Education
Sector
List for Publication
Project
Sanctioning
Authority
Sponsoring
Authority
Traditional /PPP
Status
Construction
Start
Completion
Date
Grangegorman -Site Infrastructure & Public
Realm
The works in question represent the necessary
enabling works required at the Grangegorman
site in advance of the 1st phase of development
of the site which will be delivered via PPP.
Grangegorman DIT Campus
Development of a new centralised DIT campus.
The PPP element comprises the Central Quad
(Food, Sciences, Health & Engineering) and East
Quad (Creative & Cultural Industries) of the
campus.
Schools Bundle 5 (6 schools)
 St Philomena’s NS, Bray
 Eureka Secondary School, Kells, Co Meath
 Coláiste Raithin, Bray
 Loreto College, Wexford
 Carlow Town (1XPost-Primary, 1XFurther
Education)
Schools Bundle 4 (4 replacement schools)
• Comeragh College, Carrick-on-Suir, Co
Tipperary
• Skibbereen, Co. Cork
• St. Joseph’s, Tulla, Co. Clare
• St. Mary’s, Dundalk, Co. Louth
DES
GDA
Traditional
In Construction
2012
Q3 2015
Dept. of
Education
and Skills
(DES)
Grangegorman
Development
Agency (GDA)
PPP
Tender
evaluation
Q3 2015
Q3 2017
DES
DES
PPP
In Procurement
Q4 2015/Q1
2016
Q2 2017
DES
DES
PPP
In Construction
Q1 2015
Q2 2016
Information provided by relevant Departments/Agencies and the NDFA
Issues
Dark Blue – In Construction
Light Blue – In Procurement
White – In Project Planning
1
Health
Sector
List for Publication
Project
Sanctioning
Authority
Sponsoring
Authority
Traditional /PPP
Status
Construction
Start
Completion
Date
New Children's Hospital
The provision of a tertiary paediatric hospital
(384 Beds) on the St James's Hospital campus
and satellite centres on the Connolly & Tallaght
campuses.
D/Health
HSE
Traditional
2016
2019
National Maternity Hospital
The relocation of the National Maternity Hospital
(Holles Street) to St Vincent’s University Hospital
Campus
D/Health
HSE
Traditional
2016
2019
National Forensic Mental Hospital on Portrane
campus (Central Mental Hospital)
The provision of a 120 bed replacement for the
Central Mental Hospital including
accommodation for forensic mental health
services for children and adolescents (10 beds)
and persons with an Intellectual Disability (10
beds).
Primary Care Centres PPP Bundle
14 Primary Care Centres to be delivered at the
following locations: Ballinrobe, Ballymote, Boyle,
Dungarvan, Carrick on Suir, Claremorris,
Coolock/Darndale, Kilcock, Summerhill-Dublin,
Westport, Wexford Town, Waterford City, Tuam,
Limerick City.
D/Health
HSE
Traditional
Design Team
appointed August
2014.
Planning
application to be
submitted to An
Bord Pleanala
(ABP) in mid2015.
Stage 1 design
signed off.
Planning
application to be
submitted to ABP
Q4 2015.
Planning
application
lodged with ABP
in Sept 2014.
Decision expected
Q2 2015.
Q4 2015
Early 2018
D/Health
HSE
PPP
In Procurement
Q1 2016
Q1 2017
Information provided by relevant Departments/Agencies and the NDFA
Issues
Tenders received
in early February
2015
Dark Blue – In Construction
Light Blue – In Procurement
White – In Project Planning
2
Health
Sector
List for Publication
Project
Sanctioning
Authority
Sponsoring
Authority
Traditional /PPP
Status
Construction
Start
Completion
Date
Issues
Cork University Hospital Radiation Oncology
Unit: Development of a new Unit containing 5
Linear Accelerators (LINACs) (4 replacement, I
additional) as part of the National Plan for
Radiation Oncology. The project will include
capacity for future expansion as it would be
technically complex and more expensive to
expand the facility at a later date.
D/Health
HSE
Traditional
Design Team
appointed.
Planning
application
submitted in
December 2014.
Q3 2015
Mid-2017
construction
completed.
University College Hospital Galway Radiation
Oncology Unit: Development of a new Unit
containing 4 LINACs (3 replacement, I additional)
as part of the National Plan for Radiation
Oncology. The project will include capacity for
future expansion as it would be technically
complex and more expensive to expand the
facility at a later date.
D/Health
Design Team
appointed.
Planning
application
submitted in
December 2014.
Q2 2016
(indicative
date given
site issues)
Enabling works and
construction start
dependent on site
being vacated by
transfer of acute
mental health
services to the new
adult mental health
department
(complex build)
Enabling works and
construction start
dependent on site
being vacated by
transfer of acute
mental health
services to new
accommodation
(complex build). Site
issues have delayed
construction of
mental health unit.
National Rehabilitation Hospital
Redevelopment: Phase 1 - Provision of
replacement beds and associated therapy space.
D/Health
HSE
Traditional
Q4 2015/Q1
2016
Q4 2017
St James’s Hospital - MISA Project
Mercer Institute for Successful Aging - 157 Bed
development at St James’s Hospital.
D/Health
HSE
Traditional
Planning
Application with
ABP. Decision due
Q2 2015.
In Construction
Q1 2014
Q4 2015
HSE
Information provided by relevant Departments/Agencies and the NDFA
Traditional
Mid-2018 full
clinical
commissioning
of LINACs
completed.
Mid-2018
construction
completed.
Mid-2019 full
clinical
commissioning
of LINACs
completed.
(Indicative
dates)
Dark Blue – In Construction
Light Blue – In Procurement
White – In Project Planning
3
Transport
Sector
List for Publication
Project
Sanctioning
Authority
Sponsoring
Authority
Traditional
/PPP
Status
Construction
Start
Completion
Date
Luas Cross City
Link existing Luas lines in Dublin city centre and
connect Cabra via Luas to Stephen's Green.
Integrate with rail services from
Maynooth/Dunboyne and most Quality Bus
schemes which enter or cross city centre.
N17/N18 Gort-Tuam
57 km of motorway/dual carriageway providing
bypasses of Clarinbridge, Claregalway and Tuam
NTA
RPA
Traditional
Utility works
currently
underway and
70% complete
Enabling
works 2013
Main
contract
mid-2015
Q4 2017
NRA
NRA
PPP
In Construction
Q2 2014
(Contract
award )
Q1 2018
M11 Gorey-Enniscorthy Motorway
Works of approximately 26km of mainline to
motorway standard (M11 route), 4km of dual
carriageway (N80 Link Road), 8km of single
carriageway (Enniscorthy N30 route)
N25 New Ross Bypass
14.6km of dual carriageway (N25 and N30 route),
and 1.2km of single carriageway (New Ross N30
route).
NRA
NRA
PPP
In Procurement
Estimated
contract
award date
mid-2015
Mid-end 2018
NRA
NRA
PPP
Engagement with
preferred
tenderer
Estimated
contract
award date
mid-2015
Mid-end 2018
N11/Newlands Cross Interchange Bundle
N11 Rathnew to Arklow Road Improvement
Scheme (16.5km of new dual c/way linking the
existing M11 Arklow Bypass and M11 Ashford/
Rathnew schemes); and N7 Newlands Cross
Junction Upgrade Scheme (Replacement of
existing signal controlled at-grade junction with
a grade separated junction on the N7)
NRA
NRA
PPP
In Construction
Newlands Cross
element
completed.
Q3 2013
Q3 2015
Information provided by relevant Departments/Agencies and the NDFA
Issues
Dark Blue – In Construction
Light Blue – In Procurement
White – In Project Planning
4
Sport
Justice
Sector
List for Publication
Project
Sanctioning
Authority
Sponsoring
Authority
Traditional
/PPP
Status
Construction
Start
Completion
Date
Courts Bundle
New courthouses to be built in Drogheda,
Letterkenny, Limerick and Wexford.
Refurbishment and extension works in Cork,
Mullingar and Waterford.
D/Justice
Courts Service
PPP
Tenders due back
in March
Q4 2015
Q4 2017
National Children Detention Facilities (NCDF)
project, Oberstown
Extension / improvement of facilities to increase
residential detention capacity for children on the
Oberstown campus, and allow for the ending of
the practice of detaining children in adult prison
facilities.
D/Children
and Youth
Affairs
Irish Youth
Justice Service
Traditional
In construction
(facilities for 17
year old males
were completed
in Q1 2015 and
are likely to be
brought into
operation for that
age group by
mid-year).
Sept 2013
October 2015.
National Indoor arena: Indoor element of the
National Sports Campus Master Plan comprising
indoor athletics centre, gymnastics centre and
multi-sport hall.
DTTAS
National Sports
Campus
development
Authority
Traditional
Contract signed
January 2015
Feb 2015
Nov 2016
Information provided by relevant Departments/Agencies and the NDFA
Issues
Completion date
depends on phasing
of total Sports
Campus project.
Dark Blue – In Construction
Light Blue – In Procurement
White – In Project Planning
5