MEEG401 Performance Criteria - PHASE 1 & 2 Synthesized for 10/5 & 7 Reviews Reference: Phase 1 & 2 Detailed Evaluation Sheets on the following two pages Design Synthesis: A feasible commercial system design concept was developed at the overall system level and/or at various sub-system levels, based on the project sponsor’s business goals and specific requirements; and a compelling case was made that the concept was the best among viable alternatives from the standpoint of: - Potential satisfaction of Sponsor’s requirements, and performance/cost metrics derived from them - Benchmark comparison with, and maximum integration of, current technology that was researched - Application of engineering based analysis, and decision making Resource Management: It was evident that the project was proceeding as planned, and that a viable path forward plan to was developed to design, build, and testing of a prototype system to demonstrate attainment of targeted performance/cost goals . Viability of the plan was established via inclusion of the following elements: - Task/time elements with project specificity - Extended team resource allocation - Critical path analysis, including contingency plans in areas of technical or resource/time uncertainty - Cost estimate of prototype approved by sponsor (purchase of: fabricated components; materials; and equipment) Communication: The above was presented in a clear, concise, and professional manner; and it was evident from the material presented, and the post review dialog with the advisor team, that the team had maintained a high level of continuous communication with their sponsors, and other resources. Glossary: FYI: UD definitions: A = excellent B = good C = fair D = poor my expansion for senior design: 100, A+ = perfect 95, A = excellent 90, A/B = very good 85, B = good 80, B/C = OK 75, C = average 70, C/D = weak 65, D = poor 60, D/F = awful/lousy/stinks <60, F = not acceptable MEEG401 Performance Criteria - PHASE 1, Project Requirements & Scope Dimension Summary Detailed % of Phase Grade Design Synthesis Articulated the business need and project benefits/value. Defined a project scope that can be accomplished with available resources and that aligns with the sponsor’s goal. Resource Use Effectiveness Developed ‘first-cut’ project execution plan in conjunction with scope requirements, including consideration of broad project steps and resource utilization given time constraints of the course. Determined relevant customer(s)/partner(s) and their goal(s) for the project. Worked closely with sponsor to define project scope to a degree that all constituents are satisfied. Derived appropriate wants/needs/constraints, and Developed key performance/cost measures (metrics) that define business success for you sponsor; and Set appropriate ‘current state’ and future ‘target values’ for key performance/cost measures. Developed and articulated a business/engineering basis for the above structure , including an understanding of the hierarchical and cause – effect relationship of the above wants/metrics variables. Initiated background research and began benchmarking competitive and applicable technology. Demonstrated technical competence for all key project aspects. 55 Completed the above design-synthesis phase results on time. Functioned as a team: o finalized the team resume and reviewed with sponsor and advisor, o professionally executed a peer review, and through interaction with advisor, etc., moved forward as a team; taking corrective action(s) as needed. Developed initial plan for resources ($; people; equipment; etc ) and their task-time allocations. 10 Contacted sponsor immediately and began intensive interaction. Demonstrated continuous communication: o via regular contact with sponsor, o via weekly updates/meetings with advisor, o via initiation & then regular use of online logbook. Communicated clearly and professionally with advisor and sponsor (written & oral means). Developed team norms to facilitate team communication; and justify objective peer evals. 35 Communication Demonstrated continuous communication between all team members, advisor, and sponsor. All interactions were timely & were conducted professionally. MEEG401 Performance Criteria - PHASE 2, Concept Generation/Selection & Project Plan Dimension Design Synthesis Summary Developed a feasible design concept that was justifiably best among viable alternatives - both at the overall system level and at various sub-system levels (as appropriate). Detailed Updated, as necessary, project requirements/scope - given new/better project information. Continued and targeted background research on required key sciences/technologies. Presented viable (different) concepts focused upon the key performance functions. Benchmarked best practices for functionalities that are relevant to viable concepts. Developed key performance measures for viable concepts. Used engineering evidence to present the ‘best’ path-forward concept. % of Phase Grade 55 Articulated a project plan that demonstrates senior-design project completion appears to be attainable. Resource Use Effectiveness Reviewed progress-to-date and presented project-specific details of the plan; that is, identified resources (people, time, equipment, etc.) and set of project-specific milestones that are clearly aligned with completing a senior-design prototype that satisfies project goal. Completed above design-synthesis phase results on time. Functioned as a team: o professionally executed a peer review, and through interaction with advisor, etc., o moved forward as a team; taking corrective action(s) as needed. Developed project-specific task/time (Gantt) chart identifying critical milestones. Integrated needed resources considering extended team (sponsor + UD + contacts). Identified any critical ‘long lead’ items and have under control. 25 Developed complete cost estimate for envisioned proofof-concept prototype. Communication Demonstrated continuous communication between all team members, advisor, and sponsor. All interactions were timely & were conducted professionally. Demonstrated continuous communication: o via regular contact with sponsor, o via weekly updates/meetings with advisor, o via regular use of online logbook. Communicated clearly and professionally with advisor and sponsor (written & oral means): o presentations were clear (using appropriate visuals) and concise, o formal presentations were professionally delivered, o responses during question & answer dialog were professional and to the point. 20