Page |1 ClearCove Systems Enhanced Primary Treatment Demonstration at the Ithaca Area Wastewater Treatment Facility Agreement No. 38782 Reporting Period: 5/21/2104 – 10/3/2014 All report materials can be found at www.clearcovesystems.com/pon2722, password: pac1 Report Summary: - Energy Reduction: Section II reports the removal rates of various parameters achieved by the Enhanced Primary Treatment (EPT) pilot which will be used to calculate the energy and cost savings at full scale. o For more information regarding how the EPT pilot was optimized for both operational mode and chemical dosing refer to Appendix A. o Expanded removal data from the ClearCove EPT pilot can be found in Appendix B. Mass Balance: Preliminary Results - Energy Production: Section III details the energy production piloting operation and results of: o Phase 1 and Phase 2 of the mini-digester pilot Expanded data for the mini-digester pilot can be found in Attachments 2A and 2B. o Biochemical Methane Potential Testing Individual Biochemical Methane Potential (BMP) reports can be found in Appendix C. - Sludge Processing: Section IV explains how the sludge processing impacts of both the EPT and Recommended Viewing: A tutorial animation of how the technology works including key features impacting energy reduction and production can be found at: http://clearcovesystems.com/the-idea/settling-system-design/ Page |2 Introduction Using data collected from the ClearCove Enhanced Primary Treatment (EPT) pilot unit (EPT pilot), ClearCove Sludge Classifying Press (SCP), and custom constructed mini-digesters (O’Brien and Gere) located at the Ithaca Area Wastewater Treatment Facility (IAWWTF), the goal of the study is to predict potential impacts to plant-wide operations should the solution be implemented at full-scale at the IAWWTF. It is anticipated that when operating at full-scale, the technology solution will provide the IAWWTF with the following benefits: Aeration energy savings as a result of enhanced BOD removal; Increased biogas generation as a result of enhanced primary sludge capture; Relative capacity increase of the digesters as a result of increased sludge biodegradability and improved inorganics removal; Improved sludge processing as a result of higher percent solids and improved ratio of primary to secondary sludge; and Plant chemical usage/costs compared to current chemical usage/costs. I. Background Figure 1: EPT Pilot Unit The technology is a physical / chemical process that: equalizes the flow; stops the water; removes 100% of the grit; 100% of the fibers; settles the high value organics through chemical dosing and gravity; filters the effluent through a 50 micron screen; removes the sludge to a classifying press; routes the material to a sludge holding tank or to disposal. (Please see video and animation file) The pilot EPT unit consists fully automated 20,000 gallon per day (GPD) fully operational, multiple section reactor tank as shown in Figure 1. The unit has been installed in close proximity to the head works of the IAWWTF. Raw sewage is pumped to the pilot from the influent feed channel of the IAWWTF downstream of a 1.5” Climber Screen and the return of plant process side streams from the thickeners, Anaerobic Digesters, belt press, and tank drains, and upstream of any chemical addition. Twenty four (24) hour composite samples of the pilot influent, pilot effluent, pilot sludge, and IAWWTF primary clarifier effluent are collected on Monday, Tuesday, Wednesday, and Thursday at 8 am and analyzed by CES Environmental, a third party laboratory for: Biochemical Oxygen Demand, 5-day (BOD5) Soluble Biochemical Oxygen Demand, 5-day (SBOD5) Chemical Oxygen Demand (COD) Total Suspended Solids (TSS) Volatile Suspended Solids (VSS) Total Phosphorous (TP) Page |3 Total Kjeldahl Nitrogen (TKN) The purpose of this accumulated data is to calculate the aeration energy savings, sludge impact, methane gas production, and chemical usage calculations for the potential full-scale build-out of the IAWWTF. Biogas production (as a proxy for energy production) is being evaluated using two distinct methods. The first method uses pilot-scale mini digesters (four (4), 350 gallons each). The second is through biochemical methane potential testing using Bioprocess Control’s Automatic Methane Potential Test System (AMPTS) II. The CCS EPT Pilot sludge is processed through the Sludge Classifying Press (SCP). The SCP technology removes inorganics, difficult to digest organics, and trash from the sludge, which would unnecessarily take up digester capacity. Additionally, encased and large organics, which would otherwise be sent to the landfill, are forced through a small diameter opening to promote digestibility of the materials. Sludge samples are tested for COD, TS, and VS before and after the SCP to help quantify the sludge processing, solids disposal, and energy generation benefits of the technology. II. Enhancing BOD Removal for Aeration Energy Reduction Raw sewage is pumped to the pilot from the influent feed channel of the IAWWTF at 80 gallons per minute (GPM). A chemical injection point is located just prior to where the wastewater enters the pilot’s influent feed system (shown in Figure 2). Numerous dosing and operating variations were tested to identify the optimal dosing and operating methodology for BOD removal (COD was used as a surrogate for BOD due to shorter analysis period using an on-site COD reactor). Jar testing was also performed to help determine the optimal chemical selection and dosing (see Appendix A). Through jar testing and beta runs, it was determined that maximum removal rates were achieved by dosing the influent with a Ferric Chloride coagulant at 80 milligrams per liter (mg/l), in addition to 0.25 mg/l of an anionic polymer. The methodology and results from this process are summarized in Appendix A with more detail available upon request. There are approximately 15 to 16 seconds hydraulic retention time between the chemical injection point and the pilot unit. No formal mixing occurs in the system, but the liquid does flow through three (3) elbows before reaching the pilot unit. Attempts are currently underway to improve mixing conditions. It is hypothesized that for a full-scale system, the placement of a formal mixing mechanism and longer hydraulic retention times should result in lower required dosing rates or higher organic and solids removal rates. Figure 2: Chemical Feed System Chemical Injection Point Influent Piping The dosed wastewater enters the pilot unit through the influent feed system (IFS) located at either end of the tank. The grit and heavier solids settle in the IFS. After filling the IFS, the de-gritted wastewater spills over the weirs at either end of the pilot unit and into the main chamber of the unit as shown in Figure 3. Page |4 Figure 3: Influent Feed System and Weir Wastewater first enters the system through the Influent Feed Systems located at both ends of the tank Grit and dense solids settle out in the Influent Feed System Water flows down the face of the weir and into the main chamber of the tank After the main chamber has filled, there is a 35 minute settling period during which the organics settle into the central hopper of the pilot unit. While the tank is full, floatables are removed by scum troughs located at either end of the tank. Following the settling period, the sludge that has accumulated both in the hopper and the IFS with an approximate volume of 60-gallons or approximately 250-300 gallons per day (GPD) is removed from the pilot unit via actuated valves and piped to a holding tank for subsequent processing in the SCP. Figure 4: Decanter Screen Box The screen box is lowered into the low BOD, low solids supernatant after the settling period. Wastewater flows through the screen and into the box then down a central effluent hose. 50 micron stainless steel screen on all 4 sides of the screen box. Air scour bubbles deflect any floating material from coming in contact with screen. The sludge wasting process is being optimized based on the COD concentration of the hopper sludge compared to the volume of sludge removed from the pilot unit. The goal is to provide a stable COD load / concentration and residual coagulant / polymer content in the EPT. Once the sludge has been removed, a 50 micron screen box (stainless steel), as shown in Figure 4, is lowered into the low BOD, low solids water. The water flows in to the box through the screen, then down a central effluent hose connect to the base of the screen box. In a full-scale application, the effluent would then continue on to the activated sludge process. Since the bulk of organics have been removed, as shown in Table 1, it would require significantly less energy to treat than wastewater coming from a conventional primary clarifier. A number of the Page |5 pilot unit’s parameters can be adjusted via its Supervisory Control and Data Acquisition (SCADA) interface including but not limited to settle time, chemical dosing, pump rate, screened decanter position, screen loading rate, sludge and grit withdrawal time and frequency, and mode of operation (Batch, Continuous, Storm). Composite samplers are directed by the pilot’s SCADA system to collect influent and effluent samples. Because the pilot operates in a batch configuration, the influent samples are only collected when the tank is filling; and the effluent samples are only collected when the tank is discharging. Results Provided in Table 1, are calculated values showing the maximum removal rates achieved in the pilot after completing the chemical dosage optimization work, other dosing rates and results are provided in Appendix A for later economic analysis as related to gas generation and energy reduction. For the detailed results which generated the averages below please refer to Appendix B. Table 1: Pilot Unit Results 80 mg/L Ferric : 0.25 mg/L Polymer (15 Composite Samples; collected 7/29/14 – 9/12/14) BOD Rem SBOD Rem Min 58% 14% Max 79% Avg 67% TSS Rem VSS Rem COD Rem Phos Removal TKN Removal 77% 75% 39% 66% 13% 48% 91% 91% 82% 83% 50% 28% 84% 84% 62% 76% 26% Refer to Attachment 1 for Certified Lab reports In Process Adjustments: WWTP’s are not predictable, at times The IAWWTF has a new trucked waste receiving facility that accepts organic industrial waste, food waste, septage, and other organic waste material. On occasion, smaller septic trucks are directed to dump directly into the influent feed channel of the influent building. At times when the pilot unit is filling simultaneously to the septic hauler emptying into the influent channel which caused the pilot unit will draw this higher concentration material into the unit’s feed tank. Fortunately, the IAWWTF keeps a time log that indicates septic hauler deposits, which can be referenced if a sample result returns an abnormally high BOD concentration. The removal rates, as supported by the data, during these anomalies did not degrade and in fact seemed to improve as BOD concentrations ran higher. The IAWWTF is a functioning WWTP with many liquid streams returning to the Influent Building upstream of the pilot’s influent pump. These liquids may enter the pilot unit during a fill cycle thus causing some anomalies in sample data. The influent pump to the pilot can pass a 2” solid and occasionally would plug with solids. On several occasions this occurred when the pilot was not staffed resulting in the need to scrap those composite samples. The sludge withdrawal actuated valve requires 10-seconds to open and 10-seconds to close with a 3-second wait period programmed into the SCADA. This resulted in rat holing (pulled in water versus solids) causing low solids percentage and 60+ gallons of liquid exiting the EPT sludge hopper during each of the 18-daily cycles. This volume exceeded the 775Gallon capacity of the sludge holding tank. In order to provide a mass balance and to be in alignment with the project 300-gallons of sludge to be removed each day, sludge withdrawal was changed to every 4-cycles. This did not improve the % solids of the sludge as the flow rate (GPM) was not lowered. Page |6 III. Enhancing Primary Sludge Capture for Increased Biogas Generation Mini Digesters Four (4) mini digesters are installed in the digester room of the IAWWTF. Samples are collected on Monday, Wednesday and Friday from the feed tanks and digester overflows and analyzed by a third party laboratory for total solids, volatile solids, COD, ammonia and orthophosphate. Samples are collected twice daily from the digester drain and tested for pH on-site in the IAWWTF laboratory by a ClearCove operator. Biogas samples are taken once daily from the digester gas sample lines and tested on-site for methane content using a handle-held Fyrite CO2 analyzer. Biogas flow is also measured through the use of a flow meter outside of the digester room. The accumulated data will be used in the energy production calculations for the potential full-scale build-out of the IAWWTF. All biogas and mini-digester data was generated by O’Brien & Gere Engineers. Mini Digesters – Phase 1 In March 2014, four (4) 500 gallon mini digesters (Figure 6) were installed. Each mini digester has a dedicated 100 gallon feed tank (Figure 6) to provide each digester a specified sludge. Hot water is used to heat the mini-digesters. Temperature and pH are manually monitored and adjusted as needed. Each digester is fed at a different rate, as shown in the schedule below. The first digester serves as a control, and mirrors the current feeding conditions at the IAWWTF. Digester 1 (MD-1): IAWWTF Thickened Sludge (combination of IAWWTF Primary and Secondary Sludge collected from full scale sludge thickening tank) loaded at the same rate as that of the IAWWTF’s full-scale primary digester; 0.05 pounds of VSS per cubic foot per day (lb /cf /day). Digester 2 (MD-2): IAWWTF Primary Sludge (from IAWWTF Primary Clarifier) loaded at a rate similar to IAWWTF primary digester. Digester 3 (MD-3): ClearCove Enhanced Primary Sludge (collected from small thickening tank that follows pilot) loaded at a rate similar to IAWWTF primary digester. Digester 4 (MD-4): ClearCove Enhanced Primary Sludge – Double Feed Rate (collected from small thickening tank that follows pilot) loaded at two times the rate of the IAWWTF primary digester. (The double feed rate is based on laboratory testing that suggested that sludge from the ClearCove EPT pilot unit is more readily biodegradable than sludge produced conventionally. During Phase 1, an attempt was made to achieve the double feed rate; however, due to challenges encountered during the phase (see below) this did not occur.) Figure 5: Mini Digester Process Diagram Influent ClearCove EPT IAWWTF Sludge Thickening Tank IAWWTF Primary Clarifier ClearCove EPT Sludge ClearCove SCP 1 ClearCove EPT Sludge 300 Gallon Thickening Tank Mini-Digesters 2 3 4 Page |7 Figure 6: Phase 1 500 Gallon Mini Digesters Figure 7: Phase 1 100 Gallon Feed Tanks Phase 1 Process Adjustments A number of challenges were encountered with the 500 gallon mini-digesters: fouling of feed pumps, inadequate mixing, freezing of gas lines, plugging of overflows (which resulted in a digester overflowing), sludge getting into gas lines, leaks in the gas lines, and an over temperature event. Due to the small volumes of feed material that were to be handled by these units, small diameter hoses and small volume pumps were originally installed, which led to plugging of lines and inadequate mixing in the mini-digesters. Upon opening the cover of one mini-digester to investigate, “dead zones” were observed. It was suspected that the poor mixing was a result of an inadequate recycle flow and the flat bottom shape of the digester tanks, which together resulted in separation of the solids separation within the digesters. As such, samples collected from the overflows and drains of the digesters were found to have higher percent solids than expected. Sludge thickening evolved over the course of the pilot project. Initially, thickening was done by manually filling five (5)gallon pails of effluent from the pilot, allowing it to settle for 45-minutes, then manually decanting it and allowing it to consolidate. At this point in the project, the Sludge Classifying Press (SCP) was not yet installed. The thickening process was altered when the SCP was introduced into the pilot such that captured sludge was pumped to the SCP and into a 300gallon coned-bottom tank. The settling was limited to 45-minutes because of sampling time required for Pre & Post SCP sludge, startup and shutdown of the SCP, delivery of the sludge to the mini-digesters and to BMP, testing of COD, TS, and VS% before the IAWWTF laboratory closed. The short settling period and the limited depth (<56”) resulted in a solids content of the sludge from 1 to 2%. In pilot scale we found thickening capabilities to be less than that of a full scale system where primary sludge is typically thickened to 3-5%. The short settling time also resulted in a non-defined solids liquid separation layer. Samples of the sludge were taken using a sludge judge and a scoop for the decant. Both of these were tested leaving the balance of the contents of the tank being somewhere between these test results. Flow meters were installed on the sludge and grit lines into the 900-Gallon storage tank. The low volume and flow rate of the grit pipe caused the flow readings to be unrecorded. Inconsistencies of the sludge flow meter created concerns so that visual readings from graduations on the side of the tank were used instead of the flow meter readings. Phase 1 Design Improvements for Phase 2 The digester tanks needed to be replaced; flat bottom tanks could not be mixed effectively. Critical Control Parameters i. Proper Mixing Page |8 1. Need to have a homogenous mixing pattern 2. Tank volume turnover rate for full-scale 30-60 minutes ii. Temperature Control 1. Range needs to be 950F to 980F 2. Better to be cooler than too hot iii. pH control 1. pH issues can be managed by reducing loading rate or adding chemicals\ iv. Feed Rate Phase 1 Results Despite the Phase 1 challenges, valid data was collected during the phase (Table 2). During this period, data shows that mini-digester #3 (MD-3; EPT pilot sludge) produced 1.8 times more biogas per pound of VS applied than mini-digester #2 (MD-2; IAWWTF primary sludge). Table 2: Phase 1 Biogas Results: Per O’Brien & Gere Methane Number of VS Loading Biogas Flow Content Dates Data Points (lb/kcf/d) (sL/d) (%) IAWWTF 2005-2009 unknown 50 106,000 scfd 66.0 MD-2 (IPS) 4/11-6/17 68 50 423 65 ** MD-3 (SCP) 4/11-6/17 68 44 676 65 ** ** methane content estimated due to CO2 meter out of calibration Phase 1 Methane Yield (scf CH4/ lb VS fed) 5.2 4.0 7.4 Mini Digesters – Phase 2: Rebuild In June 2014, due to the mixing and clogging challenges encountered, the four (4) 500 gallon min-digesters were removed and four (4) 350 gallon mini-digesters (Figure 8) were installed. The new digesters were designed to operate with 100 gallons of working volume. The new mini-digesters have a cone-shaped bottom and a greater number of internal nozzles than the original digesters, to ensure complete mixing is achieved within the tank. In addition to the new tanks, larger double diaphragm pumps, and larger diameter hose lines were installed to prevent clogging. Again, each digester has a dedicated feed tank (Figure 9), feed pump, and heating/mixing pump with heat exchanger; and temperature and pH were manually monitored and adjusted as needed. The new mini-digesters were placed in service in late June. The new MD-1 (IAWWTF Thickened Sludge) was seeded with solids from the IAWWTF full-scale primary digester. The other three new mini-digesters were seeded with acclimated sludge that had been saved from the Phase 1 mini-digesters and stored. The new MD-2 was seeded with material from the old MD-2 and the new MD-3 and MD-4 units were seeded with material from the old MD-3. The digesters acclimated to increasing loads throughout the month of July. Biogas flow readings were used to monitor the degree of acclimation of each mini-digester. Page |9 Figure 8: Phase 2 Mini Digester Figure 9: Phase 2 Sludge Feed Tank Digesters MD-1, MD-2 and MD-3 are fed as in Phase 1 at 0.05 lbs VS/cf/day. Digester MD-4 is fed at double that rate, 0.1 lbs VS/cf/day. The feed sludge is constantly pumped in a recirculation loop running from the feed tank to the mini digester and back to the feed tank. A solenoid valve connected to a timer periodically redirects the feed from the recirculation loop into the digester. The feed timer is set based on the results of daily total solids tests, so that the desired pounds of solids are delivered to each mini-digester. Feed volumes are measured and samples are collected to determine the actual loading rates on a daily basis. Phase 2 Process Adjustments An issue encountered during Phase 2 has been the leaking and rupturing of hoses in the heating and mixing lines of the digester due to vibration/pulsing causing rubbing against various surfaces. This resulted in three of the four digesters losing around half to all of their contents in one instance per digester. Keeping the pH in digesters MD-2, MD-3 and MD-4 at in the optimal range of pH 7 – 7.2 has required the addition of sodium bicarbonate so steady operating conditions can be achieved in a quicker timeframe. The pH of the digesters is monitored twice daily to ensure quick reaction to any drop in pH value. Regardless of adjustments we were able to recover from all issues and operate the digesters at steady state for data collection. Phase 2 Results We were able to recover from Phase 1 and collect the necessary data points on the Phase 2 mini- digesters. Total Solids (TS) and Volatile Solids (VS) testing are performed multiple times per week on feed sludge and the mini digester overflow. This data are used to calculate the feed rate to the digesters and evaluate if volatile solids destruction is occurring in the digesters. Provided in Table 3 are the calculated values for the average TS and VS of the feed sludge. Table 3: Average % Total Solids & Volatile Solids Dates IAWWTF Thickened Sludge IAWWTF Primary Sludge ClearCove Enhanced Primary Sludge ClearCove Enhanced Primary Sludge 2X Note: 7/15-9/12 7/21-8/15 8/18-9/30 9/3-9/30 # of Samples 27 13 20 10 Feed Sludge % TS % VS 2.0 2.0 1.9 1.8 63.1 71.1 69.4 70.3 Digester Overflow % TS % VS 58.0 1.4 66.8 1.3 59.0 1.1 59.2 1.3 The IAWWTF Thickened Sludge was tested for scale and loading comparison with IAWWTF Primary Digester and Primary Sludge was tested for direct comparison with CCS Enhanced Primary Sludge. IAWWTF Thickened Sludge is P a g e | 10 taken directly from the sample port at their full-scale thickening tanks. The IAWWTF Primary Sludge and ClearCove Enhanced Primary sludge were pre-thickened prior to being fed to the digesters, the data above represents the percent solid post-thickening. Based on bench top testing the sludge is expected to thicken to 5-7% using a gravity deck. Table 4 displays the Phase 2 mini-digester performance data in comparison with data collected from the IAWWTF on their full scale primary digester performance (labeled IAWWTF on table). Table 4: Phase 2 Mini-Digester Results: Per O’Brien & Gere Phase 2 IAWWTF MD-1 (ITS) MD-2A (IPS) MD-3 (SCP) MD-2B (SCP-2x) Dates 2013-2014 7/14-9/14 7/21-8/15 8/18-10/1 9/3-10/1 Detention VS VS Biogas Methane Methane Yield Methane Yield # Data Time # Reactor Loading Destroyed Flow Content (scf CH4/ (scf CH4/ Points (d) Volumes (lb/kcf/d) (%) (sL/d) (%) lb VS fed) lb VS removed) 548 23 N/A 72 52% 156,000 scfd 68.0 7.8 15.1 63 13.5 4.7 59 38% 169 70.6 5.4 14.3 26 12.8 2.0 70 38% 178 60.1 4.1 10.7 45 17.5 2.6 46 50% 204 71.5 8.3 16.7 30 9.7 3.1 81 41% 360 67.6 7.9 19.4 Note: ITS – Ithaca Thickened Sludge, IPS – Ithaca Primary Sludge, SCP – ClearCove Post-SCP Sludge Biochemical Methane Potential Testing Biochemical methane potential (BMP) testing is performed simultaneously with operation of the mini digesters, using sludge from the same collection vessels. Bioprocess Control’s Bioprocess Control’s Automatic Methane Potential Test System (Figure 10) is used for BMP testing. BMP testing is performed as a recommended alternative by the NYSERDA PAC to mini digesters in the event of performance failures. The BMP testing will be also used as a correlation tool with the mini-digesters. Gas generation is recorded and viewable in real time on a dedicated computer connected to the BMP equipment using a software platform provided by Bioprocess Control. Figure 10: Bioprocess Controls AMPTS II Equipment Gas Volume Measuring Device CO2 Fixing Unit Reactors Sample Incubator The BMP system allows for fifteen (15) 640 ml reactors to be run at the same time. For each batch, the following five (5) sludge types are run in triplicate to ensure accuracy and repeatability of the results: P a g e | 11 IAWWTF Thickened Sludge IAWWTF Primary Sludge ClearCove Post-SCP Sludge ClearCove Post-SCP Sludge 2X (Double VS Loading Rate) Inoculum Only (Serves as the experimental control) BMP Results Summary To date, six BMP tests have been conducted. The calculated average of the test results are shown in Table 5. With each subsequent test the results are more consistent and seem to track to the mini digesters where reliable data are present. On average, it appears that the ClearCove EPT sludge generated approximately 1.8 times more methane than the IAWWTF Thickened Sludge, and 1.3 times more methane than the IAWWTF Primary Sludge. In terms of total methane production, the ClearCove EPT double loading rate generated just over double that of the normal loading rate ClearCove EPT sludge. The six BMP tests performed during this reporting period were as follows: - 6/24 – 7/1 (Exhibit 1) 7/1 – 7/8 (Exhibit 2) 7/8 – 7/24 (Exhibit 3) 7/25 – 8/11 (Exhibit 4) 8/15 – 9/2 (Exhibit 5) 9/3 – 9/15 (Exhibit 6) For further details on each of the individual BMP tests see Appendix C and refer to the Exhibit numbers above. Table 5: Average BMP Results Substrate Average VS Load (g) Average Total Methane (Nml) Average Applied Yield (scf methane/ lb VS applied) IAWWTF Thickened IAWWTF Primary ClearCove EPT ClearCove EPT 2X 1.58 1.70 1.71 3.71 298 481 633 1,351 3.0 4.4 5.7 5.7 Compared to Ithaca Thickened Sludge 146% 188% 189% The IAWWTF’s Environmental Lab ran a BMP test of their own comparing the EPT sludge and the IAWWTF Thickened sludge as an additional control experiment, the results of which are shown in Table 6. Expanded data and calculations can be found in Attachment 3. Table 6: IAWWTF BMP Results Substrate Average VS Load (g) Corrected Average Total Biogas (mL)* Applied Yield (mL biogas/ g VS applied) Compared to Ithaca Thickened Sludge IAWWTF Thickened ClearCove EPT 0.155 0.255 22 97 140 381 270% *Corrected Average Total Biogas values have been adjusted to remove inoculum gas generation from the total gas produced. P a g e | 12 IV. Improved Sludge Processing as a Result of Higher Percent Solids and Improved Ratio of Primary to Secondary Sludge In order to quantify any sludge processing effects, a mass balance is being established around the EPT pilot in Ithaca. As depicted in the process schematic in Figure 12, sludge from the main hopper and IFS of the pilot is sent to a 900 gallon holding tank prior to being processed through the Sludge Classifying Press. A flow meter has been placed on these lines between the pilot and the 900 gallon tank in order to quantify the sludge exiting the EPT unit. The sludge is mixed within the 900 gallon tank to keep it homogeneous, and then pumped from the tank to the SCP. The SCP also has a flow meter on its influent line. From the SCP, a coagulant is added to the “cleaned” sludge, which is then sent to a 300 gallon thickening tank. The total volume sent to the 300 gallon tank is measured, as are the distinct volumes of sludge and decant after a one (1) hour settling period. Split samples are collected Monday, Wednesday Friday and analyzed for COD, TS, and VS on-site by a ClearCove operator and sent to a third part lab for analysis. Samples are collected from the following points: 900 gallon Pre-SCP holding tank sludge 300 gallon Post-SCP holding tank sludge 300 gallon Post-SCP holding tank decant water The on-site testing allows for a faster turnaround time and allows for predictive information to be gathers and acted upon which waiting for the third party lab result. These organic sources, in addition to the organic sources collected during the influent and effluent composite sampling events (from the pilot), should account for all of the organics sources coming in to and out of the system. Figure 12: ClearCove Pilot Mass Balance Data Point Process Diagram P a g e | 13 Appendix A Chemical Selection and Dosage Optimization Chemical selection and dosage optimization were performed on the ClearCove EPT pilot to determine which chemicals and dosage rates (mg/l) would achieve the best organic removal. Three coagulants were tested: Ferric Chloride, PCH 180, and Slack Plus; all in combination with two (2) anionic polymer dosing rates (0.5 mg/l and 1.0 mg/l). Based on jar testing performed on-site, Ferric Chloride was determined to provide the best results based on flocculation observation and measurements of COD and turbidity as shown in Table 1. Ferric Chloride is also what the IAWWTF uses in its full scale operation. Table 1 Chemical Selection Jar Test Results PCH180 Turbidity (NFAU) 50 COD mg/L 238 Slack Plus 64 244 FeCl3 50 230 Blank 107 297 Once the Ferric Chloride was chosen, the optimal dosage of coagulant and polymer was determined by pilot scale operation. The coagulant and polymer were tested at six (6) different dosage combinations, after which the COD and turbidity of the influent and effluent was tested to determine which dosage combination provided the best results. Two different operational modes were tested for each of the six (6) different dosage combinations. These two modes were referred to as Set Point #1 and Set Point #2. The main difference between the two set points was their sludge removal method. Set Point #1 Set Point #1 performs a sludge scour every batch, meaning that after each completed batch of the pilot it would empty out the entire tank. After the tank was completely scoured of sludge a new cycle would begin with an empty tank. The reasoning for this mode of operation is that it would prevent the organic and solids concentration from getting too high and thus effecting the organic removal rate of the screened decanter. The EPT is a solids and organic concentrator as roughly 25 to 35% of the influent organics and solids remain in the EPT tank until removed via the sludge hopper or IFS. As shown in Table 2 below, 60 mg/l Ferric Chloride with 1.0 mg/l anionic polymer delivered the bester results for this set point. Table 2: Set Point #1 Results Coag (mg/l) 40 50 60 40 50 60 Polymer (mg/l) 0.5 0.5 0.5 1.0 1.0 1.0 Average % Removal 51.80 56.17 61.05 40.89 56.76 66.07 Max % Removal 55.40 64.65 66.67 40.89 64.52 73.92 Min % Removal 48.53 44.10 53.81 40.89 48.48 61.75 Set Point #2 Set Point #2 was different in that it would never completely empty the tank, but instead there would be a timed draw off of sludge after the settle cycle of each batch resulting in approximately 25 gallons of sludge being P a g e | 14 drained. The reasoning for this mode of operations was to maintain the residual chemical in the tank to improve flocculation and contact time each cycle. It was determined that a 50 mg/l dosage of Ferric Chloride with a 1.0 mg/l dosage of anionic polymer provided the best COD removal as shown in Table 3. Table 3: Set Point #2 Results Coag (mg/l) 40 50 60 40 50 60 Conclusion Polymer (mg/l) 0.5 0.5 0.5 1.0 1.0 1.0 Average % Removal 64.45 58.43 69.07 60.46 72.18 50.05 Max % Removal 66.53 60.58 71.34 63.36 77.32 62.94 Min % Removal 61.37 55.52 66.80 57.25 66.22 40.98 Based on the results of the jar testing, set point testing, and dosage optimization tests the 50 mg/l Ferric Chloride with 1.0 mg/l polymer dose was chosen using the Set Point #2 mode of operation. These will be the operational parameters for the rest of the project going forward to ensure the highest level of organic removal is achieved from the pilot. P a g e | 15 Appendix B Optimized Case Study Data: Dosing of 80 MGL Ferric / .25 MGL Poly BOD SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf BOD 276 161 159 126 105 150 148 191 174 162 179 184 196 136 211 105 276 176 Prim Eff BOD Prim BOD Rem 237.00 14% 77.35 85.00 39% 19% 172.00 171.00 161.00 213.00 223.00 213.00 230.00 195.00 77 237 180 10% 2% 1% -19% -21% -9% -69% 8% -69% 39% -2% CCS Eff BOD 67 63 48 49 32 31 62.0 73 70 43 51 74 62 38 66 31 74 55 CCS BOD Rem 76% 61% 70% 61% 70% 79% 58% 62% 60% 73% 72% 60% 68% 72% 69% 58% 79% 67% P a g e | 16 SBOD SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf SBOD 24 45 37 29 23 19 17 34 40 51 26 47 27 62 42 17 62 34 Prim Eff SBOD 31 26 48 35 47 32 44 31 63 47 26 63 40 CCS Eff SBOD CCS SBOD Rem 14 42% 33 27% 36 3% 25 14% 12 48% 15 21% 15 12% 31 9% 30 25% 38 25% 16 38% 36 23% 13 52% 53 15% 31 26% 12 14% 53 48% 27 28% P a g e | 17 TSS SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf TSS 360 176 236 234 147 280 214 293 213 260 240 187 260 196 256 147 360 241 Prim Eff TSS 136 Prim TSS Rem 62% 110 120 53% 18% 124 150 148 453 327 391 590 230 110 590 253 58% 30% 43% -89% -75% -50% -201% 10% -201% 62% -5% CCS Eff TSS 45 40 22 30 33 26 46 43 40 38 42 25 41 33 39 22 46 36 CCS TSS Rem 88% 77% 91% 87% 78% 91% 79% 85% 81% 85% 83% 87% 84% 83% 85% 77% 91% 84% P a g e | 18 VSS SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf VSS 393 148 218 164 130 240 162 193 147 227 200 136 207 153 200 130 393 181 Prim Eff VSS 176 Prim VSS Rem 55% 96 26% 84 105 124 380 273 264 490 150 84 490 214 56% 29% 45% -90% -101% -28% -220% 25% -220% 56% -16% CCS Eff VSS 43 35 20 18 33 22 36 32 25 29 27 18 30 21 27 18 43 28 CCS VSS Rem 89% 76% 91% 89% 75% 91% 78% 83% 83% 87% 87% 87% 86% 86% 87% 75% 91% 84% P a g e | 19 COD SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf COD 760 440 180 240 220 260 341 390 341 391 428 333 350 391 350 180 760 359 Prim Eff COD Prim COD Rem 330 57% 220 0% 341 333 391 333 391 350 376 300 220 391 337 13% 2% 0% 22% -17% 0% 4% 14% -17% 57% 7% CCS Eff COD 138 270 63 110 100 85 112 154 112 133 120 134 184 134 154 63 270 134 CCS COD Rem 82% 39% 65% 54% 55% 67% 67% 61% 67% 66% 72% 60% 47% 66% 56% 39% 82% 62% P a g e | 20 Phosphorous SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf Phos 6.49 3.75 3.09 2.27 2.44 3.60 3.94 3.22 2.97 3.48 3.86 3.94 4.00 3.37 3.75 2.27 6.49 3.41 Prim Eff Phos Prim Phos Rem 2.86 56% 1.70 30% 2.73 2.46 3.18 3.15 3.72 3.94 3.97 3.34 1.70 3.97 3.11 15% 17% 9% 18% 6% 2% -18% 11% -18% 56% 10% CCS Eff Phos 1.22 0.78 0.69 0.75 0.49 0.62 1.33 0.95 0.89 0.98 0.95 1.15 1.19 2.18 0.96 0.49 2.18 1.01 Phos Removal 81% 79% 78% 67% 80% 83% 66% 83% 70% 72% 75% 71% 70% 35% 74% 66% 83% 76% P a g e | 21 TKN SAMPLE # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 80 MGL Ferric / .25 MGL Poly Date* 7/29/2014 7/30/2014 8/1/2014 8/5/2014 8/6/2014 8/7/2014 9/2/2014 9/3/2014 9/4/2014 9/5/2014 9/8/2014 9/9/2014 9/10/2014 9/11/2014 9/12/2014 Min Max Avg Sampler AW AW AW AW AW AW CW SM AW AW SM CW CW CW CW Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf TKN 35.90 23.60 22.90 17.50 15.80 27.20 35.60 28.20 25.20 27.60 29.10 32.00 34.40 39.00 34.10 15.8 39.0 27.4 Prim Eff TKN 18.60 Prim TKN Rem 48% 20.30 -28% 35.30 32.50 35.90 35.30 38.80 43.90 41.30 39.90 18.6 43.9 34.2 -25% -29% -30% -21% -21% -28% -6% -17% -30% 48% -20% CCS Eff TKN 17.90 18.40 17.80 13.10 11.00 14.40 23.70 21.50 21.80 22.00 21.80 25.20 27.60 34.10 28.00 11.0 34.1 21.2 TKN Removal 50% 22% 22% 25% 30% 47% 33% 24% 13% 20% 25% 21% 20% 13% 18% 13% 50% 26% P a g e | 22 Alternative Dosing Experiment (For reference only; not used for any other experiments): Dosing of 50 MGL Ferric / 1 MGL Poly SAMPLE # 1 2 3 4 5 6 7 8 9 SAMPLE # 1 2 3 4 5 6 7 8 9 50 MGL Ferric /1 MGL Poly Date* 8/12/2014 8/15/2014 8/18/2014 8/19/2014 8/20/2014 8/21/2014 8/26/2014 8/27/2014 8/29/2014 Min Max Avg 50 MGL Ferric /1 MGL Poly Date* 8/12/2014 8/15/2014 8/18/2014 8/19/2014 8/20/2014 8/21/2014 8/26/2014 8/27/2014 8/29/2014 Min Max Avg Sampler AW AW SM AW SM AW BH SM SM Sampler AW AW SM AW SM AW BH SM SM Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Type Comp Comp Comp Comp Comp Comp Comp Comp Comp Inf BOD 141 117 106 201 210 138 166 165 189 106 210 159 Inf TSS 244 140 152 192 264 204 200 176 198 140 264 197 Prim Eff BOD Prim BOD Rem 81 43% 81 31% 98 8% 100 50% 129 39% 107 22% 113 32% 123 25% 150 21% 81 8% 150 50% 109 30% Prim Eff TSS 74 80 76 236 116 178 142 84 100 74 236 121 Prim TSS Rem 70% 43% 50% -23% 56% 13% 29% 52% 49% -23% 70% 38% CCS Eff BOD 52 51 33 60 96 47 76 78 94 33 96 65 CCS Eff TSS 26 37 36 38 57 34 53 56 53 26 57 43 CCS BOD Rem 63% 56% 69% 70% 54% 66% 54% 53% 50% 50% 70% 60% CCS TSS Rem 89% 74% 76% 80% 78% 83% 74% 68% 73% 68% 89% 77% Inf VSS 140 120 116 172 228 168 172 170 170 116 228 162 Inf SBOD 35 28 12 27 45 19 60 51 49 12 60 36 Prim Eff SBOD 15 25 12 15 34 13 15 39 56 12 56 25 Prim Eff VSS 66 71 56 212 11 148 132 80 73 11 212 94 Prim VSS Rem 53% 41% 52% -23% 95% 12% 23% 53% 57% -23% 95% 40% CCS Eff SBOD CCS SBOD Rem 16 54% 18 36% 8 32% 21 22% 38 16% 15 21% 55 8% 35 31% 48 2% 8 2% 55 54% 28 25% CCS Eff VSS 26 33 27 29 47 25 43 48 42 25 48 36 CCS VSS Rem 81% 73% 77% 83% 79% 85% 75% 72% 75% 72% 85% 78% P a g e | 23 SAMPLE # 1 2 3 4 5 6 7 8 9 50 MGL Ferric /1 MGL Poly Date* 8/12/2014 8/15/2014 8/18/2014 8/19/2014 8/20/2014 8/21/2014 8/26/2014 8/27/2014 8/29/2014 Min Max Avg SAMPLE # 1 2 3 4 5 6 7 8 9 Sampler AW AW SM AW SM AW BH SM SM Type Comp Comp Comp Comp Comp Comp Comp Comp Comp 50 MGL Ferric /1 MGL Poly Date* 8/12/2014 8/15/2014 8/18/2014 8/19/2014 8/20/2014 8/21/2014 8/26/2014 8/27/2014 8/29/2014 Min Max Avg Inf COD 280 260 156 272 352 216 310 340 439 156 439 292 Sampler AW AW SM AW SM AW BH SM SM Prim Eff COD Prim COD Rem 180 36% 160 38% 116 26% 156 43% 196 44% 180 17% 240 23% 220 35% 341 22% 116 17% 341 44% 199 32% Type Comp Comp Comp Comp Comp Comp Comp Comp Comp CCS Eff COD 110 100 78 118 156 100 190 140 150 78 190 127 Inf TKN 22.20 20.30 20.80 28.80 29.30 20.10 26.40 30.80 38.00 20.10 38.00 26.30 CCS COD Rem 61% 62% 50% 57% 56% 54% 39% 59% 66% 39% 66% 56% Prim Eff TKN 25.00 22.70 23.10 31.00 29.30 21.70 31.40 36.40 39.90 21.70 39.90 28.94 Inf Phos 2.91 2.65 2.85 3.75 4.96 2.99 3.48 3.78 3.79 2.65 4.96 3.46 Prim Eff Phos Prim Phos Rem 2.23 23% 1.94 27% 1.67 41% 2.51 33% 2.82 43% 0.15 95% 2.74 21% 2.60 31% 2.74 28% 0.15 21% 2.82 95% 2.16 38% Prim TKN Rem -13% -12% -11% -8% 0% -8% -19% -18% -5% -19% 0% -10% CCS Eff TKN 14.20 15.60 15.60 18.60 19.60 14.90 23.50 25.30 31.40 14.20 31.40 19.86 CCS Eff Phos 0.98 1.01 0.79 1.04 1.28 0.78 1.23 1.38 1.66 0.78 1.66 1.13 Phos Removal 66% 62% 72% 72% 74% 74% 65% 63% 56% 56% 74% 67% TKN Removal 36% 23% 25% 35% 33% 26% 11% 18% 17% 11% 36% 25% P a g e | 24 Appendix C BMP Reports Exhibit 1: 6/24/2014 – 7/1/2014 Summary This test was started on 6/24 and concluded on 7/1. All reactors were seeded with sludge from the IAWWTF Primary Digester however no separate inoculum bottle was run for this BMP test. The bottles were loaded at an inoculum/substrate ratio of 1.5. As shown in the table below reactors fed the same sludges as the mini-digesters with extra bottles of Pre-SCP sludge and Post-SCP Thickened sludge being tested as well. The Pre-SCP sludge was tested to determine if greater biogas production is achieved after the sludge has been processed by ClearCove’s SCP technology. The Post-SCP Thickened sludge was tested to determine if greater biogas production is achieved by thickening the Post-SCP sludge to approximately 7.1% solids from 1.0% solids. In this test, the Pre-SCP sludge produced approximately the same methane yield per pound of VS applied as the Post-SCP sludge. The Post-SCP Thickened sludge produced approximately 30% more methane than the normal Post-SCP sludge. Substrate IAWWTF Thickened Sludge IAWWTF Primary Sludge Pre-SCP Sludge Post-SCP Sludge Post-SCP Thickened Inoculum Source IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester Inoculum/Substrate Ration: 1.5 Bottle Breakdown: IAWWTF Thickened Sludge IAWWTF Primary Sludge Pre-SCP Sludge Post-SCP Sludge Post-SCP Thickened Sludge Total: 3 Bottles 3 Bottles 3 Bottles 3 Bottles 3 Bottles 15 Bottles Substrate Volatile Solids Concentrations Substrate VS%* IAWWTF Thickened Sludge 1.9 IAWWTF Primary Sludge 2.2 Pre-SCP Sludge 2.1 Post-SCP Sludge 0.8 Post-SCP Thickened 5.5 *% VS is of the wet weight Inoculum IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester VS%* .90 .90 .90 .90 .90 P a g e | 25 Results Sludge IAWWTF Thickened Sludge IAWWTF Primary Sludge Pre-SCP Sludge Post-SCP Sludge Post-SCP Thickened VS Load (g) 1.5 1.55 1.54 1.17 1.73 Total Methane (nml) 297 376 424 320 613 Applied Yield (scf methane/ lb VS applied) 3.2 3.9 4.4 4.4 5.7 *As inoculum negative bottle was not run, inoculum methane gas generation was estimated to be 145 Nml Methane Production 900 IAWWTF Thickened 1 800 IAWWTF Thickened 2 IAWWTF Thickened 3 700 IAWWTF Primary 1 Volume (Nml) 600 IAWWTF Primary 2 IAWWTF Primary 3 500 CCS Pre-SCP 1 400 CSS Pre-SCP 2 CCS Pre-SCP 3 300 CCS Post-SCP 1 CCS Post-SCP 2 200 CCS Post-SCP 3 100 CCS Post-SCP Thickened 1 CCS Post-SCP Thickened 2 0 0 25 50 75 Hours 100 125 150 CCS Post-SCP Thickened 3 P a g e | 26 Exhibit 2: 7/1/2014 – 7/8/2014 Summary This test was started on 7/1 and concluded on 7/8. All reactors were seeded with sludge from the IAWWTF Primary Digester however no separate inoculum bottle was run for this BMP test. The bottles were loaded at an inoculum/substrate ratio of 1.5. As shown in the table below the digesters were fed the same sludges as the mini-digesters, with the exception of Pre-SCP sludge which is not fed to the mini-digesters. This test was also the first test to include reactors which were loaded Post-SCP sludge at double the volatile solids loading rate, this sludge is referred to as Post-SCP Sludge 2X. These bottles were run to collect supplementary data to the fourth mini digester which is fed Post-SCP at double the conventional loading rate. In this test, the Pre-SCP sludge provided approximately half the methane yield per pound of VS applied as the Post-SCP sludge. The Post-SCP 2X sludge produced approximately double the methane volume of the Post-SCP conventional load sludge and provided a slightly higher yield per pound VS loaded. Substrate IAWWTF Thickened Sludge IAWWTF Primary Sludge Pre-SCP Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Source IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester Inoculum/Substrate Ration: 1.5 Bottle Breakdown: IAWWTF Thickened Sludge IAWWTF Primary Sludge Pre-SCP Sludge Post-SCP Sludge Post-SCP Sludge 2X Total: 3 Bottles 3 Bottles 3 Bottles 3 Bottles 3 Bottles 15 Bottles Substrate Volatile Solids Concentrations Substrate VS%* IAWWTF Thickened Sludge 1.63 IAWWTF Primary Sludge 1.98 Pre-SCP Sludge 1.30 Post-SCP Sludge 3.36 Post-SCP Sludge 2X 3.36 *% VS is of the wet weight Inoculum IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester VS%* .86 .86 .86 .86 .86 P a g e | 27 Results Sludge IAWWTF Thickened Sludge IAWWTF Primary Sludge Pre-SCP Sludge Post-SCP Sludge Post-SCP Sludge 2X VS Load (g) 1.36 1.41 1.29 1.52 3.06 Total Methane (nml) 212 382 291 582 1,219 Applied Yield (scf methane/ lb VS applied) 2.5 4.3 3.6 6.1 6.4 *As inoculum negative bottle was not run, inoculum methane gas generation was estimated to be 145 Nml Methane Production 1600 IAWWTF Thickened 1 1400 IAWWTF Thickened 2 IAWWTF Thickened 3 1200 Volume (Nml) IAWWTF Primary 1 IAWWTF Primary 2 1000 IAWWTF Primary 3 CCS Pre-SCP 1 800 CSS Pre-SCP 2 600 CCS Pre-SCP 3 CCS Post-SCP 1 400 CCS Post-SCP 2 CCS Post-SCP 3 200 CCS Post-SCP 2X 1 CCS Post-SCP 2X 2 0 0 25 50 75 Hours 100 125 150 CCS Post-SCP 2X 3 P a g e | 28 Exhibit 3: 7/8/2014 – 7/24/2014 Summary This test was started on 7/8 and concluded on 7/24. All reactors were seeded with sludge from the IAWWTF Primary Digester, this is the first test which was run with a separate Inoculum Only “blank” bottle. The bottles were loaded at an inoculum/substrate ratio of 1.5. As shown in the table below the digesters were fed the same sludges as the mini-digesters with the exception of the additional Inoculum Only bottle. This test was the second test to include reactors which were loaded Post-SCP sludge at double the volatile solids loading rate, this sludge is referred to as PostSCP Sludge 2X. In this test, the Post-SCP 2X sludge produced over double the total methane volume of the Post-SCP conventional load sludge and provided a slightly higher yield per pound VS loaded. The inoculum only reactors produced very little methane volume and yield. Substrate IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Inoculum Source IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester Inoculum/Substrate Ration: 1.5 Bottle Breakdown: IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Total: 3 Bottles 3 Bottles 3 Bottles 3 Bottles 3 Bottles 15 Bottles Substrate Volatile Solids Concentrations Substrate VS%* IAWWTF Thickened Sludge 2.03 IAWWTF Primary Sludge 1.60 Post-SCP Sludge 2.19 Post-SCP Sludge 2X 2.19 Inoculum Only 0.92 *% VS is of the wet weight Inoculum IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester VS%* 0.92 0.92 0.92 0.92 0.92 P a g e | 29 Results Sludge IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Total Methane (nml) 352 481 611 1,340 85 VS Load (g) 1.88 1.77 1.92 3.84 3.68 Applied Yield (scf methane/ lb VS applied) 3.0 4.4 5.1 5.6 0.4 Methane Production 1600 It Thickened 1 Volume [Nml] It Thickened 2 Volume [Nml] 1400 It Thickened 3 Volume [Nml] Primary 1 Volume [Nml] 1200 Volume (Nml) Primary 2 Volume [Nml] 1000 Primary 3 Volume [Nml] Inoculum Only 1 Volume [Nml] 800 Inoculum Only 2 Volume [Nml] Inoculum Only 3 Volume [Nml] 600 Post SCP 1 Volume [Nml] Post SCP 2 Volume [Nml] 400 Post SCP 3 Volume [Nml] Post SCP 2X 1 Volume [Nml] 200 Post SCP 2X 2 Volume [Nml] 0 Post SCP 2X 3 Volume [Nml] 0 50 100 150 200 Hours 250 300 350 400 P a g e | 30 Exhibit 4: 7/25/2014 – 8/11/2014 Summary This test was started on 7/25 and concluded on 8/11. All reactors were seeded with sludge from the IAWWTF Primary Digester. The bottles were loaded at an inoculum/substrate ratio of 1.5. As shown in the table below the digesters were fed the same sludges as the mini-digesters with the exception of the additional Inoculum Only bottle. This test was the third test to include reactors which were loaded Post-SCP sludge at double the volatile solids loading rate, this sludge is referred to as PostSCP Sludge 2X. In this test, the Post-SCP 2X sludge produced approximately double the total methane volume of the Post-SCP conventional load sludge and provided a slightly higher yield per pound VS loaded. The inoculum only reactors produced very little methane volume and yield. Substrate IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Inoculum Source IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester Inoculum/Substrate Ration: 1.5 Bottle Breakdown: IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Total: 3 Bottles 3 Bottles 3 Bottles 3 Bottles 3 Bottles 15 Bottles Substrate Volatile Solids Concentrations Substrate VS%* IAWWTF Thickened Sludge 1.40 IAWWTF Primary Sludge 1.36 Post-SCP Sludge 1.57 Post-SCP Sludge 2X 1.57 Inoculum Only 0.93 *% VS is of the wet weight Inoculum IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester VS%* 0.93 0.93 0.93 0.93 0.93 P a g e | 31 Results Sludge IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Total Methane (nml) 350 477 630 1,287 205 VS Load (g) 1.72 1.70 1.78 3.56 3.72 Applied Yield (scf methane/ lb VS applied) 3.3 4.5 5.7 5.8 0.9 Methane Production 1600 It Thickened 1 Volume [Nml] 1400 It Thickened 2 Volume [Nml] It Thickened 3 Volume [Nml] Volume (Nml) 1200 Primary 1 Volume [Nml] Primary 2 Volume [Nml] 1000 Primary 3 Volume [Nml] Inoculum Only 1 Volume [Nml] 800 Inoculum Only 2 Volume [Nml] 600 Inoculum Only 3 Volume [Nml] Post SCP 1 Volume [Nml] 400 Post SCP 2 Volume [Nml] Post SCP 3 Volume [Nml] 200 Post SCP 2X 1 Volume [Nml] Post SCP 2X 2 Volume [Nml] 0 0 50 100 150 200 250 Hours 300 350 400 450 Post SCP 2X 3 Volume [Nml] P a g e | 32 Exhibit 5: 8/15/2014 – 9/2/2014 Summary This test was started on 8/15 and concluded on 9/2. All reactors were seeded with sludge from the IAWWTF Primary Digester. For this experiment the bottles were loaded at an inoculum/substrate ratio of .5 to observe if they produced more gas over a longer period of time. This inoculum/substrate ratio means that there was twice the volatile solids load of substrate in comparison to the volatile solids load of the inoculum. In this test, each sludge produced more methane as expected from the higher VS loading rate and the reactors ran for a longer period of time before methane production stopped. When methane generation was normalized for VS load, Post-SCP, Post-SCP 2X, and IAWWTF Primary Sludge achieved slightly higher than the average yield of previous tests. The IAWWTF Thickened sludge however had an abnormally high yield in comparison to any previous test previously run leading one to believe there may have been an operator error during the setup of the BMP test. Substrate IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Inoculum Source IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester Inoculum/Substrate Ration: 1.5 Bottle Breakdown: IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only Total: 3 Bottles 3 Bottles 3 Bottles 3 Bottles 3 Bottles 15 Bottles Substrate Volatile Solids Concentrations Substrate VS%* IAWWTF Thickened Sludge 2.26 IAWWTF Primary Sludge 1.03 Post-SCP Sludge 1.60 Post-SCP Sludge 2X 1.60 Inoculum Only 0.63 *% VS is of the wet weight Inoculum IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester IAWWTF Primary Digester VS%* 0.63 0.63 0.63 0.63 0.63 P a g e | 33 Results Sludge IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP Sludge 2X Inoculum Only VS Load (g) 3.24 2.27 2.82 5.63 2.52 Total Methane (nml) 2,652 851 1,208 2,233 283 Applied Yield (scf methane/ lb VS applied) 13.1 6.0 6.9 6.4 1.8 P a g e | 34 Exhibit 6: 9/3/2014 – 9/15/2014 Summary The test was started at 5:00 PM on 9/3 and concluded on 9/15. The BMP test performed from 9/3-9/15 is the first test performed using paired inoculums from the mini-digesters. The reason for doing so is to test if there is a greater biogas yield when the reactors are seeded with an inoculum that is acclimated to their specific substrate. The reactors for Post-SCP and Post-SCP 2X were both seeded with material from Mini-digester 3 as the inoculum because the material from the Post-SCP 2X digester was not yet mature enough to use as an inoculum. The inoculum/substrate ratio was set back to 1.5 for this test. \ Substrate IAWWTF Thickened Sludge IAWWTF Primary Sludge Post-SCP Sludge Post-SCP 2X Sludge Inoculum/Substrate Ration: 1.5 Bottle Breakdown: IAWWTF Thickened Sludge Thickened Sludge Inoculum (MD-1) IAWWTF Primary Sludge Primary Sludge Inoculum (MD-2) Post-SCP Sludge Post-SCP Sludge Inoculum (MD-3) Post-SCP 2X Sludge Total: Inoculum Source Mini-Digester 1 Mini-Digester 2 Mini-Digester 3 Mini-Digester 3 3 Bottles 2 Bottles 2 Bottles 2 Bottles 2 Bottles 2 Bottles 2 Bottles 15 Bottles Substrate Volatile Solids Concentrations Substrate VS% IAWWTF Thickened Sludge 1.48 IAWWTF Primary Sludge 1.58 Post-SCP Sludge 1.37 Post-SCP 2X Sludge 1.37 Inoculum Thickened Sludge Inoculum (MD-1) Primary Sludge Inoculum (MD-2) Post-SCP Sludge Inoculum (MD-3) Post-SCP Sludge Inoculum (MD-3) VS% 0.71 0.75 0.60 0.60 Results Sludge IAWWTF Thickened Sludge Thickened Inoculum IAWWTF Primary Sludge Primary Inoculum Post-SCP Sludge Post-SCP Inoculum Post-SCP 2X Sludge Post-SCP Inoculum VS Load (g) 1.43 2.84 1.52 3.00 1.24 2.40 2.48 2.40 Total Methane (Nml) 281 47 317 293 449 176 675 176 Applied Yield (scf methane/lb VS applied) 3.1 0.27 3.3 1.6 5.8 1.2 4.4 1.2 P a g e | 35