VARIANCE ANALYSIS Variance is the different between Expected Performance and Actual Performance. When expected costs/standard costs are more (less) than actual costs then the difference is said to be a favourable (adverse) variance. However when expected revenue or contribution is more (less) than actual revenue or contribution then the difference is said to be an adverse (favourable) variance. Variance analysis is the sub analysis of variances into constituent components in a bid to investigate and explain the sources of the variances. Eventually, all variances calculated explain why planned/budgeted profits are different from actual profits. A statement called operating statement, containing all computed variances reconciles budgeted profits to actual profits. Illustration. Zugzwang Ltd produces a single product known as Petroff. The product’s standard cost is presented in the following standard cost card. Standard cost card $ Direct Material: 2kg of caro @ $ 8 1kg of kahn @ $12 16 12 Zugzwang Ltd planned to produce 10,000 units of Petroff in the coming month of September. Annual budgeted fixed overheads are $1,800,000 incurred evenly throughout the year. The actual information for the month of September was as follows. The actual profit for September. $ Sales (9,000 units @$105) D. Materials A(17,000kg @$9) B(11,000 kg @ $11) $ 945,000 153,000 121,000 Actual production and sales for the period was 9,000 units. Material Variances. Total Material Variance is the difference between the expected cost of materials given actual output units (standard cost or flexed budget material cost) and the actual material costs incurred. When standard cost (SC) is more than actual cost (AC) the variance is said to be favourable whereas when SC is less than actual costsfor actual Production and the actual cost (AC) πππ‘ππ πππ‘πππππ π£πππππππ = ππ‘ππππππ πππ π‘ − π΄ππ‘π’ππ πππ π‘ = ππΆ − π΄πΆ = (π΄ππ‘π’ππ πππππ’ππ‘πππ π£πππ’ππ × π π‘ππππππ πππ‘πππππ πππ π‘ /π’πππ‘) − π΄ππ‘π’ππ πππ π‘ 1 By: Maloba πππ‘ππππ πΆπππ: 9,000 × 20 − 209,000 = 29,000 π΄ πππ‘πππππ πΎπβπ: 9,000 × 15 – 141,400 = 6,400 π΄ πππ‘ππ πππ‘πππππ π£πππππππ $ 35,400 π΄ππ£πππ π Note: The formula has been arranged such that when the answer is positive the variance is Favourable whereas when the answer is negative the variance is adverse. The cost of materials which are used in manufacturing products are determined by two basic factors: the price paid for the materials or the quantity of materials used in production. This gives rise to two possibilities for the source of material variance: either the actual material price was different from planned price (standard price per kg) or the actual usage of materials was different the expected usage (standard quantity). Material Price Variance. Material price variance is the difference between the expected price per unit of materials (standard price: SP) that should have been paid for the actual quantity of materials purchased and the actual price (AP) that was paid for each unit of materials bought. Since the variance occurs for every unit actually purchased, then the difference between SP and AP is multiplied by the actual quantity of materials purchased (AQ). The variance is favourable when the actual price (AP) is less than the expected price (SP) whereas the variance is adverse when AP is more than SP. In summary material price variance is the different between standard price per unit of materials (SP) and the actual price (AP) per unit of materials multiplied by the actual quantity of materials purchased (AQ) πππ‘πππππ πππππ π£πππππππ = (π π‘ππππππ πππππ − πππ‘π’ππ πππππ)π΄ππ‘π’ππ ππ’πππ‘ππ‘π¦ = (ππ – π΄π) π΄π. From illustration Material A: (10 – 11)19,000 = −19000 $19,000 A Material B (15 – 14 ) 10,100 = 10100 $10,100 F Total material price variance $8,900 A Possible Causes. i) Change in market conditions that causes a change in gem prices of materials used. ii) Failure by purchasing department to seek most advantageous source of supply. iii) A favorable price variance may be due to purchase of inferior quality materials which may lead to inferior product quality or more wastage. iv) Shortage of materials resulting from bad inventory control necessitating an emergency purchase being made at short notice will make the supplies incur additional cost e.g. handling freight charges e.t.c. and may charge a higher price for the materials. 2 By: Maloba Direct Material Usage Variance. i) The difference between (SQ) standard Quantity of material. Amount of material that should have been consumed in producing actual units of output and the actual quantity (AQ) used in production. This difference is multiplied (valued at) by standard price (SP). From illustration. Material A: if a unit requires 2kg of A, then to produce actual output of 9,000 units 2 × 9,000 = 18,000ππ should have been used (standard quantity) Standard quantity = πππ‘π’ππ ππ’π‘ππ’π‘ π’πππ‘π × πππ‘π πππ π’πππ‘ Therefore (18000 – 19000) × 10 = 10,000π΄ Material B = (9000 × 1 – 10,100) × 15 = 16,500 π΄ Possible Causes. i) Careless handling of materials by production personnel. ii) Purchase of interior quality materials. iii) Pilferages. iv) Changes in quality control requirement. v) Changes in method of production. Fixed Overhead variance. Fixed overhead variance is computed differently under marginal costing system and under absorption costing system. This is so due to underlying assumptions of fixed overheads under the two systems. Absorption costing system absorbs fixed overheads based on an appropriate activity say number of units, thus it treats fixed overheads as if they are variable; in that more fixed overheads will be absorbed when production volume increases. Marginal costing system on the other hand treats fixed overhead costs as is their nature: fixed regardless of the activity level. Under marginal costing, fixed overheads are expensed as period costs Fixed overhead variance under marginal costing system Fixed overhead costs under marginal costing are assumed to remain unchanged regardless of changes in activity level. Actual fixed overhead costs however may be different from budgeted in response to other factors say inflation, taxes change of suppliers etc that have an impact on expenditure change. Fixed overhead variance therefore occurs only when budgeted expenditure on fixed overheads (BFO) is different from actual expenditure on fixed overheads (AFO). Fixed overheads variance under marginal costing is known as fixed overhead expenditure variance. πΉππ₯ππ ππ£ππβπππ ππ₯ππππππ‘π’ππ π£πππππππ = (π΅πΉπ – π΄πΉπ). 3 By: Maloba Summary of Variances Variance Price Aspect Quantity Aspect Direct Material variance Material Price Material Usage = ππΆ − π΄πΆ = (ππ – π΄π) π΄π = (ππ – π΄π) ππ Direct labour variance Labour Rate Labour Efficiency = ππΆ − π΄πΆ = (ππ – π΄π ) π΄π» = (ππ» – π΄π») ππ Variable Overheads Variable Overheads Expenditure Variable Overheads Efficiency = ππΆ − π΄πΆ = (ππππ – π΄πππ ) π΄π» = (ππ»– π΄π») ππππ Sales Variance Sales Price Variance Sales volume varianve = (π΄π − π΅π)π΄π Under marginal costing system Under Absorption costing system Sales volume contribution Variance Sales volume profit Variance = (π΄π − π΅π)ππΆπ = (π΄π − π΅π)πππ FIXED OVERHEADS VARIANCE UNDER ABSORPTION COSTING TOTAL FOH VARIANCE = over/(under) absorption = π΄ππ πππππ ππ» − π΄ππ‘π’ππ ππ» = π΄ππ πππ π’πππ‘ × πππ‘π’ππ ππ’π‘ππ’π‘ − πππ‘π’ππ ππ» FOH expenditure variance = π΅π’ππππ‘ππ πΉππ₯ππ ππ» − π΄ππ‘π’ππ πΉππ₯ππ ππ» = π΅πΉπ − π΄πΉπ FOH volume variance = (Actual production vol – budgeted production vol) AOR per unit = (π΄π − π΅π)π΄ππ πππ π’πππ‘ FOH Efficiency Variance FOH capacity Variance = (Std labour hrs – Actual labour hrs) AOR per hour = (Actual labour hrs – budgeted labour hrs) AOR per hr = (ππ» – π΄π») π΄ππ πππ βππ’π 4 = (π΄π» – π΅π») π΄ππ πππ βππ’π By: Maloba Definition of Terms AFO Actual fixed overheads AH Actual hours worked AOR/hr Budgeted Fixed Overheads per hr (Absorption overhead rate per hour) AOR/unit Budgeted Fixed Overheads per unit (Absorption overhead rate per unit) AP Actual Price AQ Actual material quantity (either purchased or used) AR Actual rate (of pay per hour for employees) AV Actual Volume (production or sales volume) AVOR Actual Variable Overhead rate BFO Budgeted fixed overheads BH Budgeted labour hours BP Budgeted selling price BV Budgeted Volume SCM Standard contribution margin SH Standard hours (Expected hours that should have been worked to produce actual quantity) SP Standard Price SPM Standard Profit margin SQ Standard (Expected) Quantity (of materials used to produce actual volume) SR Standard Rate SVOR Standard Variable Overhead rate 5 By: Maloba