Red Swamp Crayfish - Germantown Executive Summary By Andrew Notbohm Water Resources Management Specialist, Wisconsin DNR December 19, 2013 Discovery – August, 2009 In late August, 2009 the Wisconsin Department of Natural Resources (WDNR) received a report about a possible invasive crayfish species inhabiting a 4.88 acre stormwater pond in the Esquire Estates community in the Village of Germantown, Wisconsin. The report was investigated and it was determined that the red swamp crayfish had established itself in this pond. This was the first documented discovery of this species in Wisconsin. Because red swamp crayfish are considered to be one of the most invasive crayfish species in the world, the WDNR felt it was necessary to act quickly. Many different methods were used to control this pest, as effective invasive species eradication/control generally is not successful with a single method. Initial Monitoring – Fall, 2009 During the fall of 2009, 2,390 red swamp crayfish were captured and removed from the Esquire Estates Pond. Hand netting resulted in the removal of 247 of these crayfish while 2,143 crayfish were removed via minnow traps. The catch per unit effort (CPUE) of the minnow traps was 0.19 crayfish/day*trap. In addition to capturing red swamp crayfish from the Esquire Estates Pond, nearby ponds were also monitored for the presence of this species. Red swamp crayfish were found in a small pond located next to the Germantown Police station. This pond was connected to the Esquire Estates Pond via a drainage ditch that meandered through Ashbury Woods. A barrier constructed out of Nicotarp was installed around the entire Esquire Estates Pond and Police Pond to prevent emigration. Chemical Treatment and Drawdowns – Fall, 2009-Winter, 2009-2010 On November 12, 2009, the WDNR treated the Esquire Estates Pond with San-IKing which is a 12.5 percent bleach solution. The pond received 500 gallons of product to reach a concentration of 50 ppm. Burrows created by red swamp crayfish were identified and were treated with a 200 ppm solution of this product. The Police Pond was also treated with San-I-King at the same rate as Esquire Estates Pond. Post treatment monitoring was performed in late fall, 2009 which resulted in the capture of zero crayfish. Throughout the winter of 2009-2010, the Esquire Estates pond was held below normal water level and the Police Pond was drawn down via pumping with the goal of freezing burrowed crayfish. Fish Stocking and Crayfish Monitoring – Spring, 2010 In May, 2010, Fisheries staff stocked the Esquire Estates Pond with largemouth bass, smallmouth bass and rock bass to help control the remaining red swamp crayfish population through predation. Esquire Estates Pond was monitored with traps April 1 through June, 2010. During this time, 120 red swamp crayfish were caught and removed. Total Average CPUE data is not available for this time period. This data indicated that the mechanical removal and chemical treatment performed in fall, 2009, the drawdown performed throughout the winter of 2009-2010 and the fish stocking performed in spring, 2010 contributed to a 90% decline in the red swamp crayfish population. Funding Issues and Police Pond Chemical Treatment – July-December, 2010 Due to the intensive work performed up to this point, funding was limited during this six month period in 2010. Funds were secured, however, to perform a second chemical treatment on the Police Pond. In November, 2010, Fisheries Staff treated the Police Pond with Pyronyl 303. Pyronyl is a botanical pesticide labeled for use in the United States in wetlands and terrestrial environments, but not ponds. Therefore, a Federal permit was needed to apply this product to the Police Pond. Pyronyl was the desired chemical to use during the Esquire treatment but the necessary permit was not obtained in time. After the Pyronyl treatment, the Police Pond was routinely dewatered to keep it as dry as possible throughout the winter of 2010-2011 to increase the effect freezing would have on any crayfish that burrowed prior to the treatment. Monitoring – Summer, 2011 Students from the Wisconsin Lutheran College were hired and trapping resumed in the Esquire Estates and Police Ponds to evaluate the success of the 2010 efforts. Due to the timing of the chemical treatment and the inability to maintain the dewatered state of the Police Pond, red swamp crayfish were captured in the Police Pond throughout 2011. Between May and September, 2011, 40 red swamp crayfish were captured and removed from the Police Pond with a CPUE of 0.02. During the same time span, 918 red swamp crayfish were captured and removed from the Esquire Estates Pond with a CPUE of 0.17. Other nearby waters within a mile were monitored, including 13 ponds and the Jefferson Ditch tributary to the Menomonee River but no red swamp crayfish were captured. Great Lakes Restoration Initiative Grant – Late Summer, 2011 In August/September, 2011 the WDNR was awarded a $286,843.00 grant from the United States Environmental Protection Agency to attempt eradication of the red swamp crayfish population. Filling In Police Pond – October, 2011 A portion of the recently acquired grant was used right away as WDNR staff from Fisheries, Water Resources, and Equipment Operations as well as staff from the Village of Germantown worked together to fill in the Police Pond, thus eliminating red swamp crayfish from this site. The pond was dewatered and amphibians and reptiles were transferred to the adjacent Ashbury Woods. Next, the banks were excavated and the material was used to mix with the bottom sediments of the pond. Finally, the pond was filled in with crushed road millings and compacted to crush and/or encapsulate any remaining crayfish. 2 Monitoring – Summer, 2012 The Esquire Estates Pond and the Ashbury Woods ditch were monitored with traps April through October, 2012. During that time, 2,480 red swamp crayfish were captured and removed from Esquire Estates Pond. Average CPUE for this time period is not available but catch rates were highest in late June and July when water temperature was warmest. Eleven nearby ponds within a mile of Esquire Estates were monitored in 2012; all were negative for red swamp crayfish. Two additional sites on the Menomonee River were sampled in 2012; both negative for red swamp crayfish. Development of Final Eradication Plan – June-September, 2012 Up to this point, much work had been done to eliminate this pesky invasive species. Red swamp crayfish had been trapped, poisoned, and their habitat had been removed but they still were present in the Esquire Estates Pond and potentially present in the adjoining Ashbury Woods ditch. To address this issue, an eradication plan was conceived though many meetings and intensive experiments. Construction contractors and a worldwide crayfish expert from the U.K. assisted in the development of the plan. The resulting strategy included a large scale shoreline and ditch manipulation in the Esquire Estates Pond and Ashbury Woods ditch. In addition to the manipulations, a second Esquire Pond chemical treatment was scheduled to take place following construction completion. Similar to the second Police Pond treatment, the second Esquire Pond treatment would use Pyronyl instead of bleach. Ashbury Woods Construction – October, 2012 The first phase of the eradication plan included a manipulation of the drainage ditch in Ashbury Woods from the outlet of the former Police Pond to the culvert at Western Ave. WDNR Fisheries, Water Resources and Wildlife staff cleared a swath on both sides of the ditch to maneuver equipment. Skid loaders were used to scrape a more defined channel through the woods which would hold the majority of future water flow. Once the channel was shaped, 12 ounce road construction fabric was placed in the channel and on the perimeter of the channel. This fabric was used because it was determined that red swamp crayfish could not penetrate it when burrowing. After the fabric was placed, approximately five inches of crushed number two limestone was spread across the fabric. Crushed number two limestone was used because it was determined that this would prevent the burrowing of any red swamp crayfish. Lastly, after the channel was rocked, any disturbed areas were seeded and covered with erosion control fabric. Esquire Estates Construction-Phase I – November-December, 2012 Similar to the Ashbury Woods project, the banks of the Esquire Estates Pond were excavated to disturb any crayfish burrows and shaped to create a slope that would allow the placement of fabric and rock. A contractor was hired to perform the construction work on the island which consisted of brushing and excavating the banks and placing the 12 ounce road fabric and three to six inches of number two stone in a 15-20 foot wide band around the entire 899 feet of the island. WDNR Fisheries, Water Resources and Equipment Operations staff worked on the perimeter of the pond which included excavating and shaping the bank as well as placing the 12 ounce road fabric and four to 3 eight inches of number two stone in a 10-25 foot wide band around 1,450 feet of bank. To accomplish this, an access road was first carved out at the base of the bank and the bank shaping, fabric and rock work was done in a retreating fashion. In addition to the pond itself, WDNR staff performed the same procedure on the inlet to the pond placing the fabric and rock in a 132 foot band 15-20 feet wide. Unfavorable winter weather conditions forced work to be stopped in mid-December, 2012. Completion of the project was then planned for 2013. Monitoring – Summer, 2013 Traps were set in the Esquire Pond May through August 2013. Thanks in part to the bank modification work done the previous fall, only 39 red swamp crayfish were captured throughout the 2013 sampling season for an average CPUE of 0.007. The majority of these crayfish were captured along the shoreline of the pond that had not yet been covered with fabric and rock. Once again, surrounding ponds and streams were monitored with no red swamp crayfish observed. Esquire Estates Construction-Phase II – Fall, 2013 In September, 2013, the same contractor that did the Esquire Pond island work completed the remainder of the excavating, fabric and rock work, with the assistance of some WDNR staff. A five to fifteen foot band was shaped (where needed) and lined with fabric and four to eight inches of number two stone along 1,160 feet of shore. Due to steep topography, the remaining 80 feet of shore received #3 rip rap stone on top of the fabric instead of the number two crushed stone. Esquire Estates Chemical Treatment – Fall, 2013 With the bank and channel modifications to the Esquire Pond and the Ashbury ditch completed, the final phase of the eradication plan included another chemical treatment to the pond, this time with Pyronyl. During this two day treatment, WDNR Fisheries and Water Resources staff used a combination of spraying and injecting to deliver the chemical to the pond and the surrounding banks, including the drainage ditch between the former Police Pond and the Esquire Pond. Post Chemical Treatment Monitoring – Fall, 2013 Following the chemical treatment, the pond was monitored to determine the duration and the level at which the chemical persisted in the water. Water samples were collected from two points within the pond (Figure 1) and tested for Pyrethrins. These samples were collected for nearly one month post treatment and indicate that the entire pond retained a high level of the chemical for at least five days (Table 1, Figure 1-2). In addition to the water samples, water quality parameters were measured at the same points as the water sample collections. This data is presented in table 2 and table 3. Finally, bio-assays cages were used to assess the ability of crayfish and minnows to survive in the pond. The cages were stocked with either crayfish or minnows and were checked periodically to determine the condition of the specimens. Bio-assay crayfish continued to die within a few hours of exposure up to three weeks after the treatment. The results of 4 the bio-assay cages and residual Pyrethrins water samples indicate that the chemical treatment was a success. Future Monitoring – Summer, 2014 As a result of the activities described above, the WDNR is hopeful that red swamp crayfish have been eradicated from the Esquire Estates Pond, Police Pond, Ashbury Woods ditch and have not spread to any nearby waterbodies. The Esquire Pond and neighboring ponds and streams will be monitored May through August, 2014 to see if this extremely invasive species has in fact been eradicated from this area. 5 East Basin Sample Point West Basin Sample Point Figure 1. Ariel map of the Esquire Estates Pond. Water samples and water quality measurements were taken from multiple depths at one point in the West Basin and one point in the East Basin. Table 1. Esquire Estates water sample Pyrethrins data following Pyronyl treatment on September 17-18, 2013. Sample Concentrations (ug/L) West Basin West Basin East Basin East Basin Date 2 Feet 4 Feet 2 Feet 6 Feet 09/18/2013 410 340 410 370 09/19/2013 AM 420 410 380 280 09/19/2013 PM 360 330 410 340 09/20/2013 AM 290 250 300 300 09/20/2013 PM 290 250 260 270 09/23/2013 110 120 140 150 09/26/2013 34 34 10/02/2013 17 25 10/10/2013 1.4 3.3 10/16/2013 2.2 3.3 6 Figure 2. Water sample data from West Basin of Esquire Estates Pond following Pyronyl treatment on September 17-18, 2013. Figure 3. Water sample data from East Basin of Esquire Estates Pond following Pyronyl treatment on September 17-18, 2013. 7 Table 2. Water Quality Data from West Basin of Esquire Estates Pond. September 12 2013 Depth Temp pH DO Cond % Sat 3 24.69 8.95 9.16 1572 4.5 24.5 8.99 9.95 1570 September 18 2013 Depth Temp pH DO Cond % Sat 2 19.28 8.98 11.39 1388 126.9 4 19.22 9 11.7 1386 128.9 September 19 2013 - AM Depth Temp pH DO Cond % Sat 2 19.94 8.96 11.99 1385 136 4 19.67 8.97 12.4 1387 140.1 September 19 2013 - PM Depth Temp pH DO Cond % Sat 2 20.02 8.99 11.71 1388 134 4 19.99 8.99 12.09 1390 139.2 September 20 2013 - AM Depth Temp pH DO Cond % Sat 2 21.12 8.9 9.9 1415 115.5 4 20.43 9 12.22 1451 140.8 September 20 2013 - PM Depth Temp pH DO Cond % Sat 2 21.7 8.91 1417 4 September 23 2013 Depth Temp pH DO Cond % Sat 2 18.18 8.89 9.81 1433 107.8 4 17.97 8.95 11.04 1428 120.3 September 26 2013 Depth Temp pH DO Cond % Sat 2 17.7 8.68 1374 4 17.69 8.72 1373 October 10 2013 Depth Temp pH DO Cond % Sat 2 18.15 8.77 1288 4 17.44 9.03 1284 - 8 Table 3. Water Quality Data from East Basin of Esquire Estates September 12 2013 Depth Temp pH DO Cond 2 24.62 8.89 8.96 1576 4 24.4 8.86 8.5 1573 6 24.17 8.86 8.51 1574 September 18 2013 Depth Temp pH DO Cond 2 19.72 8.8 9.11 1391 4 19.04 8.81 9.06 1390 6 18.77 8.83 9.23 1390 September 19 2013 - AM Depth Temp pH DO Cond 2 19.94 8.83 9.72 1389 4 19.11 8.88 10.82 1392 6 19 8.82 9.47 1394 September 19 2013 - PM Depth Temp pH DO Cond 2 20.38 8.83 9.51 1393 4 19.19 8.81 9.4 1392 6 19.09 8.83 9.53 1392 September 20 2013 - AM Depth Temp pH DO Cond 2 21.25 8.75 7.73 1396 4 19.71 8.82 8.92 1462 6 19.29 8.76 7.78 1464 September 20 2013 - PM Depth Temp pH DO Cond 2 21.87 8.76 7.94 1398 4 19.76 8.8 8.91 1460 6 19.42 8.78 8.43 1461 September 23 2013 Depth Temp pH DO Cond 2 18.1 8.63 6.46 1436 4 17.74 8.64 6.53 1434 6 17.51 8.62 6.5 1435 September 26 2013 Depth Temp pH DO Cond 2 17.97 8.43 1380 4 17.41 8.46 1377 6 17.32 8.44 1379 October 10 2013 Depth Temp pH DO Cond 2 4 6 - 9 Pond. % Sat % Sat 102.2 99.9 101.2 % Sat 110.5 119 106.1 % Sat 108.7 102.5 106.4 % Sat 90.8 103.1 88.8 % Sat 94.6 101.6 96.8 % Sat 70.5 71.1 69.9 % Sat % Sat -