Ambawatta Buildwell Pvt. Ltd.

advertisement
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Six-Monthly Environmental Compliance Report of
Stipulated Conditions of Environmental Clearance
(June 2013 to Nov 2013)
For
“Group Housing Project”
SECTOR-3, Village Gwal Pahari
Gurgaon (Haryana)
For Submission to:
Ministry of Environment and Forests (MOEF)
Submitted by:
Ambawatta Buildwell Pvt. Ltd.
NOV, 2013
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
INDEX
Description
Page No.
Chapter 1 Compliance of Stipulated Conditions of Environmental Clearance
Part A
Part B
Specific Conditions for buildings in operational phase
4
I. Construction Phase
4
II. Operation Phase
8
General Conditions
12
Chapter 2 Details of Environmental Monitoring
2.2
Ambient Air Quality Monitoring
14
2.2.1
Ambient Air Quality Monitoring Stations
14
2.2.2
Ambient Air Quality Monitoring Methodology
14
2.2.3
Ambient Air Quality Monitoring Results
15
2.2.4
Discussion on Ambient Air Quality in the Study Area
16
2.3
Ambient Noise Monitoring
17
2.3.1
Ambient Noise Monitoring Locations
17
2.3.2
Methodology of Noise Monitoring
17
2.3.3
Ambient Noise Monitoring Results
17
2.3.4
Discussion on Ambient Noise Levels in the Study Area
18
2.4
Groundwater Quality Monitoring
19
2.4.1
Groundwater Quality Monitoring Locations
19
2.4.2
Methodology of Groundwater Quality Monitoring
19
2.4.3
Groundwater Quality Monitoring Results
20
2.4.4
Discussion on Groundwater Quality in the Study Area
21
2.5
Soil Monitoring
22
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Description
Page No.
2.5.1
Soil Monitoring Locations
22
2.5.2
Methodology of Soil Monitoring
22
2.5.3
Soil Monitoring Results
23
2.5.4
Discussion on Soil Characteristics in the Study Area
23
2.1
Location-wise Variation of Ambient Air Quality
16
2.2
Location-wise Variation of Ambient Noise Levels
18
Figures
Annexure
1
Lab reports of Ambient Air, Ambient Noise, Water and Soil monitoring
2
Clearance from Airport Authority.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
S. No.
PART A:- SPECIFIC CONDITION
Construction Phase:CONDITIONED OF EIA CLEARENCE REPLY
[i]
A first aid room as proposed in the project
report
shall
be
provided
Adequate first Aid facilities have been
during ensured for construction labours.
construction and operation phase of the
project.
[ii]
Adequate drinking water and sanitary Yes being complied. Adequate facilities
facilities
should
be
provided
for are being provided in regard to drinking
construction workers at the site. Provision water, sanitation and
solid waste
should be made for mobile toilets. Open management.
defecation by the labours is strictly
prohibited. The safe disposal of waste
water and solid waste generated during the
construction phase should be ensured.
[iii]
All
the
top
soil
excavated
during Complied. The same excavated earth
construction activities should be stored for will
be
reused
for
horticulture
use in horticulture/ landscape development development.
within the project site.
[iv]
Disposal of muck during construction Yes, all the practicable precautions are
phase should not create any adverse effect being adopted for the proper disposal of
on the neighbouring communities and be excavation materials at project site and
disposed
off
taking
the
necessary it will not go beyond our project
precautions for general safety and health premises.
aspects of people, Only in approved sites
with the approval of competent authority.
[v]
Construction spoils including bituminous Complied; all feasible precautions will
material and other hazardous materials, be undertaken to prevent water source
must not be allowed to contaminate contamination.
watercourse and the dump sites for such
material must be secured so that they
should not leach into the ground water and
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
any hazardous waste generated during
construction phase, should be disposed off
as per applicable rules and norms with
necessary approval of the Haryana State
Pollution Control Board.
[vi]
The diesel generator sets to be used during DG sets during construction phase are
construction phase should be of low used for running only the site office.
sulphur diesel type and should conform to And they are operated only during
Environment (Protection) Rules prescribed power
for air and noise emission standards.
failure;
added
that
the
construction activities are during day
time only. Hence usage of D.G. sets
during construction phase is minimal.
D.G. sets being used in the construction
phase
are
as
per
Environment
(Protection) Rules for air and Noise
emission standard. Only low sulphur
diesel is used for DG sets.
[vii]
The diesel required for operator DG sets Will be complied.
shall be stored in underground tanks and if
required, clearance from Chief controller
of Explosive shall be taken.
[viii]
Ambient noise levels should conform to
Available best construction practices
residential standards both during day and are followed to take care of the
night. Incremental pollution loads on the Environment. The Lab Analysis Report
ambient air and noise quality should be attach as Annexure 1.
closely monitored during construction
phase. Adequate measures should be taken
to reduce ambient air and noise level
during construction phase, so as to conform
to the stipulated residential standards.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
[ix]
Fly ash should be used as building material Yes, fly ash based ready mixed
in the construction as per the provision of concrete material is used in building
Fly Ash notification of September 1999 construction.
and amended as on 27th August 2003.
[x]
Ready mixed concrete must be used in Yes, ready mixed concrete is used for
building construction.
[xi]
building construction.
Strom water control and its re-use as per Yes, being complied. Layout of storm
CGWB and BIS Standards for various water drainage network has already
applications should be ensured.
[xii]
submitted.
Water demand during construction should Yes, pre-mixed concrete is being used
be reduced by use of Premixed concrete, and will be used to reduce the water
curing agents and other best practices as demand during the construction phase
referred.
[xiii]
of the project.
Permission from component Authority for Yes, MOU will be signed With HUDA.
supply of water shall be obtained prior to
operation of the project.
[xiv]
Roof should meet perspective requirements All the roofs will be designed as per
as per Energy conservation Building Code ECBC norms and will be insulated to
by using appropriate thermal insulation minimize heat gain.
material to fulfil requirements.
[xv]
Opaque wall should meet prescriptive The
project
is
being
developed
requirements as per Energy Conservation according to ECBC norms.
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it
is aspirational
for non-air-
conditioned spaces by use appropriate
thermal
insulation
material
to
fulfil
requirement
[xvi]
The approval of the competent authority Yes, being complied. The project is
shall be obtained for structural safety of the
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
building
on
account
of
earthquake, being developed as per NBC norms.
adequacy of fire fighting equipments, etc.
as per National Building Code including
protection measures from lighting etc. If
any forest land is involved in the proposed
site, clearance under Forest Conservation
Act shall be taken from the Competent
Authority.
[xvii]
The said project doesn’t fall under
forest land. Copy of NOC issued from
forest department, has already been
submitted. The necessary approval will
be taken in the operation phase,
whoever safely measures are adopted
from any fire etc.
The project proponent will use the water Yes, being complied. Agreement with
for construction phase through tankers. private water tanker to supply water
However, prior permission from CGWA from safe zone has already been
will be taken before using the bore well submitted.
water for construction purpose.
[xviii]
The project proponent will construct rain Yes, being complied. Rain water
water harvesting pits@1pit per acre for Harvesting pit details have already
recharging the ground water within the submitted.
project premises.
[xix]
The
project
proponent
will
start Yes, we have obtained clearance from
construction only after getting permission Airport Authority for the said project.
of the Airport authority.
Copy of the same is enclosed as
Annexure 2.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
[i]
Operation Phase:The STP shall be installed for the treatment Yes, will be complied.
of the sewage generated to the prescribed
standards
including
odour
and
treated
effluent will be recycled to achieve zero exit
Relevant details have been already
submitted.
discharge. The STP should be installed at the
remotest place in the project area.
[ii]
Separation of the gray and black water Will be complied. Dual plumbing
should be done by the use of dual plumbing system will be adopted to avoid the
line. Treatment of 100% gray water by contamination between fresh water
decentralized treatment should be done and the tertiary level treated water.
ensuring that the re-circulated water should
be have BOD maximum 10ppm and the
recycled water will be used for flushing,
gardening and DG set cooling and running of
fountain in the water body.
[iii]
For disinfections of the treated wastewater Yes, ultra violet radiation system will
ultra violate radiation or ozonization should be adopted.
be used.
[iv]
The solid waste generated should be properly The generated solid waste from the
collected and segregated. Bio-degradable project will be managed as per MSW
waste will be decomposed at site and Rules 2000. Details are already
dry/inert solid waste should be disposed off submitted with initial compliance
to the approved sites for land filling after report.
recovering recyclable material.
[v]
Diesel power generating sets proposed as All the DG sets provided for the
source of backup power for lifts, common project will be acoustically treated
area illumination and for domestic use should and will conform to rules made under
be of enclosed type and conform to rules Environment (Protection) Act for air
made under the Environment (Protection) and noise emission standard. The
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
Act, 1986. The location of the DG sets provided DG sets will use low sulfur
should be in the basements as promised by content HSD.
the project proponent with appropriate stack
height i.e. above the roof level of the building
as per the CPCB norms. The diesel used for
The stack height will be kept as per
CPCB norms.
DG sets should be of Low Sulphur contents
(maximum 0.25%).
[vi]
Ambient Noise level should be controlled to Will be complied.
ensure that it does not exceed the prescribed
standards both within and at the boundary of
the Proposed Residential Complex.
[vii]
The project proponent should maintain at Yes, the green belt will be developed
least 20% as green cover for tree plantation as per the guidelines of SEAC
especially all around the periphery of the Haryana.
project and on the road sides preferably with
local species so as to provide protection
against particulates and noise. The open
spaces inside the plot should be preferably
landscaped
and
covered
Please refer the landscape details
submitted with initial compliance
report.
with
vegetation/grass.
[viii]
Weep holes in the compound front wall shall Will be complied. Relevant plans
be provided to ensure natural drainage of rain already submitted.
water in the catchments area during the
monsoon period.
[ix]
Rain water harvesting for roof run-off and Will be complied.
surface runoff, as per plan submitted should
be implemented. Before recharging the
surface run-off, pre-treatment must be done
to remove suspended matter, oil & grease.
The bore well for rainwater recharging
should be kept at least 5mts. Above the
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
highest ground water table.
[x]
The ground water level and its quality should Being complied. Sampling results are
be monitored regularly in consultation with covered under Monitoring Reports
Central ground Water Authority.
[xi]
enclosed as Annexure 1
There should be no traffic congestion near The road network for the project has
the entry and exit points from the roads been designed as per the applicable
adjoining the proposed project site. Parking guidelines. Please refer the submitted
should be fully internalized and no public parking plan with initial compliance
spaces should be utilized.
[xii]
A
report
on
the
report.
energy
conservation Will be complied.
measures confirming to energy conservation
norms
finalize
by
Bureau
of
Energy
Efficiency should be prepared incorporating
details
about
building
materials
and
technology, R and U factors, etc and
submitted to SEIAA, Haryana in three
months time.
[xiii]
Energy
conservation
measures
like Installation
of
CFLs/TFLs
for
installation of CFLs/TFLs for lighting the lighting the area will be integral part
area outside the building should be integral of the project design. Used/damaged
part of the project design and should be in CFLs will be stored separately from
place before project commissioning. Used domestic waste in a HDPE container
CFLs and TFLs should be properly collected and periodically will be handed over
and disposed off/sent for recycling as per the only to Authorized Vendor. Solar
prevailing guidelines/rules of the regulatory lighting feasibility will be explored
authority to avoid mercury contamination. for the project.
Use of solar panels must be adapted to the
maximum
extent
possible
for
energy
conservation.
[xiv]
The solid waste generated should be properly The solid waste generated will be
collected
and
segregated
as
per
the properly collected and segregated as
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
requirements of the MSW rules, 2000 and as per the requirements.
amended from time to time. The biodegradable waste should be composted by
vermin-compositing at the site ear marked
within the project area and dry/inert solid
The
details
of
solid
waste
management plan proposed for the
project have been submitted already.
waste should be disposed off to the approved
sites
for
land
filing
after
recovering
recyclable material.
[xv]
The provision of the solar water heating Since the project is a commercial
system shall be as per the norms specified by complex development so there are no
HAREDA and shall be made operational in requirements of solar hot water
each building block.
[xvi]
system.
The project proponent will use the water All requisite permission from the
from the tube well for domestic purposes and competent authorities will be taken.
commercial
purpose
only after
getting
permission from CGWA or will use water
supply from HUDA whichever is earlier
during operation phase.
[xvii]
The traffic plan and the parking plan Yes, will be complied.
proposed by the project proponent should be
adhered to meticulously with further scope of
additional parking for future requirements.
There should be no traffic congestion near
the entry and exit points from the roads
adjoining the proposed site. Parking should
be fully internalized and no public space
should be used.
Please refer the submitted parking
plan with initial compliance report.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
PART B:-GENERAL CONDITIONS
[i]
The environmental safeguards contained in Yes,
the
EIA/EMP
Reports
should
Adequate
environmental
be safeguards will be implemented for
implemented in letter and spirit.
the proposed project in a time bound
and satisfactory manner.
[ii]
Six monthly compliance reports should be Being complied.
submitted to the HSPCB and Regional
Office, MoEF, GOI, Northern Region,
Chandigarh and a copy to the SEIAA,
Haryana
[iii]
The SEIAA , Haryana reserves the right to We will abide by the additional
add
additional
subsequently,
safeguards
if
found
measures safeguards time to time if suggested
necessary, by
the
ministry
in
future
as
Environmental Clearance granted will be applicable and technically feasible.
revoked if it is found that false information
has been given for getting approval of this
project.
[iv]
The project proponent will start construction Yes, we have obtained clearance
only after getting NOC from the forest from forest department for the said
department that the area under consideration project. Copy already submitted.
does not fall under section -4 and -5 PLPA1990.
[v]
All other statutory clearances such as the We are committed to abide by the
approvals for storage of diesel from Chief rules applicable for the project.
Controller of Explosives, Fire Department,
Civil
Aviation
Conservation
Act,
Department,
1980
and
Forest
wildlife
Approvals of:

(Protection) Act, 1972. Forest Act, 1927,
PLPA 1900, etc. shall be obtained as
applicable by project proponent from the
Chief Controller of Explosives:
will be obtained in time.

PLPA, 1900, Forest Act, 1927:
Already submitted.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
[vi]
respective authorities prior to construction of

Forest Conservation Act: N/A
the project.

Wildlife Act : N/A
The project proponent will not violate any We are committed to adhere to the
judicial orders/pronouncements issued by the said stipulations stated by SEIAA in
Hon’ble Supreme Court/High Courts.
[vii]
the said EC letter.
The project proponent shall seek NOC from Yes, we have obtained clearance
the Mining Department before the start of from Mining Department for the said
construction activity.
project.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
CHAPTER- 2
Details of Environmental Monitoring
2.1
AMBIENT AIR QUALITY MONITORING
2.1.1 Ambient Air Quality Monitoring Stations
Ambient air quality monitoring has been carried out at two locations, one being near
the front gate and one location is Project site of the building to assess the ambient air
quality of the project site. This will enable to have a comparative analytical
understanding about air quality and the changes in the air environment in the study
area with respect to the condition prevailing. The locations of the ambient air quality
monitoring stations are given in Table 2.1.
Table 2.1 Details of Ambient Air Quality Monitoring Stations
S. No.
Location Name
Location Code
Environmental Setting
1.
AAQ-1
Near Front Gate
Residential
2.
AAQ-2
Near Project Site
Residential
AAQ-1: Front Gate
The sampler was placed near front gate of building and was free from any
obstructions. Surroundings of the sampling site represent residential environmental
setting
AAQ-2: Project Site
The sampler was placed near project site of building. Vicinity represents residential
environmental setting.
2.1.2 Ambient Air Quality Monitoring Methodology
Monitoring was conducted in respect of the following parameters:

Particulate Matter 2.5 (PM 2.5)

Particulate Matter 10 (PM 10)

Sulphur Dioxide (SO2)

Oxides of Nitrogen (NOx)

Carbon Monoxide (CO)
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
The duration of sampling of PM2.5, PM10, SO2 and NOx was 24 hourly continuous
sampling per day and CO was sampled for 8 hours continuous, thrice in 24 hour
duration monitoring. The monitoring was conducted for one day at each location. This
is to allow a comparison with the National Ambient Air Quality Standards.
The air samples were analyzed as per standard methods specified by Central Pollution
Control Board (CPCB) and IS: 5182. The techniques used for ambient air quality
monitoring and minimum detectable levels are given in Table 2.2.
Fine Particulate Sampler instruments have been used for monitoring Particulate
Matter 2.5 (PM2.5 i.e. <2.5 microns), and Respirable Dust Sampler was used for
sampling Respirable fraction (<10 microns), gaseous pollutants like SO2, and NOx.
Bladder and Aspirator bags were used for collection Carbon monoxide samples. Gas
Chromatography techniques have been used for the estimation of CO.
Table 2.2 Techniques used for Ambient Air Quality Monitoring
S. No.
Parameter
Technique
Technical Protocol
1
Particulate Matter
2.5
Fine Particulate Sampler, Gravimetric
Method
CPCB/MOEF
Guideline
2
Particulate Matter 10 Respirable Dust Sampler, with cyclone IS-5182 (Part-23)
separator, Gravimetric Method
3
Sulphur dioxide
Modified West and Gaeke
IS-5182 (Part- II)
4
Oxides of Nitrogen
Jacob & Hochheiser
IS-5182 (Part-VI)
5
Carbon Monoxide
Gas Chromatography
IS-5182 (Part-X)
2.1.3 Ambient Air Quality Monitoring Results
The detailed on-site monitoring results of PM2.5, PM10, SO2, NOx and CO are
presented in Table 2.3.
Table 2.3 Ambient Air Quality Monitoring Results
S.No. Location
Location
PM10
PM2.5
(g/m3) (g/m3)
Code
SO2
NOx
CO
(g/m3)
(g/m3)
(mg/m3)
1.
AAQ1
Near Main Gate
87.35
41.30
11.20
22.30
<0.50
2.
AAQ2
Near Project Site
83.25
39.24
9.36
19.20
<0.50
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
120
100
80
AAQ1
60
AAQ2
LIMIT
40
20
0
PM10
PM2.5
SO2
Nox
Figure 2.1 Location-wise Variation of Ambient Air Quality
2.5
2
1.5
CO(mg/m3)
1
0.5
0
AAQ1
AAQ2
LIMIT
Figure 2.2 Location-wise Variation of Ambient Air Quality
2.1.4 Discussion on Ambient Air Quality in the Study Area
PM10 and PM2.5 levels at the project site are under the permissible limit of 100 μg/m3 and
60 μg/m3 respectively (for residential, rural and other areas as stipulated in the National
Ambient Air Quality Standards). SO2, NOx and CO was observed within the
corresponding stipulated limits (Limit for SO2 and NOx: 80 g/m3 and limit for CO: 4.0
mg/m3) at all monitoring locations. Station wise variation of ambient air quality
parameters has been pictorially shown in Figure 1&2
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.2
AMBIENT NOISE MONITORING
2.2.1 Ambient Noise Monitoring Locations
The main objective of noise monitoring in the study area is to assess the present
ambient noise levels in project site & project boundary due to various construction
allied activities and increased vehicular movement. A preliminary reconnaissance
survey has been undertaken to identify the major noise generating sources in the area.
Ambient noise monitoring was conducted at locations at the boundary of the project
site as given in Table 2.4
Table 2.4 Details of Ambient Noise Monitoring Stations
S. No. Locn. Code
1.
Location Name/ Description
Present Land use
Near Main Gate
Residential
N1
2.2.2 Methodology of Noise Monitoring
Noise levels were measured using sound level meter. Noise level monitoring was
carried out continuously for 24-hours with one hour interval starting at 06:00 hrs to
06:00 hrs next day. The noise levels were monitored on working days only. During
each hour Leq were directly computed by the instrument based on the sound pressure
levels. Leq day & Leq night values were computed using correspond in hourly .
Monitoring was carried out at ‘A’response and fast mode.
2.2.3 Ambient Noise Monitoring Results
The location wise ambient noise monitoring results is summarized in Table 2.5. The
location-wise variation of noise levels are graphically presented in Figure 2.2.
Table 2.5 Ambient Noise Monitoring Results
Day
Location code
Location
Leq
N1
Night
Near Main Gate
56.20
Lmin
52.30
Lmax
62.30
Leq
50.25
Lmin
47.50
Lmax
54.20
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
70
60
50
40
Day
30
Night
20
10
0
Leq
Lmin
Lmax
Figure 2.2 Location-wise Variation of Ambient Noise Levels
2.2.4 Discussion on Ambient Noise Levels in the Study Area
Day Time Noise Levels (Lday):
The day time noise level at all the locations were found to within limits prescribed for
commercial area i.e. 65 db(A).
Night Time Noise Levels (Lnight):
The night time noise level at all the locations were found to within limit prescribed for
commercial area i.e. 55 dB (A).
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.3
GROUNDWATER QUALITY MONITORING
2.3.1 Groundwater Quality Monitoring Locations
Keeping in view the importance of groundwater as an important source of drinking
water to the local population, sample of ground water was collected from the project
site for the assessment of impacts of the project on the ground water quality.
Water sample was collected from the project site. The sample was analyzed for various
parameters to compare with the standards for drinking water as per IS: 10500 for
ground water sources. The details of water sampling locations are given in Table 2.6.
Table 2.6 Details of Water Quality Monitoring Station
S. No. Locn. Code
GW 1
1.
Location Name/ Description
Onsite
2.3.2 Methodology of Groundwater Quality Monitoring
Sampling of ground water was carried out on April 2013. Samples were collected as
grab sample and sampling forms are filled in as per the sampling plan. The preservative
sample were properly added to preserve as per standard operating procedures (SOP)
and stored immediately in ice boxes, which were ensured for appropriate temperatures.
Sample for chemical analysis was collected in polyethylene carboys. Sample collected
for metal content were acidified to <2 pH with 1 ml HNO3. A sample for
bacteriological analysis was collected in sterilized glass bottles.
Soon after the completion of sampling, chain of custody sheets for the samples are
filled in and then they were transported by road to Vardan Enviro Lab Gurgaon for
further analysis. Proper care was taken during packing and transportation of samples.
After ensuring the same the samples were forwarded immediately for analysis.
The samples were analyzed as per the standard procedures specified in 'Standard
Methods for the Examination of Water and Wastewater' published by American Public
Health Association (APHA) and CPCB. The analytical techniques and the test methods
adopted for testing of ground water are given in Table 2.7.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.3.3 Groundwater Quality Monitoring Results
The detailed groundwater quality monitoring results are presented in Table 2.7.
Table 2.7 Groundwater Quality Monitoring Results
S. No.
Parameters
Onsite
Units
Test Method
1
pH
7.11
-
APHA 4500 – H+B
2
Colour
<1.0
Hazen
APHA 2120 B
3
Turbidity
5.0
NTU
APHA 2130 B
4
Odour
5
Taste
6
Total Hardness (as
CaCO3)
236.50
mg/L
7
Chloride (as Cl-)
117.50
mg/L
APHA 4500 –Cl B
8
Calcium (as Ca)
69.50
mg/L
APHA 3500 –Ca B
9
Magnesium (as Mg)
15.33
mg/L
APHA 3500 –Mg B
10
Chlorine Residual
BDL
mg/L
APHA 4500 –Cl B
11
Total Disolve Solids
448.50
mg/L
APHA 2540 D
12
Alkalinity (as CaCO3)
198.50
mg/L
APHA 4500 Norg B
13
Sulphate (as SO4)
54.20
mg/L
APHA 4500 NO3- B
14
Total Kjehldal
Nitrogen
BDL
mg/L
15
Nitrate (as NO3-)
1.65
mg/L
APHA 4500 SO4-- E
16
Fluoride (as F-)
0.56
mg/L
APHA 4500 F- D,B
17
Iron Dissolve (as Fe)
0.24
mg/L
APHA 3500 Fe B
18
Nickel (as Ni)
BDL
mg/L
APHA 3111 B
19
Chromium Total
(as Cr)
Unobjectionable -
APHA 2150 B
-
APHA 2160 B
Agreeable
APHA 2340 C
IS: 3025-1964 (13)
APHA 3111 B
BDL
mg/L
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
S. No.
Parameters
Onsite
Units
Test Method
20
Copper (as Cu)
BDL
mg/L
APHA 3111 B
21
Lead (as Pb)
BDL
mg/L
APHA 3111 B
22
Zinc (as Zn)
<0.01
mg/L
APHA 3111 B
23
Mercury (as Hg)
BDL
mg/L
APHA 5530 D
24
Phenolic Compounds
BDL
mg/L
APHA 3112 B
25
Cyanide (as CN)
BDL
mg/L
APHA 4500 CN- C
26
Cadmium (as Cd)
BDL
mg/L
IS 3025 Part -59
27
Manganese (as Mn)
BDL
mg/L
APHA 3111 B
28
Selenium (as Se)
BDL
mg/L
IS: 3025 Part 56
29
Arsenic (as As)
BDL
mg/L
APHA 3114 B
30
Boron (as B)
0.010
mg/L
APHA 4500 B 8
31
Total Coliform
< 2/100ml
MPN/100 IS: 1622:1981
ml
Absent
MPN/100 IS:1622:1981
ml
32
E. Coli
2.3.4 Discussion on Groundwater Quality in the Study Area
The ground water quality in the project area is observed to be alkaline in nature with
total alkalinity reaching up to 214.14 against desirable limit of 200 mg/L, however,
alkalinity is less than the permissible limit of 600 mg/L. Total dissolved solids in the
ground water is 590.25 mg/L which is higher then prescribed limit of 500 mg/L.
However, remaining parameters are within the CPCB prescribed limits.
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.4
SOIL MONITORING
2.4.1 Soil Monitoring Locations
The objective of the soil monitoring is to identify the impacts of ongoing project
activities on soil quality and also predict impacts, which have arisen due to execution
of various constructions allied activities. Accordingly, a study of assessment of the
soil quality has been carried out.
To assess impacts of ongoing project activities on the soil in the area, the physicochemical characteristics of soils were examined by obtaining soil samples from
selected points and analysis of the same. single sample of soil was collected from the
project site for studying soil characteristics, the location of which is listed in Table
2.8.
Table 2.8 Details of Soil Quality Monitoring Location
S. No. Locn. Code
Location Name/ Description
1.
S1
Onsite
2.4.2 Methodology of Soil Monitoring
The sampling has been done in line with IS: 2720 & Methods of Soil Analysis, Part-1,
2nd edition, 1986 of American Society for Agronomy and Soil Science Society of
America. The homogenized samples were analyzed for physical and chemical
characteristics (physical, chemical and heavy metal concentrations). The soil samples
were collected in the month of Oct. 2013.
The samples have been analyzed as per the established scientific methods for physicochemical parameters. The heavy metals have been analyzed by using Atomic
Absorption Spectro-photometer .
Compliance Report “Group Housing Project” By Ambawatta Build Well Pvt Ltd
2.4.3 Soil Monitoring Results
Single sample of soil is collected from the site to check the quality of soil of the study
area .The physico-chemical characteristics of the soil, as obtained from the analysis of
the soil sample, are presented in Table 2.9.
Table 2.9 Physico - Chemical Characteristics of Soil in the Study Area
S.
No.
Parameters
Test Method
Result
Unit
Onsite
1
pH
TM- S/10
7.25
-
2
Moisture Content
TM- S/16
1.30
%
3
Organic Matter
TM- S/08
0.80
%
4
Phosphorus Available as P
TM- S/11
3.36
mg/100 gm
5
Total Kjehldal Nitrogen
TM- S/17
0.046
%
6
Potassium as K
TM- S/13
59.68
mg/100 gm
7
Exchangable Calcium
TM- S/15
2.15
%
8
Exchangable Magnesium
TM- S/05
0.032
%
9
Iron as Fe
TM- S/05
1.22
mg/kg
10
Zinc as Zn
TM- S/25
3.20
mg/kg
11
Copper as Cu
TM- S/25
1.20
mg/kg
12
Bulk Density
TM- S/25
0.91
Gm/cm3
13
Lead as Pb
TM- S/25
BDL
mg/kg
14
Water Holding Capacity
TM- S/34
101.25
ml/100 gm
15
Sodium as Na
TM- S/47
27.45
mg/100 gm
2.4.4 Discussion on Soil Characteristics in the Study Area
The soil in study area is characterized by moderate organic content. The soil quality in
the project area has not been affected by the project activities.
Download