Master Development Plan Template A Master Development Plan addresses two or more APDs that share a common drilling plan, Surface Use Plan of Operations, and plans for future development and production. Submitting a Master Development Plan facilitates early planning, orderly development, and the cumulative effects analysis for all the APDs expected to be drilled by an operator in a developing field. Approval of a Master Development Plan serves as approval of all of the APDs submitted with the Plan. Processing of a Master Development Plan follows the procedures in Section III.E.2. of the Oil and Gas Onshore Order No. 1. After the Master Development Plan is approved, subsequent APDs can reference the Master Development Plan and be approved using the NEPA analysis for the Master Development Plan, absent substantial deviation from the Master Development Plan previously analyzed or significant new information relevant to environmental effects. Therefore, an approved Master Development Plan results in timelier processing of subsequent APDs. Each subsequent proposed well must have a survey plat and an APD (Form 3160–3) that references the Master Development Plan and any specific variations for that The following includes a complete Master Development Plan Template. Adhering to this template will allow for efficient processing by the BLM field office and reduce the number deficiencies. Attached are helpful example tables and guidelines for maps. 1. Cover Page a. Title of Master Development Plan b. Date and amendment/version number c. Company contact information 2. Introduction or Executive Summary Could include, but is not limited to, a brief description of the following: a. Project Overview i. Schedule/Duration ii. Development Plan b. Location i. County, Distance from City, General Description c. Objective 3. Proposed Action – A more in-depth description of the project specifically items that may not be included in the Surface Use Plan which may include, but is not limited, to the following: a. A more in-depth description of the project b. Leases and stipulations (prefer inclusion in Appendices) c. Well list (prefer inclusion in Table) i. Well name Master Development Plan Template ii. Legal location (surveyed footages or if unsurveyed most accurate location description ; include bottom hole if known) iii. Type of well(s) – example gas, oil, SWD iv. Type of drilling – horizontal, vertical v. Status – include if the well been surveyed, onsited, APD submitted, etc. d. Facilities – a description of facilities and whether they’ll be centralized or located on well pads e. Table(s) of types of surface disturbance and approximate acreage of disturbance for the following: i. Well pads – estimated number of well pads ii. Access 1. estimated miles of new access roads 2. estimated miles of reconstructed access roads iii. Pipelines 1. estimated miles of surface 2. estimated miles of buried iv. Electric Lines 1. estimated miles of surface 2. estimated miles of buried v. Facilities 1. estimated number of new offsite tank batteries vi. Frac Ponds 1. Estimated number of frac ponds f. Rights-of-way (ROW) i. Existing ROWs that will be utilized for the project ii. New ROWs that will be required (if known) g. Overview maps - If the project area is large, it may be necessary to include one general overview map and several 1:10,000 maps which could include, but is not limited, to the following: i. Leases ii. Proposed Surface Hole Locations iii. Well Bore Path iv. Land status 4. Drilling Use Plan a. Provide estimated tops of all geologic formations – select from the following (Onshore Order 1 requires all groups, formations, members or zones: develop lists i. Back reef ii. Reef iii. Basin 2|Page Master Development Plan Template b. Provide formation for pilot hole so that plug back of pilot hole can be properly evaluated. c. Provide estimated depths and thicknesses of formations, members or zones potentially containing useable water, hydrocarbons and other minerals that operator expects to encounter. These can be marked on the geologic formation list. d. Provide operator’s minimum specifications for blowout prevention equipment and diverter systems. – develop schematics for standard operations (need several types if we are to use different ram configurations 2 or 3 rams, operations with H2S). Onshore Order 2 currently only contains choke manifold schematics. Insert schematics for multi-bowls that have been used. Operator can select or send information on different type. Equipment shall meet Onshore Order 2 requirements. i. Size ii. Pressure rating configuration iii. Testing procedure iv. Closed loop requirements v. Flex hose specifications – test certification, hydrostatic chart, anchors. vi. Type of well head – inspector driven request so that tests can be witnessed. If a multi-bowl e. Provide detailed casing program. i. Size ii. Grade iii. Weight iv. Type of thread and coupling v. Setting depth for each string vi. Condition of casing vii. Minimum design criteria, including loading assumptions and corresponding safety factors for burst, collapse and tension (body yield and joint strength). If operator will use our minimum requirements and loading criteria, their APDs can be processed more quickly. Anytime that we have to evaluate the design criteria, additional time is spent on the review. viii. If tapered string is used, operator shall provide details on each segment of the string. ix. Hole size x. Non-API casing – provide specifications for review. xi. Special casing such as coiled tubing or expandable casing may require additional information. 3|Page Master Development Plan Template f. Provide detailed cement program, which will also provide the information necessary to answer if the resources are adequately protected. i. Amount of cement in sacks for each casing string or stage. ii. Type of cement for each casing string or stage iii. Additives for each cement slurry used. iv. DV tool/ECP setting depths v. Top of cement for each casing string or stage vi. Excess cement for each casing string or stage vii. Cement slurry yield viii. Cement slurry water volume in gallons/sack – request for AFMSS II by National Training Center. ix. Pilot hole plug back procedures with cement details. g. Circulating medium i. Type of circulating medium for each well bore section. ii. Characteristics of each circulating medium proposed. iii. Quantities and types of mud and weighting material to be maintained on location. iv. Describe mud monitoring system. h. Air drilling i. Blooie line details – length, size, location, gas ignition and dust suppression systems ii. Compressor equipment – location and capacity, safety devices, distance from well bore and location on drill site iii. Standby mud or kill fluid – anticipated amounts, types, and other characteristics. Include details on circulating equipment. i. Testing, logging and coring procedures i. List all proposed ii. List details regarding drill stem tests – procedures, equipment, safety measures. j. Expected bottom hole pressure k. Hazards i. Abnormal pressures ii. Abnormal temperatures iii. Potential hazards – lost circulation / H2S – provide mitigation measures. iv. If H2S is a hazard – drilling plan shall be included. If determined that H2S plan is needed and it is not included, operator will be informed in 10 day letter. 4|Page Master Development Plan Template l. Additional information i. Directional/horizontal well – provide directional plan. Watch for stranded 40s. Well must be able to produce from at least one location that would be considered orthodox for a vertical well. Operators usually plan for maximum drainage, so usually the first take point is about 500’ or greater from the end line of the first 40. The plan shall include proposed design, plan view and vertical section in true vertical and measured depths. ii. Coil tubing operations iii. Any other information that will assist in the evaluation of the proposed well. m. Unit well – if not in current UPOD, BLM will hold approved permit. 5. Surface Use Plan a. Existing Roads i. Identify on a map existing access roads planned to be used to access the proposed wells. The map would identify the access route from the proposed wells to a locatable public access point (Example: county road). ii. Maintenance plan for existing roads 1. Plan for Dust Abatement 2. Plan for high traffic litter removal b. New/Reconstructed Roads i. Survey plats (if available) that depicts the proposed new/reconstructed roads to the wells. If not available, provide legible maps of the new/reconstructed roads to the well sites ii. Survey plats/maps must include distances from established roads to the well sites iii. Road design for all new roads – A description that may include diagrams to include the following: 1. Type of Surfacing Material 2. Width of Roadbed 3. Width of Construction Easement 4. Maximum Grade 5. Turnouts 6. Drainage and Ditch Design 7. Crown Design 8. Erosion control (on site/offsite) 9. Location/Size of Proposed Culverts 10. Location of Proposed Cattle Guards 11. Storage Placement of Topsoil 5|Page Master Development Plan Template 12. Revegetation of Disturbed Areas 13. Plan for Dust Abatement c. Well Radius Map i. A map of all wells within one mile radius of all SHL and BHL of proposed wells or the project area (Preference would be an overview map and inclusion in the Appendices); An individual map will be needed with each APD submitted. d. Existing/Proposed Production Facilities i. Describe plans for using existing production facilities 1. Depict location of facilities in a legible map ii. Describe plans for constructing onsite/offsite production facilities 1. Depict location of new onsite/offsite facilities in a legible map (if known) 2. Provide a general diagram of facilities (if available) 3. Survey plats of offsite facilities a. If not available, provide map depicting general location of offsite production facilities iii. Describe plans for pipelines 1. Provide a survey plat/legible map of proposed pipelines depicting the following: a. Starting Points (well sites) b. Ending Points (e.g. production facilities, etc.) 2. General Information for Pipelines: a. Size b. Length c. Working psi (surface pipelines need to be under 125 psi) d. Type (steel, fiberspar, etc.) e. Surface or Buried f. If buried, state width needed construction g. What is being transported h. If pipeline is paralleling existing disturbance (road), state distance from it iv. Electric Lines (prefer inclusion in Table) 1. Provide a survey plat of proposed electric lines depicting the following: a. Overhead/Buried b. Starting Points (Wells Sites) c. Ending Points (Tie-in points or e.g. production facilities etc.) 6|Page Master Development Plan Template d. Span of Poles and Total Distance 2. Voltage (e.g. 3-phase, 480kv) 3. Number of Poles 4. Use of APLIC Standards e. Water i. Water supply information should be shown by quarter/quarter on map or described in writing. ii. Identify the following for all water anticipated for use: 1. Source (Also include water sources for frac operation, if different) a. Well, river, etc. b. 3rd party company to include contact information (Map preferred) 2. Type a. Fresh, salt, or produced, ect. 3. Access Route a. Identify beginning points, ending points, and route to source. b. Identify the route from the source to the frac pond, and identify the route from the frac pond to the proposed well. 4. Transport method for water a. Trucked or pipeline b. Include a map of proposed road/pipeline route. f. Construction Material – a description of the following: i. Character (e.g. caliche, gravel, etc.) ii. Source 1. Material source (e.g. pit) must be shown by quarter/quarter section on a map. 2. If construction material is obtained from the well location, describe the procedures for excavation (e.g. flipping). iii. Intended use 1. What will the material be used for. (May include, but not limited to): a. Fill b. Surface material c. Containment berms 2. Use or storage of excess construction material. g. Waste from drilling the well (Before, during, and after) 7|Page Master Development Plan Template i. Describe methods and locations proposed for safe containment and disposal of each type of waste material: 1. Cuttings (e.g., closed loop or reserve pit) 2. Garbage 3. Salts 4. Chemicals 5. Sewage and gray water ii. Describe plans for eventual disposal of drilling fluids and any produced oil or water recovered. iii. Describe plan for construction and design of reserve pit including lining, fencing, closure, and reclamation, etc. iv. If a reserve pit is proposed, a survey plat will be required. h. Ancillary Facility i. Identify on a map the location and construction methods for all anticipated ancillary facilities (e.g. Staging areas). ii. Must include a survey plat i. Well site i. Provide a diagram of typical rig layout(s) which will include 1. Well pad dimensions 2. Rig components ii. Survey plats, if available, will include the following: 1. North arrow 2. Well pad dimensions 3. Access road entry points 4. Cuts and fills (if needed) 5. Location and orientation of pad 6. Reserve pit 7. Flare pit and blooie line 8. Dikes and ditches 9. Topsoil stockpiles iii. Interim Reclamation 1. If onsite was conducted, depict on a diagram the areas and dimensions of interim reclamation. 2. If onsite was not conducted, describe the typical well pad dimensions after interim reclamation. 3. Describe plans and estimated timeframe for the following: a. Removal of surfacing material b. Reconfiguration of topography c. Redistribution of topsoil d. Re-seeding 8|Page Master Development Plan Template e. Weed control iv. Final Reclamation 1. Describe plans and estimated timeframe for the following: a. Removal of all trash b. Removal of surfacing material c. Reconfiguration of topography d. Redistribution of topsoil e. Re-seeding f. Weed control g. Any other practices necessary to reclaim all disturbed areas, including access roads, electric lines, pipelines, and any other infrastructure associated with the well pad. j. Surface Ownership i. Describe the surface ownership (Federal, state, private, etc.) of the project including: 1. Well location 2. Roads 3. Infrastructure ii. Include the private landowner information: 1. Name 2. Phone Number 3. Address iii. Certify that a copy of the surface use plan was provided to the private landowner or a good faith effort was made to provide the document. iv. Certify that an agreement with the private landowner has been reached or a good faith effort to reach an agreement failed. (If no agreement is reached a bond will be required, see IM #). k. Other (Including, but not limited to the following): i. Spill prevention plans ii. Salt Water Disposal 1. Describe plans for disposal of salt water: a. Location of a disposal well or facility i. Provide name of 3rd party company, if used b. Pipeline route, length, diameter, and dimensions, if used c. Transportation method, if used l. Special design features of well pad (if discussed at POD or onsite then include) i. Fracing 1. Describe the following: 9|Page Master Development Plan Template a. b. c. d. e. f. g. h. i. j. Single location or centralization Portable or pond Permanent or temporary Location Pipeline routes Road Turn arounds Fencing Berms (height, thickness, and depth) if applicable Liners (thickness) if applicable i. Leak detection system, if required k. Bird deterrents l. List of wells to be frac’d i. Associated frac pond if multiple wells are frac’d 10 | P a g e Master Development Plan Template Sample Tables and Appendices Well Table………………………………………………………………………………………………………………….Page 11 Disturbance Table Example………………………………………………………………………………………..Page 12 SUPO Map and Diagram Guide…………………………………………………………………….…Page 13 SUPO Survey Requirements………………………………………………………………………………………...Page 16 11 | P a g e Master Development Plan Template 1. Well Table Example Well Name Section Township Range Well Name Table Quarter/Quarter SHL (if known) BHL (if known) Well Type Drilling Type Status Facilities 2. Well Table Example Table 2. Surface and Bottomhole Locations of Proposed Wells. (GJFO pads shown with gray shading; GSFO pads shown without shading) Lease Proposed Pad Proposed Wells Orchard Unit 31-14 Currently Unleased pending 11/8/07 BLM Lease Sale ON6 (Four wells) Note: 4 wells will be drilled into adjacent existing BLM leases Fee Lease (Surface) OP13 (Four wells) Surface Location Bottomhole Location Lot 3, Section 6, Section 31,T8S R96W 660 FSL 1980 FWL T9S R96W Section 31, T8S R96W Orchard Unit 31-15 660 FSL 1980 FEL Orchard Unit 7-3 Section 7, T9S R96W 660 FNL 1980 FWL Orchard Unit 7-4 Section 7, T9S R96W 660 FNL 660 FWL Federal 18-12 Section 18, T9S R96W 1980 FSL 660 FWL Federal 18-13 Federal 18-14 Federal 19-4 SE¼SE¼, Section 13 T9S R97W Section 18, T9S R96W 660 FSL 660 FWL Section 18, T9S R96W 660 FSL 1980 FWL Section 19, T9S R96W 660 FNL 660 FWL 12 | P a g e Master Development Plan Template 3. Disturbance Table Disturbance Table Number of Wells Pipelines/Electric Roads Lines Miles of New Miles of Miles of Miles of Access Road Reconstructred Surface Buried Roads Number Frac of Ponds Offsite Facilities 4. Disturbance Table Number/Amount Length* Width* Total Acres of Disturbance Well Pads 20 340' 340' 53.08 New Access Roads NA 2.5 miles 14' 4.24 Reconstructed Roads NA 1.2 miles 14' 2.04 Buired Pipelines NA 1,000 feet 30' 0.69 Surface Pipelines NA 3 miles NA NA 5 170' 300' 5.85 NA 1.5 miles 30' 5.45 Frac Ponds 2 300' 300' 4.13 Total - - - 75.48 Type of Disturbance Offsite Production Facilities Electric Lines * indicate measurement 13 | P a g e Master Development Plan Template APD Surface Use Plan of Operations Maps & Diagrams Guide Existing Roads Map Supply a legible map that shows and identifies the proposed well site and access route to the proposed well from a state or county maintained road. Must have: o Title (Exhibit E) o Well Site identified o Existing Road route identified o Aerial map or county road/topo map New or Reconstructed Access Road Map Must be a separate survey plat from the well site plat if the new access road leaves the 600x600 arch area. Survey plat must be zoomed-in to only depict the following: o Well Site o Starting and Ending points o Distances between PI’s (turns) o Show tie-in point to section corner Survey plat must show locations of all proposed road structures (low water crossings, cattle guards, etc.). Upgrading a two-track to a surfaced road and increasing the width of existing lease roads would be considered new access roads. Location of Existing Wells Include a map identifying all known wells (producing, abandoned, SWD, water, etc.) within a one mile radius of the proposed location. Provide a legend with the map. Tank Battery Diagram Onsite Tank Battery Diagram: o Title (Exhibit 6) o Name of Well o North Arrow o Road Entry Point o Dimensions of the Area of Pad to be Reclaimed o Final Pad Dimensions 14 | P a g e Master Development Plan Template o Proposed Production Facilities (Storage Tanks, On-site Pipelines, Separators, Heaters, etc.) Label Facilities and/or Describe in Surface Use Plan of Operations o Ensure Consistency with Well Site Layout Infrastructure Map (Pipeline, Electric line, etc.) Surveyed Map - Power lines, buried lines, lines that cross undisturbed land Survey plat must be zoomed-in to only depict the following: o Well Site o Starting and Ending points o Distances between PI’s (turns) o Show tie-in point to section corner Aerial Map - Surface pipelines that follow existing lease roads Aerial map must include: o Title (Exhibit 3D) o Proposed Well Site o Existing Tank Battery Name o Route of pipeline identified o If pipeline is paralleling existing road not on aerial photo, draw in road o Zoom in to only show project area Well Site Layout Map/Diagram Survey Plat of the well site by a professional surveyor/engineer. o Exterior and interior dimensions of the well pad (includes stingers, flare pit, frac pad needed off the well pad) o Proposed road (if any) o North arrow o Existing structures within the area (labeled) o Topsoil or spoil material stockpile dimensions Supply a diagram of the well site which includes: o Title (Exhibit 5) o Well Name o Well pad edge o Drilling rig components Interim Reclamation Diagram “Production Facility Layout” can be used if the diagram shows reclaimed areas of the pad. Diagram must include: 15 | P a g e Master Development Plan Template o o o o o o Title (Exhibit 6) Name of Well North Arrow Road Entry Point Dimensions of the Area of Pad to be Reclaimed Final Pad Dimensions 16 | P a g e Master Development Plan Template APD Surface Use Plan of Operations Survey Requirements for Oil & Gas Actions 1. Well Sites Staking Requirements a. Exterior pad corners b. Access road if the well pad does not overlap an existing caliche road or well pad. c. Additional disturbances (stingers, frac farm pad, flare pit, etc.) d. Topsoil Stockpile (usually 30’ wide) e. Reserve pit corners (if applicable) i. Reserve pit topsoil stockpile and subsoil stockpile f. 600’ x 600’ Archeological Survey Boundary Survey Plat Requirements a. Plat must have north arrow (Arrow should point to the top of the page) b. Plat must have a reasonable scale (1”:50’ to 1”:100’) c. Depict an access road if the well pad does not overlap an existing caliche road or well pad. i. If road exits page, then provide a separate “Proposed Road Map” zoomed in to show the starting and ending points. d. Clearly label all lines, symbols, features on survey plat i. Especially label the Proposed Well Pad, 600’ x 600’ Archeological Survey Boundary, Proposed Road, etc. ii. All proposed features must be labeled “Proposed” e. Plat must depict all existing features within a 600’ x 600’ area i. Existing features include pipelines, roads, well pads, electric lines, etc. f. Depict dimensions of all proposed disturbances i. Interior dimensions of well pad (distance from wellbore to all four edges of the pad) ii. Exterior dimensions of other disturbances (stinger, topsoil, etc.) g. Depict elevations at all points of the well pad (wellbore, corners, etc.) h. If a reserve pit is proposed, then the following needs to be staked and surveyed: i. Exterior pit dimensions ii. “Topsoil Stockpile” from pit area iii. “Subsoil Stockpile” from excavated material iv. Cut and fill diagram of the final level of pad and bottom of reserve pit 17 | P a g e Master Development Plan Template v. vi. vii. Topography lines (1 – 2 foot intervals) need to be depicted across the well pad Final pad elevation (post construction) depicted Bottom of reserve pit elevation depicted 2. Access Roads Staking Requirements a. Proposed new roads require a centerline flagging with stakes clearly visible from one to the next. i. The road must end at an established road (caliche road, county road, etc.) ii. Two track roads are not established roads b. All proposed locations for road structures must be clearly staked. i. Low water crossings ii. Cattle guards iii. Culverts iv. Center and end of lead-off ditches v. Center of turn outs (Turn outs are located in 1,000 ft. intervals. and on blind curves.) Survey Plat Requirements a. Plat must have north arrow (Arrow should point to the top of the page) b. Plat must have a reasonable scale (Zoomed in to only contain the starting and ending points of the access road.) i. If the road is long, then also provide segments of the road on separate plats c. Plat must depict the entire access road from established/maintained roads to the drill site d. Plat must depict distances of every segment of the access road e. Plat must state the maximum grade of the access road f. Two track roads that need to be upgraded to oil and gas roads need to be depicted as a proposed new road or proposed upgraded road. g. Depict an access road if the well pad does not overlap an existing caliche road or well pad. h. Typical access road driving surfaces do not exceed 14 feet and the allowable disturbance area to construct the road does not exceed 25 feet. 3. Other Infrastructure Staking Requirements 18 | P a g e Master Development Plan Template a. The following infrastructure must be survey staked and platted i. Electric Lines ii. Buried Pipelines iii. Other Buried Infrastructure iv. Cross-Country Infrastructure (surface pipeline, etc.) v. Other ground disturbing activities such as frac ponds, pads, etc. Survey Plat Requirements a. Survey plats must clearly depict the starting and ending points of the infrastructure b. Plat must have a reasonable scale (Zoomed in to only contain the starting and ending points.) c. Proposed fence crossings must be depicted d. Disturbance area must be defined e. Show detailed views if necessary Other activities may be depicted in detail on an aerial map or diagram when submitted by the operator in an appropriate application to the Carlsbad Field Office. 19 | P a g e