LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Edmonton Region 240 kV Line Upgrades – P786 240 1/2015 .6 The project includes the following components: • increase the capacity of 908L and 909L up to the summer rating of the primary conductor (2x477 kcmil) by replacing the conductor on the small conductor section (first 4 km of line east of Sundance 310P), • increase the capacity rating of 902L up to the summer rating of the primary conductor (2x477kcmil) by replacing the conductor on the small conductor sections of 902L (first 4 km of line east of Wabamun 19S and first 4 km of line east of Sundance 310P), This is scheduled for completion by March 31, 2013. • rebuild the 41 km east-west single circuit wood pole sections of 904L (Jasper to Wabamun) using 2x1033 kcmil conductor, Due to on-going negotiations with land owners in the area this has been postponed to early 2014. • rebuild the 6 km east-west single circuit wood pole section of 904L (Jasper to Petrolia) using 2X1033 kcmil conductor, Due to on-going negotiations with land owners in the area this has been postponed to early 2014. • increase the capacity of both 904L sections out of Jasper 805S up to the summer rating of the primary conductor (2x477 kcmil) by replacing the conductor on the small conductor section (12 km of line south of Jasper 805S), Due to on-going negotiations with land owners in the area this has been postponed to early 2014. • construct 12 km of new double circuit 240 kV line with one side strung east from Keephills 320P to the 904L-908L-909L confluence point west of Stony Plain in order to move the termination point of 908L from Sundance 310P to Keephills 320P, and add two associated 240 kV breakers at Keephills 320P • swap the connections of 904L and 908L at the 904L-908L-909L confluence point south of Jasper 805S in order to move the termination point of 904L from Wabamun 19S to Sundance 310P • install Special Protection Systems (SPS) for three double circuit tower failure events (Category C5), and • install a 240 kV 600 MVA phase shifting transformer in 9L57 line and three associated 240 kV breakers; preferred location is the proposed Livock substation north of Brintnell. This is scheduled for September 1, 2013. Brian Belway Project Manager Transmission Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2569 Brian.Belway@aes o.ca (AESO) Northwest Alberta Transmission System Reinforcement 240 2011-2012 .5 This project involves adding new transmission facilities listed below and is required to maintain reliability of supply and to meet load growth in the northwest Alberta. The need for the entire project has been approved by the provincial regulatory board. Brintnell to Wesley Creek 240 kV Line – This sub-project involves building a new 240 kV line (145 mi) with 2 x 477 MCM conductors per phase (summer/winter capacity of 550/702 MVA respectively). This new line was energized December 18, 2009. Wesley Creek to Hotchkiss 144 kV Line – This sub-project involves building a new 144 kV double circuit line (83 mi) with each circuit with 2 x 477 MCM conductors/phase (summer/winter capacity – 330/422 MVA) and is planned to be completed in 2011. Sulphur Point to High Level 144 kV Line – This sub-project involves building a new 144 kV single circuit line (65 mi) with 1 x 266.8 MCM conductors/phase (summer/winter capacity – 114/146 MVA) and is planned ″ Page 1 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From to be completed in 2012. Ring Creek Arcenceil (near Rainbow Lake) 144 kV Line – This sub-project involves building a new 144 kV single circuit line (70 mi) with 1 x 266.8 MCM conductors/phase (summer/winter capacity – 114/146 MVA) and is planned to be completed in 2012. Reactive Power Support in Northwest Alberta – This sub-project involves adding smaller cap banks at various locations to a total of 180 MVARs in northwest Alberta. In addition, two small SVCs will be added as follows: 30 MVAR @ Cranberry Lake; -5 + 30 MVAR at High Level. This subproject is planned to be completed in 2012. 9L15 termination into Livock 240 2015 .2 This project involves the following developments to provide additional support to the NortWest region of Alberta and increase flows inout of the Fort McMurray area; 15 km of 240 kV line (Brintnell to Livock) Remove 9L15 termination from Brintnell Terminate 9L15 at Livock (brkrs only, Livock should already have the diameter) “ Northwest Alberta Transmission System Reinforcement 240 2015-2017 .3 This project involves the following 240kV and 138kV reinforcements to the NorthWest region of Alberta; “ Bickerdick to Little Smoky- The double circuit 240kV line will help to eliminate the voltage collape and overloaded problem in northwest; it is assumed to be in the service by 2015 New Wimbley 240kV substation New Double Circuit 240kV line from Little Smokey to Wimbley. Southeast Transmission Reinforcement (SETR) 240/138 2011 .4 SETR is a system upgrade to accommodate continued growth in wind generation in the southern Alberta region. This project was approved in July 2008 and is under construction. 138 kV and 240 kV lines and substations upgrade in Lethbridge, Brooks and Empress areas. Construction of a new 138/240 kV 2 x 200 MVA Cypress Substation. Salvage of 2 x 200 MVA 138/240 kV auto-transformers and replacement by 2 x 400 MVA 138/240 kV auto-transformers. Addition of a third 138/240 kV 200 MVA auto-transformer at North Lethbridge. Addition of capacitor banks at Tilley and McNeill. “ Yellowhead Area Transmission Development – P671 240/138 2011 .1 138 kV and 240 kV development in the area to support future load growth. “ Livock 240/144 kV Connection – P834 240/144 2011 .1 Development of Livock 240/144 kV connection to support load growth in the Fort McMurray area near Brintnell station. “ Fidler 312S 240/138 kV Interconnection – P936 240/138 2012 .2 AESO is preparing needs identification document (NID) application and transmission facility owner is preparing facility application (FA) targeted to file with the Alberta “ Page 2 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Utilities Commission (AUC) in Q2 2010. This system upgrade is to accommodate continued growth in wind generation in the southern Alberta region. The target in service date is 2011 with the following major components: New 240/138 kV Fidler Substation 138 kV line re-location Northeast Fort McMurray 240 kV Loop – P791 240 2012 .1 Development of 240 kV loop to reinforce the north Fort McMurray area to support load growth. “ Halkirk 1 Wind Project – P723 150 240 2012 .1 Capital Power intends to connect a 150 MW WTG facility into the Alberta electric grid system via a new 240 kV Transmission line by mid 2012. “ ENMAX Shepard Energy Centre – P719 800 240 6/2015 1.5 The ENMAX Shepard Energy Centre includes a natural gas-fired 800 MW combined cycle power station. The power station is composed of two 240 MW gas turbines and one 320 MW HRSG. The power station is proposed at the eastern edge of the City of Calgary and approximately 4 km south of existing Janet 74S substation. There is a large system portion associated with this project in order to prepare the AIES in the Calgary area to be able to accept a maximum generation output of 860 MW from the Shepherd Energy Center. Sonja Tessari Project Manager Transmission Alberta Electric System Operator (AESO) 2500, 330 - 5th Avenue SW Calgary, AB T2P 0L4 403-539-2669 Sonja.Tessari@aes o.ca Major transmission related components of the Project are outlined below. The following is an overview summary of interconnection facilities required: Customer Provided Facilities: • Construct Shepard Energy Centre and tie-in to ENMAX No. 25 substation (SS-25). Facilities to connect Shepard Energy Centre to AIES (Customer Related): • Construct a new switching station ENMAX SS-25 and tie-in to Shepard Energy Centre. • Construct underground circuits to connect ENMAX SS-25 substation to AIES. • Connect ENMAX SS-25 to existing 911L from ENMAX SS-65. The new line section shall be renumbered as 1080L with a minimum summer rating of 489 MVA as per line data information provided by the TFO. System Reinforcement to accommodate Shepard Energy Centre (System Related): • Build a 240kV double circuit line to connect ENMAX SS-25 to Janet 74S substation. The lines shall be designated as 985L and 1003L, with minimum summer rating of 920MVA. • De-energize or salvage the portion of existing 911L line north of ENMAX SS-25 based on construction space requirements. System Reinforcement as part of Foothills Area Transmission Development (FATD) Project (System Related): • Upgrade East Calgary 5S Substation (new 240kV equipment and two (2) 400MVA transformers). • Build a new 138kV line 23.80L from ENMAX SS-23 to Janet 74S. 23.80L shall have a minimum summer rating of 260 MVA. • Build a new 138kV line 2.80L from ENMAX SS-23 to ENMAX SS-2. 2.80L shall have a minimum summer rating of 260 MVA. Page 3 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From • Rebuild 138kV and 15kV system at ENMAX SS-2. • Connect portion of the existing 917L and existing 2.80L together to form a single 240kV circuit. The line shall be designated as 1077L and this line will not be energized as part of Shepard interconnection. 1077L shall have a minimum summer rating of 489 MVA. • Maintain 240kV system connectivity between East Calgary 5S and Janet 74S substations by connecting portion of the existing 917L and existing 23.80L together to form a single 240kV circuit. The line is designated as 917L. 917L shall have a minimum summer rating of 489 MVA. Note: The terms “Customer Related” and “System Related” are included here only for the purpose of cost allocation under the AESO Tariff. Construction is underway and the project has a planned in service date of June 2015 for full commercial operation. Greengate Blackspring Ridge Wind Farm – P728 300 Naturener Wild Rose Wind Farm 1 – P479 210 240 3/2014 .3 This application proposed the construction and operation of the power plant consisting of 166 wind turbines, each rated at 1.8 MW, for a total installed capacity of 300 MW located in the Carmangay area. Connection of the Facility to the transmission system requires development of a new 240kV switching station to provide access to existing line 1036L and a new single-circuit 240 kV transmission line connected to wind power plant. The requested in-service date for the new connection is March, 2014. The project is currently in Stage 4, filed in December, 2011 waiting on AUC review and approval. Gate 4 completion is planned for July, 2012 depending on AUC approval. Mark Appelt Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 587-952-4943 Mark.Appelt@aeso .ca April, 2016 .4 Wild Rose 1, a 210 MW wind-powered generating facility, is comprised of 70 x 3 MW wind turbine generators with a collector substation located approximately 55 km southeast of the City of Medicine Hat. This wind power plant will be connected from the Wild Rose 1 547S substation to the Elkwater 264S substation via a single circuit 240 kV line. Dale Bergmen Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2704 Dale.Bergman@ae so.ca The proposed in-service date for the interconnection of Wild Rose 1 is July, 2013 April, 2016 The Facilities Application was approved by the Alberta Utilities Commission on March 21, 2012. Page 4 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Naturener Wild Rose Wind Farm 2 – P693 Gen MW 204 Transmission kV 240 Date March, 2016 No. of pages .4 Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Wild Rose 2, a 210 MW wind-powered generating facility, is comprised of 70 x 3MW wind turbine generators with a collector substation located approximately 30 km south of the City of Medicine Hat. In the near future, the wind power facility will be expanded to have a total of 204 MW installed capacity. This wind power plant will be connected from the Eagle Butte 274S substation to the Elkwater 264S substation via a single circuit 240kV line. The proposed in-service date for the interconnection of Wild Rose 2 is March, 2016. The Facilities Application was approved by the Alberta Utilities Commission on March 21, 2012. Fort McMurray Bulk Transmissioin System Development Project (Stage 2) – P838 500 2019-2021 Christina Lake Area Development 240/144 2015 Algar 240/144 kV substation 240/144 240 Algar-Kinosis 240 kV line .3 Request Copy of Report From Dale Bergmen Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2704 Dale.Bergman@ae so.ca The project includes the following components: One 500 kV AC line (2000-3000 MVA) from the Genesee generating station to a new 500 kV substation in the Fort McMurray area (stage 1) with expected operation date around 2019. One 500 kV AC line (2000-3000 MVA) from the Heartland station to a new 500 kV substation in the Fort McMurray area (stage 2) with expected operation date around 2021. The project NID has been approved through legislation, therefore transmission facilities need approval from Alberta Utilities Commission is not required. The project will be competitively procured; no TFOs are assigned to this project yet. At the conclusion of the competitive procurement process, a proponent will be selected and the facility application with Alberta Utilities Commission can proceed. Dean Patterson Senior Program Specialist Transmission Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2694 Dean.Patterson@a eso.ca This project involves the development of looped 240kV double circuit in the Christina Lake area south of FortMcMurray. The project will allow connection of new load and reinforce the transmission system to accommodate the forecasted load and generation growth in the area south of Fort McMurray. The project involves the following; 3 new 240/144kV substations (CHL1, CHL2 and CHL4) Termination of the new looped 240kv line into the existing HeartLake substation “ 2015-2017 This project involves the construction of a new 240/144 kV substation to provide a fourth source to the 144 kV transmission system in Fort McMurray to accommodate load growth in the area and alleviate anticipated congestion on the 144 kV system. “ 2017-2020 This project involves the construction of a new 240 kV circuit connecting the existing Kinosis substation to the new Algar substation. This project will provide needed reinforcement to the Fort McMurray 240 kV network in order to accommodate the forecasted load growth. “ Page 5 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Southern Alberta Transmission Reinforcement (SATR) – P787 Gen MW Transmission kV 240 Date No. of pages 2016 1 Transfer Capability 2400 Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps The project considers the implementation of a 240 kV loop in the Southern Alberta region in order to allow the future connection of 2400 MW of wind development in that region and to move this power to the Calgary area through three power corridors; on the east from Whitla to West Brooks, on the center from Peigan to Foothills and on the west from Goose Lake to Langdon through the 500 kV transmission line 1201L. This project consists of the following lines: • 911L replaced by Foothills to Peigan 240 kV double circuit transmission line with 50% series compensation. Each circuit rated with a summer/winter capacity of 980/980 MVA. • A new 240 kV double circuit line, approximately 150 km in length, from Cassils (near West Brooks) to Bowmanton (East Medicine Hat). Each circuit rated at a summer/winter capacity of 980/980 MVA. • A new 240 kV switching station at a location known as Milo Junction and converting the two existing three terminal Langdon - West Brooks - North Lethbridge lines into six two-terminal lines. • A new 240 kV double circuit line, approximately 80 km in length, from Bowmanton (Medicine Hat) to Whitla connecting the wind farms in the south. Each circuit rated at a summer/winter capacity of 980/980 MVA. • A new Chapel Rock (Crowsnest) 500/240 kV substation cut into existing 1201L. The station will include two 1200 MVA 500/240 kV transformers, two 240 kV 100 MVAr capacitor banks and a +200/-100 MVAR SVC and one 45 MVAr shunt reactor. • A new Chapel Rock –Castle Rock Ridge - Goose Lake 240 kV double circuit transmission line with a rated summer/winter capacity of 980/1200 MVA. • The addition of a 138 kV Phase Shifting Transformer between Coleman and Pincher Creek. • A new Ware Junction – Langdon 240 kV double circuit transmission line with a rated summer/winter capacity of 980/1200 MVA with 50% series compensation. • The addition of two (2) 240/138kV 400MVA transformers at Peigan. • New 240 kV Etzikom Coulee substation to connect future wind farms. • Interconnect Etzikom Coulee with Picture Butte (MATL) substation. • Interconnect Etzikom Coulee with Goose Lake. The project is planned to be fully operational by 2016. Request Copy of Report From Dale Bergman Project Manager – Transmission Project Delivery South Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 Tel: 403-539-2704 Dale.Bergman@ae so.ca Currently most of the project developments are at Facility Application stage. The eastern corridor Whitla-West Brooks is under construction with a forecast ISD March 2014. Two facilities, the Phase shifting transformer at Russell and the new Milo switching station, are in-service since December 2011. The Ware Junction Substation Upgrade is in-service since November 2013. The connection studies conducted for this system project does not indicate an impact on the transfer capability of WECC Path 1. South and West of Edmonton Transmission Development – P850 240 April, 2017 1 The Project 850 addresses the need for development in the area South and West of Edmonton. The preferred alternative includes: New 240/138kV substation (Harry Smith) south of Stony Plain with 2 x Ed Mayer Project Manager – Transmission Page 6 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps 240/138kV 400MVA transformer New 240/138kV substation (Saunders Lake) north of Leduc with 2 x 240/138kV 400MVA transformer New 25km 138kV line from 780L to Cooking Lake and reconfiguration New 33km 138kV line from Harry Smith to Carvel 432S New Capacitor Banks at Leduc 325S (27MVAR), Camrose 285S (27MVAR), N.W. Cardiff 191S (27MVAR) and Onoway 352S (3.5MVAR). Up-rate to 550MVA of 910L (~700m) and 914L (~650m) at Ellerslie 89S; and up-rate 723L within Westlock 438S and Clyde 150S substation The AESO conducted additional analysis capturing the impact of the proposed development on the SOK- 240kV transmission path capability. The results showed that the project will have a minimal impact on the SOK capability if either of the N-S developments (Project 737) is energized before the energization of the Saunders Lake substation. The ISD will be Q4 2015 April, 2017. Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2757 ed.mayer@aeso.ca The project includes a new 240kV substation Enmax No. 65 with 2x400MVA 240/138kV transformers. 400m of new double circuit 240kV lines with a rating of 965MVA will connect the Enmax No. 65 substation to the existing 240kV lines 9L11. Sonja Tessari Project Manager Transmission Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2669 Sonja.Tessari@aes o.ca The project includes 65km of 3000MVA 500kV double circuit line from Ellerslie substation to the new 500kV substation Heartland located in Fort Saskatchewan. The project will also include 20km of 1000MVA 240kV double circuit lines connected to the existing 240kV lines between Lamoureux substation, Josephburg substation and Deerland substation near the new Heartland substation. Ilice Tan, PMP Project Manager Heartland, Project Delivery North Transmission Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2530 Ilice.Tan@aeso.ca ENMAX South Calgary SS65 Substation – P922 240/138 In-Service .2 Alberta Industrial Heartland Bulk Transmission Development – P629 500/240 6/2014 .2 3000 Montana-Alberta Tie 240/230 In-Service 6 300 3 Request Copy of Report From The MATL project proposes to interconnect the transmission systems in Alberta and Robert Stade Page 7 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date Constructed by Montana Alberta Tie Ltd. – P482 No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Montana via a 240/230 kV transmission line. Within Alberta, the construction of a new substation approximately 6 km north of Lethbridge including three 240 kV breakers in a ring configuration and approximately 1 km of double circuit 240 kV line to accommodate the MATL interconnection. MATL’s merchant line will be Alberta’s first direct transmission interconnection with the United States. The proposed transmission line is a 230 kV three-phase AC line running from north of Lethbridge, Alberta, to Great Falls, Montana. In Alberta, the line will be connected to the existing 240 kV line (923L) through a new substation Picture Butte 120S located 15 km northeast of the existing North Lethbridge 370S substation. In addition to the substation connection facilities the substation will also contain a 240/230kV phaseshifting transformer to control the amount and direction of power flowing on the line. From the proposed substation, the transmission line will head east and south before leaving Alberta and entering Montana. The line will continue southward through Montana to a new mid point station, Marias Substation, and then on to Great Falls. At Great Falls, the line will connect to an existing NorthWestern Energy (NWE) substation. Request Copy of Report From Sr. Mgr. Engineering – MATL Project Enbridge Inc. 425 – 1st Street S.W. Calgary, AB T2P 3L8 w. 403-767-3614 c. 403-463-0582 robert.stade@enbri dge.com The MATL project will have a normal rating of 300 MW. The line will be operated by the AESO in Alberta and by NWE in Montana. The project has received approval the Alberta Utilities Commission (AUC), National Energy Board (NEB) as well as other responsible Federal, Provincial authorities. Construction is on-going with a scheduled completion date of Q4 2012. The estimated in-service energization date is in June 2013. Intertie commissioning will start after energization followed by Commercial Operation in July 2013. The temporary NaturEner Rim Rock Windfarm in Montana has been cancelled. The energization date was August 8, 2013. Alberta Industrial Heartland Bulk Transmission Development – State 2 500/240 2015-2020 The purpose of this project is to reinforce the 240 kV network in northeastern Alberta and increase reliability to the connection of the East HVDC lines. This project will involve the following reinforcements: Second 500/240 kV transformer at Heartland Double circuit 240 kV from Heartland to Eastwood Double circuit 240 kV from Eastwood to 942L tap. 10 km 2 x 1033 double circuit. “ P116 – Foothills Area Transmission Development 240 June-14 The Foothills Area Transmission Development is a regional system project that is required to support load growth and generation increase in the Calgary and Foothills areas, and also to support the wind power generation increase in southern Alberta. The project consists of initial stage of a new Foothills substation to terminate the new 240 kV lines from Fort McLeod area in southern Alberta. “ Page 8 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project P1117 – Foothills Area Transmission Development – FATD – Foothills 237S Substation & East Calgary Development - Updated Gen MW Transmission kV 240/138 Date June-14 No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps The AESO has identified the need to reinforce the transmission system in the south Calgary and in the High River Planning area. This reinforcement will alleviate the existing and anticipated constraints to accommodate the expected load growth and integrate the proposed generation capacity within the subject area, and facilitate transmission of generation from southern Alberta to load centers. The FATD project will consist of two separate sub-projects. This project proposes to install various 240 kV lines between substations Janet 74S, SS-25, SS-65, Foothills 237S and Langdon 102S to improve the area system capacity as well as the construction of a new Substation Foothills 237S. Also included in this project is the installation of 138 kV lines in the High River planning area. The new Foothills 237S substation will serve as the termination points for the double circuit line 1029L/1030L from Peigan 59S. This is where the Southern Alberta Transmission Reinforcement (SATR) project is tied with FATD project to achieve the required overall system performance. The scope of the 240 kV transmission developments included in the AESO’s FATD East NID is as follows: • A new 240 kV substation designated Foothills 237S that includes two new 240/138 kV transformers, each with a rating of 400 MVA. • A new 240 kV double circuit line from Foothills 237S substation to future ENMAX No. 65 substation with a minimum summer rating of 600 MVA for each circuit. The lines will be designated 1106L and 1107L. • A new 240 kV double circuit line from Langdon 102S to Janet 74S with a minimum summer rating of 800 MVA for each circuit. The lines are designated 1064L and 1065L. • Create a new 240 kV double circuit line from Langdon 102S to East Calgary 5S2 using a combination of lines 936L, 937L, 917L, and 1077L; 917L and 1077L, which were included in the East Calgary NID are connected to 936L and 937L to create the new 240 kV path between East Calgary and Langdon substation in FATD East NID. As per the TFO’s data submission, the summer rating of each circuit is 489 MVA. The lines are to be designated 936L and 937L. Summary of Transmission System Developments included in the ‘FATD East’ NID • Create a 240 kV double circuit line between future ENMAX No. 65 substation to future ENMAX No. 25 substation, by energizing sections of the existing 850L transmission line to 240 kV. Transmission line 850L is built to 240 kV standards and is currently operating at 138 kV. 850L and 1080L share the same towers. As per the TFO’s data submission, the summer rating of the line is 489 MVA. The line designation will be changed from 850L to 1109L. • Terminate line 985L at Janet 74S substation, thus completing the circuit. The new 240 kV transmission line 985L is included in the East Calgary NID and proposed to be built on the same towers as 1003L. The minimum summer rating of this line is 920 MVA. • De-energize sections of the 911L line from south of ENMAX No. 65 substation to Foothills 237S.The existing 911L in the High River planning area will be de-energized upon completion of theSATR project. The project has been approved by the Alberta Utilities Commission in October 2013, ISD forecasted for 1117- FATD-East is Q3 2015. The connection studies conducted for this system project does not indicate an impact Request Copy of Report From Sonja Tessari Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 - 5th Avenue SW Calgary, AB T2P 0L4 403-539-2669 Sonja.Tessari@aes o.ca Page 9 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From on the transfer capability of WECC Path 1. P1118 – Foothills Area Transmissiion Development West Calgary Development C-Free Power Oyen Wind Project – P763 240/138 100 On Hold .5 Foothills Area Transmission Development – West Region (FATD West, Project No. 1118) This project will include the installation of 240 kV lines between Foothills 237S and Sarcee 42S. • A new 240 kV double circuit line from Foothills 237S to Sarcee 42S with a minimum summer rating of 600 MVA for each circuit. The lines are designated 1066L and 1067L. ISD beyond 2020. Sonja Tessari Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 - 5th Avenue SW Calgary, AB T2P 0L4 403-539-2669 Sonja.Tessari@aes o.ca 2013 .1 The project involves development of a 100 MW wind power generating plant. “ Edmonton - Calgary West DC Lline – P962 +/- 500 DC Q4/2014 .3 To alleviate congestion on the N-S transmission system, restore capacity of interties, improve efficiency of the transmission system (reduce losses), and avoid potential reliability issues, the following development has been proposed: Construct a +/- 500 kV bipole, HVDC transmission line between the Genesee area and the existing Langdon 102S substation. Construct monopole HVDC converter station facilities, with an initial rating of a minimum of 1000 MW. The need for this project was approved by the Government of Alberta as part of the Critical Transmission Infrastructure. The project is currently in the facility siting phase and is forecasted to be in service by Q4 2014. “ Edmonton - Calgary East DC Lline – P961 +/- 500 DC Q4/2014 .3 To alleviate congestion on the N-S transmission system, restore capacity of interties, improve efficiency of the transmission system (reduce losses), and avoid potential reliability issues, the following development has been proposed: Construct a +/- 500 kV bipole, HVDC transmission line between the Heartland area and a new 240 kV substation south of Westbrooks (Newell). Construct monopole HVDC converter station facilities, with an initial rating of a minimum of 1000 MW. The need for this project was approved by the Government of Alberta as part of the Critical Transmission Infrastructure. The project is currently in the facility siting phase and is forecasted to be in service by Q4 2014. “ On Hold .5 The proposed Heritage WAGF will be connected to the Alberta Interconnected Electric System (“AIES”) at the Fidler 312S substation in the Pincher Creek area. The windfarm is rated at 350 MW with 100 MW inservice at Stage 1 and 250MW at Stage 2. The Stage 1 development is dependent upon the completion of substation Fidler 312S for Dale Bergmen Project Manager Transmission Project Delivery Benign Energy Heritage Wind Farm - P515 350 Page 10 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date Bow City Power Project – P465 500 Pikani Energy Corp. Wind Farm – P773 220 Vindt Willowridge – P614 100 240 2013 Old Elm and Pothole Creek P1080 300 240 12/2016 Bloodtribe Wild Turnip Hill 150 P635 - Suncor Hand Hills Wind Energy Project 80 Project on hold 2014 240 Dec-13 No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From connection. The Stage 2 development is dependent upon the completion of transmission lines 1004L/992L from Fidler 312S to Chapel Rock 491S for connection. Under the current configuration, the wind power plant will consist of Vestas V90 3MW wind turbines. Both stages are onhold pending regulatory approval of Fidler 312S and transmission lines 1004L/992L. The reason for the staged approach is to inject as much as the system can handle without serious RAS constraints prior to the approval and completion of the Chapel Rock substation (connection to the 500 kV line). After the Chapel Rock Substation is built the system in the Pincher Creek area will become unconstrained (mostly) and will be able to handle the full projected output of the Heritage Windfarm. The requested In Service Dates (“ISD”) for Stages 1 & 2 are on-hold. Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2704 Dale.Bergman@ae so.ca .1 This project requires 240 kV transmission development to accommodate the connection of the 500 MW Bow City coal fired power station. The project consists of a new 240 kV substation with approximately 4 km of 240 kV transmission line and the upgrade of existing 923L and 927L to a higher thermal rating. The project has been on hold since January 2008 and therefore a firm in service date is unknown. “ .1 This 220 MW wind farm project is in the early conceptual stage and no connection has been determined or in service date targeted. “ Vindt Willowridge is a 100MW wind project that will connect to 966L “ .3 The customer is proposing a 300 MW wind farm consists of 130 Siemens 2.3MW wind turbines located in the Glenwood Area close to the Magrath 225S. The proposed interconnection is to the line 988L, a planned 240 kV transmission line between Goose Lake 103S and Journault 260S (SATR Phase 2). Connection includes construction of 240 kV transmission line to the Nine Mile Coulee 143S wind farm substation complete with two 240/35kV transformers. The customer had requested an ISD of October, 2013 however due to the system development required for the connection (988L) the ISD has been set at March, 2018. The project is currently completing P&L application waiting on further details of the 988L development before consultation can begin. P&L application is dependent on the facilities application filing date of the 988L 240kV line. Dale Bergmen Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2704 Dale.Bergman@ae so.ca 150 MW connecting into 240KV Line 968L “ The Suncor Hand Hills Wind Farm project is a 80 MW wind power site that is located north-west of Anderson 801S. The project consists of a 240 kV switching station (Mother Mountain) that is a 240 kV ring bus, a 240 kV single-circuit transmission line and a 240/34.5 kV collector substation (Hand Hills 605S). “ Page 11 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Transmission kV 80 240 Apr-13 The Nexen Hand Hills Wind Farm project is a 80 MW wind power site that is located north-west of Anderson 801S. The project consists of a 240 kV additions at proposed Coyote Lake 963S, a 240 kV single-circuit transmission line and a 240/34.5 kV collector substation (High Land 572S). “ P811 - Central East Transmission Development 240 Dec-17 The Central East Transmission Development is a regional system project that is required to support growth in the Central Region. The project consists of re-energizing an existing transmission line to 240 kV from proposed Bourque 970S substation to Bonnyville 700S, modifications to Bourque 970S and a new 240 kV transmission line from Marguerite Lake 826S to proposed Bourque 970S. “ P812 - Hanna Region Transmission Development 240 Mar-13 The Hanna Region Transmission Development is a regional system project that is required to support growth in the Hanna region. The project consists of four 240 kV source substations (Coyote Lake 963S, Lanfine 959S, Pemukan 932S and Nilrem 574S) one 240 kV switching station (Oakland 946S), modifcations to existing 240 kV substations (Hansman Lake 650S, Ware Junction 132S and Cassils 324S), -100/+200 MVar SVC's (Hansman Lake 650S and Lanfine 959S) and about 300 km of new 240 kV double-circuit transmission. “ P1113 - Hanna Region Transmission Development Phase 2 240 2017 The Hanna Region Transmission Development Project is designed to reinforce the transmission system in the Western Part of Central Alberta in anticipation of future load growth, in particular, pipeline pumping load. Several Transmission Facility Owners are involved in this project. The major components of this project consist of: • String second side on the 240 kV double-circuit line from Oakland to Lanfine and Related Alterations at Oakland 946S and Lanfine 959S. • Cordel 755S to Halkirk Switching Substation, New double circuits 240 kV Line (one side strung) and Related Alterations. • Anderson to Oakland Transmission Project 9L70/9L97 240kV lines, Oakland Substation and Related Alterations • String Second Side on the 240 kV double circuits Line from Oakland 946S to Coyote Lake 963S and Related Alterations at Oakland 946S and Lanfine 959S. Additionally, the following components are designed to reinforce the local network: • Convert existing Hanna 763S Substation to 144 kV Substation. • New 144 kV Line from Coyote Lake 963S to Hanna 763S and Related Alterations • Addition of 2nd 240/144 kV Transformer at Pemukan 932S. • Addition of 2nd 240/144 kV Transformer at Lanfine 959S. • Addition of 2nd 240/144 kV Transformer at Hansman Lake 650S. • Nilrem 574S Substation Capacitor Bank Addition • Hansman Lake 650S Substation Capacitor Bank Addition • Metiskow 648S Substation Capacitor Bank Additions • Decommission of 6L44 (Rowley 768S to Big Valley 778S) and 6L22 (Michichi Creek 802S to Rowley 768S) The current scheduled complete date is in year 2017 subject to change The need of this project has been approved by the Alberta Utilities Commission with Anita Patel Project Manager – Transmission Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2516 Anita.Patel@aeso. ca Name of Project P678 - Nexen Hand Hills Wind Project Date No. of pages 1 Transfer Capability CONTENTS AND REMARKS Power Transient Tables Flow Stability Gen MW Phase Post Transient Stability One Lines Maps Request Copy of Report From Page 12 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From the timing and staging of this project under review. Due to the broad scope of this project involving multiple transmission facility owners, AESO has the oversight on this project under Anita Patel. P813 - Red Deer Transmission Development 240 Q3 2014 1 The Red Deer Area Transmission Development project will be implemented in two stages. Pending the approval of the Facility Application. Following is an overview of the major components of the proposed developments in stage I. The timing of stage II will be determined by the future load projections. • Split 768L and 778L and re-terminate at Red Deer North 217S (add 1 brk, use 1 existing brk) and Gaetz 87s (add 2 brks, use 1 existing brk) • Add a second autotransformer at Benalto 17S. • Add one 50 MVAR 138 kV capacitor bank at Joffre 535S • Add one 50 MVAR 138 kV capacitor bank at Prentiss 276S • Add one 27.6 MVAR 138 kV capacitor bank at Ellis 332S • Re-build 5 km of 80L 138 kV transmission line from South Red Deer 194S (use existing1 brk) to North Red Deer 217S (use existing brk) • Re-build 5 (including 1 km of underground) km of 80L 138 kV transmission line from South Red Deer 194S (use existing brk) to Red Deer 63 (use existing brk) • Re-build 29 km 755L 138 kV transmission line from Red Deer 63S (use existing brk) to Piper Creek 247S (use existing brk) to Joffre 535S (use existing brk) • Re-build 33 km 717L (now called 367L and 648L) 138 kV transmission line from Red Deer 63S (use existing brk) to Sylvan Lake (use existing brk) to Benalto (use existing brk) • New Johnson 281S 240/138 kV substation with 240 kV double circuit (200m) from 918L and 2 km of double-circuit 138kV line to 80L and a connection to 166L • New 240/138 kV Wolf Creek 247S Substation with 240 kV double circuit (200m) from 910L and 4 km of double-circuit 138kV line to Ponoka 331S (use existing brk from salvage of D13 and D16) connect to 883L • New 240/138 kV Hazelwood 287S Substation on the 240 kV line 924L • New 13 km of 138 kV transmission line from Lacombe 212S (add 1 brk) to Ellis332S (add 1 brk) • Salvage 53 kM 80L 138 kV transmission line from Red Deer 63S to Innisfail 214S • Salvage 23 KM 80L 138 kV transmission line from Ponoka 331S to West Lacombe 958S (this will be less by the approx.. 5 km of salvage now part of Wolf Creek (CP44)) • Salvage 40 km of 716L from Wetaskiwin 40S to Ponoka 331S (this will be less by the approx.. 5 km of salvage now part of Wolf Creek (CP44)) Anita Patel Project Manager – Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2516 Anita.Patel@aeso. ca The in-service date is in stages starting from 2013. The Need Identification Document was filed to Alberta Utilities Commission in July 2011, and approved in April 2012, Facilities Applications are being prepared in stages with the last stage scheduled to be filed by Q3 2014. North South Transmission Reinforcement – P737 500 4/2015 1 This project consists of two 1000 MW 500 kV line-commutated HVDC lines to alleviate transmission congestion along the SOK cut-plane. These two transmission lines are mandated by the Alberta Dean Patterson Senior Program Specialist Transmission Page 13 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Legislature as a Critical Transmission Infrastructure (CTI) project in the Electric Status Amendment Act, 2009. The need for this line was re-affirmed by the Minister of Energy in February 2012. East Alberta Tie-Line (EATL) connects the Heartland 500 kV substation in the Fort Saskatchewan Area to the new Newell 240 kV substation in the Brooks Area. It will be built as bi-pole line with 1000 MW monopole converters using remaining conductor as metallic return. The project was approved by the Alberta Utilities Commission on November 15, 2012. Request Copy of Report From Project Delivery Alberta Electric System Operator (AESO) 403-539-2694 Dean.Patterson@a eso.ca West Alberta Tie-Line (WATL) connects from new Sunnybrook substation near Genesee substation in the Wabamun Area to Langdon substation which is also the terminal of 1201L 500kV BC-Alberta Tie-line. It will be built as bi-pole line with 1000 MW mono-pole converters using remaining conductor as metallic return. The project was approved by the Alberta Utilities Commission on December 6, 2012. The addition of these two HVDC lines will significantly increase the North to South transfer capability (SOK limit) within Alberta. As the 1201L 500 kV Alberta to BC export capability is limited by the SOK limit, the addition of these two lines will increase the Total Transfer Capability of 1201L. This impact will be quantified by Inter-Tie Rating Studies and HVDC Operations Studies scheduled to be completed by the end of 2014. The estimated ISD of WATL is April 2015 and ISD of EATL is December 2014. New Fidler 312S Substation – Project 1343 240/138 10/2017 .5 Increased transmission capacity is needed in the area northeast of Pincher Creek and west of the Piikani Nation reserve to provide several wind generating facilities, two of which are already in service and others which are planned to be in service within the next two years, access to the transmission system. The existing two wind generating facilities are frequently required to reduce output during normal operating conditions due to existing transmission system constraints. The Fidler 312S Collector Substation Connection Project NID was submitted by the AESO to the AUC on October 26, 2012. NID and FA approval is expected by August 2013. The planned in-service date is April, 2014. The Fidler Project includes a two stage development. Stage 1: • Develop a new 240/138kV collector substation with one transformer • Add a new double circuit 240 kV line connecting Fidler 312S to the existing 1071L transmission line in an in-out configuration • Rebuild existing portions of 138 kV transmission lines connecting into the Fidler 312S substation • Configure 893L between Goose Lake 103S and the tap-off to Oldman River Dam 806S to normal open under normal operating conditions Stage 2: • Add a second transformer at Fidler 312S Dale Bergmen Project Manager Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2704 Dale.Bergman@ae so.ca Page 14 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From • Salvage existing 138kV transmission line 893L between Goose Lake 103S and the tap-off to Oldman River Dam 806S. Stage 2 is dependent on meeting the milestone when installed and proposed generation capacity connected at the 138 kV side of Fidler 312S exceeds 80% of the capacity of the first transformer (288 MW assuming 0.9 power factor). The requested in-service date for the new connection is October, 2017. Whitetail Peaking Station – Project 1290 200 Shell Carmon Creek – Project 1321 230 Project 1421 - ATCO Power Heartland Generating Station 1080 240/25/18 5/2014 .1 BowMont Capital and Advisory Ltd. (BowMont) is planning to construct the Whitetail Peaking Station (“the Project”) as a new point of supply (POS) - Project 1290. The Project is to be developed in one stage with an in service date (“ISD”) of May 1, 2014. The plant consists of 4x50MW of gas fired peaking units. The plant is located in the Peace River area (Area 19) in the vicinity of LSD 29-85-19W5 which is located approximately 13.5 km to the north of the existing Wesley Creek 834S substation. The preferred alternatve is to complete an in and out connection to 7L106 in the Northwest Region of Alberta. The project is currently in Stage 3 out of 6 of the Connection Process and a Functional Specification is being drafted by the AESO with Planned In-service date of May 1, 2014 Robert Michaud Manager, Transmission Projects ATCO Electric 10035 105 Street Edmonton, AB T5J 2V6 Ph: 780-508-4896 Cell: 780-719-5697 7/2015 .1 The proposed project has an in service date of July 1, 2015. A total of three 230 MW cogeneration units are planned with 70 MW of on-site load. Shell intends to build a customer owned 240/25/18 kV substation and seeks an Industrial System Designation for the project. All projects loads will be served from Shell's proposed substation. The transmission connection requested could be a double-circuit 240 kV line from Carmen Creek to Wesley Creek in the Northwest Region of Alberta (Alternatives currently being studied). Project is currently completing studies and is in Stage 2 of the Connection Process with planned ISD of July 1, 2015 Vladimir Lopez Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 (T) 403-539-2819 vladimir.lopez@aes o.ca 10/2018 1 Generation Station. The generation station will be located at NW-27-55-21-W4M. The project will consist of three identical phases. • Phase 1: 15MW DTS in March 1, 2016, and 510 MW STS in September 2016 • Phase 2: Additional 15MW DTS in March 1, 2018, and additional 510 MW STS in October 2018 The dates associated with the three phases are the start of commissioning and expect the plant to begin commercial generation six months thereafter. Each facility will include the following major components: • 1 x Natural Gas Turbine • 1 x Steam Turbine • 1 x Heat Recover Steam Generator (Include ~50 MW of Duct Burners) Steve Palmer Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 403-539-2558 steve.palmer@aes Page 15 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From The equipment specified above is subject to change, but they do not expect the nominal capacity to exceed 470 MW. The generation facility will be designed and operated to ensure that the outage of any single element/component will not cause a loss of more than 466 MW of generation to the AIES. Generation Component Each phase of the project consists of a generation with the Maximum Capability (MA) 1 level of 470 MW with 0.9 PF lagging and 0.95 PF leading. The requested Supply Transmission Service (STS) includes: • 510 MW STS in September 1, 2016 • Additional 510 MW STS in October 1, 2018 Load Component The requested Demand Transmission Service (DTS) consists of 15 MW in March 1, 2016, with an additional 15 MW in March 1, 2018, and another additional 15 MW in March 1, 2020. o.ca Project 1440 - Genesee Generating Station Unit 4 (“G4”) and Genesee Generating Station Unit 5 (“G5”) 1000 12/2017 .5 On April 30, 2013 AESO received a System Access Service Request (“SASR”) from Capital Power L.P. to connect a 1000MW Power Generation Facility, the Capital Power Energy Centre (“CPEC”) to the AIES. The CPEC will be a new gas combined cycle facility to be located within the Genesee Generating Station land. The new facility will consist of two Gas Turbine Generators (“GTG”) and associated Steam Turbine Generator (“STG”). CPEC indicated that the Gross Generation Capacity is expected to be up to a 1000MW; which could be developed in stages to meet Alberta’s demand. Therefore, the study will proceed with the assumption that the gross capacity of the proposed generating station is 1000MW. The facility in-service date is currently expected to be December 31, 2017; however, CPEC indicated that this date is subject to change due to market conditions. Vladimir Lopez Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 (T) 403-539-2819 vladimir.lopez@aes o.ca Project 1477 - TransAlta Sundance 7 Gas Turbine/Generators Installation 818 6/2018 .5 TransAlta MidAmerican Partnership is proposing to construct approximately 850 MW Sundance 7 generating facility in the vicinity of LSD 10-52-4-W5M. The site is located near existing TransAlta generating facilities near Wabamun. The facility will be a Combined Cycle Gas Turbine consisting of two Gas Turbine/Generators (GT) of approximate 295 MW capacity (345 MVA, 0.85 pf) and a single Steam Turbine/Generator (ST) of approximately 345 MW (405 MVA, 0.85 pf). The gross output is approximately 943 MW with an STS capacity of 850 MW. The maximum Gross Capacity at an average summer temperature of 15.3 degrees Celsius is 818 MW and the Net Output is 797 MW. The anticipated in service date (ISD) is June 29, 2018 and the commercial operation date (COD) is January 31, 2019. Vladimir Lopez Transmission Project Delivery Alberta Electric System Operator (AESO) 2500, 330 – 5th Avenue SW Calgary, AB T2P 0L4 (T) 403-539-2819 vladimir.lopez@aes o.ca In-Service .5 Avista has begun construction (in late CY 2010) on a new Moscow 230/115 kV substation (located adjacent to the existing Moscow 230/115 kV substation). This Moscow 230 kV Transformer and station rebuild 230/115 Tracy Rolstad (509) 495-4538 Page 16 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Noxon Rapids Turbine Upgrades Gen MW Transmission kV + 42 MW Major Generation Addition (> 200 MW) Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From project will be constructed in a double bus-double breaker configuration for the 230 kV yard, and in a breaker-and-a-half configuration for the 115 kV yard. Additionally, Avista will replace the existing 125 MVA 230/115 step-down transformer and associated 125 MVA 115/115 kV regulating transformer with a new 250 MVA 230/115 kV tap changing transformer. The Moscow 230 kV station rebuild (including the transformer replacement), and associated minor 115 kV reconductoring in the Moscow, ID and Pullman, WA area will positively impact the performance of the West of Hatwai path (WECC path #6). (AVA) “ 6/2012 .2 Avista’s Power Supply function is engaged in turbine blade upgrades on Noxon Rapids units #2, #3, and #4. These upgrades will add an additional 14 MW’s respectively to the existing turbine capacities. The total electrical output of the Noxon Rapids project will be a maximum of 557 MW. This electrical limit does not consider any hydraulic limitations associated with the greater Clark Fork River project (which includes Cabinet Gorge and Noxon Rapids). 2014-2023 .4 Plant Capacity Waneta Expansion G1 167.5 MW Waneta Expansion G2 167.5 MW Mica G5 500 MW Mica G6 500 MW Rev G6 500 MW Site C G1 183.3 MW Site C G2 183.3 MW Site C G3 183.3 MW Site C G4 183.3 MW Site C G5 183.3 MW Site C G6 183.3 MW April 2023 In Service Date April 2015 April 2015 Oct. 2014 April 2015 April 2029 April 2023 April 2023 April 2023 April 2023 April 2023 Guihua Wang (604) 699-7367 (BCHA) Vancouver City Central 230 kV Transmission Project 230 Spring 2014 .2 Currently in implementation phase, this project constructs a new substation and new transmission lines. New station: Mount Pleasant Substation New lines: 2L20 (3.4 KM) – Cathedral Square to Mount Pleasant 2L44 (4.8 KM) – Mount Pleasant to Sperling “ Dawson Creek / Chetwynd Area Transmission (DCAT) Project 230 6/2015 .2 The Dawson Creek / Chetwynd Area Transmission Project (DCAT) consists a two 60 km 230kV lines running from a new 230 / 138 kV substation named Sundance Substation (SLS) to Bear Mountain Terminal (BMT) and a new 138 kV line from BMT to Dawson Creek Substation (DAW). This project would provide additional transmission capacity into the Dawson Creek area to support new unconventional gas production loads. “ Northwest Transmission Line (NTL) Project 287 5/2014 .2 Currently in implementation phase, the Northwest Transmission (NTL) Project consists of approximately 340 km of 287 kV transmission line from the Skeena Substation near Terrace to a new substation at Bob Quinn and a series compensation capacitor bank (35%) at Bob Quin. The NTL will provide infrastructure for connecting new sources of “ Page 17 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From generation, future industrial development and communities in the area. Fraser Valley West Area Reinforcement (230 kV) 230 6/2015 .2 Construction of a new substation and new transmission lines. New station: Fleetwood Substation Splitting 2L75 from Ingledow to McLellan to 2 lines. New lines: 2L75 (8 KM) – Ingledow to Fleetwood 2L81 (8 KM) – Fleetwood to McLellan “ Series Compensation on Southern Interior 500 kV lines (SISC) 500 10/2019 .2 The project is to add one 500 kV series capacitor station, on 5L98 transmission line from Nicola to Vaseux Lake. This project is still in definition phase. ″ Seymour Arm Series Capacitor (SASC) (Mica – Nicola 500 kV Series Compensation) 500 In-Service .1 The series compensation project on the two 500 kV lines between Mica and Nicola was in service in November 2013. “ New ILM 500 kV line 500 1/2015 .2 The new line is planned to provide incremental transmission transfer capability from the Interior of British Columbia to the load centers in the Lower Mainland. This new 500 kV transmission circuit, 5L83, will be approximately 250 km long and will run between the Nicola and Meridian substations. 5L83 will be 50% series compensated at new Ruby Creek Capacitor Station near Agassiz. Technical planning studies have been completed and the project is currently undergoing implementation phase. ″ Spring 2014 .2 A project is planned to reconfigure Nicola station, a critical station that collects power flows from the South Interior before transmitting the power to Lower Mainland, to prevent total lost of the station and increase the reliability of the transfer of power to the Lower Mainland. Definition work was initiated for this project. “ Nicola Station Reconfiguration Metro North Area 230 kV Reinforcement 230 10/2017 .2 The planning study is in progress and the following identified is only one alternative, may subject to changes: 1) Reterminate 2L49 from Meridian – Horne Payne to Meridian – Murrin (34 KM) 2) Reterminate 2L50 from Burrard – Murrin to Burrard – Horne Payne (19.5 KM) 3) Add 2 new lines: 2L26 (7.45 KM) – Horne Payne to Murrin 2L23 (19.3 KM) – Como Lake to Horne Payne “ West End 230 kV Substation 230 10/2018 .2 The planning study is in progress and the following identified is only one alternative, may subject to changes: 1) Construct a new 21.5 kM, 230 kV circuit from Meridian to Horne Payne (2L18). 2) Extend an underground circuit (2L51) from Barnard to Mount Pleasant. 3) Add 203 kV – 60 MVAR switchable shunt reactor on dedicated 230 kV line position at Camosun “ Transmission Lines from Site C to Peace Canyon. 500 4/2023 .1 At preliminary planning stage, this project is to build two 500 KV lines from Site C to Peace Canyon, to accommodate site C new generation. “ Page 18 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Meridian T2 Addition 500/230 4/2014 .1 Install a new 500/230 kV 1200 MVA transformer at Meridian Substation. Meridian substation is located on Westwood Plateau in Coquitlam and it is the major supply source to Metro North subsystem serving downtown Vancouver, Burnaby and Tri-cities area loads. “ Kitmat Modernization Project 287 11/2014 .2 Kitmat Modernization Project consists of rebuilding the Kitimat smelter and adding 35% series compensation on the two Kimano to Kitmat 287 kV transmission lines by building a series capacitor station near Kitmat. Five 287/100/28 kV 219 MVA regulating transformers will be installed. “ Series Compensation Increase (from 50% to 65%) at KDY and MLS Stations 10/2022 .2 At preliminary planning stage, this project is to increase series compensation level at 5L1, 5L2, 5L7 at KDY, 5L11,5L12, 5L13 at MLS from 50% to 65%, to accommodate site C new generation. “ Prince George Terrace Compensation (PGTC) Summer 2017 .1 At preliminary planning stage, this project is to install 65% series compensation at 5L61, 5L62, 5L63 from WSN to SKA substation, to accommodate LNG loads in North Coastal BC region. “ 6/1/2014 .1 This project is to construct a 92 km 287 kV transmission extension, from the planned NTL line (Item 7) terminal Bob Quinn substation. The transmission line would terminate at a new substation at Tatooga Lake and a 16 km 25 kV distribution line continuing to Iskut. “ 2014 .1 Coast Mountain Hydro proposes to develop a run-of-river hydroelectric facility North of Stewart. Total plant rated output is 211.4 MW. “ 230 2015 .1 Add a new 230 kV cable circuit (2L142) from George Tripp to Horsey and add one 150 MVA – 230/138 (T14) transformer at George Tripp. “ 230/25 2015 .1 Add a new 150 MVA transformer to supply the load growth in the Tsawwassen/Delta area. “ 2016 .1 An interim upgrade of 2L99 involves imporving the design defects and upgrading the winter line rating to 650 MVA “ 2017 .1 Add Skeena T3 (500/287/12.6) transformer due to new Kitimat LNG2 load. “ Bob Quinn SVC Addition 2016 .1 Add +100/-40 SVC for system reinforcement to accommodate NTL (2L102) new mining loads. “ Add series compensation on circuit 2L102 2018 .1 Add series compensation on NTL (2L102) near Skeena due to new mine loads “ Horne Payne Substation Updrade 2016 .1 Add 2 x 230/25 kV – 150 MVA transformers at Horne Payne Sub “ Iskut Expansion project Forrest Kerr IPP Vancouver Island Cable Project New Arnott 230/25 kV Transformer 287 211.4 Minette to Skeena Line Rating Upgrade (2L99) Skeena Substation Upgrade 500/287/12.6 Page 19 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Date Peace Region Electric Supply (PRES) Project – Alternative 2 2018 .1 Construct a 2nd 22.8 KM 230 kV overhead transmission line from GMS to Dokie Terminal. Construct a 64.1 KM 230 kV transmission line from Dokie Wind Terminal to Sundance. Replace GMS T13 & T14 with 2 new 600 MVA 500/230 kV transformers. “ In Preparation For The Site C Generation Project 2023 .1 Add 250 MVAR switchable shunt capacitor at Williston 500 kV substation Add static var compensator (SVC +250/-150 MVAR) at Williston “ 7/1/2014 This project is to construct a new 138 kV radial transmission line from the existing Highland Substation to a new substation in Merritt, to meet the increased demand for power in the Merritt area. “ 11/1/2018 This project is to supply and install an approximately 500 MW unit in the existing empty Unit 6 bay at Revelstoke Generating station to add capacity to the BC Hydro system. “ The purpose of West of McNary Reinforcement (WOMR) Project is to increase the transfer capability across the West of McNary (WOM), West of Slatt (WOS) and West of John Day (WOJ) paths that will enable BPA to provide transmission service for proposed renewable energy from the McNary area to Northwest load centers west of the Cascade Mountains, to the California-Oregon (COI) AC Intertie, and to the Pacific DC Intertie (PDCI). WOMR is one of multiple BPA projects being developed as a result BPA’s 2008 Network Open Season (NOS). The WOMR Project was divided into two phases and phase 1 has been completed. Phase 2 included: 1. A new 500 KV switching station called Knight Substation, located near Goldendale, Washington at tower 73/1 on the BPA Wautoma-Ostrander 500 kV line, 2. A new 28 mile, 500 kV transmission line connecting BPA’s Big Eddy Substation near The Dalles, Oregon to Knight Substation, A Wautoma - Ostrander 500-kV line re-sag, and 4. A Wautoma 500 kV 300 MVAR shunt reactor which is in service on March 2014 Berhanu Tesema 360-619-6819 (BPA) Merritt Area Transmission (MAT) project Revelstoke Unit 6 Installation Transmission kV 138 500 West of McNary Reinforcement (WOMR) Project 500 11/2015 1 North Cross Cascade 500 kV Line Project 500 2024 .05 345/138/115 2016 1 Lower Valley Area Reinforcement Project Transfer Capability CONTENTS AND REMARKS Power Transient Tables Flow Stability No. of pages Name of Project Gen MW Phase Post Transient Stability One Lines Maps Request Copy of Report From Consisting of a Chief Joe – Monroe 500 kV line, this project is associated with load service and is on hold until load growth supports construction. A 345/161-kV transformer at PacifiCorp’s (PAC) Goshen Substation currently serves the Lower Valley area. Three transmission lines serve load out of Goshen. The Goshen-Drummond 161-kV line serves mostly Fall River loads and provides back-up service to Lower Valley. The Goshen- Swan Valley 161-kV line serves most of the Lower Valley load. The Goshen-Palisades 115-kV line serves the Palisades Generating Plant and some Lower Valley load. BPA constructed a second Swan Valley-Teton line in 2000 and upgraded the GoshenDrummond line to 161-kV in 2002. These upgrades increased the reliability of the Fall River system and helped support load growth in the Jackson Hole area, but did not increase the transmission capability to the southern part of Lower Valley’s system. Capacitor banks have been installed at Targhee, Tincup, Teton, and Madison. PAC has constructed a new 345/138-kV Three Mile Knoll Substation a couple of miles ″ Larry Furumasu 360-619-6851 (BPA) Page 20 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From north of their existing Caribou switching station. This new substation includes a new 345-kV interconnection with Idaho Power. Idaho Power’s Bridger-Goshen 345-kV line is looped into the new Three Mile Knoll 345/138-kV Substation which includes two new 345/138-kV, 650 MVA transformers. For the Lower Valley Area reinforcement Project, BPA will construct Hooper Springs 200 MVA 138/115-kV Substation adjacent to PAC's Three Mile Knoll Substation. I-5 Corridor Reinforcement Project 500 2018 1.5 Central Ferry-Lower Monumental (Little Goose Reinforcement Project) 500 12/2015 500/230 2016 Raver 500/230 kV Transformer 1100-1400 MW This purpose of this project is to increase the transfer capability of the I-5 Corridor in the vicinity of Southwest Washington and Northwest Oregon. This load service area includes the cities of Portland, Oregon and Vancouver, Washington, which include high concentrations of industrial, commercial, and residential load. The generating resources serving this area are a mix of hydro and thermal plants. This proposed project includes a new 500 kV transmission line (approximately 70 miles) between Castle Rock, Washington and Troutdale, Oregon. This would require the construction of a new 500 KV switching station in the vicinity of Castle Rock Washington and the expansion of BPA's Troutdale Substation near Troutdale, Oregon. The project is projected to increase capacity by approximately 1100 to 1400 MW on the South of Allston path. “ 1 The purpose of the Central Ferry-Lower Monumental Project is to increase the transfer capability West of Lower Monumental that will enable BPA to provide transmission service for proposed renewable energy from the Little Goose area to Northwest load centers and to the sending end of the California Interties (COI and PDCI). This project is one of several BPA projects being developed as a result BPA’s 2010 Network Open Season (NOS) process. The Central Ferry-Lower Monumental project includes a new 38 mile 500 KV line. The project also includes a shunt 300 MVAR reactor at Central Ferry Substation and line re-terminations at Lower Monumental substation necessary to terminate the planned new 500 KV line. Chuck Matthews (360) 619-6833 (BPA) 1 This purpose of this project is to improve load service reliability to the Puget Sound area and Northern Intertie. The Puget Sound and Northern Intertie (PSANI) area transmission system is a winter peaking system that primarily consists of the interconnected systems of BPA, Puget Sound Energy (PSE), Seattle City Light (SCL), Snohomish PUD (SPUD), Tacoma Power Utilities (TPU), and British Columbia Transmission Company (BCTC), which serve Seattle, Tacoma, Olympia, and surrounding areas. The Puget Sound Area is a highly congested network due to large concentrations of load and varying local generation patterns, which are further stressed by transfer levels between the US and Canada on the Northern Intertie. Winter peak loads are typically the worst, combined with lower local generation patterns and high exports to Canada. Through a joint Columbia Grid study effort, several system fixes have been agreed to by BPA, SCL, and PSE. They include several 115kV and 230kV PSE and SCL line upgrades, a BPA RAS upgrade and a new BPA 500/230kV transformer. The PSANI Berhanu Tesema (360) 619-6819 (BPA) Page 21 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Reinforcements projects are scheduled to be completed in full by fall 2018. The Raver 500/230kV transformer addition is scheduled for completion in fall 2016. The most limiting outage for the South Puget Sound area is a common corridor N-2 Tacoma- Raver #2 and Raver-Covington #1, which results in loss of two 500/230kV banks in the area. Other N-2 common corridor outages result in a loss of two 500/230kV banks either at Tacoma, Covington, or Maple Valley substations and cause severe loading on the remaining transformer banks. Once the Raver 500/230kV transformer addition is completed, the severity of these N-2 outages will be greatly reduced, mitigating overloads, and resulting in greater reliability to load service and operational flexibility for the Southern Puget Sound Area. The project also helps to reduce the risk of curtailment or redispatch events in the Puget Sound Area for certain outage conditions. The plan of service is to install a 1300 MVA transformer at Raver substation. A new 230kV substation will be developed adjacent to the existing 500kV substation. The high side of the new transformer will terminate at Raver 500 KV. The Tacoma-Raver #1 and #2 500 KV lines are currently jumpered together and operated as double circuit 500kV for about 10 miles from Raver until it reaches Covington substation. The corridor for both circuits runs adjacent to Covington 230kV station and in the same corridor as the Raver-Covington #1 and #2 500 KV circuits. The project will reconfigure the Tacoma-Raver 500 KV lines by removing jumpers and reterminating the TacomaRaver #2 circuit into Covington 230 KV and Raver 230 KV Substations. The TacomaRaver #2 line will be renamed and operated as the Raver-Covington #3 230 KV line. The plan of service also requires reconfiguring the Covington 230 KV bus, adding a new sectionalizing breaker and 2 bus tie breakers. Schultz-Raver #3 & #4 500 Series Capacitors Project 500 PDCI Uprate Project John Day Substation – Golden Hills 200 MW (G0099-2) 200 2018/19 .5 2016 (Celilo DC Upgrade Only) .5 10/1/2013 .5 The purpose of this project is to increase transfer capability across the West of Cascades North Path and provide increased load service to the Puget Sound area. This project adds 500 kV series capacitors at Schultz Substation on the Schultz-Raver 500 kV #3 and the Schultz-Raver 500 kV #4 lines. 3800 MW The Pacific DC Intertie (PDCI) provides a direct current (DC) intertie between The Dalles Oregon, and Los Angeles, CA. The current PDCI is rated at 3100 MW. The PDCI Uprate project would increase the capacity by 700 MW from 3100 MW to 3800 MW. This project replaces the convertors at the Celilo HVDC terminal and reconductors a small section of the DC transmission line. To reach the full 3800 MW will require the southern partner (LA Department of Water and Power) will need to reinforce the AC system on the southern end, upgrade some DC line sections, and make minor changes to their terminal equipment. John Day Substation is a major 500 KV switching station east of The Dalles Oregon. It serves as the northern terminus of the California-Oregon AC Intertie (COI). It integrates the generation from the US Corp of Engineers John Day Dam. It the next major 500 KV substation west of Slatt Substation. In 2007, a 230 KV yard was added to interconnect Portland General Electric's (PGE) 400 MW Bigelow Canyon wind Berhanu Tesema (360) 619-6819 (BPA) Kyle Kohne 360-619-6839 (BPA) Chuck Matthews 360-619-6833 (BPA) Page 22 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From project. PGE sold 200 MW of their original 600 MW project to BP Alternative Energy. This remaining 200 MW is a wind generation project called Golden Hills. Shepherds Flat Wind Phase 1 (aka North Hulburt Wind) (G0118 and G0291) Phase 1 – 266 2 – 190 3 - 190 12/2011 5/1/2012 5/1/2013 .05 G0118 and G0291 are Shepherds Flat. It is being commissioned in 3 phases: Phase 1 (266 MW) energized in 12/1/2011. Phase 1 is called North Hulburt. Phase 2 (190 MW) is planned for 2012, and Phase 3 (190 MW) for 2013. The LGIA has been executed and we are planning the first synchronization for July 15, 2011. “ Montague I 202 12/2011 .05 The generation project has executed or is in the process of executing a Large Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection studies can be obtained by signing a non-disclosure agreement with BPA. “ Lower Snake Wind 341 2/2012 .05 The generation project has executed or is in the process of executing a Large Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection studies can be obtained by signing a non-disclosure agreement with BPA. “ Miller Ranch Wind 150 6/2012 .05 The generation project has executed or is in the process of executing a Large Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection studies can be obtained by signing a non-disclosure agreement with BPA. “ Golden Hills Wind 200 10/2013 .05 The generation project has executed or is in the process of executing a Large Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection studies can be obtained by signing a non-disclosure agreement with BPA. “ Morrow Flats Project 230 2015 .1 This is a new 230/115 kV substation approximately 3 miles east of BPA’s Boardman Substation connecting to the McNary-Boarddman 230-kV and the McNary-Jones Canyon 230-kV lines. This substation is needed to provide load service in the Boardman-Umatilla area. “ Montana to Washington 500 2018 .5 In 2010, Bonneville Power Administration (BPA) conducted a Network Open Season (NOS) to determine projects needed for requests for long-term firm transmission service. During the NOS process, entities requested the use of BPA's transmission system to transmit their power. “ The studies found that there was not enough available transmission capacity to accommodate all requests for long-term service from BPA's Garrison Substation in Western Montana to load centers west of the Cascades and to market hubs serving the entire Northwest power market. Wind generation facilities built and proposed in the region have greatly increased the amount of planned generation in Montana seeking load and markets in the Northwest. As a result, BPA is proposing several reinforcements on BPA's transmission system at Garrison, Hot Springs, Bell, Dworshak, and Hatwai Substations. Additionally, reconductoring is being proposed totaling 12 miles on the Dworshak-Taft No. 1 500-kilovolt (kV) line and a new series compensation substation is being proposed along the Garrison-Taft No. 1 and No. 2 500-kV lines, both of which would Page 23 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From allow BPA to accommodate the requests for transmission service in this area. These reinforcements would increase the firm east-to-west transfer capability of the West of Garrison and West of Hatwai paths by primarily increasing the series compensation in existing 500-kV lines in the area. Douglas-Rapids 230 kV Transmission Line 230 4/2014 21 Douglas County PUD is constructing a new 13-mile, 230-kV transmission line to connect its Douglas Switchyard with its Rapids Switchyard. The conductor will be 1590 ACSR/TW and is expected to have a Summer rating of 589.5 MVA, a Winter rating of 766.8 MVA, an Autumn rating of 687.9 MVA, and a Spring rating of 671.6 MVA. A new 230/115-kV transformer will be installed at Rapids Switchyard with expected ratings of 200 MVA (ONAN) 55° C, 266 MVA (ONAF) 55° C, 333 MVA (ONAF) 55° C, and 373 MVA (ONAF) 65° C. The new 230-kV circuit breakers at Douglas Switchyard and Rapids Switchyard will be rated for 3000 A of continuous current. The new 230-kV breaker disconnect switches at Douglas Switchyard will be rated for 3000 A of continuous current and the 230-kV line disconnect switches at Douglas Switchyard and Rapids Switchyard will be rated for 2000 A of continuous current. The new transmission line is planned to be in operation in April, 2014. The project is currently under construction and is tentatively scheduled for completion in April, 2014. The transmission line is complete, and the remaining work is to finish installing the transformer at Rapids Switchyard. Jerry Kyle 509-881-2234 (DCPUD) Rapids-Columbia 230-kV Transmission Line 230 4/2015 57 Douglas County PUD is constructing a new 230-kV transmission line to connect its Rapids Switchyard with BPA’s Columbia Substation. The conductor will be 1590 ACSR/TW and is expected to have a Summer rating of 438 MVA, a Winter rating of 591 MVA, and a Spring/Autumn rating of 512 MVA. The new circuit breaker at Rapids Switchyard will be rated for 3000 A of continuous current. The new line disconnect switch at Rapids Switchyard will be rated for 2000 A of continuous current. “ Columbia-Larson 230 kV line 230 2014 1.0 This project will involve in construction of a new 30-mile 2-1272 ACSR 230 kV line from Columbia to Rocky Ford, open the existing Larson-Rocky Ford 230 kV line at Rocky Ford during normal conditions, then tie the new line to the existing LarsonRocky Ford circuit, making a new Columbia-Larson 230 kV line. The purpose of this project is to provide additional transmission capacity to serve projected load growths. The project has been publicly announced and is scheduled to be in-service in early CY 2014. Ken Che (509) 754-5033 (GCPUD) King 230/138 kV Project 230/138 2012 .1 A new 230/138 kV 300 MVA transformer will be installed in the existing King 138 kV substation to accommodate approximately 135 – 150 MW of additional wind generation in the Hagerman area. The King substation will be interconnected to the 230 kV transmission system by looping in-and-out the existing Midpoint-Dram 230 kV line. Because the wind generation projects, which the King 230/138 kV project is to accommodate, have been slow in their development, the in-service date has been deferred to spring 2012. This project has no significant impact on the WECC transmission system. Mark D. Hanson 208-388-2253 (IPC) Hemingway – Boardman 500 2018 2 1 Idaho Power’s 2013 Integrated Resource Plan, a biennially-produced 20-year resource Mark D. Hanson 208-388-2253 1000 MW 3 Page 24 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transmission Project Midpoint T232 230/138 kV Transformer Addition Project 230/138 6/2020 .1 Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From plan for meeting our electric service obligation, identified Pacific Northwest generation resources as one component of the preferred resource portfolio. Requirements of Idaho Power’s wholesale transmission customers are also increasing. The existing transmission system connecting Idaho Power to the Pacific Northwest is fully subscribed during high-demand periods. To meet the need for more transmission capacity with the associated improvement in system reliability, Idaho Power plans to build a 500 kV transmission line from southern Idaho to northeast Oregon. The plan of service is to construct a 300 mile 500 kV transmission line from Hemingway station in southwestern Idaho to a new station, Grassland or Longhorn depending on final routing, near the existing Boardman Power Plant in northeastern Oregon. The Hemingway-Boardman Transmission Line Project’s proposed and alternative routes are shown in Figure 1. The Hemingway-Boardman Transmission Line Project scheduled in-service date will be no earlier than 2020. Path 14 transfer capacity ratings with the Hemingway-Boardman Transmission Project facilities are expected to increase to 2250 MW west to east (a 1050 MW increase) and a 3400 MW east to west (a 1000 MW increase). Project facilities are listed below: Hemingway-Boardman 500 kV line, 300 miles with approximately 50% series compensation (split equally at each end); the western termination will be at the Grassland switching station near the Boardman Power Plant Hemingway 500 kV Line Terminal with Shunt Reactors and Series Capacitor Grassland/Longhorn 500 kV Line Terminal with Shunt Reactors and Series Capacitor and 150 Mvar, 500 kV Shunt Capacitor Hemingway-Bowmont #2 230 kV line, 13 miles with single 1590 MCM ACSR “Lapwing” conductor Bowmont-Hubbard 230 kV line, 16 miles with single 1590 MCM ACSR “Lapwing” Conductor Bowmont, 2nd 230/138 kV 300 MVA Auto-Transformer The Hemingway-Boardman Transmission Project will conform to the NERC TPL-001-4 Standard and other corresponding regional System Performance requirements at the time, if any,. and the WECC “Overview of Policies and Procedures for Project Coordination Review, Project Rating Review, and Progress Reports.” A Hemingway-Boardman Transmission Project Comprehensive Progress Report (Phase I) was released for comment in November 2008 and was granted Phase II status in March 2009. Idaho Power began the Phase II study process in 2011; the initial kick-off project review work group meeting was held on June 22, 2011, and the second project review group meeting was held on November 15, 2011. The third project review group meeting was held on March 22, 2012. On August 10, 2012, a conference call/webinar was held to solicit comments on the initial Phase II draft report. In August 2012, Idaho Power submitted the Idaho-Northwest Up-rate, Hemingway-Boardman 500 kV Transmission Project Phase II Report to WECC and was granted Phase III status on November 29, 2012 with an Accepted Rating of 2250 MW west-to-east and 3400 MW east-to-west. (IPC) A second 230/138 kV 200 MVA transformer will be installed at the Midpoint substation due to anticipated load growth in the Magic Valley area. The scheduled/projected inservice date is June 2020. This project is intended for load service and has no “ Page 25 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From significant impact on the WECC transmission system. Midpoint West Upgrade Project 230 2015 .25 The 230 kV looped connection in and out of the Rattlesnake switching station, currently installed in the Midpoint-Boise Bench 230 kV #2 line, will be relocated to the Midpoint-Boise Bench 230 kV #1 line between DRAM and Justice. Both 230 kV lines, as well as the Midpoint-Boise Bench 230 kV #3 line, are all part of Idaho's internal Midpoint West path. In addition to the relocation, the series capacitor banks at Midpoint on the #2 and #3 lines will be replaced and increased to 70% comp each. These upgrades are being done to gain approximately 275 MW of east to west transfer capability across Midpoint West with the added benefit of approximately balancing the flows on the Midpoint-Boise Bench 230 kV #2 & #3 lines. We expect the in and out relocation for Rattlesnake to be completed in June of 2015. We expect the series capacitor bank replacements to be completed sometime in the fall of 2015. This project has no significant impact on the WECC transmission system Pearl Transmission Substation 230 5/2019 .3 Because of the addition of the Langley Gulch Generation Project in the Treasure Valley (see Langley Gulch Generation Project above) and developing the Hemingway 500/230 kV station and its associated 230 kV transmission integration into the Treasure Valley (see Hemingway-Boardman Transmission Project above), the Pearl Transmission Substation project has been deferred beyond Idayho Power’s 10-year planning horizon.. “ Midpoint T232 230/138 kV Transformer Addition Project 230 June 2020 .1 200 MVA A second 230/138 kV 200 MVA transformer will be installed at the Midpoint substation due to load growth in the Magic Valley area. The scheduled/projected in-service date is June 2020. This project has no significant impact on the WECC transmission system. “ Lucky Corridor Transmission Project 230/115 2016 2 850 MW 0 0 0 0 0 Lucky Corridor, LLC provided an initial progress report on December 19, 2012. Lucky Corridor, LLC is developing a transmission project to deliver renewable and gas generation from northeastern New Mexico to markets in the west. The Lucky Corridor Project is designed as a 230 KV upgrade to an existing 93 mile 115 KV transmission line between Gladstone and Taos substations. The new line will use the existing 115 KV rights of way and will be constructed as a double circuit 230 kV transmission line. Also included in the Project are upgrades to the Taos to Ojo 345 KV line and required lower voltage lines. Lynn Chapman Greene (303) 681-3073 Lucky Corridor 500 kV Upgrade Project 500 2018 10 2 3000 3 16 0 0 0 0 0 500 kV Upgrade: Series compensation system will be increased as needed to achieve new capacity. A Supplemental Progress report is attached showing new capacity as 3000 MW. The earliest operation date is 2018 John Leland 406-497-3383 (NWMT) Path 18 Upgrade 230 2014 2 383 MW 3 230 On Hold 2 WKN Wind Project 396 Path 18 Upgrade: Path 18, Montana to Idaho, will be upgraded by 46 MW. The new capacity on this 230 kV line will be 383 MW. A Supplemental Progress report is attached. The earliest operation date is 2014. “ WKN: The Feasibility, System Impact, and Facility Studies have been completed. An LGIA was signed on December 29, 2010. A Supplemental ″ Page 26 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Progress Report is attached for this 396 MW wind project. Project is suspended per customer's request. Jawbone Wind Project 460 230 On Hold 2 Mountain States Transmission Intertie Project 500 2013 3 TOT 4A Voltage Support Project 230 2016 1.1 Wallula to McNary 230 kV (#2) Transmission Line (December 2017) 230 12/2017 1 Jawbone Wind: The Feasibility, System Impact, and Facility Studies have been completed. An LGIA was signed on November 5, 2012. A Supplemental Progress Report is attached for this 460 MW wind project. Project is suspended per customer's request. 1500 2 2 The Regional Planning Project Review for this project was begun on 5/17/07. The proposed project consists of a new 500 kV line between southwestern Montana and southeastern Idaho. The main purposes for the project will be to meet requests for transmission service from customers and relieve constraints on the high-voltage transmission system in the region. The Regional Planning Project Review Report for this project was distributed for review on 2/14/08 with a review deadline of 3/14/08. On 4/23/08, the MSTI project successfully completed Regional Planning. Currently this project is in Phase II of the WECC 3-Phase Rating Process. “ The following facilities have been identified for Wyoming voltage support: Atlantic City 230 kV, 15 MVAr Capacitor (In-service: October 2010) Riverton 230 kV, 30 MVAr Capacitor (In-service: August 2010) Midwest 230 kV, 30 MVAr Capacitor (In-service: October 2010) Dynamic voltage control in the Miners Area has been superseded by Standpipe 230 KV Synchronous Condenser project-Projected in-service date for (2016) Craig Quist 801-220-4264 (PAC) The Wallula to McNary 230 kV #2 line would be a single circuit transmission line with line terminals at Wallula and McNary substations. “ Phase 2 studies are being performed; when complete they will be reviewed by the project review group. This project has impacts to other regional facilities most notably BPA as the project has a terminal at BPA’s McNary Substation. Phase 2 studies are being performed and when complete will be reviewed by the project review group. Whetstone 230/115 kV Substation Current Creek Union Gap 230/115 kV Transformer Addition Vantage-Pomona Heights 230 kV Line 230/115 2015 .1 Construct new 230 to 115 kV in the White City Oregon vicinity with a 250 MVA transformer. This substation will tap PacifiCorp’s existing 230 kV line between Meridian and Grants Pass Substations. The project is intended to provide load service redundancy. 2016 .05 Planned new generation. 230/115 2016 .1 230 12/2016 1 550 250 MVA “ This project will construct a third 250 MVA transformer at Union Gap. “ This project will construct a new 230kV line between the Vantage and Pomona Heights 230kV buses in Washington State. “ Page 27 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gateway Central Transmission Project Gateway West Transmission Project Gen MW Transfer Capability CONTENTS AND REMARKS Power Transient Tables Flow Stability Transmission kV Date No. of pages 500/345/138 2017 1.2 This project consists of the following: (1) double-circuit 345 kV transmission line stretching approximately 90 miles from the Populus Substation to be built near Downey, ID, to the existing Ben Lomond Substation in Box Elder County, UT, (2) new double-circuit 345 kV transmission line alongside existing high-voltage lines from the Ben Lomond Substation to the Terminal Substation near the Salt Lake City airport, a distance of approximately 46 miles, (3) a new high-voltage transmission line and two future substations in UT which will originate at a substation to be built near the existing Mona Substation outside Mona in Juab County, and run north to another future substation. The line will then split and connect to Oquirrh Substation in West Jordan and to Terminal Substation in Salt Lake City, and (4) a new line between the Oquirrh Substation in West Jordan north to Terminal Substation. This section of new transmission will link together other new transmission sections: Mona to Oquirrh and Populus to Terminal to complete the Gateway Central portion of the Energy Gateway Tramsmission Expansion Project. “ 500/230 2020-2024 6 The Gateway West project was jointly announced by Idaho Power and PacifiCorp (Rocky Mountain Power) in May 2007, to build and operate approximately 900 miles of new high-voltage transmission lines between the Windstar substation near Glenrock, Wyoming and the Hemingway substation near Melba, Idaho. The Gateway West – Stage 1 project will include approximately 150 miles of 230 kilovolt (kV) lines in Wyoming and approximately 800 miles of 500 kV lines in Wyoming and Idaho. Gateway West– Stage 2 transmission facilities primarily consist of a second set of 500 kV circuits from southern Wyoming to western Idaho. PacifiCorp reported in the 2011 Annual Progress Report submission that the third party requests and financial commitments that are necessary to support the Energy Gateway – Stage 2 facilities have not materialized. Therefore, PacifiCorp indicated that it would continue to pursue WECC path ratings for Stage 1 of Energy Gateway only at that time, and will not further pursue ratings for Stage 2 facilities. This Energy Gateway Project status update was also reported to TSS at the April 20-22, 2011, meeting in Westminster, Co. For Gateway West – Stage 1 transmission paths located west of Populus [specifically Borah West and Midpoint West], Idaho Power was the project sponsor for each of the path ratings studied; additionally for Gateway West transmission paths located east of Populus [specifically TOT 4A, Aeolus West, Path C and Bridger/Anticline West], PacifiCorp was the project sponsor for the path ratings studied. At the completion of the Phase 2 path rating process, TOT 4A transmission path was granted Phase 3 status on December 13, 2010; Aeolus West, Bridger/Anticline West and Path C transmission paths were granted Phase 3 status on January 5, 2011; and Borah West and Midpoint West transmission paths were granted Phase 3 status on July 21, 2011. Both the Gateway West and Gateway South siting and permitting requirements are currently being reviewed separately under the National Environmental Policy Act (NEPA) process. Future changes to the Energy Gateway Project facilities and configuration may be influenced by the NEPA process and permitting requirements until this process concludes, which today expected to conclude for Gateway West in “ Phase Post Transient Stability One Lines Maps Request Copy of Report From Page 28 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From 2013 and for Gateway South in 2015. At the conclusion of the NEPA process, specific path rating performance issues relative to any necessary changes in Energy Gateway Project facilities and configuration will be addressed with affected Project Review Groups – rather than approach the group with “piece wise” changes, at the time each change becomes known throughout the NEPA process. Based on the agreement between PacifiCorp and Idaho Power, executed in early 2012, PacifiCorp will assume responsibility for sponsoring all Gateway West transmission facilities through the NEPA process and through the project construction agreement phase. Gateway South 500 kV Project 500 2015-2022 4 Syracuse –Install 345/138 kV #2 Transformer 345/138 5/2021 Mid Valley SubstationReplace 345-138kV, 450 MVA with 700 MVA Transformers 345/138 Black Rock 230/69 kV Substation (2013) 230/69 Carbon Plant Decommissioning (2015) 2 1 The Gateway South – Stage 1 Transmission Project as proposed by PacifiCorp includes a 500 kV transmission line from the proposed Aeolus substation in southeast Wyoming (constructed as part of the Gateway West Project) to the Clover substation in central Utah, and a 345 kV transmission project from the Sigurd substation near Richfield, Utah to the Red Butte substation in southwestern Utah. PacifiCorp is leading the planning effort and managing the WECC rating process for the project. The Gateway South project entered Phase 2 in January 2009. Of the transmission paths associated with the project, the Aeolus South path was granted Phase 3 status on December 16, 2010 while the TOT 2B/2C Paths should be granted Phase 3 status in the first quarter of 2011. PacifiCorp is proposing this transmission project because of native load growth and the need to deliver renewable resources from Wyoming to PacifiCorp retail load centers. PacifiCorp forecasts that its load on the Wasatch Front of Utah will double in the next 20 years. Additionally, PacifiCorp has an independent obligation, pursuant to its Open Access Transmission Tariff, to plan for and expand its transmission system based upon the needs of its native load and network customers along with eligible customers that agree to expand the transmission system. “ .1 Install a 345-138 kV transformer (T#6) including (1) 345 kV circuit breaker and (1) 138 kV circuit breaker at Syracuse substation. “ 2020 .1 Replace two 345-138kV 450MVA transformers at Mid Valley substation with 700 MVA units. “ In Service 1 This project consists of looping in and out of Pavant-Gonder 230 kV line and the DeltaGraymont 69 kV line and installing a 75 MVA -230/69 kV transformer at Delta. “ 4/15/2015 1 The Carbon Plant decommissioning will require the addition of the following facilities: 15/+85 MVAR 138 kV static VAr system (SVS), two 138 kV 15 MVAR capacitor banks with associated breakers at the Mathington substation. The addition of a phase shifting transformer (PST) at the Upalco substation. Relocation of the Spanish Fork 138 kV series line reactors to the Upalco substation. “ Page 29 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Huntington-Mona/ 345 kV Line Series Reactor at Mona/Clover Transmission kV 345 Date No. of pages 2014 1 Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Install an 18 ohm series reactor in the Mona- Huntington 345 kV line at Mona to increase transfer capability across the “North of Sigurd/Huntington” transmission path. “ A study was conducted to determine the optimum reactor size. It was determined that an 18 ohm series reactor provided the most optionality in future resource location (Huntington vs. Sigurd), while increasing the North of Huntington/Sigurd flow limits. This project will support an increase in south to north transfers from southern to northern Utah. Snow Goose Project 500/230 2016 1 New 500/230kV substation tapping PacifiCorp’s Captain Jack to Klamath Co-Gen 500 kV line. The 230kV line construction will include looping the existing Klamath Falls to Malin 230kV line into the new substation. The project is only connected to PacifiCorp facilities and is intended to provide load service redundancy “ Lakeside II Transmission Network Upgrades (2014) 345 6/1/2014 1 Transmission of energy from the generation facility to beyond Steel Mill substation requires the installation of two new 345kV breakers and looping in of the Camp Williams – Emery 345kV line at Spanish Fork substation. Also required is a reconductoring of the 10 mile Spanish Fork – Tanner 138kV line and communication fiber to Hale substation “ Pinto #3 Phase Shifting Transformer Addition (2015) 345 12/2015 1 400 MVA Install the third 345 kV /400 MVA, phase shifting transformer in parallel with the two existing phase shifting transformers in a new bay at the Pinto substation. Improvements include a new transformer pad, extension of bus work, a new 345kV breaker, protection and control equipment and other new equipment. “ Standpipe - Construct New 230kV Substation (2016) 230 2016 1 60 MVAr Construct a new 230 kV substation called Standpipe. The new substation will be located near Miners substation, and will intercept the existing Platte-Miners-Standpipe 230 kV line, resulting in the Platte-Standpipe-Freezeout 230kV line. Miners will be fed radially from Standpipe following completion of the project. A new or relocated synchronous condenser with a minimum capability of +60/-35 MVAr will be installed at Standpipe to provide dynamic reactive support in the region. Additional project scope to improve voltage stability and reliability for customers on the south central Wyoming 230 kV transmission system includes the relocation of an existing 31.7 MVAr shunt reactor from Platte to Standpipe substation, installation of a 25 MVAr capacitor bank at Latham substation, implementation of coordinated shunt reactive device controls at Latham, Platte, Standpipe, Miners, and Foote Creek. The project will install a special protection scheme to trip local area wind generation for contingency conditions that result in low voltage in the Spence area of the Wyoming 230 kV system. Other system improvements to be completed under the project include reconfiguration of the Platte Substation 230 kV bus, relocation of the Standpipe line termination at Platte, installation of a new 230 kV circuit breaker at Platte, reconfiguration of the Latham 230 kV bus to accommodate the new shunt capacitor, and communications upgrades to facilitate relay upgrades and the special protection scheme. “ 2014-2020 1 PacifiCorp East and West Future Generation Projects 1027 Project Queue Number/Name Page 30 of 91 Location (County, Status “ Generation Capacity Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From State) Casper Substation-Install 230/115 MVA transformer 230/115 St. George SubstationInstall 345kV/138kV transformer & expand yard Lakeside II Utah, UT Under construction 2014 681 MW Carbon Carbon, UT 2015 Retirement -67 MW Carbon Carbon, UT 2015 Retirement -105 MW 375 Carbon, WY 2020 230 MW 398-B Bonneville, ID Suspended 288 MW 2015 Add a second 230-115 kV transformer at Casper substation, including expanding the 115kV bus, installing four new breakers and reconnecting the existing WAPA Casper 115kV transmission line into the new line position. 2020 This project includes three related segments necessary to provide anticipated growing energy demands in Southwest Utah and to maintain the Company’s compliance with NERC and WECC reliability standards. The three segments are as follows: – Reterminate Harry Allen 345kV Line & Reactor, and Add a 345kV Breaker. “ St. George Substation; Install a 700 MVA 345/138 Transformer, Line Termination and Two Breakers (one each @ 345kV and 138kV). Table Mountain 500/230kV substation 500/230 2019 1 New 500/230 kV Substation tapping PacifiCorp’s Meridian to Dixonville 500 kV Line, tapping the existing Meridian-Grants Pass 230 kV line and adding a new 230 kV transmission line from the new substation to the existing Grants Pass 230 kV Substation. The project is only connected to PacifiCorp facilities and is intended to provide load service redundancy. “ Troutdale Substation, Add 3- 230 kV circuit breakers 230 2016 1 This project will install 3-230 kV circuit breakers at Troutdale substation, two on the lines to PGE Gresham and Linneman Substations, and one between the two Troutdale substation busses. “ 2012-2015 3 Planned Generation Interconnection Projects 20-100 Project Queue Location Status Generation “ Type Page 31 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project (PACE/PACW) – Waiver Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability Number/Name One Lines Request Copy of Report From Maps Capacity 154 Bonneville, ID 267-A Sweetwater, WY 267-B 2012 19.8 MW Wind 2019 22 MW Wind Sweetwater, WY n/a 22 MW Wind 267-C Sweetwater, WY n/a 22 MW Wind 267-D Sweetwater, WY n/a 22 MW Wind 290-A Sweetwater, WY n/a 100.8 MW Wind 290-B Sweetwater, WY n/a 100.8 MW Wind 290-C Sweetwater, WY n/a 50.4 MW 313 Beaver, UT 2013 65 MW Geothermal 323-A Power, ID 2011 21.6 Wind 323-B Power, ID 2011 21.6 MW Wind 335 Converse, WY 49.6 MW Wind 367 Iron, UT n/a 172 MW Solar 384 San Juan, UT n/a 60 MW Wind 415 Beaver, UT n/a 11 MW Thermal 420 San Juan, UT n/a 140 MW Wind 2013 Wind Page 32 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Request Copy of Report From Maps 432 Salt Lake, UT n/a 6.3 MW Other 437 Franklin, ID n/a 0.5 MW Hydro 442 Madison, ID n/a 5.6 MW 450 Millard, ID n/a 50 MW Solar 454 Iron, UT n/a 3 MW Solar 455 Iron, UT n/a 3 MW Solar 457 Beaver, UT n/a 2.1 MW Solar 459 Beaver, UT n/a 230 Klamath, OR 3 Mw Natural Gas Solar 2014 14 MW Geothermal 237-B Skamania, WA suspende d 25 MW Hydro 237-C Skamania, WA suspende d 25 MW Hydro 276 Umatilla, OR 2015 98.9 MW Wind 373 Klamath, OR 2012 5 MW Solar 389-B Lake, OR n/a 5 MW Solar 393 Lake, OR n/a 27 MW Geothermal 422 Yakima, WA n/a 5 MW Solar 430 Klamath, OR n/a 12 MW Geothermal 431 Siskiyou, CA n/a 12 MW Geothermal Page 33 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Horizon Phase II Project 230/115 6/1/2018 0.1 The Horizon Phase II Project mitigates potential overloads to the Horizon 230/115 kV transformer for base case and single and double contingencies during peak summer loading conditions. In addition, this project mitigates potential overloads on the local area 115 kV system for double contingencies during peak summer loading conditions. PGE plans to build out the Horizon substation breaker-andonehalf bus configuration and install a second bulk power transformer at Horizon substation. The installation of this transformer dictates the need to replace seventeen 115 kV circuit breakers at Sunset substation to mitigate fault duty concerns; a second 115 kV capacitor bank will also be installed at Sunset substation to provide voltage support. To provide a second source to Horizon substation, PGE will construct a new 4.4 mile 230 kV line segment between Horizon substation and Springville Junction. This line segment will tie into the existing St Marys-Trojan 230 kV circuit, creating a Horizon-St Marys-Trojan 230 kV circuit. The bulk power transformer will be energized by June, 2017; and the new 230 kV line segment will be energized by June, 2018. Philip Augustin 503-464-7783 (PGE) Pearl-Sherwood 230 kV retermination 230 6/2019 0.1 PGE and BPA plan to re-terminate the Pearl-Sherwood 230 kV circuit (paralleled Jefferson TW) into separate breaker positions at the Pearl and Sherwood substations. In addition, this project will divide the Pearl-Sherwood section of the three-terminal McLoughlin-Pearl-Sherwood 230 kV circuit (currently paralleled between Pearl and Sherwood) into separate breaker positions at the Pearl and Sherwood substations. This will require four new 230 kV breakers, two located at BPA’s Pearl Substation and two at PGE’s Sherwood Substation. When this project is complete, there will be three Pearl-Sherwood 230 kV circuits and a McLoughlin-Pearl-Sherwood 230 kV circuit. ″ Blue Lake-Gresham 230 kV Line 230 6/2019 0.1 The Blue Lake/Gresham 230 kV Project mitigates potential overloads to the Gresham-Troutdale BPA 230 kV circuit, the Linneman-Troutdale BPA 230 kV circuit, and the Blue Lake 230/115 kV transformer for double contingencies during peak summer or winter loading conditions in the Near Term Planning Horizon. PGE plans to construct a six mile transmission line from Blue Lake Substation (Troutdale, Oregon) to Gresham Substation (Gresham, Oregon). In addition, PGE will rebuild the existing 1.5 mile Blue Lake-Troutdale 230 kV circuit tower line to accommodate the new Blue Lake-Troutdale #2 230 kV circuit. This project requires the expansion of the 230 kV yard at Blue Lake substation to a six position ring bus and the addition of new breaker positions at Gresham substation and Troutdale substation. ″ Trojan-Horizon 230 kV line 230 1/2015 .3 PGE proposes to construct approximately 40 miles of new 230 kV transmission line. The project starts from an existing PGE substation adjacent to the former Trojan plant near Rainier, OR to the new proposed PGE Horizon Substation in Hillsboro, OR. PGE will utilize 28 miles of currently unused right-of-way adjacent to the existing 230 kV lines from Trojan to the Portland area. In addition to the new transmission line, the Horizon Substation will be expanded to terminate the new 230 kV line as well as the installation of a second 230/115 kV, 320 MVA auto-transformer to connect to the adjacent 115 kV PGE Sunset Substation. Also, 2.7 miles of the Sunset-Orenco 115 kV line will need to be reconductored with a 795 ACSS conductor. “ Cascade Crossing 500 kV 500 Canceled .7 PGE proposes to construct approximately 210 miles of new 500 kV transmission line. ″ 2 Page 34 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Project Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From The project starts at PGE’s Coyote Springs generation plant located in the town of Boardman, OR, and ultimately terminates with the installation of a new 500/230 kV transformer bank at PGE’s Bethel Substation located in Salem, OR. The Boardman and Coyote Springs substations will be expanded to accommodate the project. PGE will need to acquire approximately 30 miles of new ROW for the Boardman to Coyote Springs 500 kV line. After the Boardman substation the project will connect to new wind resources being developed in Gilliam and Wasco counties in Oregon. The project will parallel existing utility lines whenever possible by acquiring additional ROW for approximately 180 miles along the route into Salem, where the line will terminate at an expanded Bethel substation. On June 3, 2013, Portland General Electric suspended permitting and development of the proposed Cascade Crossing Transmission Project. Changing market conditions have created opportunities to explore lower-cost alternatives for customers and provide the needed transmission capacity for PGE with reduced environmental impacts. At this time, PGE is requesting that the “Cascade Crossing Project” be removed from the WECC Path Rating Process; PGE will no longer represent the Project in WECC planning cases. McLoughlin 230 kV Bus Sectionalizing Breaker 6/2012 .1 PGE plans to operate the 230 kV bus sectionalizing breaker at the McLoughlin substation in Oregon City Oregon in the normally open position beginning in summer 2012. This operational procedure is different from past normal system operation. 6/2015 .1 Port Westward Unit 2 will use reciprocating engines to provide 225 megawatts of flexible peaking capacity to react to spikes in power demand and changes in power output at renewable energy generating facilities. The plant will be located adjacent to PGE’s existing natural gas-fired plants, Beaver and Port Westward, located near Clatskanie, Oregon. This project requires the reconductoring of 8 miles of the Port Westward-Trojan #1 230 kV circuit generator lead. 115 2014 .1 The project involves looping Clallam County’s 115 kV transmission line serving the Port Townsend Mill through PSE’s Irondale substation. The project is intended to provide backup transmission to Jefferson County. This project will not occur under PSE’s jurisdiction if Jefferson County’s municipalization of PSE’s energy delivery system becomes effective in 2013. Pierce County Transformer Addition and Line Reroutes 230/115 2016 .1 The project is to install a 230-115 kV transformer at Alderton Substation and build 8 miles of 230 kV transmission line from White River Substation to Alderton Substation, as well as re-routing 115 kV lines. PSE requested and received a waiver of significant transmission project status for this project in 2013. The project is intended to provide additional capacity to serve the projected load growth in Pierce County and surrounding areas. It has no impact to the WECC or any neighboring electric systems. ″ Starwood-Tideflats 115/110 kV Transformer Removal 115/110 In-Service .1 With Tacoma Power increasing its sub-transmission voltage schedule from 110 kV to 115 kV in 2013, the existing ‘step down’ Starwood transformer was no longer ″ Port Westward II generation Jefferson County 115 kV Upgrade Phase II 230 225 ″ Peter Jones 425-462-3171 (PSEI) Page 35 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From necessary. A bypass of the existing bank was finished in the summer of 2013 to coincide with the timing of Tacoma Power’s voltage schedule increase. This project was a combined engineering effort between PSE and Tacoma Power; it had no impact to the WECC or any additional neighboring electric systems. Thurston County Transformer Addition 230/115 Tono Transformer Improvements Eastside 230 kV Transformer Addition and Line 230/115 2014 .1 2014 .1 2018+ .75 546 MVA The project is to install a 230-115 kV transformer at St. Clair Substation and build a 5mile 230 kV transmission loop between St. Clair and the existing BPA Olympia – S. Tacoma 230 kV line. PSE requests a waiver of significant transmission project status for this project. The project is intended to provide additional capacity to serve the projected load growth in Thurston County and surrounding areas. It has no impact to the WECC or any neighboring electric systems. “ This project will involve replacement of limiting current transformers at the Tono bank. This improvement will increase capacity from the existing limit of 398 MVA up to 546 MVA. The project is intended to increase reliability for serving approximately half of the existing load in Thurston County. It has no impact to the WECC or any neighboring electric systems. “ This project had been titled “Lakeside Substation 230 kV Transformer Addition” in progress reports prior to 2013. The project will involve installation of a 230-115 kV transformer at an existing or future PSE Substation. This project includes new construction of 230 kV lines or rebuilding existing 115 kV lines, energizing at 230 kV to provide a source to the new transformer and adding transmission capacity. Installing this transformer will address NERC planning criteria and provide additional capacity to serve the projected load growth in north central King County and surrounding areas. The attached document, ‘Eastside Transformer Project.pdf’, shows the possible locations and associated transmission routes. ColumbiaGrid is a Subregional Planning Group in the Pacific Northwest and has open participation in its planning meetings and the Puget Sound Area Study Team (PSAST). This project has been developed by and has achieved consensus via the ColumbiaGrid PSAST, which included all the transmission owners that could be impacted by this project. The “Eastside 230 kV Transformer Addition and Line Rebuilds” project began to be studied by the PSAST in mid-2009, and was in PSE’s Annual Progress Report last year. The most recent report is entitled “Updated Recommended Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers”, June 17, 2011. The report recommends this project and four other transmission improvements, and is available from ColumbiaGrid www.columbiagrid.org. The requirements of project coordination review for this project have been met through the ColumbiaGrid acting as a Subregional Planning Group. The attached document, ‘WECC Comprehensive Project Coordination Review Letter_PSAST 2-21- 13.pdf’, describes the coordinated ColumbiaGrid study efforts. The energization date for the Eastside 230kV project has been pushed out since this review letter was written. “ Page 36 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Date 230/115 2018+ .1 Sea Breeze Pacific Regional Transmission System 500 10/1/2006 22 600 2 1 Two new 500 kV transmission lines between Vancouver Island (BCTC’s Pike substation) and the Olympic Peninsula (BPA’s Port Angeles and Fairmount 230 kV substations). E. John Tompkins Sea Breeze Pacific RTS (860) 747-0497 Sea Breeze Pacific – West Coast Cable Project 500 2010 3 1600-3200 1 1 500 kV DC bi-pole transmission interconnection between the Alston Substation in Alston, Oregon and one or more substations in the San Francisco, CA Bay area “ Sea Breeze Pacific – Juan de Fuca Cable Project (jdF) +/- 150 kV DC Q4/2014 1 550 MW 2 +/- 150 kV 550 MW HVDC Light transmission cable connecting the Olympic Peninsula of WA State (BPA) with Vancouver Island in British Columbia (BCTC). The Juan de Fuca Cable Project will run under the Strait of Juan de Fuca, connecting the Bonneville Power Administration’s Port Angeles substation in Port Angeles, Washington to the existing BC Hydro Pike substation in Greater Victoria, British Columbia. Associated facilities include converter stations adjacent to the existing substations. Sara Van Mulligen (604) 689-2991 Southwest Intertie Transmission Project (SWIP) 500 2014 .3 This project is considered as Phase II to ON Line Project. Install 500-kV 275 mile long Line from Idaho Power’s Midpoint to the proposed Robinson Summit Substation located 20 miles west of Ely, Nevada. Install 70% series compensation (for 245 mile line impedance) equipment on this line as follows: 35% at Thousand Springs located 126 miles from Midpoint and 35% at Robinson. Install 2×600 MVA 345/345 kV Phase Shifting Transformers (PST) at Robinson Summit: one on Falcon and another – on Gonder 345 kV line terminals respectively. Install 70% series compensation on Robinson – Harry Allen 500 kV line, 35 % at each end. NVE and LS Power are in a process of performing SSR studies to identify possible adverse effects on the near-by generators. As designated in the Transmission Use and Capacity Exchange Agreement (TUA) signed on 8/20/2010 between NVE and Great Basin Transmission, LLC (GBT), SWIP will be a jointly owned project by the parties. Edi von Engeln NV Energy North (775) 834-4456 Southern Nevada Intertie Transmission Project (SNIP) 500 2014 .2 This project is considered as a part of SWIP-South Project. Construct 500-kV 60 mile long line from NVE’s Harry Allen Substation to Southern California Edison’s Eldorado Substation. Install 70% series compensation at Harry Allen. NVE and GBT are in a process of performing SSR studies to identify possible adverse effects on the near-by generators. As designated in the Transmission Use and Capacity Exchange Agreement (TUA) signed on 8/20/2010 between NVE and Great Basin Transmission, LLC (GBT), the SNIP will be a jointly owned project by the parties. The proposed inservice date is, 2014. “ West Kitsap Transmission Project, Phase II Transmission kV Transfer Capability CONTENTS AND REMARKS Power Transient Tables Flow Stability No. of pages Name of Project Gen MW Phase Post Transient Stability One Lines Maps Request Copy of Report From “ The project is to install a 230-115 kV transformer at Foss Corner Substation, and build a 230 kV line from Foss Corner to a future line bay position in the BPA Kitsap 230 kV Substation. PSE requests a waiver of significant transmission project status for this project. The project is intended to provide additional capacity to serve the projected load growth in Kitsap County and surrounding areas. It has no impact to the WECC or any neighboring electric systems. Page 37 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Date 345/120 6/2018 .1 This is a new substation with a projected in-service date of June, 2018. This project is postponed indefinitely. “ Fallon 230 kV Source 230 6/2014 .3 Install a new 230 kV line From Pony Express Switching Station (Enel) to a new 230/60 kV substation (approximately 1/2 mile South of Fallon) and build a series of substations and switching stations (Pony Express, Bunejug, and Macari) to provide new source, via a 25 mile 230 kV line, to the City of Fallon. The projected in service date for this project is June 2014. The scope of this project has been changed due to a reduction in load growth in Fallon area, the termination of one LGIA and the reduction in a second LGIA have also contributed to the reduction in scope of this project. The project will now likely to be a 10 mile 230 kV generator lead line heading southward from the generator interconnect, company BO, with a reduced LGIA to the Pony Express Switching Station. The Pony Express switching station will be constructed at an existing generator interconnection site (Enel) and then connects to NV Energy’s Northern 230 kV system about five miles further south. No connection will be made from into Fallon from interconnection BO switching station. ″ One Nevada Transmission Intertie Project (ON Line) (previously known as Ely Energy Center and associated Robinson Summit – Harry Allen 500 kV Transmission Project) 500 Q1/2013 .3 Constructing 500-kV 236 mile long line from the proposed Robinson Summit Substation located 20 miles west of Ely, Nevada to the existing Harry Allen Substation located northeast of Las Vegas, Nevada. Fold existing Falcon – Gonder 345 kV line into Robinson Summit Substation and connect 345 kV and 500 kV buses through 2×525 MVA 345/500 kV autotransformers. Install 70% series compensation equipment on Falcon – Robinson 345 kV line, 35 % at each end. NV Energy has completed SubSynchronous Resonance (SSR) studies identifying adverse effects and developed mitigations for NV Energy’s assets. As designated in the Transmission Use and Capacity Exchange Agreement (TUA) signed on 8/20/2010 between NV Energy and Great Basin Transmission, LLC (GBT), the ON Line is a jointly owned by NV Energy and GBT. At this time, the latest updated in-service date is Q1, 2013.. ″ Bothell – SnoKing 230 kV lines 230 2017 .25 The project will re-conductor the double circuit Bothell-SnoKing 230KV lines with high temperature conductor. The purpose of this re-conductoring is to improve South-toNorth transfer capability between the Northwest and British Columbia. Seattle City Light and Bonneville Power Administration will re-conductor their own section of the double circuit. The estimate in-service date for project will be 2017. Desmond Chan 206-615-0654 (SCL) Delridge-Duwamish 230 kV line 230 2017 .25 This project will re-conductor the Delridge-Duwamish 230KV line with high temperature conductor. The purpose of this re-conductoring is to improve South-to-North transfer capability between the Northwest and British Columbia. The estimate in-service date for project will be 2017. “ 230/115 12/2016 .2 1. SNPD will construct a new 115 kV switchyard at Beverly Park substation, using a breaker‐and‐a‐half scheme to replace the existing single bus configuration. 2. SNPD will install ONE new 230/115 kV transformer for the Beverly Park substation. This transformer will function as a backup transformer for loss of two out of three 230/115 kV transformers at BPA Snohomish substation. 3. BPA will perform work at BPA Snohomish substation to provide a 230 kV source to Long T. Duong (425) 783-4305 (SNPD) Blackhawk 345/120 kV Substation (was Emma) Beverly Park 230/115kV Transformer Transmission kV Transfer Capability CONTENTS AND REMARKS Power Transient Tables Flow Stability No. of pages Name of Project Gen MW 1000 300 MVA Phase 2 Post Transient Stability One Lines Maps Request Copy of Report From Page 38 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From Beverly Park substation. BPA owns the new 230 kV feed from BPA Snohomish to Beverly Park substation. 230 kV Re-Termination Project 230 7/2013 .1 The purpose of this 230 kV Re-termination Project is to improve Tacoma Power’s system reliability and operational flexibility. The first part of this project to re-terminate TPWR’s Tacoma-Cowlitz #2 and Cowlitz-Southwest #3 230 kV lines to form the new Tacoma-Southwest 230 kV line was completed and placed in service in August 2012. The second part of the project, which involves the re-termination of BPA’s “South Tacoma- Cowlitz #1” 230 kV line from TPWR’s Cowlitz 230 kV bus to TPWR’s “Southwest #4” 230 kV line to form the new “South Tacoma-Southwest” 230 kV line was postponed and is now anticipated to be completed and released to operations in July 2013. Francis Tong 253-502-8262 (TPWR) Southwest 230 kV Ring Bus Conversion 230 9/2014 1 This project involves converting the existing main and auxiliary bus configuration at Tacoma Power's Southwest Substltion to a more reliable and efficient ring bus configuration. The number of terminals wiU remain at four with two for the incoming 230 kV lines and two for the 230/115 kV transformers. This project not only improves system reliability and operational1lexibility, it also prevents a single element from causing a total 230 kV bus outage at TPWR's Southwest Substation. Canyon Substation / Switching Station +/- 500 kV DC 2017-19 1 2000 MW 2 1 NorthernLights is a 500 kV, direct current, 2000 MW transmission line from southeastern Alberta, Canada to the Buckley station in northern Oregon. The Regional Planning process was completed in February 2008 and the Phase 2 status was achieved in March 2009. Further activity on the project is awaiting decisions within Alberta of the need for increased interconnection capacity to other markets. The project cost is $2 billion with an ISD of 2017 to 2019. Bill Hosie 403-920-7338 (TCP) Zephyr Project +/- 500 kV DC 2016 .1 3000 MW 1 Zephyr is a 500 kV, direct current, 3000 MW transmission line from south-eastern Wyoming to the Eldorado Valley in southern Nevada. The Zephyr development plan includes a potential 750 MW intermediate converter station near the Borah substation in south-eastern Idaho. The Regional Planning process was complete in November 2009. In 2010, TransCanada concluded a successful Open Season with three substantial creditworthy Wyoming wind developers (Pathfinder Wind, BP Wind and Horizon Wind) executing precedent agreements for the entire 3000 MW of Zephyr capacity. TransCanada and its customers are establishing market support prior to moving forward with full scale siting and permitting activities. The project cost is $3 billion with an ISD of 2016. “ Chinook Project +/- 500 kV DC 2017 .1 3000 MW 1 Chinook is a 500 kV, direct current, 3000 MW transmission line from south-central Montana to the Eldorado Valley in southern Nevada with a potential future 750 MW intermediate converter station near the Borah substation in south-eastern Idaho. The Regional Planning process was complete in November 2009. TransCanada conducted an Open Season for the Chinook project that closed on December 16, 2010. Bids totaling 1500 MW were received; however they were not accepted as the amount was insufficient to justify allocating capacity at this time. TransCanada may decide to hold a new open season process, if regulatory uncertainties get resolved and “ Page 39 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From if Montana energy project developers express sufficient interest in a new open season. It is not unusual for projects of this scale to test the market a number of times. The fact that a project is not successful in one open season does not mean that a project is dead and, indeed, other transmission projects in the west have had multiple open seasons. The project cost is $3 billion with an ISD of 2017. Havre to Rainbow 161kV Rebuild / Upgrade 161 2022 .75 This project is on-hold status due to high priority oil load growth. Western’s 103 mile Havre – Verona – Rainbow 161kV transmission line was constructed and energized in 1935. It electrically parallels NorthWestern Energy’s (NWE’s) Havre – Rainbow 161kV circuit. These two circuits maintain separate rights-of-ways with two crossings. Western intends to rebuild its circuit in segments, at 230kV specification. Each segment is anticipated to be complete and re-energized in approximately one month. The existing right-of-way is inadequate and will be expanded in most areas and rerouted in others. An Environmental Assessment (EA) is complete for this project and has been issued for final publication. The first 30 mile segment between Havre and Verona is complete, along with 1 mile at the Rainbow / Great Falls end for retermination into NorthWestern Energy’s (NWE's) Great Falls Substation in conjunction with Project 2) described below. In 2011, 14 miles of reroute and reconstruction began in the Loma, MT area and was approximately one-third complete when crews were redispatched due to storm damage in Eastern Montana / Western North Dakota (East Grid WAUE BA). Due to both storm damage and dramatic oil exploration load growth in the Eastern Montana / Western North Dakota area, this project has been placed onhold for approximately 5 years, with approximately 5 years of construction remaining prior to completion. Therefore, target completion is estimated to be 2022. Once the project resumes, construction will again continue during non-peak loading periods only. Upon completion of each segment, the line will continue to be energized at 161kV until such time that conversion to 230kV is required. Additional system impact study analyses will be required with stakeholder approval prior to the 230kV voltage conversion. No interruption of customer service during construction is anticipated with this project. The project will receive a single 1 mile reroute this summer, near Carter, to raise the highway crossing for accommodation of extra large/tall shipments of prefabricated tanks North of Great Falls, MT. Frank E. Jarvenpaa (406) 247-7384 (WAUM) Havre Substation Upgrade 161/115/12.47 Fall/ 2014 .2 Western currently owns, operates and maintains the Havre 161/115/12.47kV Substation. Upgrades are a result of needed relaying replacements and a new 115 kV interconnect for network load. The existing 115 kV single breaker and bypass switch will be replaced with a ring bus configuration serving the existing Shelby circuit and new network service interconnect. In addition, a new dedicated circuit interrupter will be installed for protection of the transformer. Construction design is complete. The control building was completed 2012 and currently is receiving protective relaying upgrades. Completion of the 115 kV yard work is expected by fall of 2014. The 115 kV bus will be out of service for extended periods during the 2014 construction season. However, no interruption of customer service during construction is anticipated. Minor outages are expected for Hill County Electric Coop during sequenced re-energization. Herron Park is currently served via a temporary tap off the Havre-Shelby 115 KV line. “ Page 40 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 NORTHWEST POWER POOL AREA Name of Project New 161/115 kV Substation between Richardson Coulee and Malta Substations Gen MW Transmission kV 161/115 Date No. of pages 2016 .2 Transfer Capability Phase CONTENTS AND REMARKS Power Transient Tables Flow Stability Post Transient Stability One Lines Maps Request Copy of Report From This project is on-hold status waiting for regulatory approval. Western currently owns, operates and maintains the 180 mile Fort Peck-Richardson Coulee-Malta-HarlemHavre 161kV circuit, which is constructed for future 230kV conversion. A new substation is anticipated to be installed approximately 18 miles East of Malta in the 49 mile section between the Richardson Coulee and Malta Substations. This new substation will provide a 161kV ring bus constructed at 230kV specification, 161/115kV transformation and a 115kV tap for a new 115kV line that will extend approximately 48 miles to serve an ultimate 21 MW of new oil development network load. VAR support will include a 15 MVAR shunt capacitance at the new 161kV substation and a 15 MVAR shunt capacitance at the load. Due to regulatory delays, construction is not anticipated to begin before fall of 2014. No interruption of customer service during construction is anticipated. “ Page 41 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Name of Project Gen MW Dry Fork Station 390 Laramie River Station 345/230 kV Transformer #2 Boone-Nyberg 115 kV Upgrade Project Transmission kV Date No. of pages 6/2011 38 345/230 8/2014 115 2015 Transfer Capability 600 MVA Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From The Dry Fork Station is a 390 MW net coal fired station under construction and scheduled to be in commercial operation in June of 2011. It is located at the Dry Fork Substation. Matthew Stoltz 701-557-5647 (BEPC) This project consists of the addition of a second 345/230kV 600MVA transformer at the Laramie River Station (LRS) switchyard in southeast Wyoming. It will connect to the existing 345kV and 230kV buses within the LRS switchyard. The in service date is August 2014. The transformer will be owned by the Missouri Basin Power Project (MBPP). This transformer will primarily function as an in service spare unit for the MBPP. No increase in system intact path ratings is expected; therefore the WECC path rating process is not necessary. Prior outage limits on the TOT3 path and LRS generation limits may be increased as determined by future operating studies. Under some conditions a LRS generation prior outage can contribute to TOT3 limits due to overload of the existing transformer. Also prior outage of elements of the LRS 345kV transmission system can cause LRS generation limitations due to overload of the existing transformer. The second transformer will improve system capacity in these situations. Matthew Stoltz 701-557-5647 (BEPC) This project is the proposed alternative to the cancelled second 230/115 kV 150 MVA transformer at the Boone 230 kV substation near Boone, CO. This project is being coordinated with Public Service Company of Colorado (PSCo) and TriState Generation and Transmission (TSG&T) for increased reliability in the Rocky Ford/La Junta area. The project consists of a new double circuit 115 kV line between Boone 115 kV and Nyberg 115 kV substations, utilizing existing right-of-way where possible and replacing the Boone – DOT Tap – Nyberg 115 kV transmission line. New 115 kV line terminal positions are required at Nyberg and Boone 115 kV substations to integrate the new circuit. The Colorado Coordinated Planning Group (CCPG) is a Sub regional Planning Group in the Rocky Mountain Region and allows open participation in its planning meetings to stakeholders interested in this project. The requirements of project coordination review for this project have been met through the CCPG. The planned in-service date is 2015. Wes Wingen 605-721-2268 (BHE) Page 42 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Date No. of pages Teckla-Osage 230 kV Transmission Line 230 2015 .2 The Teckla-Osage 230 kV line will consist of approximately 60 miles of 1272 ACSR ‘Bittern’ conductor on H-frame poles. The line will be constructed to provide needed Common Use System (CUS) transmission capacity, accommodate projected load growth, and increase Wyodak area stability margins. Reliability analysis for this project was initially performed as part of the 2008 BHBE LTP Study and the need reviewed in subsequent BHBE LTP Studies. The Colorado Coordinated Planning Group (CCPG) is a Sub regional Planning Group in the Rocky Mountain Region and allows open participation in its planning meetings to stakeholders interested in this project through the WY/SD Common Use Subcommittee (WY/SD CUS). The requirements of project coordination review for this project have been met through the CCPG. http://www.westconnect.com/filestorage/WY_CUS_Update_2012-12-13.pdf The planned in-service date is 2015. Wes Wingen 605-721-2268 (BHP) Osage-Lange 230 kV Transmission Line 230 2015 .2 The Osage-Lange 230 kV line will consist of approximately 75 miles of 1272 ACSR ‘Bittern’ conductor on H-frame poles. The line will be constructed to provide needed Common Use System (CUS) transmission capacity and provide an additional path to the Rapid City load center. Reliability analysis for this project was initially performed as part of the 2008 BHBE LTP Study and the need reviewed in subsequent BHBE LTP Studies. The Colorado Coordinated Planning Group (CCPG) is a Sub regional Planning Group in the Rocky Mountain Region and allows open participation in its planning meetings to stakeholders interested in this project through the WY/SD Common Use Subcommittee (WY/SD CUS). The requirements of project coordination review for this project have been met through the CCPG. http://www.westconnect.com/filestorage/WY_CUS_Update_2012-12-13.pdf The planned in-service date is 2015. “ Bill Durfee (Sundance) 230 kV Substation 230 2015 .1 On July 10, 2012, Powder River Energy Corporation (PREC) submitted to Black Hills Power a formal application for a new interconnection on the existing Lookout-Hughes 230 kV line. The interconnection will consist of a 100 MVA 230/69 kV transformer and a three terminal 69 kV switching station. The proposed location of the new interconnection is approximately 5 miles south of Sundance, Wyoming. Basin Electric Power Cooperative (BEPC) is currently performing a system impact study for this project. In addition, reliability analysis for this project was included as part of the 2013 BHBE LTP Study. The planned substation near Sundance, Wyoming was formerly named the Bill Durfee 230 kV substation at the end of 2013. The purpose of this project is to serve local load and increase local reliability. It is not expected to have a significant impact upon the operation of the Western Interconnection. The planned in-service date is currently 2015. “ Name of Project Gen MW Phase One Lines Request Copy of Report From Page 43 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Date No. of pages Undervoltage LoadShedding Scheme 115 2012 .3 A temporary UVLS program was implemented on 8/6/09 at nine 115 kV substations to prevent a localized voltage collapse from occurring when loads are high within a 115 kV load-serving area for a Category C contingency causing loss of two of the four 115 kV lines providing service to the loads. The program is designed to shed up to 75% of Longmont-Del Camino-Erie area load (north of Denver, CO) in three 25% stages at 4, 12, and 20 second time delays for bus voltages below 0.90 p.u. The UVLS program is in the process of being removed from service due to the Fordham-Fort Saint Vrain 230kV Line being completed in November 2011. “ Second 230kV line from Front Range Power Plant to Existing Nixon-Kelker (NX-KE) Line 230 12/2015 1 a) Second 230kV line from Front Range Power Plant to Existing Nixon-Kelker (NX-KE) Line b) Currently, there is only one transmission line from the CSU-owned Front Range Power Plant that generates 460 MW at summer peak. The purpose of this project is to provide a second line out of the plant to connect with an existing CSU transmission line. c) The termination point for the existing 230kV NX-KE line will be removed from the Nixon 230kV bus and the line will be re-routed into the Front Range Power Plant substation which it is only a few hundred feet from the existing line. Rather than two identical NX-KE lines, CSU will now have one 230kV line from Nixon to Kelker and one 230kV line from Front Range Power Plant to Kelker. d) The expected date of release to operations is December 2015. e) The expected operating voltage is 230kV. f) The project is not expected to have a significant impact on the operation of the WECC interconnected electric system because CSU is a small, relatively self-contained system. Changing the termination point of this existing 230kV line has very little impact on the CSU system and even less impact on the WECC system. The project provides a reliability improvement for CSU under certain Category C or D outages. Susan Lovejoy slovejoy@csu.org (CSU) Rifle – Parachute 230kV Line #2 230 10/2015 .3 The Rifle – Parachute Project consists of constructing a second 18-mile 230kV transmission circuit between Rifle and Parachute substations. The project is needed to accommodate projected load growth in western Colorado. The load growth consists primarily of natural gas developers that require transmission service to electric motor driven gas compressors for natural gas gathering and gas compression applications in Mesa and Garfield counties. The project has an in-service date of October, 2015. The project was granted a waiver of significant transmission project status in 2012. Thomas W. Green 303-571-7223 (PSC) Name of Project Gen MW Phase One Lines Request Copy of Report From Page 44 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Date No. of pages Pawnee – Daniels Park 345kV Transmission Project 345 2019 .3 The Pawnee – Daniels Park 345 kV Transmission Project consists of approximately 115 miles of 345 kV transmission between Pawnee Station and the Daniels Park Substation south of Denver. The project will also result in a new Smoky Hill – Daniels Park 345 kV line. The project is needed to accommodate additional generation in northeast Colorado. The project has a planned in-service date of 2019. The project was granted a waiver of significant transmission project status in 2012. “ Pawnee – Smoky Hill 345 kV Transmission Project 345 InService .1 This project consists of approximately 96 miles of 345kV transmission between the Pawnee and the Smoky Hill Substations. The project will improve local system reliability and is pursuant to Colorado Senate Bill 07-100 (“SB100”) to facilitate potential generation resources in northeast Colorado. The project was completed in 2013. “ San Luis Valley-CalumetComanche Transmission Project 345 .2 The San Luis Valley – Calumet – Comanche Transmission Project is a joint transmission plan between PSCo and Tri-State G&T. It consists of doublecircuit 230kV transmission from the San Luis Valley Substation in south-central Colorado to a new Calumet Substation, near Walsenburg, Colorado, and then double-circuit 345kV transmission from Calumet Substation to the Comanche Station, near Pueblo, Colorado. A comprehensive progress report was included with the PSCo 2010 Annual Progress Report. The timing of this project remains uncertain as indicated by the PSCo 2012 Project Report. “ ? .2 This project is expected to consist of new transmission originating in Weld County, Colorado and connecting to the existing transmission system northeast of the Denver-metro area. The project would increase local reliability to existing customers and provide transmission capacity to serve anticipated load growth in the region. The project would also accommodate additional generation resources north of Denver. Since the project impacts the existing Tot 7 path (Path 40), PSCo initiated the WECC Project Coordination process. Studies will progress through 2014 and an in-service date is uncertain at this time. “ Tot 7 Expansion Project Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Name of Project Gen MW Phase One Lines Request Copy of Report From Cogentrix of Alamosa 30 Q1/2012 .1 This project is a Solar PV generator connected to the Blanca Peak 115 kV substation. “ Limon 1 200 Q4/2012 .1 This project is wind generator connected to the Missile Site 345 kV substation. “ Limon 2 200 Q4/2012 .1 This project is wind generator connected to the Missile Site 345 kV substation. “ Cherokee 5. 6. 7 570 2016 .1 Interconnec tion Cherokee 115kV MW Type ISD 570 Gas(CC) 2016 “ Page 45 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Name of Project Gen MW Arapahoe 3 (retired) -44 Zuni 2 (retired) Cherokee 3 (retired) Transmission kV -65 Date No. of pages 2014 .1 2015 -152 2016 Transfer Capability Phase .1 .1 CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Interconnec tion Arapahoe MW Type ISD -44 Coal 2014 Interconnec tion Zuni MW Type ISD -65 Coal 2015 Interconnec tion Cherokee 115kV MW Type ISD -152 Coal 2016 One Lines Request Copy of Report From “ “ “ Laporte 230 kV Substation Expansion 230/115 5/2016 .1 Reconfigure an existing 230/115 kV substation with a 230 kV breaker-and-ahalf yard to connect four adjacent transmission lines (converting one from 115 to 230 kV) and two 230/115 autotransformers to be in-service May 2016. The project will have no regional impacts. The purpose of the project is to improve reliability in the Laporte, Colorado area which is in the northwest part of the Foothills Area system. The attached document shows the scope of the project. Jeremy Brownrigg brownriggj@prpa.o rg (PRPA) Boyd 230/115kV Transformer Addition Project 230/115 5/2017 .1 A second 230/115kV Transformer will be added to the substation along with converting the 115kV ring bus configuration to breaker and a half and is planned to be in-service May 2017. The project will have no regional impacts. The purpose of the project is to improve system reliability in the Loveland, Colorado area which is in the central part of the Foothills Area system. “ Wayne Child Substation Project (aka TOT3 Archer Interconnection Project previously known as the 300 MW Path 36 Upgrade) 345/230 Q4/2017 .3 300 MW 3 This Project will construct a new substation (Wayne Child substation) which will sectionalize MBPP’s Laramie River Station (LRS) – Story 345 kV line near the existing Archer substation, complete with 345/230 kV transformation, and construct approximately 1/3-mile of 230 kV line between Archer and Wayne Child substations. Line upgrades of the LRS – Ault and LRS – Wayne Child 345 kV lines will be necessary, as well as capacitors at Dalton substation near Sidney. This project will also establish a 34.5 kV point of delivery for High West Energy’s proposed 34.5-12.5 kV, 20 MVA substation contained within TriState’s proposed Wayne Child 345-230 kV substation. The project is planned to be completed in the 4th quarter, 2017, and is in Phase III of the WECC Three Phase Rating Process. David Gustad 303-254-3449 (TSGT) Page 46 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Transmission kV Date No. of pages Transfer Capability Lamar-Front Range Project 345 ? 1 2000 MW Burlington-Lamar 345/230 kV Project (Request for Waiver 2014) 345/230 ? Badwater – Casper 230 kV Line 230 2018 1 Keota 345/115 kV Project 345/115 2015 .25 Boone – Walsenburg 230 kV Line (2013 Waiver Granted) 230 2018 1 Name of Project Gen MW 650 MVA 645 MVA Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From This project includes two high voltage transmission paths, one from Lamar substation to Pueblo area and a second from Lamar to substations near Brush and/or Deer Trail. This will provide for better reliability to serve loads in the entire eastern Colorado footprint. Multiple voltage options have been examined. This project will be built in stages, with each designated stage being a part of the overall plan to address the eastern Colorado transmission needs. This project will also provide the infrastructure for Xcel Energy to meet Senate Bill 07-100 requirements by connecting several Energy Resource Zones in eastern Colorado to the Denver Front Range area. “ The purpose of Burlington-Lamar Transmission Project is to incrementally alleviate existing and future transmission system constraints in southeast and eastern Colorado as identified in the Lamar Front Range studies. It is a subset of the greater Lamar Front Range project. To accommodate future build outs, the Burlington-Lamar line may be constructed for 345 kV operation, but will initially be operated at 230 kV. “ This project involves constructing a new 230 kV transmission line from Casper substation to Badwater (PACE) substation. The new 70 mile long line will allow improved reliability and allow Tri-State to serve new load near central Wyoming. The planned in-service date is expected to be in 2018. “ This project involves sectionalizing the Laramie River Station (LRS)-Story 345 kV line for a load serving connection approximately 60-65 miles northwest of Story. Tri-State would install a 225 MVA, 345/115 kV transformer at Keota substation, with the possible future addition of a second transformer. The level of load planned for this substation is initially 40 MW, with a potential increase to 120 MW based on the most recent load connection requests. The planned inservice date is 2015. This project is in Phase III of the WECC Three Phase Rating Process. “ The Boone-Walsenburg project will consist of one new 230 kV transmission path from the existing Boone substation, owned by Tri-State and Xcel Energy, to the existing Walsenburg substation, owned by Tri-State. The conductor will be 1272 MCM ACSR-Bittern with a maximum design temperature of 100°C and be owned by Tri-State. Addition of a new 230 kV line will increase reliability in the Pueblo, Colorado area and also in Northeast New Mexico. Presently, the loss of the Comanche-Walsenburg 230 kV line results in severe thermal overloading on the 115 kV transmission system from West Station to Walsenburg. In order to mitigate the overloading, a Remedial Action Scheme (RAS) trips the Walsenburg-Gladstone 230 kV line which results in the loss of load and reduced reliability in Northeast New Mexico. The planned in-service date is 2018. “ Page 47 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Date No. of pages 230 ? 1 This project involves constructing a new 230 kV transmission line between the existing WAPA Shiprock Substation in New Mexico and a new 230 kV Iron Horse Substation in southwestern Colorado. A new 230 kV Kiffen Canyon Substation will also be required along with a phase shifting transformer. It will allow Tri-State to serve approximately 100 MW of new industrial load in SW Colorado. “ San Luis Valley-Carson 230 kV Line Project (aka San Luis Valley-CalumetComanche Transmission Project) 230/345 2022 1 This project consists of a new 230 kV transmission line from the existing San Luis Valley substation to a new Carson 230/345 kV substation located west of Taos NM. The Carson 230/345 kV substation will tap the existing Taos-Ojo 345 kV line and will include 230/345 kV transformation and a 230 KV phase shifting transformer. The planned in-service date for this project is 2022. “ Montrose-Nucla-Cahone Transmission Upgrades (aka Western Colorado Transmission Upgrade Project) (2013 Waiver Granted) 115/230 2019 1 This project upgrades the existing transmission lines and facilities from Montrose substation to Cahone substation from 115 kV operation to 230 kV. The purpose of this project is to improve system reliability by eliminating the Nucla Remedial Action Scheme. The planned in-service date for this project is 2019. Burlington-Wray 230 kV Line Project 230 2016 1 The Burlington-Wray 230 kV Line Project is intended to increase reliability in the project area, remove restrictions on the Burlington area network resources, and increase the deliverability of Tri-State resources to Tri-State member loads. This will be accomplished by adding a new 230 kV line from the Burlington substation to the Wray substation. The addition of the 230 kV line will add one new transmission line segment that will be constructed as a single circuit using 1272 MCM ACSR conductor with a maximum operating capacity of 1538 amps. This additional capacity will alleviate congestion in the Burlington area, increase reliability, and allow the potential development of renewable generation resources in the Burlington and Wray areas which currently have existing wind resources. The planned in-service date is 2016. “ Big Sandy-Calhan 230 kV Line Project (2012 Waiver Granted) 230 2019 1 The primary purposes of the Big Sandy -Calhan 230 kV project are threefold: mitigate the projected overloads of Tri-State’s 100 MVA 230-115 kV Fuller transformer, should other mitigating actions not take place; increase Tri- State’s ability to deliver resources to Mountain View Electric Association (MVEA) and its other southeastern Colorado members; and provide a bulk transmission connection (i.e., a "strong" voltage source and increased power transfer capacity) to the eastern side of MVEA’s service area. This will be accomplished by adding a 230 kV line from Big Sandy substation to a new Calhan substation. This project is presently planned to be in-service 2019. “ San Juan Basin Energy Connect Project (2013 Waiver Granted) Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Name of Project Gen MW Phase One Lines Request Copy of Report From Page 48 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability 1000-1500 MW San Luis Valley-CalumetComanche Transmission Project 230/345 After 2015 .4 Gladstone 230 kV Phase Shifting Transformer Project (2012 Waiver Granted) 230 2018 1 J.M. Shafer-Henry Lake 230 kV Project (Request for Waiver 2014) 230 ? .33 Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From The project consists of two basic sections and is a joint project with Xcel Energy. The first section consists of approximately ninety‐five (95) miles of new, double‐circuit 230 kV transmission, built from the San Luis Valley Substation to a new Calumet Substation, which would be located approximately six (6) miles north of the existing Tri‐State Walsenburg Substation. The second section consists of approximately forty‐five (45) miles of 19 new double‐circuit 345 kV transmission line from Calumet Substation to the existing Comanche Station near Pueblo. The project will improve local system performance and reliability, and will facilitate potential generation as part of Xcel Energy’s response to Colorado Senate Bill 07-100 which calls for development of transmission facilities to deliver power from renewable resource zones in Colorado. The project was initially planned to be in service in 2015. However, the project in service date has been delayed and will be determined after Colorado PUC and other stake holder input. This project is not expected to impose any significant impacts on the reliability of the WECC interconnected system. “ The project is to add a 300 MVA Phase Shifting Transformer (PST) at the Gladstone existing substation. Studies by Tri-State and others have all shown the need for transmission network upgrades in the North East New Mexico (NENM) area to improve system reliability, load serving capability, mitigate operating issues related to phase angle differences, and to reduce system losses. The planned in-service date for this project is 2018. “ Tri-State’s J.M. Shafer generating station has a total capacity of 272 MW and has some capability to be upgraded in the future. The station presently relies on the 230kV Fort Lupton Substation and its interconnected transmission system owned by Xcel Energy to deliver power to Tri-State’s loads in the PSCo Balancing Authority area. Since Tri-State has load in both the PSCo Balancing Authority area and the WACM Balancing Authority area, Tri-State desires the flexibility to directly deliver the output of the J.M. Shafer station to either Balancing Authority. Tri-State can do so by interconnecting the J.M. Shafer station directly to the Greenhouse Substation and constructing a Greenhouse to Henry Lake 230 kV line. Tri-State forecasts an increasing need for additional balancing resources in the WACM BA to comply with the State of Colorado’s Renewal Portfolio Standards. The J.M. Shafer to Greenhouse to Henry Lake 230kV project will permit Tri-State to utilize the J.M. Shafer station as a balancing resource in the WACM BA. The project will also improve transmission reliability by providing a second transmission source directly to the J.M. Shafer station and mitigates the problem of losing the entire station for a single line outage. “ Page 49 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013 ROCKY MOUNTAIN POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From Miracle Mile Substation Stage 03 230 Q2/2010 WAPA Projects .5 Installation of two 230/115 kV, 200 MVA power transformers, and associated equipment. Installation of two 30 MVAR shunt reactors. Lovell – Yellowtail 115-kV rebuild 115 Q4/2014 1 Rebuild with 795 ACSS Curecanti 230/115-kV 150 MVA transformer replacement 230/115 Q4/2014 1 Replace Curecanti KZ1A 230/115-kV 75 MVA with a 150 MVA transformer “ 230 Q4/2014 1 Sectionalize Western’s Ault-Cheyenne 230-kV and Archer-North Park 230-kV with a new substation known as Terry Ranch Road. Substation will be built in a 230-kV breaker and half configuration. “ TransWest Express Project 600 kV HVDC Late 2017 or Early 2018 2 3000 2 TransWest Express LLC (TransWest) is developing the TWE Project, a 3,000 MW, 600 kV, line commutated, bi-pole high voltage direct current (HVDC) transmission project. TransWest and Western Area Power Administration (Western) have entered into a joint development agreement under which Western may become a 50% owner of the TWE Project. The TWE Project is approximately 730 miles long and will be connected to the AC transmission grid in south central Wyoming and in south eastern Nevada. The primary intended use of the TWE Project is to deliver wind generated electricity from Wyoming to markets in the desert southwest. The TWE Project is planned to be in service in late 2017 or early 2018. David Smith (303) 299-1545 (TWE) Wyoming Colorado Intertie 345 2014 2 TOT3 +900 MW 2 WCI is an approximately 180-mile, 345 kV transmission line between Laramie River Station in southeastern Wyoming and Pawnee in northeastern Colorado. WCI has a Planned Rating that will add 900 MW to the TOT3 (WECC Path 36) path rating. The WCI project is owned by Wyoming Colorado Intertie, LLC, a member of the LS Power Group of companies. Bill Pascoe (406) 494-2075 WCI Consultant Terry Ranch Road Substation “ Linda Pope 970-461-7348 WAPA-RMR Page 50 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA No. of pages Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Transmission kV Date Palo Verde – Delany 500 kV line 500 2016 1 Main components of the project will include a 14.86 mile 525 kV transmission line composed of 525 kV lattice structures with a phase conductor of 3x1780 kcm ACSR Chukar. Shield conductors for the line will utilize one 7#8 AW conductor (segmented) and one OPGW conductor (non‐segmented). A new 525 kV switching station will be constructed at the Delaney site and a new line terminal will be added at the Palo Verde switching station. A 170 Mvar, 525 kV reactor has been purchased and will be located on one of the buses at the Delaney switchyard and operated through a 525 kV breaker. In 2011, APS completed a study (Preliminary Transmission Interconnection Impact Study: Q11 Palo Verde‐Delany‐Sun Valley and Q12 Hassayampa‐ North Gila #2 500 kV Lines) and the results were approved by the Western Arizona Transmission System task force. Results of the study reveal the project will not adversely impact existing facilities while providing access to new renewable generation facilities west of Phoenix, Arizona. In addition, the project has also been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission as well as a number of sub‐regional studies with no adverse effects. Results from studies mentioned in section B have found no adverse effects to the WECC or local transmission systems due to the addition of this project. Additionally, the project is anticipated to be part of the Palo Verde East transmission path. Barrie Kokanos 602-250-1370 (APS) Delany – Sun Valley 500 kV line 500 2016 1 Main components of the project will include a 28.30 mile 525 kV transmission line composed of both 525 kV lattice and monopole structures with a phase conductor of 3x1780 kcm ACSR Chukar. Shield conductors for the line will utilize one 7#8 AW conductor (segmented) and one OPGW conductor (non‐ segmented). A new 525 kV switching station will be built at the Sun Valley site and a new 525 kV terminal will be added at the Delaney switching station. “ Name of Project Gen MW Phase One Lines Maps Request Copy of Report From In 2011, APS completed a study (Preliminary Transmission Interconnection Impact Study: Q11 Palo Verde‐Delany‐Sun Valley and Q12 Hassayampa‐ North Gila #2 500 kV Lines) and the results approved by the Western Arizona Transmission System task force. Results of the study reveal the project will not adversely impact existing facilities while providing access to new renewable generation facilities west of Phoenix, Arizona. In addition, the project has also been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission as well as a number of sub‐regional studies with no adverse effects. Results from studies mentioned in section B have found no adverse effects to the WECC or local transmission systems due to the addition of this project. Additionally, the project is anticipated to be part of the Palo Verde East transmission path. Hassyayampa – N. Gila 500 kV #2 (HANG 2 500 2015 2 The project has a CEC permit, has a planned in‐service date of summer 2015 and is currently under construction. ″ Page 51 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Project) Palm Valle-Trilby Wash 230 kV Project Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From To increase transfer capacity on Path 49, increase import capability in the Yuma load pocket and increase access to renewable generation near the Palo Verde/Hassayampa hub. Main components of the project will include a 111.41 mile 525 kV transmission line composed of 525 kV lattice structures with a phase conductor of 2x2156 kcm ACSR Bluebird. Shield conductors for the line will utilize two OPGW conductors (segmented). Two 170 Mvar, 525 kV line reactors, one located at each terminal, are included in the project and will be operated through a 525 kV breaker. A single‐segment, 33.7 Ω series capacitor will be located at the N.Gila switchyard. Rating for the MOV protected capacitor will be 2200 Amps continuous with a 135% 30 minute emergency rating. In 2011, APS completed a study (Preliminary Transmission Interconnection Impact Study: Q11 Palo Verde‐Delany‐Sun Valley and Q12 Hassayampa‐ North Gila #2 500 kV Lines) and the results were approved by the Western Arizona Transmission System task force. Results of the study reveal the project will not adversely impact existing facilities along the Arizona‐California border. Also, the project has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission as well as a number of sub‐regional studies with no adverse effects. In September 2011, the project participants completed the WECC Project Coordination Review Group Report for the Hassayampa‐North Gila #2 (HANG2) Project as a partial requirement for completing the WECC Project Coordination Process for the project. Subsequently, the project participants completed the Hassayampa‐ N.Gila #2 Project (Path49) WECC Comprehensive Progress Report as a partial requirement for advancing from phase 1 to phase 2A in the WECC Path Rating Process. Based on the efforts completed to date, study results have revealed no adverse effects to the WECC or local transmission systems due to the addition of the HANG2 project. Additional studies including the phase 2 WECC Path Rating Process study are currently assessing this project. Finally, the project is anticipated to be part of the East of the Colorado River transmission path (WECC Path 49). 230 2015 1 The project has a CEC permit and has a planned in‐service date of summer 2015. Main components of the project will include a 15.91 mile 230 kV transmission line composed of 230 kV double circuit monopole structures with a phase conductor of 1x2156 kcm ACSS with the second circuit strung at a later date. Shield conductors for the line will utilize one 3/8“ HS conductor (non‐ segmented) and one OPGW conductor (non‐segmented). A new 230 kV line terminal will be added at the Palm Valley substation. In addition, the project will also include construction of a new 230/69 kV substation in the Sun City area. Sub‐regional studies are underway to assess the impacts of the project through the Western Arizona Transmission System task force. However, the project has ″ Page 52 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From been studied in various sub‐regional study efforts and has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission with no adverse effects. To date, study results have revealed no adverse effects to the WECC or local transmission systems due to the addition of this project. Sun Valley‐Trilby Wash 230 kV Project (2016) 230 2016 1 The project has a CEC permit and has a planned in‐service date of summer 2016. Main components of the project will include a 14.13 mile 230 kV transmission line composed of 230 kV double circuit monopole structures with a phase conductor of 1x2156 kcm ACSS with the second circuit strung at a later date. Shield conductors for the line will utilize one 3/8“ HS conductor (non‐ segmented) and one OPGW conductor (non‐segmented). A new 230 kV switching station will be built at Sun Valley and a new 230 kV terminal will be added at the Trilby Wash substation. In addition, the project will also include a new 600 MVA, 525/230 kV transformer at the Sun Valley switchyard. Sub‐regional studies are underway to assess the impacts of the project through the Western Arizona Transmission System task force. However, the project has been studied in various sub‐regional study efforts and has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission with no adverse effects. To date, study results have revealed no adverse effects to the WECC or local transmission systems due to the addition of this project. “ Sun Valley – Morgan (TS9) 500 kV line 500 2018 1 The project has a CEC permit and has a planned in‐service date of summer 2018. Commercial operation date for the 230 kV portion of the project is approximately 2024. “ Proposed renewable generation facilities are expected to interconnect to the Delaney 500 kV switchyard and will deliver resources to the Phoenix area through the Sun Valley‐Morgan 500 kV Project. Main components of the project will include a 38.07 mile 525 kV transmission line composed of 525/230 kV double circuit monopole structures with a phase conductor of 3x1780 kcm ACSR Chukar. Phase conductor for the 230 kV line will be 1x2156 kcm ACSS and will be strung at a later date. Shield conductors for the line will utilize one 7#8 AW conductor (segmented) and one OPGW conductor (nonsegmented). A new 525 kV terminal will be added at both Sun Valley and Morgan switching stations. Sub‐regional studies are underway to assess the impacts of the project through the Western Arizona Transmission System task force. However, the project has been studied in various sub‐regional study efforts and has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission with no adverse effects. Page 53 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From To date, study results have revealed no adverse effects to the WECC or local transmission systems due to the addition of this project. Additionally, the project is anticipated to be part of the Palo Verde East transmission path. Four Corners units 1‐3 retirement (2013) 560 MW Retired 1 Three coal fired steam units removed from service connected to the Four Corners 230 kV switching station through individual GSU transformers. Operating and planning studies have shown no effect on adjacent transmission paths with the absence of the generation. APS has investigated adding shunt reactors at the site to control high voltages when one or both of Units 4 and 5 are off‐line under light load scenarios. Study results show no effect on adjacent systems. All three units were retired on 12/30/13. Net change of capacity of 560 MW. “ Saguaro units 1‐2 retirement (2013) 210 MW Retired 1 Both units were retired on 6/30/13. Net change of capacity of 210 MW. Two gas fired steam units removed from service connected to the Saguaro 115 kV buses through individual GSU transformers. Operating studies have shown no effect on adjacent transmission paths with the absence of the generation. Study results show no effect on adjacent systems. “ 2017 1 Main components of the project will include a fold‐in of the Cholla‐ Pinnacle Peak 345 kV line into a new 345 kV switching station as well as the addition of a 150 MVA, 345/69 kV transformer and a new 69 kV switching station. “ Mazatzal 345/69 kV Substation (2017) 345/69 kV The project has been modeled in various sub‐regional studies as well as several Ten Year Plan submittals by APS to the Arizona Corporation Commission. Results from studies mentioned in section B have found no adverse effects to the WECC or local transmission systems due to the addition of this project. N.Gila‐Orchard (previously called TS8) 230 kV Project (2018) 230 kV 2018 1 The project has a CEC permit and has a planned in‐service date of summer 2018. “ Main components of the project will include a 12.50 mile 230 kV transmission line composed of 230 kV double circuit monopole structures with a phase conductor of 1x2156 kcm ACSS with the second circuit strung at a later date. Shield conductors for the line will utilize one 3/8“ HS conductor (non‐ segmented) and one OPGW conductor (non‐segmented). A new 230 kV switching station will be added at the N.Gila site. In addition, the project will also include a new 600 MVA, 525/230 kV transformer at the N.Gila switch yard and the construction of a new 230/69 kV substation in the south Yuma area. This project was included in the WECC Comprehensive Progress Report Page 54 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From Hassayampa‐N.Gila #2 Project (Path49) associated with the HANG2 project WECC Path Rating Process studies. However, the project has been studied in various sub‐regional study efforts and has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission with no adverse effects. To date, study results have revealed no adverse effects to the WECC or local transmission systems due to the addition of this project. Additional studies including the phase 2 WECC Path Rating Process study and other operating studies are currently assessing this project. Scatter Wash 230/69 kV Substation (2021) 230/69 2021 1 Main components of the project will include a fold‐in of the Raceway‐ Pinnacle Peak 230 kV line into a new 230 kV substation as well as the addition of a 188 MVA, 230/69 kV transformer and a new 69 kV switching station. “ This project has been studied in various sub‐regional study efforts and has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission with no adverse effects. To date, study results have revealed no adverse effects to the WECC or local transmission systems due to the addition of this project. Sun Valley‐Morgan 230 kV Project (2024) 230 2024 1 The project has a CEC permit and has a planned in‐service date of summer 2024. “ Main components of the project will include a 38.07 mile 230 kV transmission line composed of 230 kV circuit on double circuit monopole structures with the Morgan‐Sun Valley 500 kV transmission line (mentioned previously) with a phase conductor of 1x2156 kcm ACSS. Shield conductors will already be in‐ place due to the pre‐existing line. New 230 kV terminals will be added at both Sun Valley and Morgan switching stations. Sub‐regional studies are underway to assess the impacts of the project through the Western Arizona Transmission System task force. However, the project has been studied in various sub‐regional study efforts and has been included in several Ten Year Plan submittals by APS to the Arizona Corporation Commission with no adverse effects. To date, study results have revealed have found no adverse effects to the WECC or local transmission systems due to the addition of this project. Navajo Transmission Project Segment 1 500 2016 1 1600 2 This project is the construction of a new 500 kV transmission line starting at the Four Corners 500 kV switching station and terminating at a switchyard south of the Navajo 500 kV switching station. As a result of this project, the nomogram for Path 22 will be eliminated and the two components of the path will be separated into Path 22A (Four Corners-Moenkopi and DREP-RME 500 kV) and Tom Johns Sithe Global 509-926-3485 Page 55 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From Path 22B (Four Corners-Cholla #1 & #2 345 kV). Path 22A will have a nonsimultaneous rating of 3190 MW and Path 22B will have a non-simultaneous rating of 1370 MW. Path 23 (Four Corners 500/345 kV) will have a rating of 1040 MW. Great Basin Transmission SWIP-South Project 500 2014 1 +/- 2000 MW 2 2 Great Basin Transmission’s SWIP-South Project represents further development of the ONLine Project. Install 70% series compensation on Robinson Summit-Harry Allen 500 kV line, 35% at each end. Install two 600 MVA 345/345 kV Phase Shifting Transformers (+/- 48 degrees each) at Robinson Summit: one connected towards Falcon and the other connected towards Gonder. Construct an extending 500 kV circuit from NV Energy’s Harry Allen substation to SCE’s Eldorado substation (~60 miles), with 70% series compensation at Harry Allen. Plan of service also includes a +150 MVAR shunt capacitor at the Robinson Summit 345 kV bus, and a +400 MVAR SVD (4x100 MVAR steps) at the Robinson Summit 500 kV bus. Evan Estes LS Power Development, LLC 636-532-2200 Great Basin Transmission SWIP-North Project 500 2014 1 +/- 2000 MW 2 2 Great Basin Transmission’s SWIP-North Project consists of a new 500 kV line from Idaho Power’s Midpoint substation to a new proposed Robinson Summit substation near Ely, Nevada (~275 miles). Install 70% series compensation (for 245 mile line impedance) as follows: 35% at Thousand Springs (located !125 miles south of Midpoint) and 35% at Robinson Summit. “ Bordertown to Cal Sub 120 kV Project 345/120 2017 0 0 0 0 0 This project comprises a 345/120 kV 280 MVA transformer at Bordertown Substation and a 120 kV 11-mile line from Bordertown to California Substation. This project is expected to be in service in 2017. Alex Fratkin NV Energy North 775-834-4897 345 4/2014 Falcon Second 345/120 kV Transformer 345/120 2015 “One Nevada” Transmission Line Project (ON Line). 500/345 In-Service 345 kV Voltage Support Project 1 270 MVA This project was approved in Sierra 2007 Integrated Resource Plan. The project includes the construction of a 75 MVA 345 kV capacitor bank at North Valley Road substation and a 75 MVA 345 kV capacitor bank at Mira Loma substation for operational support of the voltage in the 345 kV transmission grid. The Mira Loma bank is already in service; the Valley Road bank is planned to enter service in March/April, 2014. “ This project is driven by the expected increase of the NVE North load. The project includes an addition of a second Falcon 345/120 kV 280 MVA transformer bank at the existing Falcon 345 kV / 120 kV substation. This project is scheduled to be in service in 2015. The project includes the following facilities: • 500-kV 231 mile 3-1590 ACSR line from Robinson Summit to Harry Allen, • New 345/500 kV Robinson Summit Substation (located 20 miles west of Ely, Nevada) with its 345 kV and 500 kV switchyards connected through 2×525 MVA 345/500 kV autotransformers, “ Page 56 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From • Fold of the existing Falcon – Gonder 345 kV line into Robinson Summit Substation and approximately 70% series compensation equipment on Falcon – Robinson 345 kV line, 35 % at each end. • A new 500 kV line terminal at the existing Harry Allen Substation (located northeast of Las Vegas, Nevada). NV Energy and GBT-South have completed this project, which entered service on 12/31/2013. Harry Allen 500/230 Transformer Addition 500/230 6/2016 NV Energy plans to request Public Utility Commission of Nevada authorization to construct a new 500/230 kV 1500 MVA transformer at Harry Allen substation. The transformer would be installed at the 500 kV switchyard and connected to the 230 kV yard through a short 230 kV line. The transformer will be designed to impedance of 8% (in order to balance the system flow ability and the fault duty at 230 kV bus). This project is scheduled to be in service in June, 2016, depending on permitting timelines. Alex Fratkin NV Energy South 775-834-4897 Crystal 500 kV Line Interconnection 500 11/2014 NV Energy will construct a new 500 kV bay with two new breakers in the South Crystal 500 kV Substation. This South Crystal 500 kV Substation work will terminate a new LADWP 500 kV line (with conductor 2-1590 ACSR per phase) interconnecting a new solar PV plant. This project is scheduled to be in service in November 1, 2014. “ McDonald 230/138 kV Additions 230/138 6/1/2016 .1 NV Energy plans to add a new 336 MVA 230/138 kV transformer at the existing McDonald substation. The existing Arden – Decatur 230 kV line will be folded into the new McDonald substation. ″ Brooks 230/138/12 kV Substation and Pecos – Brooks 230 kV Line 230/138 2017 .1 The addition of a new 230 kV transmission line between Pecos and the future Brooks substation site along with folding in the 138 kV sub-transmission between Leavitt and Gilmore substations into the Brooks substation will eliminate N-1 low voltage issues. . “ Sunrise 500/230 kV Transmission Substation 500/230 2018 .2 To increase import capability into the NEVP system, the Sunrise Project will include a new 500/230 kV Sunrise substation connected through an 8-mile fold to the Harry Allen-Mead 500 kV transmission line, with one 1500 MVA 500/230 kV transformer. The Sunrise 230 kV facilities will be integrated with existing 230 kV Nevada Power Company facilities through four new 230 kV lines. In service in 2018. The 500 kV portion of the project has been canceled and replaced with the Harry Allen 500/230 kV transformer addition. The 230 kV additions are delayed to 2018 or beyond based on current load forecasts. “ Robinson – Harry Allen Transmission Line #2 Project 500 2018 .2 Construct a 500-kV, 235 mile line #2 from the Robinson Summit Substation in Northern Nevada to the existing Harry Allen Substation in Las Vegas area. This line will parallel the “SWIP South” line route, on a separate ROW, with approximately 1000 ft separation between the two lines. The line will be 70% series compensated, 35% at each end. The line will serve as a conduit for new renewable generating resources between Northern and Southern Nevada, “ Page 57 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From including those currently being developed along and in the proximity to the SWIP corridor. NVE has recently obtained from the BLM a permit for this line and is finalizing the substation portions of the permit. Similarly to “SWIP” Project, the SSR studies to identify possible adverse effects on the near-by generators will be performed. NV Energy is the proponent and the prospective owner of this project. Northwest 500/230 #2 Transformer Addition 500/230 6/1/2018 .1 Install three 500/230 kV, single phase autotransformers with a rating of 300/400/500 MVA at the existing Northwest substation. ″ Sunrise 500/230 kV #2 Transformer Addition 500/230 6/1/2020 .1 This is a second 500/230 transformer addition at Sunrise, which will fold in the existing Harry Allen – Mead 500 kV #1 line. “ Expansion of the Rio Puerco 345 kV Station 345 2015 .3 The project consists of expanding the Rio Puerco Substation by looping in the existing San Juan-BA 345 kV and Four Corners-West Mesa 345 kV lines .The project eliminates contingency overloads of existing 115 kV lines in the northern portion of PNM’s Albuquerque 115 kV subtransmission network under high renewable generation conditions. Tom Duane (PNM) 505-241-4569 The initial expansion of the Rio Puerco station, which added a new 345/115 kV transformer to the local Albuquerque area network, was completed in May 2011. The looping in of the existing San Juan-BA 345 kV and Four CornersWest Mesa 345 kV lines is currently scheduled to be completed in 2015. Pinal West – Pinal CentralAbel – Browning 500 & 230kV line Estimated date of operation: 2014-2020 500/230 kV 2014 .5 1500 MW Point of Origin Pinal West Substation Intermediate point Duke Substation Intermediate point Pinal Central Substation Intermediate point Randolph Switchyard Intermediate point Abel Substation Intermediate point Dinosaur Substation Point of Termination Browning Substation Length Approximately 100 Miles The proposed line is part of former Southeast Valley Project (SEV). The first segments of the projects were finalized in: 2007 – Dinosaur Substation 2007 – Dinosaur – Browning 230kV 2010 – Randolph – Browning 500kV energized at 230kV 2010 – Randolph – Abel – Dinosaur 230kV 2011 – Abel 230kV Substation The Pinal West – Duke-Pinal Central-Abel – Browning 500kV line will close the SEV loop in 2014. As a part of the project following facilities will be built: 2014 – Pinal Central – Randolph 230kV 2014 – Pinal Central – Browning 500kV (the voltage and configuration change of the 2010 Randolph- Eldin Dizdarevic (602) 236-0960 (SRP) Page 58 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From Browning 230kV section) 2014 – Pinal West – Pinal Central 500kV and 230kV 2014 – Pinal Central 500kV and 230kV Substation 2014 – Duke 500kV Substation The Central Arizona Transmission System Study identified a number of system additions necessary to accommodate load growth and access to energy sources in the central Arizona area. This transmission line is the second segment of a series of transmission lines to serve the central Arizona region. This segment will initially provide an interconnection with the Palo Verde market area to market power to the Phoenix and central Arizona areas, and to accommodate the growth in development and population in Pinal County. Desert Basin-Pinal Central 230 kV Line 230 2014 .2 Point of Origin: Desert Basin Power Plant 230kV Switchyard Intermediate point: None Point of Termination: Pinal Central 230kV Substation Length Approximately: 21 miles The purpose of the project is to remove the Remedial Action Scheme installed on Desert Basin Generating Station, improve reliability of the 230kV system in the region by reducing the loading on existing lines in the area, increase local area system capacity, reduce reliance on second party transmission system and to establish the Pinal Central Substation which was identified as one of the future injection points of power and energy into the central Pinal County load area. “ Eastern Mining Area Expansion Project 230/115 2016 .5 The purpose of the project is to increase capacity to accommodate growing mining customer load. Several options are under consideration; however, the likely routing for the new transmission would be to follow the APS Cholla Saguaro 500kV line until it crosses SRP’s 115kV line. From there, the 230kV line would likely follow SRP’s existing Ray - Knoll - Morris 115kV line. “ Price Road Corridor Project 230 2016 .5 Point of Origin: Kyrene 230kV Substation Intermediate point: Knox, RS27 and RS28 Substations Point of Termination: Schrader 230kV Substation Length Approximately: 12-23 miles The purpose of the project is to serve growing industrial and commercial customer loads along the Price Road Corridor, adjacent to Price Road in south Tempe and Chandler. The project will consist of a new single-circuit 230kV line from the Schrader Substation in southwest Chandler to a new RS28 Substation, located to the west in the southern portion of the Price Road Corridor in Chandler; a new double-circuit 230kV line from the Knox Substation, located just south of the I-10 and Loop 202 freeway interchange in the westernmost tip of Chandler, to a new RS27 Substation to be located in the northern portion of the Price Road Corridor, south of the Loop 202 freeway, in Chandler; a new double-circuit 230kV line to connect the two new substations; and a single-circuit 230kV line between the Knox Substation in Chandler and the Kyrene Substation, located at the intersection of Elliott and Kyrene Roads in “ Page 59 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From south Tempe. This project will be built in phases with the first phase being energized in 2016. Rogers – Santan 230kV line 230 2016 .25 Point of Origin: Rogers230kV Substation Intermediate point: None Point of Termination: Santan 230kV Substation Length: Approximately 9 miles The purpose of the project is to provide adequate transmission facilities to deliver reliable power and energy to SRP’s customers in the eastern Phoenix Metro valley area by upgrading existing conductors and circuits. The route is generally east and south from Rogers to the Santan Substation, using existing circuit positions on existing structures, where possible. “ Silver King – RS-29 230kV Project 230 2018 .25 Point of Origin: Silver King 230kV Substation Intermediate point: None Point of Termination: New RS-29 230kV Substation Length: Approximately 12-14 miles The purpose of the project is to increase to accommodate growing customer load. Several routing options are under consideration with the most likely routing that follows APS Cholla-Saguaro 500kV line. “ New Superior – New Oak Flat 230kV line 230 2021 .25 Point of Origin: A New 230kV Substation near the existing Goldfield – Silver230kV line, tentatively named “New Superior” Intermediate point: None Point of Termination: New 230kV Substation near Oak Flat Length: Approximately 3.5 miles The purpose of the project is to serve growing customer loads at Oak Flat. The location of the New Superior and the New Oak Flat sites are still being determined. The preliminary 230kV alignment will be identified after these details are received. “ New Oak Flat – Silver King 230kV line 230 2021 .25 Point of Origin: A New 230kV Substation near the existing Oak Flat 115kV Station, tentatively named “New Oak Flat” Intermediate point: None Point of Termination: Silver King 230kV Substation Length: Approximately 3 miles The purpose of the project is to serve growing customer loads at Oak Flat. The alignment will closely follow the existing 115kV circuit connecting Silver King to Oak Flat. “ Abel – Pfister - Ball 230kV line 230 2021 .25 Point of Origin: Future Ball (RS17) 230kV Substation Intermediate point: Future Pfister (RS24) 230kV Substation Point of Termination: Abel 230kV Substation Length: Approximately 20 miles Estimated in-service dates are: 2021- Abel – Pfister – Santan 230kV line “ Page 60 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From 2021- Abel – Pfister- Schrader 230kV line 2021- Pfister Substation The purpose of the project is to meet expected load growth in the eastern service territory. The route of the line is generally south and east from a point on the Santan to Schrader 230kV line near the future Ball (RS17) Substation to the Pfister (RS24) Substation in the southeastern portion of the town of Queen Creek, continuing south and east to the future Abel Substation. Silver King – New Pinto Valley 230kV line 230 2021 .25 The purpose of the project is to serve growing customer loads at Pinto Valley. The anticipated route for this project parallels the existing Coronado - Silver King 500kV line out of Silver King to the north until it turns east to terminate at a Substation proposed in the vicinity of the existing 115kV Pinto Valley Station. “ Schrader-Abel 230 kV Line 230 2019 .1 This 230 kV transmission project is projected to be in service by 2019. “ Kyrene 500/230 kV Transformer 500/230 5/2012 .1 A third Kyrene 500/230kV transformer will be constructed and energized by May 2012. APS is participating with SRP on the transformer. “ Rudd 230/69 kV Transformer 230/69 4/2018 .1 The first Rudd 230/69kV transformer will be constructed and energized by April 2018. “ Schrader 230/69 kV Transformer 230/69 4/2014 .1 A second Schrader 230/69 kV transformer will be constructed and energized by April 2014. “ 230 2018 .1 This project is driven by customer load growth, approximate mileage is 14. This 230kV transmission project is scheduled to be in service by 2018. “ 5/20165/2020 .1 Nine 91MW generating units are scheduled to be installed at Abel 230kV station. The first unit is scheduled to be in service by 5/2016, the second unit by 5/2018, the third and fourth units by 5/2019 and the rest of the units by 5/2020. “ 500 2011-2016 .2 SRP and APS jointly plan to construct the following transmission facilities: Palo Verde-Delany (Harquahala Junction) 500 kV Line (in-service date 2014) Delany (Harquahala Junction)-Sun Valley (TS5) 500 kV Line (in-service date remains 2015. Morgan(TS9)-Pinnacle Peak 500 kV Line (in-service date 2011). Palo Verde-North Gila 500 kV Line (in-service date remains 2014). Sun Valley (TS5)-Morgan (TS9) 500 kV Line (in-service date 2016). “ 115/230/345 20142020+ .6 “ Resolution Copper 230kV Line Abel 230kV Generation Other Joint SRP/APS Projects Other SRP 115/230/345 kV Transmission Projects 819 RS26, formerly Fountain Hills Station-115 kV, 230 kV or 345 kV from Stewart Mountain, Goldfield or APS’ Cholla-Pinnacle Peak 345 kV Line (inservice date moved beyond SRP’s 10 year plan) Ball Loop-In (in-service date moved beyond SRP’s 10-year plan) Page 61 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From At this time, the in-service date for each of the following projects is not yet determined and is subject to further additional study work. Browning-Thunderstone 230 kV Line Browning-Corbell 230 kV Line Silver King-Browning 230 kV Line Silver King-Browning 230 kV/Superior Tie Santa Rosa-CATSHV03 230 kV Line Pinnacle Peak-Brandow 230 kV Line with a possible loop into Rogers or Thunderstone Silver King-Knoll-Hayden 230 kV Line Point on the Kearny-Hayden 115 kV Line to Hayden double circuit loop Pinal Central-Abel-RS20 500kV line Southline Transmission Project SunZia Southwest Transmission Project 345/230 2016 2 500 2018 9 3000 MW 2 Southline Transmission, L.L.C. proposes to construct the Southline Transmission Project, a high--‐voltage electric transmission line and associated facilities in southern New Mexico and southern Arizona. The proposed project would include a New Build Section (New Build) and an Upgrade Section (Upgrade). 1. New Build --‐--‐ The first section is a proposed double--‐circuit 345--‐kV line originating at the Afton Switching Station outside Las Cruces, New Mexico, and terminating at Apache Switching Station in Southeastern Arizona; 2. Upgrade --‐--‐ The second section is a proposed upgrade of the Western Area Power Administration's existing 115--‐ kV Apache to Saguaro transmission line, to a 230--‐kV double--‐circuit line from Apache to Saguaro and Tortolita. Depending upon the final design, Southline is seeking the following ratings: 1. Afton East--‐to--‐West (E2W) --‐ Rating of 1,030 MW; 2. Apache East--‐to--‐West (E2W) --‐ Rating of 1,000 MW; 3. Saguaro/Tortolita West--‐to--‐East (W2E) --‐ Rating of 418 MW and a Saguaro/Tortolita West--‐to--‐East (W2E) Rating of approximately 1,000 MW with the Tucson to Oracle 115--‐kV line re--‐conductor project in service); 4. Apache West--‐to--‐East (W2E) --‐ Rating of 957 MW and an Apache West‐to--‐East (W2E) Rating of approximately 1,000 MW with the Tucson to Oracle 115--‐kV line re--‐conductor project in service. Doug Patterson (Southline Transmission Project) (415) 787-4209 3 3 3 The original SunZia Southwest Transmission Project was envisioned to be comprised of three segments of two 500 kV (AC) lines each from the renewable resource energy zone(s) in central New Mexico (referred to in this report as SunZia East) to the proposed Pinal Central 500 kV substation (to be operated by Salt River Project) in central Arizona. SunZia examined two intermediate electrical interconnections: one at a new SunZia South 500 kV substation near the existing Luna 345 kV substation in southwestern New Mexico (to be operated by El Paso Electric Company (EPE)), and another at the proposed Jim Hsu Power Engineers, Inc. (Southwestern Power Group) (480) 838-1427 Page 62 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Centennial West Clean Line HVDC Project 600 Q1/2018 7 North Gila-Imperial Valley #2 500 kV Project 500 Q3/2018 8 Pinal Central – Tortolita 500 kV Line 500 2016 Hassayampa – Pinal West 500-kV Line Loop-In: 500 Willow 345 kV Switchyard 345 Transfer Capability 3500 Phase 1 1 CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Willow 500 kV Substation (to be operated by Tucson Electric Power (TEP)) in southeastern Arizona. Taken together with these two intermediate substations, the three project segments are created: (1) SunZia East to SunZia South; (2) SunZia South to Willow 500 kV; and, (3) Willow 500 kV to Pinal Central. The modified POS will be changed slightly to exclude a 500/345kV transformer at Luna and include only one intermediate electrical interconnection at the Willow 500 kV Substation. The 3 SunZia South Substation will initially only include a series capacitor bank (70% series compensation). Additional information that is periodically updated is available at the SunZia Project Website: www.sunzia.net. 1 1 The project consists of a 900 mile 3,500 MW HVDC transmission line between northeastern New Mexico, north-central Arizona, and southern California. Request Copy of Report From Jim Hsu Power Engineers, Inc. for Centennial West Clean Line LLC. (480) 838-1427 2 The 85 mile NG-IV #2 500kV project is a major intertie expansion between the North Gila area (southwest Arizona) and the Imperial Valley area (southern California); this line would parallel the existing North Gila-Imperial Valley line (also known as the Southwest Power Link, or SWPL), with an expected separation of 250 feet from the existing SWPL. The potential for a second circuit would be proposed to be constructed on the same set of structures, and would potentially loop in and out of the existing Highline 230 kV substation along the Highline Canal. The second circuit could be operated at 230kV initially until the operational and scheduling need develops over the years to potentially operate at 500kV. An additional alternative that we have been asked to review by the PCRG is to have a single 500kV line and with the loop-in to the existing Highline 230kV station. Review is currently underway of this configuration. Jim Hsu Power Engineers, Inc. for Southwest Transmission Partners (480) 838-1427 .3 TEP plans to construct a 500-kV line from the proposed Pinal Central Substation to TEP’s Tortolita Substation. The expected in-service date for this project is 2016. TEP conducted an open season to solicit interest in this project. The Arizona Corporation Commission (ACC) granted a Certificate of Environmental Compatibility (CEC) in July 2012. EvaMarie King (TEP) (520) 745-3113 2015 .25 TEP plans to construct a 500-kV line loop-in that is less than 3 spans and will drop in from the existing line into the existing Jojoba switchyard. This project will provide connectivity between two existing 500kV transmission lines. The expected in-service date for this project is 2015. The FERC interconnection study is currently in progress. “ 2016 .3 TEP plans to construct the Willow 345-kV switchyard to accommodate a “ Page 63 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From generator interconnection request. This switchyard will accommodate the lines to the generator and loop-in TEP’s Greenlee – Winchester 345-kV line. The scheduled in-service date has been delayed to late 2016. A System Impact Study is underway regarding this interconnection request. The Willow switchyard may also accommodate other renewable generation interconnection request with in-service dates earlier than 2016. Studies have not begun on these requests. Tortolita-South 345 kV line 345 2022 .1 The project will tie two of TEP’s import points together. At this time, the project is expected to be in-service in 2021 but the schedule is tentative. Initial studies are expected to begin soon. “ Vail-South #2 345 kV line 345 2022 .05 Schedule is tentative and subject to change following the completion of study work to be conducted by TEP. A Comprehensive Progress Report will be issued when design studies are complete. ″ Westwing – South #2 345 or 500 kV Line or Pinal West – South #2 345 or 500 kV Line 500 or 345 2022 .05 Schedule is tentative and subject to change following the completion of study work to be conducted by TEP. A Comprehensive Progress Report will be issued when design studies are complete. ″ Tortolita – Winchester 500 kV Line 500 2022 .05 This is a new 500 kV transmission line project. The schedule is tentative and subject to change following the completion of study work to be conducted by TEP. ″ Winchester – Vail #2 345 kV Line 345 2022 .05 This is a second circuit between Winchester and Vail parallel to existing circuit. The schedule is tentative and subject to change following the completion of study work to be conducted by TEP. ″ Winchester – Vail #3 345 kV Line 345 2022 .05 This is a third circuit between Winchester and Vail parallel to existing circuit. The schedule is tentative and subject to change following the completion of study work to be conducted by TEP. ″ Springerville – Greenlee #2 345 kV line 345 2022 .05 The schedule for this project is tentative and subject to change following the completion of study work to be conducted by TEP. ″ Vail – Irvington – South 345 kV Line 345 2022 .1 TEP plans to construct a 345-kV line between TEP’s Vail and Irvington substations and between TEP Irvington and South substations. The tentative in-service date is 2021. Preliminary studies have been conducted as part of the Southeast Arizona Transmission Study (SATS) group. Additional study efforts will be undertaken prior to submitting a comprehensive progress report for the project. “ Tres Amigas Super Station 345 Q4 2017 4 1 Tres Amigas (TA) is developing the Phase I of the Tres Amigas Super Station (TASS) which will be an HVDC back to back connection between the Western Frank Barbera (203) 216-1060 750 MW Page 64 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From Electric Coordinating Council (WECC) and the Southwest Power Pool (SPP) systems. The Phase I will consist of a 750MW back to back HVDC system utilizing voltage source converter (VSC) technology. Phase II is anticipated to provide an interconnection between the SPP and ERCOT interconnects. Successive phases may increase the TASS capacity between the interconnects. The Tres Amigas project was placed in the WECC portal on September 17, 2010. The Initial Progress Report for the project was submitted to the WECC on February 23, 2012, which initiated the Project Coordination Process and periodic updates have been provided. The Comprehensive Progress Report, submitted on April 6, 2013, provided an overall description of the Phase I Project, results of studies performed by PNM and status of the TASS. Desert View- NVE Northwest 230 kV Line 230 12/2012 .2 640 MVA 1 As reported to WECC in previous annual reports, NV Energy (NVE) was originally planning to own this line; however, NVE decided to abandon these plans. As such, VEA has decided to permit and build this facility, which represents one of the two final segments of YEA's Pahrump to NVE Northwest 230 kV transmission project. VEA has nearly completed all project permitting efforts with the BLM and BIA. All major materials have been ordered and construction of this 4.5 mile segment is expected to begin in June, 2012 with an in-service date of December, 2012. Dale Broveak (775) 727-5312 VEA Stirling Mountain – Vista 230/138 12/2012 .1 192 MVA VEA has substantially completed all construction efforts on this 25 mile segment. The in- service date is coincident with the remaining four segments associated with the Pahrump to Northwest 230 kV project, which is anticipated to be December, 2012. “ Vista – Charleston 138 12/2013 .1 192 MVA VEA plans to construct a 138 kV line between VEA Vista Substation and VEA Charleston Substation. The tentative in-service date is December, 2013. VEA is currently permitting and acquiring right-of-way for this approximate 14 mile line. “ Vista – Pahrump 230 12/2012 .1 320 MVA VEA is finalizing the acquisition of right-of-way for this 13 mile segment. Major materials have been ordered and construction of this segment is expected to begin in September, 2012 with an in-service date of December, 2012. “ Desert View 230 kV Metering Station 230 12/2012 .1 VEA plans to construct the Desert View 230 kV Metering Station as a tie between VEA and NVE facilities for both electric as well as a VEA communications h u b near Las Vegas. Major materials have been ordered. VEA anticipated construction s t a r t i n g in June, 2012 with an inservice date of December, 2012. “ Stirling Mountain -Desert View 230 kV Line 230 12/2012 .1 VEA has substantially completed all construction efforts on this 38 mile segment. The in- service date is coincident with the remaining four “ 320 MVA Page 65 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 ARIZONA – NEW MEXICO - NEVADA POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability One Lines Maps Request Copy of Report From segments associated with the Pahrump to Northwest 230 kV project, which is anticipated to be December, 2012. San Luis – Rio Colorado Project 604 Q1/2013 170 This project consists of a 604 MW two-on-one combined cycle plant to be constructed one mile south of the Arizona (U.S.) / Mexico border. Interconnection will take place via two new 230 kV lines from the plant to the existing 161 kV Gila station and on to the existing North Gila station in Yuma, AZ Leonard York WAPA-DSW (602) 605-2797 Todd Rhoades WAPA – DSW 602-605-2613 Transmission Infrastructure Program (TIP) Project 230kV ED#5 – 230 kV Transmission Project 230 7/2014 1 Installed a second circuit, 22 miles long, on Western’s 115-kV Casa GrandeEmpire and Empire-ED5 transmission lines which were recently rebuilt as dual circuit steel monopoles, and 23 miles, on the SRP’s Duke-Pinal Central 500-kV steel monopoles. TIP Project ED#5 Substation Project 230 7/2014 1 Construct a new 230 kV substation at ED#5’s existing 115 kV yard. Project includes a 225 MVA 230/115/12.47 kV transformer, two breaker 230 kV ring bus configuration, 3 breaker and a half bays built to 230 kV standards but operated at 115 kV. “ 7/2014 1 Convert existing 4 breaker ring bus to 2 breaker and a half bays, add 2 new breaker and a half bays, and build tie line into SRP’s Duke substation. “ 10/2014 1 Add a new 230/69 kV substation, sectionalizing the Davis-Topock #1 transmission line. The 230 kV facilities will be a 3 breaker ring bus configuration. TIP Project Test Track Substation Expansion Project Longtin Substation Project 230/69 Michael Baird WAPA-DSW 602-605-4428 Page 66 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Date 12/2011 1 A new generating facility to be located in the city of Anaheim (County of Orange) will have a maximum net plant output of 194.1 MW. The project consists of four (4) GE LM6000 simple cycle natural gas combustion turbines and interconnects to ANHM’s 69 kV electrical system. Planned operating date of first unit is July 2011 and the overall project completion expected by December of 2011. Nam Nguyen ANHM (714) 765-5122 230 6/2012 .1 A new SVC (-75 / +200 MVAr) will be connected at the Tecnologico 230 kV substation (20111 “TEK-230”) for local voltage support and to increase reactive margin in the Valley Area of the CFE Baja California system. Jose Santamaria CFE 011 52 (686) 5581541 El Centinela 230 kV Substation 230 11/2011 .1 A new substation “El Centinela” (20453 “CNT-230”) is planned to be built between buses 20111 (TEK-230) and 20112 (STB-230). “ Carranza 230 kV Substation 230 5/2012 .1 A new substation “Carranza” (20461 “CZA-161”) is planned to be built between buses 20153 (GOR-161) and 20147 (CTY-161). “ Valle de Puebla 230 3/2012 .1 A new substation “Valle de Puebla” (20460 “VPA-230 “) is planned to be built between TL 20111 “TEK-230 “ – 20112 “STB-230 “ 230 kV. “ El Centenario 230 kV Substation 230 InService .1 New substation “El Centenario” (20453 “CNT-230 “) between TL 20118 “ROA230 “ – 20112 “STB-230 “ 230 kV. Commercial date, June 2013. “ San Luis Rey 230 kV Substation 230 9/2014 .1 New substation “San Luis Rey” (20454 “SLR-230 “) between TL 20104 “CPD230 “ – 20177 “PID-230 “ 230 kV. Commercial date, September, 2013. “ Transmission Line ROA – CPD 230 kV 230 6/2014 .1 TL 20118 “ROA-230” – 20104 “CPD-230” will be relocated on July, 2013. New line will be 20118 “ROA-230” – 20103 “WIS-230” – 20104 “CPD-230” “ 1/2014 .1 Three new gas turbine generators, 72.823 MVA capacity each, connected to Presidente Juarez 115 kV bus, 20019 PJZ-115. Total capacity 120 MW. Commercial date, January 2014. “ Canyon Power Project Tecnologico 230 kV SVC Generator Project Transmission kV 194 200 MVAR 120 Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps No. of pages Name of Project Gen MW Phase One Lines Request Copy of Report From Paul Didsayabutra CISO (916)608-1281 Generation Projects 7684 5/1/08 – 11/30/14 1 The following are generation projects in the ISO generation interconnection queue that the facility studies have been completed and the interconnection agreements have been executed: Devers Substation – 850 MW – 2010 Tesla Substation 230 kV bus E – 1156 MW – 11/30/14 El Segundo 220 kV bus – 630 MW – 6/1/13 “ Page 67 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From Devers-Palo Verde 500 kV line near Blythe – 520 MW – 2010 McCall Substation – 300 MW – 3/31/13 Eastshore Substation – 361 MW – 6/1/12 Between Cottonwood and Vaca-Dixon – 715 MW – 2010 Walnut Substation – 501 MW – 1/3/13 Imperial Valley Substation – 300 MW – 12/1/10 These projects are to be reported on by the individual entities responsible for them so the CISO will quit reporting in this forum. Imperial Valley – Dixieland Substation 230 kV Interconnection 230/92 12/2015 0 0 0 0 4 The project consists in constructing a new single circuit (prepared for double circuit) 230 kV transmission line from IID/SDG&E’s Imperial Valley Substation (IV Sub) to IID’s Dixieland Substation. The IV Sub to Dixieland Substation 230 kV transmission line will span an estimated 7.3 miles. The project also includes the installation of a 230/92 kV 300 MVA transformer at Dixieland Substation and interconnection facilities at Imperial Valley Substation. 1.3 David L Barajas 760-482-3450 (IID) The project will provide back-up for the potential outage of the existing “S” 230 kV transmission line. The new interconnection line will also increase the IID import/export capability to meet future load requirements. Ramon Substation 230/92 kV Transformer Addition 230/92 12/2015 .2 Path 42 Upgrade Project (IID’s Scope of Work) 230 12/2014 Imperial Valley Area Policy – Driven Transmission Line and Collector Station project 230 6/2015 225 MVA The project consist of installing a second 230/92kV 300 MVA auto-transformer and convert the existing Ramon Substation 230 kV and 92 kV ring bus to breaker-and-a- half bus configuration. The purpose of this project is to provide redundancy to the existing Ramon 230/92 kV transformer. “ .75 The project consists in reconductoring approximately 20 miles of a double circuit 230 kV transmission line from IID’s Coachella Valley substation to SCE’s Mirage Substation with one circuit looping in-and-out IID’s Ramon Substation. The project also includes converting the Coachella Valley Substation 230 kV from ring bus to breaker-and-a-half bus configuration, installing a 230 kV 48 MVAR capacitor bank at Coachella Valley Substation and the installation of a Path 42 Special Protection System for outages in IID’s 230 kV collector system and Path 42 intertie lines. “ 1 In December of 2012, the CAISO initiated an accelerated competitive solicitation process conducted for a policy-driven transmission line and collector station in the Imperial Valley area (the “IV Policy Element”). In July of 2013, the Imperial Irrigation District (IID) was selected as the Approved Project Sponsor to finance, own, construct, operate and maintain the IV Policy Element. The IV Policy – Driven Transmission Line and Collector Station Project, consists of a 230 kV collector station (Liebert station), located approximately one mile north of Imperial Valley (IV) Substation, and a short (approximately 1.4 mile) 230 kV transmission line connecting Liebert Station to IV Substation. The “ Page 68 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From transmission line and the Liebert Station will become network facilities and will be turned over to the ISO operational control, once IID complete the construction of additional facilities required to interconnect the IV Policy Element project to the IID electrical system. The additional facilities required to interconnect the IV Policy Element to the IID electrical system consist of a 230 kV Station (Fern) located in the north side of Liebert Station; a 230 kV bus tie between Fern Station and Liebert Station, and the connection of the 230 kV “S” line from El Centro Switching Station (ECSS) to Fern Station. In addition IID will construct a new 230 kV circuit from Fern Station to IV Substation as part of this project. Once the IV Policy Element and the additional facilities are constructed, IID will establish two points of interconnection in the south with the CAISO and San Diego Gas and Electric (SDG&E) – one via the bus tie between Fern station and Liebert CAISO operated station, and the other via the transmission line between Fern station and IV Substation. The project also includes the relocation of an existing Gen-Tie from a Solar Generation Station from IV Substation to Liebert CAISO operated station. El Centro Switching Station (ECSS) to Highline Station double circuit 230 kV transmission line 230 4/2018 .5 Rebuild the ECSS to Pilot Knob 161 kV and the ECSS to Drop No.4 92 kV double circuit transmission line sections (18 miles) from ECSS to East Highline Canal intersection, build one mile of double circuit 230 kV transmission line to extend the line into Highline station. Build one mile of double circuit 230 kV transmission line to interconnect the remaining 161 kV line to Pilot Knob and the 92 kV line to Drop 4. The project includes the following upgrades in ECSS and Highline stations: Highline Substation: Upgrade 230 kV and 92 kV switch yards and building a new 161 kV Bus section, to interconnect the new 230 kV circuits to ECSS, the 161 kV line to Pilot Knob and the 92 kV line to Drop No.4 Generation Station. ECSS Substation: Upgrade the 230 kV switch yard to breaker–and-a-half bus configuration to accommodate the new 230 kV circuits from Highline Substation. This project is part of the initial phase of IID’s Strategic Transmission Expansion Plan (STEP). “ El Centro Switching Station (ECSS) to Fern Station double circuit 230 kV transmission line 230 4/2018 .5 Re-build the ECSS to the proposed Fern station single circuit 230 kV “S” transmission line (Approximately 17 miles) to double circuit 230 kV. Upgrade the ECSS 230 kV switch yard to interconnect the new double circuit 230 kV line to Fern Station and upgrade the Fern Station to accommodate the second 230 kV circuit from ECSS. This project is part of the initial phase of IID’s Strategic Transmission Expansion Plan (STEP). “ Page 69 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Talega-Escondido/ValleySerrano 500 kV Interconnect Project (TE/VS Interconnect) LA Basin Re-powering Projects: Haynes Phase 2 Scattergood Transmission kV 500 600 530 Date No. of pages Transfer Capability Phase Q1/2014 1 1500 1 7/2013 12/2015 CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines The TE/VS Interconnect provides a high capacity link between the main backbone of California to San Diego Gas and Electric’s (SDG&E) 230 kV grid, providing the only 500 kV connection between the northern part of the SDG&E system and Southern California Edison’s (SCE) 500 kV grid. By adding a future link between the Sunrise Project’s 500 kV Central Substation and the TE/VS Interconnects Case Springs Substation, a 500 kV loop could be formed across the western section of the 500 kV lines from the Palo Verde area to Serrano on the north and Imperial Valley on the south. The project will also serve to connect the proposed 500 MW Lake Elsinore Advanced Pumped Storage (LEAPS) into the western grid. The TE/VS Interconnect is being permitted through the California Public Utilities Commission (A.10–07–001). Relevant FERC dockets: ER06–278, ER08–654. LEAPS License docket is P– 11858. 3 .1 2 0 0 Planned in-service date is June 1, 2013. .05 .05 Planned in-service date is December 2015. 0 0 Request Copy of Report From Rex Wait (760) 599-0086 The Nevada Hydro Company John Burnett 213-367-1744 (LDWP) Upgrade terminal equipment on NorthridgeTarzana 230kV Line 1 230 6/2015 797 Upgrade terminal equipment on Northridge-Tarzana 230kV Line 1 “ Reconductor both ValleyRinaldi 230kV Lines 230 6/2018 495 Reconductor both Valley-Rinaldi 230kV Lines “ Reconductor TolucaAtwater 230kV Line 1 230 TBD 708 Reconductor Toluca-Atwater 230kV Line 1 “ Add a second Victorville 500/287kV Transformer Bank 500/287 6/2023 460 Add a second Victorville 500/287kV Transformer Bank “ Replace Toluca 500/230kV Banks G and H 500/230 6/2019 913 & 930 Replace Toluca 500/230kV Banks G and H “ MWC Wind Generation 100 5/2011 .1 New wind farm to interconnect at Intermountain 345 kV switchyard. “ Owenyo Solar 200 12/2016 .1 New solar PV plant to interconnect at Cottonwood 230 kV substation. “ Planned Wind #12 204 10/2011 .1 New wind farm to interconnect with Barren Ridge-Rinaldi 230 kV. “ Planned Solar #2 250 5/2014 .1 New solar PV plant to interconnect at Barren Ridge 230 kV substation. “ Page 70 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From Pine Canyon Wind 150 4/2013 .1 The status is pending on the new wind farm to interconnect with the Pine Tree 230 kV substation. “ Planned Solar #3 350 12/2013 .1 The status is pending for the new solar PV plant to interconnect at MarketplaceAdelanto 500 kV substation. “ Planned Solar #6 150 8/2014 .1 Status is pending for a new solar PV plant to interconnect at McCullough 230 kV substation. “ Owenyo Solar 200 12/2015 .1 Status pending for a new solar PV plant to interconnect with the Cottonwood 230 kV substation. “ Adelanto Solar 9 12/2012 .1 Under construction for a new solar PV plant to interconnect with the Adelanto 500 kV substation. “ Planned Solar #8 90 12/2012 .1 Status is pending for new solar PV plant to interconnect with Barren Ridge 230 kV substation. “ Planned Solar #9 139 12/2013 .1 Cancelled the new solar PV plant to interconnect with Barren Ridge 230 kV substation. “ Planned Wind #11 300 12/2013 .1 New wind farm to interconnect with Barren Ridge-Rinaldi 230 kV. “ Planned Wind #14 200 12/2012 .1 New wind farm to interconnect with Barren Ridge-Rinaldi 230 kV. “ Planned Wind #8 201 12/2014 .1 New wind farm to interconnect with Cottonwood-Barren Ridge 230 kV. “ Planned Solar #17 300 12/2014 .1 New solar PV plant to interconnect with Barren Ridge-Rinaldi 230 kV.. “ Castaic Modernization Project 1255 1/2013 .1 The planned completion date for the Castaic Power Plant (Units 1 to 7) Modification Project is Janurary, 2013. ″ This project was identified in LADWP’s TPL-003 studies as a long-term resolution to potential overloads on the LADWP 230 kV system in the Los Angeles basin. This new line will parallel an existing 230 kV line between the Scattergood generating station and Receiving Station K. The ScattergoodOlympic 230 kV line #1 Project is expected to have no regional impact. “ Scattergood-Olympic 230 kV cable #1 Project 230 6/2015 349 MVA Page 71 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Barren Ridge Renewable Transmission Project (formerly Barren Ridge – Castaic Transmission Project) Transmission kV 230 Date No. of pages Transfer Capability 12/2016 .5 1600 MW Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines The planned in-service date is December 2016. It is budgeted and an RFP for construction has been issued. Request Copy of Report From ″ To accommodate LADWP’s planned renewable generation along the InyoRinaldi corridor LADWP is proposing the Barren Ridge Renewable Transmission Project (BRRTP) to access potential wind, solar and other clean, renewable resources from the Mojave Desert and Tehachapi Mountain areas of Southern California. The project is in Kern and Los Angeles Counties, and is approximately 77 miles in length from Barren Ridge Switching Station (BRSS) to Rinaldi Substation and 12 miles in length from Castaic Power Plant to the proposed Haskell Canyon Switching Station. The project will consist of: 1. Construction of a 230 kV double-circuit transmission line from the LADWP BRSS to Haskell Canyon Switching Station. 2. Addition of a 230 kV circuit on the existing double-circuit structures from Haskell Canyon to the Castaic Power Plant. 3. Upgrade the existing Barren Ridge – Rinaldi 230 kV transmission line with larger capacity conductors between the BRSS and the Rinaldi Substation. 4. Construction of a new switching station at Haskell Canyon. 5. Expansion of the existing BRSS. The ultimate capacity between the BRSS and the Haskell Canyon Switching Station is approximately 1600 MW, while the existing rating is 459 MVA. The BRRTP is expected to have no regional impact. Beacon Solar 250 1/2016 Project/Upgrade: Beacon Solar Location: Barren Ridge Switching Station Capacity: 250 MW Status: Under Construction In-Service Date: January 2016 “ Copper Mountain Solar 3 250 12/2015 Project/Upgrade: Copper Mountain Solar 3 Location: Marketplace Switching Station Capacity: 250 MW Status: Under Construction In-Service Date: December 2015 “ Moapa K-Road Solar 250 6/2016 Project/Upgrade: Moapa K-Road Solar Location: Crystal Switching Station Capacity: 250 MW Status: Under Construction In-Service Date: June 2016 “ Page 72 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From Mirant Marsh Landing Generating Station 888 2013 2 The Mirant Marsh Landing Generating Station (MLGS), a proposed project near Antioch, CA will consist of four Siemens Energy simple cycle combustion turbine-generator units. The units will be located adjacent to Mirant’s Contra Costa Power Plant and will interconnect to the existing PG&E Contra Costa Power Plant 230 kV switchyard through two 230 kV transmission lines. Each unit of the MLGS will have a net winter rating of 222 MW and a net summer rating of 193.5 MW. The expected commercial operation date for the MLGS is May 1, 2013. Chuck Hicklin 925-427-3544 Mirant Marsh Landing Lodi Energy Center Project 280 6/2012 1.5 NCPA has submitted an interconnection request to the CISO for the Lodi Energy Center Project. The project consists of a 1x1 combined cycle generation plant utilizing an F-Class technology gas turbine with a net output of 280 MW to the CAISO controlled grid. The project will interconnect to PG&E’s Gold Hill – Lodi Stig and Lodi Stig – Eight Mile Road 230 kV lines via the existing NCPA Lodi Switching Station. Michael DeBortoli 916-781-4258 (NCPA) Gates – Gregg 230kV Line Project 230 12/2022 .5 This project is to construct a 68 mile long 230kV DCTL from Gates to Gregg with one side strung. This project will improve reliability in the Greater Fresno area, allow greater operational flexibility of the three units at the Helms Pumped Storage Plant (PSP), and help integrate renewable resources within California. Since the proposed Gates – Gregg 230kV line will be in parallel with the existing Gates – Gregg 230kV line that is one of the Path 15 lines, this project will trigger re-definition of Path 15. In the 2012/13 Transmission Plan Process, the CAISO recommended and approved the Gates - Gregg 230kV transmission line, constructed as a double circuit line. One of the circuits is to be strung initially (by 2022 or earlier), and the other will be strung in the future after demand has increased sufficiently (anticipated in the 2025-2027 timeframe). In June 2013, the consortium of PG&E, MidAmerican Transmission and Citizens Energy submitted a bid to CAISO for the Gates-Gregg 230kV transmission line and was awarded the project in November 2013. Kang-Ling Ching 415-973-7637 (PG&E) Panoche-McMullin 230 kV Reconductoring 230 3/2014 .1 The Panoche-McMullin 230 kV Line will be reconductored to be capable of carrying 1893 amps under normal and emergency conditions. Upgrades to terminal equipment at Panoche and McMullin substations should be performed as necessary to accommodate the higher ratings. “ 12/2014 .1 Install redundant special protection schemes at multiple substations and Helms PSP to trip pumping units offline at Helms PSP. “ 4/2015 .1 The Henrietta to McCall section of the Gates-McCall 230 kV Line will be reconductored to be capable of carrying 1893 amps under normal and emergency conditions. Upgrades to terminal equipment at Gates, Henrietta and McCall substations should be performed as necessary to accommodate the higher ratings. “ Helms PSP Special Protection Scheme Henrietta-McCall 230kV Reconductoring 230 Page 73 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Date No. of pages Pittsburg - Tesla 230 kV Reconductoring 230 4/2015 .1 Reconductor the Pittsburg-Tesla 230 kV Nos. 1 and 2 Lines with larger capacity conductors. “ Newark - Ravenswood 230 kV Reconductoring 230 5/2015 .1 Reconductor the Newark - Ravenswood 230 kV Line with larger conductors. “ Tulucay 230/60 kV Transformer No.1 Capacity Increase 230/60 5/2015 .1 This project proposes to replace Tulucay Circuit Breaker No. 62 and all of its associated switches with a circuit breaker rated at 2000 Amps or higher. Any other associated terminal equipment will also be replaced as necessary “ Embarcadero-Potrero 230 kV Project 230 12/2015 .1 Construct a new 230 kV underground cable to connect Embarcadero and Potrero substations. “ McMullin-Kearney 230 kV Reconductoring 230 12/2015 .1 The McMullin to Kearney section of the Panoche-Kearney 230 kV Line will be reconductored to be capable of carrying 1893 amps under normal and emergency conditions. Upgrades to terminal equipment at Kearney and McMullin substations should be performed as necessary to accommodate the higher ratings. “ Weber 230/60 kV Transformer Nos. 2 and 2A Replacement 230/60 4/2016 .1 Replace Weber 230/60 kV Transformer Nos. 2 and 2a with a new transformer rated at least 300 MVA with LTC and associated equipment “ Kearney 230/70 kV Transformer 2 230/70 5/2016 .1 Install second 230/70 kV Transformer at Kearney Substation rated for 200 MVA or higher, install 4 element 230 kV ring, expand 70 kV bus and re-terminate lines “ 230 12/2016 .1 Reconductor the Contra Costa - Moraga 230 kV DCTL with larger capacity conductors. Moraga Transformer No. 2 Capacity Increase 230/115 12/2016 .1 Replace Transformer number 2, 230/115 kV at Moraga Substation with a 420 MVA rated unit. “ Midway-Kern PP 230 kV Line Nos. 1, 3 and 4 Capacity Increase Project 230 5/2017 .1 Replace limiting components at Kern PP and Midway Substations, to achieve full capacity on the Midway-Kern 230 kV Line Nos. 1, 3 and 4 “ Moraga - Castro Valley 230 kV Line Capacity Increase Project 230 12/2017 .1 Upgrade the limiting substation equipment (jumper conductors and wave traps) at Moraga and Castro Valley substations “ 230/115 12/2017 .1 This project proposes to install a 230/115 kV transformer at Fulton Substation rated for 420 MVA or higher. “ 230 12/2017 .1 Reconductor limiting sections of Tesla - Newark 230 kV No. 2 with larger capacity conductors. “ Contra Costa – Moraga 230 kV Reconductoring Fulton 230/115 kV Transformer Tesla - Newark 230 kV Upgrade II Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Name of Project Gen MW Phase One Lines Request Copy of Report From Page 74 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Date No. of pages Rio Oso 230/115 kV Transformers 230/115 12/2017 .1 Replace the Rio Oso 230/115 kV transformers (Nos. 1 and 2) with two 420 MVA rated transformers. Convert 115 kV bus to BAAH. “ Rio Oso Area 230 kV Voltage Support 230 12/2017 .1 Install a new Static Var Compensator (SVC) at Rio Oso Substation and a new Shunt Capacitor at Atlantic Substation. “ Pittsburg 230/115 kV Transformer Capacity Increase 230/115 5/2018 .1 Install 3rd 230/115 kV Transformer at Pittsburg Substation with a rating of 420 MVA “ Ashlan-Gregg and AshlanHerndon 230 kV Reconductor 230 5/2018 .1 Reconductor limiting sections of Ashlan-Gregg and Ashlan-Herndon 230 kV sections with higher rated conductors. “ San Mateo Synchronous Condensor Replacement 115 5/2018 .1 Install reactive support device to replace old synchronous condensers at 115kV. “ Vaca Dixon - Lakeville 230 kV Reconductoring 230 6/2018 .1 Reconductor the Vaca – Lakeville No. 1, Tulucay – Vaca, and Tulucay – Lakeville 230 kV Lines with larger capacity conductors. “ Borden 230 kV Voltage Support 230 5/2019 .1 This project proposes to loop the Wilson-Gregg 230 kV Line into Borden Substation (Borden) and install 200 MVARs of mechanically switched capacitors on the Borden 230 kV bus. “ Morro Bay 230/115 kV Transformer 230/115 5/2019 .1 Install an additional 230/115 kV transformer at Morro Bay Substation rated for 200 MVA or higher. “ Kern PP 230 kV Area Reinforcement Project 230 12/2019 • Convert Kern PP 230 kV double bus single breaker arrangement to breaker and a half • Replace limiting equipment on Kern PP 230/115 kV transformer No. 4 as necessary to achieve full transformer rating • Install a 230/115 kV Transformer Special Protection Scheme at Kern 115 kV to mitigate overloads of Kern PP Transformer Nos. 3, 4, and 5 “ Wheeler Ridge Voltage Support 230 5/2020 .1 Install three 75 MVAR steps of mechanically switched capacitors on the Wheeler Ridge 230 kV bus, expand the 230 kV bus as necessary reconductor 0.5 miles of the Wheeler Ridge-Lakeview 70 kV line and transfer Copus from the Old River-Copus 70 kV line to the Wheeler Ridge-Lakeview 70 kV line. “ Rio Oso – Atlantic 230 kV Line 230 11/2022 .1 Construct a second Rio Oso – Atlantic 230 kV Line. “ Contra Costa sub 230kV Switch Replacement 230 5/2016 .1 Replace 230 kV Switch No. 239 at Contra Costa Substation that currently limits the Contra Costa PP-Contra Costa Sub 230 kV Line to 1600 Amps. Any other limiting element will be replaced as well. “ Name of Project Gen MW Phase One Lines Request Copy of Report From Page 75 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Date No. of pages Gates No. 2 500/230 kV Transformer 500/230 12/2017 .1 Install a second 500/230/13.8 kV transformer (three single-phase units, 374 MVA each) at Gates Substation “ Kearney-Herndon 230 kV Line Reconductor 230 12/2017 .1 Reconductor 10 miles of the Kearney - Herndon 230 kV Line “ Warnerville-Wilson 230 kV Series Reactor 230 12/2017 .1 Install a 230 kV multi-step Reactor totaling 50.5 ohms, and associated equipment at Wilson Substation, on the Warnerville-Wilson 230 kV line “ Diablo Canyon Voltage Support Project 230 5/2018 .1 Install a +150/-75 MVAR Reactive support device at Diablo Canyon 230 kV Substation “ Lockeford-Lodi Area 230 kV Development 230 5/2020 .1 Construct new 15 mile 230 kV DCTL from Eight Mile Substation to Lockeford Substation Midway-Andrew 230 kV 230 12/2020 .1 Upgrade existing 65 miles long Midway-Santa Maria 115KV line to 230kV “ Moraga-Potrero 230 kV Project 230 12/2020 .1 Establish a 230 kV connection between Moraga and Potrero Substations. “ Name of Project Gen MW Phase One Lines Request Copy of Report From Solar Star Generation Interconnection Project 110 6/2015 .1 Build a 230 kV Quinto Switching Station to interconnect 110 MW solar generation to Pacific Gas and Electric Company's (PG&E's) Los Banos-Westley 230 kV Line and reconductoring 26 miles of the line from switching station to Westley Sub “ Stockton Generation Expansion Project 508 5/2017 .1 Stockton Generation, LLC, proposing to interconnect two gas turbines and a steam turbine with a combined output of 508 MW. The proposed Commercial Operation Date of the project is May 1, 2014. The project will interconnect with PG&E’s Bellota – Tesla No. 2 and Weber-Tesla 230 kV transmission lines by looping these lines into a new switching station and require reconductoring of the Warnerville-Wilson 230 kV Line. “ 2012-18 3.5 LeGrand – Chowchilla 115 kV Reconductoring – June 2015 Corina – Eagle Rock 115 kV Reconductor – May 2014 North Valley and Sierra 230 kV line Capacity Increase – May 2015 Other Transmission Projects – Granted Waiver of “Significant Transmission Project” Status 115/230 Kang-Ling Ching 415-973-7637 (PG&E) Page 76 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From SMUD Solano Wind Phase III Generation Interconnection Project 128 3/2012 .3 The SMUD Solano Wind Project Phase III Generation Interconnection (the “Project”) consists of forty-four (44) wind turbine Generating Units each rated at 3 MW. The maximum net output to the CAISO Controlled Grid will be 128 MW. The step-up transformers are one three phase, 3.16 MVA, 1/34.5 kV for each wind turbine Generating Unit and one three-phase, 166 MVA, 34.5/230 kV for the total output of the Project. The Project will be connected to the existing Sacramento Municipal Utility District (SMUD) Russell Substation 230 kV bus which is connected to PG&E’s Birds Landing Switching Station 230 kV bus. “ Calpine Russell City Energy Center 600 7/2012 .1 Interconnect 600 MW generation project to PG&E's East shore Substation 230 kV Bus. Convert bus. Replace transformer. Build 230 kV generation tie line. “ Green Ridge Wind Power Project 75 10/2012 .3 Green Ridge Power, LLC is proposing to repower the Jackson Substation via Green Ridge Wind Power Generation Interconnection Project. This project will interconnect 75.1 MW (net output) wind power-based generation facility to the PG&E transmission system. Jackson Substation is currently interconnected onto PG&E’s Lone Tree-Cayetano 230 kV Line. “ Montezuma II Wind Generation Interconnection Project 78 5/2014 .3 NextEra Energy Resources, LLC (NextEra), proposed to interconnect its Montezuma II Wind Project (The Project) to the California Independent System Operator Corporation (“CAISO”) Controlled Grid. The Project consists of 34 Siemens wind turbine generating units each rated at 2.3 MW with total output of 78.2 MW. This project proposes to interconnect to a new ring bus at the existing Montezuma Project (High Winds III) Substation. “ Franklin 230/69 kV bulk substation 230/69 2018 1 The existing Rancho Seco – Pocket 230 kV #2 line will be looped in to a new 230/69 kV bulk substation at Franklin, Sacramento County, to serve local load growth. Anticipated in-service date is 2018. Dilip Mahendra 916-732-6180 (SMUD) Bay Blvd (formerly Bayfront) Substation Transmission Project 230/69 12/2016 .1 The Bay Blvd 230/69 kV Substation Transmission project is designed and constructed to better serve SDG&E local load and includes the following scope of work: 1) Construct a new 230/69 kV substation that will replace the existing South Bay 138/69 kV substation; 2) Install two 224 MVA 230/69 kV transformers; 3) Loop in the Miguel-Silvergate 230 kV transmission line into the new substation; 4) Transfer all 69 kV lines presently connected to the South Bay 138/69 kV substation to the new substation; and 5) Re-configure existing 138 kV lines to eliminate the need for the South Bay 138 kV bus. David Wang 858-654-8162 (SDGE) Page 77 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project South Orange County Reliability Enhancement Project ECO 500/138 kV Substation Gen MW Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Date No. of pages 230/138 12/2018 .7 The project scope contains transmission and distribution work. The system changes required to accommodate the new Capistrano 230/138/12kV substation are as follows: a. Distribution Rebuild the aging and obsolete distribution equipment (138kV & 12kV) at Capistrano substation using three new 138/12kV transformers (ultimate 4138/12kV banks). b. Substation Construct a new gas insulated (GIS) 230kV switchyard at the existing Capistrano substation with two 230/138kV transformers and a 230kV capacitor. c. Transmission Construct two new 230kV circuits from Talega to Capistrano, one from SONGS and the other from Talega (tapping the existing TL23030 from Escondido), by rebuilding the existing TL13835 with double-circuit structures (8 miles between Talega and Capistrano). Terminate six adjacent 138kV lines at Capistrano sub. “ 500/230/135 11/2014 1 This project will construct a 500/230/138kV substation near the Southwest Powerlink (SWPL), between Imperial Valley substation and Miguel substation, and it will extend a 138kV line from the new substation to the existing Boulevard substation. Also, the project will rebuild Boulevard substation on a neighboring site in order to accommodate generation interconnections at Boulevard. Scope of work include: a. Substation i. Site preparation ii. Construction of the new 500/230/138kV substation iii. Site preparation for new Boulevard substation location (near or adjacent to existing site) iv. Construction (rebuild) of 138/12kV Boulevard substation on neighboring site b. Transmission i. Loop SWPL into the new ECO substation. ii. Construction of a new 14-mile twin circuit 900 ACSS 138kV transmission line from the new ECO substation to rebuilt Boulevard substation. c. Other i. Construction of new microwave communications facilities ii. ECO substation land purchase iii. Boulevard substation adjacent land purchase iv. Acquisition of a new ROW for the new 138kV transmission line “ Phase One Lines Request Copy of Report From Page 78 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Date No. of pages Transfer Capability 500/230 3/2013 .5 1100 MVA Sycamore-Penasquitos 230 kV Line Project 230 6/2017 Artesian 230 kV Expansion 230 New 230/69 kV Transformer at Mission 230 Name of Project 3rd 500/230 Transformer Bank (IV Bank 82) at Imperial Valley Substation Gen MW Transmission kV Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From This project will add 500/230 transformer at SDG&E’s Imperial Valley Substation. Scope of work include: a. Substation i. Site preparation ii. Add 3rd 500/230 transformer at 1100MVA rating. “ .5 1. Project Scope a. new 230 kV line connecting two substations, Sycamore and Penasquitos, owned by SDG&E within SDG&E control area. 2. The estimated project In-Service-Date is June 2017. 3. Project Status: CAISO approved 4. Facility Owner: SDG&E in conjunction with and Citizen Energy 5. No Regional Impact – This is an internal system upgrade that balances power flows among transmission lines into load centers with SDG&E control area. It has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ 6/2016 .5 1. Project Scope a. Expend Artesian 69 kV substation to 230/69 kV substation adding one 230/69 kV transformer b. Loop in existing Sycamore – PEN 230 kv line at Artesian 230. 2. The estimated project In-Service-Date is June 2016. 3. Project Status: CAISO approved 4. Facility Owner: SDG&E 5. No Regional Impact – This is an internal system upgrade that provides additional source to 69 kV system around Poway area. It has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ 6/2018 .25 1. Project Scope: replace two 138/69 kV transformers with one 230/69 kV transformer at SDG&E Mission Substation 2. The estimated project In-Service-Date: June 2018 3. Project Status: CAISO approved 4. Facility Owner: SDG&E 5. No Regional Impact – This is an internal system upgrade that mitigates local contingency overloads and provides better local voltage control. It has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ Page 79 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Transmission kV Date 6/2015 .25 1. Project Scope: 2x(+225/-120) MVAr synchronous condenser at Talega Substation. 2. The estimated project In-Service-Date: June 2015 3. Project Status: CAISO approved 4. Facility Owner: SDG&E 5. No Regional Impact – This is an internal system upgrade that provides needed voltage support. It has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ 6/2017 or 18 .33 1. Project Scope: 2x(+225/-120) synchronous condenser at SDG&E SONGSMESA Substation/Switchyard that would be built near existing San Onofre Substation. 2. The estimated project In-Service-Date: June 2017 or 2018 3. Project Status: CAISO approved 4. Facility Owner: SDG&E 5. No Regional Impact – This is an internal system upgrade that provides needed voltage support. It has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ San Luis Rey Synchronous Condenser 6/2016 .33 1. Project Scope: 2x(+225/-120) MVAr synchronous condenser at SDG&E San Luis Rey Substation 2. The estimated project In-Service-Date: June 2016 3. Project Status: CAISO approved 4. Facility Owner: SDG&E 5. No Regional Impact – This is an internal system upgrade that provides needed voltage support. It has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ Shunt Reactor at Suncrest 6/2014 .33 1. Project Scope: Install three single phase reactors at Suncrest Substation and connect to the 500 kV bus. Each reactor will be rated 46 MVar at 317.5 kV phase to ground for a three phase total of 138 MVar at 550 kV. 2. The estimated project In-Service-Date: June 2014 3. Project Status: Submitted for information only to CAISO as part of SDG&E’s 2013 Grid Assessment plan. 4. Facility Owner: SDG&E 5. No Regional Impact – This is an internal system upgrade that provides needed voltage control within SDG&E’s service territory and has no impact on neighboring electric systems. SDG&E therefore requests a waiver from “Significant Transmission Project” status. “ 4/2018 .2 Build 63 miles of 220 kV line between SCE’s existing Coolwater 220/115 kV Substation and Lugo 500/220 kV Substation. Talega Synchronous Condenser SONGSMESA Synchronous Condenser Coolwater-Lugo (South of Kramer) 220 kV T/L 220 Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps No. of pages Name of Project Gen MW Phase One Lines Request Copy of Report From David Franklin 626-302-0372 (SCE) Page 80 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Date No. of pages Primm 220 kV Substation 220 10/2015 .2 Construct new Primm 220 kV Substation to interconnect renewable generation projects. “ Path 42 Upgrade Project (SCE’s Scope of Work) 220 12/2014 .2 Install relays at Devers and Mirage Substations in support of IID’s Path 42 RAS, and upgrade the following transmission lines post Devers-Coachella Valley Loop-in Project: •Devers-Mirage 220 kV # 1 T/L •Devers-Mirage 220 kV # 2 T/L •SCE-owned portion of Mirage-Ramon 220 kV T/L •SCE-owned portion of Mirage-Coachella Valley 220 kV T/L IID is a co-sponsor for this project. Please contact IID for its scope of work regarding the Path 42 Upgrade Project. “ San Joaquin Cross Valley Loop Project 230 9/2014 .1 Construction of a new 18.5 mile double-circuit 230 kV transmission line that would connect Rector Substation to an existing 230 kV line from SCE’s Big Creek hydroelectric facilities in the Siera Nevada Mountains. Loop Big Creek 3-Springville 230 kV line into Rector. ″ 500/230 10/20092/2016 .05 Change the description to – Construct the following 500 kV and 220 kV transmission facilities needed to connect 4500 MW renewable generation in the Tehachapi area: -Pardee 220 kV (In-Service) -Service) -Vincent 500 kV (In-Service) – WindHub 500 kV (In-Service) – Vincent 500 kV #2 (In-Service) -in of Midway – Vincent #3 500 kV (InService) – Whirlwind 500 kV (In-Service) “ Tehachapi Renewable Transmission Project Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Name of Project Gen MW Phase One Lines Request Copy of Report From – WindHub 500 kV (In-Service) – Rio Hondo 500 kV (Energized at 220 kV) – Mira Loma 500 kV – Mesa 500 kV (Energized at 220 kV) Alberhill 500/115 kV Substation 500/115 1/2018 .05 Develop a new 1120 MVA Alberhill 500/115 kV Substation and associated transmission lines. Construct a new 500/115 kV transmission substation (Alberhill Substation), connecting SCE’s existing Serrano-Valley 500 kV transmission line into the new Alberhill Substation with two new 500 kV line segments. Construct a new 115 kV subtransmission line and modifications to existing 115 kV subtransmission lines. “ Page 81 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Date No. of pages Wildlife (formerly Jurupa) 230 kV Substation 230 7/2020 .1 Develop a 560 MVA Wilderness 220 kV Substation for Riverside. Loop the existing Mira Loma-Vista 220 kV #1 line and construct about 7 miles of double circuit T/Ls to Wilderness 220 kV that provides a method of service to a new substation that will serve the City of Riverside. “ Riverside 220 kV Interconnection 220 7/2020 .1 The project will be constructed at the same time as and adjacent to Wildlife 230 kV Substation project and will be tied to Wildlife 230 kV. “ West of Devers (WOD) Upgrade Project 230 2020 .1 Upgrade four (five with El Casco Substation loop-in) 220 kV lines on the west side of Devers 220 kV substation to 2B-1590 ACSR conductor. “ Valley-Serrano 500 kV #2 Transmission Line 500 6/2019 .05 Construct a second Valley-Serrano 500 kV transmission line to provide load service capacity. “ 6/2024 .05 Master Plan to build transmission lines and substations to serve load in San Joaquin Valley area. “ North of Magunden Long Term Plan Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Name of Project Gen MW Phase One Lines Request Copy of Report From Mesa 500/230 kV Substation 500/230 6/2019 .05 Develop a new 500/230 kV Substation equipped with 2 x 1120 MVA transformers. “ Lighthipe 500/230 kV Substation 500/230 6/2019 .05 Develop a new 500/230 kV Substation equipped with 2 x 1120 MVA transformers. “ Manzana Wind 300 12/2015 .1 Interconnect a 300 MW Wind Generating Facility to SCE's Whirlwind 220 kV Substation. Project is being phased in that will be completed by the operating date. “ Blythe Solar Power 485 6/2015 .1 Interconnect a 485 MW Solar Generating Facility to SCE's expanded Colorado River 500/200 kV Substation. “ Palen Solar 500 6/2016 .1 Interconnect a 500 MW Solar Generating Facility to SCE's proposed Red Bluff 500/220 kV Substation. “ Abengoa Solar Project 250 4/2013 .1 Interconnect a 250 MW Solar Generating Facility to SCE's proposed Lockhart 220 kV Substation. “ Genesis-McCoy Solar Project 500 5/2016 .1 Interconnect a 500 MW Solar Generating Facility to SCE's expanded Colorado River 500/220 kV Substation. “ Desert Stateline 300 10/2015 .1 Interconnect a 300 MW Solar Generating Facility to SCE's Ivanpah 220 kV Substation. “ Silver State South 220 10/2015 .1 Interconnect a 220 MW Solar Generating Facility to a new SCE Primm 220 kV Substation. “ Page 82 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Name of Project Gen MW Transmission kV Date No. of pages Transfer Capability Phase CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps One Lines Request Copy of Report From Pacific Wind Project 250 12/2015 .1 Interconnect a 250 MW Wind Generating Facility to SCE's Whirlwind 220 kV Substation. Project is being phased in that will be completed by the operating date. “ Alta 2012 Project 720 6/2017 .1 Interconnect a 720 MW Wind Generating Facility to SCE's Windhub 220 kV Substation. Project is being phased in that will be completed by the operating date. “ North Sky River Wind Project 297 6/2015 Interconnect a 297 MW Wind Generating Facility to SCE's Highwind 220 kV Substation. Project is being phased in that will be completed by the operating date. “ Antelope Valley Solar PV 1 310 6/2015 .1 Interconnect a 310 MW Solar Generating Facility to SCE's Whirlwind 220 kV Substation. Project is being phased in that will be completed by the operating date. “ Antelope Valley Solar PV 2 276 6/2015 .1 Interconnect a 276 MW Solar Generating Facility to SCE's Whirlwind 220 kV Substation. Project is being phased in that will be completed by the operating date. “ .1 Install a new 500/220 kV AA-bank at Eldorado Substation connected to the SCE-owned Eldorado 220 kV switchyard. Desert Stateline and Silver State South triggered the need for this AA-bank. “ Add a second transformer bank at the existing Whirlwind Substation to add capacity to deliver new renewable generation interconnecting to the 220 kV bus. “ SCE Owned Eldorado 500/220 kV 5AA-Bank 500/220 kV 10/2015 Whirlwind 2nd 500/220 kV Transformer 500/220 kV 9/2014 Rector SVS Expansion 220 kV 12/2014 .1 Expand Rector Static VAR System (SVS) by adding three 79.2 MVAR Shunt Capacitor Banks at Rector Bus and SVS control points to maintain minimum voltages at Rector 220 kV. “ East Kern Wind Resource Area (EKWRA) 66 kV Project 66 kV 12/2014 .1 Description: Reconfigure Antelope-Bailey 66 kV system into two separate systems. The northern system will be served radially from Windhub Substation. The southern system will remain parallel to the existing Antelope and Bailey 220 kV systems. “ Interconnect a 150 MW Wind Generating Facility to SCE's Whirlwind 220 kV Substation via a shared generation tie line with the Pacific Wind Project. Project is being phased in that will be completed by the operating date. “ Catalina Wind Project 150 6/2015 Eldorado-Lugo Series Cap Upgrade 12/2016 .1 Upgrade series capacitor and terminal equipment at Eldorado and Lugo to 3800A/4000A (SN/SE) Lugo-Mohave Series Cap Upgrade 12/2016 .1 Upgrade series capacitor and terminal equipment at Mohave to 3800A/4000A Page 83 of 91 Revised 8/6/2014 LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014 CALIFORNIA-MEXICO POWER AREA Transfer Capability CONTENTS AND REMARKS Power Transient Post Transient Tables Flow Stability Stability Maps Transmission kV Date No. of pages Whirlwind 3rd 500/220 kV Transformer Bank 500/220 3/2017 .1 Add a third transformer bank at the existing Whirlwind Substation to add capacityto deliver new renewable generation interconnecting to the 220kV bus. Kramer-Lugo 230 kV No. 1 &2 230 2015 .1 Loop-in the Kramer-Lugo 230 kV No. 1 and No. 2 lines into Victor Substation creating Kramer-Victor 230 kV No. 1 and No. 2 and Lugo-Victor 230 kV No. 1 and No. 2. Name of Project Gen MW Phase One Lines Rising Tree Project 200 10/2015 .1 Interconnect a 200 MW Wind Generating Facility to SCE’s Windhub 220 Substation via a generation tie line. Project is being phased in that will be completed by the operating date. Alta Wind Q97 160 10/2016 .1 Interconnect a 160 MW Wind Generating Facility to SCE’s Whirlwind 220 Substation via a generation tie line shared with Alta Wind Q153. Alta Wind Q153 100 10/2016 .1 Interconnect a 100 MW Wind Generating Facility to SCE’s Whirlwind 220 Substation via a generation tie line shared with Alta Wind Q97. SVP Phase Shifting Transformer Project (SVPPST) 230 2014 2 400 MVA 0 0 0 0 1 SVP will install a 400 MVA, 230/230 kV phase shifting transformer in the SVP SSS station, located adjacent to the PG&E Los Esteros Substation in Santa Clara County, California. The transformer will be placed in series with the SSSNRS 230 kV circuit. A 4 ohm series reactor will also be installed between the bus sections of the SVP NRS 115 kV bus to allow for closing the currently open 115 kV bus tie. SVP is currently coordinating with Pacific Gas and Electric Company to determine what electric system improvements, if any, may be needed on its system. Request Copy of Report From Orville Plum (408)261-5470 Silicon Valley Power (SVP) Page 84 of 91 Revised 8/6/2014 Attachment I Member Systems reporting significant facilities* in the 2013 Annual Progress reports to WECC from which, as of July 31, 2014, no report has been received: 1. Lucky Corridor 2. Sea Breeze Pacific RTS 3. NV Energy South 4. TCP 5. Wyoming Colorado Intertie 6. Sithe Global 7. LS Power 8. Southline Transmission Project 9. Centennial West Clean Line LLC. 10. Tres Amigas 11. VEA 12. ANHM 13. CFE 14. CISO 15. The Nevada Hydro Company 16. Mirant Marsh Landing 17. NCPA * Projects listed as “In service” will be removed from the next issue of this log. Attachment II Member Systems previously reporting significant facilities* in the WECC Transmission Database from which, as of July 31, 2013, no report has been received: 1. Northwest Alberta Transmission System Reinforcement (2011-12) AESO 2. 9L15 termination into Livock AESO 3. Northwest Alberta Transmission System Reinforcement (2015-17) AESO 4. Southeast Transmission Reinforcement (SETR) AESO 5. Yellowhead Area Transmission Development – P671 AESO 6. Livock 240/144 kV Connection – P834 AESO 7. Fidler 312S 240/138 kV Interconnection – P936 AESO 8. Northeast Fort McMurray 240 kV Loop – P791 AESO 9. Halkirk 1 Wind Project – P723 AESO 10. Christina Lake Area Development AESO 11. Algar 240/144 kV substation AESO 12. Algar-Kinosis 240 kV line AESO 13. Alberta Industrial Heartland Bulk Transmission Development – State 2 AESO 14. P116 – Foothills Area Transmission Development AESO 15. C-Free Power Oven Wind-P763 AESO 16. Edmonton - Calgary West DC Lline – P962 AESO 17. Edmonton - Calgary East DC Lline – P961 AESO 18. Bow City Power Project-P465 AESO 19. Pikani Energy Corp. Wind-P773 AESO 20. Vindt Willowridge – P614 AESO 21. Bloodtribe Wild Turnip Hill AESO 22. P635 - Suncor Hand Hills Wind Energy Project AESO 23. P678 - Nexen Hand Hills Wind Project AESO 24. P811 - Central East Transmission Development AESO 25. P812 - Hanna Region Transmission Development AESO 26. Noxon Rapids Turbine Upgrades AVA 27. Metro North Area 230 kV Reinforcement BCHA 28. Merritt Area Transmission Project BCHA 29. Revelstoke Unit 6 Installation BCHA 30. North Cross Cascade 500 kV Line Project BPA 31. John Day Substation – Golden Hills 200 MW (G00099-2) BPA 32. Shepherds Flat Wind Phase 1 (aka North Hulburt Wind) (G0118 and G0291) BPA 33. Montague I BPA 34. Lower Snake Wind BPA 35. Miller Ranch Wind BPA 36. Golden Hills Wind BPA 37. Rapids – Columbia 230 kV Transmission Line DCPUD 38. Columbia – Larson 230 kV Line GCPUD 39. King 230/138 kV Project IPC 40. Pearl Transmission Substation IPC * Projects listed as “In service” will be removed from the next issue of this log. 41. Midpoint T232 230/138 kV Transformer Addition Project IPC 42. Lucky Corridor Transmission Project Lucky Corridor 43. Mountain States Transmission Intertie Project NWMT 44. Current Creek PAC 45. Pear – Sherwood 230 kV Retermination PGE 46. Trojan-Horizon 230 kV line PGE 47. McLoughlin 230 kV Bus Sectionalizing Breaker PGE 48. Jefferson County 115 kV Upgrade Phase II PSEI 49. Sea Breeze Pacific Regional Transmission System Sea Breeze 50. Sea Breeze Pacific – West Coast Cable Project Sea Breeze 51. Sea Breeze Pacific – Juan de Fuca Cable Project (jdF) Sea Breeze 52. Southwest Intertie Transmission Project (SWIP) NV Energy 53. Southern Nevada Intertie Transmission Project NV Energy 54. Blackhawk 345/120 kV Substation (was Emma) NV Energy 55. Fallon 230 kV Source NV Energy 56. One Nevada Transmission Intertie Project NV Energy 57. 230 kV Re-Termination Project TPWR 58. Canyon Substation / Switching Station TCP 59. Zephyr Project TCP 60. Chinook Project TCP 61. Dry Fork Station BEPC 62. Undervoltage Load-Shedding Scheme BHP 63. San Lues Valley – Calumet – Comanche Transmission Project PSC 64. Cogentrix of Alamosa PSC 65. Limon 1 & 2 PSC 66. San Luis Valley – Calumet – Comanche Transmission Project TSGT 67. Miracle Mile Substation TSGT 68. Wyoming Colorado Intertie WCI 69. Navajo Transmission Project Segment 1 Sithe Global 70. Great Basin Transmission SWIP – South Project LS Power 71. Great Basin Transmission SWIP – North Project LS Power 72. McDonald 230/138 kV Addition NVE 73. Brooks 230/138/12 kV Substation and Pecos – Brooks 230 kV Line NVE 74. Sunrise 500/230 kV Transmission Substation NVE 75. Robinson – Harry Allen Transmission Line #2 Project NVE 76. Northwest 500/230 #2 Transformer Addition NVE 77. Sunrise 500/230 kV #2 Transformer Addition NVE 78. Eastern Mining Area Expansion Project SRP 79. Silver King – New Pinto Valley 230 kV Line SRP 80. Schrader – Abel 230 kV Line SRP 81. Kyrene 500/230 kV Transformer SRP 82. Rudd 230/69 kV Transformer SRP 83. Schrader 230/69 kV Transformer SRP 84. Resolution Copper 230 kV Line SRP 85. Abel 230 kV Generation SRP 86. Other Joint SRP/APS Projects SRP * Projects listed as “In service” will be removed from the next issue of this log. 87. Other SRP 115/230/345 kV Transmission Project 88. Southline Transmission Project 89. Centennial West Clean Line HVDC Project 90. Willow 345 kV Switchyard 91. Winchester – Vail #2 and #3 345 kV Lines 92. Desert View – NVE Northwest 230 kV Line 93. Stirling Mountain – Vista 94. Vista – Charleston 95. Vista – Pahrump 96. Desert View 230 kV Metering Station 97. Stirling Mountain – Desert View 230 kV Line 98. San Luis – Rio Colorado Project 99. Canyon Power Project 100. Tecnologico 230 kV SVC 101. El Centinela 230 kV Substation 102. Carranza 230 kV Substation 103. Valle de Puebla 104. Generation Projects SRP Southline Centennial West TEP TEP VEA VEA VEA VEA VEA VEA WAPA DSW ANHM CFE CFE CFE CFE CISO Devers Substation Tesla Substation El Segundo 220 kV bus Devers-Palo Verde 500 kV line near Blythe McCall Substation Eastshore Substation Between Cottonwood and Vaca-Dixon Walnut Substation Imperial Valley Substation 105. Talega-Escondido/Valley-Serrano 500 kV Interconnect Project (TE/VS Interconnect) The Nevada Hydro Company 106. MWC Wind Generation LDWP 107. Owenyo Solar LDWP 108. Planned Wind #12 LDWP 109. Adelanto Solar LDWP 110. Planned Solar #9 LDWP 111. Planned Wind #11 LDWP 112. Planned Wind #14 LDWP 113. Planned Wind #8 LDWP 114. Planned Solar #17 LDWP 115. Castaic Modernization Project LDWP 116. Mirant Marsh Landing Generating Station Mirant Marsh Landing 117. Lodi Energy Center Project NCPA 118. Other Transmission Projects Granted Waivers PG&E 119. Colusa Generating Station PG&E 120. SMUD Solano Wind Phase III Generation Interconnection Project PG&E 121. Calpine Russell City Energy Center PG&E 122. Green Ridge Wind Power Project PG&E 123. Montezuma II Wind Generation Interconnection Project PG&E 124. Franklin 230/69 kV Bulk Substation SMUD 125. 3rd 500/230 Transformer at Imperial Valley Substation SDGE * Projects listed as “In service” will be removed from the next issue of this log. 126. SVP Phase Shifting Transformer Project * Projects listed as “In service” will be removed from the next issue of this log. SVP Attachment III List of Projects Requesting A Waiver of “Significant Transmission Project” Status Project Name Organization 1.Palm Valley – Trilby Wash 230 kV Project APS 2.Sun Valley‐Trilby Wash 230 kV Project APS 3.Palo Verde‐Delaney 500 kV Project APS 4.Delaney‐Sun Valley 500 kV Project APS 5.Mazatzal 345/69 kV Substation APS 6.Sun Valley‐Morgan 500 kV Project APS 7.N.Gila‐Orchard (previously called TS8) 230 kV Project APS 8.Scatter Wash 230/69 kV Substation APS 9.Sun Valley‐Morgan 230 kV Project APS 10. Bill Durfee (Sundance) 230 kV Substation BHP 11. Raver 500/230 kV Transformer Addition Project BPA 12. Front Range Power Plant to Nixon-Kelker (NX-KE) Line #2 CSU 13. Midpoint T232 230/138 kV Transformer Addition Project IPC 14. Midpoint West Upgrade Project IPC 15. Casper Substation-Install 230/115 MVA transformer PAC 16. Mid Valley Substation-Replace 345-138kV, 450 MVA with 700 MVA Transformers PAC 17. St. George Substation- Install 345kV/138kV transformer & expand yard PAC 18. Snow Goose 500/230kV substation PAC 19. Syracuse –Install 345/138 kV #2 Transformer PAC 20. Table Mountain 500/230kV substation PAC 21. Troutdale Substation, Add 3- 230 kV circuit breakers PAC 22. Union Gap 230/115 kV Transformer Addition PAC 23. Vantage –Pomona Heights 230 kV line PAC 24. Whetstone 230/115kV Substation PAC 25. Planned Generation Waiver – Link to list PAC 26. Contra Costa sub 230kV Switch Replacement PG&E 27. Gates No. 2 500/230 kV Transformer PG&E 28. Kearney-Herndon 230 kV Line Reconductor PG&E 29. Warnerville-Wilson 230 kV Series Reactor PG&E 30. Diablo Canyon Voltage Support Project PG&E 31. Lockeford-Lodi Area 230 kV Development PG&E 32. Midway-Andrew 230 kV PG&E 33. Moraga-Potrero 230 kV Project PG&E 34. Solar Star Generation Interconnection Project PG&E 35. Stockton Generation Expansion Project PG&E 36. Blue Lake/Gresham 230 kV Project PGE 37. Horizon Phase II Project PGE 38. Port Westward II generation PGE 39. Laporte 230 kV Substation Expansion PRPA 40. Boyd 230/115kV Transformer Addition Project PRPA * Projects listed as “In service” will be removed from the next issue of this log. 41. Eastside 230 kV Transformer Addition and Line 42. Sycamore-Penasquitos 230 kV Line Project 43. Artesian 230 kV Expansion 44. New 230/69 kV Transformer at Mission 45. Talega Synchronous Condenser 46. SONGSMESA Synchronous Condenser 47. San Luis Rey Synchronous Condenser 48. Shunt Reactor at Suncrest 49. Desert Basin – Pinal Central 230kV line 50. Price Road Corridor Project 51. Rogers – Santan 230kV line 52. Silver King – RS-29 230kV Project 53. New Superior – New Oak Flat 230kV line 54. New Oak Flat – Silver King 230kV line 55. Abel – Pfister - Ball 230kV line 56. Burlington-Lamar 345/230 kV Project 57. JM Schafer-Henry Lake 230 kV Project * Projects listed as “In service” will be removed from the next issue of this log. PSE SDGE SDGE SDGE SDGE SDGE SDGE SDGE SRP SRP SRP SRP SRP SRP SRP TSGT TSGT