Proposed Risk Management Policy for Mine Operations Michael Burnside February 15, 2008 The perception of risk that a mine project might pose to the environment is the biggest weapon opponents use to rally public and political opposition to mines. Thus risk is also the single biggest roadblock to mine permitting and NEPA analysis completion. Risk is defined by engineers as the probability of a project design failure multiplied times the consequences of that failure. A project has a major risk problem when the public or an agency is convinced a mine design has a high or unknown probability of failure that will cause major environmental consequences. Mine opponents use the "precautionary principle" to magnify perceptions of risk and to support their argument: "Any serious risks to the environment are unacceptable. All mine projects pose serious risks to the environment. Therefore all mine projects are unacceptable and must be banned or heavily regulated." This badly skewed and overly cautious approach to risk is providing much of the rationale for many of the worst measures of HR 2262, the Rahall mining law bill, such as the mine veto, suitability criteria, environmental standards, bonding, etc. It is not easy to correct this distorted perception of mining project risk. But one way to do it is for the mining industry to embrace and "own" the issue of risk. How do we "own" risk? As the following explains, we could start by adopting a "risk management" policy as part of our environmental policy statement. We should consider a risk policy that states as an integral part of designing and submitting our major mining proposals (that is, those at the development stage), the operator will conduct an engineering risk-based analysis of the development project. The risk analysis process should be an accepted one such as the Failure Modes Effects Analysis process for risk, which has already been widely used and accepted for major projects including some by the U.S. military, USDA, Ford Motor Company, chemical industry, hydroelectric and nuclear industries as well as for some major mine proposals in the US and Canada. Objectives of a mining risk management policy and process: To scientifically characterize a mining project's risks and demonstrate how those risks would be managed, the process would: 1. Analyze a project for "fatal flaws", ie, the probability of failure and resulting environmental consequences of each mining project component and subcomponent (see example from New World Mine risk review chart); 2. Identify the design and monitoring procedures that would manage and reduce each of those risks to an acceptable level 3. Enable risk comparisons with similar other non-mining engineering projects (see, for example, the attached Whitman Chart, of accepted non-mining project risks). 1 4. Provide the permitting agency with a detailed scientific analysis and management of the project's risks, which will facilitate the NEPA & permitting process. 5. Provide a basis to reassure the public and respond to early erroneous perceptions of the project's risk. Summary: An engineering-based risk management analysis process: has been successfully developed and used in numerous major engineering projects, including mining projects in the US and Canada (see attached paper by McLeod on Risk Management); tracks risk through design, construction, and operation phases and is compatible with "adaptive management" processes; identifies, quantifies, and manages risk, plus assesses risk management effectiveness; provides a basis to compare mining project risk to other non-mining projects. provide a basis to reassure the public and respond to early erroneous perceptions of the project risks provide permitting agencies with a detailed scientific analysis and proposed management of the project's risks, which will facilitate the permitting process. Conclusion: A mining industry risk management policy would Accept a major recommendation of the American Society of Civil Engineering to incorporate scientific risk management into project design and development (see attached ASCE statement). Show the industry has heard and is responding to the public's concerns about mine projects' perceived risks to the environment. Thus it is implementing a policy of "full disclosure" in project design to insure the risks are analyzed, disclosed, and managed, and will produce a well designed and operated project. ------------------------------------------------------------------------------------------------------5 Attachments: 1. 2. 3. 4. 5. Figure 5 Risk Review Chart - New World Project Proposed Tailings Facility Figure 6 Risk Review Chart – New World Project Proposed Tailings Facility After Compensating Factors Applied. Whitman Chart of Risks From Major Industrial Facilities, by Robert Whitman, MIT professor of engineering. McLeod, et. al., Risk Management Analyses American Society of Civil Engineers Risk Management Policy Statement, July 15, 2007. 2