Loughborough Rugby Football Club Alteration to Clubroom

advertisement
Loughborough Rugby Football Club
Alteration to Clubroom, Entrance, Bar and Ladies Toilets – Scheme One
GENERAL
1. Remove inner doors to entrance lobby.
2. Remove stud walls to boiler room and stud walls and rear doors to shop.
3. All new walls to be block work with plaster and skim both sides except in wall surfaces to new boiler
room. Existing walls to be made good before decoration.
4. All new doors to be solid, wood grain finish, with stainless steel furniture.
5. All ceiling to be under-boarded and skimmed.
6. Fit new shirting and architrave.
7. All areas to be decorated with eggshell or similar to walls and ceilings and undercoat and two coats
of gloss to all second fix joinery.
BOILER ROOM AND SHOP
1. Replace ceiling with plaster board and skim to new shop.
2. Replace ceiling with two layers of 12.5mm plaster board and skim to give 60 minute fire resistance
to new boiler room.
3. New wall between boiler room and shop to have 60 minute fire resistant, lockable, double door in
line with existing exterior door for future removal of boiler and cylinders.
4. Single, lockable, 60 minute fire resistant door fitted, with raised threshold between boiler room and
entrance lobby. Fit ID label to boiler door.
5. Install air bricks in exterior walls as required by building regulations.
6. Install 2no 1800mm fluorescent lights to boiler room and one to shop, all fitted with defusers.
7. Install double switched power socket to each room.
8. Move existing boiler controls from existing shop into boiler room.
9. Install door and window between entrance lobby and shop, including reinforced concrete lintel.
10. Shop floor to be fitted with sheet vinyl with sealed joints or similar.
11. Shop fitted out with racking as required.
ENTRANCE LOBBY AND PASSAGE TO CHANGING ROOMS
1.
2.
3.
4.
5.
Install new door with closer to passage adjacent gent’s toilet.
Build wall between lobby and club room and fit new double door to swing both ways on drop hinges.
Install 8no recessed lights and 2no switched power points.
Floor to be fitted with sheet vinyl with sealed joints or similar.
Install radiators with thermostatic valves.
KITCHEN AND STORE
1. Remove end wall to kitchen. (Check to see if universal beam required to support tank in roof).
2. Build new walls, including serving hatch with lintel over and shutter doors and lockable door off
passage.
3. Install 2no additional fluorescent lights with defuser and 3no additional double switched power
points. Allow pc sum to ‘tidy up’ existing electrics in kitchen.
4. Allow pc sum to remove existing hot water storage cylinder in ladies toilet and connect to main hot
and cold water system.
5. Extend existing floor tiles or fit new.
6. Fit new floor to ceiling wall tiles.
7. New light to store room.
8. New lockable door to store room. Fit ID label to door of store.
LADIES TOILET
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Completely gut all fixtures and fitting.
Remove load bearing wall and install universal beam.
Brick up existing exterior door and windows.
Tile walls floor to ceiling.
Tile floor with anti-slip tiles.
Install 3no partitioned cubicles and 3no wash hand basins in vanity unit with mirrors.
Install suspended ceiling with recessed lights operated by movement sensor.
Install extractor fan, operated through light switch and timer.
Fit new doors with self-closers.
Allow pc sum to remove hot water cylinder. (see KITCHEN AND STORE – ITEM 4)
Install radiator with thermostatic valves.
CLUB ROOM AND BAR
1.
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Change bar design by:
Remove bar adjacent to cellar.
Cloak brick front with panelling.
Fit new counter making gap behind bar wider.
Remove existing suspended ceiling and replace with new including new recessed lights.
Install display cabinets and glass washer.
Re-position entrance and make lockable.
Fit security shutters.
Remove wall tiles and replace with mirrors. Retain mirror with LRFC motif.
Move till to centre of bar.
Create new shelving for glasses.
Brick-up existing fire door.
Install new fire door in side wall adjacent to cellar.
Install new sliding patio doors and shutters.
Create new entrance and lobby to field side of club house.
Re-position TV and surround sound to far end of club room and install second smaller TV adjacent
door between passage and club room.
Install new floor covering.
Install new lighting and switched double power sockets.
Fit new curtains or blinds.
Photo’s to be reframed and hung to suit in club room and passage.
Make and install new President and Captains board.
Install new trophy cabinets.
Purchase new furniture. Tables and chairs.
Re-position radiators and fit thermostatic valves.
SCHEME TWO
GENERAL, SHOP, BOILER ROOM, CLUB ROOM, BAR AND ENTRANCE LOBBY TO GENERALLY
REMAIN AS SCHEME ONE
DISABLED TOILET
1. Uni-sex disabled toilet to be built off passage and to meet all aspects of Building Regulations Part
M. ie Door opening outwards, sockets and switches positioned at correct height.
2. Floor to ceiling tiles.
3. Anti-slip tiles to floor.
1.
2.
3.
4.
KITCHEN
Existing kitchen walls to be removed.
Floor tiles to be removed.
All electrics to be removed and made good.
All kitchen equipment to be re-sited in new kitchen.
NEW KITCHEN AND LADIES AND GENTS TOILETS TO BE BUILT ADJACENT CELLAR.
1. Existing ladies toilet and store to be retained for changing room use.
2. New ladies and gent’s toilet to be built to standard in scheme one.
CLUB ROOM AND BAR
1. Bar as scheme one but longer, to compensate for new toilet layout.
2. Existing fire doors to be retained and porch built to conserve heat loss.
3. TV re-positioned