and implemented a series of activities including the development and adoption of anti-cyclone construction norms that have led to significant innovations in national programs. 14. The activities financed under the proposed Project have been designed to complement what is currently being supported or being proposed by other Development Partners. Because transport and agriculture sector support by the EU, the AfDB, and the International Fund for Agricultural Development (IFAD) is concentrated in the far south and southwestern areas of the country, the proposed Project is targeting regions along the central and northern tiers of the national road network, and the adjacent agricultural production zones. Social protection activities would similarly target these zones, while retaining the flexibility to respond to as yet unidentified needs in response to future disasters. Disaster risk management work would focus on strengthening national systems, while at the same time enhancing Early Warning Systems (EWSs) and disaster response capacity in the northern and southeastern parts of the country that are highly exposed to floods and cyclones. The geographic coverage of the proposed project is presented in the map at the end of Annex 1. 15. The proposed Project would take advantage of existing implementation mechanisms and build on ongoing activities so as to expedite implementation and deliver rapid results. It would support fast-disbursing activities that would directly impact beneficiaries’ access to specific services in the short term, while strengthening overall social services systems in the medium term. The proposed Project would adopt a “Build Back Better” approach that applies climateproof construction norms to rehabilitate and reconstruct infrastructure. Much of the infrastructure targeted by the proposed Project has been damaged by natural disasters, notably cyclones. The application of construction norms (either those recently developed by the Cellule de Prévention et de Gestion des Urgences (CPGU) with Bank support or those proposed to be developed as part of the Project) would ensure future resilience of infrastructure rehabilitated or reconstructed by the proposed Project, and thereby help to ensure the sustainability of project achievements. 2. Proposed objective(s) 16. The Project Development Objectives are to preserve key lifeline infrastructure and reduce household vulnerability in targeted areas. 3. Preliminary description 17. Component A: Rehabilitation of Lifeline Infrastructure and Disaster Risk Mitigation. This component would support the following activities: (i) rehabilitation of transport lifeline infrastructure; (ii) rehabilitation of community-level basic infrastructure; (iii) enhancement of Disaster Risk Management (DRM) capacity, including an establishment of a zero-budget contingency fund for use in the aftermath of a natural disaster. 18. Component B: Reduction of Household Vulnerability. This component would support the following activities in targeted areas: (i) distribution of agricultural inputs and rehabilitation of micro-irrigation systems; and (ii) provision of short-term employment. 19. Component C: Project Management and Coordination. This component would finance project management and coordination costs, including consultant services, technical assistance, training, and operating costs. 4. Safeguard policies that might apply Which safeguard policies might apply to the project and in what ways? 20. Activities supported under the proposed Project are expected to have a number of sitespecific adverse environmental and social impacts. Therefore, the following safeguards policies are triggered: OP/BP 4.01 (Environmental Assessment); OP/BP 4.09 (Pest Management), OP/BP 4.11 (Physical Cultural), OP/BP 4.12 (Involuntary Resettlement) and OP/BP 4.37 (Safety of Dams) (refer Table 4). What actions might be needed during project preparation to assess safeguard issues and prepare to mitigate them?] 21. As this operation is subject to OP/BP 8.00, Rapid Response to Crises and Emergencies, an Environmental and Social Screening and Assessment Framework (ESSAF) should be prepared to ensure compliance with the World Bank’s safeguards policies during implementation. 5. Tentative financing Source: BORROWER/RECIPIENT International Development Association (IDA) Total 6. Contact point Contact: Noroarisoa Rabefaniraka Title: Sr Transport. Spec. Tel: 5339+6043 / 261-20-225-6043 Fax: Email: nrabefaniraka@worldbank.org Location: Antananarivo, Madagascar (IBRD) 7. The InfoShop The World Bank 1818 H Street, NW Washington, D.C. 20433 Telephone: (202) 458-4500 Fax: (202) 522-1500 Web: http://www.worldbank.org/infoshop ($m.) 102 102 102