SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED 19-13-65/A, VidyutNilayam, Srinivasapuram, Tirupati Aggregate Revenue Requirement and Retail supply business and Retail Supply Tariffs for the FY 2016-17 18th January, 2016 APSPDCL Page 0 Table of Contents 1 Introduction 2 1.1 1.2 Filings based on Multi-Year Tariff (MYT) Principles Filing Contents 2 2 2 Analysis of expected performance for Current Year 2015-16 for Retail Supply Business 4 2.1 2.2 2.3 Introduction Operating Performance Financial Performance 3 Power Purchase for Current Year H2 FY 15-16 and Ensuing Year FY 16-17 8 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Basis of estimation of quantity and cost of Power Purchase PP allocation: Installed Capacity of Major Generating Stations Basis of estimation of power availability for H2 FY 2015-16 and FY 2016-17 Power Purchase Cost Energy Requirement Summary of Power Purchase for Current Year H2 FY 15-16 and Ensuing year FY 16-17 8 8 9 18 29 49 4 Losses 52 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 DISCOM losses TRANSCO losses Losses external to APTRANSCO system APTransco Charges PGCIL and ULDC Charges SLDC Charges Distribution Costs (Rs. in Crores) Interest on Consumer Security Deposits Supply Margin Other Costs Summary of ARR 52 52 52 53 53 54 55 55 56 56 57 5 Revenue Projections 58 5.1 5.2 5.3 Sales Forecast Revenue from Current Tariffs Detailed category wise Revenue computation 58 80 83 6 7 Performance Parameters Retail Supply Business True-up for FY 2014-15 & FY 2015-16 93 103 7.1 7.2 Filing for True-up by the Distribution Licensee True-up of Aggregate Revenue Requirements components & Gap from Retail Business for FY 2014-15 & FY 2015-16 Prayer Detailed Tariff Proposal for Retail Supply Business for FY 2016-17 Other Tariff Proposals 103 7.3 8 9 4 4 6 50 106 107 108 124 COS RSF APSPDCL Page 1 Introduction 1.1 Filings based on Multi-Year Tariff (MYT) Principles The Andhra Pradesh Electricity Regulatory Commission framed the “Terms and Conditions for determination of Tariff for Wheeling and retail supply of electricity” Regulation 4 of 2005 (“Regulation”), lays down the principles for determination of Aggregate Revenue Requirement (ARR) for (a) Distribution Business and (b) Retail Supply Business of the licensees. The ARR so determined for each of the businesses will form the basis for fixation of charges for wheeling and for retail sale of electricity. In the Regulation, the Commission has also laid down the procedures for filing under multi-year tariff principles. The multi-year period is defined as the Control Period and the first Control Period is defined as the three year period starting from financial year 2006-07 and continuing till the end of financial year 2008-09. The second control period was defined as the five year period starting from FY 2009-10 to 2013-14. The current filing pertains to the third Control Period (FY 2014-15 to FY 2018-19). The Commission has specified in Para 6.2 of the Regulation the following procedure for ARR filing for the distribution and retail supply business: “The ARR filing for the Distribution business shall be for the entire Control Period. For the Retail Supply business the ARR filing will be on annual basis …...”. The current filing follows the principles laid down under this Regulation for determination of the ARR for the retail supply business for the year 2016-17, which is the Third year of the Third Control Period. 1.2 Filing Contents The filing is structured in the following way: Section 2 provides analysis of expected performance for FY 2015-16 for Retail supply Business comprising: APSPDCL Operating Performance Financial Performance Page 2 A brief analysis of the financial and operational performance of the licensee during FY 2014-15 and FY 2015-16 (with projections for second half of FY) are given. Expenditure Projections o Power Purchase Cost Power Purchase and Procurement Cost o Transmission Charges o PGCIL & ULDC Charges o SLDC Charges o Distribution Cost o Interest on Consumer Security Deposits o Supply Margin o Other Costs o Aggregate Revenue Requirement for Retail Supply Business Revenue Projections o o o o Sales Forecast Revenue from Current Tariffs Non-tariff Income at Current Charges Revenue at Current Tariffs and Charges Revenue Gap o Revenue Deficit / Surplus at Current Tariff and Charges o Proposals to handle the Deficit / Surplus The sales forecast has been used to determine the revenue from tariff for retail sale of electricity for the third year of the third control period and the energy input required for meeting the demand. The power procurement plan is based on the availability of the generation sources during FY 2016-17, cost of procurement (fixed, variable and others) and the merit order dispatch of various sources to meet the demand expected during various months. Due to reorganization of the State of Andhra Pradesh, two districts i.e., Anantapur & Kurnool districts were merged into APSPDCL w.e.f 02-06-2014. In this context, for FY 2013-14 and FY 2014-15 (during Apr & May,2014) all the figures / data considered are actuals and pertains to six districts of APSPDCL (viz., Krishna, Guntur, Prakasam, SPSR Nellore, Chittoor & Kadapa). And from June, 2014 to September, 2015 all the figures considered are actuals and pertains to entire eight districts of APSPDCL including newly added Anantapur & Kurnool districts. From October, 2015 onwards the estimated / projected figures are considered for entire 8 districts of the licensee. APSPDCL Page 3 2 Analysis of expected performance for Current Year 2015-16 for Retail Supply Business 2.1 Introduction This chapter analyses the performance of the licensee during the Current Year as compared to the previous year. Only the key operating and financial parameters have been considered for this analysis. 2.2 Operating Performance Energy Balance 2014-15 Particulars 2015-16 Actuals MU 18354.75 8006.78 26361.53 Metered Sales LT Agricultural Sales Total Sales EHT Sales APERC Order % 62.43% 27.24% 89.67% 3490.59 Discom Input (excl EHT sales) 25907.65 Distribution losses (exl EHT sales) MU 22856.34 8020.16 30876.50 % 67.55% 23.70% 91.25% 4725.92 88.13% 29398.24 100.00% 29112.76 86.03% 28727.68 10.17% 33838.68 100.00% 10.33% Loss Including EHT Sales % MU 21091.83 8392.70 29484.53 % 64.87% 25.81% 90.69% 3783.85 11.72% Discom Input (excl EHT losses) Present Estimate 8.75% 88.36% 10.54% 32511.53 100.00% 9.31% Distribution Loss: Actual Year 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 (H1) APSPDCL Excl. EHT Incl. EHT 14.03 13.37 12.53 11.87 11.84 11.72 11.58 12.98 12.21 11.29 10.71 10.68 10.33 9.10 No. of 11 KV T&MHQ feeders for which energy audit done 823 853 866 966 1024 1348 1377 11 KV 2 MVAR capacitor banks added to the system 122 136 193 35 75 7 Additional 33/11 KV substations charged 90 13 67 128 208 75 7 Page 4 As seen from the above table, the actual losses for the FY 2014-15 are 10.33% and reduced compared to previous year loss of 10.68%. However it is expected to reduce the losses further with the implementation of the following measures. Strict implementation of Restriction and Control measures to ensure the assured number of hours of supply to agricultural sector. Reduction of both technical and commercial losses by vigorously conducting 11 KV feeder wise energy audits around 1377 Nos. feeders in the company. Erection of additional substations, DTRs, 11KV capacitor banks and bifurcation of feeders, etc., HVDS for agricultural sector Utilisation of latest technology in metering, billing etc., During the year 2011-12, only 866 Nos. 11 KV Town & MHQ feeders were considered for energy audit where as during the year 2014-15, 1348 Nos. feeders are available in E-AUDIT for which energy audit is done on regular basis at corporate office level. 75 Nos. additional 11 KV 2 MVAR capacitor banks proposed during the year 2014-15 and completed. For the year 2014-15, 75 Nos. additional 33/11 KV sub-stations were charged and for the year 2015-16, 70 Nos. additional 33/11 KV sub-stations are proposed out of this 7 Nos. were already charged to reduce over loaded 33 KV & 11 KV lines and to maintain good voltage profiles at the consumers end. Metered Sales As can be seen from the table above, in 2014-15, the percentage of metered sales is 62.43 % as aginst 62.00% during 2013-14. APSPDCL Page 5 The total load curtailment (due to Load relief) during FY 2014-15 is 716.26 MU. In 2015-16, the metered sales are expected to increase by 2737.08 MU over 2014-15 levels, which is 2.44% increase. Agricultural Sales In the previous year 2014-15 the actual Agriculture Consumption is 8006.78 MU. In the current year 2015-16 during the first half of the year, the agriculture consumption is 3713 MU and projection for the entire year is 8393 MU, which is 373 MU excess over the approved agricultural sales (2.11%). The increase in the sales is mainly due to increase in the no.of consumers. 2.3 Financial Performance The following table provides an overview of APSPDCL’s financial performance for the current year and compares it with the APERC orders: Particulars 2015-16 APERC Present Estimate Total Expenditure (A) 654.10 836.12 21.05 26.91 Distribution Cost 2153.24 2,153.24 PGCIL Expenses 211.10 211.10 ULDC Expenses 9.71 9.71 12672.00 13,468.64 147.09 565.53 13.13 142.12 38.12 Total Revenue Requirement (C=A+B) 16446.95 16,899.09 Total Revenue Earned Tariff Income Non-tariff Income Revenue from Trading Surplus/ (Gap) Subsidy Net Regulatory Gap 14128.50 12,193.48 12,117.14 76.34 0.00 -4,705.61 Transmission Cost SLDC Cost Power purchase Interest on CSD Other Costs, if any Add: Supply Margin (B) APSPDCL 14128.50 0.00 2318.45 2318.45 0.00 13.13 2,318.45 -2,387.16 Page 6 Revenues from sale of electricity: The net revenue (excl. NTI) for FY 2015-16 is expected to be Rs 12117.14 Crores. For the key categories, the licensee has estimated the revenue as below: 2014-15 Category Actuals 2015-16 APERC Present Target estimate HT Industrial Non-Industrial Aviation Irrigation &Agr. Railway Traction Colony Lightning RESCO's Temporary HT Total LT Domestic Non-Domestic Industrial Cottage Industries Agricultural Local Bodies General Purpose Temporary LT Total Grand Total (LT+HT) 4440.79 478.74 14.42 280.40 475.68 20.07 9.67 0.00 5719.77 7404.24 654.69 73.78 203.16 558.25 28.43 9.33 15.00 8946.88 5184.09 587.69 17.71 294.62 513.60 24.32 7.25 0.00 6629.27 2103.90 1183.26 835.79 12.51 67.56 257.97 52.05 14.69 4527.73 2393.41 1340.12 971.83 13.75 99.13 303.70 58.65 1.03 5181.62 2537.19 1465.43 1043.78 15.54 59.10 289.88 61.45 15.50 5487.86 10247.49 14128.50 12117.14 The actual revenue during FY 2014-15 is Rs. 10247.49 crores excluding non-tariff income. The NTI during FY 2014-15 is Rs. 73.49 crores. During FY 2015-16, the estimated revenue from sale of power (exclusive of Non-tariff income) is Rs. 12117.14 crores. The expected NTI during FY 2015-16 is Rs. 76.34 crores. The estimated revenue from sale of power (inclusive of Non-tariff income) is Rs. 12193.48 crores. APSPDCL Page 7 3 3.1 Power Purchase for Current Year H2 FY 15-16 and Ensuing Year FY 16-17 Basis of estimation of quantity and cost of Power Purchase This section discusses the methodology and assumptions considered for estimating the quantum and corresponding cost of power purchase of the Licensee for the second half of the Financial Year ending March 31, 2016 and for the Financial Year ending March 31, 2017. As per section 92 read with the Twelfth Schedule of the Andhra Pradesh Reorganization Act, 2014 for bifurcation of united Andhra Pradesh (Central Act No. 6 of 2014, dated 01.03.2014), the districts of Anantapur and Kurnool which was within the jurisdiction of the erstwhile Andhra Pradesh Central Power Distribution Company Ltd. (APCPDCL, now Southern Power Distribution Company of Telangana Limited (TSSPDCL)) was reassigned to the Andhra Pradesh Southern Power Distribution Company Ltd. (APSPDCL). The proportionate share of power was transferred from the allocated share of the erstwhile APCPDCL to APSPDCL. Before the bifurcation of united Andhra Pradesh, with the implementation of MultiBuyer Model (MBM) in the state from June 9, 2005, each of the four Discoms of united Andhra Pradesh had been allocated a certain share of the generating stations contracted by APTRANSCO. According to G.O.Ms. No.20 (dated 08.05.2014), based on the last 5 years’ average consumption of Anantapur and Kurnool districts, 17.45% of power earlier allocated to the erstwhile APCPDCL has to be transferred to APSPDCL. Power allocation percentages for Andhra Pradesh Discoms and Telangana Discoms have been modified accordingly. Andhra Pradesh has been allocated a percentage of 46.11% of the erstwhile Andhra Pradesh share. The revised power allocation percentages for the two Discoms of Andhra Pradesh (APEPDCL and APSPDCL) are mentioned below. 3.2 PP allocation: Energy availability for upcoming GENCO (APGENCO and TSGENCO) stations - KTPP Stage II, DSTPP Stages I & II has been considered as per geographical location. Power from GENCO (APGENCO and TSGENCO) hydel stations have been allocated based on their geographical location. Non-conventional Energy sources have been allocated to the DISCOMs based on their geographical presence/location. APSPDCL Page 8 The two mini-power plants LVS and Srivathsa have been allocated to APEPDCL. Entire energy available from Hinduja thermal power plant has been allocated to Andhra Pradesh. Allocation percentage for existing APGENCO thermal stations, CGS stations and Gas IPPs is 46.11% of united AP share (based on the last 5 years’ average consumption of Anantapur and Kurnool districts). The allocation percentages (as on 02.06.2014 as per G.O. Ms. No. 20) for the two Discoms of Andhra Pradesh (among all the 4 Discoms of erstwhile Andhra Pradesh) for GENCO thermal stations and all the other sources(Excluding Bilateral Purchases) has been doneas follows: S. No. Name of the Distribution Company Allocation Percentage 1 APEPDCL 15.80 % 2 APSPDCL 30.31 % The energy deficit in each Discom if any is then met through procurement through bilateral sources Month-wise surplus has been estimated based on the availability and requirement. A part of this surplus is assumed to be sold through bilateral contracts and a part through open market. In the following paragraphs, the capacities and availabilities of all the generating sources have been described. The actual energy availability in MU for each Discom has been projected based on the above allocation principles. 3.3 Installed Capacity of Major Generating Stations 3.3.1 GENCO (ANDHRA PRADESH GENCO & TELENGANA STATE GENCO) The table below shows the projected capacities of the Thermal and Hydel generating stations of GENCO including the share in the interstate projects. APSPDCL Page 9 3.3.1.1 APGENCO Energy allocation for existing APGENCO thermal stations has been considered as 46.11% of united Andhra Pradesh share as per G.O. Ms. No. 20.while 100% has been considered from Damodaram Sanjeevaiah TPP I & II. For APGENCO Hydel stations allocation is as per geographical location (100%). Allocation for interstate hydel projects have been taken as per G.O.Ms. No. 20. Source Projected erstwhile AP share Projected AP share (MW) (MW) THERMAL Dr. NTTPS ( I, II, III) Dr. NTTPS – IV 1,260 500 581 231 420 420 210 800 800 194 194 97 800 800 4,410 2,896 Machkund, Orissa (AP share 70%) 84 39 T.B. Station, Karnataka (AP share 58 27 State 80%) projects: Donkarayi Upper Sileru Lower Sileru Srisailam right bank PH 25 240 460 770 25 240 460 770 Nagarjuna Sagar right canal PH PABM Mini hydro Nagarjuna Sagar Tail Pond 90 20 1 50 90 20 1 50 1,798 6,208 1,721 4,617 RTPP-I RTPP-II RTPP- III Damodaram Sanjeevaiah TPP I Damodaram Sanjeevaiah TPP II TOTAL THERMAL HYDEL Interstate projects: TOTAL HYDEL TOTAL APGENCO APSPDCL Page 10 3.3.1.2 TSGENCO Energy allocation for existing TSGENCO stations has been considered as 46.11% of united Andhra Pradesh share as per G.O. Ms. No. 20. No availability considered from KTPP Stage II. For TSGENCO hydel stations allocation is as per geographical location (0%). Source Projected erstwhile AP Projected AP share share (MW) (MW) Kothagudem-(A,B,C) Kothagudem-D Kothagudem-VI 720 500 500 332 231 231 Ramagundam-B 63 29 KTPP -I 500 THERMAL TOTAL THERMAL 2,283 231 1,054 TOTAL TSGENCO 2,283 1,054 3.3.2 CENTRAL GENERATING STATIONS AP Discoms have Power Purchase Agreements with Central Generating Stations to purchase power from NTPC (SR), NTPC (SR) Stage-III, NTPC -Talcher-II, NTPC Simhadri-I &II, Vallur (JV) Power Project, Tuticorin Thermal Power Plant (upcoming), Neyveli Lignite Corporation Ltd (“NLC”), Madras Atomic Power Station (“MAPS”) and Kaiga Atomic Power Station (“KAPS”). Allocation percentage for CGS stations has been considered as 46.11% of united AP share (based on the last 5 years’ average consumption of Anantapur and Kurnool districts as per G.O.Ms. No. 20). APSPDCL Page 11 Name of the Station Total Projected erstwhile Installed AP share Projected AP share Capacity MW MW % (of MW % (of Total Total Installed Installed Capacity) Capacity) NTPC-(SR) Ramagundam I & 2,100 679 32.32 313 14.91 500 170 33.92 78 15.68 NTPC-Talcher-II 2,000 400 20.01 184 9.22 NTPC Simhadri StageI 1,000 1,000 100.00 461 46.11 NTPC Simhadri StageII 1,000 460 46.01 212 21.21 NLC TS II Stage-I 630 116 18.33 53 8.49 NLC TS II Stage-II 840 204 24.33 94 11.20 NPC-MAPS 440 44 9.90 20 4.61 NPC-Kaiga 1 & 2 440 136 30.82 63 14.25 NPC-Kaiga 3 & 4 440 144 32.64 66 15.09 1,500 221 14.75 102 6.79 NLC-TNPL Tuticorin* 1,000 255 25.46 118 11.76 NTPC-Kudgi* 2,400 419 17.5 201 8.36 TOTAL CGS 14,290 3,829 II NTPC-(SR) Stage – Ramagundam- III Vallur (JV) NTPC with TANGEDCO 1,965 * 1000 MW (2x500 MW) Tuticorin Thermal Power Station, is a Joint Venture Company formed between Neyveli Lignite Corporation Limited (NLC) and Tamil Nadu Electricity Board (TNEB) with a equity ratio of 89 : 11 respectively. Minister of Power, Government of India has allocated 254.6 MW as firm power to erstwhile Andhra Pradesh (117.40 MW for residuary Andhra Pradesh). Accordingly, APDISCOMs have signed a Power Purchase APSPDCL Page 12 Agreement with NLC-Tamil Nadu Power Limited (A Joint Venture Company) on 30.11.2010. 1st Unit of 500 MW was pronounced COD on 18.6.2015 and Unit 2 on 29.8.2015. ** 2400 MW (3x800 MW) Thermal Power Project is being setting up by M/s. NTPC Ltd at Kudgi, Karnataka. The then APDiscoms have signed a PPA with NTPC on 23.09.2010. Power shall be allocated as per the Gadgil formula. However, the same is yet to allocate by MoP, GoI. Tentatively, as per the Gadgil formula, the residuary A.P may get 8.36% power i.e. 200.62 MW from the said Power Project. As informed by NTPC, the scheduled COD of 1st unit (800 MW) in September 2016 and the scheduled COD of 2nd (800 MW) in March 2017. 3.3.3 INDEPENDENT POWER PRODUCERS (IPPs) The following IPPs are under commercial operation in the Andhra Pradesh: a) 216.82 MW gas-based plant at Jegurupadu by GVK Industries (“GVK”); Up on the expiry of PPA on 20.06.2015, APDISCOMs have issued Buyout notice to M/s GVK-I and M/s GVK-I is scheduling entire power only to APDISCOMs w.e.f. 20.06.2015. b) 208.31 MW gas-based plant at Kakinada by Spectrum Power Generation Ltd., c) 355 MW (ISO) gas-based plant at Vijayawada by Lanco Kondapalli Power Ltd (“Lanco Kondapalli”); the present PPA gets expired by 01.01.2016 and the negotiations for renewal of PPA is under progress. d) 220 MW gas based plant at Samalkota, East Godavari District by M/s. Reliance Power Ltd. (formerly M/s. BSES). The Plant Load Factor (PLF) of above four IPPs has been considered at 40% for the second half of FY 15-16 and FY16-17 Energy allocation for gas-based IPPs has been taken as 46.11% of united Andhra Pradesh share as per G.O. Ms. No. 20. Projected erstwhile Andhra Pradesh share and residuary Andhra Pradesh share are as mentioned below. APSPDCL Page 13 Source Projected erstwhile AP share Projected AP share (MW) (MW) GVK Spectrum Lanco Kondapalli (Gas) Reliance BSES TOTAL GAS-BASED IPPs 216 96 164 101 577 216 208 355 220 999 GVK Extension (220 MW), GMR Vemagiri (370 MW), Gowthami (464 MW), and Konaseema (444.08 MW) are the new IPPs which have been commissioned in XIth Five Year Plan. Project Name Capacity Installed corresponding Capacity to 50% PLF (MW) (MW) AP share under e-bid RLNG scheme for FY 201516(H2) AP share under e-bid RLNG scheme for FY 2016-17 Remarks 46.11% as GVK Extension (IPP) 220.00 110 50.72 50.72 per G.O.Ms.No 20 GMR Vemagiri 370.00 185 85.30 85.30 -do- Gautami (IPP) 464.00 232 0 106.98 -do- Konaseema (IPP) 444.08 222 102.38 102.38 -do- LKPL (MPP)* 1108.00 554 277 277 --- GREL (MPP)** 768.00 384 384 384 ---- (IPP) * M/s LKPL offered 50 % of capacity under e-bid RLNG to AP during the period from 01.10.2015 to31.03.2016. It is assumed that M/s LKPL will offer 50 % of capacity under ebid RLNG to AP during the period from 01.04.2016 to 31.03.2017 also. ** M/s GREL offered 100 % of capacity under e-bid RLNG to AP during the period from 01.10.2015 to 31.03.2016. It is assumed that M/s GREL will offer 100 % of capacity under e-bid RLNG to AP during the period from 01.04.2016 to 31.03.2017 also. APSPDCL Page 14 The Natural gas supplies from RIL KG D-6 fields to the aforesaid IPPs became zero from 01.03.2013 onwards hence there is no generation under long term PPA. The availability is subject to natural gas supply from M/s RIL. Energy availability has not been considered from these IPPs in the absence of RIL D-6 gas supplies. 3.3.4 AP Gas Power Corporation Ltd (“APGPCL”): Joint Sector APGPCL is a joint sector gas-based power project. The allocation of power from this project is in proportion to the equity share capital of participating industries. The total installed capacity of the project along with the DISCOMs share is as given below: Source Installed Capacity (MW) Stage I Stage II Total 100 172 272 3.3.5 Projected erstwhile AP Share (MW) 16 43 59 Erstwhile AP Share (%) Projected AP Share (MW) AP Share (%) 16% 25% 22% 7 20 27 7% 12% 10% Non-Conventional Energy (NCE) Sources The installed capacities of NCE projects in Andhra Pradesh projected for FY 2015-16 2nd half and FY 2016-17 are as given below. NCE based projects have been allocated to the AP Discoms based on their geographical presence/location (NCE projects have signed PPAs with Discoms where they are located. Hence the entire power is allocated to that Discom.) APSPDCL Page 15 Type of Project Bio Mass Power Projects including Co-gen Bagasse Cogeneration Projects. Wind Power Projects Mini Hydel Power Projects Industrial Waste Based Power Projects Municipal Waste Based Power Projects NCL Energy Ltd. (TB Dam) Solar Power Projects Solar Parks Total 3.3.6 Projected AP Share (MW) FY 2015-16 143.75 105.20 914.25 48.50 21.66 6.14 16.5 135 0 1391 Projected AP Share (MW) FY 2016-17 141 105.20 1414.25 62.50 21.66 6.14 16.5 635 250 2652.25 Mini-Power Plants APTRANSCO had entered into a Power Purchase Agreement with LVS (36.8 MW) on 3rd January, 2009 for purchase of power in compliance with the Orders issued by Hon’ble Supreme Court and had entered into another Power Purchase Agreement with Srivathsa (17.20 MW)powerplant. These projects have been allocated completely to APEPDCL. 3.3.7 HNPCL GoAP directed the then APDiscoms as the successor entities of erstwhile APSEB to enter into a continuation agreement to the PPA dated 15.04.1998 which was entered by erstwhile APSEB with HNPCL. As such, a memorandum of agreement (MoA) was entered between the then APDiscoms and HNPCL on 17.05.2013. As per the directions of GoAP and MoA dated 17.05.2013, the preparation of amendments to the PPA dated 15.04.1998 is under finalization and it would be signed, shortly, by two DISCOMs of residuary A.P. 1st unit (520 MW) was synchronized on 06.12.2015 and the 2nd unit (520 MW) may be synchronized in June 2016. As per the projections in ARR for FY 2015-16 filed by APDiscoms and the same was approved by APERC in its Retail Tariff Order for FY 2015-16, the entire energy available from HNPCL Thermal Power Plant has been considered for Andhra Pradesh. APSPDCL Page 16 3.3.8 Long Term andMedium Term Purchases 3.3.8.1 LongTerm – Thermal PowerTech Corporation India Limited APDiscoms and Telangana Discoms have signed a Power Purchase Agreement with M/s. Thermal PowerTech Corporation India Limited (TPCIL) for a contracted capacity of 500 MW under long term basis through Case-I bidding route for a period of 25 years. APDiscoms have been allocated a share of 46.11% (as per G.O. Ms. No. 20) i.e. 231 MW out of the total contracted capacity of 500 MW. Variable cost per unit of Rs.1.76/kWh and fixed cost of Rs. 289.30 Crs have been considered for FY 2015-16. Variable Cost of Rs.1.81/kWh and fixed cost of Rs.302.82 Crs have been considered for FY 16-17. As per the PPA, the scheduled date of delivery for supply of 500 MW to APDiscoms and Telangana Discoms is 01.04.2017. However, TPCIL has requested for preponement of schedule delivery date from 01.04.2017 to 01.04.2015 since early commission of their units (2x660 MW) and the same is under consideration by AP Discoms. 3.3.8.2 Long Term – 1000MW DBFOO Bidding AP DISCOMS are planning to procure electricity of 1000MW on long term basis from Power Stations on BDFOO basis and the bidding process is under progress. The energy from these sources is considered from June 2016 at an energy availability of 90% PLF. 3.3.8.3 Medium Term – KSK Mahanadi In the recently concluded medium term bidding for 3 years i.e. up to 15th June 2016, the AP & Telangana Discoms have signed the Power Purchase Agreement with KSK Mahanadi for 400 MW and are availing power since 14.08.2013. APDiscoms have been allocated a share of 46.11% (as per G.O. Ms. No. 20) i.e. 184 MW out of the total contracted capacity of 400 MW. AP DISCOMS have signed the Power Purchase Agreement with KSK Mahanadi for 400MW for 100% of its share from 15th June 2016 to March 31st 2017. APERC has APSPDCL Page 17 accorded approval for the plan under Agreement with M/s KSK Mahanadi vide O.P. No.03 of 2015 on 19.08.2015. The licensees had also signed a PPA with Corporate Power for 150 MW, but the energy would not be available from the source due to non-allocation of transmission capacity by PGCIL. 3.3.9 Short Term and Bilateral/ Inter-State purchases 3.3.9.1 Bilateral Purchases The licenseehas placed order of an average of 800MW to procure short term power from June 2015 to May 2016 to bridge the power deficit. 3.4 Basis of estimation of power availability for H2 FY 2015-16 and FY 2016-17 3.4.1 3.4.1.1 GENCO (ANDHRA PRADESH GENCO & TELENGANA STATE GENCO) Thermal Energy: The Energy availability for H2 of FY 2015-16 has been projected based on the actual performance of the plants up to September 2015 and projected performance estimated by GENCO from October 2015 to March 2016. For FY 2016-17, the energy availability has been projected based on the projected performance estimated by GENCO and maintenance schedules of the plants. The following GENCO plants have been commissioned/ assumed to be commissioned in FY 2015-16 and FY 2016-17: 1. The COD of Damodaram Sanjeevaiah Thermal power plant unit I (APGENCO, 800 MW) was declared on 05.02.2015. 2. The COD of Damodaram Sanjeevaiah Thermal power plant unit II (APGENCO, 800 MW) is was declared on 24.08.2015. 3. KTPP Stage-II (TSGENCO, 600 MW) is expected to be commissioned in December 2015 APSPDCL Page 18 GENCO Thermal (Net Energy Availability- MUs) S. No. Station Name H2 FY 2015-16 FY 20156-167 APGENCO 1 Dr NTTPS-I,II,III 1857.64 3709.03 2 Dr NTTPS-IV 658.97 1494.52 3 RTPP-I 617.52 1235.04 4 RTPP-II 617.52 1235.04 5 RTPP-III 308.76 617.52 2614.48 5242.66 2614.48 5242.66 Total APGENCO 9289.38 18776.45 1 KTPS-(A,B,C) 1024.37 2084.55 2 KTPS-D 735.14 1470.28 3 KTPS-VI 747.26 1494.52 4 RTS-B 91.89 183.79 5 KTPP-I 739.30 1494.52 Total TSGENCO 3337.97 6727.65 Total 12627.35 25504.11 6 7 Damodaram Sanjeevaiah Thermal Station-I Damodaram Sanjeevaiah Thermal Station-II TSGENCO 3.4.1.2 Hydro Energy: The hydro energy availability for H2 FY 2015-16 is expected to be 942.37MU and 3241.44 MU for FY 2016-17. Energy allocation for hydel stations is based on geographical location and therefore, energy availability from TS GENCO stations has not been considered. It has been observed over the past few years that the actual availability from hydel stations has been consistently lower than the value approved in the Tariff Orders issued by APERC. The table below shows the actual hydro energy availability from FY 2002-03 to FY APSPDCL Page 19 2014-15 (for erstwhile AP). In this regard, the hydel projections have been considered to be similar to the 10 year average availability. Year 2002-03 Approved hydro energy availability in MU (As per Tariff Orders)1 6,999 Actual hydro energy availability in MU1 3,337 Variation between Approved and Actual hydro energy availability (%) -52% 2003-04 6,757 2,959 -56% 2004-05 6,423 5,267 -18% 2005-06 5,979 7,873 32% 2006-07 7,586 9,328 23% 2007-08 8,592 9,566 11% 2008-09 9,046 7,729 -15% 2009-10 8,969 5,499 -39% 2010-11 7,662 6,751 -12% 2011-12 8238 6221 -24% 2012-13 6407 3171 -50% 2013-14 7057 6761 -36.55 The following table shows the station-wise projected availability for H2 FY 2015-16 and FY 2016-17: APGENCO Hydel ( Net Energy Availability-MUs) H2 FY 2015- S. No. Station Name 1 MACHKUND PH AP Share 65.19 153.89 2 TUNGBHADRA PH AP Share 37.80 66.39 3 USL 207.90 445.38 4 LSR 501.93 1103.60 5 DONKARAYI 30.71 98.30 6 SSLM (Right Bank) 72.29 1045.25 16 FY 2016-17 1 For erstwhile AP APSPDCL Page 20 APGENCO Hydel ( Net Energy Availability-MUs) S. No. Station Name 7 NSRCPH 8 PABM 9 Mini hydro(Chettipeta) 10 16 FY 2016-17 12.59 146.76 2.20 5.98 1.78 2.62 9.98 173.25 942.37 3241.44 Nagarjuna sagar tail pond dam PH Total 3.4.2 H2 FY 2015- CENTRAL GENERATION STATIONS The energy availability for H2 of FY 2015-16 has been projected based on the actual performance upto August/September 2015 for CGS. For FY 16-17, the energy availability has been projected based on the projected performance estimated by CGS and maintenance schedules of the plants and also based on the details of energy availabilities received from respective generators. The Vallur Thermal Power Plant which is under generation (present capacity of 1,000 MW) has a total installed capacity of 1,500 MW. In this project, erstwhile AP had a share of 14.75%. The COD of the second unit of Vallur Power Project was 25.08.2013. Capacity addition from Tuticorin Thermal Power Plant Station is 118 MW (as per AP share).COD for unit 1 has been considered to be in February2015 and for unit 2 to be in March 2015. The Kudgi Thermal Power Plant has a total installed capacity of 2,400 MW. In this project, the residuary A.P is likely to get a share of 8.36% i.e. 200.62 MW. Now, the Project is in advanced stage of construction. The anticipated COD of first unit of Kudgi Power Project will achieve in September 2016 and second unit in March 2017. APSPDCL Page 21 Energy availability projections from CGS for H2 FY 2015-16 and FY 2016-17 are tabulated below: Central Generating Stations ( Net Energy Availability - MUs ) S. No. Station Name H2 FY 2015-16 FY 2016-17 1 NTPC-(SR) Ramagundam I & II 1130 2228 2 NTPC-(SR) Stage – Ramagundam- III 293 521 3 NTPC-Talcher-II 705 1361 4 NTPC- Simhadri Stage-I 1487 3129 5 NTPC- Simhadri Stage –II (Unit 3 &4) 692 1336 5 NLC TS II Stage-I 120 297 6 NLC TS II Stage-II 269 503 7 NPC-MAPS 55 120 8 NPC-Kaiga 1 & 2 193 403 9 NPC-Kaiga 3 & 4 202 392 11 Bundled Power under JVNSM 182 354 10 Vallur (JV) NTPC with TANGEDCO 277 526 11 Tuticorin Thermal Power Plant 166 961 12 NTPC - Kudigi 0 306 5707 12436 TOTAL 3.4.3 APGPCL The projections for APGPCL – I and APGPCL – II are as shown below. The actuals till September, 2015 have been factored while estimating energy availability for H2 FY 2015-16.40% PLF has been assumed for these plants for FY 2016-17 APGPCL Allocated Capacity (Energy Availability- MUs ) S. No. APSPDCL Station Name H2 FY 2015-16 FY 2016-17 1 APGPCL I - Allocated capacity 14 31.66 2 APGPCL II - Allocated capacity 46.81 84.84 Total 60.81 116.50 Page 22 3.4.4 IPPS The availability of power from the generating stations of GVK, Spectrum, Lanco Kondapalli and Reliance (BSES) have been projected based on the current gas supply levels. Actual energy availability till September, 2015 has been factored while estimating energy availability for H2 FY 2015-16. For FY 2016-17 40% PLF has been assumed. The PPA subsisting with M/s GVK Phase-I was expired on 20.06.2015. APDISCOMs have issued Buyout notice and M/s GVK-I is scheduling entire power only to APDISCOMs w.e.f. 20.06.2015. There is no share for TSDISCOMs up on expiry of PPA in respect of M/s GVK. The PPA subsisting with M/s SPGL is going to expire by 18.04.2016. The APDISCOMs would opt for either Renewal of PPA or Buyout of the project as per the terms of PPA. M/s LANCO PPA gets completed by 01.1.2016, but the projections are furnished expecting that the PPA gets renewed. Old IPPs (Energy Availability-MU) S. No. Station Name H2 FY 2015-16 FY 2016-17 1 GVK 367.19 727.27 2 Spectrum 349.04 711.67 3 Lanco Kondapalli (Gas) 494.42 1263.95 4 Reliance BSES 179.70 350.90 Total 1390.34 3053.79 Energy availability form the New IPPs viz; GVK EXtn, GMR Vemagiri, Gautami& Konaseema and Merchant Power Plants viz., GREL, LKPL is considered to be zero. S.No APSPDCL New IPPs FY 15 H2 (MU) FY 16-17 (MU) 1 GVK Extension Project 0 0 2 Vemagiri Power Generation Ltd 0 0 3 Gautami Power Ltd 0 0 4 Konaseema EPS Oakwell Power Ltd. 0 0 5 Lanco Kondapalli Power Ltd. 0 0 6 GMR Rajahmundry Energy Ltd. 0 0 Page 23 3.4.5 Non-Conventional Energy (NCE) Sources Wind: 1. For the existing Projects, the newly commissioned & to be commissioned wind projects energy is anticipated based on the threshold PLF of 23.5% considered in APERC Regulation 1 of 2015. 2. Monthly generation is assumed in proportion to the actual monthly generation values of FY14-15 3. Capacity in MWs indicated for the FY: 2015-16 (H2) is actual installed capacity commissioned under Power Purchase Agreements (Preferential & REC mechanism). 4. Capacity in MWs indicated for the FY: 16 -17 is actual installed capacity commissioned under Power Purchase Agreements upto 15-16 plus anticipated capacity of 500MW of the proposed 1016.4 MW by NREDCAP . 5. Tariff for the upcoming wind projects is assumed @ Rs.4.83/unit as per APERC orders dt: 01.08.2015. Further, Income Tax/MAT and ED are pass through and same are to be paid by DISCOMs to the developers over and above the tariff. Solar: 1. For the existing projects the newly commissioned & to be commissioned solar projects energy is anticipated based on the threshold PLF of 19%. 2. Capacity in MWs indicated for the FY: 2015-16 (H2) is actual installed capacity commissioned under Power Purchase Agreements and anticipated capacity considered based on the target time lines envisaged in the Power Purchase agreements entered by the solar developers with DISCOMs. 3. Monthly generation for FY 16-17 is assumed in proportion to the actual monthly generation values of FY14-15 4. Capacity in MWs indicated for the FY: 16 -17 is anticipated capacity considered based on the target time lines envisaged in the Power Purchase agreements entered by the solar developers with DISCOMs. APSPDCL Page 24 5. Tariff for solar projects taken as per the PPA and the same was adopted by APERC. 6. GoAP issued the G.O. Ms No. 46, dated:27.11.2012 for purchasing Solar power of 1000MW through competitive bidding route. Accordingly AP Discoms had initiated the bidding process for procurement of 1000 MW of solar power during 2012-13 and PPA’s were entered with solar power developers for a capacity of 33 MW at the tariff of Rs. 6.49/kWh for 20 years. Out of the PPA capacity of 33 MW,8 MW was commissioned so far. 7. Further, GoAP issued the G.O Ms. No.8, dated: 12.02.2015 and directed APDISCOMs for procurement of 1000 MW Solar Power through competitive bidding process . Accordingly bidding process conducted by APPCC/APSPDCL for procurement of 500 MW solar power in phase-1, the minimum first year tariff obtained was Rs. 5.25/unit and the cut-off first year tariff considered was Rs.5.999/unit. This tariff will be escalated at the rate of 3% per year till 10th year and the 10th year tariff will be continued for the remaining 15 years. The corresponding minimum levelised tariff is Rs. 6.17/unit and maximum Rs. 7.05/unit. and APDISCOMs entered PPAs for a capacity of 619 MW with consent of APERC. Out of 619 MW, 15MW has been commissioned; 500MW of the balance capacity is expected to be commissioned by March 31, 2016. 8. Further, GoAP also targeted to set up 3500 MW solar capacity through Solar Parks in Kurnool and Anantapur districts with the support of Govt. of India. As a part of this, GoAP has entered MoU with NTPC on 16.09.2014 for setting up of 1000MW solar park in Anantapur dist. Subsequently as per the directions of GoAP, APDISCOMs had entered PPAs with M/s NTPC for purchase of solar power from the proposed 250 MW (Phase-1) solar park at NP kunta, Anantapur Dist on 24.04.2015 and the 250 MW (Phase-1) will be commissioned by April-2016. APSPDCL Page 25 Mini Hydel: 1. For the existing Projects anticipated energy for the FY 2015-16 (H2) & FY: 2016-17 has been arrived based on the PLFs for the actual energy supplied for the FY 201415 & FY 2015-16 (H1). 2. For upcoming Minihydel projects energy is anticipated @ 32% PLF. 3. Capacity in MWs indicated for the FY: 2015-16 (H2) and FY: 2016-17 is actual installed capacity commissioned under Power Purchase Agreements and anticipated capacity as per the information given by the NREDCAP. 4. Tariff for the upcoming projects is assumed as Rs. 4/unit since the APERC yet to determine the tariff for new MiniHydel projects. 5. Presently, Minihydel developers are being paid APERC tariff which is exclusive of Electricity Duty, Royalty charges and MAT/Income Tax. As and when claimed by the developers, the same needs to be reimbursed. Biomass, Bagasse, Industrial Waste & Municipal Solid Waste: 1. For the all existing Projects anticipated energy for the FY 2015-16 (H2) & FY: 201617 has been arrived based on the PLFs for the actual energy supplied for the FY 2014-15 & FY 2015-16 (H1). 2. Capacity in MWs indicated for the FY: 2015-16 (H2) and FY: 2016-17 is actual installed capacity commissioned under Power Purchase Agreements. 3. Upcoming projects in these categories are nil. 4. Presently, the Biomass, Bagasse, Industrial Waste & Municipal Solid Waste developers are being paid APERC tariff which is exclusive of Electricity Duty and MAT/Income Tax. As and when claimed by the developers, the same needs to be reimbursed. Energy availability projections for H2 FY 2015-16 and FY 2016-17 from various NCE sources is as summarized in the following table: APSPDCL Page 26 Non-Conventional Energy Sources ( Net Energy Availability - MUs ) S. No. Station Name H2 FY 2015-16 FY 2016-17 1 Bio Mass Power Projects including Co-gen 162.86 320.20 2 Bagasse Cogeneration Projects. 86.56 98.54 3 Wind Power Projects 548.19 2911.38 4 Mini Hydel Power Projects 56.02 113.45 5 Industrial Waste Based Power Projects 17.16 32.96 6 Municipal Waste Based Power Projects 0.18 0.36 7 NCL Energy Ltd. 16.43 24.84 8 Solar Power Projects 147.61 1046.91 9 Solar Parks 0 416.10 1035.00 4964.74 Total 3.4.6 Mini Power Plants The energy availability projections for FY 2015-16 H2 and FY 16-17 have been projected as declared by the station at PLF 0% for Srivathsa for FY 15 H2 and at PLF 25% for FY 16-17. The energy for LVS for FY 15 H2 and FY 16-17 would not be dispatched owing to high variable cost. Mini-Power Plants Allocated to EPDCL (Energy Availability-MUs) 3.4.7 S, No. Station Name FY 15 H2 FY 16-17 1 Srivathsa 0 38.14 2 LVS 0 0 Total 0.00 38.14 Hinduja National Power Corporation Limited Energy availability of 606.12 MU and 6,082.77 MU has been considered from Hinduja power plant for H2 of FY 2015-16 and FY 2016-17 respectively considering 80% PLF. As per the projections in ARR for FY 2015-16 filed by APDiscoms and the same was approved by APERC in its Retail Tariff Order for FY 2015-16, the entire energy available from HNPCL Thermal Power Plant has been considered for Andhra Pradesh. APSPDCL Page 27 3.4.8 Long Term and Medium Term Purchases LongTerm – Thermal PowerTech Corporation India Limited The licensees (AP & Telangana Discoms) have signed a Power Purchase Agreement with M/s. Thermal PowerTech Corporation India Limited (TPCIL) for a contracted capacity of 500 MW under long term basis through Case-I bidding route for a period of 25 years. In case licensees accepts the revised schedule date of delivery as requested by TPCIL, the supply of said power will commence from 01.04.2015 and the energy availability projected from this plant for AndhraPradesh is 1,716 MU for FY 2016-17, which has been considered. Long Term – 1000MW DBFOO Bidding Energy availability has been considered from June 2016 at 90% PLF (ex-bus). The energy availability projected from 1000MW DBFOO bidding is 6,566 MU for FY 2016-17. Medium Term – KSK Mahanadi AP and Telangana Discoms have signed PPA’s with KSK Mahanadi and Corporate Power for supply of power through medium term basis starting from June 2013 for a period of 3 years. But, the energy from Corporate Power has not been considered as the PGCIL has not granted its transmission access.80% PLF (599.44 MU for H2 FY 2015-16 and 2,295.64 MU for FY 2016-17) has been considered from KSK Mahanadi. 3.4.9 Short Term and Bilateral/ Inter-State purchases Bilateral Purchases Energy availability considered from bilateral sources for FY 2015-16 is 3,406 MUs at a PLF of 85% and 821.81 MUs at a PLF of 85% for FY16-17 in the month of April and May 2016. 3.4.10 Summary A summary of the source wise current estimate of energy available for H2 FY 2015-16 and FY 2016-17 is presented below. APSPDCL Page 28 Energy Availability (MU) Generating Station H2 FY 2015-16 FY 2016-17 12627.35 25504.11 942.37 3241.44 5707.51 12436.63 60.81 116.50 IPPS 1390.34 3053.79 NCEs 1035.00 4964.74 0.00 38.14 HNPCL 606.12 6,082.77 Long Term & Medium Term 1484.03 10,578.73 Short Term & Bilateral Purchases 3,406 821.81 Total 27,323 66,839 Genco (APGenco & TSGenco)Thermal Genco (APGenco & TSGenco)Hydel CGS APGPCL Mini Power Plants 3.5 Power Purchase Cost 3.5.1 GENCO (Andhra Pradesh GENCO &Telengana State GENCO) The annual fixed costs for all APGENCO stations for FY 2015-16 have been considered as approved by APERC in its order dated 31.05.2014 in OP No.15/2009 filed by APGENCO for determination of tariff for FY 2009-14 which includes the year 2013-14. The fixed cost for FY 2014-15 was admitted as per approved tariff order for FY 2013-14 and subsequently, truing up of fixed cost for FY 2014-15 was done as per orders of APERC dt 31.05.2014 in OP No.15/2009.The fixed costs have been considered as per the projections of APGENCO for FY 2016-17. APSPDCL Page 29 The total fixed costs for all the GENCO thermal and hydel stations2 including both existing and new stations is Rs. 2,571.34 Crs for H2 of FY 2015- 16 and Rs. 5,704.87 Crs for FY 2016-17. The fixed costs for GENCO Thermal and Hydel stations have been tabulated below: Station Fixed Costs for FY Fixed Costs for FY 2015-16 H2 (Rs. Cr.) 2016-17 (Rs. Cr.) VTPS I 45.01 91.71 VTPS II 45.01 91.71 VTPS III 45.01 91.71 VTPS IV 146.86 295.62 RTPP I 68.38 138.86 RTPP Stage-II 138.87 279.51 RTPP Stage-III 91.36 183.61 582.30 1484.45 power station -II 582.30 1484.45 APGENCO Thermal Total 1745.11 4141.63 KTPS A 49.57 68.00 KTPS B 49.57 68.00 KTPS C 49.57 68.00 KTPS D 79.12 127.50 KTPS Stage VI 170.86 363.55 APGENCO-Thermal Damodaram Sanjeevaiah Thermal power station -I Damodaram Sanjeevaiah Thermal TSGENCO-Thermal 2 The fixed costs for TSGENCO stations have not been mentioned because energy availability from only APGENCO hydel stations have been considered (allocation based on geographical location). APSPDCL Page 30 Station Fixed Costs for FY Fixed Costs for FY 2015-16 H2 (Rs. Cr.) 2016-17 (Rs. Cr.) RTS B 18.26 24.44 Kakatiya Thermal Power Plant Stage I 176.19 364.87 TSGENCO Thermal Total 593.14 1084.36 Total Thermal 2338.25 5225.99 MACHKUND PH AP Share 4.65 9.30 TUNGBHADRA PH AP Share 3.19 6.38 USL 28.25 57.40 LSR 54.15 110.02 DONKARAYI 2.95 5.98 103.52 209.56 NSRCPH 9.76 19.67 PABM 5.73 11.60 Mini hydro 0.35 0.72 Nagarjuna sagar tail pond dam PH 20.54 48.26 Total Hydro 233.09 478.88 TOTAL GENCO 2571.34 5704.87 APGENCO –Hydel SSLM For existing GENCO thermal stations, the actual variable cost (including FCA) for H1 of FY 2015-16 has been considered for H2 of 2015-16. For projecting FY 2016-17 variable cost for APGENCO stations, an escalation of 3% is taken on actual H1 FY 2015-16 variable cost per unit, whereas an escalation of 3% has been considered even for TSGENCO stations. For Damodaram Sanjeevaiah Thermal power station unit I variable cost per unit for H2 FY 2015-16 has been estimated to be Rs. 2.52/unit considering that 30% imported coal, 30% MCL washed coal and 40% domestic coal to be used. Rs. 2.20/unit for FY16-17 variable cost has been assumed as the units will be running at 85%PLFfor FY 2016-17.Same variable cost per unit has been considered for Damodaram Sanjeevaiah Thermal power station unit II for FY 2016-17 APSPDCL Page 31 It has been observed over the past few years that usage of imported coal has become necessary to bridge fuel shortfall, leading to a steady increase in the variable cost over the past few years. The station-wise variable rates that have been projected for APGENCO thermal plants & TSGENCO thermal Plants for H2 FY 2015-16 H2 and for FY 2016-17are as follows: Station Variable rate (Rs./kWh) Variable rate (Rs./kWh) H2 FY 2015-16 FY 2016-17 VTPS (I, II, III) 3.30 3.34 VTPS-IV 3.21 3.3 RTPP-I 3.76 3.87 RTPP-II 3.76 3.87 RTPP-III 3.76 3.87 APGENCO Stations Damodaram SanjeeviahTPS-I Damodaram SanjeeviahTPS-II 2.52 2.52 2.20 2.20 TSGENCO Stations KTPS (A, B, C) 1.64 1.69 KTPS- D 1.50 1.55 KTPS-VI 2.74 2.82 RTS- B 3.01 3.10 KTPP-I 2.42 2.50 The incentives for GENCO thermal stations are calculated based on APERC Regulation No 1 of 2008, at a flat rate of 25 paisa/kWh for ex-bus scheduled energy corresponding to scheduled generation in excess of ex-bus energy corresponding to target Plant Load Factor. APSPDCL Page 32 3.5.2 CGS: NTPC (SR) (2100 MW) CERC had notified the terms & conditions of tariff regulations for the control period FY 2014-19 i.e., for a period of 5 years and the regulations, 2014 waspublished by CERC by end of February 2014. CERC had modified the terms & conditions for determination of fixed charges as well as energy charges to the ensuing control period for inter-state generating stations. CERC provided the revised regulations stating that beneficiaries would pay the fixed charges for FY 2016-17 and energy charges to the Inter-State Generating stations based on the approved charges for FY 2013-14 and energy charges norms as per the regulations, 2009 till the finalization of orders for the respective inter-state generating station ie, NTPC & NLC, JV. Due to non-availability of orders of CERC, the fixed charges were considered based on the CERC approved charges for FY 2013-14. The incentives payable had been considered as 50 paise per unit based on the actual PLF above threshold level of 85% as per the prevailing regulations of CERC, 2014. In the orders of CERC for FY 201314, the income tax was grossed up in ROE component as per the regulations, 2009 and hence, the fixed charges determined for H2 FY 2015-16 and FY 2016-17 are inclusive of income tax. Based on the availability projections, the fixed charges along with payable incentives are computed for H2 FY 2015-16 and FY 2016-17 for Ramagundam I & II. AP has a share of 14.91% from Ramagundam I & II. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. The recoverable PLF of fixed charges are 83% only based on the availability of generating station subject to any coal shortages occur, as per new regulations, 2014. Due to non-finalization of fixed charges in every year of the control period FY 2014-19, the prevailing fixed charges for FY 2013-14 had been recovered by NTPC by considering 83% PLF on availability. NTPC had submitted the tariff petition of Ramagundam I & II as per Regulations, 2014 before Hon’ble CERC for determination of fixed charges to the control period 2014-19. APSPDCL Page 33 NTPC (SR) STAGE-III (500 MW) CERC had notified the terms & conditions of tariff regulations for the control period FY 2014-19 i.e., for a period of 5 years and the regulations, 2014 was published by CERC by end of February 2014. CERC had modified the terms & conditions for determination of fixed charges as well as energy charges to the ensuing control period for inter-state generating stations. CERC provided the revised regulations stating that beneficiaries would pay the fixed charges for FY 2016-17 and energy charges to the inter-state generating stations based on the approved charges for FY 2013-14 and energy charges norms as per the regulations, 2009 till the finalization of orders for the respective inter-state generating stations ie, NTPC & NLC, JV. Due to non-availability of orders of CERC, the fixed charges were considered based on the CERC approved charges for FY 2013-14. The incentives payable had been considered as 50 paise per unit based on the actual PLF above threshold level of 85% as per the prevailing regulations of CERC, 2014. In the orders of CERC for FY 2013-14, the income tax was grossed up in ROE component as per the regulations, 2009 and hence, the fixed charges determined for H2 FY 2015-16 and FY 2016-17 are inclusive of income tax. Based on the availability projections, the fixed charges along with payable incentives are computed for H2 FY 2015-16 and FY 2016-17 in case of Ramagundam III. AP has a share of 15.68% from Ramagundam III. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. The recoverable PLF of fixed charges are 83% only based on availability of generating station subject to any coal shortages occur, as per new regulations, 2014. Due to non-finalization of fixed charges in every year to the control period 2014-19, the prevailing fixed charges for FY 13-14 had been recovered by NTPC by considering 83% PLF on availability. NTPC had submitted the tariff petition of Ramagundam III as per Regulations, 2014 before Hon’ble CERC for determination of fixed charges to the control period 2014-19. NTPC-TALCHER -II (2000 MW) CERC had notified the terms & conditions of tariff regulations for the control period FY 2014-19 i.e., for a period of 5 years and the regulations, 2014 was published by CERC APSPDCL Page 34 by end of February 2014. CERC had modified the terms & conditions for determination of fixed charges as well as energy charges for the ensuing control period for inter-state generating stations. CERC provided the revised regulations stating that beneficiaries would pay the fixed charges for FY 2016-17 and energy charges to the inter-state generating stations based on the approved charges for FY 2013-14 and energy charges as per the regulations, 2009 till the finalization of orders for the respective inter-state generating station ie, NTPC & NLC, JV. Due to non-availability of orders of CERC, the fixed charges were considered based on the CERC approved charges for FY 2013-14. The incentives payable had been considered as 50 paise per unit based on the actual PLF above threshold level of 85% as per the prevailing regulations of CERC, 2014. In the orders of CERC for FY 201314, the income tax was grossed up in ROE component as per the regulations, 2009 and hence, the fixed charges determined for H2 FY 2015-16 and FY 2016-17 are inclusive of income tax. Based on the availability projections, the fixed charges along with payable incentives are computed for H2 FY 2015-16 and FY 2016-17 for Talcher-II. AP has a share of 9.22% from Talcher-II. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. The recoverable PLF of fixed charges are 83% only based on availability of generating station subject to any coal shortages occur, as per new regulations, 2014. Due to non-finalization of fixed charges in every year of the control period FY 2014-19, the prevailing fixed charges for FY 2013-14 had been recovered by NTPC by considering 83% PLF on availability. NTPC had submitted the tariff petition of Talcher II as per Regulations, 2014 before Hon’ble CERC for determination of fixed charges to the control period 2014-19. NTPC SIMHADRI STAGE-I (1000 MW) CERC had notified the terms & conditions of tariff regulations for the control period FY 2014-19 i.e., for a period of 5 years and the regulations, 2014 waspublished by CERC by end of February 2014. CERC had modified the terms & conditions for determination of fixed charges as well as energy charges to the ensuing control period for inter-state generating stations. CERC provided the revised regulations stating that beneficiaries would APSPDCL Page 35 pay the fixed charges for FY 2016-17 and energy charges to the inter-state generating stations based on the approved charges for FY 2013-14 and energy charges norms as per the regulations, 2009 till the finalization of orders for the respective inter-state generating station ie, NTPC & NLC, JV. Due to non-availability of orders of CERC, the fixed charges were considered based on the CERC approved charges for FY 2013-14. The incentives payable had been considered as 50 paise per unit based on the actual PLF above threshold level of 85% as per the prevailing regulations of CERC, 2014. In the orders of CERC for FY 201314, the income tax was grossed up in ROE component as per the regulations, 2009 and hence, the fixed charges determined for H2 FY 2015-16 and FY 2016-17 are inclusive of income tax. Based on the availability projections, the fixed charges along with payable incentives are computed for H2 FY 2015-16 and FY 2016-17 in case of Simhadri Stage-I. AP has a share of 46.11% from Simhadri Stage-I. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. The recoverable PLF of fixed charges are 83% only based on availability of generating station subject to any coal shortages occur, as per new regulations, 2014. Due to non-finalization of fixed charges in every year of the control period FY 2014-19, the prevailing fixed charges for FY 2013-14 had been recovered by NTPC by considering 83% PLF on availability. NTPC had submitted the tariff petition of Simhadri Stage I as per Regulations, 2014 before Hon’ble CERC for determination of fixed charges to the control period 2014-19. NTPC- SIMHADRI II (1000 MW) CERC had notified the terms & conditions of tariff regulations for the control period FY 2014-19 i.e., for a period of 5 years and the regulations, 2014 was published by CERC by end of February 2014. CERC had modified the terms & conditions for determination of fixed charges as well as energy charges for the ensuing control period for inter-state generating stations. CERC provided the revised regulations stating that beneficiaries would pay the fixed charges for FY 2016-17 and energy charges to the inter-state generating stations based on the approved charges for FY 2013-14 and energy charges as per the APSPDCL Page 36 regulations, 2009 till the finalization of orders for the respective inter-state generating station ie, NTPC & NLC, JV. Due to non-availability of orders of CERC, the fixed charges were considered based on the CERC approved charges for FY 2013-14. The incentives payable had been considered as 50 paise per unit based on the actual PLF above threshold level of 85% as per the prevailing regulations of CERC, 2014. In the orders of CERC for FY 201314, the income tax was grossed up in ROE component as per the regulations, 2009 and hence, the fixed charges determined for H2 FY 2015-16 and FY 2016-17 are inclusive of income tax. Based on the availability projections, the fixed charges along with payable incentives are computed for H2 FY 2015-16 and FY 2016-17 in case of Simhadri Stage-II. AP has a share of 21.11% from Simhadri Stage-II. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. The recoverable PLF of fixed charges are 83% only based on availability of generating station subject to any coal shortages occur, as per new regulations, 2014. Due to non-finalization of fixed charges in every year of the control period FY 2014-19, the prevailing fixed charges for FY 2013-14 had been recovered by NTPC by considering 83% PLF on availability. NLC Stage –I (630 MW) For the APDISCOMs share of 8.49 % of 630 MW, the payable fixed charges and lignite cost for the Control Period of FY 2009-14 was determined by CERC in its final orders of NLC TPS-II (Stage-I). The lignite costs for the Control Period of FY 2014-19 is yet to be determined by Ministry of Coal, GOI. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. NLC Stage –II (840 MW) For the APDISCOMs share of 11.20 % of 840 MW, the payable fixed charges and lignite cost for the Control Period of FY 2009-14 was determined by CERC in its final orders of NLC TPS-II. (Stage-II). The lignite cost for the Control Period FY 2014-19 is yet to be determined by Ministry of Coal, GOI. Variable cost per unit for H2 FY 2015-16 has been APSPDCL Page 37 considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. KAIGA ATOMIC POWER STATION 1 & 2 (440 MW) and 3 & 4 (440MW): The AP share from Kaiga 1 & 2 is 14.25% and from Kaiga 3 &4 is 15.09%. The tariff for Kaiga 1&2 and Kaiga 3&4 for H2 FY 2015-16 has been considered same as the tariff in H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. Vallur Thermal JV Power Project (NTPC & TANGEDCO): Ministry of Power, GOI had allocated firm share of 11.87% from total capacity of 1500 MW to erstwhile AP and 12.25% was considered for erstwhile AP inclusive unallocated power. Presently, Units 1, 2 & 3 are under generation and 93 MW is being availed by AP Discoms from this power project. NTECL had made filings before CERC for determination of tariff for the control period 2014-19 for this JV Project and provisional orders were yet to be issued by CERC for payment of fixed charges. The fixed charges for H2 FY 2015-16 and FY 2016-17 are computed based on the 85% of AFC (for units 1,2&3) as approved by CEO(NTECL) pending tariff order from Hon'ble CERC for FY 2014-15 for Vallur power project. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16.The incentives payable have been factored into the fixed charges. In the orders of CERC, the income tax was grossed up in ROE component as per the regulations, 2009 and hence, the fixed charges determined for H2 FY 2015-16 and FY 2016-17 are inclusive of income tax. As per the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009, incentives are also part of fixed charges which are to be computed every month based on the formulae provided in the Regulations. Based on the availability projections, the fixed charges along with payable incentives are considered for H2 FY 2015-16 and FY 2016-17. NLC-TNPL Tuticorin A joint venture power project of NLC and TNEB had implemented at Tuticorin with an installed capacity of 1000MWs. Both the units were declared the COD and presently, AP is APSPDCL Page 38 availing 132 MWs from this power project. M/s.NTPL had filed the tariff petition before Hon’ble CERC for determination of fixed charges to the control period 2014-19. Based on these filings, CERC had issued the provisional orders. The fixed charges are computed based on the availability projections duly considering the 30% PLF for H2 FY 15-16 and with 100% PLF for FY 16-17, as submitted by NTPL. Variable cost per unit for H2 FY 2015-16 has been considered same as actual per unit variable cost as H1 FY 2015-16. FY 2016-17 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. The payable incentives were computed by considering the regulations, 2014 i.e., 50 paise per unit above the threshold PLF of 85%. NTPC-Kudgi As informed by NTPC, the estimated total cost per unit is Rs. 4.20 (Fixed Cost of Rs. 2.31 and Variable Cost of Rs. 1.89) during the first year. A petition will be filed before Hon’ble CERC for determination of tariff based on the capital cost before synchronization of the first unit i.e. in March 2016. For the period between the achievement of CoD and determination of tariff by CERC, the Company will raise bills based on the provisional tariff and reconciliation will be done after finalization of tariff by CERC. 3.5.3 APGPCL The power purchase cost incurred by APDISCOMs for procurement from APGPCL for H2 FY 2015-16 and FY 2016-17 are as per the projections given by APGPCL. The calculations were done on the basis of availability of 0.65 MSCMD of Natural Gas with the usage of part load i.e., about 172MW (out of 272 MW). As a result, about 100 MW was kept as idle for want of Natural Gas. Consequently, the fixed cost has gone up steeply. Cost components for H2 FY 2015-16 and FY 2016-17 Particulars H2 FY 2015-16 FY 2016-17 Fixed cost (Rs. Crs.) 0.69 0.98 Variable cost (Rs. / kWh) 2.78 2.87 Stage-I APSPDCL Page 39 Cost components for H2 FY 2015-16 and FY 2016-17 Stage –II Fixed cost (Rs. Crs.) 1.60 Variable cost (Rs. / kWh) 2.79 3.04 2.87 During FY 2014-15, Natural Gas dollar rate had been drastically increased from USD 59.00 to USD 62.00 Fixed cost also increased due to non-supply of natural gas due to gas pipe line blast at Nagaram Village, East Godavari Dist on 27.06.2014. APGPCL plants were totally closed for about Four and Half months. Proposed gas cost is USD 3.82 per MMBTU which is effective from October 2015. S. No Particulars H2 FY 2015-2016 FY 2016-2017 1 Gas Availability in SCMD 6,50,000 6,50,000 2 Gas Rate - per MMBTU 3.82 USD 3.82 USD 3 Exchange Dollar Rate [$] 65 65 4 Variable Cost Unit Rate : Rs. Stage-I 2.78 2.87 Stage-II 2.79 2.87 As plants are running with part load, the gas consumption i.e. SFC (Specific Fuel Consumption) is also more which is contributing to increase in the variable cost and fixed cost. 3.5.4 IPPs GVK JEGURUPADU POWER PROJECT The fixed cost is fully recoverable at 68.50 % PLF. The variable charge of H2 FY 15-16 is considered same as APERC approved FY 15-16 value of Rs 2.62/ kWh and 3% escalation on APERC approved FY15-16 value has been considered for FY 2016-17. The capital cost of this plant is Rs. 816 Crs. The estimated fixed cost for Andhra Pradesh is Rs. 68.84 Crs per annum for FY 2015-16 (H2) and Rs.123.87 Crs (estimated) for FY 2016APSPDCL Page 40 17 (.The PPA subsisting with M/s.GVK was expired on 20.06.2015. APDISCOMs had issued Buyout notice and M/s.GVK is scheduling entire power only to APDISCOMs w.e.f. 20.06.2015. There is no share for TSDISCOMs upon expiry of PPA in respect of M/s.GVK). The fixed cost includes foreign exchange variations payable by APDISCOMs to the generator as per the provisions of Power Purchase Agreement. The actual fixed cost as settled by the licensee may be different from the estimates as presented above on account of the monthly Foreign Exchange Rate Variation (FERV). The licensee submits to the Hon’ble Commission to allow the licensee to subsequently claim the change in fixed cost on account of FERV. Deemed / Notional generation claims will be payable to the generator up to 85 % PLF as per the incentive formulae provided in the PPA. Computation of incentive has been carried out based on the formula provided in the PPA. As there is gas deficit the expected PLF for H2 FY 2015-16 and for FY 2016-17 is 40%. Hence incentive may not be applicable for H2 FY 2014-15 and FY 2015-16. Incentive payment = Equity x (PLF - 68.50) x 0.00525; Equity = Rs. 244.80 Crs; Projected incentive for H2 FY 2015-16 is Rs. 0.00 Crs and for FY 2016-17 is Rs. 0.00 Crs (as there is deficit of gas). SPECTRUM The fixed cost is fully recoverable at 68.50 % PLF. The variable charge of H2 FY 15-16 is considered same as APERC approved FY 15-16 value of Rs 2.76/ kWh and 3% escalation on APERC approved FY15-16 value has been considered for FY 2016-17. The estimated fixed cost for Andhra Pradesh is Rs. 63.12 Crs per annum for FY 2015-16 and Rs.5.60 Crs for FY 2016-17 (In respect of M/s.SPGL power is sharing by AP & TS DISCOMs as per G.O.Ms.No.20 Dt.08.05.2014 but Projections are made considering full capacity of the plant (not AP share). Further, the PPA subsiding with M/s.SPGL is going to APSPDCL Page 41 expire by 18.04.2016. The APDISCOMs yet to decide for choosing the options either Renewal of PPA or Buyout of the project. Hence the projections are shown only up to 18.04.2016). The fixed cost is inclusive of foreign exchange variations payable by APDISCOMs to the generator as per the provisions of Power Purchase Agreement. The actual fixed cost as settled by the licensee may be different from the estimates as presented above on account of the monthly Foreign Exchange Rate Variation (FERV). The licensee submits to the Hon’ble Commission to allow the licensee to subsequently claim the change in fixed cost on account of FERV. Deemed / Notional generation claims will be payable to the generator up to 85% PLF as per the incentive formulae provided in the PPA. Computation of incentive has been carried out based on the formula provided in the PPA. As there is gas deficit the expected PLF for H2 FY 2015-16 and for FY 2016-17 is 40% (The projections are taken only up to 18.04.2016). Hence incentive may not be applicable for H2 FY 2014-15 and FY 2015-16. Incentive payment = Equity x (PLF - 68.50) x 0.004 (if PLF > 68.50 < 80.50); Incentive payment = Equity x (PLF - 68.50) x 0.005 (if PLF > 80.50 < 85.50); Incentive payment = Equity x (PLF - 68.50) x 0.006 (if PLF > 85.50); Equity (considered provisionally) = Rs. 117.92 Crs; Projected incentive for H2 FY 2015-16 is Rs. 0.00 Crs and for FY 2016-17 is Rs. 0.00 Crs (as there is deficit of gas). LANCO KONDAPALLI The fixed charges are fully recoverable at 80% PLF. The variable charge of H2 FY 15-16 is considered same as APERC approved FY 15-16 value of Rs 2.28/ kWh and 3% escalation on APERC approved FY15-16 value has been considered for FY 2016-17. APSPDCL Page 42 Estimated fixed costs for Andhra Pradesh for FY 2015-16 upto 01.01.2016 is Rs.43.62 Cr. The subsisting PPA with LANCO expires by 01.01.2016. As per the existing PPA of Lanco Kondapalli with APDiscoms, the FDSC component of the fixed charge will not be payable by APDiscoms after completion of 12 years from the date of commencement of supply of power. This 12 year duration was completed by December 2012. Hence, no FDSC component are payable. In case the plant achieves a PLF (I) greater than 80% for a tariff year, then the Board shall pay to the generator incentive (as a percentage of the other fixed charges) for any additional unit generated beyond the actual generation in excess of a PLF (I) of 80%. The incentive structure is as shown below: PLF (I) % Incentive (%) Up to 80 % Nil Above 80 % and up to 85 % 2 % for every 1 % increase in PLF(I) (i.e. for a PLF(I) of 85 %, the incentive will be 10 % of the Other Fixed Charge) Above 85 % and up to 90 % 3 % for every 1 % increase in PLF(I) (i.e. for a PLF(I) of 90 %, the Incentive will be 10 % + 15 % = 25 % of the Other Fixed Charge) Above 90 % Same as for 90% i.e. 25% of the Other Fixed Charge. Projected incentive for H2 FY 2014-15 is Rs. 0.00 Crs and for FY 2015-16 is Rs. 0.00 Crs. RELIANCE INFRASTRUCTURE LTD. (BSES) The fixed charge is fully recoverable at 85 % PLF. The variable charge of H2 FY 15-16 is considered same as APERC approved FY 15-16 value of Rs 2.93/ kWh and 3% escalation on APERC approved FY15-16 value has been considered for FY 2016-17. Based on the formula provided in the PPA and considering 46.11% of the fixed cost for erstwhile Andhra Pradesh (as per G.O. Ms. No. 20), the fixed costs for Andhra Pradesh for FY 2015-16 and FY 2016-17 are Rs. 3.41 Crs and Rs. 6.82 Crs respectively. Since payment of FDSC component got over by December 2013 and only OFC is payable, fixed charges are APSPDCL Page 43 being paid as per the actual PLF achieved during the month as there is no alternate fuel facility. In case the plant achieves a PLF (I) greater than 85% for a tariff year, then the incentive (as a percentage of the other fixed charges) payable for any additional unit of actual generation in excess of a PLF (I) of 85 %. The incentive structure is as shown below: PLF (I) % Incentive (%) Up to 85 % Nil Above 85 % and up to 90 % 2 % for every 1 % increase in PLF(I) (i.e. for a PLF(I) of 90 %, the Incentive will be 10 % of the Other Fixed Charge Above 90 % Same as for 90% i.e. 10 % of the Other Fixed Charge. Projected incentive for H2 FY 2015-16 is Rs. 0.00 Crs and for FY 2016-17 is Rs. 0.00 Crs. The licensee shall not bear the tax on incentives payable to the generator. New IPPs & Merchant Plants No fixed and variable charges are considered from the new IPP plants. 3.5.5 NON CONVENTIONAL ENERGY (NCE) SOURCES: The Commission issued orders on 20.03.2004, fixing power purchase price applicable for NCE Projects (Biomass/Industrial Waste, Bagasse & Mini Hydel) from 01.04.2004 to 31.03.2009. The NCE Project Developers filed cases before the Appellate Tribunal against the APERC orders. The Appellate tribunal set aside APERC Orders dated. 20.03.2004. APTRANSCO and APDISCOMs filed Appeals before Supreme Court against ATE Orders. The Hon’ble Supreme Court passed Orders dated. 08.07.2010 setting aside ATE Orders. The Supreme Court remanded the matter to APERC with a direction to hear NCE Project developers afresh and determine /fix tariff/power purchase price. APERC has initiated the public hearing in this matter from 28.09.2010 and passed three divergent orders vide its order dt:12.09.2011. The APERC orders are challenged before Appellate Tribunal for Electricity by NCE developers & APDISCOMs. APSPDCL Page 44 The Appellate Tribunal in its order dt:20.12.2012, while fixing the parameters, directed APERC to fix the tariff accordingly to be payable to Non-conventional Energy Developers for the period 2004-2009. Aggrieved by the APTEL order dt:20.12.2012, APDISCOMs filed Civil Appeals Nos 1376-1385 of 2013 before Hon’ble Supreme Court. The apex court admitted the appeals and are pending for disposal. The APDISCOMs filed an application I.A. No.22 of 2013 in O.P. No.1075 of 2000 praying the APERC to defer the hearing of the remand proceedings on NCE tariff cases as ordered by the Appellate Tribunal for Electricity in order dt:20.12.2012 till the final disposal of civil appeals (1376 to 1385) filed before Hon’ble Supreme Court. The APERC dismissed the I.A. No.22 of 2013 with the opinion that DISCOMs cannot ask for deferment of the tariff order to give effect to the APTEL order on the plea that the petition has been filed before Hon’ble Supreme Court and the same is admitted for hearing. The APERC issued order dt:22.06.2013, pursuant to APTEL order dt:20.12.2012, determining the tariff payable to NCE developers for the period 01.04.2004 to 31.03.2009. The DISCOMs filed Special Leave Petition in the Hon'ble Supreme Court against the order dated 22.6.2013 passed by the APERC vide SLP (Civil) No. 30416 to 30428 of 2013. APERC issued suo-moto order dt:6.8.13 determining variable cost tariff in respect of Bagasse & Biomass (including Industrial Waste) projects giving consequential effect to the order dated 31.03.2009 in O.P No.5 of 2009 based on Hon’ble APTEL order dated 20.12.2012 & 30.04.2013. DISCOMs filed SLP against APERC order dated 06.08.2013 in the Hon'ble Supreme Court vide SLP (Civil) No. 19508 of 2013. The Special Leave Petitions (Civil) 30416-28 filed against APERC order dt:22.6.13 & 19508 filed against APERC order dt:06.08.13 came up for admission on 28.10.2013 and the Lordships were not inclined to grant permission to file Special Leave Petitions directly against the orders of APERC and directed to withdraw the Special Leave Petitions. Accordingly, the Special Leave Petitions were withdrawn. APSPDCL Page 45 As such, IAs were filed in C.A 1376-85 of 2013 before Hon’ble Supreme Court requesting for grant of stay of APERC orders dt:22.06.2013 & 06.08.2013 and Appeal Nos. 83 & 84 of 2014 were filed before APTEL against APERC orders dt:22.06.2013 & 06.08.2013. The same were dismissed by APTEL vide order dt: 21.07.2014 as not maintainable. Subsequently, appeals 10448 & 10499 are filed before Hon’ble Supreme Court against the orders of APTEL dt: 21.07.2014. The appeals are tagged with CA 1376-85 of 2013 and are likely to be listed on 20.01.2016. About Rs. 406 Crs was already paid to the NCE developers in accordance with the various court orders (in the united Andhra Pradesh state). However, upon the directions of Hon’ble Supreme Court dt: 16.12.2013, APDISCOMs are implementing tariff to the NCE developers as per APERC order dt: 22.06.2013 from the date of order, viz., 22.06.2013. Further, vide orders dt:11.03.2014 & 13.03.2014, Hon’ble Supreme Court of India directed to release 50% amount due to the NCE developers. Accordingly, the NCE developers were paid Rs.214.96 Crs in erstwhile Andhra Pradesh. APERC determined the variable cost for the control period FY 2014-19 vide APERC order dt: 16.05.2014. Further, APERC determined the fixed cost tariff for the Biomass, Bagasse, Mini Hydel & Industrial Waste projects for beyond 10 years of operation vide APERC orders dt:19.07.2014, 05.08.2014, 23.08.2014 & 01.09.2014 respectively. The fixed cost & variable cost are adopted as per the above orders for cost projections for H2 FY 2015-16 and FY 2016-17. However, review petitions have been filed by APDiscoms on APERC orders dt: 19.07.2014, 05.08.2014, 23.08.2014& 01.09.2014. The Hon’ble Commission dismissed /rejected these review petitions. Hence, appeals DFR Nos. 645 &646 of 2015 were filed before APTEL. Further, the Biomass developers filed appeals before APTEL on APERC order dt: 16.05.2014& 19.07.2014 wherein APERC determined variable cost tariff for FY 2014-19 & APSPDCL Page 46 fixed cost tariff for biomass projects beyond 10 years of operation respectively. Also, bagasse developers preferred appeal before APTEL against APERC order dt: 16.05.2014. The Mini Hydel developers also preferred appeal before APTEL against APERC order dt: 23.08.2014. The Commission vide its order dt: 31.03.2009 fixed single part tariff for existing Wind and Municipal waste projects for the period from 1.4.2009 to 31.3.2014. Further APERC issued orders dt: 15.11.2012 duly fixing new tariff @Rs 4.70/unit for upcoming wind power projects upto 31.03.2015. The said tariff order was extended till 31.07.2015. Vide order dt:01.08.2015, APERC determined the tariff for the upcoming wind projects for FY2015-16 @ Rs.4.83/unit without AD and @Rs.4.25/unit with AD based on the regulation no 1 of 2015 pertaining to terms and conditions for tariff determination for wind projects in the state of AP for the period from FY 2015-16 to 2019-20. The weighted average costs per unit (or Tariff Order rates) for NCE sources considered for FY 2016-17 are shown in the table below: Weighted average Cost / Tariff Weighted average Cost / Tariff Order Rate Considered for H2 Order Rate Considered for FY FY 2015-16 (Rs. / kWh) 2016-17 (Rs. / kWh) 5.91 6.18 4.15 4.33 NCE – Municipal Waste to Energy 5.91 6.18 NCE – Industrial Waste based power project 5.93 6.11 NCE – Wind Power 4.27 4.40 NCE – Mini Hydel 2.63 2.30 NCE – NCL Energy Ltd. 1.62 1.67 NCE – Solar Power 6.82 6.80 NCE – Solar Parks - 6.16 Project Type NCE – Bio-mass including Co - Gen NCE – Bagasse APSPDCL Page 47 3.5.6 MINI POWER PLANTS SRIVATHSA POWER PROJECTS LTD (17.202 MW) The recovery of fixed charges is limited to the delivery of 110 MU energy units. The fixed cost payable is Rs. 0.00 Crs for FY 15 and Rs. 1.726727 Crs for FY 16-17. The variable tariff for H2 FY 2015-16 has been considered same as the tariff in H1 FY 2015-16. FY 201617 per unit variable cost has been projected by considering 3% escalation on the VC of H1 FY 2015-16. Incentives: In case the project achieves delivered energy in excess of 110 MU in a tariff year, the APDISCOMs shall pay to the generator, an incentive of Rs.0.05 (Rupees Zero and Five Paise only) / kWh for each additional unit of actual delivery of energy at the Interconnection Point. 3.5.7 HNPCL M/s. HNPCL has filed an application vide O.P.No. 21/2015 before Hon’ble APERC for determination of tariff of 1040 MW Coal fired Thermal Power Plant to be set up at Visakhapatnam under cost plus basis and the hearings are under progress. Pending determination of Tariff by APERC, M/s. HNPCL has claimed the variable cost per unit of Rs. 1.8/kWh and fixed cost of Rs. 2.16/kWh at 85% avaiability for FY 2016-17. 3.5.8 Long Term&Medium Term Long Term – Thermal PowerTech Corporation India Limited Variable cost per unit of Rs.1.76/kWh have been considered for H2 FY 2015-16. And 3% escalation for FY 16-17. Fixed cost per unit of Rs.1.76/kWh have been considered for FY 16-17. Long Term – 1000MW DBFOO Bidding Total cost per unit considered for FY 16-17 is Rs.3.87/kWh. With variable cost of Rs.1.41/kWh APSPDCL Page 48 Medium Term – KSK Mahanadi Total cost per unit considered for FY 2016-17 is Rs. 3.79/kWh. 3.5.9 Short Term and Bilateral/ Inter-State purchases Month-wise shortfall has been estimated based on the availability and requirement. A part of this deficit would be met from external sources such as power traders and power exchange. The cost of power purchase is considered at Rs.5.17/kWh same as of H1 FY 15-16 3.5.10 Bilateral Purchases/Sale of Surplus Power Month-wise surplus has been estimated based on the availability and requirement. A part of this surplus is assumed to be sold through bilateral contracts at a price of Rs.4.89/kWh. The estimated sale of such surplus power is 4,334 MUs and the remaining will be sold in the open market provided the variable cost is lower than market price. (Monthly Market Price for FY16-17 is assumed to remain same as S2 grid market price of FY 2015-16.The estimated sale from such external sources are estimated to be 2,808 MUs for FY 2016-17. 3.5.11 D-D Purchases Month-wise availability of each APDiscom has been calculated based on PPA allocation. The requirement of each Discom at APTRANSCO periphery has been calculated, by grossing up the sales with losses. The D-D purchases / sales for each Discom have been estimated after taking into account the respective allocations to each Discom as per the Final Transfer Scheme. The D-D pool price has been considered at Rs. 5.17/kWh for FY 2016-17 (price of energy from bilateral purchases). 3.6 Energy Requirement Based on the availability shown above and the energy requirement from all the Discoms, the actual energy to be purchased Discom-wise has been projected as follows: APSPDCL Page 49 H2 FY 2015-16 FY 2016-17 MU MU DISCOMS APEPDCL 8,409 19,085 APSPDCL 17,878 38,481 Total 26,288 57,566 The above energy requirement of the licensees has been arrived at by grossing up the sales of the licensee sales with appropriate transmission and distribution losses. The external loss on the power purchased from CGS and KSK Mahanadi only has also been factored in the above energy requirement. 3.7 Summary of Power Purchase for Current Year H2 FY15-16andEnsuing year FY16-17 Based on the availability, requirement and costs for each source, the summary of power purchase cost for Andhra Pradesh for H2 FY 2015-16 is projected as follows: 2015 -16 H2 Projection Source Power Purchase (MU) Available Power Purchase (MU) Despatch Costs (INR Crs) PP Cost (INR/kWh) APGENCO Thermal 9,289 9,289 4,467 4.81 TSGENCO Thermal 3,338 3,338 1,287 3.86 942 942 233 2.47 - - - APGENCO Hydel TSGENCO Hydel CGS 5,771 5,771 1,966 3.41 61 61 19 3.16 IPPs - Gas 1,390 1,390 482 3.46 NCE 1,035 1,035 492 4.76 Others* 2,090 2,090 700 3.35 Market 3,406 2,335 1,207 5.17 27,323 26,252 10,853 4.13 APGPCL Total APSPDCL Page 50 *Others include Srivathsa, Long term and Medium term purchases, Hinduja Based on the availability, requirement and costs for each source, the summary of power purchase cost for Andhra Pradesh for FY 2016-17 is projected as follows: FY 16-17 Projection Source Power Purchase (MU) Available Power Purchase (MU) Despatch PP Cost (INR/kWh) Costs (INR Crs) APGENCO Thermal 18,776 16,915 8,703 5.14 TSGENCO Thermal 6,728 6,720 2,514 3.74 APGENCO Hydel 3,241 3,241 479 1.48 TSGENCO Hydel - - - 12,437 12,437 4,252 3.42 117 107 35 3.25 IPPs - Gas 3,054 3,048 1,119 3.67 NCE 4,965 4,965 2,539 5.11 Others* 16,700 16,700 6,440 3.86 Market 822 575 297 5.17 66,839 64,706 26,378 4.08 57,566 57,566 23,533 3.97 9,274 7,142 (3,502) (4.90) CGS APGPCL Total DISCOM Requirement Energy Sale of Surplus Power *Others include Srivathsa, Long term and Medium term purchases, Hinduja APSPDCL Page 51 4 4.1 Losses DISCOM losses The DISCOM losses for H2 FY 15-16 is taken as per APERC approved values and 5% reduction is considered for FY16-17 The below table provides the voltage level losses for projecting the energy requirement for H2 FY 2015-16 and FY 2016-17. APSPDCL - DISCOM losses Voltage Level H2 FY 2015-16 FY 2016-17 33 kV 3.80% 3.61% 11 kV 3.84% 3.65% LT 5.00% 4.75% The following table gives the details of losses excluding EHT sales projected by APSPDCL for 2015-16 and 2016-17. Approved by APERC Projection of APSPDCL 4.2 TRANSCO losses 2015-16 Excl. EHT Incl. EHT 10.17 % 8.75 % 10.54 % 9.31 % 2016-17 Excl. EHT Incl. EHT 9.97 % 8.44 % The Transco losses for H2 FY 2015-16have been taken as per approved. And for FY 16-17 Transco losses for FY 15-16 H1 actuals are considered Transmission Losses H2 FY 2015-16 3.95% 4.3 Transmission Losses FY 2016-17 3.34% Losses external to APTRANSCO system The losses external to the APTRANSCO system are considered to be 3.57 % for H2 FY 1516 and also for FY16-17 APERC approved values for FY15-16. This is applicable for procurement of power from Central Generating Stations and other medium and short term purchases. However, external losses have not been considered for bilateral / inter-state purchases due to considering average landed power purchase cost at APTransco periphery. APSPDCL Page 52 4.4 APTransco Charges The Transmission Cost has been computed based on the Transmission Tariff order for the FYs 2013-14, FY 2014-15, 2015-16 and 2016-17and is tabulated below: Form - 1.1 – Transmission Cost Name of Transmission service provider Load not eligible for Open Access Open Access Load Eligible for Open Access Tariff Cost MW (Rs./kW/month) (Rs. Crs.) MW Tariff (Rs./kW/month) Cost (Rs. Crs.) 1 APTransco 2 3 4 5 6 7 2013-14 2014-15 2015-16 2016-17 3050.55 4131.55 4624.44 4806.22 61.03 65.30 76.66 91.36 144.83 301.61 425.41 348.56 1388.45 2259.99 2485.99 2734.59 61.03 65.30 76.66 91.36 101.68 177.09 228.69 299.80 As per revised regulatory formats the transmission load has been apportioned between load not eligible for open access & load eligible for open access and the transmission cost is arrived by applying the respective transmission tariff.For the FY 2014-15, contracted demand of APSPDCL of six districts are considered for entire 12 months and contracted demand of newly added Anantapur &kunool districts are considered for 10 months for computation of transmission charges. Contracted load of Anantapur &kurnool districts is taken as 17.45% of contracted load of erstwhile APCPDCL. The licensee has considered the true-up order for 2nd control period regarding transmission charges, issued by Honourable APERC on 7-11-15 in OP.No. 13 of 2015. 4.5 PGCIL and ULDC Charges The PGCIL and ULDC charges have been computed based on the information sought by the licensee from APTransco. For FY 2014-15 the figures shown are actuals. For FY 2015-16, charges approved in the Tariff Order have been adopted and the licensee has projected the PGCIL & ULDC charges for FY 2016-17 with 10% growth. The details of the PGCIL & ULDC charges are as shown in the table below: 2013-14 PGCIL (Rs. Crs.) ULDC (Rs. Crs.) APSPDCL 2014-15 2015-16 2016-17 128.19 217.12 211.10 232.21 5.90 6.89 9.71 10.68 Page 53 4.6 SLDC Charges The SLDC Charges have been adopted as per the tariff orders. The charges have been apportioned based on load not eligible for open access and load eligible for open access. The projected SLDC charges for 2015-16 are Rs. 21.05 Crs. and Rs.23 Crs. for 2016-17. For the FY 2014-15, contracted demand of APSPDCL of six districts are considered for entire 12 months and contracted demand of newly added Anantapur &kunool districts are considered for 10 months for computation of transmission charges. Contracted load of Anantapur &kurnool districts is taken as 17.45% of contracted load of erstwhile APCPDCL. Form – 1.2 SLDC Charges 2013-14 Annual Fee Tariff (Rs./MW/year) Cost (Rs. Crs.) 3190.88 4755.66 1.52 1388.45 4755.66 0.66 0.00 0.00 MW Load not eligible for Open Access Open Access Load Eligible for Open Access Availed (within area of supply) Availed ( Outside Area of supply) Charges Tariff (Rs./MW/month) Cost (Rs. Crs.) 3190.88 1406.08 5.38 6.90 1388.45 1406.08 2.34 0.00 0.00 3.00 0.00 0.00 MW Total Cost (Rs. Crs.) 2014-15 Annual Fee Tariff (Rs./MW/year) Cost (Rs. Crs.) 4131.55 2535.65 1.05 2259.99 2535.65 0.57 0.00 0.00 MW Load not eligible for Open Access Open Access Load Eligible for Open Access Availed (within area of supply) Availed ( Outside Area of supply) Charges Tariff (Rs./MW/month) Cost (Rs. Crs.) 4131.55 2378.11 11.79 12.84 2259.99 2378.11 6.45 0.00 0.00 7.02 0.00 0.00 MW Total Cost (Rs. Crs.) 2015-16 Annual Fee Tariff (Rs./MW/year) Cost (Rs. Crs.) 4624.44 3092.78 1.43 2485.99 3092.78 0.77 0.00 0.00 MW Load not eligible for Open Access Open Access Load Eligible for Open Access Availed (within area of supply) Availed ( Outside Area of supply) Charges Tariff (Rs./MW/month) Cost (Rs. Crs.) 4624.44 2209.34 12.26 13.69 2485.99 2209.34 6.59 0.00 0.00 7.36 0.00 0.00 MW Total Cost (Rs. Crs.) 2016-17 Annual Fee Tariff (Rs./MW/year) Cost (Rs. Crs.) 4806.22 3533.18 1.70 2734.59 3533.18 0.97 0.00 0.00 MW Load not eligible for Open Access Open Access Load Eligible for Open Access Availed (within area of supply) Availed ( Outside Area of supply) APSPDCL Charges Tariff (Rs./MW/month) Cost (Rs. Crs.) 4806.22 2247.62 12.96 14.66 2734.59 2247.62 7.38 0.00 0.00 8.34 0.00 0.00 MW Total Cost (Rs. Crs.) Page 54 4.7 Distribution Costs (Rs. in Crores) Open Access Load not eligible for Open Access Load Eligible for Open Access Year 1 2013-14 2014-15 2015-16 2016-17 Total MW Tariff (Rs./kW/month) 2 3 Cost (Rs. Crs.) MW Tariff (Rs./kW/month) Cost (Rs. Crs.) 5 6 4 7 8=4+7 962.27 53.54 1273.30 1453.35 945.20 28.24 1481.60 2106.73 1034.90 46.50 2153.24 2332.71 1133.33 50.44 2383.14 3617.05 1219.76 6350.00 8054.18 9256.06 The distribution cost as per the Tariff Orders are considered. For FY 2013-14, the distribution cost of APSPDCL with six districts are considered. For FY 2014-15, the distribution cost of APSPDCL with six districts and distribution cost of Anantapur & Kurnool districts are considered for 10 months duly taking a proportion of distribution cost of erstwhile APCPDCL (17.45% of 1996.63 Crs.) are considered for arriving distributin cost. For FY 2015-16& FY 2016-17, the distribution cost of APSPDCL with six districts and for Anantapur &kurnool districts a proportion of distribution cost of erstwhile APCPDCL (17.45% of Rs.2215.69 Crs.) are considered for arriving total distribution cost. 4.8 Interest on Consumer Security Deposits Interest on Security Deposit are calculated based on the past trend. The interest is calculated @ 9.50% per annum for 2015-16 and 2016-17 on the average of opening and closing balances. For previous year 2014-15 the actual average rate of interest is found to be 9.89% per annum. Form 1.5: The computation on Interest on Consumer Security Deposit is given below Revenue Requirement Item (Rs. Crs.) A Opening Balance B Additions during the Year C Deductions during the Year D Closing Balance E Average Balance ((A+D)/2) F Interest @ % p.a. # G Interest Cost (E*F) APSPDCL 2013-14 2014-15 2015-16 2016-17 1007.27 187.05 1118.07 359.28 1365.86 377.24 1626.04 396.11 76.25 111.49 117.06 122.92 1118.07 1365.86 1626.04 1899.23 1062.67 1241.97 1495.95 1762.63 8.52 9.89 9.50 9.50 90.53 122.83 142.12 167.45 Page 55 As per APERC Regulation 6 of 2004 stipulates "Security Deposit amount shall be two months charges in case of monthly billing and 3 months charges for bi-monthly billing". ..... "The interest accruing to the credit of the consumer shall be adjusted annually against the amounts outstanding from the consumer to the Licensee as on 1st May of every year and the amounts becoming due from the consumer to the Licensee immediately thereafter." In this regard, the Licensee would like to submit that the Power Purchase Cost contributes to nearly 80% of the total Retail ARR and certainty in projection of power purchase cost has become very critical. Any deviation in power purchase cost has to be funded through internal sources and to be recovered in subsequent years through ARR. On the other hand, Subsidy from government contributes to be more than 12% of the Retail ARR. This would mean that Discoms are effectively getting 2 months consumer security deposit on 88% of retail ARR. While payments to generators is being done on a monthly basis, the revenue cycle is nearly 2 months. Hence, the working capital requirement of the Distribution Licensees has become difficult to manage in recent time and hence the Licensee requests the Hon'ble Commission to increase the duration of Security Deposit from the current two month charges to 75 days charges in case of monthly billing while continuing with 3 months charges for bi-monthly billing. This would ensure the Working Capital Requirements of the Licensees are met. 4.9 Supply Margin The licensee has projected Supply Margin for FY 2015-16 and FY 2016-17. The supply margin for 2013-14, 2014-15, 2015-16 and 2016-17are as follows. Form – 1.6 - Supply Margin Supply Margin Amount Rs. in Crores 2013-14 2014-15 2015-16 2016-17 12.33 12.12 13.13 13.00 4.10 Other Costs The licensee has projected the following expenditure under other costs : 1) Amount payable towards DELP to M/s EESL, New Delhi 2) Amount payable towards solar pumpsets APSPDCL Page 56 DELP : The licensee with the approval of Honourable Commission is distributing 2 Nos. LED bulbs in all the districts of its jurisdiction. In accordance with the approval of the Honourable Commission, the licensee has projected the amounts payable to M/s EESL, New Delhi. Solar pumpsets : The licensee has erected 1000 Nos. solar pumpsets and planned to erect another 1000 Nos. in the FY 2016-17. The consumer contribution is 11% of the project cost, the MNRE, Govt. of India provides 33% of the project cost as subsidy and balance 56% is to be borne by the licensee. The licensee has projected payment towards this project in FY 2016-17. The other costs during FY 2015-16 & FY 2016-17are submitted below : Particulars Payments to M/s.EESL towards DELP Solar pumpsets Total 2015-16 38.12 38.12 2016-17 50.13 11.38 61.51 4.11 Summary of ARR Aggregate Revenue Requirement (ARR) for Retail Supply Business (Form-1) Revenue Requirement Item (Rs. Crs.) 2013-14 2014-15 2015-16 2016-17 246.51 478.70 654.10 648.35 9.90 19.86 21.05 23.00 1 Transmission Cost 2 SLDC Cost 3 Distribution Cost 1,273.30 1,481.60 2,153.24 2,383.14 4 PGCIL Expenses 128.19 217.12 211.10 232.21 5 ULDC Charges 5.90 6.89 9.71 10.68 6 Network and SLDC Cost (1+2+3+4+5) 1,663.80 2,204.17 3,049.20 3,297.39 7 Power Purchase / Procurement Cost 7,663.14 12,217.29 13,468.63 15,380.80 8 Interest on Consumer Security Deposits 90.53 122.83 142.12 167.45 9 Supply Margin in Retail Supply Business 12.33 12.12 13.13 13.00 10 Other Costs, if any 0.00 0.00 38.12 61.51 11 Supply Cost (7+8+9+10) 7,765.99 12,352.24 13,662.00 15,622.76 12 Aggregate Revenue Requirement (6+11) 9,429.79 14,556.41 16,711.20 18,920.15 APSPDCL Page 57 5 Revenue Projections 5.1 Sales Forecast The factors affecting the actual consumption are numerous and often beyond the control of the licensee due to factors such as Government Policy, economic climate, weather conditions and force majeure events like natural disasters. Therefore, an accurate pointestimate of the consumption (sales by licensee) is not possible. Under such a situation, the attempt is to look into various factors and estimate the interrelationships to arrive at a reasonably accurate forecast within a range and use a single point-estimate within the range for the limited purpose of estimating future costs / revenues. The actual sales for FY 2009-10 to FY 2014-15 are given below : Category 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 Actual sales in MU LT Category 9968.21 9716.43 10951.15 11223.49 12181.94 17262.87 Domestic 3605.65 3861.84 4121.19 4221.00 4428.14 5946.78 Non-domestic/Commercial 850.52 901.31 986.59 983.56 977.02 1314.61 Industrial 740.82 796.76 989.83 965.28 866.11 1380.24 24.52 25.01 24.42 22.17 21.58 32.32 4167.82 3664.49 4366.34 4587.91 5513.46 8006.78 533.87 419.62 412.35 394.51 327.53 489.42 43.69 46.87 49.02 48.47 47.13 77.14 1.31 0.55 1.40 0.59 0.96 15.57 HT Category 3729.07 4724.81 5437.06 5221.36 5842.52 9098.66 HT I : General 2600.28 3530.74 4115.62 3889.21 4412.70 6932.50 HT II: Others 328.43 352.45 379.60 422.86 446.79 553.31 Cottage Industries, Dhobighats& Others Irrig& Agriculture Local Bodies, St. Lighting & PWS General Purpose Temporary Supply 0.00 0.00 0.00 1.28 8.56 17.87 29.37 27.45 61.31 36.27 48.69 528.35 522.15 521.40 569.54 609.65 646.15 747.84 48.60 51.03 35.47 27.35 22.16 34.48 HT VII: Green Power 0.00 0.00 0.00 0.00 0.00 0.00 HT VIII: Temporary 0.80 0.00 0.00 0.00 0.08 0.00 199.44 241.74 275.53 234.74 257.40 284.31 13697.27 14441.24 16388.21 16444.85 18024.46 26361.53 HT III: Airports, Bus Stations and Railway Stations HT IV Government LIS & Agl. HT V: Railway Traction HT VI: Townships & Residential Colonies Category: RESCOs Total (LT+HT) APSPDCL Page 58 Trend Method This method is a non-causal model of demand forecasting which assumes that the underlying factors, which drive the demand for electricity, are expected to follow the same trend as in the past and hence the forecast for electricity is also based on the assumption that the past trend in consumption of electricity will continue in the future. The strength of this method, when used with balanced judgment, lies in its ability to reflect recent changes and therefore is probably best suited for a short-term projection as used for the ARR/ Tariff filing. However, the trend-based approach has to be adjusted for judgment on the characteristics of the specific consumer groups/ categories. For example, while this method may provide a better estimate of consumption by the domestic and commercial categories of consumers, it may not be very suitable for the industrial category because of the high dependence of demand on the end-use and also on the macroeconomic variables. In any case, the forecasts arrived at by using the trend method need to be modified for impact of any other considerations like increasing commercialization/ development in certain districts/ regions to incorporate the impact of econometric variables and the load reliefs issued in the past. The Licensee has projected the category –wise sales based on the modified trend approach. Sales Forecast for the ensuing year has been developed based primarily on analysis of historic data for the period FY 2009-10 to H1 of FY 2015-16. The following inputs have been taken to arrive at sales consumption for H2 of FY 15-16 and FY 2016-17. Actual sales (6 districts + Anantapur & Kurnool) captured from FY 2009-10 to FY 2014-15 CAGR computed for historical sales for FY 2009-10 to FY 2014-15 Actual sales (6 districts + Anantapur & Kurnool) captured for FY 2015-16 H1 Sales projected for FY 2015-16 H2 using CAGR as growth rate over FY 2014-15 H2 actual sales (except for LT Agriculture where growth rate is linked to the growth in connections) CAGR computed for actual sales from FY 2009-10 to FY 2015-16 Growth rate used on FY 2015-16 projected sales to forecast sales for FY 2016-17 APSPDCL Page 59 Additional loads for Lift irrigation schemes etc., added for projecting FY 2015-16& FY 2016-17 restricted sales Load restrictions captured for FY 2014-15 H1& H2 and FY 15-16 H1 Load shifting has been considered for modifying historical load restrictions No Load restrictions are expected in H2 FY 2015-16&FY 2016-17 Hence, sales for FY 2015-16 (H1 FY 2015-16 actuals and H2 FY 2015-16 projections) and FY 2016-17 projected after considering additional loads & LRs on actual sales From June, 2014 onwards the actual / projected figures are pertains to entire 8 districts of APSPDCL (including newly added Anantapur &Kurnool districts). The sales growth rates are considered based on the present year and previous year figures both pertains to entire 8 districts of APSPDCL. The growth rate for each category is calculated with respect to sales of 8 districts for FY 2014-15,FY 2015-16 &FY 2016-17. 5.1.1 LT Sales forecast Sales Forecast for FY 2016-17 has been developed based primarily on analysis of historic data for the period FY 2009-10 to FY 2015-16. The ARR for the retail supply business is being filed for the FY 2016-17. The Licensee submits the following forecasts of energy sales (in million units) as part of the current application to the Hon’ble Commission. For the FY 2014-15, the sales pertain to Anantapur & Kurnool districts are considered from 2nd June, 2014. 5.1.2 LT Cat-I: Domestic Supply The consumption of power by the domestic category was 5946.78 MU in the year 2014-15 consisting of 2903.37 MU in the first half and 3043.72 MU in the second half of the year. APSPDCL Page 60 The consumption of power by the domestic category in the first half of the 2015-16 is 3703.11 MU. For the year 2015-16, APSPDCL has estimated the power consumption by the domestic category at 7099.72 MU, taking into account actual sales till September 2015. The sales forecast for FY 2015-16 has been done for the months October to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15 and adding the load relief quantum. The sales so arrived shall reflect the unrestricted sales (sales projected such that there would be no load shedding). The sales for second half of FY 2015-16 for this category will be 3396.62 MU. For the year 2016-17, the licensee has projected sales using an appropriate growth rate over 2015-16 projected sales (6 districts and Anantapur & Kurnool. The licensee has projected the unrestricted sales for FY 2016-17, as it would like to plan no load restriction measures for FY 2016-17. The unrestricted sales projected for FY 2016-17 for this category is 7953.09MU. The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 15.76% and for FY 2016-17 over FY 2015-16 is 12.02%. LT Cat-I MUs % Growth 5.1.3 2009-10 2010-11 3605.65 3861.84 7.11% 2011-12 2012-13 Actuals 4121.19 6.72% 4221.00 2.42% 2013-14 2014-15 4428.14 4.91% 5946.78 12.82% 2015-16 2016-17 Projections 7099.72 15.76% 7953.09 12.02% LT Cat-II: Non-Domestic / Commercial Supply The consumption of power by the non-domestic category was 1314.61 MU in the year 2014-15 consisting of 637.75 MU in the first half and 676.85 MU in the second half of the year. APSPDCL is experiencing an increase in the commercial activity thus necessitating an increase in the release of new services as well as higher levels of specific consumption by these commercial establishments. For 2015-16, the first half sales are 813.51 MU. The sales forecast for FY 2015-16 has been done for the months October to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the APSPDCL Page 61 corresponding months of FY 2014-15 and adding the load relief quantum. The sales so arrived shall reflect the unrestricted sales. The sales for second half of FY 2014-15 for this category are 771.66 MU. SPDCL has projected the sales for entire 2015-16 at 1585.17MU For the year 2016-17, the licensee has added a moderate growth rate of 11.23 % has been used to project the sales for FY 2016-17. The licensee has projected the unrestricted sales for FY 2016-17, as it would like to plan considering no load-shedding for FY 2016-17. The sales projected for FY 2016-17 for this category is 1763.12 MU. The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 16.53% and for FY 2016-17 over FY 2015-16 is 11.23%. LT Cat-II MUs % Growth 5.1.4 2009-10 2010-11 850.52 901.31 5.97% 2011-12 2012-13 Actuals 986.59 9.46% 983.56 -0.31% 2013-14 2014-15 977.02 -0.67% 1314.61 11.38% 2015-16 2016-17 Projections 1585.17 16.53% 1763.12 11.23% LT Cat-III: Industrial Supply The consumption of power by the category is 643.04 MU in 2014-15 consisting of 737.19 MU in the first half and 1380.24 MU in the second half of the year. During the year 2015-16, APSPDCL has achieved sales of 791 MU in the first half. The sales forecast for FY 2015-16 has been done for the months October to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15. Load relief quantities of corresponding months are added to arrive unrestricted sales projections. The sales so arrived shall reflect the unrestricted sales (sales projected such that there would be no load shedding). The sales for second half of FY 2015-16 for this category is805.78 MU. The overall sales for 2015-16 are likely to be around 1596.78 MU. For projecting sales of FY 2016-17, the Company has added a growth rate of 13.57% over FY 2015-16 sales. No load reliefis expected in the FY 2016-17. The licensee has projected the sales for this category as 1813.53 MU.The growth APSPDCL Page 62 rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 11.85% and for FY 2016-17 over FY 2015-16 is 13.57%. LT Cat-III MUs % Growth 5.1.5 2009-10 2010-11 740.82 796.76 7.55% 2011-12 2012-13 Actuals 989.83 24.23% 965.28 -2.48% 2013-14 2014-15 866.11 -10.27% 1380.24 27.67% 2015-16 2016-17 Projections 1596.78 11.85% 1813.53 13.57% LT-IV - Cottage Industries &Dhobighats etc., The consumption of power by this category is 32.32 MU in 2014-15 consisting of 14.58 MU in the first half and 17.75 MU in the second half of the year. The sales in this category during first half of 2015-16 is 18.56 MU. The sales forecast for FY 2015-16 has been done for the months October to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15. Load relief quantities of corresponding months are added to arrive unrestricted sales projections. The sales so arrived shall reflect the unrestricted sales (sales projected such that there would be no load shedding). The sales for second half of FY 2015-16 for this category are 19.61 MU. For the year 2016-17, the licensee has projected unrestricted sales using an appropriate growth rate over 2015-16 projected sales to arrive at 2016-17 unrestricted sales. Growth rate of 2015-16 unrestricted sales over 2015-16 revised sales is 8.77%.The licensee has projected the unrestricted sales for FY 2016-17 for this category is 41.52 MU.The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 12.37% and for FY 2016-17 over FY 2015-16 is 8.77%. LT Cat-IV MUs % Growth APSPDCL 2009-10 2010-11 24.52 25.01 1.96% 2011-12 2012-13 Actuals 24.42 -2.33% 22.17 -9.24% 2013-14 2014-15 21.58 -2.62% 32.32 13.74% 2015-16 2016-17 Projections 38.17 12.37% 41.52 8.77% Page 63 5.1.6 LT-V - Agriculture a) The Licensed area of APSPDCL covers eight Districts after bifurcation of AP state. Farmers in these eight Districts largely depend on lifting of ground water for their irrigation needs. The Energy Demand has been growing consistently over the past years. Usually, two crops are grown in a year and in some areas where plenty of water is available, particularly in Krishna and Guntur districts & part of other districts, third crop is also grown. Among all the crops, Paddy is the most preferred crop being grown in all the eight Districts resulting in high Energy Demand on Irrigation. In recent years, depth of water table is increased, resulting in increase in the Energy demand. b) Large no. of the pump sets under usage are of not as per standard specifications and such pump sets draw more Energy. Also the farmers are replacing the old pump sets with higher capacity pump sets whenever the depth of water table increases. c) The Government of Andhra Pradesh declared a modified agriculture policy in January 2005 aimed towards incentivizing Demand side management in the agriculture sector. One of the key features of the policy is to install Capacitors for all the existing pump sets. So far, 89.63%8of the existing pump sets as on 30.11.2015 are provided with Capacitors by the consumers. The licensee is taking all necessary steps to provide Capacitors for the balance pump sets also. d) There are 8,20,732 Nos. agricultural services in the licensee’s area as on 31-03-2014. Due to inclusion of Anantapur & Kurnool districts 3,17,152 Nos. agricultural services are added on 02-06-2014. During FY 2014-15, 54,011 Nos. of new agricultural connection are added, thus resulting in total no.of agricultural connections increased to 11,91,895 Nos. as on 31-03-2015. During FY 2015-16, the licensee has planned to release 87,600 Nos. agricultural connections, out of which 45,989 Nos. are released upto November, 2015. By this addition of new connections, the total no.of APSPDCL Page 64 agricultural connections in the licensee area will be 12,79,495 Nos. at end of FY 2015-16. Further, the licensee projects 50,000 Nos. new agricultural connections during FY 2016-17. The circle wise break up of no.of agricultural connections existing, added and projections for FY 2014-15 to FY FY 2016-17 are furnished in the table below: S.No Circle Existing as on 31-03-14 No.of agricultural services in APSPDCL Added Existing as Added Existing during on during as on 2015-16 31-03-16 2014-15 31-03-15 (Proj.) (Proj.) 3905 88211 8500 94694 Added during 2016-17 (Proj.) 4852 Existing as on 31-03-17 (Proj.) 99546 1 Vijayawada 84306 2 3 4 5 Guntur Ongole Nellore Tirupati 80614 127431 137086 260329 4457 9110 8311 5499 85071 136541 145397 265828 7500 15400 4900 4600 91323 146576 156083 285366 4281 8790 2797 2626 95604 155366 158880 287992 6 7 8 Kadapa Anantapur Kurnool APSPDCL 130966 6821 205724 127336 371163 137787 205724 127336 1191895 5100 29600 12000 87600 147914 220844 136695 1279495 2911 16894 6849 50000 150825 237738 143544 1329495 820732 e) The majority of the agricultural connections are with bore wells. Hence, the average capacity of the pump-sets are increasing at every year. The connected load details of agricultural connections are furnished in the below table: Connected load (HP) of agricultural services in APSPDCL S.No 1 2 3 4 5 6 7 8 Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool APSPDCL Existing as on 31-03-14 462495 382588 671975 636395 1471976 875405 4500834 Added during 2014-15 21393 21123 47973 38529 31049 45530 973075 524952 1703622 Existing as on 31-03-15 483887 403711 719948 674924 1503025 920935 973075 524952 6204456 Added during 2015-16 (Proj.) 34000 30000 77000 19600 18400 20400 115154 48000 362554 Existing as on 31-03-16 (Proj.) 517887 433711 796948 694524 1521425 941335 1088228 572952 6567009 Added during 2016-17 (Proj.) 43865 34702 73056 35426 63597 49931 116992 47320 464889 Existing as on 31-03-17 (Proj.) 561752 468413 870004 729950 1585022 991265 1205220 620272 7031898 f) Methods adopted for agricultural sales estimation : Sales estimation are being done following the agreed methodology. As per the directions of the Honourable Commission, the licensee has implemented “ISI APSPDCL Page 65 methodology agricultural sales estimation”. The following are the details of meters fixed in connection with the new methodology. S.No 1 Meters fixed to DTRs Circle No.of meters fixed Vijayawada 317 2 Guntur 3 Ongole 4 Nellore 5 Tirupati 6 Kadapa 7 Anantapur 8 Kurnool 314 451 395 1074 0 475 285 APSPDCL 3311 For Anantapur & Kurnool circles, sales estimations are being done based on ISI methodology from FY 2014-15. For Vijayawada, Guntur, Ongole, Nellore & Tirupati circles, the sales estimations are being done based on ISI methodology from June, 2015. Fixing of meters in Kadapa circle is under progress and sales estimation using ISI methodology will be done from next financial year. g) And hence, the sales estimates furnished in this chapter is based on ISI methodology for the areas provided with connected meters (from the date of fixing) and for remaining periods the sales estimations are based on the earlier agreed methodology. Hence, the licensee humbly requests the Honourable Commission to approve agricultural sales estimations made hereunder. h) Initiatives of the licensee to control agricultural sales in line with Tariff Order : The licensee has took all possible measures to control agricultural sales within the limits of Tariff Order. The following initiatives are taken in this regard. Strict implementation of 7 Hrs. supply-a-day. Anti pilferage measures. APSPDCL has taken Demand side management measures with publicity through handouts, electronic media etc., to the farmers to install energy efficient pump APSPDCL Page 66 sets, required rating of capacitors, HDPE pipe lines at suction and delivery and frictionless foot-valves to save energy and to avail subsidized tariff. Wide publicity is being given among the consumers on installation of capacitors With the initiatives of MNRE, Govt. of India, erection of solar pump sets project has been under taken at a large scale. PFCGEL is acting as financial agency, MNRE is giving 33% as subsidy, the consumer is contributing 11% and balance 56% is to be borne by the licensee. So far, 1032 Nos. (3HP : 13Nos and 5HP : 1019 Nos.) solar pump sets were commissioned at the end of November, 2015. Agreement entered with M/s EESL, New Delhi for conducting survey and preparation of DPR at Hindupurmandal of Anantapur district for AgDSM project (for replacement of existing old inefficient pump sets with ISI pump sets). Survey work is under progress. HVDS :The APSPDCL has taken to convert existing LT network in to HVDS for all agricultural connections. Majority of services in the districts of Vijayawada, Guntur, Prakasam, Nellore, Tirupati& Kadapa are already provided supply with HVDS. Schemes were prepared and are in process for completion balance works in the above said six districts and also cover all the services in Anantapur & Kurnool districts. i) Factors for increased agricultural sales : The following factors are expected for the increased agricultural sales in the licensee area. Due to increase in depth of water table, some of the farmers replaced existing pump sets resulting in increased energy demand. Many unauthorized additional loads are existing and pilferage cases are also noticed in the agricultural sector. All necessary steps are being carried out to regularize such cases or appropriate actions are being taken. APSPDCL Page 67 Releasing of agricultural services at a large number due to increasing demand for new services. Low rainfall in majority of the districts and low water levels in the projects. j) Sales estimates with ISI methodology for Anantapur & Kurnool districts : As stated above, sales estimates in respect of Anantapur & Kurnool circles are being done with ISI methodology. The sales estimations for FY 2014-15, H1 of FY 2015-16 and projections for H2 of FY 2015-16 & FY 2016-17 are furnished below: Details of DTRs existing and computation of sales per DTR : S.No Circle 1 2 Anantapur Kurnool Total S.No Circle 1 2 Anantapur Kurnool Total APSPDCL Apr-14 Apr15 39594 22798 62392 May14 May15 40139 22798 62937 DTRs Population for FY 2014-15 AugSepOctJul-14 14 14 14 32995 32995 33317 33442 33565 19085 19085 19566 19596 19619 52080 52080 52883 53038 53184 Jun-14 Jun15 40602 22798 63400 DTRs Population for FY 2015-16 JulAugSepOct15 15 15 15 41000 41403 41725 41993 22798 23266 23414 23540 63798 64669 65139 65533 Nov14 33790 19683 53473 Dec14 34084 19801 53885 Jan15 34461 20010 54471 Feb15 35054 20139 55193 Mar15 39125 22537 61662 Nov15 Dec15 Jan16 Feb16 Mar16 0 0 0 0 0 Page 68 k) Sales estimation for other six districts for FY 2014-15, FY 2015-16 & FY 2016-17 i) For FY 2014-15 & FY 2015-16 (upto May’15, as estimation based on ISI methodology started from the month of June, 2015), the Licensee has assessed the agricultural consumption for six Districts i.eVijayawada, Guntur, Ongole, Nellore, Chittoor and Kadapa based on readings of the meters provided on LV side of the Distribution Transformers feeding agricultural loads exclusively. The Licensee has done most of the representative sampling covering the existing 310 mandals of above six Districts. The sampled pump sets, under valid metered DTRs, comprise about 1.61% of total existing pump set population in the 6 districts of APSPDCL. 12 months common valid readings are available for 461 nos. DTRs. ii) The following procedure is adopted for assessing agricultural consumption: Meter readings are collected every month from the field for the metered DTRs feeding agricultural loads, exclusively, in the prescribed extended electronic format T.F.2.10 that has 27 columns. The recorded kWh per month is computed by taking the difference of the present meter reading and the previous meter reading. The net consumption (kWhNT) is calculated by deducting the line loss from recorded kWh (kWhNT total / Consumption). The kWhNT consumption of all the valid metered DTRs is summed up for each of the mandals. Based on the HP capacity under each valid DTR in a mandal, the total valid HP in each of the mandals is arrived at. The consumption per HP is computed for each of the mandal by dividing the total kWhNT in a mandal with valid HP of the mandal. Based on the total number of pump sets and their capacity (which is available in the master list for each of the mandal), the total mandal wise consumption APSPDCL Page 69 estimate is arrived at by multiplying the capacity with per HP consumption of that mandal. By adding together the consumption estimates of the various mandals, the total consumption for the district is arrived at. The summation of consumption figures for all the districts leads to the company’s consumption estimate. Such consumption estimates have been arrived based on the total valid meter readings received from the field and employing connected load at respective periods. Since the fixing of meters in Kadapa circle is under progress, the sales estimation for this circle for FY 2014-15 and H1 of 2015-16 are estimated based on the above said procedure using valid DTR LV side meter readings. iii) Sales estimation based on ISI methodology : Sales estimations are made based on ISI methodology from June, 2015 in respect of Krishna, Guntur, Prakasam, Nellore & Chittoor districts. iv) For FY 2015-16 (H2) & FY 2016-17, sales projections are made based on the historical sales, considering new services released / to be released and anticipated seasonal changes. v) The actual sales estimated and projections made as discussed in the above paras (i), (ii) & (iii) are furnished in the below tables. APSPDCL Page 70 Paying category services consumption Paying category services consumption Existing services as on 01-4-14 Existing connected load as on 01-04-14 30591 163458.16 consumption in Mus during FY 2014-15 159.51 Consumption per HP in units Per Month Per Year 81.32 975.86 The above sales are included in the sales estimation made in the earlier para. The following issues were considered while projecting agricultural consumption for FY 2015-16 and for the next year 2016-17: The consumption of power by the category is 8006.78 MU in 2014-15 consisting of 3647.33 MU in the first half and 4359.45 MU in the second half of the year. While the consumption during 2014-15 H2 is higher than that of H1, the same trend is expected to continue in second half of 2015-16. The Agricultural consumption during H2 of 2015-16 is expected to be higher than H1 and is estimated at 4679.85 MU. Growth in agriculture restricted sales are linked to the growth rate in agriculture connections as mentioned above. The licensee is projecting 3.91% growth in sales for FY 2016-17 over the total sales for FY 2014-15. The licensee is confident that the growth-rate APSPDCL Page 71 projected would take care of the increase in specific consumption, consumption increase because of new services to be released in 2016-17 LT Cat-V MUs % Growth 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 Actuals 4167.82 3664.49 -12.08% 4366.34 19.15% 4587.91 5.07% 5513.46 20.17% 8006.78 4.12% 2015-16 2016-17 2016-17 Projections (7Hrs.) 9 Hrs. 8392.70 0.63% 8720.67 3.91% 11,212.28 33.60% The licensee has assumed 7 hours of supply to agricultural consumers, in its projections, considering the present power supply situation in the state. 5.1.7 LT Category- VI: Local bodies, Street lighting and public waterworks The consumption of power by the category is 489.42 MU in 2014-15 consisting of 232.77 MU in the first half and 256.65 MU in the second half of the year. The Consumption of street light and public water works in the first half of 2015-16 is 264.43 MU. The sales forecast for FY 2015-16 has been done for the months October to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15. Load relief quantities of corresponding months are added to arrive unrestricted sales projections. The sales so arrived shall reflect the unrestricted sales. The sales for second half of FY 2015-16 for this category is 262.16MU. For the year 2016-17, the Licensee has added a moderate growth rate of 2.06% to project the sales for FY 2016-17. The sales projected for FY 2016-17 for this category is 537.42 MU.The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 1.84% and for FY 2016-17 over FY 2015-16 is 2.06%. LT Cat-VI MUs % Growth APSPDCL 2009-10 2010-11 533.87 419.62 -21.40% 2011-12 2012-13 Actuals 412.35 -1.73% 394.51 -4.33% 2013-14 2014-15 327.53 -16.98% 489.42 5.13% 2015-16 2016-17 Projections 526.59 1.84% 537.42 2.06% Page 72 5.1.8 LT Category VII : General purpose The consumption of power by the category was 77.14 MU in 2014-15 consisting of 34.49 MU in the first half and 42.65 MU in the second half of the year. The Consumption of general purpose category in the first half of 2015-16 is 44.37 MU. The sales forecast for FY 2015-16 has been done for the months October to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15 and adding the load relief quantum. The sales so arrived shall reflect the unrestricted sales (sales projected such that there would be no load shedding). The sales for second half of FY 2015-16 for this category are45.15 MU. For the year 2016-17, the licensee has projected sales using an appropriate growth rate over 2015-16 restricted sales. Growth rate of 2016-17 unrestricted sales over 2015-16 projected sales is 8.41%. The licensee has projected the unrestricted sales for FY 2016-17 for this category is 97.05 MU. The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 9.90% and for FY 2016-17 over FY 2015-16 is 8.41%. LT Cat-VII MUs % Growth 2009-10 2010-11 43.69 46.87 7.28% 2011-12 2012-13 Actuals 49.02 4.59% 48.47 -1.12% 2013-14 2014-15 47.13 -2.77% 77.14 15.87% 2015-16 2016-17 Projections 89.52 9.90% 97.05 8.41% HT sales forecast Details of the trends envisaged for key categories are discussed in the following sections. HT Cat-I – Industrial 5.1.9 The consumption of power by the HT-Industrial category is 6932.50 MU in 2014-15 consisting of 3282.95 MU in the first half and 3649.54 MU in the second half of the year. APSPDCL Page 73 The consumption of power by the HT-Industrial category in the first half of the 201516 is 3707.31 MU. The sales forecast for FY 2015-16 has been done for the months October’15 to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15 and adding the load relief units. The sales so arrived shall reflect the unrestricted sales. The sales for second half of FY 2015-16 for this category is 4111.28 MU. For the year 2016-17, the licensee has projected sales using an appropriate growth rate over 2015-16 projected. The licensee has projected sales for this category is 8914.53 MU.The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 8.21% and for FY 2016-17 over FY 2015-16 is 14.02%. HT Cat-I 11 KV 33 KV 132 KV Total Sales % Growth 2009-10 2010-11 716.78 1236.78 646.72 2600.28 849.31 1769.39 912.04 3530.74 35.78% 2011-12 2012-13 Actuals 843.68 2020.60 1251.34 4115.62 16.57% 800.39 1909.48 1179.34 3889.21 -5.50% 2013-14 2014-15 1036.54 2056.20 1319.95 4412.70 13.46% 1415.43 3119.20 2397.88 6932.50 18.10% 2015-16 2016-17 Projections 1562.58 3572.32 2683.69 7818.59 8.21% 1804.40 4059.34 3050.79 8914.53 14.02% 5.1.10 HT Cat-II: Non-Industrial (Others) The consumption of power by the HT Non-Industrial category was 553.31 MU in the year 2014-15 consisting of 280.53 MU in the first half and 272.79 MU in the second half of the year. The consumption for the category is 347.51 MU in the first half of the 2015-16. The sales forecast for FY 2015-16 has been done for the months October’15 to March 2016 by projecting an appropriate growth rate over the sales (6 districts and Anantapur & Kurnool) of the corresponding months of FY 2014-15 and adding the load relief units. The sales so arrived shall reflect the unrestricted sales. The sales for second half of FY 2015-16 for this category is 307.68 MU. For the year 2016-17, the licensee has projected sales using an APSPDCL Page 74 appropriate growth rate over 2015-16 projected. Growth rate of 2016-17 unrestricted sales over 2015-16 revised sales is 15.12%. The licensee has projected the unrestricted sales for FY 2016-17, considering no load restriction measures for FY 2016-17. The sales projected for FY 2016-17 for this category is 754.27 MU.The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 16.67% and for FY 2016-17 over FY 2015-16 is 15.12%. 2009-10 2010-11 11 KV 33 KV 132 KV 292.89 35.54 0.00 311.54 40.91 0.00 335.93 43.67 0.00 Total Sales 328.43 352.45 7.31% HT Cat-II % Growth 2011-12 2012-13 Actuals 2013-14 2014-15 2015-16 2016-17 Projections 348.18 70.73 3.96 362.91 73.46 10.43 455.62 80.94 16.75 539.67 93.43 22.09 621.30 107.57 25.40 379.60 422.86 446.79 553.31 655.19 754.27 7.70% 11.40% 5.66% 12.13% 16.67% 15.12% 5.1.11 HT III: Airports, Bus Stations and Railway Stations: The sales projections for this category of consumers are given below for FY 2015-16 and FY 2016-17. Aviation 11 KV % Growth 2009-10 2010-11 0.00 0.00 2011-12 2012-13 Actuals 0.00 1.28 2013-14 2014-15 8.56 567.27% 17.87 78.33% 2015-16 2016-17 Projections 21.57 10.22% 23.69 9.81% 5.1.12 HT Cat-IV: Irrigation & Agriculture The consumption of power by the HT Irrigation & Agriculture category was 528.35 MU in 2014-15 consisting of 59.56 MU in the first half and 468.79 MU in the second half of the year. The consumption for the category is 64.23 MU in the first half of the 2015-16. APSPDCL projects 470.13 MU in the second half for the 2015-16. The Licensee has collected the likely commissioning dates of the upcoming lift irrigation schemes in consultation with irrigation department and projected the sales for FY2016-17. In APSPDCL, the following are major State Government Lift Irrigation Schemes are expected to be operational. APSPDCL Page 75 Accordingly, APSPDCL is projecting a sale of 1973.91 MU during 2016-17. The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 201415 is -5.42% and for FY 2016-17 over FY 2015-16 is 269.39%. 2009-10 2010-11 11 KV 33 KV 132 KV 22.76 6.61 0.00 20.19 7.26 0.00 50.89 10.42 0.00 Total Sales 29.37 27.45 -6.52% HT Cat-IV % Growth 2011-12 2012-13 Actuals 2013-14 2014-15 2015-16 2016-17 Projections 29.73 6.54 0.00 43.31 5.38 0.00 137.08 63.15 328.13 143.90 81.18 309.28 151.95 84.78 1737.17 61.31 36.27 48.69 528.35 534.36 1973.91 123.33% -40.84% 34.25% 58.47% -5.42% 269.39% 5.1.13 HT Cat-V: Railway traction The consumption of power by this category was 747.84 MU in FY 2014-15 consisting of 370.21 MU in the first half and 377.63 MU in the second half of the year. For 2015-16, the consumption for the first half is 354.99 MU and APSPDCL has projected consumption of 413.80 MU for the second half. The overall consumption for the 2015-16 is 768.79MU. The projected consumption for the 2016-17 is 830.88 MU. The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 2.28% and for FY 2016-17 over FY 2015-16 is 8.08%. HT Cat-V 132 KV % Growth APSPDCL 2009-10 2010-11 522.15 521.40 -0.14% 2011-12 2012-13 Actuals 569.54 9.23% 609.65 7.04% 2013-14 2014-15 646.15 5.99% 747.84 15.31% 2015-16 2016-17 Projections 768.79 2.28% 830.88 8.08% Page 76 5.1.14 HT Cat-VI: Townships and Residential Colonies The consumption of power by this category was 34.48 MU in the 2014-15 consisting of 16.48 MU in the first half and 18.00 MU in the second half of the year. For 2015-16, the consumption for the first half is 21.26 MU and APSPDCL has projected a consumption of 18.52 MU for the second half as the consumption of this category. APSPDCL is projecting an expected growth rate of 5.03 % for FY 2016-17 resulting in 41.77MU(unrestricted sales).The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 5.71% and for FY 2016-17 over FY 2015-16 is 5.03%. HT Cat-VI 11 KV 33 KV 132 KV Total Sales % Growth 2009-10 2010-11 47.55 1.05 0.00 48.60 51.03 0.00 0.00 51.03 5.01% 2011-12 2012-13 Actuals 33.99 1.48 0.00 35.47 -30.51% 26.53 0.82 0.00 27.35 -22.89% 2013-14 2014-15 21.39 0.77 0.00 22.16 -18.97% 33.04 1.44 0.00 34.48 2015-16 2016-17 Projections 37.80 1.97 0.00 39.77 5.71% -9.45% 39.60 2.17 0.00 41.77 5.03% 5.1.15 HT Cat-VIII : RESCOs The consumption of power by this category was 284.31 MU in 2014-15 consisting of 137.23 MU in the first half and 147.07 MU in the second half of the year. For the year 2015-16, APSPDCL has projected increase in consumption to 301.96 MU, out of which the first half sales accounts for 139.51 MU. The projected consumption for 2016-17 is 328.40 MU. The growth rate of sales for 8 districts (6 districts and Anantapur & Kurnool) for FY 2015-16 over FY 2014-15 is 6.21% and for FY 2016-17 over FY 2015-16 is 8.76%. Resco 11 KV % Growth 2009-10 2010-11 199.44 241.74 21.21% 2011-12 2012-13 Actuals 275.53 13.98% 234.74 -14.80% 2013-14 2014-15 257.40 9.65% 284.31 10.45% 2015-16 2016-17 Projections 301.96 6.21% 328.40 8.76% Sales Forecast category wise and Voltage level wise (Form – 3) Sales in MU APSPDCL Page 77 2009-10 2010-11 2011-12 2012-13 2013-14 2015-16 2016-17 (Proj.) (Proj.) 2014-15 Category Actuals LT Category 9968.21 9716.43 10951.15 11223.49 12181.94 17262.87 19344.29 20942.05 Domestic 3605.65 3861.84 4121.19 4221.00 4428.14 5946.78 7099.72 7953.09 Non-domestic/Commercial 850.52 901.31 986.59 983.56 977.02 1314.61 1585.17 1763.12 Industrial 740.82 796.76 989.83 965.28 866.11 1380.24 1596.78 1813.53 24.52 25.01 24.42 22.17 21.58 32.32 38.17 41.52 4167.82 3664.49 4366.34 4587.91 5513.46 8006.78 8392.70 8720.67 533.87 419.62 412.35 394.51 327.53 489.42 526.59 537.42 43.69 46.87 49.02 48.47 47.13 77.14 89.52 97.05 1.31 0.55 1.40 0.59 0.96 15.57 15.65 15.65 1280.22 1473.82 1540.02 1440.86 1730.18 2343.35 2606.44 2968.30 695.90 727.84 702.16 690.10 875.16 1146.52 1251.79 1448.03 17.04 20.58 8.02 1.67 1.89 31.67 39.76 45.36 Industrial Colonies 1.16 1.56 1.76 2.33 1.40 2.50 2.61 2.89 Seasonal Industries 0.00 23.12 24.45 36.06 40.95 59.05 65.03 72.83 Time of Day Tariffs (6 PM to 10 PM) 0.00 76.21 107.29 70.24 117.14 175.69 203.40 235.28 HT I (B): Ferro Alloy Units 2.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 292.89 311.54 335.93 292.28 304.15 377.31 447.77 514.95 Time of Day Tariffs (6 PM to 10 PM) 0.00 0.00 0.00 55.89 58.75 78.31 91.90 106.35 HT III: Aviation & Stations 0.00 0.00 0.00 1.28 7.22 14.59 17.32 19.05 Time of Day Tariffs (6 PM to 10 PM) 0.00 0.00 0.00 0.00 1.33 3.28 3.21 3.60 22.76 17.26 40.41 19.32 27.09 88.38 86.60 86.65 HT IV Agriculture 0.00 0.54 9.79 0.31 0.00 23.95 17.55 17.90 HT IV CPWS 0.00 2.39 0.69 10.10 16.23 24.75 39.75 47.41 47.55 51.03 33.99 26.53 21.39 33.04 37.80 39.60 HT VII: Green Power 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 HT VIII: Temporary 0.80 0.00 0.00 0.00 0.08 0.00 0.00 0.00 Cottage Industries, Dhobighats& Others Irrig& Agriculture Local Bodies, St. Lighting & PWS General Purpose Temporary Supply HT Category at 11 kv HT I (A): General Lights and Fans HT II: Others HT IV Government LIS HT VI: Townships & Residential Colonies APSPDCL Page 78 Category 2009-10 2010-11 2011-12 2012-13 2013-14 2015-16 2016-17 (Proj.) (Proj.) 2014-15 199.44 241.74 275.53 234.74 257.40 284.31 301.96 328.40 HT Category at 33 kv 1279.98 1817.55 2076.16 1987.56 2135.81 3264.72 3749.95 4254.90 HT I (A): General 1179.48 1482.15 1625.99 1652.33 1728.35 2405.91 2766.85 3154.29 Lights and Fans 5.65 6.21 3.01 0.60 0.48 32.09 40.59 46.27 Industrial Colonies 2.29 4.59 7.07 9.34 7.26 11.20 11.44 13.05 Seasonal Industries 0.00 33.28 27.73 34.88 33.83 45.39 47.13 53.73 Time of Day Tariffs (6 PM to 10 PM) 0.00 159.51 251.28 156.71 220.51 393.86 486.18 554.26 HT I (B): Ferro Alloy Units 49.36 83.66 105.52 55.63 65.77 230.75 220.14 237.75 HT II: Others 35.54 40.91 43.67 60.83 62.18 67.62 77.72 89.48 Time of Day Tariffs (6 PM to 10 PM) 0.00 0.00 0.00 9.90 11.28 13.32 15.71 18.08 HT III: Aviation & Stations 0.00 0.00 0.00 0.00 0.00 0.00 0.99 0.99 Time of Day Tariffs (6 PM to 10 PM) 0.00 0.00 0.00 0.00 0.00 0.00 0.06 0.06 HT IV Government LIS 6.61 6.53 10.16 5.58 5.38 37.70 39.35 39.38 HT IV Agriculture 0.00 0.00 0.26 0.00 0.00 10.20 9.81 10.00 HT IV CPWS 0.00 0.72 0.00 0.95 0.00 15.25 32.02 35.40 HT VI: Townships & Residential Colonies 1.05 0.00 1.48 0.82 0.77 1.44 1.97 2.17 HT VII: Green Power 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 HT VIII: Temporary 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Category: RESCOs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1168.87 1433.44 1820.88 1792.94 1976.53 3490.59 3783.85 5644.24 640.23 825.77 1109.07 1036.33 1107.02 1914.08 2112.03 2407.78 Lights and Fans 0.82 2.13 0.58 0.81 0.50 15.41 24.78 28.25 Industrial Colonies 5.66 5.36 5.96 10.01 5.81 12.38 13.92 15.87 Seasonal Industries 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Time of Day Tariffs (6 PM to 10 PM) 0.00 78.78 135.73 87.44 119.84 317.23 388.01 442.34 HT I (B): Ferro Alloy Units 0.00 0.00 0.00 44.74 86.78 138.77 144.95 156.55 HT II: Others 0.00 0.00 0.00 3.42 8.85 14.25 18.78 21.60 Category: RESCOs HT Category at 132 kv HT I (A): General APSPDCL Page 79 Category 2009-10 2010-11 2011-12 2012-13 2013-14 2015-16 2016-17 (Proj.) (Proj.) 2014-15 Time of Day Tariffs (6 PM to 10 PM) 0.00 0.00 0.00 0.54 1.58 2.50 3.30 3.80 HT III: Aviation & Stations 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Time of Day Tariffs (6 PM to 10 PM) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 HT IV Government LIS 0.00 0.00 0.00 0.00 0.00 328.13 309.28 1737.17 HT IV Agriculture 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 HT IV CPWS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 522.15 521.40 569.54 609.65 646.15 747.84 768.79 830.88 HT VI: Townships & Residential Colonies 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 HT VII: Green Power 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 HT VIII: Temporary 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Category: RESCOs 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13697.27 14441.24 16388.21 16444.85 18024.46 26361.53 29484.53 33809.49 HT V: Railway Traction Total (LT + HT) 5.2 Revenue from Current Tariffs APSPDCL Page 80 The computation of revenue at current tariff for FY 2015-16 and FY 2016-17 for each customer category is carried out as follows: Revenue from Tariffs = Energy Estimate * Approved Energy Charges … ……………………..……….. (a) + Demand Estimate * Approved Demand Charges …….……………………..... (b) + Incremental Revenue on account of Monthly Minimum Charges (‘MMC’) … (c) + Customer Charges (d) + Other Charges ----- (e) Energy charges: For customer categories having telescopic energy tariffs, the energy estimates have been apportioned into the slabs and then have been multiplied with the corresponding slab tariff. The apportionment has been based on the historical break up of telescopic consumption into the various slabs as captured in the billing information database. The energy charges are calculated as per the billing parameters i.e., KWH and KVAH for the category and the existing tariff rates of that category Demand/Fixed Charges: The estimate of demand has been made in “HP” or in “MVA” as the case maybe. Billing demand has been assumed to grow in proportion to the growth of sales in FY 2016-17. Additional demand due to additional load has been added to arrive at final demand for the year FY 2016-17. Monthly Minimum charges (MMC): The ‘incremental’ revenue due to MMC for each category is the difference between cost of units recorded and computed units billed at the relevant tariff in respect of HT categories. In respect of LT categories, it is the difference between the cost of units recorded and monthly minimum charges notified in the tariff order. Customer Charges: Customer charges are as approved in tariff Order for each of the category of consumers. As per the revised regulatory formats income from customer charges is considered as part of revenue from tariffs. Other Charges: These are the charges other than the above charges. There are no “other charges” proposed for FY 2016-17. Based on the above approach, the gross revenue (excl. NTI) for FY 2015-16 is expected to be Rs 12117.14 Cr, while that for FY 2016-17 is expected to be Rs 14493.43 Cr. The NTI APSPDCL Page 81 for FY 2015-16 is Rs. 76.34 Crs., while for FY 2016-17 NTI isRs. 79.33 crores. The table below provides the category-wise revenue for FY 2015-16 and FY 2016-17: Category-wise revenue (Excl NTI) (Form-5) Category LT Category Domestic Non-domestic/Commercial Industrial Cottage Industries, Dhobighats& Others Irrig& Agriculture Local Bodies, St. Lighting & PWS General Purpose Temporary Supply HT Category at 11 kv HT I (A): General Lights and Fans Industrial Colonies Seasonal Industries Time of Day Tariffs (6 PM to 10 PM) HT I (B): Ferro Alloy Units HT II: Others Time of Day Tariffs (6 PM to 10 PM) HT III: Airports, Bus Stations and Railway Stations Time of Day Tariffs (6 PM to 10 PM) HT IV Government LIS HT IV Agriculture HT IV CPWS HT VI: Townships & Residential Colonies HT VII: Green Power HT VIII: Temporary Category: RESCOs HT Category at 33 kv HT I (A): General Lights and Fans Industrial Colonies Seasonal Industries Time of Day Tariffs (6 PM to 10 PM) APSPDCL (Rs. Crores) 2015-16 5487.86 2537.19 1465.43 1043.78 15.54 59.10 289.88 61.45 15.50 1835.32 1004.12 23.94 1.56 47.14 143.80 0.00 413.67 76.28 14.31 2.56 49.33 9.90 18.39 23.09 0.00 0.00 7.25 2434.81 1811.41 22.61 6.82 31.06 321.85 2016-17 6185.36 2925.69 1622.52 1180.39 16.42 62.82 295.57 66.44 15.50 2106.73 1162.46 27.31 1.72 52.80 166.34 0.00 475.54 88.27 15.57 2.86 49.31 10.10 22.37 24.18 0.00 0.00 7.88 2765.26 2065.01 25.77 7.78 35.40 366.92 Page 82 Category HT I (B): Ferro Alloy Units HT II: Others Time of Day Tariffs (6 PM to 10 PM) HT III: Airports, Bus Stations and Railway Stations Time of Day Tariffs (6 PM to 10 PM) HT IV Government LIS HT IV Agriculture HT IV CPWS HT VI: Townships & Residential Colonies HT VII: Green Power HT VIII: Temporary Category: RESCOs HT Category at 132 kv HT I (A): General Lights and Fans Industrial Colonies Seasonal Industries Time of Day Tariffs (6 PM to 10 PM) HT I (B): Ferro Alloy Units HT II: Others Time of Day Tariffs (6 PM to 10 PM) HT III: Airports, Bus Stations and Railway Stations Time of Day Tariffs (6 PM to 10 PM) HT IV Government LIS HT IV Agriculture HT IV CPWS HT V: Railway Traction HT VI: Townships & Residential Colonies HT VII: Green Power HT VIII: Temporary Category: RESCOs Total (LT + HT) 2015-16 115.14 69.30 12.00 0.80 0.04 22.25 5.53 14.77 1.23 0.00 0.00 0.00 2359.14 1323.30 12.76 8.30 0.00 240.56 69.72 14.00 2.44 0.00 0.00 174.46 0.00 0.00 513.60 0.00 0.00 0.00 0.00 12117.14 2016-17 124.36 79.78 13.82 0.80 0.04 22.25 5.64 16.34 1.35 0.00 0.00 0.00 3436.09 1508.76 14.55 9.46 0.00 274.25 75.31 16.09 2.80 0.00 0.00 979.79 0.00 0.00 555.08 0.00 0.00 0.00 0.00 14493.43 5.3 Detailed category wise Revenue computation The detailed category wise computation of revenue is as follows. APSPDCL Page 83 5.3.1 Low Tension Categories 5.3.1.1 LT I: Domestic Category At present, domestic consumers are billed on the basis of monthly consumption only. The licensee submits that the existing tariff structure has the following drawbacks: Tariff shock observed by consumers on the verge of moving from one slab to another: Consumption in Units Category Bill in Rs / month 100 Category I (B) 233 101 Category I (C) 300 200 Category I (C) 667 201 Category I (D) 877 Additional Charge for extra unit in Rs 66 210 Tariff is dynamic based on consumption during the month. Consumers can not be designated with any sub-cateogry of Domestic due to non-static consumption of a consumption. Tariffs are independent of affordability / income level of consumers: Under the existing tariff regime, high-income consumers are likely to enjoy concessional tariffs intended for low-income consumers, in case their consumption during any month is reduced. Exif a consumer having an average consumption of 200 units/month consumes 30 units/month will be charged at 1.45 / unit. Non requirement of sub-category LT I(A) in presence of LT (B). Considering above, the licensee would like to propose simplied tariff structure of Domestic category by grouping consumers, with no tariff change, based on certain conditions as shown below: Group A: Domestic consumers with annual consumption upto 600 Units ( upto 50 units/ month) Group B: Domestic consumers with annual consumption greater than 600 Units and upto 2,400 Units Group C: Domestic consumers with annual consumption more than 2,400 Units and all three-phase consumers Grouping of domestic consumers will be done based on annual consumption of FY 2015-16 during the start of FY 2016-17 and will continue to be in the same group till the annual threshold limits stipulated above. In case of a new consumer, the following rules will be applicable APSPDCL Group A - if a consumer is Domestic consumers Page 84 .The existing tariff structure is as under: Existing Category / Slab Structure (Units) Energy charge (Rs./Unit) LT I (A): Upto 50 Units/Month 1.45 LT I (B): Above 50 Units/Month and Up to 100 Units/Month <50 1.45 51-100 2.60 LT I (C): Above 100 Units/Month and Up to 200 Units/Month <50 2.60 51-100 2.60 101-150 3.60 151-200 3.60 <50 2.60 51-100 3.25 101-150 4.88 151-200 5.63 201-250 6.70 251-300 7.22 301-400 7.75 401-500 8.27 >500 8.80 LT I (D): Above 200 Units/Month The licensee proposes a simplified tariff structure with grouping, with no change in in tariff, as under: Proposed Category / Slab Structure (Units) Energy charge (Rs./Unit) Group A: Domestic consumers with annual consumption < = 600 Units 0-50 1.45 51-100 2.60 101-200 3.60 APSPDCL Page 85 Above 200# 6.90 Group B: Domestic consumers with consumption ( < =2400 and > 600 units) 0-50 2.60 51-100 2.60 101-200 3.60 201-300 6.90 Above 300 7.75 Group C: Domestic consumers with annual consumption >2400 units 0-50 2.60 51-100 3.25 101-200 5.26 201-300 6.90 301-400 7.75 401-500 8.27 Above 500 units 8.80 # computed average existing tariff for a consumer whose consumption is > 200 but < 300 units Estimated revenue for FY 2015-16 & FY 2016-17 are submitted below: Year 2015-16 2016-17 Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2231.56 2600.28 0.00 0.00 66.84 68.18 238.79 257.23 0.00 0.00 2537.19 2925.69 Based on the above the total revenue estimate for the category is Rs.2537.19 Crores for 2015-16 and Rs.2925.69 Crores for 2016-17. 5.3.1.2 LT II: Non-Domestic & Commercial Category Slab-wise Breakup of Revenue APSPDCL Page 86 The incremental revenue due to the impact of the monthly minimum charges over and above the revenue from stated tariff rates in shown below. Revenue from Tariffs Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 1356.20 1509.94 69.07 71.20 13.23 13.62 26.94 27.76 0.00 0.00 1465.43 1622.52 Based on the above the total revenue estimate for the category is Rs.1465.43 Crores for 2015-16 and Rs.1622.52 Crores for 2016-17. 5.3.1.3 LT III : Industrial (Normal & Optional) Category Due to very different tariff structures between Pisciculture/ Prawn culture and nonpisciculture units, the revenue computation has been done separately for the two subcategories and is shown below: APSPDCL Page 87 Energy Charges (Rs crores) Sub-Cat Industries Seasonal Industries (off season) 2015-16 Demand Minimum /Fixed Charges charges (Rs crores) (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 892.90 54.23 0.00 3.45 0.00 950.58 0.00 0.00 0.00 0.00 0.00 0.00 1.15 0.01 0.00 0.00 0.00 55.39 2016-17 55.86 0.00 1.19 0.01 0.00 0.00 0.00 57.05 0.00 0.00 0.00 0.00 0.00 0.00 0.71 0.00 0.00 0.00 0.00 4.16 0.00 0.00 0.00 0.00 0.00 0.00 92.95 0.24 0.00 0.00 0.00 1043.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.56 0.00 0.71 0.00 0.00 0.00 0.00 4.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1078.02 0.00 102.11 0.27 0.00 0.00 0.00 1180.39 Pisciculture/Prawn culture Sugarcane crushing Poultry farms Mushroom and Rabbit farms Floriculture in Green House Total 91.09 0.23 0.00 0.00 0.00 984.23 Industries Seasonal Industries (off season) Pisciculture/Prawn culture Sugarcane crushing Poultry farms Mushroom and Rabbit farms Floriculture in Green House Total 1018.60 0.00 100.21 0.26 0.00 0.00 0.00 1119.06 The total revenue estimate for the category is Rs 1043.78 Crores for 2015-16 and Rs.1180.39 Crores for 2016-17. 5.3.1.4 LT IV: Cottage Industries &Dhobighat Category Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 14.31 15.57 0.83 0.46 0.00 0.00 0.39 0.40 0.00 0.00 15.54 16.42 The total revenue estimate for the category is Rs 15.54 Crores for 2015-16 and Rs.16.42 Crores for 2016-17. 5.3.1.5 LT V: Agriculture Category The revenue from agricultural category has been computed with reference to each subcategory. Agricultural consumers following DSM measures with less than or equal to APSPDCL Page 88 three service connections or agricultural consumers having agricultural land less than or equal to 2.5 acres are eligible for free power. The other subcategories come under paying category. The revenue computation from the category is given below: Energy Charges (Rs. Crs.) Category V - Irrigation and Agriculture Category V (A) - Agriculture (DSM) Corporate Farmers & IT Assesses Wet Land Farmers (Holdings >2.5 acre) Dry Land Farmers (Connections > 3 nos.) Wet Land Farmers (Holdings <= 2.5 acre) Dry Land Farmers (Connections <= 3 nos.) Category V (B) - Agriculture (Non-DSM) Corporate Farmers & IT Assesses Wet Land Farmers (Holdings >2.5 acre) Dry Land Farmers (Connections > 3 nos.) Wet Land Farmers (Holdings <= 2.5 acre) Dry Land Farmers (Connections <= 3 nos.) Category - V (C) - Others Category V(A)(i) Salt Farmers Category V(A)(ii) Rural Horticulture Nurseries Total 2015-16 2016-17 57.93 7.41 5.23 1.90 6.51 36.88 1.17 0.39 0.68 0.08 0.01 0.01 0.00 0.00 0.00 59.10 61.63 7.70 5.42 1.98 6.98 39.56 1.19 0.40 0.69 0.08 0.01 0.01 0.00 0.00 0.00 62.82 Based on the above computations the gross revenue from agricultural category is Rs.59.10 Crores for FY 2015-16 and Rs.62.82 Crores for FY 2016-17. 5.3.1.6 LT VI: Street Lighting & PWS Category 2015-16 Sub-Cat Street Lighting PWS Scheme NTR SujalaPadhakam Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 108.78 169.03 0.26 2.36 6.54 0.00 0.00 0.00 0.00 1.66 1.25 0.00 0.00 0.00 0.00 112.80 176.82 0.26 Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2016-17 Sub-Cat APSPDCL Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Page 89 Street Lighting PWS Scheme NTR SujalaPadhakam 110.96 172.41 0.39 2.67 6.60 0.00 0.00 0.00 0.00 1.67 1.26 0.00 0.00 0.00 0.00 115.30 180.27 0.39 The total revenue estimate for the category is Rs.289.88 Crores for 2015-16 and Rs.295.96 Crores for 2016-17. 5.3.1.7 LT VII: General Purpose Category Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 59.79 64.88 0.13 0.16 1.15 1.18 0.39 0.23 0.00 0.00 61.45 66.44 The total revenue estimate for the category is Rs.61.45 Crores for 2015-16 and Rs.66.44 Crores for 2016-17 5.3.1.8 LT VIII: Temporary supply Category Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 15.50 15.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.50 15.50 The total revenue estimate for the category is Rs.15.50 Crores for 2015-16 and Rs.15.50 Crores for 2016-17. 5.3.2 High Tension Categories 5.3.2.1 HT Cat-I: Industrial 2015-16 APSPDCL Page 90 Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Total 970.01 2038.60 1419.04 4427.65 232.40 266.67 232.90 731.97 11 KV 33 KV 132 KV Total 1119.89 2317.15 1613.57 5050.61 268.82 304.00 265.51 838.33 Voltage 11 KV 33 KV 132 KV Minimum Charges (Rs crores) 14.21 3.20 2.59 20.00 2016-17 17.86 3.66 3.14 24.66 3.94 0.42 0.11 4.47 0.00 0.00 0.00 0.00 Gross Revenue from Tariff (Rs crores) 1220.56 2308.89 1654.64 5184.09 4.06 0.43 0.11 4.60 0.00 0.00 0.00 0.00 1410.64 2625.24 1882.33 5918.21 Customer Charges (Rs crores) Others (Rs crores) Based on the above the total revenue estimate for the category is Rs.5184.09 Crores for 2015-16 and Rs.59188.21 Crores for 2016-17. 5.3.2.2 HT Cat-II: Others 2015-16 Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) 11 KV 33 KV 132 KV Total 400.91 63.22 14.33 478.46 85.04 18.01 2.08 105.13 11 KV 33 KV 132 KV Total 461.61 72.78 16.48 550.87 97.79 20.73 2.39 120.92 Voltage Minimum Charges (Rs crores) 2.26 0.02 0.00 2.28 2016-17 2.58 0.02 0.00 2.60 1.75 0.06 0.02 1.83 0.00 0.00 0.00 0.00 Gross Revenue from Tariff (Rs crores) 489.95 81.30 16.44 587.69 1.83 0.06 0.02 1.91 0.00 0.00 0.00 0.00 563.81 93.60 18.90 676.31 Customer Charges (Rs crores) Others (Rs crores) Based on the above consumption the total revenue estimate for the category is Rs.587.69 Crores for 2015-16 and Rs.676.31 Crores for 2016-17. 5.3.2.3 HT Cat-III : Aviation activity at Airports APSPDCL Page 91 Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 15.19 16.69 2.47 2.54 0.00 0.00 0.05 0.05 0.00 0.00 17.71 19.28 Based on the above consumption the total revenue estimate for the category is Rs.17.71 Crores for 2015-16 and Rs.19.28 Crores for 2016-17. 5.3.2.4 HT Cat- IV: Irrigation & Agriculture 2015-16 Voltage Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) 11 KV 33 KV 132 KV Total 77.07 42.49 174.43 293.99 0.00 0.00 0.00 0.00 11 KV 33 KV 132 KV Total 80.82 44.17 979.77 1104.75 0.00 0.00 0.00 0.00 Minimum Charges (Rs crores) 0.55 0.06 0.02 0.63 0.00 0.00 0.00 0.00 Gross Revenue from Tariff (Rs crores) 77.61 42.55 174.46 294.62 0.57 0.06 0.02 0.65 0.00 0.00 0.00 0.00 81.39 44.23 979.79 1105.41 Customer Charges (Rs crores) 0.00 0.00 0.00 0.00 2016-17 0.00 0.00 0.00 0.00 Others (Rs crores) The total revenue estimate for the category is Rs.294.62 Crores for 2015-16 and Rs.1105.41 Crores for 2016-17. 5.3.2.5 HT Cat-V: Railway Traction Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 513.55 555.02 0.00 0.00 0.00 0.00 0.05 0.05 0.00 0.00 513.60 555.08 The total revenue estimate for the category is Rs 513.60 Crores for 2015-16 and Rs.555.08 Crores for 2016-17. 5.3.2.6 HT Cat -VI: Township & Residential Colonies 2015-16 APSPDCL Page 92 Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) 11 KV 33 KV 132 KV Total 22.53 1.18 0.00 23.70 0.51 0.04 0.00 0.55 0.05 0.01 0.00 0.06 0.00 0.00 0.00 0.00 23.09 1.23 0.00 24.32 11 KV 33 KV 132 KV Total 23.60 1.29 0.00 24.90 0.52 0.04 0.00 0.56 0.00 0.01 0.00 0.01 2016-17 0.00 0.01 0.00 0.01 0.05 0.01 0.00 0.06 0.00 0.00 0.00 0.00 24.18 1.35 0.00 25.52 Voltage Gross Revenue from Tariff (Rs crores) Others (Rs crores) The total revenue estimate for the category is Rs 24.32 Crores for 2015-16 and Rs.25.52 Crores for 2016-17. 5.3.2.7 HT Cat-VII : Green Power There in no existing services 5.3.2.8 HT Cat-VIII : RESCOs Year Energy Charges (Rs crores) Demand /Fixed charges (Rs crores) Minimum Charges (Rs crores) Customer Charges (Rs crores) Others (Rs crores) Gross Revenue from Tariff (Rs crores) 2015-16 2016-17 7.25 7.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.25 7.88 The total revenue estimate for the category is Rs 7.25 Crores for 2015-16 and Rs.7.88 Crores for 2016-17. The estimated revenue gap for the licensee for FY 2016-17 is as follows: Form-9 Particulars Aggregate Revenue Requirement (Rs. Crs.) Total Revenue Revenue Deficit (-) / Surplus (+) at Current Tariffs (Rs. Crs.) Revenue Changed through Proposed Tariff Government Subsidy Envisaged Net Deficit/Surplus (Rs. Crs.) 6 FY 2016-17 18920.15 14572.76 -4347.39 488.35 3859.04 0.00 Performance Parameters APSPDCL Page 93 The details as required by the APERC as per the fresh directive (1) in the Retail supply Tariff order 2009-10 are given below: 6.1.1 Compensation paid by the licensee to consumers for deficiency of service as per the Regulations of the Commission S.N o 1 CG No. & Date Compensation awarded for FY 2014-15 (Apr'14 to Mar'15) compensatio Date of Circle n awarded in Orders Rs. 1/2014-15, 01-04-14 Nellore 25-06-14 Brief Remaks Rs. 1700 /- Delay of 17 days in releasing of additional load of 2HP to ASC No.83 of DavaraVamuru Section, Gudur Section 2 30/2014-15, 23-05-14 Ongole 30-08-14 Rs. 4500 /- Delay of 45 days in resolving the low voltage problem inrespect of Sri P.RaheemBasha, Indira Colony, Kanigiri division 3 43/2014-15, 23-05-14 Ongole 26-06-14 Rs. 11700 /- Delay of 117 days in releasing of new domestic service to Sri G. Manohar Reddy, Kanigiri division 4 46/2014-15, 31-05-14 Ongole 26-06-14 Rs. 100 /- Delay of 2 days in revision of bill inrespect of Smt. V. Sreelakshmi, Ongole 5 50/2014-15, 06-06-14 Vijayawada 30-08-14 Rs. 10800 /- Delay of 108 days in releasing of new non domestic service to Sri V.P.V. Rama Krishna, M.G.Road, Vijayawada 6 64/2014-15, 18-07-14 Kurnool 01-09-14 Rs. 6000 /- Delay of 60 days in releasing of new service to Sri M. Vishnu Vardhan Reddy of Kurnool Compensation awarded for FY 2015-16 (Apr'15 to Sep'15) 1 196/2014-15, 12-02-15 Guntur 06-05-14 Rs. 7500 /- Abnormal delay of 120 days in resolving the billing complaint against Sc.No.1155 of Chilakaluripet, Guntur 2 202/2014-15, 23-02-15 Nellore 21-08-15 Rs. 17500 /- 70 days delay in resolving low voltage problem for 5 consumers at the rate of Rs.50/- per day 3 133/2015-16, 11-06-15 Guntur 31-08-15 Rs. 12800 /- 128 days delay in releasing the industrial service (Aqua culture) at the rate of Rs.100/- per day APSPDCL Page 94 6.1.2 Details of electrical accidents and ex-gratia paid during FY 2014-15 and FY 201516Accidents : 2014-15 (Non-Departmental) S.No Circle 1 Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool Total 2 3 4 5 6 7 8 Human NonFatal fatal 27 11 15 6 12 9 90 58 228 4 0 6 2 2 2 12 5 33 Animal NonFatal fatal 18 23 9 5 2 6 13 25 101 0 0 0 0 0 0 0 0 0 2015-16 (upto Sep'15) (Non-Departmental) Human Animal NonNonFatal Fatal fatal fatal 20 6 9 5 5 16 45 56 162 5 0 0 5 3 2 6 14 35 28 24 8 3 3 4 11 79 160 0 1 0 1 0 0 0 0 2 Ex-gratia Paid 2014-15 2015-2016 (upto Sep, 2015) Animal (Nos.) Amount (Rs.) Human (Nos.) Amount (Rs.) Animal (Nos.) Amount (Rs.) Human (Nos.) Amount (Rs.) Anantapur Kurnool 8 11 11 20 1 0 2 0 1,83,000 212000 340000 400000 20000 0 40000 0 13 5 21 1 3 1 11 1 28,50,000 900000 200000 200000 600000 200000 2200000 200,000 7 5 9 21 1 0 0 0 3,47,000 100000 346000 446000 200000 0 0 0 10 2 11 23 0 5 3 0 22,00,000 400000 200000 600000 0 1000000 600000 0 SPDCL 53 1012000 56 4500000 43 1092000 54 2800000 Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa 6.1.3 APSPDCL Replacement of burnt transformers, installation of additional transformers. Page 95 2014-15 S.No. 1 2 3 4 5 6 7 8 Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool Total 6.1.4 2015-16 (upto Sep'15) Total No. of DTRs Failed Replacement of failed transformers Installation of additional transformers Total No. of DTRs Failed Replacement of failed transformers Installation of additional transformers 2099 2719 4843 4367 7251 5378 6712 4859 38228 2099 2719 4843 4367 7251 5378 6712 4859 38228 3418 3557 18637 5469 2216 2279 3650 2200 41426 1495 1767 2634 2469 4033 3335 4633 2561 22927 1495 1767 2634 2469 4033 3335 4633 2561 22927 1782 2002 1934 1384 943 6528 2224 1295 18092 Number of burnt-out, non-functioning or faulty meters (Circle-wise). Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool Total Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool Total Burnt meters for FY 2014-15 Defective as on Defective during Replaced during Defective as on 3103-2015 1/4/2014 2014-2015 2014-2015 1 Ph 3 Ph Total 1 Ph 3 Ph Total 1 Ph 3 Ph Total 1 Ph 3Ph Total 15 6 4126 1899 4130 1900 11 5 21 6025 6030 16 49 9 93 16 58 17581 2161 19742 17537 2154 19691 109 1735 42 5005 391 3544 296 1777 5396 3840 3196 137 3333 84 58 262 6045 6165 142 186 76 4231 1814 4333 1832 0 0 2405 673 2405 673 0 0 0 3078 3078 0 137 0 5264 262 5130 262 271 0 137 5526 5392 271 39 0 2970 748 2900 745 109 3 39 3718 3645 112 117 50 2905 1058 2961 1097 61 11 167 3963 4058 72 2278 183 2461 44487 9006 53493 42940 8959 51899 3825 230 4055 Burnt meters for FY 2015-2016 (upto Sep, 2015) Defective as on Defective during Replaced during Defective as on 302015-2016 (upto 2015-2016 (upto 09-2015 1/4/2015 September 2015) September 2015) 3 3 1 Ph Total 1 Ph 3 Ph Total 1 Ph 3 Ph Total 1 Ph Total Ph Ph 11 5 2162 1042 2160 1040 13 7 16 3204 3200 20 93 16 8692 382 8584 362 201 36 109 9074 8946 237 3196 137 1303 88 3784 126 715 99 3333 1391 3910 814 255 62 97 2131 1911 317 60 37 1416 715 1221 690 0 0 1218 257 1218 257 0 0 0 1475 1475 0 271 0 2991 59 3262 59 0 0 271 3050 3321 0 109 3 3150 433 3235 431 24 5 112 3583 3666 29 61 11 1360 496 1336 502 85 5 72 1856 1838 90 3801 209 4010 22292 3472 25764 24800 3467 28267 1293 214 1507 Stuck-up meters for FY 2014-15 APSPDCL Page 96 Defective as on Circle 1/4/2014 3 Ph Total 1 Ph Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool Total 14 130 6219 3810 0 298 70 1644 12185 16 25 39 320 0 0 1 98 499 1 Ph 30 155 6258 4130 0 298 71 1742 12684 55578 117010 42856 44827 36506 42475 33043 29522 401817 Replaced during 2014-2015 3 Ph Total 7340 7720 1160 4338 1648 598 1696 2152 26652 62918 124730 44016 49165 38154 43073 34739 31674 428469 Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool Total 1 Ph 21 164 5984 3Ph 9 30 173 1761 0 368 280 623 9201 296 0 0 20 22 550 Total 30 194 6157 2057 0 368 300 645 9751 1 Ph 27342 63101 18309 3 Ph 3426 836 444 21933 15074 20950 23031 11721 201461 2465 990 225 921 1057 10364 Total 30768 63937 18753 24398 16064 21175 23952 12778 211825 Defective as on 31-032015 2014-2015 3 Ph Total 1 Ph 55571 116976 43091 43984 36506 42405 32833 30543 401909 7347 7715 1026 4179 1648 598 1677 2228 26418 1 Ph 27352 62911 23655 3 Ph 3425 821 443 22682 15074 21297 23291 11487 207749 2511 990 225 938 1057 10410 1 Ph 21 164 5984 4653 0 368 280 623 12093 62918 124691 44117 48163 38154 43003 34510 32771 428327 Stuck-up meters for FY 2015-2016 (upto Sep, 2015) Defective as on Defective during Replaced during 2015-2016 (upto 2015-2016 (upto 1/4/2015 September 2015) September 2015) Circle 6.1.5 Defective during Total 30777 63732 24098 25193 16064 21522 24229 12544 218159 3 Ph Total 9 30 173 479 0 0 20 22 733 30 194 6157 5132 0 368 300 645 12826 Defective as on 30-09-2015 1 Ph 11 354 638 1012 0 21 20 857 2913 3Ph 10 45 174 250 0 0 3 22 504 Total 21 399 812 1262 0 21 23 879 3417 Performance with regard to attending fuse-off calls. 1 Performance with regard to attending fuse-off calls 2014-15 2015-2016 (upto Sep, 2015) Circle With in the With in the Received Received stipulated time stipulated time Vijayawada 18598 18550 8654 8654 2 Guntur 12149 11698 6194 6085 3 Ongole 11826 11778 6942 6935 4 Nellore 21355 21328 11332 11332 5 Tirupati 11902 11635 3075 3001 6 Kadapa 14366 14301 6949 6949 7 Anantapur 58602 58475 56062 56021 56136 55702 45022 45022 204934 203467 144230 143999 S.No. 8 APSPDCL Kurnool APSPDCL Page 97 6.1.6 Breakdowns and interruptions in power supply to urban and rural consumers (Circle-wise) and time taken for restoration. Break Downs : 2014-15 33KV Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool TOTAL Interruption : 2014-15 11KV LC Nos Duration Nos Duration Nos Duration Nos Duration 410 228 194 218 117 199 173 115 1570:17 1110:12 1246:15 1119:18 558:22 813:41 866:21 578:16 2769 2843 567 488 937 2590 716 416 9257:07 1110:12 1502:40 1119:18 3276:44 12646:36 2328:28 2327:42 310 286 99 165 6 173 77 837:05 688:23 200:02 446:45 10:59 303:40 111:36 3115 3476 3101 2542 2009 2462 960 1696 486:17 692:10 564:11 466:27 384:37 465:08 276:08 352:29 1654 7862:42 11326 33568:47 1116 2598:30 19361 3687:27 Break Downs : 2015-16 33KV Circle Vijayawada Guntur Ongole Nellore Tirupati Kadapa Anantapur Kurnool TOTAL 6.1.7 Interruption: 2015-16 11KV Trippings Nos Duration Nos Duration Nos Duration 370 242 204 312 240 286 275 187 2116 1364:02 1276:20 1200:02 2639:50 1458:17 2137:02 2053:48 834:42 12964:03 2812 1717 364 160 1947 1854 1192 663 10709 5679:12 5147:36 1334:20 990:06 4316:30 11166:46 5831:56 4079:07 38545:33 2335 2475 2505 2231 1504 2127 1423 2028 16628 521:33 715:49 570:12 547:18 366:17 514:43 430:28 436:29 4102:49 Frequency and voltage at various levels of interface over the period. Average Hz. 49.94 49.97 49.92 49.93 49.92 49.95 49.96 50.00 49.98 50.00 50.00 49.99 49.96 Hz. 50.53 50.56 50.65 50.36 50.34 50.37 50.49 50.42 50.58 50.56 50.55 50.54 Date 20.4.14 30.05.14 12.06.14 23.07.14 26.08.14 01.09.14 02.10.14 16.11.14 15.12.14 01.01.15 17.02.15 01.03.15 Hz. 49.49 49.41 49.32 49.42 49.36 49.35 49.53 49.58 49.54 49.55 49.58 49.52 Date 26.04.14 20.05.14 27.06.14 25.07.14 01.08.14 09.09.14 07.10.14 27.11.14 30.12.14 15.01.15 17.02.15 03.03.15 Apr-15 49.99 50.55 25.04.15 49.50 07.04.15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Average 2015-16 49.98 50.01 49.99 49.97 49.94 49.98 50.55 50.53 50.33 50.27 50.33 19.05.15 13.06.15 26.07.14 12.08.15 20.09.15 49.19 49.56 49.56 49.55 49.36 24.05.15 26.06.15 28.07.15 03.08.15 04.09.15 Month Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Average 2014-15 APSPDCL Trippings Max. Min. Page 98 6.1.8 Pending applications and connections released to different categories of consumers Category wise LT pending Applications in SPDCL During the year 2015-16 (upto 31.10.15) Category I II III IV V VI(a) VI(b) VII VIII Total Pending at the beginning of the month 12384 2805 1268 97 89018 272 1535 153 103 107635 Received during the month 150368 18462 1441 351 40585 545 1217 561 293 213823 2127 485 317 22 9340 87 347 31 69 12825 152926 18872 1473 297 38260 444 945 522 61 213800 4913 849 765 18 34052 149 714 104 2 94833 Deleted during the month Services released during the month Pending at the end of the month 6.1.9 Arrears of consumers over Rs.50, 000 pending for over six months and details of bad debts written off Defaulters list of individual consumers (circle wise) whose arrears are more than Rs.50,000/- as on 30-09-2015isdisplayed in APSPDCL website (www.apspdcl.in) APSPDCL Page 99 6.1.10 Court cases involving the Licensee S.No Petition No. Name of the Petitioner Subject Remarks NCE Project–list of Court cases filed at APERC 1 R.P. No. 1 of 2009 in O.P. No. 5 of 2009 M/s RPP Ltd 2 R.P. No. 2 of 2009 in O.P. No. 5 of 2009 Small Hydro Power Developers Association 3 R.P. No. 3 of 2009 in O.P. No. 5 of 2009 4 R.P. No. 4 of 2009 in O.P. No. 5 of 2009 5 R.P. No. 5 of 2009 in O.P. No. 5 of 2009 6 R.P. No. 6 of 2009 in O.P. No. 5 of 2009 R.P.No. 7 of 2009 in O.P. No. 5 of 2009 7 8 O.P. 18 of 2013 9 O.P. No. 31 of 2013 M/s Sardar Power Ltd M. Venu Gopal Rao M/s Velagapudi Power Generation Company Ltd, Hyderabad Punna Rao 1) SISMA 2) M/s Empee Power Company (India) Ltd 3) M/s GSR Sugars Ltd 4) M/s KCP Sugar Industrial Corporation Ltd 5) M/s Nizam Deccan Sugar Ltd M/s Matrix Power Private Limited M/s Hetero Wind power Limited M/s SLS Power Limited 10 O.P No. 27 of 2012 APSPDCL Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects APERC dismissed review petition on 27.7.2013 Against orders passed by APERC Dt. 31.3.2009in O.P. No. 5 of 2009 determining the tariff for NCE Projects APERC dismissed review petition on 27.7.2013 Petition for determining of the tariff to take effect on completion of 10 years from the date of commissioning of the project Regarding evacuation policy, wheeling charges and banking of power generated by captive power producers Petition for determining of the tariff to take effect on completion of 10 years from the date of commissioning of the project APERC dismissed review petition on 27.7.2013 APERC dismissed review petition on 27.7.2013 APERC dismissed review petition on 27.7.2013 APERC dismissed review petition on 27.7.2013 APERC dismissed review petition on 27.7.2013 Hearing on 9.11.2013 Hearing on 9.11.2013 Hearing on 9.11.2013 Page 100 S.No 1 2 3 4 1 2 Petition No. Name of the Petitioner Remarks NCE Project – list of Court cases filed at High court of AP Against Ld Single Judge orders in Writ Appeal Nos: APTRANSCO & W.P. No. 17344/2007 and batch 1255, 1285,1291, DISCOMS regarding provisions banking of 1293 of 2008 energy facility to NCE Developers (APERC Regulation 2 of 2006) To wheel the petitioners energy, which was generated / banked or remaining un-utilized/ un allocated M/s Tirumala hydel power Writ Petition No: as at the end of December 2006 and projects limited, 18553 of 2009 as at the end of December 2007 and Chilakaluripet as the end of December ‘2008 ( APERC Regulation 2 of 2006) High court passed interim order directing into to wheel power to scheduled consumers from unutilized energy from January 2010 High court passed To wheel the petitioners energy, interim order which was generated / banked or directing into to remaining un-utilized/ un allocated Writ Petition No: M/s Akshay profiles ltd, wheel power to as at the end of December 2006 and 18554 of 2009 Chilakaluripet scheduled as at the end of December 2007 and consumers from as the end of December ‘2008 unutilized energy (APERC Regulation 2 of 2006) from January 2010 High court passed To wheel the petitioners energy, interim order which was generated / banked or directing into to remaining un-utilized/ un allocated Writ Petition No: Trident Power Systems wheel power to as at the end of December 2006 and 18555 of 2009 Ltd, Hyderabad scheduled as at the end of December 2007 and consumers from as the end of December ‘2008 unutilized energy (APERC Regulation 2 of 2006) from January 2010 NCE Project – list of Court cases filed at Appellate Tribunal for Electricity, New Delhi NIL NCE Project – list of Court cases filed at Supreme Court of India Against the Appellate Tribunal for Civil Appeals Nos Electricity, New Delhi orders date M/s Jocil Ltd 3891-3892 of 2009 19.12.2008 in Appeal No. 92 & 38 of 2007 Civil Appeal N0. M/s Sitapuram Power Against orders passed by Appellate 837 of 2011 Limited Tribunal Appeal No. 8 of 2010 3 Civil Appeal Nos 5159 of 2005 & 5157 of 2005 M/s Sagar Sugars & Allied Products Limited 4 Civil Appeal No. 1376 – 1385 of 2013 M/s SLS & others APSPDCL Subject To consider COD of the plant from the date of synchronization of the plant without establishing the sugar plant Against Appellate Tribunal Order dated 20.12.2012 with regards NCE tariff cases in APERC order dated 20.3.2004 Still pending at Supreme court Still pending at Supreme court Still pending at Supreme court Still pending at Supreme court Page 101 6.1.11 Number of cases filed in respect of pilferage of power in various categories giving comparative picture with respect to FY 2013-14& 2014-15 (upto Sep’14) APSPDCL Page 102 7 Retail Supply Business True-up for FY 2014-15& FY 2015-16 7.1 Filing for True-up by the Distribution Licensee This filing is made by the Distribution Licensee, SOUTHERN POWER DISTRIBUTION COMPANY OF ANDHRA PRADESH LIMITED (APSPDCL) under Clause 19, Pg 11 of the Andhra Pradesh Electricity Regulatory Commission ‘(Terms and Conditions for Determination Of Tariff For Wheeling and Retail Sale of Electricity)’ Regulation No. 4 of 2005 and Clause 2, Pg 2 of the Andhra Pradesh Electricity Regulatory Commission ‘First Amendment to (Terms and Conditions for Determination of Tariff for Wheeling and Retail Sale of Electricity) Regulation No. 1 of 2014, for corrections for “uncontrollable” and “controllable” items and as well as sharing of gains/losses for FY 2013-14. As per Andhra Pradesh Electricity Regulatory Commission (APERC) Regulation No. 4 of 2005, ‘Terms and Conditions for Determination of Tariff for Wheeling and Retail Sale of Electricity’ – “4. Controllable and Uncontrollable items of ARR:- The expenditure of the Distribution Licensee considered as “controllable” and “uncontrollable” shall be as follows: ARR Item Operation & Maintenance expenses Distribution Business “Controllable”/”Uncontrollable” Controllable Return on Capital Employed Depreciation Taxes on Income Controllable Controllable Uncontrollable Non-tariff income Controllable In addition to the above items the retail supply business shall include the following: Retail Business ARR Item Cost of power purchase APSPDCL “Controllable”/”Uncontrollable” Uncontrollable Page 103 5. Pass-through of gains and losses on variations in “uncontrollable” items of ARR:The Distribution Licensee shall be eligible to claim variations in “uncontrollable” items in the ARR for the year succeeding the relevant year of the Control Period depending on the availability of data as per actuals with respect to effect of uncontrollable items: Provided that the Commission shall allow the financing cost on account of the time gap between the time when the true-up becomes due and when it is actually allowed and the corrections shall not be normally revisited. 6. Sharing of gains and losses on variations in “controllable” items of ARR:- The Distribution Licensee in its annual filings during the Control Period shall present gains and losses for each controllable item of the Aggregate Revenue Requirement. A statement of gain and loss against each controllable item will be presented after adjusting for any variations on account of uncontrollable factors. 7. For the purpose of sharing gains and losses with the consumers, only aggregate gains or losses for the Control Period as a whole will be considered. The Commission will review the gains and losses for each item of the ARR and make appropriate adjustments wherever required: Provided that for the first Control Period, insofar as the gains and losses from the Retail Supply Business of the Distribution Licensee are concerned, these will be shared with the consumers on yearly basis.” “MAIN ITEMS OF ARR The Aggregate Revenue Requirement of the Distribution Licensee, for each year of the Control Period, shall contain the following items: 1. Cost of power for (Retail Supply Business alone) 2.Transmission charges (for Retail Supply Business alone) 3.Load dispatch charges; 4.Operation and maintenance expenses; 5.Return on capital employed; 6.Depreciation; 7.Taxes on Income; 8.Corrections for “uncontrollable” items and “controllable” items (indexed to external parameters); 9.Any other relevant expenditure” “4. The Distribution Licensee shall be entitled to recover or shall refund, as the case may be, the charges on account of Fuel Surcharge Adjustment as approved by the APSPDCL Page 104 Commission from time to time, suo-motu or based on the filing made by the Distribution Licensee, as the Commission may deem fit.” “1. The Distribution Licensee shall be allowed to recover transmission and load despatch charges payable to the Transmission Licensees (Central Transmission Utility, State Transmission Utility etc.) and System Operators (Regional Load Despatch Centre, State Load Despatch Centre etc.) for access to and use of the interstate transmission system, intra-state transmission system and availing load dispatch services on long-term basis in accordance with the tariffs approved from time to time by CERC and this Commission, as the case may be. 2. The Distribution Licensee shall also be allowed to recover the expenses, at the approved level, pertaining to (a) use of transmission and load dispatch facilities under short-term procurement of power for the Retail Supply Business; and (b) wheeling charges for use of the distribution system of other Distribution Licensee for procurement of power for the Retail Supply Business.” As per Andhra Pradesh Electricity Regulatory Commission (APERC) Regulation No. 1 of 2014, ‘First Amendment to (Terms and Conditions for Determination of Tariff for Wheeling and Retail Sale of Electricity)Regulation No. 4 of 2005’ – “12.5 True-up for Retail Supply Business a. The Distribution Licensee shall include the power purchase cost variation over the previous year Power Purchase cost in the Tariff Order as expense (in the event of incurring excess cost)/rebate (in case of cost saving) in the ARR as special item with relevant details. To arrive the power purchase cost variation, the least of the following power purchase quantity is to be considered: i) Actual power purchase quantity procured by the Discoms for its consumers. ii) Power purchase quantity computed based on actual sales except LT Agriculture sales. LT Agriculture sales will be limited to Tariff Order quantity. These aggregated sales will be grossed up with approved losses for the relevant year in the MYT orders. b. Since the complete information of cost actually incurred relating to previous year will not be available at the time of filing of ARR for a particular tariff year, the Licensee may include provisional cost variation for the previous year in ARR filings which will be subject to final correction by the Commission as and when final accounts for that year become available. APSPDCL Page 105 c. The Licensees shall also include in the ARR the amounts to be collected on final basis being the difference between the cost incurred based on audited annual accounts report and costs provisionally approved by the Commission in the Tariff Order for the year immediately preceding the previous year.” The Amendment Regulation mentions about power purchase cost variation. However, deviation in actual and approved ARR and revenue arises because of variation in approved and actual agriculture sales, losses and average realization besides variation in power purchase cost. If this is not accounted for, it will result in the requirement of another Financial Restructuring Plan on account of accumulation of losses. Hence, this write-up explains the total truing up gap arising out of the deviations in Aggregate Revenue Requirement components and revenue for the Retail Supply Business for FY 2014-15. 7.2 True-up of Aggregate Revenue Requirements components & Gap from Retail Business for FY 2014-15& FY 2015-16 2015-16 Particulars 2014-15 Approved Revised Estimate Deviation Transmission Cost SLDC Cost Distribution Cost PGCIL Expenses ULDC Expenses Network and SLDC Cost Power Purchase/Procurement Cost 478.70 19.86 1,481.60 217.12 6.89 2,204.17 12,217.29 654.10 21.05 2,153.24 211.10 9.71 3,049.20 654.10 21.05 2,153.24 211.10 9.71 3,049.20 12,672.00 13,468.63 0.00 0.00 -0.00 0.00 0.00 0.00 796.63 Interest on Consumer Security Deposits Supply Margin Other Cost Supply Cost Gross ARR Revenue Subsidy Total Revenue (incl. Subsidy) 122.83 12.12 0.00 12,352.24 14,556.41 10,320.98 2,169.03 12,490.01 147.09 13.13 565.53 13,397.75 16,446.95 14,128.50 2,318.45 16,446.95 142.12 13.13 38.12 13,662.00 16,711.20 12,193.48 2,318.45 14,511.93 -4.97 -0.00 -527.41 264.25 264.25 -1,935.02 0.00 -1,935.02 Total Gap from Retail Business -2,066.40 0.00 -2,199.27 -2,199.27 As shown in the table above, the total gap for Retail Supply Business is Rs -2066.40Crs for FY 2014-15& Rs. -2199.27 Crs. for FY 2015-16. APSPDCL Page 106 7.3 Prayer The Petitioner (Distribution Licensee) prays that the Hon’ble Commission may: The Petitioner (Distribution Licensee) submits that as per the APERC Regulation 1 of 2014,APDISCOMS have to file for power purchase cost deviation of last two years. The licensee has computed the revenue gap for FY14-15 and FY 15-16, but it has not added this revenue deficit to the ARR for FY16-17 because the GoAP has given in principle approval to UDAY scheme floated by GoI. As per UDAY scheme, GoAP will take over 75% of DISCOM debt as on 30 September 2015 over two years - 50% of DISCOM debt will be taken over in 2015-16 and 25% in 2016-17.DISCOM debt not taken over by GoAP will be converted by the Banks / FIs into loans or bonds with interest rate notmore than the bank’s base rate plus 0.1%. Alternately, this debt may be fully or partly issued by the DISCOM as GoAP guaranteed DISCOM bonds at the prevailing market rates which shall be equal to or less than bank base rate plus 0.1%. In view of the above, the licensee requests not to consider the above trueup amounts (for FY 2014-15 & FY 2015-16) while determining the ARR / revenue deficit for FY 2016-17. APSPDCL Page 107 8) Detailed Tariff Proposal for Retail Supply Business for FY 2016-17 Average Cost to Serve (CoS) for the FY 2015-16 as approved by the Hon’ble Commission for the State was Rs 5.38/Unit. Whereas, revised average Cost to Serve (CoS) for the current year is Rs 5.92/Unit. The Licensee estimates the Discom level CoS for the ensuing year i.e. FY 2016-17 is estimated to be at Rs. 5.60/Unit. This implies an increase of Rs. 0.22/ Unit (4.05 % increase) when compared to approved average CoS for the previous year. The Aggregate Revenue Requirement for both the Discoms combined for FY16-17 is projected to be Rs.28,423 Crs. and the projected revenue at current tariffs including non-tariff income is Rs.23,725 Crs. which results in a gap of Rs.5,148 Crs. Also, the average CPI inflation in India was 5.41% year-on-year in November 2015. The licensee would like to propose a nominal increase in the tariffs to meet the increased costs which is detailed below. Gist of Tariff rationalization, Tariff Proposals and Revenue Impact: Summary of tariff proposals are shown below. I. No tariff increase proposed for the following categories: LT I Domestic Group A consumers (all Domestic consumers with annual consumption less than or equal to 600 units during last year) Group B consumers (all Domestic consumers with annual consumption greater than 600 Units and less than 2,400 Units during last year) LT IV (B) Agro Based Activity LT V Agriculture LT VI (C) NTR Sujala Padhakam HT I (B) Energy Intensive Industries: With a view to enable rapid industrialization in the State, the licensee would like to propose to extend concessional tariffs under HT I (B) to other energy intensive industries in addition to Ferro-alloy units. The licensee would like to propose to rename the category HT-I (B) Ferro Alloys to Energy Intensive Industries. APSPDCL Page 108 The following energy intensive industries shall be eligible for the concessional tariffs offered under this renamed category: II. Ferro Alloy Units PV Ingots & Cell Manufacturing Poly-silicon industry Aluminum industry Tariff reduction proposed for following categories Poultry farms*: As per G.O.Ms.No.49, dated 09.12.2013 it was suggested that the tariff offered to poultry farms be equivalent to the average pooled power purchase cost. Further, the licensee has received representations from poultry farmers for similar concessions. In addition, all HT services which are being billed at HT I Industrial tariff shall be billed at the same concessional tariff as LT services with the creation of a new sub category HT I (C) Aquaculture and Animal Husbandry. The licensee would like to propose the following tariffs: Tariff Component Existing Proposed 5.63 3.75 53 21 Energy Charges (Rs. / Unit) Demand Charges (Rs. / kW / month) The revenue impact is Rs. 3.78 Cr for APSPDCL. LT III Pisciculture & Prawn culture*: Associations from the Pisciculture and prawn culture industry have submitted their request for concessional tariff at Rs. 3.75 / Unit to Government of Andhra Pradesh with a view to keep these industries in AP competitive. The Government has then directed APDISCOMs to consider providing concessional tariff to these industries. APSPDCL Page 109 In addition, all HT services which are being billed at HT I Industrial tariff shall be billed at the same concessional tariff as LT services with the creation of a new sub category HT - I (C) Aqua-culture and Animal Husbandry. The licensee would like to propose the following tariffs: Tariff Component Energy Charges (Rs. / Unit) Demand Charges (Rs. / kW / month) Existing Proposed 4.63 3.75 21 21 The revenue impact is Rs. 38.74 Cr for APSPDCL. * Keeping in view that the licensee is proposing same tariffs for LT III sub categories Pisciculture/Prawn culture and Poultry farms, the licensee would like to propose a single sub category for Pisciculture/Prawn culture and Poultry farms and the sub category may be named as Aquaculture & Animal Husbandry. Further, HT services for Poultry Farms, Pisciculture, Prawn culture and Dairy Farms shall be billed under a new category HT I (C) Aquaculture & Animal Husbandry with the same tariffs as proposed for LT services. Tourism Infrastructure Projects: As per the Andhra Pradesh Tourism Policy 2015, all new and existing Tourism Infrastructure Projects eligible as per the Policy including 3 star & above Hotels shall be billed under HT III category. The licensee thus would like to propose renaming of HT III category to HT III Public Infrastructure & Tourism which shall be limited to Airports, Bus Stations, Railway Stations and eligible Tourism Infrastructure Projects as per the Andhra Pradesh Tourism Policy 2015 III. Tariff for HT IV (A) Govt. Lift Irrigation & Agriculture to be equal to Cost of Service (CoS). IV. Tariff increase for all other categories: 4% increase in Demand Charges, Energy Charges, Time of Day tariff 2.5% increase in Energy Charges for Domestic Group-C consumers No change in other components of tariff – customer charges and minimum charges APSPDCL Page 110 V. Billing demand for HT services: The licensee would like to propose that the billing demand shall be the maximum demand recorded during the month or 90% of the contracted demand, whichever is higher, except HT-VI Townships & Residential Colonies category. The licensee does not propose any change in billing demand for HT-VI category. VI. New HT sub-categories: The licensee would like to propose the following new HT categories: HT I (C) Aquaculture & Animal Husbandry: At present, HT services for Poultry Farms, Pisciculture, Prawn culture and Dairy Farms are being billed under HT I. The licensee would like to propose to create a new sub category called HT - I (C) Aqua-culture and Animal Husbandry applicable for Poultry Farms, Pisciculture, Prawn culture and Dairy Farms. These would be charged the same concessional tariff as per the corresponding sub category in LT III. HT II (B) Religious Places: At present, HT services for Religious Places are being billed under HT II Others tariff. The licensee proposed to create a new sub category called HT II (B) Religious Places applicable for religious places currently being billed under HT-II. These would be charged the same tariff as that of LT-VII (B). VII. Interruption Free Supply: It is the endeavor of the licensees to provide high reliable / interruption free power to all consumers in the state. The licensees intend to roll out this initiative with HT consumers at 33 kV and above in 6 cities / areas from April 2016. The licensee intends to roll out this initiative of providing high reliable / uninterrupted power supply to HT consumers at 33 kV and above in the following cities / areas from April 2016: • Visakhapatnam • Kakinada • Rajahmundry • Sri City • Krishnapatnam • Tirupati APSPDCL Page 111 The licensee would like to propose Rs. 0.25 / Unit as reliability charge in addition to the applicable HT tariff w.e.f. 01 October 2016 for all HT consumers at 33 kV and above in the above areas. VIII. Monthly billing of all LT I Domestic services: The licensee would like to propose to implement monthly billing of all rural domestic consumers who are currently being billed on a bi-monthly basis. It is the licensee’s view that this would improve cash flow, enable a better control on commercial aspects and also improve its finances due to (a) higher collection of minimum charges; and (b) reduction in receivable-days. Category-wise Tariff Proposals The following section lists in detail the proposed rationalized tariff structure and modifications in the tariff categories for different consumer categories. The definition of any consumer category is proposed to remain the same unless and otherwise mentioned in this section. The definition of categories or sub categories which have been merged or moved has to be modified accordingly to reflect the new consumer mix. Low Tension Category LT I Domestic The licensee has proposed grouping of domestic consumers based on consumption in the section on revenue at current tariffs. The licensee would like to propose no change in tariff for Group A and B consumers (all Domestic consumers with annual consumption less than 2,400 Units during last year). The licensee would like to propose a 2.5% increase in energy charges only for Group C consumers (all Domestic consumers with annual consumption more than 2,400 Units during last year). APSPDCL Page 112 The proposed tariff for LT I Domestic category is as under: Proposed Category / Slab Structure Existing Proposed (Units kWh) Tariff Tariff (Rs./Unit) Group A: All Domestic consumers with annual consumption < = 600 Units during last year 0-50 1.45 1.45 51-100 2.60 2.60 101-200 3.60 3.60 Above 200 # 6.90 6.90 Group B: All Domestic consumers with annual consumption < =2400 and > 600 units during last year 0-50 2.60 2.60 51-100 2.60 2.60 101-200 3.60 3.60 201-300 # 6.90 6.90 Above 300 7.75 7.75 Group C: All Domestic consumers with annual consumption >2400 units 0-50 2.67 2.60 51-100 3.33 3.25 101-200## 5.39 5.26 201-300# 7.07 6.90 301-400 7.94 7.75 401-500 8.48 8.27 Above 500 units 8.80 9.02 # computed average existing tariff for a consumer whose consumption is > 200 but < 300 units ##computed average existing tariff for a consumer whose consumption is > 100 but < 200 units LT-II Non Domestic/Commercial The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for all the sub categories in LT-II. Sub Category/ Slab Structure Proposed Energy charge Proposed Fixed charge (Rs/kW/month) (Units kVAh / kWh) (Rs. /Unit) LT II (A) Upto 50 Units/Month 55 5.62 LT II (B) Above 50 Units/Month 0-50 55 6.90 51-100 55 7.68 101-300 55 8.88 301-500 55 9.42 >500 55 9.97 LT II (C) Advertisement Hoardings 55 12.04 APSPDCL Page 113 LT III Industry The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for all the sub categories in LT III except Pisciculture / Prawn culture and Poultry farms, for which the licensee would like to propose concessional tariffs. Sub- Category Proposed Demand charge (Rs/kVA/month) LT III Industry Industries Seasonal Industries (off season) Aquaculture & Animal Husbandry * Sugarcane crushing Mushroom and Rabbit farms Floriculture in Green House Proposed Energy charge (Rs. /Unit) 55 55 6.64 7.37 21 3.75 22 55 55 4.82 5.86 5.86 * Keeping in view that the licensee is proposing same tariffs for LT III sub categories Pisciculture/Prawn culture and Poultry farms, the licensee would like to propose a single sub category for Pisciculture/Prawn culture and Poultry farms and the sub category may be named as Aquaculture & Animal Husbandry. LT IV Cottage Industries The licensee would like to propose no change in tariff for sub category LT IV (B) Agro based activities and increase in the Energy and Demand charges by 4% for sub category LT IV (A) Cottage Industries. Sub-Category Cottage Industries Agro based activities Proposed Demand charge (Rs/kVA/month) 21 20 Proposed Energy charge (Rs. /Unit) 3.90 3.75 LT V Agriculture The licensee would like to propose to continue with existing tariff for all the sub categories in LT V. The proposed tariff is same as the existing tariff for all the sub categories in LT V. APSPDCL Page 114 Sub- Category LT V(A) Agriculture with DSM Measures Corporate Farmers & IT Assesses Wet Land Farmers (Holdings >2.5 acre) Dry Land Farmers (Connections > 3 nos.) Wet Land Farmers (Holdings <= 2.5 acre) Dry Land Farmers (Connections <= 3 nos.) LT V (B) Agriculture without DSM Measures Corporate Farmers & IT Assesses Wet Land Farmers (Holdings >2.5 acre) Dry Land Farmers (Connections > 3 nos.) Wet Land Farmers (Holdings <= 2.5 acre) Dry Land Farmers (Connections <= 3 nos.) LT V (C) Others Salt farming units with CL upto 15HP Rural Horticulture Nurseries * Equivalent flat rate tariff Demand charge (Rs/HP/Year) Energy charge (Rs. /Unit) 0 525.00* 525.00* 0 0 2.50 0.50 0.50 0 0 0 1050.00* 1050.00* 525.00* 525.00* 3.50 1.00 1.00 0.50 0.50 240.00 240.00 3.70 3.70 LT VI Street Lighting & PWS The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for the sub categories in LT VI (A) and (B). The licensee would like to propose to continue with existing tariff for sub category LT VI (C) NTR Sujala Padhakam. Sub Category LT VI (A) Street Lighting Panchayats Municipalities Municipal Corporations LT VI (B) PWS Schemes Panchayats Municipalities Municipal Corporations LT-VI (C) NTR Sujala Padhakam APSPDCL Proposed Demand charge (Rs/kW/month) 33 33 33 (Rs/HP/month) 33 33 33 Rs.10/HP/month Proposed Energy charge (Rs. /Unit) 5.87 6.41 6.96 4.77 5.87 6.41 4.00 Page 115 LT VII General Purpose The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for all the sub categories in LT VII: Category LT VII (A) General Purpose LT VII (B) Religious Places Proposed Demand charge (Rs/kW/month) 22 21 Proposed Energy charge (Rs. /Unit) 7.13 4.89 LT VIII Temporary Supply The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for category LT VIII Category LT VIII Temporary Proposed Demand charge (Rs/kW/month) 22 Proposed Energy charge (Rs. /Unit) 10.30 High Tension Category HT I (A) Industry The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for all the sub categories in HT I (A) and HT I (A) ToD for all voltage levels (11 kV, 33 kV, 132 kV). Voltage Level HT I (A) 11 KV 33 KV APSPDCL Sub-Category Proposed Demand charge (Rs/kVA/month) Proposed Energy charge (Rs. /Unit) General Lights and Fans Industrial Colonies Seasonal Industries Time of Day Tariffs (6 PM to 10 PM) 386 386 6.26 6.26 6.20 7.54 - 7.35 General 386 5.79 Page 116 Voltage Level 132 KV Sub-Category Proposed Demand charge (Rs/kVA/month) Proposed Energy charge (Rs. /Unit) Lights and Fans Industrial Colonies Seasonal Industries Time of Day Tariffs (6 PM to 10 PM) General Lights and Fans Industrial Colonies Seasonal Industries Time of Day Tariffs (6 PM to 10 PM) 386 5.79 6.20 6.85 - 6.88 386 386 5.36 5.36 6.20 6.58 - 6.45 HT I (B) Energy Intensive Industries (presently termed as HT I (B) Ferro Alloys) With a view to enable rapid industrialization in the State, the licensee would like to propose to extend concessional tariffs under HT I (B) to other energy intensive industries in addition to Ferro-alloy units. The licensee would like to propose to rename the category HT I (B) to HT I (B) Energy Intensive Industries. The following industries shall be eligible for the concessional tariffs offered under this renamed category: Ferro Alloy Units PV Ingots & Cell Manufacturing Poly-silicon industry Aluminum industry The licensee would like to propose no increase on existing tariff of FY 2015-16 for category HT I (B) for all the voltage levels (11 kV, 33 kV, 132 kV). Voltage Level HT I (B) 11 KV 33 KV 132 KV APSPDCL Proposed Energy charge (Rs. /Unit) 5.68 5.23 4.81 Page 117 HT I (C) Aquaculture & Animal Husbandry (New Category) At present, HT services for Poultry Farms, Pisciculture and Prawn culture are being billed under HT I. The licensee would like to propose to create a new sub category called HT I (C) Aquaculture and Animal Husbandry applicable for Pisciculture, Prawn Culture, Dairy Farms and Poultry Farms. These would be charged the same concessional tariff as per the corresponding sub category in LT III. Category Proposed Demand charge (Rs/kVA/month) HT I (C) Rs. 21 / kVA HT II Others Proposed Energy charge (Rs. /Unit) 3.75 The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for category HT II Others & HT II Others –ToD. Voltage Level HT II Others 11 KV 11 KV - ToD 33 KV 33 KV - ToD 132 KV 132 KV - ToD Proposed Demand charge Proposed Energy charge (Rs/kVA/month) (Rs. /Unit) 386 386 386 - 7.54 8.63 6.85 7.95 6.58 7.68 HT II (B) Religious Places: At present, HT services for Religious Places are being billed under HT II Others tariff. The licensee proposes to create a new sub category called HT II (B) Religious Places applicable for religious places currently being billed under HT II. These would be charged the same tariff as that of LT VII (B): Category HT II (B) Religious Places APSPDCL Proposed Demand charge (Rs/kVA/month) Proposed Energy charge (Rs. /Unit) Rs. 21 / kVA 4.89 Page 118 HT III Public Infrastructure & Tourism (presently termed as HT III Airports, Bus Stations and Railway Stations) Presently, all tourism infrastructure projects are being billed under HT II Others category. The Andhra Pradesh Tourism Policy 2015 states that such consumers shall be billed as per HT III category. Accordingly, the licensee would like to propose to rename the category HT III to HT III Public Infrastructure & Tourism which shall be restricted to Airports, Bus Stations, Railway Stations and eligible Tourism Infrastructure Projects as per the policy. As per the policy, the following projects shall be eligible for the said incentive: “ i. Hotels (Three-Star or above category hotels as per guidelines of Ministry of Tourism, Government of India) iv. Amusement Parks vii. Botanical gardens x. Wayside amenities ” ii. Resorts, including beach resorts, jungle resorts, hill resorts etc. (Three-Star or above category hotels as per guidelines of Ministry of Tourism, Government of India) v. MICE Centers viii. Urban/Rural Haats xi. Spiritual/Wellness Centers iii. Heritage Hotels (Heritage Basic, Heritage Classic, Heritage Grand as per guidelines of Ministry of Tourism, Government of India) vi. Golf Courses ix. Tourism & Hospitality Training Institutes xii. Museums Tourism projects which are eligible as per the Andhra Pradesh Tourism Policy shall be billed under this category. The licensee would like to propose to increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for category HT III and HT III ToD. Proposed Demand charge (Rs/kVA/month) HT III Public Infrastructure & Tourism 11 KV 386 11 KV - ToD 33 KV 386 33 KV - ToD Voltage Level 132 kV 132 KV - ToD APSPDCL 386 Proposed Energy charge (Rs/ / Unit) 7.19 8.28 6.56 7.65 6.25 7.34 Page 119 HT IV Irrigation, Agriculture and CPWS The licensee would like to propose the Energy charges equivalent to Cost of Service (CoS) for FY 2016-17, i.e., Rs. 5.60 / Unit for sub categories HT IV (A) Government LIS and HT IV (A) Private Irrigation and Agriculture for all the voltage levels (11 kV, 33 kV, 132 kV). The licensee would like to propose an increase in Energy charges by 4% on existing tariff FY 2015-16 for category HT IV (B) Composite Water Supply Schemes for all the voltage levels (11 kV, 33 kV, and 132 kV). Category Proposed Energy charge (Rs. /Unit) HT IV Irrigation, Agriculture and CPWS Government LIS 5.60 Agriculture 5.60 CPWS 4.79 HT V Railway Traction The licensee would like to propose an increase in Energy charges by 4% on existing tariff FY 2015-16 for category HT V. Category Proposed Energy charge (Rs. /Unit) HT V Railway Traction 6.95 HT VI Townships and Residential Colonies The licensee would like to propose an increase in the Demand charges by 4% and an increase in Energy charges by 4% on existing tariff FY 2015-16 for category HT VI for all the voltage levels (11 kV, 33 kV, 132 kV). Category HT VI Townships & Residential Colonies APSPDCL Proposed Demand charge (Rs/kVA/month) 55 Proposed Energy charge (Rs. /Unit) 6.20 Page 120 HT VII Green Power The licensee would like to propose no increase on existing tariff of FY 2015-16 for category HT VII for all the voltage levels (11 kV, 33 kV, 132 kV). Category Proposed Energy charge (Rs. /Unit) HT VII Green Power 11.32 HT VIII Temporary The licensee would like to propose the continuation of the current tariff structure i.e. 1.5 times of the corresponding HT category HT – RESCOs (11 KV) The licensees would like to propose the following tariffs for the RESCOs: Anakapalle : Rs. 1.53/unit Chipurpalle : Rs. 0.26/unit Kuppam : Rs. 0.41/unit Billing demand for HT services The licensee would like to propose that the billing demand shall be the maximum demand recorded during the month or 90% of the contracted demand, whichever is higher, except HT-VI Townships & Residential Colonies category. The licensee does not propose any change in billing demand for HT-VI category. Madhya Pradesh and Tamil Nadu currently levy demand charges on 90% of contract demand or maximum demand, whichever is higher. Interruption Free Supply AP has been one of the pioneering states in India in implementing reforms in the Power Sector. Government of Andhra Pradesh has successfully achieved zero load restrictions from past one year giving the most required boost to the industrial sector. Now the government envisages to go a step further and make the state interruption free. AP currently has an interruption of 6000 minutes per customer per year (as per CEA report) compared to 100 – 200 minutes internationally: APSPDCL Page 121 Country Average frequency of Average interruption duration per interruption per consumer for an consumer (Minutes) year (No.) Singapore 0.47 0.015 UK 34 1–2 US 100 ~1 Australia 200 1.8 Interruption free power is viewed as one of the most important drivers for industrial growth: Xi'an LONGi, Foxconn and other major global industrial players have expressed their desire for interruption free power to invest in the State Many industries have invested in setting up dedicated captive power plants to ensure uninterrupted supply It is the endeavor of the licensee to achieve high reliability and become the most reliable power distributor in India. A diagnostic study has been carried out both APDISCOMs to baseline the current level of interruptions, analyze reasons & root causes leading to interruptions, and develop a strategy to substantially reduce the current level of interruptions. Based on real-time interruption data using modem communication for all 11 kV feeders, following is the current level of interruptions in APSPDCL: SAIDI (System Average Interruption Duration Index) – 2,019 mins / year SAIFI (System Average Interruption Frequency Index) – 99.04 interruptions / year The above is in line with the CEA data. Daily interruption data can be monitored on the website www.apspdcl.in The licensee intends to roll out this initiative of providing high reliable / uninterrupted power supply to HT consumers at 33 kV and above in the following cities / areas from April 2016: Visakhapatnam Kakinada Rajahmundry APSPDCL Page 122 Krishnapatnam Sri City Tirupati The licensee would like to propose Rs. 0.25 / Unit as reliability charge in addition to the applicable HT tariff w.e.f. October 2016 for all HT consumers at 33 kV and above in the above areas. The licensee shall form a baseline on present level of interruptions using SAIDI and SAIFI as KPIs for each of the above cities / areas by April 2016. The detailed analysis, design, implementation and review for the initiative shall require 6 – 9 months. The licensee is targeting to bring down the SAIDI by 40% by March 2017 as compared to April 2016. In case the licensee fails to meet its target, the license shall refund the reliability charge as under: Target met (% reduction in SAIDI) > 0% and <= 10% > 10% and <=20% > 20% and <= 30% > 30% and <= 40% >= 40% Refund of Reliability Charge to consumer by the licensee at the end of the Financial Year 20 paise / Unit 15 paise / Unit 10 paise / Unit 5 paise / Unit No refund Going forward, it is the intent of the licensee to ensure negligible interruptions to all HT consumers in the state – with a view to position AP as the most desirable destination for investment. The funds collected shall be utilized toward building of infrastructure for interruption free supply with a view to cater to (n – 1) contingency. Also, providing highly reliable power to the industries would boost investments especially in the high growth clusters. The licensee submits that at present it is unable to compute the revenue impact due to collection of reliability surcharge and building of additional infrastructure to achieve interruption-free supply in these areas. APSPDCL Page 123 Other Tariff Proposals Cross subsidy surcharge determination for FY 2016-17: Provisions under the National Tariff Policy – 2006 Cross subsidy and additional surcharge for open access When open access is allowed the surcharge for the purpose of sections 38, 39, 40 and subsection 2 of section 42 would be computed as the difference between (i) The tariff applicable to the relevant category of consumers and (ii) The cost of the distribution licensee to supply electricity to the consumers of the applicable class In case of a consumer opting for open access, the distribution licensee could be in a position to discontinue purchase of power at the margin in the merit order. Accordingly, the cost of supply to the consumer for this purpose may be computed as the aggregate of (a) The weighted average of power purchase costs (inclusive of fixed and variable charges) of top 5% power at the margin, excluding liquid fuel based generation, in the merit order approved by the SERC adjusted for average loss compensation of the relevant voltage level and (b) The distribution charges determined on the principles as laid down for intra-state transmission charges. Surcharge formula: S = T–[C/ (1-L) +D] Where S is the surcharge T is the Tariff payable by the relevant category of consumers; C is the Weighted average cost of power purchase of top 5% at the margin excluding liquid fuel based generation and renewable power D is the Wheeling charge APSPDCL Page 124 L is the system losses for the applicable voltage level, expressed as a percentage The Hon’ble commission, in 2015-16 determined the Cross Subsidy Surcharge for various categories of consumers based on the embedded cost methodology. The Commission is of the opinion that Embedded Cost Approach is the most appropriate approach since the embedded accounting costs are actually used to allocate costs to various consumer categories and to determine the current level of cross-subsidy. As per National Tariff Policy, the Cross Subsidy Surcharge has to be determined based on avoided cost methodology. In view of this, the licensee would like to file a proposal for determination of cross-subsidy surcharge for Open Access transactions along with this ARR filing for FY 2016-17. It may be noted that the licensee has adopted the methodology stated in the National Tariff Policy for determination of the cross-subsidy surcharge. The Cross Subsidy as computed by the licensee for each category is as shown below: SPDCL Categories HIGH TENSION HT Category at 11 kV HT-I Indl Segregated HT-II - Industrial Non Segregated HT - III Aviation HT -IV A Govt Lift Irrigation HT-VI -Colony Supply HT- VII Green Power Rural co-operatives Temporary HT Category at 33 kV HT-I Indl Segregated HT-II - Industrial Non Segregated HT - III Aviation HT -IV A Govt Lift Irrigation HT-VI -Colony Supply HT- VII Green Power Rural co-operatives Temporary APSPDCL Cross Average Marginal Wheeling Applicable Subsidy Realization PP Charges Loss% Surcharge (Rs./unit) (Rs./unit) (Rs./unit) (Rs./unit) 8.01 9.35 8.06 5.41 6.37 0.43 - 5.36 5.36 5.36 5.36 5.36 5.36 5.36 5.36 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 10.23% 10.23% 10.23% 10.23% 10.23% 10.23% 10.23% 10.23% 1.46 2.80 1.50 0.00 0.00 0.00 0.00 0.00 6.74 9.07 8.43 5.29 6.47 - 5.36 5.36 5.36 5.36 5.36 5.36 5.36 5.36 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 6.83% 6.83% 6.83% 6.83% 6.83% 6.83% 6.83% 6.83% 0.80 3.13 2.49 0.00 0.53 0.00 0.00 0.00 Page 125 Categories HT Category at 132 kV HT-I Indl Segregated HT-II - Industrial Non Segregated HT - III Aviation HT -IV A Govt Lift Irrigation HT-V –Railway Traction HT-VI -Colony Supply HT- VII Green Power Rural co-operatives Temporary Cross Average Marginal Wheeling Applicable Subsidy Realization PP Charges Loss% Surcharge (Rs./unit) (Rs./unit) (Rs./unit) (Rs./unit) 6.43 7.76 5.62 6.97 - 5.36 5.36 5.36 5.36 5.36 5.36 5.36 5.36 5.36 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 3.34% 3.34% 3.34% 3.34% 3.34% 3.34% 3.34% 3.34% 3.34% 0.72 2.05 0.00 0.00 1.27 0.00 0.00 0.00 0.00 Revenue Impact SPDCL: The total revenue impact due to above tariff proposals is Rs. 488.35 Cr. APSPDCL Page 126 Tariff Table for All Consumer Categories The present and proposed tariffs for all consumer categories are as shown below: Category Units Rates for FY 2015-16 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Rates for FY 2016-17 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit LT Category I Domestic Group A: All Domestic consumers with annual consumption < = 600 kWh First 50 units kWh 1.45 1.45 51-100 units kWh 2.60 2.60 101 - 200 units kWh 3.60 Above 200 units kWh 3.60 6.70 8.80 Group B: All Domestic consumers with consumption ( < =2400 and > 600 units) First 50 units kWh 2.60 2.60 51-100 units kWh 2.60 2.60 101 - 200 units kWh 3.60 201 - 300 units kWh Above 300 units kWh 3.60 6.70 7.22 7.75 8.80 Group C: All Domestic consumers with annual consumption >2400 units First 50 units kWh 2.60 2.67 51-100 units kWh 3.33 101 - 200 units kWh 201 - 300 units kWh 301 - 400 units kWh 3.25 4.88 5.63 6.70 7.22 7.75 401 – 500 units Above 500 units kWh 8.27 8.48 kWh 8.80 9.02 APSPDCL 6.90 6.90 7.75 5.39 7.07 7.94 Page 127 Category LT Category II Nondomestic/Commercial LT II (A) Upto 50 Units/Month LT II (B) Above 50 Units/Month 0-50 units Units Rates for FY 2015-16 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Rates for FY 2016-17 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit kWh/kVAh 53/kW 5.40 55/kW 5.62 kWh/kVAh 53/kW 6.63 55/kW 6.90 51-100 units kWh/kVAh 53/kW 7.38 55/kW 7.68 101-300 units kWh/kVAh 53/kW 8.54 55/kW 8.88 301-500 units kWh/kVAh 53/kW 9.06 55/kW 9.42 Above 500 Units LT-II(C) Advertising Hoardings LT Category III Industry Industries Seasonal Industries (Off Season) Aquaculture & Animal Husbandry Sugarcane crushing Mushroom & Rabbit Farms Floriculture in Green House LT Category IV Cottage Industries Cottage Industries upto 10 HP@ Agro based activity upto 10 HP@ LT Category V Agriculture LT V (A) Agriculture with DSM Measures Corporate Farmers & IT Assesses Wet Land Farmers (Holdings >2.5 acre) Dry Land Farmers (Connections > 3 nos.) kWh/kVAh 53/kW 9.59 55/kW 9.97 kWh/kVAh 53/kW 11.58 55/kW 12.04 kWh/kVAh 53/kW 6.38 55/kW 6.64 kWh/kVAh 53/kW 7.09 55/kW 7.37 kWh/kVAh 21/kW 4.63 21/kW 3.75 kWh/KVAh 21/kW 4.63 22/kW 4.82 kWh/kVAh 53/kW 5.63 55/kW 5.86 kWh/kVAh 53/kW 5.63 55/kW 5.86 kWh 20/kW 3.75 21/kW 3.90 kWh 20/kW 3.75 20/kW 3.75 kWh 0 2.50 0 2.50 kWh * 525/HP/Year 0.50 * 525/HP/Year 0.50 kWh * 525/HP/Year 0.50 * 525/HP/Year 0.50 APSPDCL Page 128 Category Wet Land Farmers (Holdings <= 2.5 acre) Dry Land Farmers (Connections <= 3 nos.) LT V (B) Agriculture without DSM Measures Corporate Farmers & IT Assesses Wet Land Farmers (Holdings >2.5 acre) Dry Land Farmers (Connections > 3 nos.) Wet Land Farmers (Holdings <= 2.5 acre) Dry Land Farmers (Connections <= 3 nos.) Category LT V(C) Others Salt farming units with CL up to 15HP $ Rural Horticulture Nurseries upto 15HP $ LT Category VI Street Lighting & PWS LT VI (A)-Street Lighting Panchayats Units Rates for FY 2015-16 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Rates for FY 2016-17 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit kWh 0 0 0 0 kWh 0 0 0 0 kWh 0 3.50 0 3.50 kWh * 1050/HP/Year 1.00 * 1050/HP/Year 1.00 kWh * 1050/HP/Year 1.00 * 1050/HP/Year 1.00 kWh * 525/HP/Year 0.50 * 525/HP/Year 0.50 kWh * 525/HP/Year 0.50 * 525/HP/Year 0.50 kWh 20/HP 3.70 20/HP 3.70 kWh 20/HP 3.70 20/HP 3.70 kWh 32/kW 5.64 33/kW 5.87 Municipalities kWh 32/kW 6.16 33/kW 6.41 Municipal Corporations LT VI (B) PWS Schemes Panchayats kWh 32/kW 6.69 33/kW 6.96 kWh/kVAh 32/HP 4.59 33/HP 4.77 Municipalities kWh/kVAh 32/HP 5.64 33/HP 5.87 Municipal Corporations LT - VI(C) NTR Sujala Padhakam LT Category VII General kWh/kVAh 32/HP 6.16 33/HP 6.41 kWh/kVAh 10/HP 4.00 10/HP 4.00 kWh/kVAh 21/KW 6.86 22/KW 7.13 LT VII (A) - General Purpose APSPDCL Page 129 Category LT VII (B) – Religious Places Units Rates for FY 2015-16 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Rates for FY 2016-17 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit kWh 20/KW 4.70 21/KW 4.89 kWh/kVAh 21/KW 9.90 22/KW 10.30 HT I (A) General 132 KV and above kVAh 5.15 kVAh 11 KV kVAh Rs. 386/KVA/Month of maximum demand recorded or 90% of CMD whichever is higher 5.36 33 KV Rs. 371/KVA/Month of maximum demand recorded or 80% of CMD whichever is higher Lights & Fans 132 KV and above kVAh 5.15 5.36 33 KV kVAh 5.57 5.79 11 KV kVAh 6.02 6.26 132 KV and above kVAh 5.96 6.20 33 KV kVAh 5.96 6.20 11 KV kVAh 5.96 6.20 Seasonal Industries 132 KV and above kVAh 33 KV kVAh 11 KV kVAh Time-of-Day Tariff (6 PM to 10 PM) 132 KV and above kVAh 6.20 6.45 kVAh 6.62 6.88 kVAh 7.07 7.35 LT Category VIII Temporary Supply HT-I Industry 5.57 6.02 5.79 6.26 Industrial Colonies 33 KV 11 KV Rs. 371/KVA/Month of maximum demand recorded or 80% of CMD whichever is higher 6.33 6.59 7.25 Rs. 386/KVA/Month of maximum demand recorded or 90% of CMD whichever is higher 6.58 6.85 7.54 HT I (B) Energy APSPDCL Page 130 Category Units Rates for FY 2015-16 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Rates for FY 2016-17 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Intensive Industries 132 KV and above kVAh 4.81 4.81 33 KV kVAh 5.23 5.23 11 KV HT I (C) Aquaculture & Animal Husbandry 11 KV kVAh 5.68 5.68 kVAh New category Rs. 21/kVA 3.75 Rs. 386/KVA/Month of maximum demand recorded or 90% of CMD whichever is higher 6.58 HT II (A) Others Rs. 371/KVA/Month of maximum demand recorded or 80% of CMD whichever is higher 132 KV and above kVAh 33 KV kVAh 11 KV kVAh Time-of-Day Tariff (6 PM to 10 PM) 132 KV and above kVAh 7.38 7.68 33 KV kVAh 7.64 7.95 11 KV HT II (B) Religious Places kVAh 8.30 8.63 11 kV kVAh HT III Public Infrastructure & Tourism 132 KV and above kVAh 33 KV kVAh 11 KV kVAh Time-of-Day Tariff (6 PM to 10 PM) 132 KV and above kVAh 7.06 7.34 kVAh 7.36 7.65 kVAh 7.96 8.28 33 KV 11 KV APSPDCL 6.33 6.59 7.25 New category Rs. 371/KVA/Month of maximum demand recorded or 80% of CMD whichever is higher 6.01 6.31 6.91 6.85 7.54 Rs. 21 / kVA 4.89 Rs. 386/KVA/Month of maximum demand recorded or 90% of CMD whichever is higher 6.25 6.56 7.19 Page 131 Category HT IV Irrigation, Agriculture & CPWS Lift Irrigation & Agriculture CP Water Supply Schemes HT V Railway Traction 132 KV HT VI Townships & Residential Colonies Units Rates for FY 2015-16 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit Rates for FY 2016-17 Fixed/Demand Energy Charges in Rs/ Charges Month Rs/Unit kVAh 5.64 5.60 kVAh 4.61 4.79 kVAh KVAh 6.68 Rs. 53/KVA/Month of Billing demand 5.96 6.95 Rs. 55/KVA/Month of Billing demand 6.20 RESCOs Kuppam HT VII Green Power HT VII Temporary kWh kVAh 0.24 0.41 11.32 1.5 times of the Tariff of corresponding HT category 11.32 1.5 times of the Tariff of corresponding HT category @ - Units which exceed 10 HP connected load shall be billed at tariff specified for LT-III Industrial category * -Equivalent flat rate of tariff $ - Units with connected load more than 15 HP shall be billed under LT –III Industrial Normal tariff Note: All other conditions are as per in the Chapter -XII of the Retail supply Tariff Schedule for FY 2015-16. The total revenue increase from the tariff proposals for both licensees is Rs. 783.05 Crs. APSPDCL Page 132