Annual Progress Report - Western Electricity Coordinating Council

advertisement
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Edmonton Region 240 kV
Line Upgrades – P786
240
1/2015
.6
The project includes the following components:
• increase the capacity of 908L and 909L up to the summer rating of the primary
conductor (2x477 kcmil) by replacing the conductor on the small conductor section
(first 4 km of line east of Sundance 310P),
• increase the capacity rating of 902L up to the summer rating of the primary conductor
(2x477kcmil) by replacing the conductor on the small conductor sections of 902L (first
4 km of line east of Wabamun 19S and first 4 km of line east of Sundance 310P), This
is scheduled for completion by March 31, 2013.
• rebuild the 41 km east-west single circuit wood pole sections of 904L (Jasper to
Wabamun) using 2x1033 kcmil conductor, Due to on-going negotiations with land
owners in the area this has been postponed to early 2014.
• rebuild the 6 km east-west single circuit wood pole section of 904L (Jasper to
Petrolia) using 2X1033 kcmil conductor, Due to on-going negotiations with land owners
in the area this has been postponed to early 2014.
• increase the capacity of both 904L sections out of Jasper 805S up to the summer
rating of the primary conductor (2x477 kcmil) by replacing the conductor on the small
conductor section (12 km of line south of Jasper 805S), Due to on-going negotiations
with land owners in the area this has been postponed to early 2014.
• construct 12 km of new double circuit 240 kV line with one side strung east from
Keephills 320P to the 904L-908L-909L confluence point west of Stony Plain in order to
move the termination point of 908L from Sundance 310P to Keephills 320P, and add
two associated 240 kV breakers at Keephills 320P
• swap the connections of 904L and 908L at the 904L-908L-909L confluence point
south of Jasper 805S in order to move the termination point of 904L from Wabamun
19S to Sundance 310P
• install Special Protection Systems (SPS) for three double circuit tower failure events
(Category C5), and
• install a 240 kV 600 MVA phase shifting transformer in 9L57 line and three
associated 240 kV breakers; preferred location is the proposed Livock substation north
of Brintnell. This is scheduled for September 1, 2013.
Brian Belway
Project Manager
Transmission
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2569
Brian.Belway@aes
o.ca
(AESO)
Northwest Alberta
Transmission System
Reinforcement
240
2011-2012
.5
This project involves adding new transmission facilities listed below and is required to
maintain reliability of supply and to meet load growth in the northwest Alberta. The
need for the entire project has been approved by the provincial regulatory board.
 Brintnell to Wesley Creek 240 kV Line – This sub-project involves building a
new 240 kV line (145 mi) with 2 x 477 MCM conductors per phase
(summer/winter capacity of 550/702 MVA respectively). This new line was
energized December 18, 2009.
 Wesley Creek to Hotchkiss 144 kV Line – This sub-project involves building
a new 144 kV double circuit line (83 mi) with each circuit with 2 x 477 MCM
conductors/phase (summer/winter capacity – 330/422 MVA) and is planned
to be completed in 2011.
 Sulphur Point to High Level 144 kV Line – This sub-project involves building
a new 144 kV single circuit line (65 mi) with 1 x 266.8 MCM
conductors/phase (summer/winter capacity – 114/146 MVA) and is planned
″
Page 1 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability


Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
to be completed in 2012.
Ring Creek Arcenceil (near Rainbow Lake) 144 kV Line – This sub-project
involves building a new 144 kV single circuit line (70 mi) with 1 x 266.8
MCM conductors/phase (summer/winter capacity – 114/146 MVA) and is
planned to be completed in 2012.
Reactive Power Support in Northwest Alberta – This sub-project involves
adding smaller cap banks at various locations to a total of 180 MVARs in
northwest Alberta. In addition, two small SVCs will be added as follows:
30 MVAR @ Cranberry Lake; -5 + 30 MVAR at High Level. This subproject is planned to be completed in 2012.
9L15 termination into Livock
240
2015
.2
This project involves the following developments to provide additional support to the
NortWest region of Alberta and increase flows inout of the Fort McMurray area;
 15 km of 240 kV line (Brintnell to Livock)
 Remove 9L15 termination from Brintnell
Terminate 9L15 at Livock (brkrs only, Livock should already have the diameter)
“
Northwest Alberta
Transmission System
Reinforcement
240
2015-2017
.3
This project involves the following 240kV and 138kV reinforcements to the NorthWest
region of Alberta;
“

Bickerdick to Little Smoky- The double circuit 240kV line will help to
eliminate the voltage collape and overloaded problem in northwest; it is
assumed to be in the service by 2015

New Wimbley 240kV substation
New Double Circuit 240kV line from Little Smokey to Wimbley.
Southeast Transmission
Reinforcement (SETR)
240/138
2011
.4
SETR is a system upgrade to accommodate continued growth in wind generation in
the southern Alberta region. This project was approved in July 2008 and is under
construction.
 138 kV and 240 kV lines and substations upgrade in Lethbridge, Brooks and
Empress areas.
 Construction of a new 138/240 kV 2 x 200 MVA Cypress Substation.
 Salvage of 2 x 200 MVA 138/240 kV auto-transformers and replacement by
2 x 400 MVA 138/240 kV auto-transformers.
 Addition of a third 138/240 kV 200 MVA auto-transformer at North
Lethbridge.
 Addition of capacitor banks at Tilley and McNeill.
“
Yellowhead Area
Transmission Development
– P671
240/138
2011
.1
138 kV and 240 kV development in the area to support future load growth.
“
Livock 240/144 kV
Connection – P834
240/144
2011
.1
Development of Livock 240/144 kV connection to support load growth in the Fort
McMurray area near Brintnell station.
“
Fidler 312S 240/138 kV
Interconnection – P936
240/138
2012
.2
AESO is preparing needs identification document (NID) application and transmission
facility owner is preparing facility application (FA) targeted to file with the Alberta
“
Page 2 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Utilities Commission (AUC) in Q2 2010. This system upgrade is to accommodate
continued growth in wind generation in the southern Alberta region. The target in
service date is 2011 with the following major components:
 New 240/138 kV Fidler Substation
 138 kV line re-location
Northeast Fort McMurray
240 kV Loop – P791
240
2012
.1
Development of 240 kV loop to reinforce the north Fort McMurray area to support load
growth.
“
Halkirk 1 Wind Project –
P723
150
240
2012
.1
Capital Power intends to connect a 150 MW WTG facility into the Alberta electric grid
system via a new 240 kV Transmission line by mid 2012.
“
ENMAX Shepard Energy
Centre – P719
800
240
6/2015
1.5
The ENMAX Shepard Energy Centre includes a natural gas-fired 800 MW combined
cycle power station. The power station is composed of two 240 MW gas turbines and
one 320 MW HRSG. The power station is proposed at the eastern edge of the City of
Calgary and approximately 4 km south of existing Janet 74S substation. There is a
large system portion associated with this project in order to prepare the AIES in the
Calgary area to be able to accept a maximum generation output of 860 MW from the
Shepherd Energy Center.
Sonja Tessari
Project Manager
Transmission
Alberta Electric
System Operator
(AESO)
2500, 330 - 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2669
Sonja.Tessari@aes
o.ca
Major transmission related components of the Project are outlined below. The following
is an overview summary of interconnection facilities required:
Customer Provided Facilities:
• Construct Shepard Energy Centre and tie-in to ENMAX No. 25 substation (SS-25).
Facilities to connect Shepard Energy Centre to AIES (Customer Related):
• Construct a new switching station ENMAX SS-25 and tie-in to Shepard Energy
Centre.
• Construct underground circuits to connect ENMAX SS-25 substation to AIES.
• Connect ENMAX SS-25 to existing 911L from ENMAX SS-65. The new line section
shall be renumbered as 1080L with a minimum summer rating of 489 MVA as per line
data information provided by the TFO.
System Reinforcement to accommodate Shepard Energy Centre (System Related):
• Build a 240kV double circuit line to connect ENMAX SS-25 to Janet 74S substation.
The lines shall be designated as 985L and 1003L, with minimum summer rating of
920MVA.
• De-energize or salvage the portion of existing 911L line north of ENMAX SS-25
based on construction space requirements.
System Reinforcement as part of Foothills Area Transmission Development (FATD)
Project (System Related):
• Upgrade East Calgary 5S Substation (new 240kV equipment and two (2) 400MVA
transformers).
• Build a new 138kV line 23.80L from ENMAX SS-23 to Janet 74S. 23.80L shall have a
minimum summer rating of 260 MVA.
• Build a new 138kV line 2.80L from ENMAX SS-23 to ENMAX SS-2. 2.80L shall have
a minimum summer rating of 260 MVA.
Page 3 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
• Rebuild 138kV and 15kV system at ENMAX SS-2.
• Connect portion of the existing 917L and existing 2.80L together to form a single
240kV circuit. The line shall be designated as 1077L and this line will not be energized
as part of Shepard interconnection. 1077L shall have a minimum summer rating of 489
MVA.
• Maintain 240kV system connectivity between East Calgary 5S and Janet 74S
substations by connecting portion of the existing 917L and existing 23.80L together to
form a single 240kV circuit. The line is designated as 917L. 917L shall have a
minimum summer rating of 489 MVA.
Note: The terms “Customer Related” and “System Related” are included here only for
the purpose of cost allocation under the AESO Tariff.
Construction is underway and the project has a planned in service date of June 2015
for full commercial operation.
Greengate Blackspring
Ridge Wind Farm – P728
300
Naturener Wild Rose Wind
Farm 1 – P479
210
240
3/2014
.3
This application proposed the construction and operation of the power plant consisting
of 166 wind turbines, each rated at 1.8 MW, for a total installed capacity of 300 MW
located in the Carmangay area. Connection of the Facility to the transmission system
requires development of a new 240kV switching station to provide access to existing
line 1036L and a new single-circuit 240 kV transmission line connected to wind power
plant.
The requested in-service date for the new connection is March, 2014.
The project is currently in Stage 4, filed in December, 2011 waiting on AUC review and
approval. Gate 4 completion is planned for July, 2012 depending on AUC approval.
Mark Appelt
Project Manager
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
587-952-4943
Mark.Appelt@aeso
.ca
April, 2016
.4
Wild Rose 1, a 210 MW wind-powered generating facility, is comprised of 70 x 3 MW
wind turbine generators with a collector substation located approximately 55 km
southeast of the City of Medicine Hat. This wind power plant will be connected from the
Wild Rose 1 547S substation to the Elkwater 264S substation via a single circuit 240
kV line.
Dale Bergmen
Project Manager
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2704
Dale.Bergman@ae
so.ca
The proposed in-service date for the interconnection of Wild Rose 1 is July, 2013 April,
2016
The Facilities Application was approved by the Alberta Utilities Commission on March
21, 2012.
Page 4 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Naturener Wild Rose Wind
Farm 2 – P693
Gen
MW
204
Transmission
kV
240
Date
March,
2016
No. of
pages
.4
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Wild Rose 2, a 210 MW wind-powered generating facility, is comprised of 70 x 3MW
wind turbine generators with a collector substation located approximately 30 km south
of the City of Medicine Hat. In the near future, the wind power facility will be expanded
to have a total of 204 MW installed capacity. This wind power plant will be connected
from the Eagle Butte 274S substation to the Elkwater 264S substation via a single
circuit 240kV line.
The proposed in-service date for the interconnection of Wild Rose 2 is March, 2016.
The Facilities Application was approved by the Alberta Utilities Commission on March
21, 2012.
Fort McMurray Bulk
Transmissioin System
Development Project (Stage
2) – P838
500
2019-2021
Christina Lake Area
Development
240/144
2015
Algar 240/144 kV substation
240/144
240
Algar-Kinosis 240 kV line
.3
Request Copy of
Report From
Dale Bergmen
Project Manager
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2704
Dale.Bergman@ae
so.ca
The project includes the following components:
One 500 kV AC line (2000-3000 MVA) from the Genesee generating station to a new
500 kV substation in the Fort McMurray area (stage 1) with expected operation date
around 2019.
One 500 kV AC line (2000-3000 MVA) from the Heartland station to a new 500 kV
substation in the Fort McMurray area (stage 2) with expected operation date around
2021.
The project NID has been approved through legislation, therefore transmission
facilities need approval from Alberta Utilities Commission is not required.
The project will be competitively procured; no TFOs are assigned to this project yet. At
the conclusion of the competitive procurement process, a proponent will be selected
and the facility application with Alberta Utilities Commission can proceed.
Dean Patterson
Senior Program
Specialist
Transmission
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2694
Dean.Patterson@a
eso.ca
This project involves the development of looped 240kV double circuit in the Christina
Lake area south of FortMcMurray. The project will allow connection of new load and
reinforce the transmission system to accommodate the forecasted load and generation
growth in the area south of Fort McMurray. The project involves the following;

3 new 240/144kV substations (CHL1, CHL2 and CHL4)

Termination of the new looped 240kv line into the existing HeartLake
substation
“
2015-2017
This project involves the construction of a new 240/144 kV substation to provide a
fourth source to the 144 kV transmission system in Fort McMurray to accommodate
load growth in the area and alleviate anticipated congestion on the 144 kV system.
“
2017-2020
This project involves the construction of a new 240 kV circuit connecting the existing
Kinosis substation to the new Algar substation. This project will provide needed
reinforcement to the Fort McMurray 240 kV network in order to accommodate the
forecasted load growth.
“
Page 5 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Southern Alberta
Transmission Reinforcement
(SATR) – P787
Gen
MW
Transmission
kV
240
Date
No. of
pages
2016
1
Transfer
Capability
2400
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
The project considers the implementation of a 240 kV loop in the Southern Alberta
region in order to allow the future connection of 2400 MW of wind development in that
region and to move this power to the Calgary area through three power corridors; on
the east from Whitla to West Brooks, on the center from Peigan to Foothills and on the
west from Goose Lake to Langdon through the 500 kV transmission line 1201L. This
project consists of the following lines:
• 911L replaced by Foothills to Peigan 240 kV double circuit transmission line with 50%
series compensation. Each circuit rated with a summer/winter capacity of 980/980
MVA.
• A new 240 kV double circuit line, approximately 150 km in length, from Cassils (near
West Brooks) to Bowmanton (East Medicine Hat). Each circuit rated at a
summer/winter capacity of 980/980 MVA.
• A new 240 kV switching station at a location known as Milo Junction and converting
the two existing three terminal Langdon - West Brooks - North Lethbridge lines into six
two-terminal lines.
• A new 240 kV double circuit line, approximately 80 km in length, from Bowmanton
(Medicine Hat) to Whitla connecting the wind farms in the south. Each circuit rated at a
summer/winter capacity of 980/980 MVA.
• A new Chapel Rock (Crowsnest) 500/240 kV substation cut into existing 1201L. The
station will include two 1200 MVA 500/240 kV transformers, two 240 kV 100 MVAr
capacitor banks and a +200/-100 MVAR SVC and one 45 MVAr shunt reactor.
• A new Chapel Rock –Castle Rock Ridge - Goose Lake 240 kV double circuit
transmission line with a rated summer/winter capacity of 980/1200 MVA.
• The addition of a 138 kV Phase Shifting Transformer between Coleman and Pincher
Creek.
• A new Ware Junction – Langdon 240 kV double circuit transmission line with a rated
summer/winter capacity of 980/1200 MVA with 50% series compensation.
• The addition of two (2) 240/138kV 400MVA transformers at Peigan.
• New 240 kV Etzikom Coulee substation to connect future wind farms.
• Interconnect Etzikom Coulee with Picture Butte (MATL) substation.
• Interconnect Etzikom Coulee with Goose Lake.
The project is planned to be fully operational by 2016.
Request Copy of
Report From
Dale Bergman
Project Manager –
Transmission
Project Delivery
South
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
Tel: 403-539-2704
Dale.Bergman@ae
so.ca
Currently most of the project developments are at Facility Application stage. The
eastern corridor Whitla-West Brooks is under construction with a forecast ISD March
2014. Two facilities, the Phase shifting transformer at Russell and the new Milo
switching station, are in-service since December 2011. The Ware Junction Substation
Upgrade is in-service since November 2013.
The connection studies conducted for this system project does not indicate an impact
on the transfer capability of WECC Path 1.
South and West of
Edmonton Transmission
Development – P850
240
April, 2017
1
The Project 850 addresses the need for development in the area South and West of
Edmonton. The preferred alternative includes:

New 240/138kV substation (Harry Smith) south of Stony Plain with 2 x
Ed Mayer
Project Manager –
Transmission
Page 6 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
240/138kV 400MVA transformer
New 240/138kV substation (Saunders Lake) north of Leduc with 2 x
240/138kV 400MVA transformer

New 25km 138kV line from 780L to Cooking Lake and reconfiguration

New 33km 138kV line from Harry Smith to Carvel 432S

New Capacitor Banks at Leduc 325S (27MVAR), Camrose 285S
(27MVAR), N.W. Cardiff 191S (27MVAR) and Onoway 352S (3.5MVAR).

Up-rate to 550MVA of 910L (~700m) and 914L (~650m) at Ellerslie 89S;
and up-rate 723L within Westlock 438S and Clyde 150S substation
The AESO conducted additional analysis capturing the impact of the proposed
development on the SOK- 240kV transmission path capability. The results showed that
the project will have a minimal impact on the SOK capability if either of the N-S
developments (Project 737) is energized before the energization of the Saunders Lake
substation.
The ISD will be Q4 2015 April, 2017.
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2757
ed.mayer@aeso.ca
The project includes a new 240kV substation Enmax No. 65 with 2x400MVA
240/138kV transformers. 400m of new double circuit 240kV lines with a rating of
965MVA will connect the Enmax No. 65 substation to the existing 240kV lines 9L11.
Sonja Tessari
Project Manager
Transmission
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2669
Sonja.Tessari@aes
o.ca
The project includes 65km of 3000MVA 500kV double circuit line from Ellerslie
substation to the new 500kV substation Heartland located in Fort Saskatchewan. The
project will also include 20km of 1000MVA 240kV double circuit lines connected to the
existing 240kV lines between Lamoureux substation, Josephburg substation and
Deerland substation near the new Heartland substation.
Ilice Tan, PMP
Project Manager
Heartland, Project
Delivery North
Transmission
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2530
Ilice.Tan@aeso.ca

ENMAX South Calgary SS65 Substation – P922
240/138
In-Service
.2
Alberta Industrial Heartland
Bulk Transmission
Development – P629
500/240
6/2014
.2
3000
Montana-Alberta Tie
240/230
In-Service
6
300
3
Request Copy of
Report From
The MATL project proposes to interconnect the transmission systems in Alberta and
Robert Stade
Page 7 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
Constructed by Montana
Alberta Tie Ltd. – P482
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Montana via a 240/230 kV transmission line.
Within Alberta, the construction of a new substation approximately 6 km north of
Lethbridge including three 240 kV breakers in a ring configuration and approximately 1
km of double circuit 240 kV line to accommodate the MATL interconnection. MATL’s
merchant line will be Alberta’s first direct transmission interconnection with the United
States.
The proposed transmission line is a 230 kV three-phase AC line running from north of
Lethbridge, Alberta, to Great Falls, Montana. In Alberta, the line will be connected to
the existing 240 kV line (923L) through a new substation Picture Butte 120S located 15
km northeast of the existing North Lethbridge 370S substation. In addition to the
substation connection facilities the substation will also contain a 240/230kV phaseshifting transformer to control the amount and direction of power flowing on the line.
From the proposed substation, the transmission line will head east and south before
leaving Alberta and entering Montana. The line will continue southward through
Montana to a new mid point station, Marias Substation, and then on to Great Falls. At
Great Falls, the line will connect to an existing NorthWestern Energy (NWE)
substation.
Request Copy of
Report From
Sr. Mgr.
Engineering –
MATL Project
Enbridge Inc.
425 – 1st Street
S.W.
Calgary, AB T2P
3L8
w. 403-767-3614
c. 403-463-0582
robert.stade@enbri
dge.com
The MATL project will have a normal rating of 300 MW. The line will be operated by
the AESO in Alberta and by NWE in Montana.
The project has received approval the Alberta Utilities Commission (AUC), National
Energy Board (NEB) as well as other responsible Federal, Provincial authorities.
Construction is on-going with a scheduled completion date of Q4 2012. The estimated
in-service energization date is in June 2013. Intertie commissioning will start after
energization followed by Commercial Operation in July 2013. The temporary
NaturEner Rim Rock Windfarm in Montana has been cancelled.
The energization date was August 8, 2013.
Alberta Industrial Heartland
Bulk Transmission
Development – State 2
500/240
2015-2020
The purpose of this project is to reinforce the 240 kV network in northeastern Alberta
and increase reliability to the connection of the East HVDC lines. This project will
involve the following reinforcements:

Second 500/240 kV transformer at Heartland

Double circuit 240 kV from Heartland to Eastwood

Double circuit 240 kV from Eastwood to 942L tap. 10 km 2 x 1033 double
circuit.
“
P116 – Foothills Area
Transmission Development
240
June-14
The Foothills Area Transmission Development is a regional system project that is
required to support load growth and generation increase in the Calgary and Foothills
areas, and also to support the wind power generation increase in southern Alberta.
The project consists of initial stage of a new Foothills substation to terminate the new
240 kV lines from Fort McLeod area in southern Alberta.
“
Page 8 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
P1117 – Foothills Area
Transmission Development
– FATD – Foothills 237S
Substation & East Calgary
Development - Updated
Gen
MW
Transmission
kV
240/138
Date
June-14
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
The AESO has identified the need to reinforce the transmission system in the south
Calgary and in the High River Planning area. This reinforcement will alleviate the
existing and anticipated constraints to accommodate the expected load growth and
integrate the proposed generation capacity within the subject area, and facilitate
transmission of generation from southern Alberta to load centers. The FATD project
will consist of two separate sub-projects.
This project proposes to install various 240 kV lines between substations Janet 74S,
SS-25, SS-65, Foothills 237S and Langdon 102S to improve the area system capacity
as well as the construction of a new Substation Foothills 237S. Also included in this
project is the installation of 138 kV lines in the High River planning area.
The new Foothills 237S substation will serve as the termination points for the double
circuit line 1029L/1030L from Peigan 59S. This is where the Southern Alberta
Transmission Reinforcement (SATR) project is tied with FATD project to achieve the
required overall system performance.
The scope of the 240 kV transmission developments included in the AESO’s FATD
East NID is as follows:
• A new 240 kV substation designated Foothills 237S that includes two new 240/138
kV transformers, each with a rating of 400 MVA.
• A new 240 kV double circuit line from Foothills 237S substation to future ENMAX No.
65 substation with a minimum summer rating of 600 MVA for each circuit. The lines will
be designated 1106L and 1107L.
• A new 240 kV double circuit line from Langdon 102S to Janet 74S with a minimum
summer rating of 800 MVA for each circuit. The lines are designated 1064L and
1065L.
• Create a new 240 kV double circuit line from Langdon 102S to East Calgary 5S2
using a combination of lines 936L, 937L, 917L, and 1077L; 917L and 1077L, which
were included in the East Calgary NID are connected to 936L and 937L to create the
new 240 kV path between East Calgary and Langdon substation in FATD East NID. As
per the TFO’s data submission, the summer rating of each circuit is 489 MVA. The
lines are to be designated 936L and 937L.
Summary of Transmission System Developments included in the ‘FATD East’ NID
• Create a 240 kV double circuit line between future ENMAX No. 65 substation to
future ENMAX No. 25 substation, by energizing sections of the existing 850L
transmission line to 240 kV. Transmission line 850L is built to 240 kV standards and is
currently operating at 138 kV. 850L and 1080L share the same towers. As per the
TFO’s data submission, the summer rating of the line is 489 MVA. The line designation
will be changed from 850L to 1109L.
• Terminate line 985L at Janet 74S substation, thus completing the circuit. The new
240 kV transmission line 985L is included in the East Calgary NID and proposed to be
built on the same towers as 1003L. The minimum summer rating of this line is 920
MVA.
• De-energize sections of the 911L line from south of ENMAX No. 65 substation to
Foothills 237S.The existing 911L in the High River planning area will be de-energized
upon completion of theSATR project.
The project has been approved by the Alberta Utilities Commission in October 2013,
ISD forecasted for 1117- FATD-East is Q3 2015.
The connection studies conducted for this system project does not indicate an impact
Request Copy of
Report From
Sonja Tessari
Project Manager Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 - 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2669
Sonja.Tessari@aes
o.ca
Page 9 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
on the transfer capability of WECC Path 1.
P1118 – Foothills Area
Transmissiion Development
West Calgary Development
C-Free Power Oyen Wind
Project – P763
240/138
100
On Hold
.5
Foothills Area Transmission Development – West Region (FATD West, Project No.
1118)
This project will include the installation of 240 kV lines between Foothills 237S and
Sarcee 42S.
• A new 240 kV double circuit line from Foothills 237S to Sarcee 42S with a minimum
summer rating of 600 MVA for each circuit. The lines are designated 1066L and
1067L.
ISD beyond 2020.
Sonja Tessari
Project Manager
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 - 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2669
Sonja.Tessari@aes
o.ca
2013
.1
The project involves development of a 100 MW wind power generating plant.
“
Edmonton - Calgary West
DC Lline – P962
+/- 500 DC
Q4/2014
.3
To alleviate congestion on the N-S transmission system, restore capacity of interties,
improve efficiency of the transmission system (reduce losses), and avoid potential
reliability issues, the following development has been proposed:
 Construct a +/- 500 kV bipole, HVDC transmission line between the
Genesee area and the existing Langdon 102S substation.
 Construct monopole HVDC converter station facilities, with an initial rating
of a minimum of 1000 MW.
The need for this project was approved by the Government of Alberta as part of the
Critical Transmission Infrastructure. The project is currently in the facility siting phase
and is forecasted to be in service by Q4 2014.
“
Edmonton - Calgary East
DC Lline – P961
+/- 500 DC
Q4/2014
.3
To alleviate congestion on the N-S transmission system, restore capacity of interties,
improve efficiency of the transmission system (reduce losses), and avoid potential
reliability issues, the following development has been proposed:
 Construct a +/- 500 kV bipole, HVDC transmission line between the
Heartland area and a new 240 kV substation south of Westbrooks
(Newell).
 Construct monopole HVDC converter station facilities, with an initial rating
of a minimum of 1000 MW.
The need for this project was approved by the Government of Alberta as part of the
Critical Transmission Infrastructure. The project is currently in the facility siting phase
and is forecasted to be in service by Q4 2014.
“
On Hold
.5
The proposed Heritage WAGF will be connected to the Alberta Interconnected Electric
System (“AIES”) at the Fidler 312S substation in the Pincher Creek area. The windfarm
is rated at 350 MW with 100 MW inservice at Stage 1 and 250MW at Stage 2. The
Stage 1 development is dependent upon the completion of substation Fidler 312S for
Dale Bergmen
Project Manager
Transmission
Project Delivery
Benign Energy Heritage
Wind Farm - P515
350
Page 10 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
Bow City Power Project –
P465
500
Pikani Energy Corp. Wind
Farm – P773
220
Vindt Willowridge – P614
100
240
2013
Old Elm and Pothole Creek
P1080
300
240
12/2016
Bloodtribe Wild Turnip Hill
150
P635 - Suncor Hand Hills
Wind Energy Project
80
Project on
hold
2014
240
Dec-13
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
connection. The Stage 2 development is dependent upon the completion of
transmission lines 1004L/992L from Fidler 312S to Chapel Rock 491S for connection.
Under the current configuration, the wind power plant will consist of Vestas V90 3MW
wind turbines. Both stages are onhold pending regulatory approval of Fidler 312S and
transmission lines 1004L/992L.
The reason for the staged approach is to inject as much as the system can handle
without serious RAS constraints prior to the approval and completion of the Chapel
Rock substation (connection to the 500 kV line). After the Chapel Rock Substation is
built the system in the Pincher Creek area will become unconstrained (mostly) and will
be able to handle the full projected output of the Heritage Windfarm.
The requested In Service Dates (“ISD”) for Stages 1 & 2 are on-hold.
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2704
Dale.Bergman@ae
so.ca
.1
This project requires 240 kV transmission development to accommodate the
connection of the 500 MW Bow City coal fired power station. The project consists of a
new 240 kV substation with approximately 4 km of 240 kV transmission line and the
upgrade of existing 923L and 927L to a higher thermal rating. The project has been on
hold since January 2008 and therefore a firm in service date is unknown.
“
.1
This 220 MW wind farm project is in the early conceptual stage and no connection has
been determined or in service date targeted.
“
Vindt Willowridge is a 100MW wind project that will connect to 966L
“
.3
The customer is proposing a 300 MW wind farm consists of 130 Siemens 2.3MW wind
turbines located in the Glenwood Area close to the Magrath 225S. The proposed
interconnection is to the line 988L, a planned 240 kV transmission line between Goose
Lake 103S and Journault 260S (SATR Phase 2). Connection includes construction of
240 kV transmission line to the Nine Mile Coulee 143S wind farm substation complete
with two 240/35kV transformers.
The customer had requested an ISD of October, 2013 however due to the system
development required for the connection (988L) the ISD has been set at March, 2018.
The project is currently completing P&L application waiting on further details of the
988L development before consultation can begin. P&L application is dependent on the
facilities application filing date of the 988L 240kV line.
Dale Bergmen
Project Manager
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2704
Dale.Bergman@ae
so.ca
150 MW connecting into 240KV Line 968L
“
The Suncor Hand Hills Wind Farm project is a 80 MW wind power site that is located
north-west of Anderson 801S. The project consists of a 240 kV switching station
(Mother Mountain) that is a 240 kV ring bus, a 240 kV single-circuit transmission line
and a 240/34.5 kV collector substation (Hand Hills 605S).
“
Page 11 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Transmission
kV
80
240
Apr-13
The Nexen Hand Hills Wind Farm project is a 80 MW wind power site that is located
north-west of Anderson 801S. The project consists of a 240 kV additions at proposed
Coyote Lake 963S, a 240 kV single-circuit transmission line and a 240/34.5 kV
collector substation (High Land 572S).
“
P811 - Central East
Transmission Development
240
Dec-17
The Central East Transmission Development is a regional system project that is
required to support growth in the Central Region. The project consists of re-energizing
an existing transmission line to 240 kV from proposed Bourque 970S substation to
Bonnyville 700S, modifications to Bourque 970S and a new 240 kV transmission line
from Marguerite Lake 826S to proposed Bourque 970S.
“
P812 - Hanna Region
Transmission Development
240
Mar-13
The Hanna Region Transmission Development is a regional system project that is
required to support growth in the Hanna region. The project consists of four 240 kV
source substations (Coyote Lake 963S, Lanfine 959S, Pemukan 932S and Nilrem
574S) one 240 kV switching station (Oakland 946S), modifcations to existing 240 kV
substations (Hansman Lake 650S, Ware Junction 132S and Cassils 324S), -100/+200
MVar SVC's (Hansman Lake 650S and Lanfine 959S) and about 300 km of new 240
kV double-circuit transmission.
“
P1113 - Hanna Region
Transmission Development
Phase 2
240
2017
The Hanna Region Transmission Development Project is designed to reinforce the
transmission system in the Western Part of Central Alberta in anticipation of future load
growth, in particular, pipeline pumping load. Several Transmission Facility Owners are
involved in this project. The major components of this project consist of:
• String second side on the 240 kV double-circuit line from Oakland to Lanfine and
Related
Alterations at Oakland 946S and Lanfine 959S.
• Cordel 755S to Halkirk Switching Substation, New double circuits 240 kV Line (one
side strung) and Related Alterations.
• Anderson to Oakland Transmission Project 9L70/9L97 240kV lines, Oakland
Substation and Related Alterations
• String Second Side on the 240 kV double circuits Line from Oakland 946S to Coyote
Lake 963S and Related Alterations at Oakland 946S and Lanfine 959S.
Additionally, the following components are designed to reinforce the local network:
• Convert existing Hanna 763S Substation to 144 kV Substation.
• New 144 kV Line from Coyote Lake 963S to Hanna 763S and Related Alterations
• Addition of 2nd 240/144 kV Transformer at Pemukan 932S.
• Addition of 2nd 240/144 kV Transformer at Lanfine 959S.
• Addition of 2nd 240/144 kV Transformer at Hansman Lake 650S.
• Nilrem 574S Substation Capacitor Bank Addition
• Hansman Lake 650S Substation Capacitor Bank Addition
• Metiskow 648S Substation Capacitor Bank Additions
• Decommission of 6L44 (Rowley 768S to Big Valley 778S) and 6L22 (Michichi Creek
802S to Rowley 768S)
The current scheduled complete date is in year 2017 subject to change
The need of this project has been approved by the Alberta Utilities Commission with
Anita Patel
Project Manager –
Transmission
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2516
Anita.Patel@aeso.
ca
Name of Project
P678 - Nexen Hand Hills
Wind Project
Date
No. of
pages
1
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Gen
MW
Phase
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Page 12 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
the timing and staging of this project under review.
Due to the broad scope of this project involving multiple transmission facility owners,
AESO has the oversight on this project under Anita Patel.
P813 - Red Deer
Transmission Development
240
Q3 2014
1
The Red Deer Area Transmission Development project will be implemented in two
stages. Pending the approval of the Facility Application.
Following is an overview of the major components of the proposed developments in
stage I. The timing of stage II will be determined by the future load projections.
• Split 768L and 778L and re-terminate at Red Deer North 217S (add 1 brk, use 1
existing brk) and Gaetz 87s (add 2 brks, use 1 existing brk)
• Add a second autotransformer at Benalto 17S.
• Add one 50 MVAR 138 kV capacitor bank at Joffre 535S
• Add one 50 MVAR 138 kV capacitor bank at Prentiss 276S
• Add one 27.6 MVAR 138 kV capacitor bank at Ellis 332S
• Re-build 5 km of 80L 138 kV transmission line from South Red Deer 194S (use
existing1 brk) to North Red Deer 217S (use existing brk)
• Re-build 5 (including 1 km of underground) km of 80L 138 kV transmission line from
South Red Deer 194S (use existing brk) to Red Deer 63 (use existing brk)
• Re-build 29 km 755L 138 kV transmission line from Red Deer 63S (use existing brk)
to Piper Creek 247S (use existing brk) to Joffre 535S (use existing brk)
• Re-build 33 km 717L (now called 367L and 648L) 138 kV transmission line from Red
Deer 63S (use existing brk) to Sylvan Lake (use existing brk) to Benalto (use existing
brk)
• New Johnson 281S 240/138 kV substation with 240 kV double circuit (200m) from
918L and 2 km of double-circuit 138kV line to 80L and a connection to 166L
• New 240/138 kV Wolf Creek 247S Substation with 240 kV double circuit (200m) from
910L and 4 km of double-circuit 138kV line to Ponoka 331S (use existing brk from
salvage of D13 and D16) connect to 883L
• New 240/138 kV Hazelwood 287S Substation on the 240 kV line 924L
• New 13 km of 138 kV transmission line from Lacombe 212S (add 1 brk) to Ellis332S
(add 1 brk)
• Salvage 53 kM 80L 138 kV transmission line from Red Deer 63S to Innisfail 214S
• Salvage 23 KM 80L 138 kV transmission line from Ponoka 331S to West Lacombe
958S (this will be less by the approx.. 5 km of salvage now part of Wolf Creek (CP44))
• Salvage 40 km of 716L from Wetaskiwin 40S to Ponoka 331S (this will be less by the
approx.. 5 km of salvage now part of Wolf Creek (CP44))
Anita Patel
Project Manager –
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2516
Anita.Patel@aeso.
ca
The in-service date is in stages starting from 2013.
The Need Identification Document was filed to Alberta Utilities Commission in July
2011, and approved in April 2012, Facilities Applications are being prepared in stages
with the last stage scheduled to be filed by Q3 2014.
North South Transmission
Reinforcement – P737
500
4/2015
1
This project consists of two 1000 MW 500 kV line-commutated HVDC lines to alleviate
transmission congestion along the SOK cut-plane. These two transmission lines are
mandated by the Alberta
Dean Patterson
Senior Program
Specialist
Transmission
Page 13 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Legislature as a Critical Transmission Infrastructure (CTI) project in the Electric Status
Amendment Act, 2009. The need for this line was re-affirmed by the Minister of Energy
in February 2012. East Alberta Tie-Line (EATL) connects the Heartland 500 kV
substation in the Fort Saskatchewan Area to the new Newell 240 kV substation in the
Brooks Area. It will be built as bi-pole line with 1000 MW monopole converters using
remaining conductor as metallic return. The project was approved by the Alberta
Utilities Commission on November 15, 2012.
Request Copy of
Report From
Project Delivery
Alberta Electric
System Operator
(AESO)
403-539-2694
Dean.Patterson@a
eso.ca
West Alberta Tie-Line (WATL) connects from new Sunnybrook substation near
Genesee substation in the Wabamun Area to Langdon substation which is also the
terminal of 1201L 500kV BC-Alberta Tie-line. It will be built as bi-pole line with 1000
MW mono-pole converters using remaining conductor as metallic return. The project
was approved by the Alberta Utilities Commission on December 6, 2012.
The addition of these two HVDC lines will significantly increase the North to South
transfer capability (SOK limit) within Alberta. As the 1201L 500 kV Alberta to BC export
capability is limited by the SOK limit, the addition of these two lines will increase the
Total Transfer Capability of 1201L.
This impact will be quantified by Inter-Tie Rating Studies and HVDC Operations
Studies scheduled to be completed by the end of 2014.
The estimated ISD of WATL is April 2015 and ISD of EATL is December 2014.
New Fidler 312S Substation
– Project 1343
240/138
10/2017
.5
Increased transmission capacity is needed in the area northeast of Pincher Creek and
west of the Piikani Nation reserve to provide several wind generating facilities, two of
which are already in service and others which are planned to be in service within the
next two years, access to the transmission system. The existing two wind generating
facilities are frequently required to reduce output during normal operating conditions
due to existing transmission system constraints. The Fidler 312S Collector Substation
Connection Project NID was submitted by the AESO to the AUC on October 26, 2012.
NID and FA approval is expected by August 2013. The planned in-service date is April,
2014.
The Fidler Project includes a two stage development.
Stage 1:
• Develop a new 240/138kV collector substation with one transformer
• Add a new double circuit 240 kV line connecting Fidler 312S to the existing 1071L
transmission line in an in-out configuration
• Rebuild existing portions of 138 kV transmission lines connecting into the Fidler 312S
substation
• Configure 893L between Goose Lake 103S and the tap-off to Oldman River Dam
806S to normal open under normal operating conditions
Stage 2:
• Add a second transformer at Fidler 312S
Dale Bergmen
Project Manager
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2704
Dale.Bergman@ae
so.ca
Page 14 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
• Salvage existing 138kV transmission line 893L between Goose Lake 103S and the
tap-off to Oldman River Dam 806S.
Stage 2 is dependent on meeting the milestone when installed and proposed
generation capacity connected at the 138 kV side of Fidler 312S exceeds 80% of the
capacity of the first transformer (288 MW assuming 0.9 power factor).
The requested in-service date for the new connection is October, 2017.
Whitetail Peaking Station –
Project 1290
200
Shell Carmon Creek –
Project 1321
230
Project 1421 - ATCO Power
Heartland Generating
Station
1080
240/25/18
5/2014
.1
BowMont Capital and Advisory Ltd. (BowMont) is planning to construct the Whitetail
Peaking Station (“the Project”) as a new point of supply (POS) - Project 1290. The
Project is to be developed in one stage with an in service date (“ISD”) of May 1, 2014.
The plant consists of 4x50MW of gas fired peaking units.
The plant is located in the Peace River area (Area 19) in the vicinity of LSD 29-85-19W5 which is located approximately 13.5 km to the north of the existing Wesley Creek
834S substation. The preferred alternatve is to complete an in and out connection to
7L106 in the Northwest Region of Alberta.
The project is currently in Stage 3 out of 6 of the Connection Process and a Functional
Specification is being drafted by the AESO with Planned In-service date of May 1,
2014
Robert Michaud
Manager,
Transmission
Projects
ATCO Electric
10035 105 Street
Edmonton, AB T5J
2V6
Ph: 780-508-4896
Cell: 780-719-5697
7/2015
.1
The proposed project has an in service date of July 1, 2015. A total of three 230 MW
cogeneration units are planned with 70 MW of on-site load. Shell intends to build a
customer owned 240/25/18 kV substation and seeks an Industrial System Designation
for the project. All projects loads will be served from Shell's proposed substation. The
transmission connection requested could be a double-circuit 240 kV line from Carmen
Creek to Wesley Creek in the Northwest Region of Alberta (Alternatives currently being
studied).
Project is currently completing studies and is in Stage 2 of the Connection Process
with planned ISD of July 1, 2015
Vladimir Lopez
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
(T) 403-539-2819
vladimir.lopez@aes
o.ca
10/2018
1
Generation Station. The generation station will be located at NW-27-55-21-W4M. The
project will consist of three identical phases.
• Phase 1: 15MW DTS in March 1, 2016, and 510 MW STS in September 2016
• Phase 2: Additional 15MW DTS in March 1, 2018, and additional 510 MW STS in
October 2018
The dates associated with the three phases are the start of commissioning and expect
the plant to begin commercial generation six months thereafter.
Each facility will include the following major components:
• 1 x Natural Gas Turbine
• 1 x Steam Turbine
• 1 x Heat Recover Steam Generator (Include ~50 MW of Duct Burners)
Steve Palmer
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
403-539-2558
steve.palmer@aes
Page 15 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
The equipment specified above is subject to change, but they do not expect the
nominal capacity to exceed 470 MW.
The generation facility will be designed and operated to ensure that the outage of any
single element/component will not cause a loss of more than 466 MW of generation to
the AIES.
Generation Component
Each phase of the project consists of a generation with the Maximum Capability (MA) 1
level of 470 MW with 0.9 PF lagging and 0.95 PF leading.
The requested Supply Transmission Service (STS) includes:
• 510 MW STS in September 1, 2016
• Additional 510 MW STS in October 1, 2018
Load Component
The requested Demand Transmission Service (DTS) consists of 15 MW in March 1,
2016, with an additional 15 MW in March 1, 2018, and another additional 15 MW in
March 1, 2020.
o.ca
Project 1440 - Genesee
Generating Station Unit 4
(“G4”) and Genesee
Generating Station Unit 5
(“G5”)
1000
12/2017
.5
On April 30, 2013 AESO received a System Access Service Request (“SASR”) from
Capital Power L.P. to connect a 1000MW Power Generation Facility, the Capital Power
Energy Centre (“CPEC”) to the AIES.
The CPEC will be a new gas combined cycle facility to be located within the Genesee
Generating Station land. The new facility will consist of two Gas Turbine Generators
(“GTG”) and associated Steam Turbine Generator (“STG”).
CPEC indicated that the Gross Generation Capacity is expected to be up to a
1000MW; which could be developed in stages to meet Alberta’s demand. Therefore,
the study will proceed with the assumption that the gross capacity of the proposed
generating station is 1000MW.
The facility in-service date is currently expected to be December 31, 2017; however,
CPEC indicated that this date is subject to change due to market conditions.
Vladimir Lopez
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
(T) 403-539-2819
vladimir.lopez@aes
o.ca
Project 1477 - TransAlta
Sundance 7 Gas
Turbine/Generators
Installation
818
6/2018
.5
TransAlta MidAmerican Partnership is proposing to construct approximately 850 MW
Sundance 7 generating facility in the vicinity of LSD 10-52-4-W5M. The site is located
near existing TransAlta generating facilities near Wabamun. The facility will be a
Combined Cycle Gas Turbine consisting of two Gas Turbine/Generators (GT) of
approximate 295 MW capacity (345 MVA, 0.85 pf) and a single Steam
Turbine/Generator (ST) of approximately 345 MW (405 MVA, 0.85 pf). The gross
output is approximately 943 MW with an STS capacity of 850 MW. The maximum
Gross Capacity at an average summer temperature of 15.3 degrees Celsius is 818
MW and the Net Output is 797 MW.
The anticipated in service date (ISD) is June 29, 2018 and the commercial operation
date (COD) is January 31, 2019.
Vladimir Lopez
Transmission
Project Delivery
Alberta Electric
System Operator
(AESO)
2500, 330 – 5th
Avenue SW
Calgary, AB T2P
0L4
(T) 403-539-2819
vladimir.lopez@aes
o.ca
In-Service
.5
Avista has begun construction (in late CY 2010) on a new Moscow 230/115 kV
substation (located adjacent to the existing Moscow 230/115 kV substation). This
Moscow 230 kV Transformer
and station rebuild
230/115
Tracy Rolstad
(509) 495-4538
Page 16 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Noxon Rapids Turbine
Upgrades
Gen
MW
Transmission
kV
+ 42
MW
Major Generation Addition
(> 200 MW)
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
project will be constructed in a double bus-double breaker configuration for the 230 kV
yard, and in a breaker-and-a-half configuration for the 115 kV yard. Additionally,
Avista will replace the existing 125 MVA 230/115 step-down transformer and
associated 125 MVA 115/115 kV regulating transformer with a new 250 MVA 230/115
kV tap changing transformer. The Moscow 230 kV station rebuild (including the
transformer replacement), and associated minor 115 kV reconductoring in the
Moscow, ID and Pullman, WA area will positively impact the performance of the West
of Hatwai path (WECC path #6).
(AVA)
“
6/2012
.2
Avista’s Power Supply function is engaged in turbine blade upgrades on Noxon Rapids
units #2, #3, and #4. These upgrades will add an additional 14 MW’s respectively to
the existing turbine capacities. The total electrical output of the Noxon Rapids project
will be a maximum of 557 MW. This electrical limit does not consider any hydraulic
limitations associated with the greater Clark Fork River project (which includes Cabinet
Gorge and Noxon Rapids).
2014-2023
.4
Plant
Capacity
Waneta Expansion G1 167.5 MW
Waneta Expansion G2 167.5 MW
Mica G5
500 MW
Mica G6
500 MW
Rev G6
500 MW
Site C G1
183.3 MW
Site C G2
183.3 MW
Site C G3
183.3 MW
Site C G4
183.3 MW
Site C G5
183.3 MW
Site C G6 183.3 MW April 2023
In Service Date
April 2015
April 2015
Oct. 2014
April 2015
April 2029
April 2023
April 2023
April 2023
April 2023
April 2023
Guihua Wang
(604) 699-7367
(BCHA)
Vancouver City Central 230
kV Transmission Project
230
Spring
2014
.2
Currently in implementation phase, this project constructs a new substation and new
transmission lines.
New station:
Mount Pleasant Substation
New lines:
2L20 (3.4 KM) – Cathedral Square to Mount Pleasant
2L44 (4.8 KM) – Mount Pleasant to Sperling
“
Dawson Creek / Chetwynd
Area Transmission (DCAT)
Project
230
6/2015
.2
The Dawson Creek / Chetwynd Area Transmission Project (DCAT) consists a two 60
km 230kV lines running from a new 230 / 138 kV substation named Sundance
Substation (SLS) to Bear Mountain Terminal (BMT) and a new 138 kV line from BMT
to Dawson Creek Substation (DAW). This project would provide additional
transmission capacity into the Dawson Creek area to support new unconventional gas
production loads.
“
Northwest Transmission
Line (NTL) Project
287
5/2014
.2
Currently in implementation phase, the Northwest Transmission (NTL) Project consists
of approximately 340 km of 287 kV transmission line from the Skeena Substation near
Terrace to a new substation at Bob Quinn and a series compensation capacitor bank
(35%) at Bob Quin. The NTL will provide infrastructure for connecting new sources of
“
Page 17 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
generation, future industrial development and communities in the area.
Fraser Valley West Area
Reinforcement (230 kV)
230
6/2015
.2
Construction of a new substation and new transmission lines.
New station:
Fleetwood Substation
Splitting 2L75 from Ingledow to McLellan to 2 lines.
New lines:
2L75 (8 KM) – Ingledow to Fleetwood
2L81 (8 KM) – Fleetwood to McLellan
“
Series Compensation on
Southern Interior 500 kV
lines (SISC)
500
10/2019
.2
The project is to add one 500 kV series capacitor station, on 5L98 transmission line
from Nicola to Vaseux Lake. This project is still in definition phase.
″
Seymour Arm Series
Capacitor (SASC) (Mica –
Nicola 500 kV Series
Compensation)
500
In-Service
.1
The series compensation project on the two 500 kV lines between Mica and Nicola
was in service in November 2013.
“
New ILM 500 kV line
500
1/2015
.2
The new line is planned to provide incremental transmission transfer capability from
the Interior of British Columbia to the load centers in the Lower Mainland. This new
500 kV transmission circuit, 5L83, will be approximately 250 km long and will run
between the Nicola and Meridian substations. 5L83 will be 50% series compensated at
new Ruby Creek Capacitor Station near Agassiz.
Technical planning studies have been completed and the project is currently
undergoing implementation phase.
″
Spring
2014
.2
A project is planned to reconfigure Nicola station, a critical station that collects power
flows from the South Interior before transmitting the power to Lower Mainland, to
prevent total lost of the station and increase the reliability of the transfer of power to
the Lower Mainland. Definition work was initiated for this project.
“
Nicola Station
Reconfiguration
Metro North Area 230 kV
Reinforcement
230
10/2017
.2
The planning study is in progress and the following identified is only one alternative,
may subject to changes:
1) Reterminate 2L49 from Meridian – Horne Payne to Meridian – Murrin (34 KM)
2) Reterminate 2L50 from Burrard – Murrin to Burrard – Horne Payne (19.5 KM)
3) Add 2 new lines: 2L26 (7.45 KM) – Horne Payne to Murrin
2L23 (19.3 KM) – Como Lake to Horne Payne
“
West End 230 kV Substation
230
10/2018
.2
The planning study is in progress and the following identified is only one alternative,
may subject to changes:
1) Construct a new 21.5 kM, 230 kV circuit from Meridian to Horne Payne (2L18).
2) Extend an underground circuit (2L51) from Barnard to Mount Pleasant.
3) Add 203 kV – 60 MVAR switchable shunt reactor on dedicated 230 kV line position
at Camosun
“
Transmission Lines from
Site C to Peace Canyon.
500
4/2023
.1
At preliminary planning stage, this project is to build two 500 KV lines from Site C to
Peace Canyon, to accommodate site C new generation.
“
Page 18 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Meridian T2 Addition
500/230
4/2014
.1
Install a new 500/230 kV 1200 MVA transformer at Meridian Substation. Meridian
substation is located on Westwood Plateau in Coquitlam and it is the major supply
source to Metro North subsystem serving downtown Vancouver, Burnaby and Tri-cities
area loads.
“
Kitmat Modernization
Project
287
11/2014
.2
Kitmat Modernization Project consists of rebuilding the Kitimat smelter and adding
35% series compensation on the two Kimano to Kitmat 287 kV transmission lines by
building a series capacitor station near Kitmat. Five 287/100/28 kV 219 MVA regulating
transformers will be installed.
“
Series Compensation
Increase (from 50% to 65%)
at KDY and MLS Stations
10/2022
.2
At preliminary planning stage, this project is to increase series compensation level at
5L1, 5L2, 5L7 at KDY, 5L11,5L12, 5L13 at MLS from 50% to 65%, to accommodate
site C new generation.
“
Prince George Terrace
Compensation (PGTC)
Summer
2017
.1
At preliminary planning stage, this project is to install 65% series compensation at
5L61, 5L62, 5L63 from WSN to SKA substation, to accommodate LNG loads in North
Coastal BC region.
“
6/1/2014
.1
This project is to construct a 92 km 287 kV transmission extension, from the planned
NTL line (Item 7) terminal Bob Quinn substation. The transmission line would terminate
at a new substation at Tatooga Lake and a 16 km 25 kV distribution line continuing to
Iskut.
“
2014
.1
Coast Mountain Hydro proposes to develop a run-of-river hydroelectric facility North of
Stewart. Total plant rated output is 211.4 MW.
“
230
2015
.1
Add a new 230 kV cable circuit (2L142) from George Tripp to Horsey and add one 150
MVA – 230/138 (T14) transformer at George Tripp.
“
230/25
2015
.1
Add a new 150 MVA transformer to supply the load growth in the Tsawwassen/Delta
area.
“
2016
.1
An interim upgrade of 2L99 involves imporving the design defects and upgrading
the winter line rating to 650 MVA
“
2017
.1
Add Skeena T3 (500/287/12.6) transformer due to new Kitimat LNG2 load.
“
Bob Quinn SVC Addition
2016
.1
Add +100/-40 SVC for system reinforcement to accommodate NTL (2L102) new
mining loads.
“
Add series compensation on
circuit 2L102
2018
.1
Add series compensation on NTL (2L102) near Skeena due to new mine loads
“
Horne Payne Substation
Updrade
2016
.1
Add 2 x 230/25 kV – 150 MVA transformers at Horne Payne Sub
“
Iskut Expansion project
Forrest Kerr IPP
Vancouver Island Cable
Project
New Arnott 230/25 kV
Transformer
287
211.4
Minette to Skeena Line
Rating Upgrade (2L99)
Skeena Substation Upgrade
500/287/12.6
Page 19 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Date
Peace Region Electric
Supply (PRES) Project –
Alternative 2
2018
.1
Construct a 2nd 22.8 KM 230 kV overhead transmission line from GMS to Dokie
Terminal. Construct a 64.1 KM 230 kV transmission line from Dokie Wind Terminal to
Sundance. Replace GMS T13 & T14 with 2 new 600 MVA 500/230 kV transformers.
“
In Preparation For The Site
C Generation Project
2023
.1
Add 250 MVAR switchable shunt capacitor at Williston 500 kV substation
Add static var compensator (SVC +250/-150 MVAR) at Williston
“
7/1/2014
This project is to construct a new 138 kV radial transmission line from the existing
Highland Substation to a new substation in Merritt, to meet the increased demand for
power in the Merritt area.
“
11/1/2018
This project is to supply and install an approximately 500 MW unit in the existing empty
Unit 6 bay at Revelstoke Generating station to add capacity to the BC Hydro system.
“
The purpose of West of McNary Reinforcement (WOMR) Project is to increase the
transfer capability across the West of McNary (WOM), West of Slatt (WOS) and West
of John Day (WOJ) paths that will enable BPA to provide transmission service for
proposed renewable energy from the McNary area to Northwest load centers west of
the Cascade Mountains, to the California-Oregon (COI) AC Intertie, and to the Pacific
DC Intertie (PDCI). WOMR is one of multiple BPA projects being developed as a result
BPA’s 2008 Network Open Season (NOS).
The WOMR Project was divided into two phases and phase 1 has been completed.
Phase 2 included:
1. A new 500 KV switching station called Knight Substation, located near Goldendale,
Washington at tower 73/1 on the BPA Wautoma-Ostrander 500 kV line,
2. A new 28 mile, 500 kV transmission line connecting BPA’s Big Eddy Substation near
The Dalles, Oregon to Knight Substation,
A Wautoma - Ostrander 500-kV line re-sag, and
4. A Wautoma 500 kV 300 MVAR shunt reactor which is in service on March 2014
Berhanu Tesema
360-619-6819
(BPA)
Merritt Area Transmission
(MAT) project
Revelstoke Unit 6
Installation
Transmission
kV
138
500
West of McNary
Reinforcement (WOMR)
Project
500
11/2015
1
North Cross Cascade 500
kV Line Project
500
2024
.05
345/138/115
2016
1
Lower Valley Area
Reinforcement Project
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
No. of
pages
Name of Project
Gen
MW
Phase
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Consisting of a Chief Joe – Monroe 500 kV line, this project is associated with load
service and is on hold until load growth supports construction.
A 345/161-kV transformer at PacifiCorp’s (PAC) Goshen Substation currently serves
the Lower Valley area. Three transmission lines serve load out of Goshen. The
Goshen-Drummond 161-kV line serves mostly Fall River loads and provides back-up
service to Lower Valley. The Goshen- Swan Valley 161-kV line serves most of the
Lower Valley load. The Goshen-Palisades 115-kV line serves the Palisades
Generating Plant and some Lower Valley load.
BPA constructed a second Swan Valley-Teton line in 2000 and upgraded the GoshenDrummond line to 161-kV in 2002. These upgrades increased the reliability of the Fall
River system and helped support load growth in the Jackson Hole area, but did not
increase the transmission capability to the southern part of Lower Valley’s system.
Capacitor banks have been installed at Targhee, Tincup, Teton, and Madison.
PAC has constructed a new 345/138-kV Three Mile Knoll Substation a couple of miles
″
Larry Furumasu
360-619-6851
(BPA)
Page 20 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
north of their existing Caribou switching station. This new substation includes a new
345-kV interconnection with Idaho Power. Idaho Power’s Bridger-Goshen 345-kV line
is looped into the new Three Mile Knoll 345/138-kV Substation which includes two new
345/138-kV, 650 MVA transformers. For the Lower Valley Area reinforcement Project,
BPA will construct Hooper Springs 200 MVA 138/115-kV Substation adjacent to PAC's
Three Mile Knoll Substation.
I-5 Corridor Reinforcement
Project
500
2018
1.5
Central Ferry-Lower
Monumental (Little Goose
Reinforcement Project)
500
12/2015
500/230
2016
Raver 500/230 kV
Transformer
1100-1400
MW
This purpose of this project is to increase the transfer capability of the I-5 Corridor in
the vicinity of Southwest Washington and Northwest Oregon. This load service area
includes the cities of Portland, Oregon and Vancouver, Washington, which include high
concentrations of industrial, commercial, and residential load. The generating
resources serving this area are a mix of hydro and thermal plants.
This proposed project includes a new 500 kV transmission line (approximately 70
miles) between Castle Rock, Washington and Troutdale, Oregon. This would require
the construction of a new 500 KV switching station in the vicinity of Castle Rock
Washington and the expansion of BPA's Troutdale Substation near Troutdale, Oregon.
The project is projected to increase capacity by approximately 1100 to 1400 MW on
the South of Allston path.
“
1
The purpose of the Central Ferry-Lower Monumental Project is to increase the transfer
capability West of Lower Monumental that will enable BPA to provide transmission
service for proposed renewable energy from the Little Goose area to Northwest load
centers and to the sending end of the California Interties (COI and PDCI). This project
is one of several BPA projects being developed as a result BPA’s 2010 Network Open
Season (NOS) process.
The Central Ferry-Lower Monumental project includes a new 38 mile 500 KV line. The
project also includes a shunt 300 MVAR reactor at Central Ferry Substation and line
re-terminations at Lower Monumental substation necessary to terminate the planned
new 500 KV line.
Chuck Matthews
(360) 619-6833
(BPA)
1
This purpose of this project is to improve load service reliability to the Puget Sound
area and Northern Intertie. The Puget Sound and Northern Intertie (PSANI) area
transmission system is a winter peaking system that primarily consists of the
interconnected systems of BPA, Puget Sound Energy (PSE), Seattle City Light (SCL),
Snohomish PUD (SPUD), Tacoma Power Utilities (TPU), and British Columbia
Transmission Company (BCTC), which serve Seattle, Tacoma, Olympia, and
surrounding areas.
The Puget Sound Area is a highly congested network due to large concentrations of
load and varying local generation patterns, which are further stressed by transfer levels
between the US and Canada on the Northern Intertie. Winter peak loads are typically
the worst, combined with lower local generation patterns and high exports to Canada.
Through a joint Columbia Grid study effort, several system fixes have been agreed to
by BPA, SCL, and PSE. They include several 115kV and 230kV PSE and SCL line
upgrades, a BPA RAS upgrade and a new BPA 500/230kV transformer. The PSANI
Berhanu Tesema
(360) 619-6819
(BPA)
Page 21 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Reinforcements projects are scheduled to be completed in full by fall 2018. The Raver
500/230kV transformer addition is scheduled for completion in fall 2016.
The most limiting outage for the South Puget Sound area is a common corridor N-2
Tacoma- Raver #2 and Raver-Covington #1, which results in loss of two 500/230kV
banks in the area. Other N-2 common corridor outages result in a loss of two
500/230kV banks either at Tacoma, Covington, or Maple Valley substations and cause
severe loading on the remaining transformer banks. Once the Raver 500/230kV
transformer addition is completed, the severity of these N-2 outages will be greatly
reduced, mitigating overloads, and resulting in greater reliability to load service and
operational flexibility for the Southern Puget Sound Area. The project also helps to
reduce the risk of curtailment or redispatch events in the Puget Sound Area for certain
outage conditions.
The plan of service is to install a 1300 MVA transformer at Raver substation. A new
230kV substation will be developed adjacent to the existing 500kV substation. The
high side of the new transformer will terminate at Raver 500 KV. The Tacoma-Raver
#1 and #2 500 KV lines are currently jumpered together and operated as double circuit
500kV for about 10 miles from Raver until it reaches Covington substation. The
corridor for both circuits runs adjacent to Covington 230kV station and in the same
corridor as the Raver-Covington #1 and #2 500 KV circuits. The project will reconfigure
the Tacoma-Raver 500 KV lines by removing jumpers and reterminating the TacomaRaver #2 circuit into Covington 230 KV and Raver 230 KV Substations. The TacomaRaver #2 line will be renamed and operated as the Raver-Covington #3 230 KV line.
The plan of service also requires reconfiguring the Covington 230 KV bus, adding a
new sectionalizing breaker and 2 bus tie breakers.
Schultz-Raver #3 & #4 500
Series Capacitors Project
500
PDCI Uprate Project
John Day Substation –
Golden Hills 200 MW
(G0099-2)
200
2018/19
.5
2016
(Celilo DC
Upgrade
Only)
.5
10/1/2013
.5
The purpose of this project is to increase transfer capability across the West of
Cascades North Path and provide increased load service to the Puget Sound area.
This project adds 500 kV series capacitors at Schultz Substation on the Schultz-Raver
500 kV #3 and the Schultz-Raver 500 kV #4 lines.
3800 MW
The Pacific DC Intertie (PDCI) provides a direct current (DC) intertie between The
Dalles Oregon, and Los Angeles, CA. The current PDCI is rated at 3100 MW.
The PDCI Uprate project would increase the capacity by 700 MW from 3100 MW to
3800 MW. This project replaces the convertors at the Celilo HVDC terminal and reconductors a small section of the DC transmission line. To reach the full 3800 MW will
require the southern partner (LA Department of Water and Power) will need to
reinforce the AC system on the southern end, upgrade some DC line sections, and
make minor changes to their terminal equipment.
John Day Substation is a major 500 KV switching station east of The Dalles Oregon. It
serves as the northern terminus of the California-Oregon AC Intertie (COI). It
integrates the generation from the US Corp of Engineers John Day Dam. It the next
major 500 KV substation west of Slatt Substation. In 2007, a 230 KV yard was added
to interconnect Portland General Electric's (PGE) 400 MW Bigelow Canyon wind
Berhanu Tesema
(360) 619-6819
(BPA)
Kyle Kohne
360-619-6839
(BPA)
Chuck Matthews
360-619-6833
(BPA)
Page 22 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
project. PGE sold 200 MW of their original 600 MW project to BP Alternative Energy.
This remaining 200 MW is a wind generation project called
Golden Hills.
Shepherds Flat Wind Phase
1 (aka North Hulburt Wind)
(G0118 and G0291)
Phase
1 – 266
2 – 190
3 - 190
12/2011
5/1/2012
5/1/2013
.05
G0118 and G0291 are Shepherds Flat. It is being commissioned in 3 phases: Phase
1 (266 MW) energized in 12/1/2011. Phase 1 is called North Hulburt. Phase 2 (190
MW) is planned for 2012, and Phase 3 (190 MW) for 2013. The LGIA has been
executed and we are planning the first synchronization for July 15, 2011.
“
Montague I
202
12/2011
.05
The generation project has executed or is in the process of executing a Large
Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection
studies can be obtained by signing a non-disclosure agreement with BPA.
“
Lower Snake Wind
341
2/2012
.05
The generation project has executed or is in the process of executing a Large
Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection
studies can be obtained by signing a non-disclosure agreement with BPA.
“
Miller Ranch Wind
150
6/2012
.05
The generation project has executed or is in the process of executing a Large
Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection
studies can be obtained by signing a non-disclosure agreement with BPA.
“
Golden Hills Wind
200
10/2013
.05
The generation project has executed or is in the process of executing a Large
Generation Interconnection Agreement (LGIA) with BPA. Technical interconnection
studies can be obtained by signing a non-disclosure agreement with BPA.
“
Morrow Flats Project
230
2015
.1
This is a new 230/115 kV substation approximately 3 miles east of BPA’s Boardman
Substation connecting to the McNary-Boarddman 230-kV and the McNary-Jones
Canyon 230-kV lines.
This substation is needed to provide load service in the Boardman-Umatilla area.
“
Montana to Washington
500
2018
.5
In 2010, Bonneville Power Administration (BPA) conducted a Network Open Season
(NOS) to determine projects needed for requests for long-term firm transmission
service. During the NOS process, entities requested the use of BPA's transmission
system to transmit their power.
“
The studies found that there was not enough available transmission capacity to
accommodate all requests for long-term service from BPA's Garrison Substation in
Western Montana to load centers west of the Cascades and to market hubs serving
the entire Northwest power market. Wind generation facilities built and proposed in the
region have greatly increased the amount of planned generation in Montana seeking
load and markets in the Northwest. As a result, BPA is proposing several
reinforcements on BPA's transmission system at Garrison, Hot Springs, Bell,
Dworshak, and Hatwai Substations.
Additionally, reconductoring is being proposed totaling 12 miles on the Dworshak-Taft
No. 1 500-kilovolt (kV) line and a new series compensation substation is being
proposed along the Garrison-Taft No. 1 and No. 2 500-kV lines, both of which would
Page 23 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
allow BPA to accommodate the requests for transmission service in this area. These
reinforcements would increase the firm east-to-west transfer capability of the West of
Garrison and West of Hatwai paths by primarily increasing the series compensation in
existing 500-kV lines in the area.
Douglas-Rapids 230 kV
Transmission Line
230
4/2014
21
Douglas County PUD is constructing a new 13-mile, 230-kV transmission line to
connect its Douglas Switchyard with its Rapids Switchyard. The conductor will be 1590
ACSR/TW and is expected to have a Summer rating of 589.5 MVA, a Winter rating of
766.8 MVA, an Autumn rating of 687.9 MVA, and a Spring rating of 671.6 MVA. A new
230/115-kV transformer will be installed at Rapids Switchyard with expected ratings of
200 MVA (ONAN) 55° C, 266 MVA (ONAF) 55° C, 333 MVA (ONAF) 55° C, and 373
MVA (ONAF) 65° C. The new 230-kV circuit breakers at Douglas Switchyard and
Rapids Switchyard will be rated for 3000 A of continuous current. The new 230-kV
breaker disconnect switches at Douglas Switchyard will be rated for 3000 A of
continuous current and the 230-kV line disconnect switches at Douglas Switchyard and
Rapids Switchyard will be rated for 2000 A of continuous current.
The new transmission line is planned to be in operation in April, 2014.
The project is currently under construction and is tentatively scheduled for completion
in April, 2014. The transmission line is complete, and the remaining work is to finish
installing the transformer at Rapids Switchyard.
Jerry Kyle
509-881-2234
(DCPUD)
Rapids-Columbia 230-kV
Transmission Line
230
4/2015
57
Douglas County PUD is constructing a new 230-kV transmission line to connect its
Rapids Switchyard with BPA’s Columbia Substation. The conductor will be 1590
ACSR/TW and is expected to have a Summer rating of 438 MVA, a Winter rating of
591 MVA, and a Spring/Autumn rating of 512 MVA. The new circuit breaker at Rapids
Switchyard will be rated for 3000 A of continuous current. The new line disconnect
switch at Rapids Switchyard will be rated for 2000 A of continuous current.
“
Columbia-Larson 230 kV
line
230
2014
1.0
This project will involve in construction of a new 30-mile 2-1272 ACSR 230 kV line
from Columbia to Rocky Ford, open the existing Larson-Rocky Ford 230 kV line at
Rocky Ford during normal conditions, then tie the new line to the existing LarsonRocky Ford circuit, making a new Columbia-Larson 230 kV line. The purpose of this
project is to provide additional transmission capacity to serve projected load growths.
The project has been publicly announced and is scheduled to be in-service in early CY
2014.
Ken Che
(509) 754-5033
(GCPUD)
King 230/138 kV Project
230/138
2012
.1
A new 230/138 kV 300 MVA transformer will be installed in the existing King 138 kV
substation to accommodate approximately 135 – 150 MW of additional wind
generation in the Hagerman area. The King substation will be interconnected to the
230 kV transmission system by looping in-and-out the existing Midpoint-Dram 230 kV
line. Because the wind generation projects, which the King 230/138 kV project is to
accommodate, have been slow in their development, the in-service date has been
deferred to spring 2012. This project has no significant impact on the WECC
transmission system.
Mark D. Hanson
208-388-2253
(IPC)
Hemingway – Boardman
500
2018
2
1
Idaho Power’s 2013 Integrated Resource Plan, a biennially-produced 20-year resource
Mark D. Hanson
208-388-2253
1000 MW
3
Page 24 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transmission Project
Midpoint T232 230/138 kV
Transformer Addition Project
230/138
6/2020
.1
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
plan for meeting our electric service obligation, identified Pacific Northwest generation
resources as one component of the preferred resource portfolio. Requirements of
Idaho Power’s wholesale transmission customers are also increasing. The existing
transmission system connecting Idaho Power to the Pacific Northwest is fully
subscribed during high-demand periods. To meet the need for more transmission
capacity with the associated improvement in system reliability, Idaho Power plans to
build a 500 kV transmission line from southern Idaho to northeast Oregon.
The plan of service is to construct a 300 mile 500 kV transmission line from
Hemingway station in southwestern Idaho to a new station, Grassland or Longhorn
depending on final routing, near the existing Boardman Power Plant in northeastern
Oregon. The Hemingway-Boardman Transmission Line Project’s proposed and
alternative routes are shown in Figure 1. The Hemingway-Boardman Transmission
Line Project scheduled in-service date will be no earlier than 2020.
Path 14 transfer capacity ratings with the Hemingway-Boardman Transmission Project
facilities are expected to increase to 2250 MW west to east (a 1050 MW increase) and
a 3400 MW east to west (a 1000 MW increase). Project facilities are listed below:
Hemingway-Boardman 500 kV line, 300 miles with approximately 50% series
compensation (split equally at each end); the western termination will be at the
Grassland switching station near the Boardman Power Plant
Hemingway 500 kV Line Terminal with Shunt Reactors and Series Capacitor
Grassland/Longhorn 500 kV Line Terminal with Shunt Reactors and Series Capacitor
and 150 Mvar, 500 kV Shunt Capacitor Hemingway-Bowmont #2 230 kV line, 13 miles
with single 1590 MCM ACSR “Lapwing” conductor
Bowmont-Hubbard 230 kV line, 16 miles with single 1590 MCM ACSR “Lapwing”
Conductor Bowmont, 2nd 230/138 kV 300 MVA Auto-Transformer
The Hemingway-Boardman Transmission Project will conform to the NERC TPL-001-4
Standard and other corresponding regional System Performance requirements at the
time, if any,. and the WECC “Overview of Policies and Procedures for Project
Coordination Review, Project Rating Review, and Progress Reports.”
A Hemingway-Boardman Transmission Project Comprehensive Progress Report
(Phase I) was released for comment in November 2008 and was granted Phase II
status in March 2009. Idaho Power began the Phase II study process in 2011; the
initial kick-off project review work group meeting was held on June 22, 2011, and the
second project review group meeting was held on November 15, 2011.
The third project review group meeting was held on March 22, 2012. On August 10,
2012, a conference call/webinar was held to solicit comments on the initial Phase II
draft report. In August 2012, Idaho Power submitted the Idaho-Northwest Up-rate,
Hemingway-Boardman 500 kV Transmission Project Phase II Report to WECC and
was granted Phase III status on November 29, 2012 with an Accepted Rating of 2250
MW west-to-east and 3400 MW east-to-west.
(IPC)
A second 230/138 kV 200 MVA transformer will be installed at the Midpoint substation
due to anticipated load growth in the Magic Valley area. The scheduled/projected inservice date is June 2020. This project is intended for load service and has no
“
Page 25 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
significant impact on the WECC transmission system.
Midpoint West Upgrade
Project
230
2015
.25
The 230 kV looped connection in and out of the Rattlesnake switching station,
currently installed in the Midpoint-Boise Bench 230 kV #2 line, will be relocated to the
Midpoint-Boise Bench 230 kV #1 line between DRAM and Justice. Both 230 kV lines,
as well as the Midpoint-Boise Bench 230 kV #3 line, are all part of Idaho's internal
Midpoint West path. In addition to the relocation, the series capacitor banks at Midpoint
on the #2 and #3 lines will be replaced and increased to 70% comp each. These
upgrades are being done to gain approximately 275 MW of east to west transfer
capability across Midpoint West with the added benefit of approximately balancing the
flows on the Midpoint-Boise Bench 230 kV #2 & #3 lines. We expect the in and out
relocation for Rattlesnake to be completed in June of 2015. We expect the series
capacitor bank replacements to be completed sometime in the fall of 2015. This project
has no significant impact on the WECC transmission system
Pearl Transmission
Substation
230
5/2019
.3
Because of the addition of the Langley Gulch Generation Project in the Treasure
Valley (see Langley Gulch Generation Project above) and developing the Hemingway
500/230 kV station and its associated 230 kV transmission integration into the
Treasure Valley (see Hemingway-Boardman Transmission Project above), the Pearl
Transmission Substation project has been deferred beyond Idayho Power’s 10-year
planning horizon..
“
Midpoint T232 230/138 kV
Transformer Addition Project
230
June 2020
.1
200 MVA
A second 230/138 kV 200 MVA transformer will be installed at the Midpoint substation
due to load growth in the Magic Valley area. The scheduled/projected in-service date is
June 2020. This project has no significant impact on the WECC transmission system.
“
Lucky Corridor Transmission
Project
230/115
2016
2
850 MW
0
0
0
0
0
Lucky Corridor, LLC provided an initial progress report on December 19, 2012. Lucky
Corridor, LLC is developing a transmission project to deliver renewable and gas
generation from northeastern New Mexico to markets in the west. The Lucky Corridor
Project is designed as a 230 KV upgrade to an existing 93 mile 115 KV transmission
line between Gladstone and Taos substations. The new line will use the existing 115
KV rights of way and will be constructed as a double circuit 230 kV
transmission line. Also included in the Project are upgrades to the Taos to Ojo 345 KV
line and required lower voltage lines.
Lynn Chapman
Greene
(303) 681-3073
Lucky Corridor
500 kV Upgrade Project
500
2018
10
2
3000
3
16
0
0
0
0
0
500 kV Upgrade: Series compensation system will be increased as needed to
achieve new capacity. A Supplemental Progress report is attached showing
new capacity as 3000 MW. The earliest operation date is 2018
John Leland
406-497-3383
(NWMT)
Path 18 Upgrade
230
2014
2
383 MW
3
230
On Hold
2
WKN Wind Project
396
Path 18 Upgrade: Path 18, Montana to Idaho, will be upgraded by 46 MW.
The new capacity on this 230 kV line will be 383 MW. A Supplemental
Progress report is attached. The earliest operation date is 2014.
“
WKN: The Feasibility, System Impact, and Facility Studies have been
completed. An LGIA was signed on December 29, 2010. A Supplemental
″
Page 26 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Progress Report is attached for this 396 MW wind project. Project is
suspended per customer's request.
Jawbone Wind Project
460
230
On Hold
2
Mountain States
Transmission Intertie Project
500
2013
3
TOT 4A Voltage Support
Project
230
2016
1.1
Wallula to McNary 230 kV
(#2) Transmission Line
(December 2017)
230
12/2017
1
Jawbone Wind: The Feasibility, System Impact, and Facility Studies have
been completed. An LGIA was signed on November 5, 2012. A
Supplemental Progress Report is attached for this 460 MW wind project.
Project is suspended per customer's request.
1500
2
2
The Regional Planning Project Review for this project was begun on 5/17/07. The
proposed project consists of a new 500 kV line between southwestern Montana and
southeastern Idaho. The main purposes for the project will be to meet requests for
transmission service from customers and relieve constraints on the high-voltage
transmission system in the region. The Regional Planning Project Review Report for
this project was distributed for review on 2/14/08 with a review deadline of 3/14/08. On
4/23/08, the MSTI project successfully completed Regional Planning. Currently this
project is in Phase II of the WECC 3-Phase Rating Process.
“
The following facilities have been identified for Wyoming voltage support:

Atlantic City 230 kV, 15 MVAr Capacitor (In-service: October 2010)

Riverton 230 kV, 30 MVAr Capacitor (In-service: August 2010)

Midwest 230 kV, 30 MVAr Capacitor (In-service: October 2010)

Dynamic voltage control in the Miners Area has been superseded by
Standpipe 230 KV Synchronous Condenser project-Projected in-service
date for (2016)
Craig Quist
801-220-4264
(PAC)
The Wallula to McNary 230 kV #2 line would be a single circuit transmission line with
line terminals at Wallula and McNary substations.
“
Phase 2 studies are being performed; when complete they will be reviewed by the
project review group.
This project has impacts to other regional facilities most notably BPA as the project
has a terminal at BPA’s McNary Substation. Phase 2 studies are being performed and
when complete will be reviewed by the project review group.
Whetstone 230/115 kV
Substation
Current Creek
Union Gap 230/115 kV
Transformer Addition
Vantage-Pomona Heights
230 kV Line
230/115
2015
.1
Construct new 230 to 115 kV in the White City Oregon vicinity with a 250 MVA
transformer. This substation will tap PacifiCorp’s existing 230 kV line between Meridian
and Grants Pass Substations. The project is intended to provide load service
redundancy.
2016
.05
Planned new generation.
230/115
2016
.1
230
12/2016
1
550
250 MVA
“
This project will construct a third 250 MVA transformer at Union Gap.
“
This project will construct a new 230kV line between the Vantage and Pomona Heights
230kV buses in Washington State.
“
Page 27 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gateway Central
Transmission Project
Gateway West Transmission
Project
Gen
MW
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Transmission
kV
Date
No. of
pages
500/345/138
2017
1.2
This project consists of the following: (1) double-circuit 345 kV transmission line
stretching approximately 90 miles from the Populus Substation to be built near
Downey, ID, to the existing Ben Lomond Substation in Box Elder County, UT, (2) new
double-circuit 345 kV transmission line alongside existing high-voltage lines from the
Ben Lomond Substation to the Terminal Substation near the Salt Lake City airport, a
distance of approximately 46 miles, (3) a new high-voltage transmission line and two
future substations in UT which will originate at a substation to be built near the existing
Mona Substation outside Mona in Juab County, and run north to another future
substation. The line will then split and connect to Oquirrh Substation in West Jordan
and to Terminal Substation in Salt Lake City, and (4) a new line between the Oquirrh
Substation in West Jordan north to Terminal Substation. This section of new
transmission will link together other new transmission sections: Mona to Oquirrh and
Populus to Terminal to complete the Gateway Central portion of the Energy Gateway
Tramsmission Expansion Project.
“
500/230
2020-2024
6
The Gateway West project was jointly announced by Idaho Power and PacifiCorp
(Rocky Mountain Power) in May 2007, to build and operate approximately 900 miles of
new high-voltage transmission lines between the Windstar substation near Glenrock,
Wyoming and the Hemingway substation near Melba, Idaho. The Gateway West –
Stage 1 project will include approximately 150 miles of 230 kilovolt (kV) lines in
Wyoming and approximately 800 miles of 500 kV lines in Wyoming and Idaho.
Gateway West– Stage 2 transmission facilities primarily consist of a second set of 500
kV circuits from southern Wyoming to western Idaho.
PacifiCorp reported in the 2011 Annual Progress Report submission that the third party
requests and financial commitments that are necessary to support the Energy
Gateway – Stage 2 facilities have not materialized. Therefore, PacifiCorp indicated that
it would continue to pursue WECC path ratings for Stage 1 of Energy Gateway only at
that time, and will not further pursue ratings for Stage 2 facilities. This Energy
Gateway Project status update was also reported to TSS at the April 20-22, 2011,
meeting in Westminster, Co.
For Gateway West – Stage 1 transmission paths located west of Populus [specifically
Borah West and Midpoint West], Idaho Power was the project sponsor for each of the
path ratings studied; additionally for Gateway West transmission paths located east of
Populus [specifically TOT 4A, Aeolus West, Path C and Bridger/Anticline West],
PacifiCorp was the project sponsor for the path ratings studied. At the completion of
the Phase 2 path rating process, TOT 4A transmission path was granted Phase 3
status on December 13, 2010; Aeolus West, Bridger/Anticline West and Path C
transmission paths were granted Phase 3 status on January 5, 2011; and Borah West
and Midpoint West transmission paths were granted Phase 3 status on July 21, 2011.
Both the Gateway West and Gateway South siting and permitting requirements are
currently being reviewed separately under the National Environmental Policy Act
(NEPA) process. Future changes to the Energy Gateway Project facilities and
configuration may be influenced by the NEPA process and permitting requirements
until this process concludes, which today expected to conclude for Gateway West in
“
Phase
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Page 28 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
2013 and for Gateway South in 2015. At the conclusion of the NEPA process, specific
path rating performance issues relative to any necessary changes in Energy Gateway
Project facilities and configuration will be addressed with affected Project Review
Groups – rather than approach the group with “piece wise” changes, at the time each
change becomes known throughout the NEPA process.
Based on the agreement between PacifiCorp and Idaho Power, executed in early
2012, PacifiCorp will assume responsibility for sponsoring all Gateway West
transmission facilities through the NEPA process and through the project construction
agreement phase.
Gateway South 500 kV
Project
500
2015-2022
4
Syracuse –Install 345/138
kV #2 Transformer
345/138
5/2021
Mid Valley SubstationReplace 345-138kV, 450
MVA with 700 MVA
Transformers
345/138
Black Rock 230/69 kV
Substation (2013)
230/69
Carbon Plant
Decommissioning (2015)
2
1
The Gateway South – Stage 1 Transmission Project as proposed by PacifiCorp
includes a 500 kV transmission line from the proposed Aeolus substation in southeast
Wyoming (constructed as part of the Gateway West Project) to the Clover substation in
central Utah, and a 345 kV transmission project from the Sigurd substation near
Richfield, Utah to the Red Butte substation in southwestern Utah. PacifiCorp is leading
the planning effort and managing the WECC rating process for the project. The
Gateway South project entered Phase 2 in January 2009. Of the transmission paths
associated with the project, the Aeolus South path was granted Phase 3 status on
December 16, 2010 while the TOT 2B/2C Paths should be granted Phase 3 status in
the first quarter of 2011. PacifiCorp is proposing this transmission project because of
native load growth and the need to deliver renewable resources from Wyoming to
PacifiCorp retail load centers. PacifiCorp forecasts that its load on the Wasatch Front
of Utah will double in the next 20 years. Additionally, PacifiCorp has an independent
obligation, pursuant to its Open Access Transmission Tariff, to plan for and expand its
transmission system based upon the needs of its native load and network customers
along with eligible customers that agree to expand the transmission system.
“
.1
Install a 345-138 kV transformer (T#6) including (1) 345 kV circuit breaker and (1) 138
kV circuit breaker at Syracuse substation.
“
2020
.1
Replace two 345-138kV 450MVA transformers at Mid Valley substation with 700 MVA
units.
“
In Service
1
This project consists of looping in and out of Pavant-Gonder 230 kV line and the DeltaGraymont 69 kV line and installing a 75 MVA -230/69 kV transformer at Delta.
“
4/15/2015
1
The Carbon Plant decommissioning will require the addition of the following facilities: 15/+85 MVAR 138 kV static VAr system (SVS), two 138 kV 15 MVAR capacitor banks
with associated breakers at the Mathington substation. The addition of a phase shifting
transformer (PST) at the Upalco substation. Relocation of the Spanish Fork 138 kV
series line reactors to the Upalco substation.
“
Page 29 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Huntington-Mona/ 345 kV
Line Series Reactor at
Mona/Clover
Transmission
kV
345
Date
No. of
pages
2014
1
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Install an 18 ohm series reactor in the Mona- Huntington 345 kV line at Mona to
increase transfer capability across the “North of Sigurd/Huntington” transmission path.
“
A study was conducted to determine the optimum reactor size. It was determined that
an 18 ohm series reactor provided the most optionality in future resource location
(Huntington vs. Sigurd), while increasing the North of Huntington/Sigurd flow limits.
This project will support an increase in south to north transfers from southern to
northern Utah.
Snow Goose Project
500/230
2016
1
New 500/230kV substation tapping PacifiCorp’s Captain Jack to Klamath Co-Gen 500
kV line. The 230kV line construction will include looping the existing Klamath Falls to
Malin 230kV line into the new substation. The project is only connected to PacifiCorp
facilities and is intended to provide load service redundancy
“
Lakeside II Transmission
Network Upgrades (2014)
345
6/1/2014
1
Transmission of energy from the generation facility to beyond Steel Mill substation
requires the installation of two new 345kV breakers and looping in of the Camp
Williams – Emery 345kV line at Spanish Fork substation. Also required is a
reconductoring of the 10 mile Spanish Fork – Tanner 138kV line and communication
fiber to Hale substation
“
Pinto #3 Phase Shifting
Transformer Addition (2015)
345
12/2015
1
400 MVA
Install the third 345 kV /400 MVA, phase shifting transformer in parallel with the two
existing phase shifting transformers in a new bay at the Pinto substation.
Improvements include a new transformer pad, extension of bus work, a new 345kV
breaker, protection and control equipment and other new equipment.
“
Standpipe - Construct New
230kV Substation (2016)
230
2016
1
60 MVAr
Construct a new 230 kV substation called Standpipe. The new substation will be
located near Miners substation, and will intercept the existing Platte-Miners-Standpipe
230 kV line, resulting in the Platte-Standpipe-Freezeout 230kV line. Miners will be fed
radially from Standpipe following completion of the project. A new or relocated
synchronous condenser with a minimum capability of +60/-35 MVAr will be installed at
Standpipe to provide dynamic reactive support in the region. Additional project scope
to improve voltage stability and reliability for customers on the south central Wyoming
230 kV transmission system includes the relocation of an existing 31.7 MVAr shunt
reactor from Platte to Standpipe substation, installation of a 25 MVAr capacitor bank at
Latham substation, implementation of coordinated shunt reactive device controls at
Latham, Platte, Standpipe, Miners, and Foote Creek. The project will install a special
protection scheme to trip local area wind generation for contingency conditions that
result in low voltage in the Spence area of the Wyoming 230 kV system. Other system
improvements to be completed under the project include reconfiguration of the Platte
Substation 230 kV bus, relocation of the Standpipe line termination at Platte,
installation of a new 230 kV circuit breaker at Platte, reconfiguration of the Latham 230
kV bus to accommodate the new shunt capacitor, and communications upgrades to
facilitate relay upgrades and the special protection scheme.
“
2014-2020
1
PacifiCorp East and West
Future Generation Projects
1027
Project Queue
Number/Name
Page 30 of 91
Location
(County,
Status
“
Generation
Capacity
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
State)
Casper Substation-Install
230/115 MVA transformer
230/115
St. George SubstationInstall 345kV/138kV
transformer &
expand yard
Lakeside II
Utah, UT
Under
construction
2014
681 MW
Carbon
Carbon, UT
2015
Retirement
-67 MW
Carbon
Carbon, UT
2015
Retirement
-105 MW
375
Carbon, WY
2020
230 MW
398-B
Bonneville, ID
Suspended
288 MW
2015
Add a second 230-115 kV transformer at Casper substation, including expanding the
115kV bus, installing four new breakers and reconnecting the existing WAPA Casper
115kV transmission line into the new line position.
2020
This project includes three related segments necessary to provide anticipated growing
energy demands in Southwest Utah and to maintain the Company’s compliance with
NERC and WECC reliability standards.
The three segments are as follows:
– Reterminate
Harry Allen 345kV
Line & Reactor, and Add a
345kV Breaker.
“
St. George Substation; Install a
700 MVA 345/138 Transformer,
Line Termination and Two
Breakers (one each @ 345kV
and 138kV).
Table Mountain 500/230kV
substation
500/230
2019
1
New 500/230 kV Substation tapping PacifiCorp’s Meridian to Dixonville 500 kV Line,
tapping the existing Meridian-Grants Pass 230 kV line and adding a new 230 kV
transmission line from the new substation to the existing Grants Pass 230 kV
Substation. The project is only connected to PacifiCorp facilities and is intended to
provide load service redundancy.
“
Troutdale Substation, Add
3- 230 kV circuit breakers
230
2016
1
This project will install 3-230 kV circuit breakers at Troutdale substation, two on the
lines to PGE Gresham and Linneman Substations, and one between the two Troutdale
substation busses.
“
2012-2015
3
Planned Generation
Interconnection Projects
20-100
Project Queue
Location
Status
Generation
“
Type
Page 31 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
(PACE/PACW) – Waiver
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
Number/Name
One
Lines
Request Copy of
Report From
Maps
Capacity
154
Bonneville,
ID
267-A
Sweetwater,
WY
267-B
2012
19.8 MW
Wind
2019
22 MW
Wind
Sweetwater,
WY
n/a
22 MW
Wind
267-C
Sweetwater,
WY
n/a
22 MW
Wind
267-D
Sweetwater,
WY
n/a
22 MW
Wind
290-A
Sweetwater,
WY
n/a
100.8 MW
Wind
290-B
Sweetwater,
WY
n/a
100.8 MW
Wind
290-C
Sweetwater,
WY
n/a
50.4 MW
313
Beaver, UT
2013
65 MW
Geothermal
323-A
Power, ID
2011
21.6
Wind
323-B
Power, ID
2011
21.6 MW
Wind
335
Converse,
WY
49.6 MW
Wind
367
Iron, UT
n/a
172 MW
Solar
384
San Juan,
UT
n/a
60 MW
Wind
415
Beaver, UT
n/a
11 MW
Thermal
420
San Juan,
UT
n/a
140 MW
Wind
2013
Wind
Page 32 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Request Copy of
Report From
Maps
432
Salt Lake,
UT
n/a
6.3 MW
Other
437
Franklin, ID
n/a
0.5 MW
Hydro
442
Madison, ID
n/a
5.6 MW
450
Millard, ID
n/a
50 MW
Solar
454
Iron, UT
n/a
3 MW
Solar
455
Iron, UT
n/a
3 MW
Solar
457
Beaver, UT
n/a
2.1 MW
Solar
459
Beaver, UT
n/a
230
Klamath,
OR
3 Mw
Natural
Gas
Solar
2014
14 MW
Geothermal
237-B
Skamania,
WA
suspende
d
25 MW
Hydro
237-C
Skamania,
WA
suspende
d
25 MW
Hydro
276
Umatilla, OR
2015
98.9 MW
Wind
373
Klamath,
OR
2012
5 MW
Solar
389-B
Lake, OR
n/a
5 MW
Solar
393
Lake, OR
n/a
27 MW
Geothermal
422
Yakima, WA
n/a
5 MW
Solar
430
Klamath,
OR
n/a
12 MW
Geothermal
431
Siskiyou, CA
n/a
12 MW
Geothermal
Page 33 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Horizon Phase II Project
230/115
6/1/2018
0.1
The Horizon Phase II Project mitigates potential overloads to the Horizon 230/115
kV transformer for base case and single and double contingencies during peak
summer loading conditions. In addition, this project mitigates potential overloads
on the local area 115 kV system for double contingencies during peak summer
loading conditions. PGE plans to build out the Horizon substation breaker-andonehalf bus configuration and install a second bulk power transformer at Horizon
substation. The installation of this transformer dictates the need to replace
seventeen 115 kV circuit breakers at Sunset substation to mitigate fault duty
concerns; a second 115 kV capacitor bank will also be installed at Sunset substation
to provide voltage support. To provide a second source to Horizon substation, PGE
will construct a new 4.4 mile 230 kV line segment between Horizon substation and
Springville Junction. This line segment will tie into the existing St Marys-Trojan 230
kV circuit, creating a Horizon-St Marys-Trojan 230 kV circuit. The bulk power
transformer will be energized by June, 2017; and the new 230 kV line segment will
be energized by June, 2018.
Philip Augustin
503-464-7783
(PGE)
Pearl-Sherwood 230 kV
retermination
230
6/2019
0.1
PGE and BPA plan to re-terminate the Pearl-Sherwood 230 kV circuit (paralleled
Jefferson TW) into separate breaker positions at the Pearl and Sherwood substations.
In addition, this project will divide the Pearl-Sherwood section of the three-terminal
McLoughlin-Pearl-Sherwood 230 kV circuit (currently paralleled between Pearl and
Sherwood) into separate breaker positions at the Pearl and Sherwood substations.
This will require four new 230 kV breakers, two located at BPA’s Pearl Substation and
two at PGE’s Sherwood Substation. When this project is complete, there will be three
Pearl-Sherwood 230 kV circuits and a McLoughlin-Pearl-Sherwood 230 kV circuit.
″
Blue Lake-Gresham 230 kV
Line
230
6/2019
0.1
The Blue Lake/Gresham 230 kV Project mitigates potential overloads to the
Gresham-Troutdale BPA 230 kV circuit, the Linneman-Troutdale BPA 230 kV circuit,
and the Blue Lake 230/115 kV transformer for double contingencies during peak
summer or winter loading conditions in the Near Term Planning Horizon. PGE
plans to construct a six mile transmission line from Blue Lake Substation (Troutdale,
Oregon) to Gresham Substation (Gresham, Oregon). In addition, PGE will rebuild
the existing 1.5 mile Blue Lake-Troutdale 230 kV circuit tower line to accommodate
the new Blue Lake-Troutdale #2 230 kV circuit. This project requires the expansion
of the 230 kV yard at Blue Lake substation to a six position ring bus and the addition
of new breaker positions at Gresham substation and Troutdale substation.
″
Trojan-Horizon 230 kV line
230
1/2015
.3
PGE proposes to construct approximately 40 miles of new 230 kV transmission line.
The project starts from an existing PGE substation adjacent to the former Trojan plant
near Rainier, OR to the new proposed PGE Horizon Substation in Hillsboro, OR. PGE
will utilize 28 miles of currently unused right-of-way adjacent to the existing 230 kV
lines from Trojan to the Portland area. In addition to the new transmission line, the
Horizon Substation will be expanded to terminate the new 230 kV line as well as the
installation of a second 230/115 kV, 320 MVA auto-transformer to connect to the
adjacent 115 kV PGE Sunset Substation. Also, 2.7 miles of the Sunset-Orenco 115 kV
line will need to be reconductored with a 795 ACSS conductor.
“
Cascade Crossing 500 kV
500
Canceled
.7
PGE proposes to construct approximately 210 miles of new 500 kV transmission line.
″
2
Page 34 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Project
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
The project starts at PGE’s Coyote Springs generation plant located in the town of
Boardman, OR, and ultimately terminates with the installation of a new 500/230 kV
transformer bank at PGE’s Bethel Substation located in Salem, OR. The Boardman
and Coyote Springs substations will be expanded to accommodate the project. PGE
will need to acquire approximately 30 miles of new ROW for the Boardman to Coyote
Springs 500 kV line. After the Boardman substation the project will connect to new
wind resources being developed in Gilliam and Wasco counties in Oregon. The
project will parallel existing utility lines whenever possible by acquiring additional ROW
for approximately 180 miles along the route into Salem, where the line will terminate at
an expanded Bethel substation.
On June 3, 2013, Portland General Electric suspended permitting and development of
the proposed Cascade Crossing Transmission Project. Changing market conditions
have created opportunities to explore lower-cost alternatives for customers and
provide the needed transmission capacity for PGE with reduced environmental
impacts.
At this time, PGE is requesting that the “Cascade Crossing Project” be removed from
the WECC Path Rating Process; PGE will no longer represent the Project in WECC
planning cases.
McLoughlin 230 kV Bus
Sectionalizing Breaker
6/2012
.1
PGE plans to operate the 230 kV bus sectionalizing breaker at the McLoughlin
substation in Oregon City Oregon in the normally open position beginning in
summer 2012. This operational procedure is different from past normal system
operation.
6/2015
.1
Port Westward Unit 2 will use reciprocating engines to provide 225 megawatts of
flexible peaking capacity to react to spikes in power demand and changes in power
output at renewable energy generating facilities. The plant will be located adjacent to
PGE’s existing natural gas-fired plants, Beaver and Port Westward, located near
Clatskanie, Oregon. This project requires the reconductoring of 8 miles of the Port
Westward-Trojan #1 230 kV circuit generator lead.
115
2014
.1
The project involves looping Clallam County’s 115 kV transmission line serving the
Port Townsend Mill through PSE’s Irondale substation. The project is intended to
provide backup transmission to Jefferson County. This project will not occur under
PSE’s jurisdiction if Jefferson County’s municipalization of PSE’s energy delivery
system becomes effective in 2013.
Pierce County Transformer
Addition and Line Reroutes
230/115
2016
.1
The project is to install a 230-115 kV transformer at Alderton Substation and build 8
miles of 230 kV transmission line from White River Substation to Alderton Substation,
as well as re-routing 115 kV lines. PSE requested and received a waiver of significant
transmission project status for this project in 2013. The project is intended to provide
additional capacity to serve the projected load growth in Pierce County and
surrounding areas. It has no impact to the WECC or any neighboring electric systems.
″
Starwood-Tideflats 115/110
kV Transformer Removal
115/110
In-Service
.1
With Tacoma Power increasing its sub-transmission voltage schedule from 110 kV to
115 kV in 2013, the existing ‘step down’ Starwood transformer was no longer
″
Port Westward II generation
Jefferson County 115 kV
Upgrade Phase II
230
225
″
Peter Jones
425-462-3171
(PSEI)
Page 35 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
necessary. A bypass of the existing bank was finished in the summer of 2013 to
coincide with the timing of Tacoma Power’s voltage schedule increase. This project
was a combined engineering effort between PSE and Tacoma Power; it had no impact
to the WECC or any additional neighboring electric systems.
Thurston County
Transformer Addition
230/115
Tono Transformer
Improvements
Eastside 230 kV
Transformer Addition and
Line
230/115
2014
.1
2014
.1
2018+
.75
546 MVA
The project is to install a 230-115 kV transformer at St. Clair Substation and build a 5mile 230 kV transmission loop between St. Clair and the existing BPA Olympia – S.
Tacoma 230 kV line. PSE requests a waiver of significant transmission project status
for this project. The project is intended to provide additional capacity to serve the
projected load growth in Thurston County and surrounding areas. It has no impact to
the WECC or any neighboring electric systems.
“
This project will involve replacement of limiting current transformers at the Tono bank.
This improvement will increase capacity from the existing limit of 398 MVA up to 546
MVA. The project is intended to increase reliability for serving approximately half of the
existing load in Thurston County. It has no impact to the WECC or any neighboring
electric systems.
“
This project had been titled “Lakeside Substation 230 kV Transformer Addition” in
progress reports prior to 2013.
The project will involve installation of a 230-115 kV transformer at an existing or future
PSE Substation. This project includes new construction of 230 kV lines or rebuilding
existing 115 kV lines, energizing at 230 kV to provide a source to the new transformer
and adding transmission capacity. Installing this transformer will address NERC
planning criteria and provide additional capacity to serve the projected load growth in
north central King County and surrounding areas.
The attached document, ‘Eastside Transformer Project.pdf’, shows the possible
locations and associated transmission routes.
ColumbiaGrid is a Subregional Planning Group in the Pacific Northwest and has open
participation in its planning meetings and the Puget Sound Area Study Team (PSAST).
This project has been developed by and has achieved consensus via the
ColumbiaGrid PSAST, which included all the transmission owners that could be
impacted by this project. The “Eastside 230 kV Transformer Addition and Line
Rebuilds” project began to be studied by the PSAST in mid-2009, and was in PSE’s
Annual Progress Report last year. The most recent report is entitled “Updated
Recommended Transmission Expansion Plan for the Puget Sound Area to Support
Winter South-to-North Transfers”, June 17, 2011. The report recommends this project
and four other transmission improvements, and is available from ColumbiaGrid
www.columbiagrid.org. The requirements of project coordination review for this project
have been met through the ColumbiaGrid acting as a Subregional Planning
Group.
The attached document, ‘WECC Comprehensive Project Coordination Review
Letter_PSAST 2-21- 13.pdf’, describes the coordinated ColumbiaGrid study efforts.
The energization date for the Eastside 230kV project has been pushed out since this
review letter was written.
“
Page 36 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Date
230/115
2018+
.1
Sea Breeze Pacific Regional
Transmission System
500
10/1/2006
22
600
2
1
Two new 500 kV transmission lines between Vancouver Island (BCTC’s Pike
substation) and the Olympic Peninsula (BPA’s Port Angeles and Fairmount 230 kV
substations).
E. John Tompkins
Sea Breeze Pacific
RTS
(860) 747-0497
Sea Breeze Pacific – West
Coast Cable Project
500
2010
3
1600-3200
1
1
500 kV DC bi-pole transmission interconnection between the Alston Substation in
Alston, Oregon and one or more substations in the San Francisco, CA Bay area
“
Sea Breeze Pacific – Juan
de Fuca Cable Project (jdF)
+/- 150 kV DC
Q4/2014
1
550 MW
2
+/- 150 kV 550 MW HVDC Light transmission cable connecting the Olympic Peninsula
of WA State (BPA) with Vancouver Island in British Columbia (BCTC). The Juan de
Fuca Cable Project will run under the Strait of Juan de Fuca, connecting the Bonneville
Power Administration’s Port Angeles substation in Port Angeles, Washington to the
existing BC Hydro Pike substation in Greater Victoria, British Columbia. Associated
facilities include converter stations adjacent to the existing substations.
Sara Van Mulligen
(604) 689-2991
Southwest Intertie
Transmission Project
(SWIP)
500
2014
.3
This project is considered as Phase II to ON Line Project. Install 500-kV 275 mile long
Line from Idaho Power’s Midpoint to the proposed Robinson Summit Substation
located 20 miles west of Ely, Nevada. Install 70% series compensation (for 245 mile
line impedance) equipment on this line as follows: 35% at Thousand Springs located
126 miles from Midpoint and 35% at Robinson. Install 2×600 MVA 345/345 kV Phase
Shifting Transformers (PST) at Robinson Summit: one on Falcon and another – on
Gonder 345 kV line terminals respectively. Install 70% series compensation on
Robinson – Harry Allen 500 kV line, 35 % at each end. NVE and LS Power are in a
process of performing SSR studies to identify possible adverse effects on the near-by
generators. As designated in the Transmission Use and Capacity Exchange
Agreement (TUA) signed on 8/20/2010 between NVE and Great Basin Transmission,
LLC (GBT), SWIP will be a jointly owned project by the parties.
Edi von Engeln
NV Energy North
(775) 834-4456
Southern Nevada Intertie
Transmission Project (SNIP)
500
2014
.2
This project is considered as a part of SWIP-South Project. Construct 500-kV 60 mile
long line from NVE’s Harry Allen Substation to Southern California Edison’s Eldorado
Substation. Install 70% series compensation at Harry Allen. NVE and GBT are in a
process of performing SSR studies to identify possible adverse effects on the near-by
generators. As designated in the Transmission Use and Capacity Exchange
Agreement (TUA) signed on 8/20/2010 between NVE and Great Basin Transmission,
LLC (GBT), the SNIP will be a jointly owned project by the parties. The proposed inservice date is, 2014.
“
West Kitsap Transmission
Project, Phase II
Transmission
kV
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
No. of
pages
Name of Project
Gen
MW
Phase
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
“
The project is to install a 230-115 kV transformer at Foss Corner Substation, and build
a 230 kV line from Foss Corner to a future line bay position in the BPA Kitsap 230 kV
Substation. PSE requests a waiver of significant transmission project status for this
project. The project is intended to provide additional capacity to serve the projected
load growth in Kitsap County and surrounding areas. It has no impact to the WECC or
any neighboring electric systems.
Page 37 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Date
345/120
6/2018
.1
This is a new substation with a projected in-service date of June, 2018. This project is
postponed indefinitely.
“
Fallon 230 kV Source
230
6/2014
.3
Install a new 230 kV line From Pony Express Switching Station (Enel) to a new 230/60
kV substation (approximately 1/2 mile South of Fallon) and build a series of
substations and switching stations (Pony Express, Bunejug, and Macari) to provide
new source, via a 25 mile 230 kV line, to the City of Fallon. The projected in service
date for this project is June 2014. The scope of this project has been changed due to a
reduction in load growth in Fallon area, the termination of one LGIA and the reduction
in a second LGIA have also contributed to the reduction in scope of this project. The
project will now likely to be a 10 mile 230 kV generator lead line heading southward
from the generator interconnect, company BO, with a reduced LGIA to the Pony
Express Switching Station. The Pony Express switching station will be constructed at
an existing generator interconnection site (Enel) and then connects to NV Energy’s
Northern 230 kV system about five miles further south. No connection will be made
from into Fallon from interconnection BO switching station.
″
One Nevada Transmission
Intertie Project (ON Line)
(previously known as Ely
Energy Center and
associated Robinson
Summit – Harry Allen 500
kV Transmission Project)
500
Q1/2013
.3
Constructing 500-kV 236 mile long line from the proposed Robinson Summit
Substation located 20 miles west of Ely, Nevada to the existing Harry Allen Substation
located northeast of Las Vegas, Nevada. Fold existing Falcon – Gonder 345 kV line
into Robinson Summit Substation and connect 345 kV and 500 kV buses through
2×525 MVA 345/500 kV autotransformers. Install 70% series compensation equipment
on Falcon – Robinson 345 kV line, 35 % at each end. NV Energy has completed SubSynchronous Resonance (SSR) studies identifying adverse effects and developed
mitigations for NV Energy’s assets. As designated in the Transmission Use and
Capacity Exchange Agreement (TUA) signed on 8/20/2010 between NV Energy and
Great Basin Transmission, LLC (GBT), the ON Line is a jointly owned by NV Energy
and GBT. At this time, the latest updated in-service date is Q1, 2013..
″
Bothell – SnoKing 230 kV
lines
230
2017
.25
The project will re-conductor the double circuit Bothell-SnoKing 230KV lines with high
temperature conductor. The purpose of this re-conductoring is to improve South-toNorth transfer capability between the Northwest and British Columbia. Seattle City
Light and Bonneville Power Administration will re-conductor their own section of the
double circuit. The estimate in-service date for project will be 2017.
Desmond Chan
206-615-0654
(SCL)
Delridge-Duwamish 230 kV
line
230
2017
.25
This project will re-conductor the Delridge-Duwamish 230KV line with high temperature
conductor. The purpose of this re-conductoring is to improve South-to-North transfer
capability between the Northwest and British Columbia. The estimate in-service date
for project will be 2017.
“
230/115
12/2016
.2
1. SNPD will construct a new 115 kV switchyard at Beverly Park substation, using a
breaker‐and‐a‐half scheme to replace the existing single bus configuration.
2. SNPD will install ONE new 230/115 kV transformer for the Beverly Park substation.
This transformer will function as a backup transformer for loss of two out of three
230/115 kV transformers at BPA Snohomish substation.
3. BPA will perform work at BPA Snohomish substation to provide a 230 kV source to
Long T. Duong
(425) 783-4305
(SNPD)
Blackhawk 345/120 kV
Substation (was Emma)
Beverly Park 230/115kV
Transformer
Transmission
kV
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
No. of
pages
Name of Project
Gen
MW
1000
300 MVA
Phase
2
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Page 38 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
Beverly Park substation. BPA owns the new 230 kV feed from BPA Snohomish to
Beverly Park substation.
230 kV Re-Termination
Project
230
7/2013
.1
The purpose of this 230 kV Re-termination Project is to improve Tacoma Power’s
system reliability and operational flexibility. The first part of this project to re-terminate
TPWR’s Tacoma-Cowlitz #2 and Cowlitz-Southwest #3 230 kV lines to form the new
Tacoma-Southwest 230 kV line was completed and placed in service in August 2012.
The second part of the project, which involves
the re-termination of BPA’s “South Tacoma- Cowlitz #1” 230 kV line from TPWR’s
Cowlitz 230 kV bus to TPWR’s “Southwest #4” 230 kV line to form the new “South
Tacoma-Southwest” 230 kV line was postponed and is now anticipated to be
completed and released to operations in July 2013.
Francis Tong
253-502-8262
(TPWR)
Southwest 230 kV Ring Bus
Conversion
230
9/2014
1
This project involves converting the existing main and auxiliary bus configuration at
Tacoma Power's Southwest Substltion to a more reliable and efficient ring bus
configuration. The number of terminals wiU remain at four with two for the incoming
230 kV lines and two for the 230/115 kV transformers. This project not only improves
system reliability and operational1lexibility, it also prevents a single element from
causing a total 230 kV bus outage at TPWR's Southwest Substation.
Canyon Substation /
Switching Station
+/- 500 kV DC
2017-19
1
2000 MW
2
1
NorthernLights is a 500 kV, direct current, 2000 MW transmission line from
southeastern Alberta, Canada to the Buckley station in northern Oregon. The
Regional Planning process was completed in February 2008 and the Phase 2 status
was achieved in March 2009. Further activity on the project is awaiting decisions
within Alberta of the need for increased interconnection capacity to other markets. The
project cost is $2 billion with an ISD of 2017 to 2019.
Bill Hosie
403-920-7338
(TCP)
Zephyr Project
+/- 500 kV DC
2016
.1
3000 MW
1
Zephyr is a 500 kV, direct current, 3000 MW transmission line from south-eastern
Wyoming to the Eldorado Valley in southern Nevada. The Zephyr development plan
includes a potential 750 MW intermediate converter station near the Borah substation
in south-eastern Idaho. The Regional Planning process was complete in November
2009. In 2010, TransCanada concluded a successful Open Season with three
substantial creditworthy Wyoming wind developers (Pathfinder Wind, BP Wind and
Horizon Wind) executing precedent agreements for the entire 3000 MW of Zephyr
capacity. TransCanada and its customers are establishing market support prior to
moving forward with full scale siting and permitting activities. The project cost is $3
billion with an ISD of 2016.
“
Chinook Project
+/- 500 kV DC
2017
.1
3000 MW
1
Chinook is a 500 kV, direct current, 3000 MW transmission line from south-central
Montana to the Eldorado Valley in southern Nevada with a potential future 750 MW
intermediate converter station near the Borah substation in south-eastern Idaho. The
Regional Planning process was complete in November 2009. TransCanada
conducted an Open Season for the Chinook project that closed on December 16,
2010. Bids totaling 1500 MW were received; however they were not accepted as the
amount was insufficient to justify allocating capacity at this time. TransCanada may
decide to hold a new open season process, if regulatory uncertainties get resolved and
“
Page 39 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
if Montana energy project developers express sufficient interest in a new open season.
It is not unusual for projects of this scale to test the market a number of times. The
fact that a project is not successful in one open season does not mean that a project
is dead and, indeed, other transmission projects in the west have had multiple open
seasons. The project cost is $3 billion with an ISD of 2017.
Havre to Rainbow 161kV
Rebuild / Upgrade
161
2022
.75
This project is on-hold status due to high priority oil load growth. Western’s 103 mile
Havre – Verona – Rainbow 161kV transmission line was constructed and energized in
1935. It electrically parallels NorthWestern Energy’s (NWE’s) Havre – Rainbow 161kV
circuit. These two circuits maintain separate rights-of-ways with two crossings.
Western intends to rebuild its circuit in segments, at 230kV specification. Each
segment is anticipated to be complete and re-energized in approximately one month.
The existing right-of-way is inadequate and will be expanded in most areas and rerouted in others. An Environmental Assessment (EA) is complete for this project and
has been issued for final publication. The first 30 mile segment between Havre and
Verona is complete, along with 1 mile at the Rainbow / Great Falls end for retermination into NorthWestern Energy’s (NWE's) Great Falls Substation in conjunction
with Project 2) described below. In 2011, 14 miles of reroute and reconstruction began
in the Loma, MT area and was approximately one-third complete when crews were redispatched due to storm damage in Eastern Montana / Western North Dakota (East
Grid WAUE BA). Due to both storm damage and dramatic oil exploration load growth
in the Eastern Montana / Western North Dakota area, this project has been placed onhold for approximately 5 years, with approximately 5 years of construction remaining
prior to completion. Therefore, target completion is estimated to be 2022. Once the
project resumes, construction will again continue during non-peak loading periods only.
Upon completion of each segment, the line will continue to be energized at 161kV until
such time that conversion to 230kV is required. Additional system impact study
analyses will be required with stakeholder approval prior to the 230kV voltage
conversion. No interruption of customer service during construction is anticipated with
this project. The project will receive a single 1 mile reroute this summer, near Carter, to
raise the highway crossing for accommodation of extra large/tall shipments of prefabricated tanks North of Great Falls, MT.
Frank E. Jarvenpaa
(406) 247-7384
(WAUM)
Havre Substation Upgrade
161/115/12.47
Fall/ 2014
.2
Western currently owns, operates and maintains the Havre 161/115/12.47kV
Substation. Upgrades are a result of needed relaying replacements and a new 115 kV
interconnect for network load. The existing 115 kV single breaker and bypass switch
will be replaced with a ring bus configuration serving the existing Shelby circuit and
new network service interconnect. In addition, a new dedicated circuit interrupter will
be installed for protection of the transformer. Construction design is complete. The
control building was completed 2012 and currently is receiving protective relaying
upgrades. Completion of the 115 kV yard work is expected by fall of 2014. The 115 kV
bus will be out of service for extended periods during the 2014 construction season.
However, no interruption of customer service during construction is anticipated. Minor
outages are expected for Hill County Electric Coop during sequenced re-energization.
Herron Park is currently served via a temporary tap off the Havre-Shelby 115 KV line.
“
Page 40 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
NORTHWEST POWER POOL AREA
Name of Project
New 161/115 kV Substation
between Richardson Coulee
and Malta Substations
Gen
MW
Transmission
kV
161/115
Date
No. of
pages
2016
.2
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Tables
Flow
Stability
Post Transient
Stability
One
Lines
Maps
Request Copy of
Report From
This project is on-hold status waiting for regulatory approval. Western currently owns,
operates and maintains the 180 mile Fort Peck-Richardson Coulee-Malta-HarlemHavre 161kV circuit, which is constructed for future 230kV conversion. A new
substation is anticipated to be installed approximately 18 miles East of Malta in the 49
mile section between the Richardson Coulee and Malta Substations. This new
substation will provide a 161kV ring bus constructed at 230kV specification, 161/115kV
transformation and a 115kV tap for a new 115kV line that will extend approximately 48
miles to serve an ultimate 21 MW of new oil development network load. VAR support
will include a 15 MVAR shunt capacitance at the new 161kV substation and a 15
MVAR shunt capacitance at the load. Due to regulatory delays, construction is not
anticipated to begin before fall of 2014. No interruption of customer service during
construction is anticipated.
“
Page 41 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Name of Project
Gen
MW
Dry Fork Station
390
Laramie River Station
345/230 kV Transformer
#2
Boone-Nyberg 115 kV
Upgrade Project
Transmission
kV
Date
No. of
pages
6/2011
38
345/230
8/2014
115
2015
Transfer
Capability
600 MVA
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
The Dry Fork Station is a 390 MW net coal fired station under construction and
scheduled to be in commercial operation in June of 2011. It is located at the
Dry Fork Substation.
Matthew Stoltz
701-557-5647
(BEPC)
This project consists of the addition of a second 345/230kV 600MVA
transformer at the Laramie River Station (LRS) switchyard in southeast
Wyoming. It will connect to the existing 345kV and 230kV buses within the LRS
switchyard. The in service date is August 2014. The transformer will be owned
by the Missouri Basin Power Project (MBPP). This transformer will primarily
function as an in service spare unit for the MBPP. No increase in system intact
path ratings is expected; therefore the WECC path rating process is not
necessary. Prior outage limits on the TOT3 path and LRS generation limits may
be increased as determined by future operating studies. Under some conditions
a LRS generation prior outage can contribute to TOT3 limits due to overload of
the existing transformer. Also prior outage of elements of the LRS 345kV
transmission system can cause LRS generation limitations due to overload of
the existing transformer. The second transformer will improve system capacity
in these situations.
Matthew Stoltz
701-557-5647
(BEPC)
This project is the proposed alternative to the cancelled second 230/115 kV 150
MVA transformer at the Boone 230 kV substation near Boone, CO. This project
is being coordinated with Public Service Company of Colorado (PSCo) and TriState Generation and Transmission (TSG&T) for increased reliability in the
Rocky Ford/La Junta area.
The project consists of a new double circuit 115 kV line between Boone 115 kV
and Nyberg 115 kV substations, utilizing existing right-of-way where possible
and replacing the Boone – DOT Tap – Nyberg 115 kV transmission line. New
115 kV line terminal positions are required at Nyberg and Boone 115 kV
substations to integrate the new circuit.
The Colorado Coordinated Planning Group (CCPG) is a Sub regional Planning
Group in the Rocky Mountain Region and allows open participation in its
planning meetings to stakeholders interested in this project. The requirements
of project coordination review for this project have been met through the CCPG.
The planned in-service date is 2015.
Wes Wingen
605-721-2268
(BHE)
Page 42 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Date
No. of
pages
Teckla-Osage 230 kV
Transmission Line
230
2015
.2
The Teckla-Osage 230 kV line will consist of approximately 60 miles of 1272
ACSR ‘Bittern’ conductor on H-frame poles. The line will be constructed to
provide needed Common Use System (CUS) transmission capacity,
accommodate projected load growth, and increase Wyodak area stability
margins. Reliability analysis for this project was initially performed as part of the
2008 BHBE LTP Study and the need reviewed in subsequent BHBE LTP
Studies.
The Colorado Coordinated Planning Group (CCPG) is a Sub regional Planning
Group in the Rocky Mountain Region and allows open participation in its
planning meetings to stakeholders interested in this project through the WY/SD
Common Use Subcommittee (WY/SD CUS). The requirements of project
coordination review for this project have been met through the CCPG.
http://www.westconnect.com/filestorage/WY_CUS_Update_2012-12-13.pdf
The planned in-service date is 2015.
Wes Wingen
605-721-2268
(BHP)
Osage-Lange 230 kV
Transmission Line
230
2015
.2
The Osage-Lange 230 kV line will consist of approximately 75 miles of 1272
ACSR ‘Bittern’ conductor on H-frame poles. The line will be constructed to
provide needed Common Use System (CUS) transmission capacity and
provide an additional path to the Rapid City load center. Reliability analysis for
this project was initially performed as part of the 2008 BHBE LTP Study and the
need reviewed in subsequent BHBE LTP Studies.
The Colorado Coordinated Planning Group (CCPG) is a Sub regional Planning
Group in the Rocky Mountain Region and allows open participation in its
planning meetings to stakeholders interested in this project through the WY/SD
Common Use Subcommittee (WY/SD CUS). The requirements of project
coordination review for this project have been met through the CCPG.
http://www.westconnect.com/filestorage/WY_CUS_Update_2012-12-13.pdf
The planned in-service date is 2015.
“
Bill Durfee (Sundance) 230
kV Substation
230
2015
.1
On July 10, 2012, Powder River Energy Corporation (PREC) submitted to Black
Hills Power a formal application for a new interconnection on the existing
Lookout-Hughes 230 kV line. The interconnection will consist of a 100 MVA
230/69 kV transformer and a three terminal 69 kV switching station. The
proposed location of the new interconnection is approximately 5 miles south of
Sundance, Wyoming. Basin Electric Power Cooperative (BEPC) is currently
performing a system impact study for this project. In addition, reliability analysis
for this project was included as part of the 2013 BHBE LTP Study. The planned
substation near Sundance, Wyoming was formerly named the Bill Durfee 230
kV substation at the end of 2013. The purpose of this project is to serve local
load and increase local reliability. It is not expected to have a significant impact
upon the operation of the Western Interconnection. The planned in-service date
is currently 2015.
“
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Page 43 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Date
No. of
pages
Undervoltage LoadShedding Scheme
115
2012
.3
A temporary UVLS program was implemented on 8/6/09 at nine 115 kV
substations to prevent a localized voltage collapse from occurring when loads
are high within a 115 kV load-serving area for a Category C contingency
causing loss of two of the four 115 kV lines providing service to the loads. The
program is designed to shed up to 75% of Longmont-Del Camino-Erie area
load (north of Denver, CO) in three 25% stages at 4, 12, and 20 second time
delays for bus voltages below 0.90 p.u. The UVLS program is in the process of
being removed from service due to the Fordham-Fort Saint Vrain 230kV Line
being completed in November 2011.
“
Second 230kV line from
Front Range Power Plant
to Existing Nixon-Kelker
(NX-KE) Line
230
12/2015
1
a) Second 230kV line from Front Range Power Plant to Existing Nixon-Kelker
(NX-KE) Line
b) Currently, there is only one transmission line from the CSU-owned Front
Range Power Plant that generates 460 MW at summer peak. The purpose of
this project is to provide a second line out of the plant to connect with an
existing CSU transmission line.
c) The termination point for the existing 230kV NX-KE line will be removed from
the Nixon 230kV bus and the line will be re-routed into the Front Range Power
Plant substation which it is only a few hundred feet from the existing line.
Rather than two identical NX-KE lines, CSU will now have one 230kV line from
Nixon to Kelker and one 230kV line from Front Range Power Plant to Kelker.
d) The expected date of release to operations is December 2015.
e) The expected operating voltage is 230kV.
f) The project is not expected to have a significant impact on the operation of
the WECC interconnected electric system because CSU is a small, relatively
self-contained system. Changing the termination point of this existing 230kV
line has very little impact on the CSU system and even less impact on the
WECC system. The project provides a reliability improvement for CSU under
certain Category C or D outages.
Susan Lovejoy
slovejoy@csu.org
(CSU)
Rifle – Parachute 230kV
Line #2
230
10/2015
.3
The Rifle – Parachute Project consists of constructing a second 18-mile 230kV
transmission circuit between Rifle and Parachute substations. The project is
needed to accommodate projected load growth in western Colorado. The load
growth consists primarily of natural gas developers that require transmission
service to electric motor driven gas compressors for natural gas gathering and
gas compression applications in Mesa and Garfield counties. The project has
an in-service date of October, 2015.
The project was granted a waiver of significant transmission project status in
2012.
Thomas W. Green
303-571-7223
(PSC)
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Page 44 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Date
No. of
pages
Pawnee – Daniels Park
345kV Transmission
Project
345
2019
.3
The Pawnee – Daniels Park 345 kV Transmission Project consists of
approximately 115 miles of 345 kV transmission between Pawnee Station and
the Daniels Park Substation south of Denver. The project will also result in a
new Smoky Hill – Daniels Park 345 kV line. The project is needed to
accommodate additional generation in northeast Colorado. The project has a
planned in-service date of 2019. The project was granted a waiver of significant
transmission project status in 2012.
“
Pawnee – Smoky Hill 345
kV Transmission Project
345
InService
.1
This project consists of approximately 96 miles of 345kV transmission between
the Pawnee and the Smoky Hill Substations. The project will improve local
system reliability and is pursuant to Colorado Senate Bill 07-100 (“SB100”) to
facilitate potential generation resources in northeast Colorado. The project was
completed in 2013.
“
San Luis Valley-CalumetComanche Transmission
Project
345
.2
The San Luis Valley – Calumet – Comanche Transmission Project is a joint
transmission plan between PSCo and Tri-State G&T. It consists of doublecircuit 230kV transmission from the San Luis Valley Substation in south-central
Colorado to a new Calumet Substation, near Walsenburg, Colorado, and then
double-circuit 345kV transmission from Calumet Substation to the Comanche
Station, near Pueblo, Colorado. A comprehensive progress report was included
with the PSCo 2010 Annual Progress Report. The timing of this project remains
uncertain as indicated by the PSCo 2012 Project Report.
“
?
.2
This project is expected to consist of new transmission originating in Weld
County, Colorado and connecting to the existing transmission system northeast
of the Denver-metro area. The project would increase local reliability to existing
customers and provide transmission capacity to serve anticipated load growth
in the region. The project would also accommodate additional generation
resources north of Denver. Since the project impacts the existing Tot 7 path
(Path 40), PSCo initiated the WECC Project Coordination process. Studies will
progress through 2014 and an in-service date is uncertain at this time.
“
Tot 7 Expansion Project
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Cogentrix of Alamosa
30
Q1/2012
.1
This project is a Solar PV generator connected to the Blanca Peak 115 kV
substation.
“
Limon 1
200
Q4/2012
.1
This project is wind generator connected to the Missile Site 345 kV substation.
“
Limon 2
200
Q4/2012
.1
This project is wind generator connected to the Missile Site 345 kV substation.
“
Cherokee 5. 6. 7
570
2016
.1
Interconnec
tion
Cherokee
115kV
MW
Type
ISD
570
Gas(CC)
2016
“
Page 45 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Name of Project
Gen
MW
Arapahoe 3 (retired)
-44
Zuni 2 (retired)
Cherokee 3 (retired)
Transmission
kV
-65
Date
No. of
pages
2014
.1
2015
-152
2016
Transfer
Capability
Phase
.1
.1
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Interconnec
tion
Arapahoe
MW
Type
ISD
-44
Coal
2014
Interconnec
tion
Zuni
MW
Type
ISD
-65
Coal
2015
Interconnec
tion
Cherokee
115kV
MW
Type
ISD
-152
Coal
2016
One
Lines
Request Copy of
Report From
“
“
“
Laporte 230 kV Substation
Expansion
230/115
5/2016
.1
Reconfigure an existing 230/115 kV substation with a 230 kV breaker-and-ahalf yard to connect four adjacent transmission lines (converting one from 115
to 230 kV) and two 230/115 autotransformers to be in-service May 2016. The
project will have no regional impacts. The purpose of the project is to improve
reliability in the Laporte, Colorado area which is in the northwest part of the
Foothills Area system. The attached document shows the scope of the project.
Jeremy Brownrigg
brownriggj@prpa.o
rg
(PRPA)
Boyd 230/115kV
Transformer Addition
Project
230/115
5/2017
.1
A second 230/115kV Transformer will be added to the substation along with
converting the 115kV ring bus configuration to breaker and a half and is
planned to be in-service May 2017. The project will have no regional impacts.
The purpose of the project is to improve system reliability in the Loveland,
Colorado area which is in the central part of the Foothills Area system.
“
Wayne Child Substation
Project (aka TOT3 Archer
Interconnection Project
previously known as the
300 MW Path 36 Upgrade)
345/230
Q4/2017
.3
300 MW
3
This Project will construct a new substation (Wayne Child substation) which will
sectionalize MBPP’s Laramie River Station (LRS) – Story 345 kV line near the
existing Archer substation, complete with 345/230 kV transformation, and
construct approximately 1/3-mile of 230 kV line between Archer and Wayne
Child substations. Line upgrades of the LRS – Ault and LRS – Wayne Child 345
kV lines will be necessary, as well as capacitors at Dalton substation near
Sidney. This project will also establish a 34.5 kV point of delivery for High West
Energy’s proposed 34.5-12.5 kV, 20 MVA substation contained within TriState’s proposed Wayne Child 345-230 kV substation. The project is planned to
be completed in the 4th quarter, 2017, and is in Phase III of the WECC Three
Phase Rating Process.
David Gustad
303-254-3449
(TSGT)
Page 46 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Transmission
kV
Date
No. of
pages
Transfer
Capability
Lamar-Front Range Project
345
?
1
2000 MW
Burlington-Lamar 345/230
kV Project (Request for
Waiver 2014)
345/230
?
Badwater – Casper 230 kV
Line
230
2018
1
Keota 345/115 kV Project
345/115
2015
.25
Boone – Walsenburg 230
kV Line (2013 Waiver
Granted)
230
2018
1
Name of Project
Gen
MW
650 MVA
645 MVA
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
This project includes two high voltage transmission paths, one from Lamar
substation to Pueblo area and a second from Lamar to substations near Brush
and/or Deer Trail. This will provide for better reliability to serve loads in the
entire eastern Colorado footprint. Multiple voltage options have been examined.
This project will be built in stages, with each designated stage being a part of
the overall plan to address the eastern Colorado transmission needs. This
project will also provide the infrastructure for Xcel Energy to meet Senate Bill
07-100 requirements by connecting several Energy Resource Zones in eastern
Colorado to the Denver Front Range area.
“
The purpose of Burlington-Lamar Transmission Project is to incrementally
alleviate existing and future transmission system constraints in southeast and
eastern Colorado as identified in the Lamar Front Range studies. It is a subset
of the greater Lamar Front Range project. To accommodate future build outs,
the Burlington-Lamar line may be constructed for 345 kV operation, but will
initially be operated at 230 kV.
“
This project involves constructing a new 230 kV transmission line from Casper
substation to Badwater (PACE) substation. The new 70 mile long line will allow
improved reliability and allow Tri-State to serve new load near central
Wyoming. The planned in-service date is expected to be in 2018.
“
This project involves sectionalizing the Laramie River Station (LRS)-Story 345
kV line for a load serving connection approximately 60-65 miles northwest of
Story. Tri-State would install a 225 MVA, 345/115 kV transformer at Keota
substation, with the possible future addition of a second transformer. The level
of load planned for this substation is initially 40 MW, with a potential increase to
120 MW based on the most recent load connection requests. The planned inservice date is 2015. This project is in Phase III of the WECC Three Phase
Rating Process.
“
The Boone-Walsenburg project will consist of one new 230 kV transmission
path from the existing Boone substation, owned by Tri-State and Xcel Energy,
to the existing Walsenburg substation, owned by Tri-State. The conductor will
be 1272 MCM ACSR-Bittern with a maximum design temperature of 100°C and
be owned by Tri-State. Addition of a new 230 kV line will increase reliability in
the Pueblo, Colorado area and also in Northeast New Mexico. Presently, the
loss of the Comanche-Walsenburg 230 kV line results in severe thermal
overloading on the 115 kV transmission system from West Station to
Walsenburg. In order to mitigate the overloading, a Remedial Action Scheme
(RAS) trips the Walsenburg-Gladstone 230 kV line which results in the loss of
load and reduced reliability in Northeast New Mexico. The planned in-service
date is 2018.
“
Page 47 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Date
No. of
pages
230
?
1
This project involves constructing a new 230 kV transmission line between the
existing WAPA Shiprock Substation in New Mexico and a new 230 kV Iron
Horse Substation in southwestern Colorado. A new 230 kV Kiffen Canyon
Substation will also be required along with a phase shifting transformer. It will
allow Tri-State to serve approximately 100 MW of new industrial load in SW
Colorado.
“
San Luis Valley-Carson
230 kV Line Project (aka
San Luis Valley-CalumetComanche
Transmission Project)
230/345
2022
1
This project consists of a new 230 kV transmission line from the existing San
Luis Valley substation to a new Carson 230/345 kV substation located west of
Taos NM. The Carson 230/345 kV substation will tap the existing Taos-Ojo 345
kV line and will include 230/345 kV transformation and a 230 KV phase shifting
transformer. The planned in-service date for this project is 2022.
“
Montrose-Nucla-Cahone
Transmission Upgrades
(aka Western Colorado
Transmission
Upgrade Project) (2013
Waiver Granted)
115/230
2019
1
This project upgrades the existing transmission lines and facilities from
Montrose substation to Cahone substation from 115 kV operation to 230 kV.
The purpose of this project is to improve system reliability by eliminating the
Nucla Remedial Action Scheme. The planned in-service date for this project is
2019.
Burlington-Wray 230 kV
Line Project
230
2016
1
The Burlington-Wray 230 kV Line Project is intended to increase reliability in
the project area, remove restrictions on the Burlington area network resources,
and increase the deliverability of Tri-State resources to Tri-State member loads.
This will be accomplished by adding a new 230 kV line from the Burlington
substation to the Wray substation. The addition of the 230 kV line will add one
new transmission line segment that will be constructed as a single circuit using
1272 MCM ACSR conductor with a maximum operating capacity of 1538 amps.
This additional capacity will alleviate congestion in the Burlington area, increase
reliability, and allow the potential development of renewable generation
resources in the Burlington and Wray areas which currently have existing wind
resources. The planned in-service date is 2016.
“
Big Sandy-Calhan 230 kV
Line Project (2012 Waiver
Granted)
230
2019
1
The primary purposes of the Big Sandy -Calhan 230 kV project are threefold:
mitigate the projected overloads of Tri-State’s 100 MVA 230-115 kV Fuller
transformer, should other mitigating actions not take place; increase Tri- State’s
ability to deliver resources to Mountain View Electric Association (MVEA) and
its other southeastern Colorado members; and provide a bulk transmission
connection (i.e., a "strong" voltage source and increased power transfer
capacity) to the eastern side of MVEA’s service area. This will be accomplished
by adding a 230 kV line from Big Sandy substation to a new Calhan substation.
This project is presently planned to be in-service 2019.
“
San Juan Basin Energy
Connect Project (2013
Waiver Granted)
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Page 48 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
1000-1500
MW
San Luis Valley-CalumetComanche Transmission
Project
230/345
After
2015
.4
Gladstone 230 kV Phase
Shifting Transformer
Project (2012 Waiver
Granted)
230
2018
1
J.M. Shafer-Henry Lake
230 kV Project (Request
for Waiver 2014)
230
?
.33
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
The project consists of two basic sections and is a joint project with Xcel
Energy. The first section consists of approximately ninety‐five (95) miles of
new, double‐circuit 230 kV transmission, built from the San Luis Valley
Substation to a new Calumet Substation, which would be located approximately
six (6) miles north of the existing Tri‐State Walsenburg Substation. The second
section consists of approximately forty‐five (45) miles of 19 new double‐circuit
345 kV transmission line from Calumet Substation to the existing Comanche
Station near Pueblo. The project will improve local system performance and
reliability, and will facilitate potential generation as part of Xcel Energy’s
response to Colorado Senate Bill 07-100 which calls for development of
transmission facilities to deliver power from renewable resource zones in
Colorado. The project was initially planned to be in service in 2015. However,
the project in service date has been delayed and will be determined after
Colorado PUC and other stake holder input. This project is not expected to
impose any significant impacts on the reliability of the WECC interconnected
system.
“
The project is to add a 300 MVA Phase Shifting Transformer (PST) at the
Gladstone existing substation. Studies by Tri-State and others have all shown
the need for transmission network upgrades in the North East New Mexico
(NENM) area to improve system reliability, load serving capability, mitigate
operating issues related to phase angle differences, and to reduce system
losses. The planned in-service date for this project is 2018.
“
Tri-State’s J.M. Shafer generating station has a total capacity of 272 MW and
has some capability to be upgraded in the future. The station presently relies on
the 230kV Fort Lupton Substation and its interconnected transmission system
owned by Xcel Energy to deliver power to Tri-State’s loads in the PSCo
Balancing Authority area. Since Tri-State has load in both the PSCo Balancing
Authority area and the WACM Balancing Authority area, Tri-State desires the
flexibility to directly deliver the output of the J.M. Shafer station to either
Balancing Authority. Tri-State can do so by interconnecting the J.M. Shafer
station directly to the Greenhouse Substation and constructing a Greenhouse
to Henry Lake 230 kV line. Tri-State forecasts an increasing need for additional
balancing resources in the WACM BA to comply with the State of Colorado’s
Renewal Portfolio Standards. The J.M. Shafer to Greenhouse to Henry Lake
230kV project will permit Tri-State to utilize the J.M. Shafer station as a
balancing resource in the WACM BA. The project will also improve
transmission reliability by providing a second transmission source directly to the
J.M. Shafer station and mitigates the problem of losing the entire station for a
single line outage.
“
Page 49 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2013
ROCKY MOUNTAIN POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
Miracle Mile Substation
Stage 03
230
Q2/2010
WAPA
Projects
.5
Installation of two 230/115 kV, 200 MVA power transformers, and associated
equipment. Installation of two 30 MVAR shunt reactors.
Lovell – Yellowtail 115-kV
rebuild
115
Q4/2014
1
Rebuild with 795 ACSS
Curecanti 230/115-kV 150
MVA transformer
replacement
230/115
Q4/2014
1
Replace Curecanti KZ1A 230/115-kV 75 MVA with a 150 MVA transformer
“
230
Q4/2014
1
Sectionalize Western’s Ault-Cheyenne 230-kV and Archer-North Park 230-kV
with a new substation known as Terry Ranch Road. Substation will be built in a
230-kV breaker and half configuration.
“
TransWest Express Project
600 kV
HVDC
Late
2017 or
Early
2018
2
3000
2
TransWest Express LLC (TransWest) is developing the TWE Project, a 3,000
MW, 600 kV, line commutated, bi-pole high voltage direct current (HVDC)
transmission project. TransWest and Western Area Power Administration
(Western) have entered into a joint development agreement under which
Western may become a 50% owner of the TWE Project.
The TWE Project is approximately 730 miles long and will be connected to the
AC transmission grid in south central Wyoming and in south eastern Nevada.
The primary intended use of the TWE Project is to deliver wind generated
electricity from Wyoming to markets in the desert southwest. The TWE Project
is planned to be in service in late 2017 or early 2018.
David Smith
(303) 299-1545
(TWE)
Wyoming Colorado Intertie
345
2014
2
TOT3
+900 MW
2
WCI is an approximately 180-mile, 345 kV transmission line between Laramie
River Station in southeastern Wyoming and Pawnee in northeastern Colorado.
WCI has a Planned Rating that will add 900 MW to the TOT3 (WECC Path 36)
path rating. The WCI project is owned by Wyoming Colorado Intertie, LLC, a
member of the LS Power Group of companies.
Bill Pascoe
(406) 494-2075
WCI Consultant
Terry Ranch Road
Substation
“
Linda Pope
970-461-7348
WAPA-RMR
Page 50 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
No. of
pages
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Transmission
kV
Date
Palo Verde – Delany 500
kV line
500
2016
1
Main components of the project will include a 14.86 mile 525 kV transmission
line composed of 525 kV lattice structures with a phase conductor of 3x1780
kcm ACSR Chukar. Shield conductors for the line will utilize one 7#8 AW
conductor (segmented) and one OPGW conductor (non‐segmented). A new
525 kV switching station will be constructed at the Delaney site and a new line
terminal will be added at the Palo Verde switching station. A 170 Mvar, 525 kV
reactor has been purchased and will be located on one of the buses at the
Delaney switchyard and operated through a 525 kV breaker.
In 2011, APS completed a study (Preliminary Transmission Interconnection
Impact Study: Q11 Palo Verde‐Delany‐Sun Valley and Q12 Hassayampa‐
North Gila #2 500 kV Lines) and the results were approved by the Western
Arizona Transmission System task force. Results of the study reveal the project
will not adversely impact existing facilities while providing access to new
renewable generation facilities west of Phoenix, Arizona. In addition, the project
has also been included in several Ten Year Plan submittals by APS to the
Arizona Corporation Commission as well as a number of sub‐regional studies
with no adverse effects.
Results from studies mentioned in section B have found no adverse effects to
the WECC or local transmission systems due to the addition of this project.
Additionally, the project is anticipated to be part of the Palo Verde East
transmission path.
Barrie Kokanos
602-250-1370
(APS)
Delany – Sun Valley 500
kV line
500
2016
1
Main components of the project will include a 28.30 mile 525 kV transmission
line composed of both 525 kV lattice and monopole structures with a phase
conductor of 3x1780 kcm ACSR Chukar. Shield conductors for the line will
utilize one 7#8 AW conductor (segmented) and one OPGW conductor (non‐
segmented). A new 525 kV switching station will be built at the Sun Valley site
and a new 525 kV terminal will be added at the Delaney switching station.
“
Name of Project
Gen
MW
Phase
One
Lines
Maps
Request Copy of
Report From
In 2011, APS completed a study (Preliminary Transmission Interconnection
Impact Study: Q11 Palo Verde‐Delany‐Sun Valley and Q12 Hassayampa‐
North Gila #2 500 kV Lines) and the results approved by the Western Arizona
Transmission System task force. Results of the study reveal the project will not
adversely impact existing facilities while providing access to new renewable
generation facilities west of Phoenix, Arizona. In addition, the project has also
been included in several Ten Year Plan submittals by APS to the Arizona
Corporation Commission as well as a number of sub‐regional studies with no
adverse effects.
Results from studies mentioned in section B have found no adverse effects to
the WECC or local transmission systems due to the addition of this project.
Additionally, the project is anticipated to be part of the Palo Verde East
transmission path.
Hassyayampa – N. Gila
500 kV #2 (HANG 2
500
2015
2
The project has a CEC permit, has a planned in‐service date of summer 2015
and is currently under construction.
″
Page 51 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Project)
Palm Valle-Trilby Wash
230 kV Project
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
To increase transfer capacity on Path 49, increase import capability in the
Yuma load pocket and increase access to renewable generation near the Palo
Verde/Hassayampa hub.
Main components of the project will include a 111.41 mile 525 kV transmission
line composed of 525 kV lattice structures with a phase conductor of 2x2156
kcm ACSR Bluebird. Shield conductors for the line will utilize two OPGW
conductors (segmented). Two 170 Mvar, 525 kV line reactors, one located at
each terminal, are included in the project and will be operated through a 525 kV
breaker. A single‐segment, 33.7 Ω series capacitor will be located at the N.Gila
switchyard. Rating for the MOV protected capacitor will be 2200 Amps
continuous with a 135% 30 minute emergency rating.
In 2011, APS completed a study (Preliminary Transmission Interconnection
Impact Study: Q11 Palo Verde‐Delany‐Sun Valley and Q12 Hassayampa‐
North Gila #2 500 kV Lines) and the results were approved by the Western
Arizona Transmission System task force. Results of the study reveal the project
will not adversely impact existing facilities along the Arizona‐California border.
Also, the project has been included in several Ten Year Plan submittals by APS
to the Arizona Corporation Commission as well as a number of sub‐regional
studies with no adverse effects. In September 2011, the project participants
completed the WECC Project Coordination Review Group Report for the
Hassayampa‐North Gila #2 (HANG2) Project as a partial requirement for
completing the WECC Project Coordination Process for the project.
Subsequently, the project participants completed the Hassayampa‐
N.Gila #2 Project (Path49) WECC Comprehensive Progress Report as a partial
requirement for advancing from phase 1 to phase 2A in the WECC Path Rating
Process.
Based on the efforts completed to date, study results have revealed no adverse
effects to the WECC or local transmission systems due to the addition of the
HANG2 project. Additional studies including the phase 2 WECC Path Rating
Process study are currently assessing this project. Finally, the project is
anticipated to be part of the East of the Colorado River transmission path
(WECC Path 49).
230
2015
1
The project has a CEC permit and has a planned in‐service date of summer
2015.
Main components of the project will include a 15.91 mile 230 kV transmission
line composed of 230 kV double circuit monopole structures with a phase
conductor of 1x2156 kcm ACSS with the second circuit strung at a later date.
Shield conductors for the line will utilize one 3/8“ HS conductor (non‐
segmented) and one OPGW conductor (non‐segmented). A new 230 kV line
terminal will be added at the Palm Valley substation. In addition, the project will
also include construction of a new 230/69 kV substation in the Sun City area.
Sub‐regional studies are underway to assess the impacts of the project through
the Western Arizona Transmission System task force. However, the project has
″
Page 52 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
been studied in various sub‐regional study efforts and has been included in
several Ten Year Plan submittals by APS to the Arizona Corporation
Commission with no adverse effects.
To date, study results have revealed no adverse effects to the WECC or local
transmission systems due to the addition of this project.
Sun Valley‐Trilby Wash
230 kV Project (2016)
230
2016
1
The project has a CEC permit and has a planned in‐service date of summer
2016.
Main components of the project will include a 14.13 mile 230 kV transmission
line composed of 230 kV double circuit monopole structures with a phase
conductor of 1x2156 kcm ACSS with the second circuit strung at a later date.
Shield conductors for the line will utilize one 3/8“ HS conductor (non‐
segmented) and one OPGW conductor (non‐segmented). A new 230 kV
switching station will be built at Sun Valley and a new 230 kV terminal will be
added at the Trilby Wash substation. In addition, the project will also include a
new 600 MVA, 525/230 kV transformer at the Sun Valley switchyard.
Sub‐regional studies are underway to assess the impacts of the project through
the Western Arizona Transmission System task force. However, the project has
been studied in various sub‐regional study efforts and has been included in
several Ten Year Plan submittals by APS to the Arizona Corporation
Commission with no adverse effects.
To date, study results have revealed no adverse effects to the WECC or
local transmission systems due to the addition of this project.
“
Sun Valley – Morgan (TS9)
500 kV line
500
2018
1
The project has a CEC permit and has a planned in‐service date of summer
2018. Commercial operation date for the 230 kV portion of the project is
approximately 2024.
“
Proposed renewable generation facilities are expected to interconnect to the
Delaney 500 kV switchyard and will deliver resources to the Phoenix area
through the Sun Valley‐Morgan 500 kV Project.
Main components of the project will include a 38.07 mile 525 kV transmission
line composed of 525/230 kV double circuit monopole structures with a phase
conductor of 3x1780 kcm ACSR Chukar. Phase conductor for the 230 kV line
will be 1x2156 kcm ACSS and will be strung at a later date. Shield conductors
for the line will utilize one 7#8 AW conductor (segmented) and one OPGW
conductor (nonsegmented). A new 525 kV terminal will be added at both Sun
Valley and Morgan switching stations.
Sub‐regional studies are underway to assess the impacts of the project through
the Western Arizona Transmission System task force. However, the project has
been studied in various sub‐regional study efforts and has been included in
several Ten Year Plan submittals by APS to the Arizona Corporation
Commission with no adverse effects.
Page 53 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
To date, study results have revealed no adverse effects to the WECC or local
transmission systems due to the addition of this project. Additionally, the project
is anticipated to be part of the Palo Verde East transmission path.
Four Corners units 1‐3
retirement (2013)
560
MW
Retired
1
Three coal fired steam units removed from service connected to the Four
Corners 230 kV switching station through individual GSU transformers.
Operating and planning studies have shown no effect on adjacent transmission
paths with the absence of the generation. APS has investigated adding shunt
reactors at the site to control high voltages when one or both of Units 4 and 5
are off‐line under light load scenarios.
Study results show no effect on adjacent systems.
All three units were retired on 12/30/13.
Net change of capacity of 560 MW.
“
Saguaro units 1‐2
retirement (2013)
210
MW
Retired
1
Both units were retired on 6/30/13.
Net change of capacity of 210 MW.
Two gas fired steam units removed from service connected to the Saguaro 115
kV buses through individual GSU transformers.
Operating studies have shown no effect on adjacent transmission paths with
the absence of the generation.
Study results show no effect on adjacent systems.
“
2017
1
Main components of the project will include a fold‐in of the Cholla‐ Pinnacle
Peak 345 kV line into a new 345 kV switching station as well as the addition of
a 150 MVA, 345/69 kV transformer and a new 69 kV switching station.
“
Mazatzal 345/69 kV
Substation (2017)
345/69 kV
The project has been modeled in various sub‐regional studies as well as
several Ten Year Plan submittals by APS to the Arizona Corporation
Commission.
Results from studies mentioned in section B have found no adverse effects to
the WECC or local transmission systems due to the addition of this project.
N.Gila‐Orchard (previously
called TS8) 230 kV Project
(2018)
230 kV
2018
1
The project has a CEC permit and has a planned in‐service date of summer
2018.
“
Main components of the project will include a 12.50 mile 230 kV transmission
line composed of 230 kV double circuit monopole structures with a phase
conductor of 1x2156 kcm ACSS with the second circuit strung at a later date.
Shield conductors for the line will utilize one 3/8“ HS conductor (non‐
segmented) and one OPGW conductor (non‐segmented). A new 230 kV
switching station will be added at the N.Gila site. In addition, the project will
also include a new 600 MVA, 525/230 kV transformer at the N.Gila switch yard
and the construction of a new 230/69 kV substation in the south Yuma area.
This project was included in the WECC Comprehensive Progress Report
Page 54 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
Hassayampa‐N.Gila #2 Project (Path49) associated with the HANG2 project
WECC Path Rating Process studies. However, the project has been studied in
various sub‐regional study efforts and has been included in several Ten Year
Plan submittals by APS to the Arizona Corporation Commission with no
adverse effects.
To date, study results have revealed no adverse effects to the WECC or local
transmission systems due to the addition of this project. Additional studies
including the phase 2 WECC Path Rating Process study and other operating
studies are currently assessing this project.
Scatter Wash 230/69 kV
Substation (2021)
230/69
2021
1
Main components of the project will include a fold‐in of the Raceway‐ Pinnacle
Peak 230 kV line into a new 230 kV substation as well as the addition of a 188
MVA, 230/69 kV transformer and a new 69 kV switching station.
“
This project has been studied in various sub‐regional study efforts and has
been included in several Ten Year Plan submittals by APS to the Arizona
Corporation Commission with no adverse effects.
To date, study results have revealed no adverse effects to the WECC or local
transmission systems due to the addition of this project.
Sun Valley‐Morgan 230 kV
Project (2024)
230
2024
1
The project has a CEC permit and has a planned in‐service date of summer
2024.
“
Main components of the project will include a 38.07 mile 230 kV transmission
line composed of 230 kV circuit on double circuit monopole structures with the
Morgan‐Sun Valley 500 kV transmission line (mentioned previously) with a
phase conductor of 1x2156 kcm ACSS. Shield conductors will already be in‐
place due to the pre‐existing line. New 230 kV terminals will be added at both
Sun Valley and Morgan switching stations.
Sub‐regional studies are underway to assess the impacts of the project through
the Western Arizona Transmission System task force. However, the project has
been studied in various sub‐regional study efforts and has been included in
several Ten Year Plan submittals by APS to the Arizona Corporation
Commission with no adverse effects.
To date, study results have revealed have found no adverse effects to the
WECC or local transmission systems due to the addition of this project.
Navajo Transmission
Project Segment 1
500
2016
1
1600
2
This project is the construction of a new 500 kV transmission line starting at the
Four Corners 500 kV switching station and terminating at a switchyard south of
the Navajo 500 kV switching station. As a result of this project, the nomogram
for Path 22 will be eliminated and the two components of the path will be
separated into Path 22A (Four Corners-Moenkopi and DREP-RME 500 kV) and
Tom Johns
Sithe Global
509-926-3485
Page 55 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
Path 22B (Four Corners-Cholla #1 & #2 345 kV). Path 22A will have a nonsimultaneous rating of 3190 MW and Path 22B will have a non-simultaneous
rating of 1370 MW. Path 23 (Four Corners 500/345 kV) will have a rating of
1040 MW.
Great Basin Transmission
SWIP-South Project
500
2014
1
+/- 2000
MW
2
2
Great Basin Transmission’s SWIP-South Project represents further
development of the ONLine Project. Install 70% series compensation on
Robinson Summit-Harry Allen 500 kV line, 35% at each end. Install two 600
MVA 345/345 kV Phase Shifting Transformers (+/- 48 degrees each) at
Robinson Summit: one connected towards Falcon and the other connected
towards Gonder. Construct an extending 500 kV circuit from NV Energy’s
Harry Allen substation to SCE’s Eldorado substation (~60 miles), with 70%
series compensation at Harry Allen. Plan of service also includes a +150
MVAR shunt capacitor at the Robinson Summit 345 kV bus, and a +400 MVAR
SVD (4x100 MVAR steps) at the Robinson Summit 500 kV bus.
Evan Estes
LS Power
Development, LLC
636-532-2200
Great Basin Transmission
SWIP-North Project
500
2014
1
+/- 2000
MW
2
2
Great Basin Transmission’s SWIP-North Project consists of a new 500 kV line
from Idaho Power’s Midpoint substation to a new proposed Robinson Summit
substation near Ely, Nevada (~275 miles). Install 70% series compensation
(for 245 mile line impedance) as follows: 35% at Thousand Springs (located
!125 miles south of Midpoint) and 35% at Robinson Summit.
“
Bordertown to Cal Sub 120
kV Project
345/120
2017
0
0
0
0
0
This project comprises a 345/120 kV 280 MVA transformer at Bordertown
Substation and a 120 kV 11-mile line from Bordertown to California Substation.
This project is expected to be in service in 2017.
Alex Fratkin
NV Energy North
775-834-4897
345
4/2014
Falcon Second 345/120 kV
Transformer
345/120
2015
“One Nevada”
Transmission Line Project
(ON Line).
500/345
In-Service
345 kV Voltage Support
Project
1
270 MVA
This project was approved in Sierra 2007 Integrated Resource Plan. The
project includes the construction of a 75 MVA 345 kV capacitor bank at North
Valley Road substation and a 75 MVA 345 kV capacitor bank at Mira Loma
substation for operational support of the voltage in the 345 kV transmission
grid. The Mira Loma bank is already in service; the Valley Road bank is
planned to enter service in March/April, 2014.
“
This project is driven by the expected increase of the NVE North load. The
project includes an addition of a second Falcon 345/120 kV 280 MVA
transformer bank at the existing Falcon 345 kV / 120 kV substation. This project
is scheduled to be in service in 2015.
The project includes the following facilities:
• 500-kV 231 mile 3-1590 ACSR line from Robinson Summit to Harry Allen,
• New 345/500 kV Robinson Summit Substation (located 20 miles west of Ely,
Nevada) with its 345 kV and 500 kV switchyards connected through 2×525
MVA 345/500 kV autotransformers,
“
Page 56 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
• Fold of the existing Falcon – Gonder 345 kV line into Robinson Summit
Substation and approximately 70% series compensation equipment on Falcon
– Robinson 345 kV line, 35 % at each end.
• A new 500 kV line terminal at the existing Harry Allen Substation (located
northeast of Las Vegas, Nevada).
NV Energy and GBT-South have completed this project, which entered service
on 12/31/2013.
Harry Allen 500/230
Transformer Addition
500/230
6/2016
NV Energy plans to request Public Utility Commission of Nevada authorization
to construct a new 500/230 kV 1500 MVA transformer at Harry Allen substation.
The transformer would be installed at the 500 kV switchyard and connected to
the 230 kV yard through a short 230 kV line. The transformer will be designed
to impedance of 8% (in order to balance the system flow ability and the fault
duty at 230 kV bus). This project is scheduled to be in service in June, 2016,
depending on permitting timelines.
Alex Fratkin
NV Energy South
775-834-4897
Crystal 500 kV Line
Interconnection
500
11/2014
NV Energy will construct a new 500 kV bay with two new breakers in the South
Crystal 500 kV Substation. This South Crystal 500 kV Substation work will
terminate a new LADWP 500 kV line (with conductor 2-1590 ACSR per phase)
interconnecting a new solar PV plant. This project is scheduled to be in service
in November 1, 2014.
“
McDonald 230/138 kV
Additions
230/138
6/1/2016
.1
NV Energy plans to add a new 336 MVA 230/138 kV transformer at the existing
McDonald substation. The existing Arden – Decatur 230 kV line will be folded
into the new McDonald substation.
″
Brooks 230/138/12 kV
Substation and Pecos –
Brooks 230 kV Line
230/138
2017
.1
The addition of a new 230 kV transmission line between Pecos and the future
Brooks substation site along with folding in the 138 kV sub-transmission
between Leavitt and Gilmore substations into the Brooks substation will
eliminate N-1 low voltage issues. .
“
Sunrise 500/230 kV
Transmission Substation
500/230
2018
.2
To increase import capability into the NEVP system, the Sunrise Project will
include a new 500/230 kV Sunrise substation connected through an 8-mile fold
to the Harry Allen-Mead 500 kV transmission line, with one 1500 MVA 500/230
kV transformer. The Sunrise 230 kV facilities will be integrated with existing 230
kV Nevada Power Company facilities through four new 230 kV lines. In service
in 2018. The 500 kV portion of the project has been canceled and replaced with
the Harry Allen 500/230 kV transformer addition. The 230 kV additions are
delayed to 2018 or beyond based on current load forecasts.
“
Robinson – Harry Allen
Transmission Line #2
Project
500
2018
.2
Construct a 500-kV, 235 mile line #2 from the Robinson Summit Substation in
Northern Nevada to the existing Harry Allen Substation in Las Vegas area.
This line will parallel the “SWIP South” line route, on a separate ROW, with
approximately 1000 ft separation between the two lines. The line will be 70%
series compensated, 35% at each end. The line will serve as a conduit for new
renewable generating resources between Northern and Southern Nevada,
“
Page 57 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
including those currently being developed along and in the proximity to the
SWIP corridor. NVE has recently obtained from the BLM a permit for this line
and is finalizing the substation portions of the permit. Similarly to “SWIP”
Project, the SSR studies to identify possible adverse effects on the near-by
generators will be performed. NV Energy is the proponent and the prospective
owner of this project.
Northwest 500/230 #2
Transformer Addition
500/230
6/1/2018
.1
Install three 500/230 kV, single phase autotransformers with a rating of
300/400/500 MVA at the existing Northwest substation.
″
Sunrise 500/230 kV #2
Transformer Addition
500/230
6/1/2020
.1
This is a second 500/230 transformer addition at Sunrise, which will fold in the
existing Harry Allen – Mead 500 kV #1 line.
“
Expansion of the Rio
Puerco 345 kV Station
345
2015
.3
The project consists of expanding the Rio Puerco Substation by looping in the
existing San Juan-BA 345 kV and Four Corners-West Mesa 345 kV lines .The
project eliminates contingency overloads of existing 115 kV lines in the northern
portion of PNM’s Albuquerque 115 kV subtransmission network under high
renewable generation conditions.
Tom Duane
(PNM)
505-241-4569
The initial expansion of the Rio Puerco station, which added a new 345/115 kV
transformer to the local Albuquerque area network, was completed in May
2011. The looping in of the existing San Juan-BA 345 kV and Four CornersWest Mesa 345 kV lines is currently scheduled to be completed in 2015.
Pinal West – Pinal CentralAbel – Browning 500 &
230kV line Estimated date
of operation: 2014-2020
500/230 kV
2014
.5
1500 MW
Point of Origin Pinal West Substation
Intermediate point Duke Substation
Intermediate point Pinal Central Substation
Intermediate point Randolph Switchyard
Intermediate point Abel Substation
Intermediate point Dinosaur Substation
Point of Termination Browning Substation
Length Approximately 100 Miles
The proposed line is part of former Southeast Valley Project (SEV). The first
segments of the projects
were finalized in:
2007 – Dinosaur Substation
2007 – Dinosaur – Browning 230kV
2010 – Randolph – Browning 500kV energized at 230kV
2010 – Randolph – Abel – Dinosaur 230kV
2011 – Abel 230kV Substation
The Pinal West – Duke-Pinal Central-Abel – Browning 500kV line will close the
SEV loop in 2014. As a
part of the project following facilities will be built:
2014 – Pinal Central – Randolph 230kV
2014 – Pinal Central – Browning 500kV (the voltage and configuration change
of the 2010 Randolph-
Eldin Dizdarevic
(602) 236-0960
(SRP)
Page 58 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
Browning 230kV section)
2014 – Pinal West – Pinal Central 500kV and 230kV
2014 – Pinal Central 500kV and 230kV Substation
2014 – Duke 500kV Substation
The Central Arizona Transmission System Study identified a number of system
additions necessary to accommodate load growth and access to energy
sources in the central Arizona area. This transmission line is the second
segment of a series of transmission lines to serve the central Arizona region.
This segment will initially provide an interconnection with the Palo Verde market
area to market power to the Phoenix and central Arizona areas, and to
accommodate the growth in development and population in Pinal County.
Desert Basin-Pinal Central
230 kV Line
230
2014
.2
Point of Origin: Desert Basin Power Plant 230kV Switchyard
Intermediate point: None
Point of Termination: Pinal Central 230kV Substation
Length Approximately: 21 miles
The purpose of the project is to remove the Remedial Action Scheme installed
on Desert Basin Generating Station, improve reliability of the 230kV system in
the region by reducing the loading on existing lines in the area, increase local
area system capacity, reduce reliance on second party transmission system
and to establish the Pinal Central Substation which was identified as one of the
future injection points of power and energy into the central Pinal County load
area.
“
Eastern Mining Area
Expansion Project
230/115
2016
.5
The purpose of the project is to increase capacity to accommodate growing
mining customer load. Several options are under consideration; however, the
likely routing for the new transmission would be to follow the APS Cholla Saguaro 500kV line until it crosses SRP’s 115kV line. From there, the 230kV
line would likely follow SRP’s existing Ray - Knoll - Morris 115kV line.
“
Price Road Corridor
Project
230
2016
.5
Point of Origin: Kyrene 230kV Substation
Intermediate point: Knox, RS27 and RS28 Substations
Point of Termination: Schrader 230kV Substation
Length Approximately: 12-23 miles
The purpose of the project is to serve growing industrial and commercial
customer loads along the Price Road Corridor, adjacent to Price Road in south
Tempe and Chandler. The project will consist of a new single-circuit 230kV line
from the Schrader Substation in southwest Chandler to a new RS28
Substation, located to the west in the southern portion of the Price Road
Corridor in Chandler; a new double-circuit 230kV line from the Knox Substation,
located just south of the I-10 and Loop 202 freeway interchange in the
westernmost tip of Chandler, to a new RS27 Substation to be located in the
northern portion of the Price Road Corridor, south of the Loop 202 freeway, in
Chandler; a new double-circuit 230kV line to connect the two new substations;
and a single-circuit 230kV line between the Knox Substation in Chandler and
the Kyrene Substation, located at the intersection of Elliott and Kyrene Roads in
“
Page 59 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
south Tempe. This project will be built in phases with the first phase being
energized in 2016.
Rogers – Santan 230kV
line
230
2016
.25
Point of Origin: Rogers230kV Substation
Intermediate point: None
Point of Termination: Santan 230kV Substation
Length: Approximately 9 miles
The purpose of the project is to provide adequate transmission facilities to
deliver reliable power and energy to SRP’s customers in the eastern Phoenix
Metro valley area by upgrading existing conductors and circuits. The route is
generally east and south from Rogers to the Santan Substation, using existing
circuit positions on existing structures, where possible.
“
Silver King – RS-29 230kV
Project
230
2018
.25
Point of Origin: Silver King 230kV Substation
Intermediate point: None
Point of Termination: New RS-29 230kV Substation
Length: Approximately 12-14 miles
The purpose of the project is to increase to accommodate growing customer
load. Several routing options are under consideration with the most likely
routing that follows APS Cholla-Saguaro 500kV line.
“
New Superior – New Oak
Flat 230kV line
230
2021
.25
Point of Origin: A New 230kV Substation near the existing Goldfield –
Silver230kV line, tentatively named “New Superior”
Intermediate point: None
Point of Termination: New 230kV Substation near Oak Flat
Length: Approximately 3.5 miles
The purpose of the project is to serve growing customer loads at Oak Flat. The
location of the New Superior and the New Oak Flat sites are still being
determined. The preliminary 230kV alignment will be identified after these
details are received.
“
New Oak Flat – Silver King
230kV line
230
2021
.25
Point of Origin: A New 230kV Substation near the existing Oak Flat 115kV
Station, tentatively named “New Oak Flat”
Intermediate point: None
Point of Termination: Silver King 230kV Substation
Length: Approximately 3 miles
The purpose of the project is to serve growing customer loads at Oak Flat. The
alignment will closely follow the existing 115kV circuit connecting Silver King to
Oak Flat.
“
Abel – Pfister - Ball 230kV
line
230
2021
.25
Point of Origin: Future Ball (RS17) 230kV Substation
Intermediate point: Future Pfister (RS24) 230kV Substation
Point of Termination: Abel 230kV Substation
Length: Approximately 20 miles
Estimated in-service dates are:
2021- Abel – Pfister – Santan 230kV line
“
Page 60 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
2021- Abel – Pfister- Schrader 230kV line
2021- Pfister Substation
The purpose of the project is to meet expected load growth in the eastern
service territory. The route of the line is generally south and east from a point
on the Santan to Schrader 230kV line near
the future Ball (RS17) Substation to the Pfister (RS24) Substation in the
southeastern portion of the town of Queen Creek, continuing south and east to
the future Abel Substation.
Silver King – New Pinto
Valley 230kV line
230
2021
.25
The purpose of the project is to serve growing customer loads at Pinto Valley.
The anticipated route for this project parallels the existing Coronado - Silver
King 500kV line out of Silver King to the north until it turns east to terminate at a
Substation proposed in the vicinity of the existing 115kV Pinto Valley Station.
“
Schrader-Abel 230 kV Line
230
2019
.1
This 230 kV transmission project is projected to be in service by 2019.
“
Kyrene 500/230 kV
Transformer
500/230
5/2012
.1
A third Kyrene 500/230kV transformer will be constructed and energized by
May 2012. APS is participating with SRP on the transformer.
“
Rudd 230/69 kV
Transformer
230/69
4/2018
.1
The first Rudd 230/69kV transformer will be constructed and energized by April
2018.
“
Schrader 230/69 kV
Transformer
230/69
4/2014
.1
A second Schrader 230/69 kV transformer will be constructed and energized by
April 2014.
“
230
2018
.1
This project is driven by customer load growth, approximate mileage is 14. This
230kV transmission project is scheduled to be in service by 2018.
“
5/20165/2020
.1
Nine 91MW generating units are scheduled to be installed at Abel 230kV
station. The first unit is scheduled to be in service by 5/2016, the second unit
by 5/2018, the third and fourth units by 5/2019 and the rest of the units by
5/2020.
“
500
2011-2016
.2
SRP and APS jointly plan to construct the following transmission facilities:
Palo Verde-Delany (Harquahala Junction) 500 kV Line (in-service date
2014)
Delany (Harquahala Junction)-Sun Valley (TS5) 500 kV Line (in-service date
remains 2015.
Morgan(TS9)-Pinnacle Peak 500 kV Line (in-service date 2011).
Palo Verde-North Gila 500 kV Line (in-service date remains 2014).
Sun Valley (TS5)-Morgan (TS9) 500 kV Line (in-service date 2016).
“
115/230/345
20142020+
.6

“
Resolution Copper 230kV
Line
Abel 230kV Generation
Other Joint SRP/APS
Projects
Other SRP 115/230/345 kV
Transmission Projects
819

RS26, formerly Fountain Hills Station-115 kV, 230 kV or 345 kV from
Stewart Mountain, Goldfield or APS’ Cholla-Pinnacle Peak 345 kV Line (inservice date moved beyond SRP’s 10 year plan)
Ball Loop-In (in-service date moved beyond SRP’s 10-year plan)
Page 61 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
At this time, the in-service date for each of the following projects is not yet
determined and is subject to further additional study work.
 Browning-Thunderstone 230 kV Line
 Browning-Corbell 230 kV Line
 Silver King-Browning 230 kV Line
 Silver King-Browning 230 kV/Superior Tie
 Santa Rosa-CATSHV03 230 kV Line
 Pinnacle Peak-Brandow 230 kV Line with a possible loop into Rogers or
Thunderstone
 Silver King-Knoll-Hayden 230 kV Line
 Point on the Kearny-Hayden 115 kV Line to Hayden double circuit loop
 Pinal Central-Abel-RS20 500kV line
Southline Transmission
Project
SunZia Southwest
Transmission Project
345/230
2016
2
500
2018
9
3000 MW
2
Southline Transmission, L.L.C. proposes to construct the Southline
Transmission Project, a high--‐voltage electric transmission line and associated
facilities in southern New Mexico and southern Arizona. The proposed project
would include a New Build Section (New Build) and an Upgrade Section
(Upgrade).
1. New Build --‐--‐ The first section is a proposed double--‐circuit 345--‐kV
line originating at the Afton Switching Station outside Las Cruces, New Mexico,
and terminating at Apache Switching Station in Southeastern Arizona;
2. Upgrade --‐--‐ The second section is a proposed upgrade of the Western
Area Power Administration's existing 115--‐ kV Apache to Saguaro
transmission line, to a 230--‐kV double--‐circuit line from Apache to Saguaro
and Tortolita. Depending upon the final design, Southline is seeking the
following ratings:
1. Afton East--‐to--‐West (E2W) --‐ Rating of 1,030 MW;
2. Apache East--‐to--‐West (E2W) --‐ Rating of 1,000 MW;
3. Saguaro/Tortolita West--‐to--‐East (W2E) --‐ Rating of 418 MW and a
Saguaro/Tortolita West--‐to--‐East (W2E) Rating of approximately 1,000 MW
with the Tucson to Oracle 115--‐kV line re--‐conductor project in service);
4. Apache West--‐to--‐East (W2E) --‐ Rating of 957 MW and an Apache West‐to--‐East (W2E) Rating of approximately 1,000 MW with the Tucson to Oracle
115--‐kV line re--‐conductor project in service.
Doug
Patterson
(Southline
Transmission
Project)
(415) 787-4209
3
3
3
The original SunZia Southwest Transmission Project was envisioned to be
comprised of three segments of two 500 kV (AC) lines each from the renewable
resource energy zone(s) in central New Mexico (referred to in this report as
SunZia East) to the proposed Pinal Central 500 kV substation (to be operated
by Salt River Project) in central Arizona. SunZia examined two intermediate
electrical interconnections: one at a new SunZia South 500 kV substation near
the existing Luna 345 kV substation in southwestern New Mexico (to be
operated by El Paso Electric Company (EPE)), and another at the proposed
Jim Hsu
Power Engineers,
Inc.
(Southwestern
Power Group)
(480) 838-1427
Page 62 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Centennial West Clean
Line HVDC Project
600
Q1/2018
7
North Gila-Imperial Valley
#2 500 kV Project
500
Q3/2018
8
Pinal Central – Tortolita
500 kV Line
500
2016
Hassayampa – Pinal West
500-kV Line Loop-In:
500
Willow 345 kV Switchyard
345
Transfer
Capability
3500
Phase
1
1
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Willow 500 kV Substation (to be operated by Tucson Electric Power (TEP)) in
southeastern Arizona. Taken together with these two intermediate substations,
the three project segments are created: (1) SunZia East to SunZia South; (2)
SunZia South to Willow 500 kV; and, (3) Willow 500 kV to Pinal Central.
The modified POS will be changed slightly to exclude a 500/345kV transformer
at Luna and include only one intermediate electrical interconnection at the
Willow 500 kV Substation. The 3 SunZia South Substation will initially only
include a series capacitor bank (70% series compensation).
Additional information that is periodically updated is available at the SunZia
Project Website: www.sunzia.net.
1
1
The project consists of a 900 mile 3,500 MW HVDC transmission line between
northeastern New Mexico, north-central Arizona, and southern California.
Request Copy of
Report From
Jim Hsu
Power Engineers,
Inc. for
Centennial West
Clean Line LLC.
(480) 838-1427
2
The 85 mile NG-IV #2 500kV project is a major intertie expansion between the
North Gila area (southwest Arizona) and the Imperial Valley area (southern
California); this line would parallel the existing North Gila-Imperial Valley line
(also known as the Southwest Power Link, or SWPL), with an expected
separation of 250 feet from the existing SWPL. The potential for a second
circuit would be proposed to be constructed on the same set of structures, and
would potentially loop in and out of the existing Highline 230 kV substation
along the Highline Canal. The second circuit could be operated at 230kV
initially until the operational and scheduling need develops over the years to
potentially operate at 500kV. An additional alternative that we have been asked
to review by the PCRG is to have a single 500kV line and with the loop-in to the
existing Highline 230kV station. Review is currently underway of this
configuration.
Jim Hsu
Power Engineers,
Inc. for
Southwest
Transmission
Partners
(480) 838-1427
.3
TEP plans to construct a 500-kV line from the proposed Pinal Central
Substation to TEP’s Tortolita Substation. The expected in-service date for this
project is 2016. TEP conducted an open season to solicit interest in this project.
The Arizona Corporation Commission (ACC) granted a Certificate of
Environmental Compatibility (CEC) in July 2012.
EvaMarie King
(TEP)
(520) 745-3113
2015
.25
TEP plans to construct a 500-kV line loop-in that is less than 3 spans and will
drop in from the existing line into the existing Jojoba switchyard. This project
will provide connectivity between two existing 500kV transmission lines. The
expected in-service date for this project is 2015. The FERC interconnection
study is currently in progress.
“
2016
.3
TEP plans to construct the Willow 345-kV switchyard to accommodate a
“
Page 63 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
generator interconnection request. This switchyard will accommodate the lines
to the generator and loop-in TEP’s Greenlee – Winchester 345-kV line. The
scheduled in-service date has been delayed to late 2016. A System Impact
Study is underway regarding this interconnection request.
The Willow switchyard may also accommodate other renewable generation
interconnection request with in-service dates earlier than 2016. Studies have
not begun on these requests.
Tortolita-South 345 kV line
345
2022
.1
The project will tie two of TEP’s import points together. At this time, the project
is expected to be in-service in 2021 but the schedule is tentative. Initial studies
are expected to begin soon.
“
Vail-South #2 345 kV line
345
2022
.05
Schedule is tentative and subject to change following the completion of study
work to be conducted by TEP. A Comprehensive Progress Report will be
issued when design studies are complete.
″
Westwing – South #2 345
or 500 kV Line or Pinal
West – South #2 345 or
500 kV Line
500 or 345
2022
.05
Schedule is tentative and subject to change following the completion of study
work to be conducted by TEP. A Comprehensive Progress Report will be
issued when design studies are complete.
″
Tortolita – Winchester 500
kV Line
500
2022
.05
This is a new 500 kV transmission line project. The schedule is tentative and
subject to change following the completion of study work to be conducted by
TEP.
″
Winchester – Vail #2 345
kV Line
345
2022
.05
This is a second circuit between Winchester and Vail parallel to existing circuit.
The schedule is tentative and subject to change following the completion of
study work to be conducted by TEP.
″
Winchester – Vail #3 345
kV Line
345
2022
.05
This is a third circuit between Winchester and Vail parallel to existing circuit.
The schedule is tentative and subject to change following the completion of
study work to be conducted by TEP.
″
Springerville – Greenlee #2
345 kV line
345
2022
.05
The schedule for this project is tentative and subject to change following the
completion of study work to be conducted by TEP.
″
Vail – Irvington – South
345 kV Line
345
2022
.1
TEP plans to construct a 345-kV line between TEP’s Vail and Irvington
substations and between TEP Irvington and South substations. The tentative
in-service date is 2021. Preliminary studies have been conducted as part of the
Southeast Arizona Transmission Study (SATS) group. Additional study efforts
will be undertaken prior to submitting a comprehensive progress report for the
project.
“
Tres Amigas Super Station
345
Q4 2017
4
1
Tres Amigas (TA) is developing the Phase I of the Tres Amigas Super Station
(TASS) which will be an HVDC back to back connection between the Western
Frank Barbera
(203) 216-1060
750 MW
Page 64 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
Electric Coordinating Council (WECC) and the Southwest Power Pool (SPP)
systems. The Phase I will consist of a 750MW back to back HVDC system
utilizing voltage source converter (VSC) technology. Phase II is anticipated to
provide an interconnection between the SPP and ERCOT interconnects.
Successive phases may increase the TASS capacity between the
interconnects.
The Tres Amigas project was placed in the WECC portal on September 17,
2010. The Initial Progress Report for the project was submitted to the WECC on
February 23, 2012, which initiated the Project Coordination Process and
periodic updates have been provided. The Comprehensive Progress Report,
submitted on April 6, 2013, provided an overall description of the Phase I
Project, results of studies performed by PNM and status of the TASS.
Desert View- NVE
Northwest 230 kV Line
230
12/2012
.2
640 MVA
1
As reported to WECC in previous annual reports, NV Energy (NVE) was
originally planning to own this line; however, NVE decided to abandon
these plans. As such, VEA has decided to permit and build this facility,
which represents one of the two final segments of YEA's Pahrump to NVE
Northwest 230 kV transmission project. VEA has nearly completed all
project permitting efforts with the BLM and BIA. All major materials have
been ordered and construction of this 4.5 mile segment is expected to
begin in June, 2012 with an in-service date of December, 2012.
Dale Broveak
(775) 727-5312
VEA
Stirling Mountain – Vista
230/138
12/2012
.1
192 MVA
VEA has substantially completed all construction efforts on this 25 mile
segment. The in- service date is coincident with the remaining four
segments associated with the Pahrump to Northwest 230 kV project, which
is anticipated to be December, 2012.
“
Vista – Charleston
138
12/2013
.1
192 MVA
VEA plans to construct a 138 kV line between VEA Vista Substation
and VEA Charleston Substation. The tentative in-service date is
December, 2013. VEA is currently permitting and acquiring right-of-way for
this approximate 14 mile line.
“
Vista – Pahrump
230
12/2012
.1
320 MVA
VEA is finalizing the acquisition of right-of-way for this 13 mile segment.
Major materials have been ordered and construction of this segment is
expected to begin in September, 2012 with an in-service date of December,
2012.
“
Desert View 230 kV
Metering Station
230
12/2012
.1
VEA plans to construct the Desert View 230 kV Metering Station as a tie
between VEA and NVE facilities for both electric as well as a VEA
communications h u b near Las Vegas. Major materials have been
ordered. VEA anticipated construction s t a r t i n g in June, 2012 with an inservice date of December, 2012.
“
Stirling Mountain -Desert
View 230 kV Line
230
12/2012
.1
VEA has substantially completed all construction efforts on this 38 mile
segment. The in- service date is coincident with the remaining four
“
320 MVA
Page 65 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
ARIZONA – NEW MEXICO - NEVADA POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
One
Lines
Maps
Request Copy of
Report From
segments associated with the Pahrump to Northwest 230 kV project, which
is anticipated to be December, 2012.
San Luis – Rio Colorado
Project
604
Q1/2013
170
This project consists of a 604 MW two-on-one combined cycle plant to be
constructed one mile south of the Arizona (U.S.) / Mexico border.
Interconnection will take place via two new 230 kV lines from the plant to the
existing 161 kV Gila station and on to the existing North Gila station in Yuma,
AZ
Leonard York
WAPA-DSW
(602) 605-2797
Todd Rhoades
WAPA – DSW
602-605-2613
Transmission Infrastructure
Program (TIP) Project 230kV ED#5 – 230 kV
Transmission Project
230
7/2014
1
Installed a second circuit, 22 miles long, on Western’s 115-kV Casa GrandeEmpire and Empire-ED5 transmission lines which were recently rebuilt as dual
circuit steel monopoles, and 23 miles, on the SRP’s Duke-Pinal Central 500-kV
steel monopoles.
TIP Project ED#5
Substation Project
230
7/2014
1
Construct a new 230 kV substation at ED#5’s existing 115 kV yard. Project
includes a 225 MVA 230/115/12.47 kV transformer, two breaker 230 kV ring
bus configuration, 3 breaker and a half bays built to 230 kV standards but
operated at 115 kV.
“
7/2014
1
Convert existing 4 breaker ring bus to 2 breaker and a half bays, add 2 new
breaker and a half bays, and build tie line into SRP’s Duke substation.
“
10/2014
1
Add a new 230/69 kV substation, sectionalizing the Davis-Topock #1
transmission line. The 230 kV facilities will be a 3 breaker ring bus
configuration.
TIP Project Test Track
Substation Expansion
Project
Longtin Substation Project
230/69
Michael Baird
WAPA-DSW
602-605-4428
Page 66 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Date
12/2011
1
A new generating facility to be located in the city of Anaheim (County of
Orange) will have a maximum net plant output of 194.1 MW. The project
consists of four (4) GE LM6000 simple cycle natural gas combustion turbines
and interconnects to ANHM’s 69 kV electrical system. Planned operating date
of first unit is July 2011 and the overall project completion expected by
December of 2011.
Nam Nguyen
ANHM
(714) 765-5122
230
6/2012
.1
A new SVC (-75 / +200 MVAr) will be connected at the Tecnologico 230 kV
substation (20111 “TEK-230”) for local voltage support and to increase reactive
margin in the Valley Area of the CFE Baja California system.
Jose Santamaria
CFE
011 52 (686) 5581541
El Centinela 230 kV
Substation
230
11/2011
.1
A new substation “El Centinela” (20453 “CNT-230”) is planned to be built
between buses 20111 (TEK-230) and 20112 (STB-230).
“
Carranza 230 kV
Substation
230
5/2012
.1
A new substation “Carranza” (20461 “CZA-161”) is planned to be built between
buses 20153 (GOR-161) and 20147 (CTY-161).
“
Valle de Puebla
230
3/2012
.1
A new substation “Valle de Puebla” (20460 “VPA-230 “) is planned to be built
between TL 20111 “TEK-230 “ – 20112 “STB-230 “ 230 kV.
“
El Centenario 230 kV
Substation
230
InService
.1
New substation “El Centenario” (20453 “CNT-230 “) between TL 20118 “ROA230 “ – 20112 “STB-230 “ 230 kV. Commercial date, June 2013.
“
San Luis Rey 230 kV
Substation
230
9/2014
.1
New substation “San Luis Rey” (20454 “SLR-230 “) between TL 20104 “CPD230 “ – 20177 “PID-230 “ 230 kV. Commercial date, September, 2013.
“
Transmission Line ROA –
CPD 230 kV
230
6/2014
.1
TL 20118 “ROA-230” – 20104 “CPD-230” will be relocated on July, 2013. New
line will be 20118 “ROA-230” – 20103 “WIS-230” – 20104 “CPD-230”
“
1/2014
.1
Three new gas turbine generators, 72.823 MVA capacity each, connected to
Presidente Juarez 115 kV bus, 20019 PJZ-115. Total capacity 120 MW.
Commercial date, January 2014.
“
Canyon Power Project
Tecnologico 230 kV SVC
Generator Project
Transmission
kV
194
200
MVAR
120
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
No. of
pages
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Paul Didsayabutra
CISO
(916)608-1281
Generation Projects
7684
5/1/08 –
11/30/14
1
The following are generation projects in the ISO generation interconnection
queue that the facility studies have been completed and the interconnection
agreements have been executed:
Devers Substation – 850 MW – 2010
Tesla Substation 230 kV bus E – 1156 MW – 11/30/14
El Segundo 220 kV bus – 630 MW – 6/1/13
“
Page 67 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
Devers-Palo Verde 500 kV line near Blythe – 520 MW – 2010
McCall Substation – 300 MW – 3/31/13
Eastshore Substation – 361 MW – 6/1/12
Between Cottonwood and Vaca-Dixon – 715 MW – 2010
Walnut Substation – 501 MW – 1/3/13
Imperial Valley Substation – 300 MW – 12/1/10
These projects are to be reported on by the individual entities responsible for
them so the CISO will quit reporting in this forum.
Imperial Valley – Dixieland
Substation 230 kV
Interconnection
230/92
12/2015
0
0
0
0
4
The project consists in constructing a new single circuit (prepared for double
circuit) 230 kV transmission line from IID/SDG&E’s Imperial Valley Substation
(IV Sub) to IID’s Dixieland Substation. The IV Sub to Dixieland Substation 230
kV transmission line will span an estimated 7.3 miles. The project also includes
the installation of a 230/92 kV 300 MVA transformer at Dixieland Substation
and interconnection facilities at Imperial Valley Substation.
1.3
David L Barajas
760-482-3450
(IID)
The project will provide back-up for the potential outage of the existing “S” 230
kV transmission line. The new interconnection line will also increase the IID
import/export capability to meet future load requirements.
Ramon Substation 230/92
kV Transformer Addition
230/92
12/2015
.2
Path 42 Upgrade Project
(IID’s Scope of Work)
230
12/2014
Imperial Valley Area Policy
– Driven Transmission Line
and Collector Station
project
230
6/2015
225 MVA
The project consist of installing a second 230/92kV 300 MVA auto-transformer
and convert the existing Ramon Substation 230 kV and 92 kV ring bus to
breaker-and-a- half bus configuration.
The purpose of this project is to provide redundancy to the existing Ramon
230/92 kV transformer.
“
.75
The project consists in reconductoring approximately 20 miles of a double
circuit 230 kV transmission line from IID’s Coachella Valley substation to SCE’s
Mirage Substation with one circuit looping in-and-out IID’s Ramon Substation.
The project also includes converting the Coachella Valley Substation 230 kV
from ring bus to breaker-and-a-half bus configuration, installing a 230 kV 48
MVAR capacitor bank at Coachella Valley Substation and the installation of a
Path 42 Special Protection System for outages in IID’s 230 kV collector system
and Path 42 intertie lines.
“
1
In December of 2012, the CAISO initiated an accelerated competitive
solicitation process conducted for a policy-driven transmission line and collector
station in the Imperial Valley area (the “IV Policy Element”). In July of 2013, the
Imperial Irrigation District (IID) was selected as the Approved Project Sponsor
to finance, own, construct, operate and maintain the IV Policy Element.
The IV Policy – Driven Transmission Line and Collector Station Project,
consists of a 230 kV collector station (Liebert station), located approximately
one mile north of Imperial Valley (IV) Substation, and a short (approximately 1.4
mile) 230 kV transmission line connecting Liebert Station to IV Substation. The
“
Page 68 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
transmission line and the Liebert Station will become network facilities and will
be turned over to the ISO operational control, once IID complete the
construction of additional facilities required to interconnect the IV Policy
Element project to the IID electrical system.
The additional facilities required to interconnect the IV Policy Element to the IID
electrical system consist of a 230 kV Station (Fern) located in the north side of
Liebert Station; a 230 kV bus tie between Fern Station and Liebert Station, and
the connection of the 230 kV “S” line from El Centro Switching Station (ECSS)
to Fern Station.
In addition IID will construct a new 230 kV circuit from Fern Station to IV
Substation as part of this project.
Once the IV Policy Element and the additional facilities are constructed, IID will
establish two points of interconnection in the south with the CAISO and San
Diego Gas and Electric (SDG&E) – one via the bus tie between Fern station
and Liebert CAISO operated station, and the other via the transmission line
between Fern station and IV Substation.
The project also includes the relocation of an existing Gen-Tie from a Solar
Generation Station from IV Substation to Liebert CAISO operated station.
El Centro Switching Station
(ECSS) to Highline Station
double circuit 230 kV
transmission line
230
4/2018
.5
Rebuild the ECSS to Pilot Knob 161 kV and the ECSS to Drop No.4 92 kV
double circuit transmission line sections (18 miles) from ECSS to East Highline
Canal intersection, build one mile of double circuit 230 kV transmission line to
extend the line into Highline station. Build one mile of double circuit 230 kV
transmission line to interconnect the remaining 161 kV line to Pilot Knob and
the 92 kV line to Drop 4.
The project includes the following upgrades in ECSS and Highline stations:
Highline Substation: Upgrade 230 kV and 92 kV switch yards and building a
new 161 kV Bus section, to interconnect the new 230 kV circuits to ECSS, the
161 kV line to Pilot Knob and the 92 kV line to Drop No.4 Generation Station.
ECSS Substation: Upgrade the 230 kV switch yard to breaker–and-a-half bus
configuration to accommodate the new 230 kV circuits from Highline
Substation.
This project is part of the initial phase of IID’s Strategic Transmission
Expansion Plan (STEP).
“
El Centro Switching Station
(ECSS) to Fern Station
double circuit 230 kV
transmission line
230
4/2018
.5
Re-build the ECSS to the proposed Fern station single circuit 230 kV “S”
transmission line (Approximately 17 miles) to double circuit 230 kV.
Upgrade the ECSS 230 kV switch yard to interconnect the new double circuit
230 kV line to Fern Station and upgrade the Fern Station to accommodate the
second 230 kV circuit from ECSS.
This project is part of the initial phase of IID’s Strategic Transmission
Expansion Plan (STEP).
“
Page 69 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Talega-Escondido/ValleySerrano 500 kV
Interconnect Project
(TE/VS Interconnect)
LA Basin Re-powering
Projects:
Haynes Phase 2
Scattergood
Transmission
kV
500
600
530
Date
No. of
pages
Transfer
Capability
Phase
Q1/2014
1
1500
1
7/2013
12/2015
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
The TE/VS Interconnect provides a high capacity link between the main
backbone of California to San Diego Gas and Electric’s (SDG&E) 230 kV grid,
providing the only 500 kV connection between the northern part of the SDG&E
system and Southern California Edison’s (SCE) 500 kV grid. By adding a
future link between the Sunrise Project’s 500 kV Central Substation and the
TE/VS Interconnects Case Springs Substation, a 500 kV loop could be formed
across the western section of the 500 kV lines from the Palo Verde area to
Serrano on the north and Imperial Valley on the south. The project will also
serve to connect the proposed 500 MW Lake Elsinore Advanced Pumped
Storage (LEAPS) into the western grid. The TE/VS Interconnect is being
permitted through the California Public Utilities Commission (A.10–07–001).
Relevant FERC dockets: ER06–278, ER08–654. LEAPS License docket is P–
11858.
3
.1
2
0
0
Planned in-service date is June 1, 2013.
.05
.05
Planned in-service date is December 2015.
0
0
Request Copy of
Report From
Rex Wait
(760) 599-0086
The Nevada Hydro
Company
John Burnett
213-367-1744
(LDWP)
Upgrade terminal
equipment on NorthridgeTarzana 230kV Line 1
230
6/2015
797
Upgrade terminal equipment on Northridge-Tarzana 230kV Line 1
“
Reconductor both ValleyRinaldi 230kV Lines
230
6/2018
495
Reconductor both Valley-Rinaldi 230kV Lines
“
Reconductor TolucaAtwater 230kV Line 1
230
TBD
708
Reconductor Toluca-Atwater 230kV Line 1
“
Add a second Victorville
500/287kV Transformer
Bank
500/287
6/2023
460
Add a second Victorville
500/287kV Transformer Bank
“
Replace Toluca 500/230kV
Banks G and H
500/230
6/2019
913 & 930
Replace Toluca 500/230kV Banks G and H
“
MWC Wind Generation
100
5/2011
.1
New wind farm to interconnect at Intermountain 345 kV switchyard.
“
Owenyo Solar
200
12/2016
.1
New solar PV plant to interconnect at Cottonwood 230 kV substation.
“
Planned Wind #12
204
10/2011
.1
New wind farm to interconnect with Barren Ridge-Rinaldi 230 kV.
“
Planned Solar #2
250
5/2014
.1
New solar PV plant to interconnect at Barren Ridge 230 kV substation.
“
Page 70 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
Pine Canyon Wind
150
4/2013
.1
The status is pending on the new wind farm to interconnect with the Pine Tree
230 kV substation.
“
Planned Solar #3
350
12/2013
.1
The status is pending for the new solar PV plant to interconnect at MarketplaceAdelanto 500 kV substation.
“
Planned Solar #6
150
8/2014
.1
Status is pending for a new solar PV plant to interconnect at McCullough 230
kV substation.
“
Owenyo Solar
200
12/2015
.1
Status pending for a new solar PV plant to interconnect with the Cottonwood
230 kV substation.
“
Adelanto Solar
9
12/2012
.1
Under construction for a new solar PV plant to interconnect with the Adelanto
500 kV substation.
“
Planned Solar #8
90
12/2012
.1
Status is pending for new solar PV plant to interconnect with Barren Ridge 230
kV substation.
“
Planned Solar #9
139
12/2013
.1
Cancelled the new solar PV plant to interconnect with Barren Ridge 230 kV
substation.
“
Planned Wind #11
300
12/2013
.1
New wind farm to interconnect with Barren Ridge-Rinaldi 230 kV.
“
Planned Wind #14
200
12/2012
.1
New wind farm to interconnect with Barren Ridge-Rinaldi 230 kV.
“
Planned Wind #8
201
12/2014
.1
New wind farm to interconnect with Cottonwood-Barren Ridge 230 kV.
“
Planned Solar #17
300
12/2014
.1
New solar PV plant to interconnect with Barren Ridge-Rinaldi 230 kV..
“
Castaic Modernization
Project
1255
1/2013
.1
The planned completion date for the Castaic Power Plant (Units 1 to 7)
Modification Project is Janurary, 2013.
″
This project was identified in LADWP’s TPL-003 studies as a long-term
resolution to potential overloads on the LADWP 230 kV system in the Los
Angeles basin. This new line will parallel an existing 230 kV line between the
Scattergood generating station and Receiving Station K. The ScattergoodOlympic 230 kV line #1 Project is expected to have no regional impact.
“
Scattergood-Olympic 230
kV cable #1 Project
230
6/2015
349 MVA
Page 71 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Barren Ridge Renewable
Transmission Project
(formerly Barren Ridge –
Castaic Transmission
Project)
Transmission
kV
230
Date
No. of
pages
Transfer
Capability
12/2016
.5
1600 MW
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
The planned in-service date is December 2016. It is budgeted and an RFP
for construction has been issued.
Request Copy of
Report From
″
To accommodate LADWP’s planned renewable generation along the InyoRinaldi corridor LADWP is proposing the Barren Ridge Renewable
Transmission Project (BRRTP) to access potential wind, solar and other
clean, renewable resources from the Mojave Desert and Tehachapi
Mountain areas of Southern California. The project is in Kern and Los
Angeles Counties, and is approximately 77 miles in length from Barren Ridge
Switching Station (BRSS) to Rinaldi Substation and 12 miles in length from
Castaic Power Plant to the proposed Haskell Canyon Switching Station. The
project will consist of:
1. Construction of a 230 kV double-circuit transmission line from the LADWP
BRSS to Haskell Canyon Switching Station.
2. Addition of a 230 kV circuit on the existing double-circuit structures from
Haskell Canyon to the Castaic Power Plant.
3. Upgrade the existing Barren Ridge – Rinaldi 230 kV transmission line with
larger capacity conductors between the BRSS and the Rinaldi Substation.
4. Construction of a new switching station at Haskell Canyon.
5. Expansion of the existing BRSS.
The ultimate capacity between the BRSS and the Haskell Canyon Switching
Station is approximately 1600 MW, while the existing rating is 459 MVA. The
BRRTP is expected to have no regional impact.
Beacon Solar
250
1/2016
Project/Upgrade: Beacon Solar
Location: Barren Ridge Switching Station
Capacity: 250 MW
Status: Under Construction
In-Service Date: January 2016
“
Copper Mountain Solar 3
250
12/2015
Project/Upgrade: Copper Mountain Solar 3
Location: Marketplace Switching Station
Capacity: 250 MW
Status: Under Construction
In-Service Date: December 2015
“
Moapa K-Road Solar
250
6/2016
Project/Upgrade: Moapa K-Road Solar
Location: Crystal Switching Station
Capacity: 250 MW
Status: Under Construction
In-Service Date: June 2016
“
Page 72 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
Mirant Marsh Landing
Generating Station
888
2013
2
The Mirant Marsh Landing Generating Station (MLGS), a proposed project near
Antioch, CA will consist of four Siemens Energy simple cycle combustion
turbine-generator units. The units will be located adjacent to Mirant’s Contra
Costa Power Plant and will interconnect to the existing PG&E Contra Costa
Power Plant 230 kV switchyard through two 230 kV transmission lines. Each
unit of the MLGS will have a net winter rating of 222 MW and a net summer
rating of 193.5 MW. The expected commercial operation date for the MLGS is
May 1, 2013.
Chuck Hicklin
925-427-3544
Mirant Marsh
Landing
Lodi Energy Center Project
280
6/2012
1.5
NCPA has submitted an interconnection request to the CISO for the Lodi
Energy Center Project. The project consists of a 1x1 combined cycle
generation plant utilizing an F-Class technology gas turbine with a net output of
280 MW to the CAISO controlled grid. The project will interconnect to PG&E’s
Gold Hill – Lodi Stig and Lodi Stig – Eight Mile Road 230 kV lines via the
existing NCPA Lodi Switching Station.
Michael DeBortoli
916-781-4258
(NCPA)
Gates – Gregg 230kV Line
Project
230
12/2022
.5
This project is to construct a 68 mile long 230kV DCTL from Gates to Gregg
with one side strung. This project will improve reliability in the Greater Fresno
area, allow greater operational flexibility of the three units at the Helms Pumped
Storage Plant (PSP), and help integrate renewable resources within California.
Since the proposed Gates – Gregg 230kV line will be in parallel with the
existing Gates – Gregg 230kV line that is one of the Path 15 lines, this project
will trigger re-definition of Path 15.
In the 2012/13 Transmission Plan Process, the CAISO recommended and
approved the Gates - Gregg 230kV transmission line, constructed as a double
circuit line. One of the circuits is to be strung initially (by 2022 or earlier), and
the other will be strung in the future after demand has increased sufficiently
(anticipated in the 2025-2027 timeframe).
In June 2013, the consortium of PG&E, MidAmerican Transmission and
Citizens Energy submitted a bid to CAISO for the Gates-Gregg 230kV
transmission line and was awarded the project in November 2013.
Kang-Ling Ching
415-973-7637
(PG&E)
Panoche-McMullin 230 kV
Reconductoring
230
3/2014
.1
The Panoche-McMullin 230 kV Line will be reconductored to be capable of
carrying 1893 amps under normal and emergency conditions. Upgrades to
terminal equipment at Panoche and McMullin substations should be performed
as necessary to accommodate the higher ratings.
“
12/2014
.1
Install redundant special protection schemes at multiple substations and Helms
PSP to trip pumping units offline at Helms PSP.
“
4/2015
.1
The Henrietta to McCall section of the Gates-McCall 230 kV Line will be
reconductored to be capable of carrying 1893 amps under normal and
emergency conditions. Upgrades to terminal equipment at Gates, Henrietta and
McCall substations should be performed as necessary to accommodate the
higher ratings.
“
Helms PSP Special
Protection Scheme
Henrietta-McCall 230kV
Reconductoring
230
Page 73 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Date
No. of
pages
Pittsburg - Tesla 230 kV
Reconductoring
230
4/2015
.1
Reconductor the Pittsburg-Tesla 230 kV Nos. 1 and 2 Lines with larger capacity
conductors.
“
Newark - Ravenswood 230
kV Reconductoring
230
5/2015
.1
Reconductor the Newark - Ravenswood 230 kV Line with larger conductors.
“
Tulucay 230/60 kV
Transformer No.1 Capacity
Increase
230/60
5/2015
.1
This project proposes to replace Tulucay Circuit Breaker No. 62 and all of its
associated switches with a circuit breaker rated at 2000 Amps or higher. Any
other associated terminal equipment will also be replaced as necessary
“
Embarcadero-Potrero 230
kV Project
230
12/2015
.1
Construct a new 230 kV underground cable to connect Embarcadero and
Potrero substations.
“
McMullin-Kearney 230 kV
Reconductoring
230
12/2015
.1
The McMullin to Kearney section of the Panoche-Kearney 230 kV Line will be
reconductored to be capable of carrying 1893 amps under normal and
emergency conditions. Upgrades to terminal equipment at Kearney and
McMullin substations should be performed as necessary to accommodate the
higher ratings.
“
Weber 230/60 kV
Transformer Nos. 2 and 2A
Replacement
230/60
4/2016
.1
Replace Weber 230/60 kV Transformer Nos. 2 and 2a with a new transformer
rated at least 300 MVA with LTC and associated equipment
“
Kearney 230/70 kV
Transformer 2
230/70
5/2016
.1
Install second 230/70 kV Transformer at Kearney Substation rated for 200 MVA
or higher, install 4 element 230 kV ring, expand 70 kV bus and re-terminate
lines
“
230
12/2016
.1
Reconductor the Contra Costa - Moraga 230 kV DCTL with larger capacity
conductors.
Moraga Transformer No. 2
Capacity Increase
230/115
12/2016
.1
Replace Transformer number 2, 230/115 kV at Moraga Substation with a 420
MVA rated unit.
“
Midway-Kern PP 230 kV
Line Nos. 1, 3 and 4
Capacity Increase Project
230
5/2017
.1
Replace limiting components at Kern PP and Midway Substations, to achieve
full capacity on the Midway-Kern 230 kV Line Nos. 1, 3 and 4
“
Moraga - Castro Valley
230 kV Line Capacity
Increase Project
230
12/2017
.1
Upgrade the limiting substation equipment (jumper conductors and wave traps)
at Moraga and Castro Valley substations
“
230/115
12/2017
.1
This project proposes to install a 230/115 kV transformer at Fulton Substation
rated for 420 MVA or higher.
“
230
12/2017
.1
Reconductor limiting sections of Tesla - Newark 230 kV No. 2 with larger
capacity conductors.
“
Contra Costa – Moraga
230 kV Reconductoring
Fulton 230/115 kV
Transformer
Tesla - Newark 230 kV
Upgrade II
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Page 74 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Date
No. of
pages
Rio Oso 230/115 kV
Transformers
230/115
12/2017
.1
Replace the Rio Oso 230/115 kV transformers (Nos. 1 and 2) with two 420
MVA rated transformers. Convert 115 kV bus to BAAH.
“
Rio Oso Area 230 kV
Voltage Support
230
12/2017
.1
Install a new Static Var Compensator (SVC) at Rio Oso Substation and a new
Shunt Capacitor at Atlantic Substation.
“
Pittsburg 230/115 kV
Transformer Capacity
Increase
230/115
5/2018
.1
Install 3rd 230/115 kV Transformer at Pittsburg Substation with a rating of 420
MVA
“
Ashlan-Gregg and AshlanHerndon 230 kV
Reconductor
230
5/2018
.1
Reconductor limiting sections of Ashlan-Gregg and Ashlan-Herndon 230 kV
sections with higher rated conductors.
“
San Mateo Synchronous
Condensor Replacement
115
5/2018
.1
Install reactive support device to replace old synchronous condensers at
115kV.
“
Vaca Dixon - Lakeville 230
kV Reconductoring
230
6/2018
.1
Reconductor the Vaca – Lakeville No. 1, Tulucay – Vaca, and Tulucay –
Lakeville 230 kV Lines with larger capacity conductors.
“
Borden 230 kV Voltage
Support
230
5/2019
.1
This project proposes to loop the Wilson-Gregg 230 kV Line into Borden
Substation (Borden) and install 200 MVARs of mechanically switched
capacitors on the Borden 230 kV bus.
“
Morro Bay 230/115 kV
Transformer
230/115
5/2019
.1
Install an additional 230/115 kV transformer at Morro Bay Substation rated for
200 MVA or higher.
“
Kern PP 230 kV Area
Reinforcement Project
230
12/2019
• Convert Kern PP 230 kV double bus single breaker arrangement to breaker
and a half
• Replace limiting equipment on Kern PP 230/115 kV transformer No. 4 as
necessary to achieve full transformer rating
• Install a 230/115 kV Transformer Special Protection Scheme at Kern 115 kV
to mitigate overloads of Kern PP Transformer Nos. 3, 4, and 5
“
Wheeler Ridge Voltage
Support
230
5/2020
.1
Install three 75 MVAR steps of mechanically switched capacitors on the
Wheeler Ridge 230 kV bus, expand the 230 kV bus as necessary reconductor
0.5 miles of the Wheeler Ridge-Lakeview 70 kV line and transfer Copus from
the Old River-Copus 70 kV line to the Wheeler Ridge-Lakeview 70 kV line.
“
Rio Oso – Atlantic 230 kV
Line
230
11/2022
.1
Construct a second Rio Oso – Atlantic 230 kV Line.
“
Contra Costa sub 230kV
Switch Replacement
230
5/2016
.1
Replace 230 kV Switch No. 239 at Contra Costa Substation that currently limits
the Contra Costa PP-Contra Costa Sub 230 kV Line to 1600 Amps. Any other
limiting element will be replaced as well.
“
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Page 75 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Date
No. of
pages
Gates No. 2 500/230 kV
Transformer
500/230
12/2017
.1
Install a second 500/230/13.8 kV transformer (three single-phase units, 374
MVA each) at Gates Substation
“
Kearney-Herndon 230 kV
Line Reconductor
230
12/2017
.1
Reconductor 10 miles of the Kearney - Herndon 230 kV Line
“
Warnerville-Wilson 230 kV
Series Reactor
230
12/2017
.1
Install a 230 kV multi-step Reactor totaling 50.5 ohms, and associated
equipment at Wilson Substation, on the Warnerville-Wilson 230 kV line
“
Diablo Canyon Voltage
Support Project
230
5/2018
.1
Install a +150/-75 MVAR Reactive support device at Diablo Canyon 230 kV
Substation
“
Lockeford-Lodi Area 230
kV Development
230
5/2020
.1
Construct new 15 mile 230 kV DCTL from Eight Mile Substation to Lockeford
Substation
Midway-Andrew 230 kV
230
12/2020
.1
Upgrade existing 65 miles long Midway-Santa Maria 115KV line to 230kV
“
Moraga-Potrero 230 kV
Project
230
12/2020
.1
Establish a 230 kV connection between Moraga and Potrero Substations.
“
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Solar Star Generation
Interconnection Project
110
6/2015
.1
Build a 230 kV Quinto Switching Station to interconnect 110 MW solar
generation to Pacific Gas and Electric Company's (PG&E's) Los Banos-Westley
230 kV Line and reconductoring 26 miles of the line from switching station to
Westley Sub
“
Stockton Generation
Expansion Project
508
5/2017
.1
Stockton Generation, LLC, proposing to interconnect two gas turbines and a
steam turbine with a combined output of 508 MW. The proposed Commercial
Operation Date of the project is May 1, 2014. The project will interconnect with
PG&E’s Bellota – Tesla No. 2 and Weber-Tesla 230 kV transmission lines by
looping these lines into a new switching station and require reconductoring of
the Warnerville-Wilson 230 kV Line.
“
2012-18
3.5
LeGrand – Chowchilla 115 kV Reconductoring – June 2015
Corina – Eagle Rock 115 kV Reconductor – May 2014
North Valley and Sierra 230 kV line Capacity Increase – May 2015
Other Transmission
Projects – Granted Waiver
of “Significant
Transmission Project”
Status
115/230
Kang-Ling Ching
415-973-7637
(PG&E)
Page 76 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
SMUD Solano Wind Phase
III Generation
Interconnection Project
128
3/2012
.3
The SMUD Solano Wind Project Phase III Generation Interconnection (the
“Project”) consists of forty-four (44) wind turbine Generating Units each rated at
3 MW. The maximum net output to the CAISO Controlled Grid will be 128 MW.
The step-up transformers are one three phase, 3.16 MVA, 1/34.5 kV for each
wind turbine Generating Unit and one three-phase, 166 MVA, 34.5/230 kV for
the total output of the Project. The Project will be connected to the existing
Sacramento Municipal Utility District (SMUD) Russell Substation 230 kV bus
which is connected to PG&E’s Birds Landing Switching Station 230 kV bus.
“
Calpine Russell City
Energy Center
600
7/2012
.1
Interconnect 600 MW generation project to PG&E's East shore Substation 230
kV Bus. Convert bus. Replace transformer. Build 230 kV generation tie line.
“
Green Ridge Wind Power
Project
75
10/2012
.3
Green Ridge Power, LLC is proposing to repower the Jackson Substation via
Green Ridge Wind Power Generation Interconnection Project. This project will
interconnect 75.1 MW (net output) wind power-based generation facility to the
PG&E transmission system. Jackson Substation is currently interconnected
onto PG&E’s Lone Tree-Cayetano 230 kV Line.
“
Montezuma II Wind
Generation Interconnection
Project
78
5/2014
.3
NextEra Energy Resources, LLC (NextEra), proposed to interconnect its
Montezuma II Wind Project (The Project) to the California Independent System
Operator Corporation (“CAISO”) Controlled Grid. The Project consists of 34
Siemens wind turbine generating units each rated at 2.3 MW with total output of
78.2 MW. This project proposes to interconnect to a new ring bus at the
existing Montezuma Project (High Winds III) Substation.
“
Franklin 230/69 kV bulk
substation
230/69
2018
1
The existing Rancho Seco – Pocket 230 kV #2 line will be looped in to a new
230/69 kV bulk substation at Franklin, Sacramento County, to serve local load
growth. Anticipated in-service date is 2018.
Dilip Mahendra
916-732-6180
(SMUD)
Bay Blvd (formerly
Bayfront) Substation
Transmission Project
230/69
12/2016
.1
The Bay Blvd 230/69 kV Substation Transmission project is designed and
constructed to better serve SDG&E local load and includes the following scope
of work: 1) Construct a new 230/69 kV substation that will replace the existing
South Bay 138/69 kV substation; 2) Install two 224 MVA 230/69 kV
transformers; 3) Loop in the Miguel-Silvergate 230 kV transmission line into the
new substation; 4) Transfer all 69 kV lines presently connected to the South
Bay 138/69 kV substation to the new substation; and 5) Re-configure existing
138 kV lines to eliminate the need for the South Bay 138 kV bus.
David Wang
858-654-8162
(SDGE)
Page 77 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
South Orange County
Reliability Enhancement
Project
ECO 500/138 kV
Substation
Gen
MW
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Date
No. of
pages
230/138
12/2018
.7
The project scope contains transmission and distribution work. The system
changes required to accommodate the new Capistrano 230/138/12kV
substation are as follows:
a. Distribution
Rebuild the aging and obsolete distribution equipment (138kV & 12kV) at
Capistrano substation using three new 138/12kV transformers (ultimate 4138/12kV banks).
b. Substation
Construct a new gas insulated (GIS) 230kV switchyard at the existing
Capistrano substation with two 230/138kV transformers and a 230kV
capacitor.
c. Transmission
Construct two new 230kV circuits from Talega to Capistrano, one from
SONGS and the other from Talega (tapping the existing TL23030 from
Escondido), by rebuilding the existing TL13835 with double-circuit structures
(8 miles between Talega and Capistrano). Terminate six adjacent 138kV
lines at Capistrano sub.
“
500/230/135
11/2014
1
This project will construct a 500/230/138kV substation near the Southwest
Powerlink (SWPL), between Imperial Valley substation and Miguel substation,
and it will extend a 138kV line from the new substation to the existing
Boulevard substation. Also, the project will rebuild Boulevard substation on a
neighboring site in order to accommodate generation interconnections at
Boulevard. Scope of work include:
a. Substation
i. Site preparation
ii. Construction of the new 500/230/138kV substation
iii. Site preparation for new Boulevard substation location (near or adjacent
to existing site)
iv. Construction (rebuild) of 138/12kV Boulevard substation on neighboring
site
b. Transmission
i. Loop SWPL into the new ECO substation.
ii. Construction of a new 14-mile twin circuit 900 ACSS 138kV transmission
line from the new ECO substation to rebuilt Boulevard substation.
c. Other
i. Construction of new microwave communications facilities
ii. ECO substation land purchase
iii. Boulevard substation adjacent land purchase
iv. Acquisition of a new ROW for the new 138kV transmission line
“
Phase
One
Lines
Request Copy of
Report From
Page 78 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Date
No. of
pages
Transfer
Capability
500/230
3/2013
.5
1100 MVA
Sycamore-Penasquitos
230 kV Line Project
230
6/2017
Artesian 230 kV Expansion
230
New 230/69 kV
Transformer at Mission
230
Name of Project
3rd 500/230 Transformer
Bank (IV Bank 82) at
Imperial Valley Substation
Gen
MW
Transmission
kV
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
This project will add 500/230 transformer at SDG&E’s Imperial Valley
Substation. Scope of work include:
a. Substation
i. Site preparation
ii. Add 3rd 500/230 transformer at 1100MVA rating.
“
.5
1. Project Scope
a. new 230 kV line connecting two substations, Sycamore and
Penasquitos, owned by SDG&E within SDG&E control area.
2. The estimated project In-Service-Date is June 2017.
3. Project Status: CAISO approved
4. Facility Owner: SDG&E in conjunction with and Citizen Energy
5. No Regional Impact – This is an internal system upgrade that balances
power flows among transmission lines into load centers with SDG&E control
area. It has no impact on neighboring electric systems. SDG&E therefore
requests a waiver from “Significant Transmission Project” status.
“
6/2016
.5
1. Project Scope
a. Expend Artesian 69 kV substation to 230/69 kV substation adding one
230/69 kV transformer
b. Loop in existing Sycamore – PEN 230 kv line at Artesian 230.
2. The estimated project In-Service-Date is June 2016.
3. Project Status: CAISO approved
4. Facility Owner: SDG&E
5. No Regional Impact – This is an internal system upgrade that provides
additional source to 69 kV system around Poway area. It has no impact on
neighboring electric systems. SDG&E therefore requests a waiver from
“Significant Transmission Project” status.
“
6/2018
.25
1. Project Scope: replace two 138/69 kV transformers with one 230/69 kV
transformer at SDG&E Mission Substation
2. The estimated project In-Service-Date: June 2018
3. Project Status: CAISO approved
4. Facility Owner: SDG&E
5. No Regional Impact – This is an internal system upgrade that mitigates local
contingency overloads and provides better local voltage control. It has no
impact on neighboring electric systems. SDG&E therefore requests a waiver
from “Significant Transmission Project” status.
“
Page 79 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Transmission
kV
Date
6/2015
.25
1. Project Scope: 2x(+225/-120) MVAr synchronous condenser at Talega
Substation.
2. The estimated project In-Service-Date: June 2015
3. Project Status: CAISO approved
4. Facility Owner: SDG&E
5. No Regional Impact – This is an internal system upgrade that provides
needed voltage support. It has no impact on neighboring electric systems.
SDG&E therefore requests a waiver from “Significant Transmission Project”
status.
“
6/2017 or
18
.33
1. Project Scope: 2x(+225/-120) synchronous condenser at SDG&E
SONGSMESA Substation/Switchyard that would be built near existing San
Onofre Substation.
2. The estimated project In-Service-Date: June 2017 or 2018
3. Project Status: CAISO approved
4. Facility Owner: SDG&E
5. No Regional Impact – This is an internal system upgrade that provides
needed voltage support. It has no impact on neighboring electric systems.
SDG&E therefore requests a waiver from “Significant Transmission Project”
status.
“
San Luis Rey Synchronous
Condenser
6/2016
.33
1. Project Scope: 2x(+225/-120) MVAr synchronous condenser at SDG&E San
Luis Rey Substation
2. The estimated project In-Service-Date: June 2016
3. Project Status: CAISO approved
4. Facility Owner: SDG&E
5. No Regional Impact – This is an internal system upgrade that provides
needed voltage support. It has no impact on neighboring electric systems.
SDG&E therefore requests a waiver from “Significant Transmission Project”
status.
“
Shunt Reactor at Suncrest
6/2014
.33
1. Project Scope: Install three single phase reactors at Suncrest Substation and
connect to the 500 kV bus. Each reactor will be rated 46 MVar at 317.5 kV
phase to ground for a three phase total of 138 MVar at 550 kV.
2. The estimated project In-Service-Date: June 2014
3. Project Status: Submitted for information only to CAISO as part of SDG&E’s
2013 Grid Assessment plan.
4. Facility Owner: SDG&E
5. No Regional Impact – This is an internal system upgrade that provides
needed voltage control within SDG&E’s service territory and has no impact on
neighboring electric systems. SDG&E therefore requests a waiver from
“Significant Transmission Project” status.
“
4/2018
.2
Build 63 miles of 220 kV line between SCE’s existing Coolwater 220/115 kV
Substation and Lugo 500/220 kV Substation.
Talega Synchronous
Condenser
SONGSMESA
Synchronous Condenser
Coolwater-Lugo (South of
Kramer) 220 kV T/L
220
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
No. of
pages
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
David Franklin
626-302-0372
(SCE)
Page 80 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Date
No. of
pages
Primm 220 kV Substation
220
10/2015
.2
Construct new Primm 220 kV Substation to interconnect renewable generation
projects.
“
Path 42 Upgrade Project
(SCE’s Scope of Work)
220
12/2014
.2
Install relays at Devers and Mirage Substations in support of IID’s Path 42
RAS, and upgrade the following transmission lines post Devers-Coachella
Valley Loop-in Project:
•Devers-Mirage 220 kV # 1 T/L
•Devers-Mirage 220 kV # 2 T/L
•SCE-owned portion of Mirage-Ramon 220 kV T/L
•SCE-owned portion of Mirage-Coachella Valley 220 kV T/L
IID is a co-sponsor for this project. Please contact IID for its scope of work
regarding the Path 42 Upgrade Project.
“
San Joaquin Cross Valley
Loop Project
230
9/2014
.1
Construction of a new 18.5 mile double-circuit 230 kV transmission line that
would connect Rector Substation to an existing 230 kV line from SCE’s Big
Creek hydroelectric facilities in the Siera Nevada Mountains. Loop Big Creek
3-Springville 230 kV line into Rector.
″
500/230
10/20092/2016
.05
Change the description to – Construct the following 500 kV and 220 kV
transmission facilities
needed to connect 4500 MW renewable generation in the Tehachapi area:
-Pardee 220 kV (In-Service)
-Service)
-Vincent 500 kV (In-Service)
– WindHub 500 kV (In-Service)
– Vincent 500 kV #2 (In-Service)
-in of Midway – Vincent #3 500 kV (InService)
– Whirlwind 500 kV (In-Service)
“
Tehachapi Renewable
Transmission Project
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
– WindHub 500 kV (In-Service)
– Rio Hondo 500 kV (Energized at 220 kV)
– Mira Loma 500 kV
– Mesa 500 kV (Energized at 220 kV)
Alberhill 500/115 kV
Substation
500/115
1/2018
.05
Develop a new 1120 MVA Alberhill 500/115 kV Substation and associated
transmission lines. Construct a new 500/115 kV transmission substation
(Alberhill Substation), connecting SCE’s existing Serrano-Valley 500 kV
transmission line into the new Alberhill Substation with two new 500 kV line
segments. Construct a new 115 kV subtransmission line and modifications to
existing 115 kV subtransmission lines.
“
Page 81 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Date
No. of
pages
Wildlife (formerly Jurupa)
230 kV Substation
230
7/2020
.1
Develop a 560 MVA Wilderness 220 kV Substation for Riverside. Loop the
existing Mira Loma-Vista 220 kV #1 line and construct about 7 miles of double
circuit T/Ls to Wilderness 220 kV that provides a method of service to a new
substation that will serve the City of Riverside.
“
Riverside 220 kV
Interconnection
220
7/2020
.1
The project will be constructed at the same time as and adjacent to Wildlife 230
kV Substation project and will be tied to Wildlife 230 kV.
“
West of Devers (WOD)
Upgrade Project
230
2020
.1
Upgrade four (five with El Casco Substation loop-in) 220 kV lines on the west
side of Devers 220 kV substation to 2B-1590 ACSR conductor.
“
Valley-Serrano 500 kV #2
Transmission Line
500
6/2019
.05
Construct a second Valley-Serrano 500 kV transmission line to provide load
service capacity.
“
6/2024
.05
Master Plan to build transmission lines and substations to serve load in San
Joaquin Valley area.
“
North of Magunden Long
Term Plan
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Name of Project
Gen
MW
Phase
One
Lines
Request Copy of
Report From
Mesa 500/230 kV
Substation
500/230
6/2019
.05
Develop a new 500/230 kV Substation equipped with 2 x 1120 MVA
transformers.
“
Lighthipe 500/230 kV
Substation
500/230
6/2019
.05
Develop a new 500/230 kV Substation equipped with 2 x 1120 MVA
transformers.
“
Manzana Wind
300
12/2015
.1
Interconnect a 300 MW Wind Generating Facility to SCE's Whirlwind 220 kV
Substation. Project is being phased in that will be completed by the operating
date.
“
Blythe Solar Power
485
6/2015
.1
Interconnect a 485 MW Solar Generating Facility to SCE's expanded Colorado
River 500/200 kV Substation.
“
Palen Solar
500
6/2016
.1
Interconnect a 500 MW Solar Generating Facility to SCE's proposed Red Bluff
500/220 kV Substation.
“
Abengoa Solar Project
250
4/2013
.1
Interconnect a 250 MW Solar Generating Facility to SCE's proposed Lockhart
220 kV Substation.
“
Genesis-McCoy Solar
Project
500
5/2016
.1
Interconnect a 500 MW Solar Generating Facility to SCE's expanded Colorado
River 500/220 kV Substation.
“
Desert Stateline
300
10/2015
.1
Interconnect a 300 MW Solar Generating Facility to SCE's Ivanpah 220 kV
Substation.
“
Silver State South
220
10/2015
.1
Interconnect a 220 MW Solar Generating Facility to a new SCE Primm 220 kV
Substation.
“
Page 82 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Name of Project
Gen
MW
Transmission
kV
Date
No. of
pages
Transfer
Capability
Phase
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
One
Lines
Request Copy of
Report From
Pacific Wind Project
250
12/2015
.1
Interconnect a 250 MW Wind Generating Facility to SCE's Whirlwind 220 kV
Substation. Project is being phased in that will be completed by the operating
date.
“
Alta 2012 Project
720
6/2017
.1
Interconnect a 720 MW Wind Generating Facility to SCE's Windhub 220 kV
Substation. Project is being phased in that will be completed by the operating
date.
“
North Sky River Wind
Project
297
6/2015
Interconnect a 297 MW Wind Generating Facility to SCE's Highwind 220 kV
Substation. Project is being phased in that will be completed by the operating
date.
“
Antelope Valley Solar PV 1
310
6/2015
.1
Interconnect a 310 MW Solar Generating Facility to SCE's Whirlwind 220 kV
Substation. Project is being phased in that will be completed by the operating
date.
“
Antelope Valley Solar PV 2
276
6/2015
.1
Interconnect a 276 MW Solar Generating Facility to SCE's Whirlwind 220 kV
Substation. Project is being phased in that will be completed by the operating
date.
“
.1
Install a new 500/220 kV AA-bank at Eldorado Substation connected to the
SCE-owned Eldorado 220 kV switchyard. Desert Stateline and Silver State
South triggered the need for this AA-bank.
“
Add a second transformer bank at the existing Whirlwind Substation to add
capacity to deliver new renewable generation interconnecting to the 220 kV
bus.
“
SCE Owned Eldorado
500/220 kV 5AA-Bank
500/220 kV
10/2015
Whirlwind 2nd 500/220 kV
Transformer
500/220 kV
9/2014
Rector SVS Expansion
220 kV
12/2014
.1
Expand Rector Static VAR System (SVS) by adding three 79.2 MVAR Shunt
Capacitor Banks at Rector Bus and SVS control points to maintain minimum
voltages at Rector 220 kV.
“
East Kern Wind Resource
Area (EKWRA) 66 kV
Project
66 kV
12/2014
.1
Description: Reconfigure Antelope-Bailey 66 kV system into two separate
systems. The northern system will be served radially from Windhub Substation.
The southern system will remain parallel to the existing Antelope and Bailey
220 kV systems.
“
Interconnect a 150 MW Wind Generating Facility to SCE's Whirlwind 220 kV
Substation via a shared generation tie line with the Pacific Wind Project. Project
is being phased in that will be completed by the operating date.
“
Catalina Wind Project
150
6/2015
Eldorado-Lugo Series Cap
Upgrade
12/2016
.1
Upgrade series capacitor and terminal equipment at Eldorado and Lugo to
3800A/4000A (SN/SE)
Lugo-Mohave Series Cap
Upgrade
12/2016
.1
Upgrade series capacitor and terminal equipment at Mohave to 3800A/4000A
Page 83 of 91
Revised
8/6/2014
LIST OF ANNUAL PROGRESS REPORTS TO WECC - 2014
CALIFORNIA-MEXICO POWER AREA
Transfer
Capability
CONTENTS AND REMARKS
Power
Transient
Post Transient
Tables
Flow
Stability
Stability
Maps
Transmission
kV
Date
No. of
pages
Whirlwind 3rd 500/220 kV
Transformer Bank
500/220
3/2017
.1
Add a third transformer bank at the existing Whirlwind Substation to add
capacityto deliver new renewable generation interconnecting to the 220kV bus.
Kramer-Lugo 230 kV No. 1
&2
230
2015
.1
Loop-in the Kramer-Lugo 230 kV No. 1 and No. 2 lines into Victor Substation
creating Kramer-Victor 230 kV No. 1 and No. 2 and Lugo-Victor 230 kV No. 1
and No. 2.
Name of Project
Gen
MW
Phase
One
Lines
Rising Tree Project
200
10/2015
.1
Interconnect a 200 MW Wind Generating Facility to SCE’s Windhub 220
Substation via a generation tie line. Project is being phased in that will be
completed by the operating date.
Alta Wind Q97
160
10/2016
.1
Interconnect a 160 MW Wind Generating Facility to SCE’s Whirlwind 220
Substation via a generation tie line shared with Alta Wind Q153.
Alta Wind Q153
100
10/2016
.1
Interconnect a 100 MW Wind Generating Facility to SCE’s Whirlwind 220
Substation via a generation tie line shared with Alta Wind Q97.
SVP Phase Shifting
Transformer Project (SVPPST)
230
2014
2
400 MVA
0
0
0
0
1
SVP will install a 400 MVA, 230/230 kV phase shifting transformer in the SVP
SSS station, located adjacent to the PG&E Los Esteros Substation in Santa
Clara County, California. The transformer will be placed in series with the SSSNRS 230 kV circuit. A 4 ohm series reactor will also be installed between the
bus sections of the SVP NRS 115 kV bus to allow for closing the currently open
115 kV bus tie. SVP is currently coordinating with Pacific Gas and Electric
Company to determine what electric system improvements, if any, may be
needed on its system.
Request Copy of
Report From
Orville Plum
(408)261-5470
Silicon Valley
Power
(SVP)
Page 84 of 91
Revised
8/6/2014
Attachment I
Member Systems reporting significant facilities* in the 2013 Annual Progress reports to WECC from
which, as of July 31, 2014, no report has been received:
1. Lucky Corridor
2. Sea Breeze Pacific RTS
3. NV Energy South
4. TCP
5. Wyoming Colorado Intertie
6. Sithe Global
7. LS Power
8. Southline Transmission Project
9. Centennial West Clean Line LLC.
10. Tres Amigas
11. VEA
12. ANHM
13. CFE
14. CISO
15. The Nevada Hydro Company
16. Mirant Marsh Landing
17. NCPA
* Projects listed as “In service” will be removed from the next issue of this log.
Attachment II
Member Systems previously reporting significant facilities* in the WECC Transmission Database from
which, as of July 31, 2013, no report has been received:
1. Northwest Alberta Transmission System Reinforcement (2011-12) AESO
2. 9L15 termination into Livock
AESO
3. Northwest Alberta Transmission System Reinforcement (2015-17) AESO
4. Southeast Transmission Reinforcement (SETR)
AESO
5. Yellowhead Area Transmission Development – P671
AESO
6. Livock 240/144 kV Connection – P834
AESO
7. Fidler 312S 240/138 kV Interconnection – P936
AESO
8. Northeast Fort McMurray 240 kV Loop – P791
AESO
9. Halkirk 1 Wind Project – P723
AESO
10. Christina Lake Area Development
AESO
11. Algar 240/144 kV substation
AESO
12. Algar-Kinosis 240 kV line
AESO
13. Alberta Industrial Heartland Bulk Transmission Development – State 2 AESO
14. P116 – Foothills Area Transmission Development
AESO
15. C-Free Power Oven Wind-P763
AESO
16. Edmonton - Calgary West DC Lline – P962
AESO
17. Edmonton - Calgary East DC Lline – P961
AESO
18. Bow City Power Project-P465
AESO
19. Pikani Energy Corp. Wind-P773
AESO
20. Vindt Willowridge – P614
AESO
21. Bloodtribe Wild Turnip Hill
AESO
22. P635 - Suncor Hand Hills Wind Energy Project
AESO
23. P678 - Nexen Hand Hills Wind Project
AESO
24. P811 - Central East Transmission Development
AESO
25. P812 - Hanna Region Transmission Development
AESO
26. Noxon Rapids Turbine Upgrades
AVA
27. Metro North Area 230 kV Reinforcement
BCHA
28. Merritt Area Transmission Project
BCHA
29. Revelstoke Unit 6 Installation
BCHA
30. North Cross Cascade 500 kV Line Project
BPA
31. John Day Substation – Golden Hills 200 MW (G00099-2)
BPA
32. Shepherds Flat Wind Phase 1 (aka North Hulburt Wind) (G0118 and G0291) BPA
33. Montague I
BPA
34. Lower Snake Wind
BPA
35. Miller Ranch Wind
BPA
36. Golden Hills Wind
BPA
37. Rapids – Columbia 230 kV Transmission Line
DCPUD
38. Columbia – Larson 230 kV Line
GCPUD
39. King 230/138 kV Project
IPC
40. Pearl Transmission Substation
IPC
* Projects listed as “In service” will be removed from the next issue of this log.
41. Midpoint T232 230/138 kV Transformer Addition Project
IPC
42. Lucky Corridor Transmission Project
Lucky Corridor
43. Mountain States Transmission Intertie Project
NWMT
44. Current Creek
PAC
45. Pear – Sherwood 230 kV Retermination
PGE
46. Trojan-Horizon 230 kV line
PGE
47. McLoughlin 230 kV Bus Sectionalizing Breaker
PGE
48. Jefferson County 115 kV Upgrade Phase II
PSEI
49. Sea Breeze Pacific Regional Transmission System
Sea Breeze
50. Sea Breeze Pacific – West Coast Cable Project
Sea Breeze
51. Sea Breeze Pacific – Juan de Fuca Cable Project (jdF)
Sea Breeze
52. Southwest Intertie Transmission Project (SWIP)
NV Energy
53. Southern Nevada Intertie Transmission Project
NV Energy
54. Blackhawk 345/120 kV Substation (was Emma)
NV Energy
55. Fallon 230 kV Source
NV Energy
56. One Nevada Transmission Intertie Project
NV Energy
57. 230 kV Re-Termination Project
TPWR
58. Canyon Substation / Switching Station
TCP
59. Zephyr Project
TCP
60. Chinook Project
TCP
61. Dry Fork Station
BEPC
62. Undervoltage Load-Shedding Scheme
BHP
63. San Lues Valley – Calumet – Comanche Transmission Project
PSC
64. Cogentrix of Alamosa
PSC
65. Limon 1 & 2
PSC
66. San Luis Valley – Calumet – Comanche Transmission Project
TSGT
67. Miracle Mile Substation
TSGT
68. Wyoming Colorado Intertie
WCI
69. Navajo Transmission Project Segment 1
Sithe Global
70. Great Basin Transmission SWIP – South Project
LS Power
71. Great Basin Transmission SWIP – North Project
LS Power
72. McDonald 230/138 kV Addition
NVE
73. Brooks 230/138/12 kV Substation and Pecos – Brooks 230 kV Line NVE
74. Sunrise 500/230 kV Transmission Substation
NVE
75. Robinson – Harry Allen Transmission Line #2 Project
NVE
76. Northwest 500/230 #2 Transformer Addition
NVE
77. Sunrise 500/230 kV #2 Transformer Addition
NVE
78. Eastern Mining Area Expansion Project
SRP
79. Silver King – New Pinto Valley 230 kV Line
SRP
80. Schrader – Abel 230 kV Line
SRP
81. Kyrene 500/230 kV Transformer
SRP
82. Rudd 230/69 kV Transformer
SRP
83. Schrader 230/69 kV Transformer
SRP
84. Resolution Copper 230 kV Line
SRP
85. Abel 230 kV Generation
SRP
86. Other Joint SRP/APS Projects
SRP
* Projects listed as “In service” will be removed from the next issue of this log.
87. Other SRP 115/230/345 kV Transmission Project
88. Southline Transmission Project
89. Centennial West Clean Line HVDC Project
90. Willow 345 kV Switchyard
91. Winchester – Vail #2 and #3 345 kV Lines
92. Desert View – NVE Northwest 230 kV Line
93. Stirling Mountain – Vista
94. Vista – Charleston
95. Vista – Pahrump
96. Desert View 230 kV Metering Station
97. Stirling Mountain – Desert View 230 kV Line
98. San Luis – Rio Colorado Project
99. Canyon Power Project
100. Tecnologico 230 kV SVC
101. El Centinela 230 kV Substation
102. Carranza 230 kV Substation
103. Valle de Puebla
104. Generation Projects
SRP
Southline
Centennial West
TEP
TEP
VEA
VEA
VEA
VEA
VEA
VEA
WAPA DSW
ANHM
CFE
CFE
CFE
CFE
CISO
Devers Substation
Tesla Substation
El Segundo 220 kV bus
Devers-Palo Verde 500 kV line near Blythe
McCall Substation
Eastshore Substation
Between Cottonwood and Vaca-Dixon
Walnut Substation
Imperial Valley Substation
105. Talega-Escondido/Valley-Serrano 500 kV Interconnect Project
(TE/VS Interconnect)
The Nevada Hydro Company
106. MWC Wind Generation
LDWP
107. Owenyo Solar
LDWP
108. Planned Wind #12
LDWP
109. Adelanto Solar
LDWP
110. Planned Solar #9
LDWP
111. Planned Wind #11
LDWP
112. Planned Wind #14
LDWP
113. Planned Wind #8
LDWP
114. Planned Solar #17
LDWP
115. Castaic Modernization Project
LDWP
116. Mirant Marsh Landing Generating Station
Mirant Marsh Landing
117. Lodi Energy Center Project
NCPA
118. Other Transmission Projects Granted Waivers
PG&E
119. Colusa Generating Station
PG&E
120. SMUD Solano Wind Phase III Generation Interconnection Project PG&E
121. Calpine Russell City Energy Center
PG&E
122. Green Ridge Wind Power Project
PG&E
123. Montezuma II Wind Generation Interconnection Project
PG&E
124. Franklin 230/69 kV Bulk Substation
SMUD
125. 3rd 500/230 Transformer at Imperial Valley Substation
SDGE
* Projects listed as “In service” will be removed from the next issue of this log.
126. SVP Phase Shifting Transformer Project
* Projects listed as “In service” will be removed from the next issue of this log.
SVP
Attachment III
List of Projects Requesting A Waiver of “Significant Transmission Project” Status
Project Name
Organization
1.Palm Valley – Trilby Wash 230 kV Project
APS
2.Sun Valley‐Trilby Wash 230 kV Project
APS
3.Palo Verde‐Delaney 500 kV Project
APS
4.Delaney‐Sun Valley 500 kV Project
APS
5.Mazatzal 345/69 kV Substation
APS
6.Sun Valley‐Morgan 500 kV Project
APS
7.N.Gila‐Orchard (previously called TS8) 230 kV Project
APS
8.Scatter Wash 230/69 kV Substation
APS
9.Sun Valley‐Morgan 230 kV Project
APS
10. Bill Durfee (Sundance) 230 kV Substation
BHP
11. Raver 500/230 kV Transformer Addition Project
BPA
12. Front Range Power Plant to Nixon-Kelker (NX-KE) Line #2
CSU
13. Midpoint T232 230/138 kV Transformer Addition Project
IPC
14. Midpoint West Upgrade Project
IPC
15. Casper Substation-Install 230/115 MVA transformer
PAC
16. Mid Valley Substation-Replace 345-138kV, 450 MVA with 700 MVA
Transformers
PAC
17. St. George Substation- Install 345kV/138kV transformer & expand yard
PAC
18. Snow Goose 500/230kV substation
PAC
19. Syracuse –Install 345/138 kV #2 Transformer
PAC
20. Table Mountain 500/230kV substation
PAC
21. Troutdale Substation, Add 3- 230 kV circuit breakers
PAC
22. Union Gap 230/115 kV Transformer Addition
PAC
23. Vantage –Pomona Heights 230 kV line
PAC
24. Whetstone 230/115kV Substation
PAC
25. Planned Generation Waiver – Link to list
PAC
26. Contra Costa sub 230kV Switch Replacement
PG&E
27. Gates No. 2 500/230 kV Transformer
PG&E
28. Kearney-Herndon 230 kV Line Reconductor
PG&E
29. Warnerville-Wilson 230 kV Series Reactor
PG&E
30. Diablo Canyon Voltage Support Project
PG&E
31. Lockeford-Lodi Area 230 kV Development
PG&E
32. Midway-Andrew 230 kV
PG&E
33. Moraga-Potrero 230 kV Project
PG&E
34. Solar Star Generation Interconnection Project
PG&E
35. Stockton Generation Expansion Project
PG&E
36. Blue Lake/Gresham 230 kV Project
PGE
37. Horizon Phase II Project
PGE
38. Port Westward II generation
PGE
39. Laporte 230 kV Substation Expansion
PRPA
40. Boyd 230/115kV Transformer Addition Project
PRPA
* Projects listed as “In service” will be removed from the next issue of this log.
41. Eastside 230 kV Transformer Addition and Line
42. Sycamore-Penasquitos 230 kV Line Project
43. Artesian 230 kV Expansion
44. New 230/69 kV Transformer at Mission
45. Talega Synchronous Condenser
46. SONGSMESA Synchronous Condenser
47. San Luis Rey Synchronous Condenser
48. Shunt Reactor at Suncrest
49. Desert Basin – Pinal Central 230kV line
50. Price Road Corridor Project
51. Rogers – Santan 230kV line
52. Silver King – RS-29 230kV Project
53. New Superior – New Oak Flat 230kV line
54. New Oak Flat – Silver King 230kV line
55. Abel – Pfister - Ball 230kV line
56. Burlington-Lamar 345/230 kV Project
57. JM Schafer-Henry Lake 230 kV Project
* Projects listed as “In service” will be removed from the next issue of this log.
PSE
SDGE
SDGE
SDGE
SDGE
SDGE
SDGE
SDGE
SRP
SRP
SRP
SRP
SRP
SRP
SRP
TSGT
TSGT
Download