THIRD QUARTER PERFORMANCE EVALUATION REPORT OF VAAL GAMAGARA BULK WATER SUPPLY PROJECT NORTHERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 OCTOBER 2014 TO 31 DECEMBER 2014 1 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 1 Table of Contents INTRODUCTION .................................................................................................................... 3 2 BACKGROUND TO THE PROJECT ............................................................................................ 3 2.1 Project description .................................................................................................................. 5 2.1.1 Groundwater Investigation .......................................................................................... 5 2.1.2 Addendum to the Feasibility Study ............................................................................ 6 2.1.3 Implementation Readiness Study .............................................................................. 6 2.1.4 Phase 1 Implementation – Appointment of PSP...................................................... 7 3 AREA OF SUPPLY ................................................................................................................... 7 4 PROJECT CONTRACT AND COST ........................................................................................... 10 5 4.1 Allocated Funding for the Groundwater Investigation: ........................................................ 10 4.2 Expected Project Cost for Option 1 ....................................................................................... 10 4.3 Contract Details and Cost ...................................................................................................... 11 4.4 Funding Allocated to the Project ........................................................................................... 12 PROGRESS ON CURRENT PROJECT ....................................................................................... 12 5.1 Groundwater Investigation ................................................................................................... 12 5.2 Addendum to the Feasibility Study ....................................................................................... 13 5.3 Implementation Readiness Study.......................................................................................... 13 5.3.1 Water Use Licence Application Process ................................................................. 13 5.3.2 Environmental Impact Assessment.......................................................................... 14 5.4 Communication Strategy ....................................................................................................... 15 5.5 Phase 1 Implementation – Appointment of PSP ................................................................... 15 5.6 Other ..................................................................................................................................... 15 6 RISKS TAKEN AND MANAGEMENT THEREOF ........................................................................ 16 7 PROJECT RESULTS AND BENEFICIARIES ................................................................................ 17 7.1 Beneficiaries .......................................................................................................................... 17 7.1.1 Local Authorities ......................................................................................................... 17 2 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 7.2 DECEMBER 2014 Employment during the Implementation of the Project....................................................... 17 8 KEY CHALLENGES WITHIN THE PROJECT ............................................................................... 18 9 CONCLUSIONS .................................................................................................................... 18 10 RECOMMENDATIONS .......................................................................................................... 18 11 PHOTOGRAPHS ON THE IMPLEMENTATION OF THE PROJECT ............................................... 19 List of Figures Figure 1: Supply area of Vaal Gamagara Bulk Water Supply Scheme ..................................................... 9 List of Tables Table 1: Construction Cost (VAT excluded) ........................................................................................... 11 Table 2: Contract details: Drilling and Testing Contractors................................................................... 11 Table 3: Funding to date........................................................................................................................ 12 Table 4: Population of beneficiaries ...................................................................................................... 17 Annexures Annexure A: Project Implementation Photos 3 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 1 DECEMBER 2014 INTRODUCTION In terms of Section 10(7)(b) of the Division of Revenue Act (DoRA), Act No 10 of 2014 as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit to the National Treasury a quarterly performance report of all programmes partially or fully funded by a Schedule 5 or 6 allocation within 45 days after the end of each quarter, in accordance with the requirements of the relevant framework. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective therefore is to provide quarterly performance report of projects that are funded through the Regional Bulk Infrastructure Grant, in compliance with the Division of Revenue Act, 2014. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This annual report, covering quarter 3 of the 2014/15 fiscal year, presents the results of the performance evaluation of Vaal Gamagara Water Supply Scheme, one of the Regional Bulk Infrastructure Grant projects, currently being implemented by the Sedibeng Water Board in the Northern Cape Province, with Department of Water and Sanitation (DWS) as funder 2 BACKGROUND TO THE PROJECT The Vaal Gamagara Water Supply Scheme (VGWS) was completed in the late sixties with the purpose to supply Vaal River water to the arid areas of the Gamagara Valley near Postmasburg and north thereof. This was done to enable large scale diamond mining at Lime Acres and the mining of iron ore and manganese at Beeshoek, Sishen, Mamatwan, Hotazel and Blackrock. Several local authorities receive water from the scheme of which the towns of Delportshoop, Postmasburg, Kathu and Hotazel are the largest. Later the addition of the Kalahari East Board, a bulk consumer of the VGWS scheme, brought about further changes in water demand. The Kalahari East scheme was completed in 1992 to supply domestic and stock water to an area of ± 1 412 000 ha that includes more than 250 farms. The VGWS scheme consists of a purification works that can purify 13.27 million m³/a water, pumps, 11 reservoirs and 370 km of pipes that delivers water to users. The pipeline has the capacity to convey and import approximately 15 million m³/a into the D41J and D41K catchments. The 13.27 million m³/a water is augmented by dewatering activities of the Kolomela, Beeshoek and Sishen mines to lower the groundwater table to ensure safe mining conditions. The need for a feasibility study of the VGWS scheme arose from the increase in water demand experienced by Sedibeng Water because of new water applications and extension of existing water allocations. The current scheme is operating at capacity and is not able to supply the future water demand due to the increased water demand, and the increased water supply interruptions. 4 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 The major driving force of the increased water demand is the iron ore and manganese mining operations. These mines of the Northern Cape produce 84% of South Africa’s iron ore and 92% of the world’s high-grade manganese deposits are in the Kalahari basin. Diamond and lime operations also contribute to the water demand, but to a lesser degree. Secondary to the expected increased water demand are water supply interruptions that are amplified due to the aging infrastructure. The infrastructure, being more than 44 years old, is nearing its useful life. The feasibility study was completed in August 2011 and recommends the upgrade of the total VGWS scheme to supply the water demand of users for the planning horizon to 2030. The study indicated the current water demand of 13.7 million m³/a is to increase to approximately 40 million m³/a by the year 2030. It is projected that the mining sector will be the largest consumer; consuming approximately 63.5% of the water, whereas the local authorities and other water users will utilise 14.7% and 21.8% respectively by 2030. Households in the area supplied by the VGWS scheme are anticipated to increase from 18 332 in 2010 to 31 367 in 2030 (71% increase) with a projected increase in population from 77 316 to 129 196 over the same period. For planning purposes a 20-year design horizon (2010 to 2030) was used. The results of the hydraulic analyses indicated that the existing infrastructure has insufficient capacity to accommodate the anticipated 2030 demand. A condition assessment of the existing pipelines also confirmed the need for refurbishment. It was assumed that the ultimate scheme must be capable of providing the total demand from the Vaal River source. The addition of groundwater or mine dewatering sources would therefore only provide relief in terms of operational supply and water price. Planning was performed for three options: Option 1: Replace the existing scheme with a single pipeline with sufficient capacity to supply the anticipated 2030 demand. Option 2: Add capacity to the existing scheme to supply the anticipated 2030 demand by an additional pipeline. Option 3: Replace the existing scheme with a double pipeline with sufficient capacity to supply the anticipated 2030 demand. For all three options the basis was that pumping occurs from the Water Treatment Works (WTW) near Delportshoop to Clifton and that the rest of the scheme is supplied from there under gravity with no booster pumps. It was also assumed that over the pumped sector the scheme would operate at the same pressures as the existing scheme. All the strategic and technical alternatives studied were compared mainly on economic grounds which results in the lowest present value of capital works, operations and maintenance. A costing and engineering economic analysis was conducted by means of a Unit Reference Value (URV) for each technical alternative. 5 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 From the calculations it was evident that Option 1 has the lowest URV and thus from an engineering economic point of view, Option 1 - Replace the existing scheme with a single pipeline with sufficient capacity to supply the anticipated 2030 demand, is the recommended way forward. 2.1 Project description Subsequent to the completion of the study in August 2011, the optimization of an Option 1 was considered for augmenting the water resources of the VGWS, i.e. the inclusion of possible additional groundwater resources (SD sources) that were identified initially as a short to medium augmentation measure as part of the original study. Several detailed investigations were conducted of which the groundwater exploration project was the main element. The scheme was analysed to include the SD groundwater sources and to determine the benefit from including this additional source. The optimization analysis of the scheme entailed the replacement of the existing scheme with a single pipeline with sufficient capacity to supply the anticipated 2030 demand from the Vaal River and the SD groundwater sources. Two demand scenarios were included in the further study namely the in- and exclusion of the trans-border demand from Botswana. The options investigated are: Option 1A - replacement of the existing scheme with a single pipeline with sufficient capacity to supply the anticipated 2030 demand from the Vaal River and the SD groundwater sources including Botswana Option 1A - replacement of the existing scheme with a single pipeline with sufficient capacity to supply the anticipated 2030 demand from the Vaal River and the SD groundwater sources excluding Botswana An addendum to the Feasibility Study was compiled including the groundwater investigations, hydraulic optimization and costing of Options 1A and 1B and an economic and affordability study. The following phases of the project entail the completion of the Implementation Readiness Study (IRS) which includes the Water Use Licensing of the four targeted well fields, the environmental authorities and the implementation of a communication strategy amongst others. Sedibeng Water appointed a professional service provider (PSP) for the design and construction of the most critical section of the scheme between Kathu and Black Rock. 2.1.1 Groundwater Investigation The groundwater investigation comprised out of two phases, namely: Phase I – Assessment of Available Groundwater Resources Phase II – Development of Groundwater Supply Phase I was concluded March 2014 and information from this assessment phase will guide the next phase. Phase II consist of the following: 6 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 Public participation processes and all relevant tasks relating to the Water Use Licence Application (WULA). Ground geophysical survey to pin point production borehole positions Drafting of tender documentation and related contract for the appointment and management of drilling and test contractors. Production borehole drilling, long term test to confirm aquifer sustainability and water quality sampling Assessment of the sustainable water supply including the updating of the numerical model, management recommendation for the production boreholes, preparation and finalising of the WULA. The main deliverable from Phase 2 will be the drilling of the production boreholes and associated testing and licensing. Note must be taken that little drilling of production boreholes will be required as most of the drilling were completed in Phase 1. 2.1.2 Addendum to the Feasibility Study After presenting the project to the Acting Director General (ADG) of DWS the project team was tasked to compile an addendum to the August 2011 Feasibility Study which primarily detailed the optimization of Option 1, i.e. then Option 1A and 1B. During the optimization process, the need to take a different approach to the tariffs was discussed. This, rather than a previous tariff study which was based on differentiated tariffs per section of the scheme. Instead uniform tariffs per sector/user group were suggested and this was examined during the optimization phase. Uniform tariffs per sector/user group were examined and documented in this new tariff study as part of the Addendum to the Feasibility Study. 2.1.3 Implementation Readiness Study The IRS is to provide the required information, as requested by the Department of Water Affairs’ (DWA) Regional Bulk Infrastructure Grant (RBIG) program, to apply for a grant from DWA. The grant is required by Sedibeng Water to counter fund the Vaal Gamagara Bulk Water Scheme. The IRS addresses strategic and planning issues, social, economic, technical, institutional, financial, legal criteria and sustainability criteria according to the implementation phases. As a result of regular interaction with stakeholders and landowners, Sedibeng Water and Department of Water and Sanitation (DWS) (formerly known as the Department of Water Affairs (DWA)) found that people were concerned about the number of different projects in the study area and the lack of consistent messages. It was decided to prepare a Communication and Stakeholder Engagement Strategy regarding the implementation of various aspects of the project. This was done through pro-active and transparent engagement with stakeholders representing key sectors of society in the project affected area, namely directly affected landowners, communities in the study area, Agri-SA Northern Cape, various farmer's unions in the area, existing Water User Associations, the mines and relevant government departments representing all spheres of government. 7 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 Ongoing support is provided to the DWS and Sedibeng Water to ensure that meetings take place with stakeholders on a regular basis to keep them abreast of progress. Telephonic liaison with stakeholders also plays a critical role in ensuring that they are informed about different actions being undertaken as part of the IRS and the different components. The implementation of the strategy is being implemented and will be on-going for the duration of the project. As highlighted above the potential for available groundwater resources in the general area served or proposed to be served by the pipeline to augment the bulk water supply was investigated. Several areas were identified as possessing enhanced groundwater development potential, these areas were designated Source Development (SD) Areas. Authorisation is required in terms of the National Water Act, 1998 (Act 36 of 1998) (NWA) for the abstraction of water from these groundwater resources. The NWA requires that all water use described under section 21 be authorised. Groundwater abstraction in this case falls within Section 21(a) and will require a water use licence (WUL). The Water Use Licence Application (WULA) will contain the following: Compilation of the required technical information into one technical supporting summary document; and Completed water use licence forms. The objective is as follows: Confirmation of water uses for the planned abstraction and submission of a WULA in accordance with the DWS External Guideline as required in terms of the NWA for the water uses associated with the abstraction; Compilation of a summary report; and Submission of the WULAs and summary report to DWS. A broad environmental assessment is in the process of being conducted for the proposed upgrade of the VGWS relating to the Phase 1 development. 2.1.4 Phase 1 Implementation – Appointment of PSP Sedibeng Water invited suitable qualified and experienced PSP to submit tenders to conduct the design, contract documentation and site supervision for the refurbishment and upgrading of the existing Vaal Gamagara regional water supply scheme Phase 1A (replace pipeline from Roscoe to the Sishen Western Expansion Project (SWEP) pipeline and from SWEP to Kathu and Blackrock). Sedibeng appointed Royal HaskoningDHV for Phase 1 and design commenced with the expected construction date of August 2015. 3 AREA OF SUPPLY The Study Area falls within the Northern Cape Province and is mostly located within Water Management Area (WMA) 10 with some extension to WMA 14. It covers the area served/interacting by/with Sedibeng Water’s Vaal Gamagara Scheme. 8 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 The local authorities’ water demand are from the 18 332 households (year 2010) that are anticipated to increase to 31 367 in 2030 (71% increase). The population is expected to grow from 77 316 in 2010 to 129 196 in 2030. Based on the norms, number of indigents and associated users, the social component of the project is calculated. The portion of the pipeline that delivers water to the social component is 6.1%. This excludes the water that is supplied to possible indigents and emerging farmers via the Kalahari East Scheme. This will be quantified in the near future. The Kalahari East Scheme currently exports water at approximately 1.8 million m³/a from the D41J catchment (with the off-take from the Vaal Gamagara pipeline north of Sishen mine) for stock-farming and related domestic purposes to areas. Refer to Figure 1 indicating the area of supply. 9 Regional Bulk Infrastructure Grant Programme Figure 1: Area of Supply Figure 1: Supply area of Vaal Gamagara Bulk Water Supply Scheme December 2014 10 Regional Bulk Infrastructure Grant Programme 4 December 2014 PROJECT CONTRACT AND COST The project is managed by the Department of Water and Sanitation Regional Office in the Northern Cape and implemented by Sedibeng Water. The total estimated project cost for Option 1B (excluding Botswana) is R 8 779 304 417 (VAT excluded) and based on the level of indigence and social water demand, the social component has been fixed on 9.54%. This equates to R 837 545 641, which will be allocated by the RBIG Programme. Sedibeng Water needs to secure an amount of R7 941 758 775from other sources. The budget of this project is divided in two stages, namely the investigation stage and the construction stage. For the purpose of this Report Option 1B’s costs is referred to. 4.1 Allocated Funding for the Groundwater Investigation: The estimated cost for the Assessment of Exploitable Groundwater Resources for augmentation of the Vaal Gamagara Bulk Scheme is summarised as follows: The expenditure for the Groundwater Exploration Project is as follows (all amounts VAT inclusive): 2011/2012 FY 2012/2013 FY 2013/2014 FY 2014/2015 FY R 9 414 837 R 16 534 283 R 27 892 190 R 4 416 270 The expenditure for the 2014/2015 amounts to R 4 416 270 (VAT included) with an allocated budget of R40 million. 4.2 Expected Project Cost for Option 1 The expected construction cost as per proposed phase is as indicated in the Table 1. 11 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 Table 1: Construction Cost (VAT excluded) Phase 1 2015 - 2016 Description Phase 2 2017 - 2018 Final 2019 - 2022 TOTAL Construction Costs Pump Stations Rising Mains Gravity Mains Reservoirs Sumps Water Treatment Works Abstraction Works Telemetry Substations SD Groundwater 319 584 838 2 527 500 50 000 000 77 455 504 390 463 040 269 383 503 208 260 000 8 375 000 2 527 500 2 992 000 576 904 841 212 333 103 1 107 033 093 614 751 664 20 075 000 638 501 500 31 318 696 5 055 000 6 827 200 - 289788607 1497496133 1203720005 208260000 28450000 638501500 31318696 10110000 9819200 626904841 SUB-TOTAL A 372 112 338 1 536 361 388 2 635 895 257 4544368982 SUB TOTAL B (landscaping, miscellaneous, P&G, contingencies and design fees) 348 216 321 1 037 210 905 2 849 508 208 4 234 935 434 TOTAL COST OPTION 1B 720 328 659 2 573 572 293 5 485 403 465 8 779 304 417 8.2% 29.3% 62.5% 100.00% PERCENTAGE OF TOTAL COST 4.3 Contract Details and Cost The contract details for the Groundwater Exploration Project are mentioned in the table below: Table 2: Contract details: Drilling and Testing Contractors Contract no 245460YNB/1 245460YNB/2 Contract name Drilling of Exploration/Monitoring/Production Boreholes Testing of Exploration/Monitoring/Production Boreholes Contractor Environmental Drilling and Remediation Services CC Groundwater Solutions CC t/a AB Pumps Contract award start date 20 June 2012 20 June 2012 Completion date Expected March 2014 - Not fixed Expected March 2014 - Not fixed Completion extension No No Actual completion date 31 March 2014 31 March 2014 Contract value (including VAT) R24 488 308.05 (Final amount invoiced) R3 546 525.20 (Final amount invoiced) Completion 100% 100% 12 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 4.4 DECEMBER 2014 Funding Allocated to the Project The Groundwater Exploration project cost is R 51.3 million and the completion date is 31 March 2014. Table 3: Funding to date Approved amount budget *2011/12 *2012/13 *2013/14 2014/2015 R 9 414 837 R 16 534 283 R 27 892 190 R 35 000 000 Total R 88 841 310 *Actual expenditure No counter funding is secured at this stage and the project is completely funded from RBIG. Sedibeng is however in the process of investigation different funding models. The budget allocation of the 2014/2015 FY is divided in two sectors namely: Vaal Gamagara pipeline investigations (IRS, communication strategy, completion of drilling, completion of groundwater reports and WULA) – R 5 million. The design, procurement and implementation – R 30 million. construction management of Phase 1 The total budget allocated to this project amounts R35 million. 5 PROGRESS ON CURRENT PROJECT No formal performance evaluation was conducted however regular Project Team meeting are conducted consisting among other of the following people 5.1 Kobus Streuders Ian Hassenjager Frans Wiegmans Elmar Deysel Antoinette Pietersen Department of Water and Sanitation Sedibeng Water Golder Associates WorleyParsonsRSA Golder Associates Groundwater Investigation The exploration drilling was concluded March 2014. The study reports were submitted to the project team for approval. Based on the results of the groundwater investigations the following summary conclusions and recommendations are made to augment bulk water supply to the VGWS: The combined long term sustainable groundwater abstraction to augment the VGWS amounts to 11 200 536 m3/a, with an additional short term peak supply (4 months per year) of 3 222 064 m3/a. SD1 Study Area: A WULA should be submitted to develop the 22 production boreholes (scenario B) to abstract 5 329 584 m3/a on a sustainable basis over the long term with an additional peak / short term supply (four months per year) of 1 314 000 m3/a (6 13 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 643 584 m3/a combined long and short term peak supply) to augment water supply to the VGWS The groundwater chemical classification for SD1 study area is calcium magnesium bicarbonate type of water (Ca, Mg) (HCO3)2 representing unpolluted potable water suitable for long term human consumption SD2 Study Area: A WULA should be submitted to develop 21 production boreholes to abstract 3 689 712 m3/a on a sustainable basis over the long term with an additional peak / short term supply (four months per year) of 1 808 064 m3/a, (5 497 776 m3/a combined long and short term supply) to augment water supply to the VGWS The groundwater chemical classification for the SD2 study area is calcium magnesium bicarbonate type of water (Ca, Mg) (HCO3)2, representing unpolluted potable water suitable for long term human consumption SD4 – Study Area A WULA should be submitted to develop the production of 15 boreholes to abstract 2 181 240 m3/a on a sustainable basis over the long term to augment water supply to the VGWS The groundwater samples from newly drilled boreholes were analysed for physical parameters, macro and micro-determinants, with potable water quality concentrations suitable for long term human consumption 5.2 Addendum to the Feasibility Study A first draft of the Addendum to the Feasibility Study was submitted for comments to the project team on the 18 August 2014 including the Affordability study. The final draft report was submitted 20 November 2014 for final comments. As part of the Addendum report, the proposed SD4 villages’ bulk supply scheme was included. A draft report was submitted 22 October 2014 to DWS and Sedibeng Water regarding the preliminary desktop investigation to supply these villages. A proposal was also discussed with DWS and Sedibeng Water to utilize the available budget for the current financial year. The proposal includes items such as the environmental process, geotechnical investigations, topographical survey, further groundwater investigations and preliminary designs. Approval on this proposal is pending. 5.3 Implementation Readiness Study The IRS is in the process of being finalised and expected completion date is end of February 2014. The sub tasks of the IRS are listed below. 5.3.1 Water Use Licence Application Process Meeting with Department of Water and Sanitation (DWS) was held on the 29th September 2014 to discuss the water use licence process and the way forward. Outcomes were as follows: DWS require one application for all SD areas - the application cannot be submitted in phases as originally intended. This will lead to delays in obtaining authorisation as we will need to wait for all studies to be completed before the application can 14 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 be compiled and submitted. Obtaining landowner consent could be problematic for some of the areas and lead to delays in the submission; The EIA will need to be completed before we can submit - DWS might consider processing the application prior to obtaining the RoD but that decision will depend on how far along the process is; The public participation still needs to be done for the Water Use Licence Application (WULA); DWS confirmed that they require one application form per borehole. Thus an application cannot be submitted per area or wellfield. We will apply for maximum possible yields per borehole; There were concerns from DWS regarding the WULA submitted by Sishen for recharge of the aquifer as they felt this should be considered as an alternative to the project. This is an internal discussion for DWS; The status of the Reserve Determination will be established by DWS to determine if this will cause delays in processing the application. If the Reserve is not available it can only be requested upon receipt of the RoD. It is however likely there is a Reserve available. The draft WULA forms have been compiled for SD4 with all the available information. As soon as the studies for SD 2 and SD 3 are available the rest of the forms will be completed. A consent letter must be compiled for each landowner to sign. This will be done at the same time as the WULA forms are presented to the landowners to sign. Detailed information on the pumps that will be used is required and a list will be forwarded. Work that has been done so far is filling up of the water use licence application forms with the available information. In December work will commence with the summary report that will be the supporting document to accompany the WULA. This report contains the motivation and supporting information required by DWS in order for them to process and make a decision on the application. A separate report will be required for each of the SD areas and will be compiled as information is available. The next step will be printing the forms for the client to review, provide outstanding information and sign. A summary report will also be drafted. 5.3.2 Environmental Impact Assessment The environmental assessment process is well underway. The draft Basic Assessment Report was submitted to the Department and the ref no. was obtained from the Department. The site meeting with the Department of Environment and Nature Conservation, Northern Cape Province took place on the 4th of November 2014 to visit Phase 1. 15 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 Comments from the Department of Environment and Nature Conservation, Northern Cape Province was obtained and is being addressed before the final Basic Assessment Report can be submitted to NC DENC. An EIA process for the SD groundwater sources is outstanding. The SD4 one should be commissioned and dealt with on its own. The EIA for SD 1 and 2 areas could be combined. 5.4 Communication Strategy The progress to date focussed on the following: Coordination of strategic communications activities, including liaison with several key role players, e.g., Sedibeng Water, the Department of Water and Sanitation (DWS) and key mining/industrial water users. Subsequently, Golder maintained contact with both the DWS and Sedibeng Water and provided support as and where required. Providing ongoing support in preparation and finalisation of the presentation to the DWA Acting Director General to motivate for an application for project funding from national Treasury. As part of the preparation of the presentation, Golder arranged a meeting with key members of the Project Steering Committee during which the content of the presentation was deliberated and refined. Golder recorded these discussions at the meeting and circulated the draft minutes for comment. The groundwater exploration study is in the process of being finalised. Golder’s Stakeholder Engagement Task Lead is assisting in setting up meetings with the directly affected stakeholders and would accompany the groundwater specialist to convey the findings of the groundwater exploration study done in SD areas 1 to 4. Immediate next steps in the process will be to finalise the following: 5.5 Communicating the findings of the groundwater exploration study to directly affected stakeholders. Ongoing liaison with Sedibeng Water and the DWS. Coordination of Project Steering Committee meetings. Phase 1 Implementation – Appointment of PSP As mentioned above, Royal HaskoningDHV is appointed and design is well underway. 5.6 Other A proposal to conduct a study into the possibility to establish an additional scheme in the vicinity of Douglas supplying the Vaal Gamagara and Kimberley is in the process to be drafted. A meeting was held with Assmang on 15 December to discuss the following: The progress on the current Sedibeng water strategy for the Northern Cape 16 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 6 DECEMBER 2014 Day to day operational water supply issues being faced by the Assmang mines in the Northern Cape Kumba dewatering strategy and potential synergy with Khumani. RISKS TAKEN AND MANAGEMENT THEREOF A number of potential risks were identified during the course of the IRS and actions put in place to facilitate the management of the risks, namely: Lack of awareness regarding the IRS: As mentioned earlier, the IRS has several components and people living in the study area were not aware of the project’s different aspects and phases. A Communication Strategy was developed to identify key groups of stakeholders, clarify roles and responsibilities within the project team and identify appropriate methods and actions to be implemented to create better awareness of the project and ensure that stakeholders had a direct line of communication with the project team. Regular meetings were convened with key role-players to ensure that they were kept informed of the project and the progress as milestones were achieved. Perception that water belongs to the people/farmers: Through meetings with key role players such as the mines, Water User Associations, organised and informal agriculture, local government departments and local communities with stakeholders in the project area, the theme of water as a precious commodity belonging to the government and being managed by the government was emphasised. However, more work still needs to be done to help people to understand that the DWS is the national custodian of the country’s water resources. Potential future opposition against the VGG Bulk Water Infrastructure Scheme: Many landowners, during the groundwater assessment study indicated that whereas it was in order for the DWS to commission the study to determine whether a viable water resource exists in the study area, they would strongly oppose the project should it ever go into a full environmental impact assessment study and water use licence application process. Landowners are concerned that their future existence and means of livelihood will be threatened and taken away if the VGG pipeline is augmented by groundwater. Already, landowners in the Kuruman area are concerned about perceived fast-dwindling groundwater due to the mining operations at Sishen. There is a risk that landowners may not want to sign the water use licence application (WULA) forms once the WULA process starts. Attempts have been made to avoid farm properties where this issue was voiced, however, in other cases landowners who were accommodating towards the groundwater study, clearly indicated that they would oppose such project should it proceed. This will require ongoing management through adequate communications and maintaining constructive relationships with all key stakeholders in the area. Project funding and responsibility: At this stage it is not yet clear which institution will be responsible for the funding of the VGG Bulk Water Infrastructure Pipeline Scheme and, as a result it is not certain who will be responsible for the implementation of the project. Once this is known, a project steering committee meeting will be arranged to inform the members accordingly. 17 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME DECEMBER 2014 The Communication Strategy will continue to control information flow and manage expectations. 7 PROJECT RESULTS AND BENEFICIARIES The project beneficiaries are mentioned below: 7.1 Beneficiaries The beneficiaries of the water in the Vaal Gamagara pipeline consist of 5 main groups: 7.1.1 Local Authorities/Municipalities (Dikgatlong, Kgatelopele, Tsantsabane, Gamagara, Ga-Segonyana, Joe Morolong). Mining houses (Petra Diamonds, BHP Billiton, Kumba Iron Ore, Kgalagadi Manganese, National Manganese, PMG Mining, Kudumani Manganese Resources, Tarnisani Dynamic Mining Company, Diro Minerals, United Manganese of Kalahari, Sedibeng Iron Ore, Tshipi e Ntle Manganese and Amari Resources). Agriculture – mainly stock watering along the scheme, farmer and domestic use. The largest user of agriculture water is the Kalahari East scheme. Government water supply to Lohatla Military Base and Koopmansfontein Experimental Farm. The possible water supply to Botswana with an off-take from Blackrock. Local Authorities The population of the Local Authorities to benefit from the scheme are listed in the Table below. Table 4: Population of beneficiaries Towns 7.2 Population 2030 Indigent population Indigent users 2030 Koopmansfontein 195 100.0% 195 Vaal Gamagara 276 72.7% 201 Delportshoop and Longlands 21,901 72.7% 15,922 Postmasburg and Beeshoek 42,876 55.2% 23,668 Olifantshoek 11,230 55.2% 6,199 Kathu and Dingleton 45,478 48.0% 21,829 Hotazel 7,240 66.4% 4,807 Blackrock 2,097 66.4% 1,392 Employment during the Implementation of the Project Since the work at this stage is specialised no local labour is utilized. For the construction phase the following employment is expected: 18 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 8 DECEMBER 2014 Temporary employment: 4 005 300 person days (approx. 2 200 temporary jobs over a 5 year construction period) Permanent employment: 52 direct jobs: - 200 Indirect jobs - 510 Induced jobs KEY CHALLENGES WITHIN THE PROJECT The funding of the total project can be listed as the major challenge. Another challenge is the inclusion of Botswana. It is unclear whether Botswana should be included in the design. 9 CONCLUSIONS The Groundwater Exploration project is completed and study reports submitted. The finalization or the reports will be during October 2014. The Addendum to the Feasibility Study was submitted as a final draft. The expenditure for the 2014/2015 financial year (FY) is R 3 211187.41 (VAT included). It is expected that an additional R 1 500 000 (VAT included) will be required to complete the IRS. The Water Use Licensing of the SD4 area is underway as well as the EIA for Phase 1 development. The IRS report is being compiled and will be updated as information become available and expected to be concluded February 2015. 10 RECOMMENDATIONS Funds for the next phases have to be secured to ensure the sustainable supply of water to the consumers. A session with the DG of DWS has to be arranged and a way forward determined. 19 REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 11 PHOTOGRAPHS ON THE IMPLEMENTATION OF THE PROJECT Project team meetings Site visit with Department of Environmental – Kathu Pan Test Pumping of New Borehole in SD2 Area DECEMBER 2014