Section 3: Hydraulics & Hydrology 1 Section 3: Hydraulics & Hydrology Design Final Design Report Prepared For: Capstone Developers 306 Lowry Hall Clemson, SC Date: November 28, 2012 Prepared By: Freeman Mach Consulting (2-1) Frederick Paige Armen Zadoorian Mason Smith Christopher Stubbs Hydraulic and Hydrology Specialist Mason Smith Calculations Deliverable Manager Armen Zadoorian Final Report Deliverable Manager Christopher Stubbs Section 3: Hydraulics & Hydrology 2 Table of Contents Section 3: Hydraulics and Hydrology Calculations Report 3.1: Objective and Scope……………………………………………………………………………………………………..……3 3.2: Pre-Development Site Description…………………………………………………………………………………..…4 3.3: Pre-Development Flow Pattern Description……………………………………………………………….………4 3.4: Pre-Development Curve Number and Time of Concentration…………………………………………….5 3.5: Pre-Development IDEAL Work Space and Hydrographs..……………………………………………………6 3.6: Post-Development Site Description…………………………………………………………………………….………8 3.7: Post-Development Flow Pattern Description………………………………………………………………………8 3.8: Post-Development Curve Number and Time of Concentration…………………………………………11 3.9: Post-Development IDEAL Work Space and Hydrographs………..……………………………………..…13 3.10: Hydrology & Hydraulics Methodology………………………………………………………………………………16 3.11: Analysis and Results…………………………………………………………………………………………………………22 3.12: References………………………………………………………………………………………………………………….……23 3.13: Sample Calculations………………………………………………………………………………………….……………..24 3.14: Lessons Learned……………………………………………………………………………………………….………………28 3.15: Drawings………………………………………………………………………………………………………………….………29 Section 3: Hydraulics & Hydrology 3 3.1 Objective and Scope The Museum of Clemson History, located off Perimeter Rd across from the Botanical Gardens, is under the jurisdiction of Greenville County Stormwater Ordinance and the Master Plan established by Clemson University. Key design parameters and restrictions that are to be satisfied in the design are as follows: Install storm water management facilities to limit the 2-year and 10-year developed peak discharge rates to pre-developed peak discharge rates using a duration of 24 hours with a SCS Type II design storm and pass the 100 year 24 hour storm event resulting in a minimum of 2ft of free board on storm water pond. Return periods, rainfall intensities, pipe sizes, etc should follow the requirements outlined in the Greenville, SC Stormwater Management Design Manual. All pipes shall be designed to flow as open channels. Pressurized flow in any pipe is not acceptable for the 10-year rainfall design event. Gravity-driven flow only, i.e. no pumps. For 100-year storm event pressurized flow in pipes is acceptable. No pipes shall be designed under the building pad. Finished grade spot elevations for structures and invert elevations must be notes on the appropriate drawing(s). IDEAL can be used for pipe sizing, calculating runoff hydrographs, and for the designing the Stormwater pond. Erosion control during construction does not need to be designed, but prevention measures shall be specified for the finished site. Water on rooftops should be collected in a gutter and downspout system. Pavement must be drained with curb and gutter, drainage inlets, or appropriately designed channels. Both a primary and emergency outlet must be designed for the Stormwater pond. The water level in the pond must not me higher than 2ft below the tope of the pond during the 100-year rainfall event. The design of the Stormwater pond must account for the setbacks specified by Professor Csernak. Pervious parking lots cannot be used as detention/retention pond. This reports outlines how the stormwater is to be managed including the design of pipes, inlets, roof drainage, swales, and stormwater pond. All essential components and properties are outlined through tables and figures including a comparison of pre-development runoff with post-development runoff to ensure compliance with code. Section 3: Hydraulics & Hydrology 4 3.2 Pre-Development Site Description The property is approximately 4.5 acres of mostly open area covered primarily with good condition maintained grassland. The northern section of the lot, towards Commons Court, is covered by a wooded area of approximately 1.05 acres, which extends from midway between markers 14-15 to Newman Road Extension. The site is currently used as open park space for students and residents to enjoy recreational and leisure activities. The site has a moderate slope across the entire lot from a maximum elevation of approximately 808 ft to a low point of 780.67 ft which is the top elevation of a catch basin already existing on the site. The resulting change in elevation is approximately 28 ft. The existing catch basin is located on a sag and collects water from the project site and an adjacent property. The catch basin on site measures 3ft by 4ft with an open area of approximately 6 square feet. The majority of the lot results in a natural flow eastwardly toward the existing catch basin. What flows into the catch basin through the top grate and the pipe under Newman Rd. The site is considered to have 3 sub-basins which are displayed in drawing H1 of Section 3.15. The flow from sub-basins 1 and 2 fall into an existing ditch which runs parallel to Perimeter Rd. Sub-basin 3 was determined to flow into the parking lot north of the property along Commons Court. There are several existing trees on site adjacent to Perimeter Rd that run parallel to the ditch. The design of the storm water plan will focus on the preservation of these trees. The soil type is primarily composed of sands and silts resulting in a classification of soil group B and soil type Pacolet. 3.3 Pre-Development Flow Pattern Description The pre-development state can be divided into 3 sub basins as shown in drawing H1 to allocate the runoff to the shared outlet point. The highest elevation on the property, 808ft, is located about 50ft south of marker 15. From this point the majority of the flow will move south and become collected in the existing ditch along Perimeter Rd. The ditch disperses the water east and west to the shared outlet point. The northern most sub-basin, denoted as sub-basin 2 in H1, flows northwardly towards Commons Court where the water is dispersed into existing catch basins. Section 3: Hydraulics & Hydrology 5 3.4 Pre-Development Curve Number and Time of Concentration Table 1: Average Curve Numbers Sub-Basin Grass Cover [acres] Wood Land [acres] Total Area [acres] CN, Grass Cover CN, Wood Land CN, Avg 1 2.215 0.27 2.485 61 55 60.5 2 0.268 0.76 1.028 61 55 56.56 3 0.977 0.977 61 55 61 Using the Greenville County Storm Water Management Design Manual, the curve numbers for each sub basin were determined. Two different land use types were selected, open space with good grass cover and good condition wood land. From the soils report it was determined that the property satisfied the conditions of hydrologic soil group B. Weighing the respective curve numbers with their areas yielded the average curve numbers shown in Table 1 above. Table 2: 2Yr-24Hr Storm Event Time of Concentration 2Yr-24Hr Storm Event Sub-Basin Sheet Flow Tt [hrs] Shallow Concentrated Flow Tt [hrs] Time of Concentration [hrs] 1 0.3156 0.0857 0.4013 2 0.1622 0.1622 3 0.3139 0.0208 0.3347 2 0.1343 0.1343 3 0.2599 0.0208 0.2806 Table 3: 10Yr-24Hr Storm Event Time of Concentration 10Yr-24Hr Storm Event Sub-Basin Sheet Flow Tt [hrs] Shallow Concentrated Flow Tt [hrs] Time of Concentration [hrs] 1 0.2613 0.0857 0.347 Section 3: Hydraulics & Hydrology 6 The time of concentration for each sub basin was computed using the formulas provided by Greenville County’s design manual which can be seen in the sample calculations of section 3.13. The time of concentration was equal to the sum of the sheet flow travel time (first 300’) and the shallow concentrated flow travel time. To use these formulas the hydraulic grade was determined along with the manning sheet flow coefficient (n) and average overland flow velocity (v) for each sub-basin. 3.5 Pre-Development IDEAL Work Space and Hydrographs Figure 1: Pre-Development IDEAL work space Using the software IDEAL, a pre-development workspace was created to model the existing flow conditions and features on the site. From the workspace shown above in Figure 1, two hydrographs were produced for 2Yr and 10Yr-24Hr storm events. Several inputs were used in the model including but not limited to the curve numbers, areas, time of concentrations, and slopes of each basin. Growing season was assumed for the pre-development case to lower the peak discharge for the outlet. This in return provides a more conservative design when paired with a dormant season post-development site. Existing catch basin on site included the dimensions, open area, and elevations. The peak discharge for the 2Yr and 10Yr storm events were 4.448 cfs and 10.54 cfs respectively. Section 3: Hydraulics & Hydrology Figure 2: Pre-Development 2Yr-24Hr Storm Event Hydrograph Figure 3: Pre-Development 10Yr-24Hr Storm Event Hydrograph 7 Section 3: Hydraulics & Hydrology 8 3.6 Post-Development Site Description The post-development site is composed of approximately 1.69 acres of impervious cover (roof, access road, parking lot, sidewalks) and 2.81 acres of pervious good condition grassland. The site will mostly serve academic visits and events as well as tailgating adventures on the weekends. The property will host a 12,500 square foot building pad and roof. The building was designed with a traditional gutter and downspout to remove and disperse the water from the roof surface. Northeast of the museum lies an 84-space parking lot designed to accommodate the guests and service vehicles. Several combination inlets were strategically placed around the parking lot to capture the runoff. The facility also features an access road off Newman Rd Ext directly across from the entrance of the commuter lot R-1. Two slotted drain inlets are located at the beginning and end of the entrance road to prevent runoff from spreading from the parking lot onto the access road and also to eliminate runoff from flowing onto Newman Rd Ext. To allow water flow under the entrance road a culvert was installed as seen in drawing H3. To the north west of the entrance road a stormwater pond was designed to satisfy the hydrologic requirements and setback requirements as outlined by the universities’ master plan and Greenville County Stormwater Ordinance. At 10ft deep, including the 2ft freeboard requirement, the pond has a top stage area of 0.119 acres. The existing ditches along Perimeter Rd. as well as the existing catch basin were included in the stormwater design. Several trees were cut down to satisfy the design requirements. The soil type remains the same as pre-development conditions, Type B Pacolet. 3.7 Post-Development Flow Pattern Description The post-development site can be divided into 17 sub basins as shown in drawing H2. All flow paths are designated with arrows showing the directions of flow within each sub-basin. In the basin delineation 4 major land cover areas were determined for design: roof drainage, parking lot drainage, pervious areas, and the stormwater pond. Section 3: Hydraulics & Hydrology 9 Building Roof Drainage The museum’s roof has a surface area of 12,500 square feet. Due to its irregular shape the roof plan was sloped in two different directions. The two areas were modeled as sub-basins 9 and 10 which can be seen in drawing H2. Sub-Basin 9 of the roof drains northeast where the water is collected in a 5 inch gutter and directed down through 3 inch diameter spaced leaders into the horizontal storm drain pipe GP1. Similarly, Sub-Basin 10 of the roof drains southeast were the water is collected in a 4 inch gutter and distributed into 2 and 3 inch diameter spaced leaders to the horizontal ground pipe GP2. For efficiency the two horizontal ground pipes were connected at a junction located at the northeast face of the building. The junction consists of a 6” ground pipe and 8” ground pipe converging into a 12 inch concrete pipe denoted as P9 in figure 4. Parking Lot Drainage As seen in drawing H2 the parking lot can be divided into 9 sub-basins. Each sub-basin features an inlet to capture the water and direct it to either the storm water pond or off site to the shared final outlet point. The parking lot slopes 2% in one direction toward Marker 15 at the north end of the property. Several islands and 6 inch raised curbs required the Water Drop command in AutoCAD Civil 3D to achieve accurate delineation. Sub-Basin 11 flows northwest where the flow if captured in SD3, a 0.67ft x 30ft slotted drain inlet, and then piped through P5 into the next inlet of the network. Sub-Basin 12 flows north following the raised curb and is collected in I1, a 2ft x 3ft combination inlet. From Inlet I4 the flow is piped through P4 to the outfall structure O1. Sub-Basin 13 flows north and is collected along the 6 inch raised curb connecting the parking lot islands. At the north end of the curb the flow is collected in Inlet I4, a 2ft x 3ft combination inlet. Sub-Basin 14 flows north and collected in I3, a 2ft x 3ft combination inlet. As shown in drawing H3 the ground pipe junction connects to Inlet I4, which connects to I3 where finally the water is piped through P7 to the outfall structure. Sub-Basin 15 flows north into I5 where the water flows through pipe P10 to inlet I3. From Inlet I3 the water is piped through P7 to the outfall structure. Sub-basin 16 flows directly toward the access road where a 0.5ft x 40ft slotted drain inlet, SD2, was designed to capture and prevent the flow from spreading down toward Newman Rd Ext. Section 3: Hydraulics & Hydrology 10 Pervious Areas Several areas around the site remained undisturbed from the pre-development conditions. These include sub-basins 1, 2, 4, 5, and 17. Sub-basin 1 and 2 become collected in the existing ditch along Perimeter Rd. The ditch disperses the water east and west to the shared outlet point. The northern most sub-basin, denoted as sub-basin 5 in H2, flows northwardly towards Commons Court where the water is dispersed into existing catch basins. Sub-basin 4 flows southeast under the access road through a 15” RCP culvert to the existing catch basin on site. Sub-basin 17 lies within the grading of the stormwater pond so runoff will naturally flow into the pond. Access Road and Road Surrounding Building As seen in drawing H2 the access road is defined as sub-basin 3 and the road surrounding the building pad is labeled as sub-basins 6,7, and 8. Sub-Basins 6 and 7 flow southwest where they share inlet I2, a 2ft x 6ft combination inlet. Inlet I2 is piped through P6 where it joins the network at slotted drain Inlet SD3. Sub-basin 8 is located at an elevation lower than the stormwater pond so water was collected in inlet SD4, a 0.67ft x 22ft slotted drain inlet, and then piped through SP2, an 8 inch PVC pipe, to swale 2 where the water is dispersed to the shared outlet point. The connection of SP2 and swale 2 is riprapped to reduce scouring and erosion when the flow hits the ground surface and also to allow for increased time of infiltration. The access road is sloped toward Newman Rd Ext. To capture the runoff a 0.5ft x 40ft slotted drain inlet, SD1, was placed at the intersection of the access road and Newman Rd Ext. From SD1 the water is sent through SP1, a 6 inch PVC pipe, (with Riprap protection) to swale 1 where the water is collected in the grate of the existing catch basin on site. Storm Water Pond (Refer to Drawings H3,H4,H5) The first step in designing the storm water pond was recognizing the setbacks established by Clemson’s master plan. With a 25ft setback from the access road, Newman Rd Ext, and Commons court the pond was polygon shaped to fit within the setbacks. The size of the pond was determined using the hydrograph of outfall structure O1 before the stormwater pond was introduced to the post-development IDEAL file. The run-off volume was approximately 1.13 acft or 1823 yd3. The lowest elevation of the pond was determined to be 780ft allowing for a total Section 3: Hydraulics & Hydrology 11 depth of 10 ft including the 2 ft freeboard requirement. With the limited space the pond slope was designed at 2H:1V to maximize the total volume. Greenville County Stormwater Ordinance requires that pond slopes shall be no steeper than 3H:1V but erosion control measures on a 2H:1V slope satisfy the requirements. TRMs (Turf Reinforcement Mats) are recommended in the design to enhance the ability of plants to stabilize the soil and prevent erosion of the pond side slopes. The maximum top stage area was 0.119 acres and bottom stage area was 0.0135 acres. To reduce the peak runoff an open top barrel riser was designed with several orifices at varying heights which is displayed in H5. Once water enters the barrel riser flow travels through pipe P1, an 18” RCP, to the existing catch basin on site. A 5ft wide rectangular emergency spillway located at 7.5ft from the bottom of the pond was included for 100Yr storm events. Riprap protection outside the spillway was provided to reduce erosion and scouring when in use and shown in drawing H5. 3.8 Post-Development Curve Number and Time of Concentration Table 4: 2Yr-24Hr Storm Event Average Curve Number and Time of Concentration 2yr-24Hr Storm Event Sub-Basin 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Area [acres] 0.998 0.831 0.051 0.0845 0.587 0.17 0.297 0.05 0.115 0.172 0.138 0.24 0.245 0.087 0.202 0.071 0.034 Curve Number, Avg 61 61 98 61 56.2 84.27 75.2 92.8 98 98 98 98 98 98 98 98 61 Flow Path [ft] 367.28 437.9 83.71 124.6 104.2 216 187 108.62 150 150 155.72 192.04 243.6 111 186.68 98.4 5.52 Hydraulic Grade [ft/ft] 0.075 0.041 0.087 0.064 0.08 0.025 0.02 0.021 0.02 0.02 0.027 0.023 0.025 0.029 0.024 0.032 0.732 Travel Time [hrs] 0.335 0.420 0.009 0.166 0.131 0.034 0.031 0.020 0.026 0.026 0.024 0.030 0.035 0.018 0.029 0.015 0.005 Table 5: 10Yr-24Hr Storm Event Average Curve Number and Time of Concentration 10yr-24Hr Storm Event Sub-Basin 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Area [acres] 0.998 0.831 0.051 0.0845 0.587 0.17 0.297 0.05 0.115 0.172 0.138 0.24 0.245 0.087 0.202 0.071 0.034 Curve Number, Avg 61 61 98 61 56.2 84.27 75.2 92.8 98 98 98 98 98 98 98 98 61 Flow Path [ft] 367.28 437.9 83.71 124.6 104.2 216 187 108.62 150 150 155.72 192.04 243.6 111 186.68 98.4 5.52 Hydraulic Grade [ft/ft] 0.075 0.041 0.087 0.064 0.08 0.025 0.02 0.021 0.02 0.02 0.027 0.023 0.025 0.029 0.024 0.032 0.732 Travel Time [hrs] 0.281 0.352 0.007 0.137 0.109 0.028 0.026 0.016 0.022 0.022 0.020 0.025 0.029 0.015 0.024 0.013 0.004 Section 3: Hydraulics & Hydrology 12 Table 6: 100Yr-24Hr Storm Event Average Curve Number and Time of Concentration 100yr-24Hr Storm Event Sub-Basin 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 0.998 0.831 0.051 0.0845 0.587 0.17 0.297 0.05 0.115 0.172 0.138 0.24 0.245 0.087 0.202 0.071 0.034 61 61 98 61 56.2 84.27 75.2 92.8 98 98 98 98 98 98 98 98 61 Flow Path [ft] 367.28 437.9 83.71 124.6 104.2 216 187 108.62 150 150 155.72 192.04 243.6 111 186.68 98.4 5.52 Hydraulic Grade [ft/ft] 0.075 0.041 0.087 0.064 0.08 0.025 0.02 0.021 0.02 0.02 0.027 0.023 0.025 0.029 0.024 0.032 0.732 Travel Time [hrs] 0.221 0.276 0.006 0.106 0.084 0.022 0.020 0.013 0.017 0.017 0.015 0.019 0.022 0.011 0.018 0.010 0.003 Area [acres] Curve Number, Avg Using the same methods as the pre-development case, the curve numbers and time of concentration for each sub basin were determined. Two different land use types were selected, open space with good grass cover and paved surfaces. Weighing the respective curve numbers with their areas yielded the average curve numbers shown in the tables. The time of concentration for each sub basin was computed using the formulas provided by Greenville County’s design manual which can be seen in the sample calculations. The time of concentration was equal to the sum of the sheet flow travel time (first 300’) and the shallow concentrated flow travel time. To use these formulas the hydraulic grade was determined along with the manning sheet flow coefficient (n) and average overland flow velocity (v) for each subbasin. Section 3: Hydraulics & Hydrology 13 3.9 Post-Development IDEAL Work Space and Hydrographs Figure 4: Post-Development IDEAL work space Using the software IDEAL, a post-development workspace was created to model the flow features and conditions displayed in drawing H3. Dormant season was assumed for the post-development case to increase the peak discharge for the outlet. This in return provides a more conservative design when paired with a growing season used on the pre-development site. From the workspace shown above in Figure 4, four hydrographs were produced for 2Yr and 10Yr 24Hr storm events. Two hydrographs before and after the storm water pond was inputted into IDEAL. From the pre-development case the peak discharge for the 2Yr and 10 Yr storm events where 4.448 cfs and 10.54 cfs respectively. Without the stormwater pond the post-development yielded a 2Yr and 10Yr storm event peak discharge of 10.39cfs and 16.85cfs respectively. With the stormwater pond the post-development yielded a 2Yr and 10Yr storm event peak discharge of 4.246cfs and 9.822cfs respectively. Section 3: Hydraulics & Hydrology Figure 5: Post-Development (W/Out Pond) 2Yr-24Hr Storm Event Hydrograph Figure 6: Post-Development (W/Out) 10Yr-24Hr Storm Event Hydrograph 14 Section 3: Hydraulics & Hydrology Figure 7: Post-Development (With Pond) 2Yr-24Hr Storm Event Hydrograph Figure 8: Post-Development (With Pond) 10Yr-24Hr Storm Event Hydrograph 15 Section 3: Hydraulics & Hydrology 16 3.10 Hydrology & Hydraulics Methodology Pipes & Inlets The design of the stormwater system was completed using the computer program IDEAL. IDEAL is a computer software used to model stormwater runoff. Several inputs and storm events can be tested to accurately produce hydrographs and other environmental impacts on the soil and water. The initial IDEAL file was setup without a storm water pond. The design of the inlets and pipes above the storm water pond elevation needed to satisfy the 2Yr and 10Yr requirements as stated in the Greenville County Stormwater Ordinance. Using the information from tables 4, 5, and 6 each sub-basin was created in the workspace as shown in figure 4. Sub-basins were selected as pervious, impervious or combined areas. Areas, curve number, peak rate factor, and time of concentration were imputed for each individual sub-basin. All soils were selected as Pacolet from the provided soils report. With the subbasins arranged each was connected with the appropriate feature (Non-Routed Connector, Pipe Structure, or Circular Conduit) based on drawing H3. Sub-basins that drained off site away from the existing catch basin were connected to the shared final outlet. Before IDEAL was ran several design guidelines were established on top of the requirements set by Greenville County. 1. 2. 3. 4. Maximum Spread of 3ft (6-feet is Actual Max GCSO 6.5.1.7) Maximum Spacing of 300ft. Minimum Pipe Slope of 0.5% (GCSO 6.5.1.5) The minimum fill over on all pipes shall be 1-foot (GCSO 6.5.1.6) To be conservative a maximum spread of 3ft was established and a maximum spacing of 300ft was selected to treat the runoff as sheet flow. Initially all pipe sizes were assumed to be 15” RCP pipes and all combinations inlets assumed to be 2ft x 3ft combination inlets with a 4” throat height. Slotted drain inlets spanned the width of the road and the grates were assumed to be either 6 or 8 inches wide depending on the pavement slope. Combination inlets were selected because they provide both trash and water removal. Slotted drain inlets were selected to separate parking lot and road areas for delineation purposes as well as reduced flow paths. All sub-basins that flowed over the surface were treated as non-routed connectors to their respective inlets. With all assumptions and properties inputted IDEAL was validated and run. The report following displayed spreads, surcharges, and error messages. All conduits and inlets that were surcharged were increased until the error message cleared. The error message “Convergence criteria is not met. Flow is routed as simple translation” was ignored. This process was repeated until all pipes and inlets met design requirements but yet remained cost effective. With the maximum spacing between inlets 300ft this did not affect any of the design. Section 3: Hydraulics & Hydrology 17 Roof Drainage The roof drainage design can be seen in Roof Drainage Calculations of the sample calculations in section 3.13. Following the guidelines provided by the 2000 International Plumbing Code (IBC) the roof drainage design satisfies the 100-YR-1Hr Rainfall events for this particular area. A traditional downspout and gutter was chosen for the Museum of Clemson History. As seen in the calculations the roof plan was divided into 3 areas to simplify the irregularly shaped roof. From figure 1106.1 of the IBC the 100-Yr-1Hr rainfall was determined to be 4.0 inches for the Clemson area. A 3-inch diameter vertical leader was assumed from table 1106.2. Spacing for the leaders was then determined and checks to ensure the assumed leader diameter satisfied the requirements. Both gutter size and horizontal storm drainage piping were selected at ¼” slope in 12. From tables 1106.6 and 1106.3 the gutter size and horizontal storm drain piping were determined. These steps were followed for each of the three roof areas. Areas 2 and 3 converge to form a single 3-inch diameter leader to satisfy both areas to the left and right of the dashed line as depicted in the sample calculations. Table 7: Combination Inlets Structure I1 I2 I3 I4 I5 Size (ft) 2X3 2X6 2X3 2X3 2X3 Throat Height (in) 4.0 6.0 4.0 4.0 4.0 Opening Area (ft2) 3.0* 6.0 3.0* 3.0* 3.0* * Not included in IDEAL for inlets on grade. Table 7 displays the final dimensions for the combination inlets. Inlet I2 was the only one surcharged during the 10Yr event so the size was doubled to reduce the spread down below the 3ft goal. Table 8: Slotted Drain Inlets Structure SD1 SD2 SD3 SD4 Size (ft) 0.5X40 0.5X40 0.67X30 0.67X22 Opening Area (ft2) 8.0* 8.0* 6.0* 4.0* * Not included in IDEAL for inlets on grade. Section 3: Hydraulics & Hydrology 18 Table 8 displays the final dimensions for the slotted drain inlets. 6-inch wide grates were used for low slope areas and 8-inch wide grate for steeper slopes and/or increased catchment area. Table 9: Pipe Dimensions and Properties Pipe Diameter (in) Length (ft) Slope Material P1 18 130 0.007 RCP P2 18 5 0.02 RCP P3 15 60 0.005 RCP P4 15 80 0.0063 RCP P5 15 120 0.0058 RCP P6 12 170 0.0165 RCP P7 15 22 0.01 RCP P8 15 22 0.01 RCP P9 12 150 0.03 RCP P10 15 80 0.05 RCP GP1 6 54 0.02 PVC GP2 8 58 0.02 PVC SP1 6 20 0.075 PVC SP2 8 50 0.04 RCP PIPE UNDER PERIMETER RD 20 120 0.0125 RCP Abbreviations: PVC - Polyvinyl Chloride RCP - Reinforced Concrete Pipe Table 9 displays the pipe schedule with appropriate dimensions, slope, and material. The diameter of P1, P2, and the pipe under Perimeter Rd had to be increased to prevent surcharging. The increase in the diameter of the pipe under Perimeter required the invert elevation at the existing catch basin to be lowered to 778.5ft to accommodate the increased pipe diameter. GP1, GP2, and SP1 were all selected to be PVC to reduce costs. Section 3: Hydraulics & Hydrology Table 10: Structure Rim Elevations and Pipe Invert Elevations Structure Rim Elevation (ft) P4 I1 791.8 787.5 P6 I2 793.6 791 P7 I3 793 787.4 P8 I4 793.85 787.8 P10 I5 795.25 791.4 SP1 SD 1 787 785.5 P3 SD 2 794.2 787.3 P5 SD 3 794.6 788.2 SD 4 797.3 O1 790 Swale 1 785 Swale 2 795 Invert Elevation (ft) P5 787.5 P8 787.4 P10 787.4 P6 788.2 SP2 795 P3 P4 787 787 SP1 784 SP2 793 Pipe Under Perimeter Pipe Under Newman 779.07 Existing Catch Basin on Site 780.67 778.5 Catch Basin 780 Pipe Under Perimeter 777 P7 787 Table 10 displays all the rim elevations of the stormwater system structures. Each structure has the invert elevations of all pipes entering or exiting the structure. All pipes remained at a minimum 1ft below the ground surface to satisfy the fill requirements. All pipes were also designed at a minimum pipe slope of 0.5% to meet code. 19 Section 3: Hydraulics & Hydrology 20 Table 11: Swale Dimensions Type Length (ft) Width (ft) Max Depth (ft) Slope (ft/ft) Side Slope (ft/ft) Mannings Coeff. (n) Swales SW1 Trapazoidal 52 2 1 0.01 0.3 0.24 SW2 Trapazoidal 150 2 1 0.01 0.3 0.24 As seen in drawing H3 two swales were designed to increase the flow path of the runoff from SP1 and SP2 to the existing catch basin and shared outlet point respectively. The dimensions of the swales were all assumed based on common design surrounding the university. Sod was used to cover the swales due to an increased manning coefficient and time of concentration. Table 12: Pre and Post-Development Hydrograph Properties Hydrograph Properties 2-Yr Storm Event Peak Flow (cfs) 10-Yr Storm Event Peak Flow (cfs) 2-Yr Storm Event Peak Discharge Time (hrs) 10-Yr Storm Event Peak Discharge Time (hrs) 2-Yr Storm Event Runoff Volume (ac-ft) 10-Yr Storm Event Runoff Volume (ac-ft) PreDevelopment 4.448 10.54 12.1 12.1 0.5862 1.222 PostDevelopment 4.246 9.822 12.1 11.0 0.7083 1.62 Table 12 displays the tabulated output from figures 2,3,7 and 8 for the pre and post-development hydrographs. The post-development 2Yr and 10Yr storm event peak flow satisfies the design requirements set by the Greenville County Stormwater Ordinance. The post-development 10Yr storm peak discharge time was reduced from the effects of the stormwater pond. Section 3: Hydraulics & Hydrology 21 Table 13: Pond Properties Pond Properties Depth (ft) 10 Stage-Area 0ft (acres) 0.0135 Stage-Area 10ft (acres) 0.119 Riser Type Open Top Shape Circular Height (ft) 7.5 Diameter (in) 24 Orifices Diameter (in) 1 @ 0ft 1.5 1 @ 3ft 1.5 3 @ 6ft 3 Barrel Diameter (in) 18 Length (ft) 25 Slope 0.02 Material RCP Emergency Spillway Type Broad-Crested Weir Shape Rectangular Crest Height (ft) 7.5 Width (ft) 6.0 Table 12 displays the pond properties during the 2,10, and 100Yr-24Hr storm events. With the confined area from the parking lot and property setbacks the pond surface area was at its max. With a 2H:1V grading the stage area at the top of the pond was 0.119 acres and bottom equal to 0.0135 acres. A 7.5ft tall 24-inch diameter open top riser was designed to control the outflow from the pond. The storm water pond was tested at 2yr, 10yr, and 100yr storms to determine the elevations and number of orifices along the riser. The barrel was designed to be 25ft long with an 18inch diameter composed of RCP. The emergency spillway was designed at 7.5ft above the bottom surface of the pond. Rectangular in shape the broad-crested weir spans 6.0ft wide. Riprap protection on the opposite side of the weir provides erosion control from scouring when the emergency spillway is in use. A plan and profile view of the stormwater pond can be seen in drawings H4 and H5. Section 3: Hydraulics & Hydrology 22 3.11 Analysis and Results Table 14: Pre-Development Peak Flow versus Post-Development Peak Flow 2-Yr Storm Event 10-Yr Storm Event Peak Flow (cfs) Pre-Development 4.448 10.54 Post-Development 4.246 9.822 As stated in the Greenville County Stormwater Ordinance the post-development peak flow shall not be greater than the pre-development peak flow rate. With the given stormwater design the posdevelopment satisfies this requirement for both the 2Yr and 10Yr-24Hr storm events. Table 15: Inlet Spreads Inlet I1 I2 I3 I4 I5 Spread (ft) 1.97 2.82 1.35 2.66 1.85 As stated by the Greenville County Stormwater Ordinance the maximum spread in the travel lane must not exceed 6-feet during the 10Yr storm event. A 3-feet maximum spread was used in the design during IDEAL so this requirement is satisfied. Table 16: Stormwater Pond Peak Stage Peak Stage (ft) 2-Yr Storm Event 10-Yr Storm Event 100-Yr Storm Event 5.37 7.393 7.937 As stated by Capstone Developers a minimum freeboard of 2-foot above the 100-year 240hr design storm water elevation must be maintained. Additionally the emergency spillway must be utilized by the 100-year storm only. During the 2Yr-24Hr storm event he pond rises to 5.37ft using the first two sets of orifices on the barrel riser. During the 10Yr-24Hr storm event the water level rises 7.393ft utilizing the last set of orifices at 6ft above the bottom surface of the pond. With an emergency spillway elevation of Section 3: Hydraulics & Hydrology 23 7.5ft above the bottom of the pond the emergency spillway is being utilized during the 100-yr storm event only. The maximum pond depth is 10ft including the freeboard requirement concluding that the peak stage of 7.937ft lies below the 8ft maximum required in design. The stormwater design for the Museum of Clemson History satisfies all design requirements established by the Clemson University Master Plan and the Greenville County Stormwater Ordinance. Technical Specification included in the stormwater design: Division 33: 334100 3.12 References Greenville County Storm Water Management Design Manual 2000 International Plumbing Code “Hydrology and Hydraulic Systems”, Gupta, Ram S. 3rd Edition IDEAL® Software PowerPoint’s provided by Dr. Earl Hayter Clemson University Section 3: Hydraulics & Hydrology 3.13 Sample Hand Calculations Time of Concentration, Tc Pre-Development Sub-Basin 1: Flow Line A: 577.8ft 𝐻𝑦𝑑𝑟𝑎𝑢𝑙𝑖𝑐 𝐺𝑟𝑎𝑑𝑒 𝑓𝑜𝑟 𝑓𝑖𝑟𝑠𝑡 300′ = 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 1−𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 2 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒 𝐻𝑦𝑑𝑟𝑎𝑢𝑙𝑖𝑐 𝐺𝑟𝑎𝑑𝑒 𝑓𝑜𝑟 𝑓𝑖𝑟𝑠𝑡 300′ = 𝑆ℎ𝑒𝑒𝑡 𝐹𝑙𝑜𝑤 𝑇𝑟𝑎𝑣𝑒𝑙 𝑇𝑖𝑚𝑒, 𝑇𝑡 = 𝑇𝑡 = 808𝑓𝑡 −785.81𝑓𝑡 300𝑓𝑡 = 0.074 0.007(𝑛𝐿)0.8 𝑃2 0.5 𝑆 0.4 0.007(0.24 ∗ 300)0.8 = 0.3156 ℎ𝑟𝑠 3.70.5 0.0740.4 𝑆ℎ𝑎𝑙𝑙𝑜𝑤 𝐶𝑜𝑛𝑐𝑒𝑛𝑡𝑟𝑎𝑡𝑒𝑑 𝐹𝑙𝑜𝑤 𝑇𝑟𝑎𝑣𝑒𝑙 𝑇𝑖𝑚𝑒, 𝑇𝑡 = 𝑇𝑡 = 277.8𝑓𝑡 3600∗0.9𝑓𝑡/𝑠 𝐿 3600𝑣 = 0.0857 ℎ𝑟𝑠 𝑇𝑖𝑚𝑒 𝑜𝑓 𝐶𝑜𝑛𝑐𝑒𝑛𝑡𝑟𝑎𝑡𝑖𝑜𝑛, 𝑡𝑐 = 𝑆ℎ𝑒𝑒𝑡 𝐹𝑙𝑜𝑤 𝑇𝑡 + 𝑆ℎ𝑎𝑙𝑙𝑜𝑤 𝐶𝑜𝑛𝑐𝑒𝑛𝑡𝑟𝑎𝑡𝑒𝑑 𝐹𝑙𝑜𝑤 𝑇𝑡 𝑡𝑐 = 0.3156ℎ𝑟𝑠 + 0.0857ℎ𝑟𝑠 = 0.4013 ℎ𝑟𝑠 Curve Number, CN Pre-Development Sub-Basin 1: Total Area: 2.485 acres composed of grass and wood land. Good Condition Open Space Grass Cover = 2.215 acres Good Condition Wood Land = 0.27 acres CN Grass Cover = 61 CN Wood Land = 55 𝐶𝑁𝐴𝑣𝑔 = 𝐶𝑁𝐴𝑣𝑔 = 𝐴𝑟𝑒𝑎1 𝐶𝑁1 + 𝐴𝑟𝑒𝑎2 𝐶𝑁2 𝐴𝑟𝑒𝑎 1 + 𝐴𝑟𝑒𝑎 2 2.215 ∗ 61 + 0.27 ∗ 55 = 60.3 2.485 24 Section 3: Hydraulics & Hydrology Page 1 of roof calcs 25 Section 3: Hydraulics & Hydrology Page 2 of roof calcs 26 Section 3: Hydraulics & Hydrology Page 3 of roof calcs 27 Section 3: Hydraulics & Hydrology 28 3.14 Lessons Learned In the design of the stormwater system several lessons were learned. From a software standpoint AutoCAD Civil 3D was heavily used in the pre-development and post-development basin delineation. Features like Water Drop were a useful tool to gain a visual perspective of how water would flow over the created surface. IDEAL created a computer model of the basin delineation that could be analyzed through several storm events displaying reports for the inlets, pipes, pond, and runoff values. Following the design requirements from Capstone Developers and the Greenville County Stormwater Ordinance required a lot of checklists and management duties to ensure the design was compliant with the minimum standards and also the higher standards on top of the GCSO. Communication and planning between Freeman Mach Consulting played a crucial role in an efficient stormwater design. Grading the site to use natural gravity flow while leaving sufficient area on a confined plot for the storm water pond required several inputs from the transportation, construction, and hydrologic design specialist. Section 3: Hydraulics & Hydrology Section 3.15 Hydraulics & Hydrology Drawings H1: Pre-Development Sub-Basin Delineation H2: Post-Development Sub-Basin Delineation H3: Building and Parking Lot Flow Features H4: Stormwater Pond Plan View H5: Stormwater Pond Elevation View 29