SOUTH CANBERRA COMPANY PLAYS AN
IMPORTANT ROLE IN CAPITAL METRO PROJECT
Today Capital Metro Agency commenced a program of utility services investigation works by Kambah company
Leach Steger that will provide further detail around the location of underground services along the light rail
corridor.
Minister for Capital Metro, Simon Corbell, said the works were a critical part of informing the project’s next
phase of design, in addition to providing more certainty around costs.
“This is an important and exciting step for the Capital Metro project. These investigations will provide the
Capital Metro Agency with required detail to further progress their early designs and to validate the projected
costs.
“I am very pleased to say this work is being planned and delivered out of local offices and using local experts.
The Canberra office of Brown Consulting is working closely with Kambah-based survey company Leach Steger
to deliver these works and this is a great example of Capital Metro engaging well with local industry.”
Utilities can present a significant risk for infrastructure projects and this activity is one of many steps teh
government is taking to ensure the first stage of light rail in Canberra is well planned, managed and delivered.
“A great deal of work has already occurred to get to this point and through desktop analysis and detailed
discussions with utility owners Capital Metro has developed a good understanding of the utility network. This
work will take that understanding to a far more detailed level.
“These investigations, which will include careful excavation techniques such as potholing and trenching, will be
delivered between Gungahlin and the City, starting at the Gungahlin end.”
The works are expected to take three to four months to complete, during which almost 1,000 small excavations
will be used to verify the location and the condition of the utilities. In each case a photo will be taken of the
infrastructure and this will be combined with spatial data that is fed into the stage one designs. The excavations
will then be carefully filled in and the area will be monitored to ensure the right levels are maintained.
“As these works will occur alongside and sometimes within a busy roadway, they will be managed carefully, with
a reduced speed limit, signage and in some instances, traffic controllers in place to coordinate traffic safely.
Aspects of this work that require traffic changes to busy intersections will be completed outside of peak times
to support efficient traffic and pedestrian flows,” Mr Corbell said.
Weekly updates on works progress and upcoming activities will be provided on the Capital Metro website.
Statement ends:
Media contact:
14 July 2014
Andrew Benson
6205 0434 (w)
0481 004 015 (m)
andrew.benson@act.gov.au
ACT Legislative Assembly
Phone: (02) 6205 0000 Fax: (02) 6205 0535 Email: corbell@act.gov.au
@SimonCorbell
www.facebook.com/simon.corbell
Download