NSW section in s43A7 notice NOTICE BY THE NSW GOVERNMENT UNDER SECTION 43A(7) OF THE WATER ACT 2007 This section for the s43A(7) notice expands on some issues raised in both the consensus notice and NSW’s joint notice with Victoria, as well as providing some specific NSW concerns with the altered draft Basin Plan and supporting Commonwealth programs. SDL adjustment mechanism 1. As specified in the joint notice with Victoria, NSW considers that the SDL reduction mechanism must first focus on offsetting the proposed 2,750 GL reduction target. 2. The SDL adjustment mechanism must be workable to enable it to deliver offsets of at least 650 GL to minimise the impacts on Basin communities of the SDL reductions. The environmental outcomes achieved by the Living Murray environmental works and measures must be incorporated into the SDL adjustment mechanism to contribute to an offset reduction. Similarly, additional water inflowing to Menindee Lakes from the northern SDL reductions must be able to offset SDLs downstream. 3. All measures must be explored to limit the further buyback of water licences to meet the 2,750 GL reduction target, consistent with the NSW position that buyback of water licences should not exceed 3% per catchment per decade. 4. If constraints are then able to be lifted that could allow for increased flows and a subsequent increase in the SDL reduction by a further 450 GL without third party impacts, then this must occur only after water recovery to meet the 2,750 GL reduction has been contracted or committed to. All water recovery, including on-farm efficiency projects must first contribute to bridging the gap. 5. NSW believes that undertaking water recovery to achieve the 2,750 GL reduction, while concurrently seeking to further increase the reduction by another 450 GL will cause confusion and lack of clarity on whether measures are being properly attributed. This issue has been raised as a significant concern by NSW stakeholders. 6. Further, NSW reinforces the position in the consensus notice that additional water must only be recovered by measures such as on-farm efficiency measures which do not create socio-economic impacts. The details of the additional recovery proposal need to be provided by the Commonwealth and incorporated in its water recovery strategy. NSW will not support any open licence buyback to achieve any additional reduction beyond 2,750 GL. Apportionment 7. NSW position remains that apportionment of the shared downstream recovery volume should be allocated between jurisdictions according to their share of the Baseline Diversion Limits (BDL) and, in the case of the southern basin, specified in the Basin Plan. The apportionment by BDL clearly recognises that all extractions impact on river health. However, given the need for further work on the shared downstream reduction, NSW will work with Queensland on finalising the volume and the allocation between states and catchments. 8. The principles for apportionment of the downstream shared reduction components in the northern and southern basin must be consistent to enable equitable apportionment between States across the Basin. NSW requires that the principles for water apportionment across both the northern and southern basin must be equity, transparency and consistency and preferably incorporated in the Basin Plan. Groundwater SDLs 9. NSW has provided detailed information in the joint notice with Victoria on its concerns with the MDBA’s approach to determining SDLs for four deep saline aquifers in NSW. NSW requires that the Basin Plan take into account the NSW expert hydrogeological advice and the NSW policy settings that recognise and account for surface water to groundwater connectivity. 10. NSW can demonstrate that it has, and will continue, to apply groundwater management mechanisms to ensure that the SDLs requested by NSW in these four relatively undeveloped aquifers will not have impacts on other water users including environmental water holders, the sustainability of the groundwater resource and any surface water resources. If appropriate, the MDBA could include a requirement in the Basin Plan requiring jurisdictions to regularly report on how extractions are being managed in aquifers where it has agreed to an increase in the SDL. Date of commencement of SDLs 11. The consensus notice recognises that generating water savings through the full range of infrastructure, efficiency and other measures will take longer than 2019 to fully realise outcomes. 12. NSW reiterates that the date of effect of the SDLs must be from 2019. Given the SDL adjustment mechanism and the roll out of infrastructure projects, full compliance with the SDLs cannot be fully achieved until these measures are implemented. 13. For the balance of water recovery through licence purchase, the NSW position remains that water purchase should be limited to 3 percent of BDL per water source per 10 year period and this should be undertaken in consultation with the State Government and communities. On an annual basis, this equates to purchase rates of approximately 15 GL per year for the southern NSW Basin and 5 GL per year for the northern NSW Basin. 14. As currently planned, the SDL adjustment mechanism and the recovery of water through the full range of mechanisms, should mean that the Commonwealth can maintain their licence purchase within this rate and still meet or be close to their goal of bridging the gap by 1 July 2019. 15. Should the SDL adjustment mechanism and other means to recover water not generate the recovery volumes currently anticipated, the Commonwealth’s purchased water recovery to make up any shortfall must take place at the NSW approved rate. 16. NSW requires that any further licence purchases are strategic and in accordance with a strategic water recovery plan. Third Party Impacts 17. As set out in the joint notice in Victoria, the delivery of environmental water and any relaxation of constraints must fully address the issue of third party impacts, including liability issues. 18. Further, NSW requires the Plan to include a specific statement that the Plan will not result in the compulsory acquisition of land, easements or water licences. Implementation funding and structural adjustment for communities 19. NSW has limited capacity to deliver on the wide range of implementation obligations placed on Basin States by the Basin Plan. NSW notes that while the consensus notice seeks to tie implementation to Commonwealth funding, there is still no Commonwealth commitment to fund the activities. 2 20. NSW requires that the Commonwealth must have in place an agreement with NSW for funding of new or extended activities for NSW for the life of the Plan, before the Basin Plan commences. This will require up-front payments to the State rather than payment in arrears. 21. While NSW supports the development of an agreement between the MDBA and each Basin State regarding implementation obligations, it is still critical that the MDBA clarifies the implementation requirements for States before it finalises the Plan. This review should ensure that all water management requirements in the Plan are appropriate to achieve defined, improved water management outcomes. 22. Of concern is that there has been no progress on the development of a structural adjustment assistance package for communities impacted by water licence buybacks. Resolution of this is essential before the Basin plan is submitted to Parliament. The NSW Submission on the draft Basin Plan April 2012 contained constructive proposals for a cohesive structural adjustment package that should be addressed by the Commonwealth. Clarification of wording and intent 23. NSW has raised on a number of occasions concerns with the wording of various clauses of the Basin Plan. NSW requires that the MDBA works with jurisdictions over the next few weeks to clarify a number of provisions in the Basin Plan. 24. A case in point is the definition of floodplain harvesting in the Basin Plan as “the taking of water from a flood plain after it leaves a water course during a flood.” Water on the flood plain can originate from a river, local runoff or rainfall. Under the NSW approach to flood plain harvesting, any water taken off the floodplain would be managed as floodplain harvesting irrespective of is origin. NSW calculates the volume that can be taken under a basic right and exemptions and any excess to this will require a floodplain harvesting access licence. 25. The Basin Plan approach that requires the specification of the origin of water will be difficult to assess to prove and puts at risk NSW's ability to fully manage flood plain harvesting. 3