Issue: 2 August 2014 Gascoyne Food Bowl Initiative 11Number: 1 Growing the Carnarvon Horticultural Precinct Contents Borefield progress Land expansion the process explained Market analysis Next steps Welcome to the second edition of the Gascoyne Food Bowl (GFB) Initiative newsletter. The last couple of months in the Gascoyne have been busy for the project team. Highlights include: Community and key stakeholder engagement including : o The project team met with the reconstituted Local Consultative Committee (LCC) on 8 May. The LCC included representatives from the Carnarvon Grower’s Asssociation, Gascoyne Water Asset Management Cooperative, the Gascoyne Development Commission and industry representatives. The committee was originally formed in 2008 to report and make recommendations on the development of the initiative to the Ministerial Advisory Committee (MAC). The MAC comprises the Ministers of Agriculture, Water and Regional Development. The LCC submitted a report and recommendations to the MAC in 2010. o The project team met on 8 May 2014 to update the LCC on the progress of these recommendations. Tony Della Bosca (project manager) presented to the Carnarvon Ministerial Advisory Committee on the GFB initiative, its key achievements and milestones achieved to date. The Carnarvon Ministerial Advisory Committee is comprised of key government and industry stakeholders and was established in 2013 as part of a co-ordinated approach to address water shortages in the Carnarvon area. Carnarvon Shire was provided with an update on the project by Trina Anderson, Project senior planning officer, and discussions took place on future working arrangements. The contract for the electrification of the existing northern borefield has been awarded to Horizon Power. The drilling and water tender contracts have awarded with targets identified and access paths cleared. Borefield progress Drilling Sourcing and delivering additional water suitable for the new and expanded horticultural precinct is a major part of the Gascoyne Food Bowl (GFB) initiative. As discussed in the last newsletter, aerial electromagnetic survey (AEM) data has been collated and analysed to identify the potential location, quantity and quality of aquifer water to the east of the existing Carnarvon horticultural precinct. Drilling targets have now been identified and access paths have been cleared, ready for the drilling to start. Awarding a drilling contract is a complicated procedure. It is an open tender process and has to be approved by the State Tender Review Committee. The drilling and the water testing contracts have been awarded to Austral Drilling Services Pty Ltd and Advanced Bore Services Pty Ltd respectively. Drilling is set to begin early August and is due to be completed by June 2015.. Austral drill production rig in operation Once the drilling program has been completed, design will commence for a new pipeline which will be installed to deliver water to the new horticultural precinct. Electrification of existing northern borefield and new borefield The electrification of the existing northern borefield (NBF) is another important component of the GFB project. It will lower pumping costs significantly, compared to current diesel generation and create a more reliable power system for all growers and the community as a whole. The contract for the electrification of the northern borefield has been awarded to Horizon Power. Works have commenced and are due for completion in September. Civil works The infrastructure corridor for the existing northern borefield has been completed, with access paths now being developed for the new northern borefield drilling program. caption for photo All residents are reminded that the northern borefield isThis nowisaaconstruction site and strict entry protocols are in force. Existing northern borefield completed infrastructure corridor 2 Land expansion: the process explained The GFB initiative will see 400 hectares of additional land and infrastructure for horticulture development released to the market. A further 800 hectares of land will also be identified for future expansion. To date, technical studies including an airborne electromagnetic survey (AEM) analysis, soil surveys, revised floodway modelling, land use constraints mapping and flora surveys have taken place to identify suitable parcels of unconstrained land. As a result of this work, approximately 600 hectares of high to moderate capability land has been identified for potential annual and perennial horticulture. The next step in the GFB land expansion process is land tenure change. There are various types of land tenure in Carnarvon which will involve changing land primarily from Unallocated or Vacant Crown Land and Pastoral lease tenure into freehold, which importantly requires Native Title negotiations to occur. Simultaneously, further technical and land use planning studies also need to occur to include the new areas into the Shire of Carnarvon’s ‘Town Planning Scheme 10’. The process to change the land tenure and amend the Shire of Carnarvon Local Town Planning Scheme is a complex process defined by statutory requirements. Below is a flow chart identifying some high level key milestones in this work. Some of this can be undertaken simultaneously, while some can only occur following a linear pathway. The approximate time frame is two years. As you can see a lot of underlying processes are involved in changing land tenure. This process is key to enabling the release of the new horticultural land to the market and will be on-going in the background for the next couple of years. 3 Market analysis An expanded horticultural precinct is seen as a key driver for the Carnarvon horticultural industry to reach a production scale that will support export markets, and therefore increase opportunities for existing and new producers to market their produce both domestically and internationally. Economic studies on developing new and target markets investigating existing and new market opportunities and to consider the impacts of growth on industry development are being developed. Independent contractors are being sourced for an independent review of DAFWA studies on export opportunities for Carnarvon. Carnarvon produce being transported Next Steps The next steps you can look forward to seeing are: full Council briefing on 12 August work to start on the consultancy services for the town planning studies drilling beginning in August electrification of the northern Borefield to be completed September 2014 next newsletter due out in October The project team would like to hear your feedback and comments. Please e-mail Gascoyne@agric.wa.gov.au Important disclaimer The Chief Executive Officer of the Department of Agriculture and Food and the State of Western Australia accept no liability whatsoever by reason of negligence or otherwise arising from the use or release of this publication 4