Appendix A- Project Scope Definition MIDAS Detailed Design

advertisement
2950 HIGHWAY DRIVE UPGRADE FOR
METALLURGICAL INDUSTRIAL DEVELOPMENT
ACCELERATION & STUDIES (MIDAS) FACILITY
Project Scope Definition: Detailed Design
Prepared by:
Kootenay Association for Science and Technology (“KAST”)
Trail, B.C.
(Rev. A Sept 23-2015)
Kootenay Association for Science and Technology (KAST),
#108-2196 LeRoi Ave,
Rossland, BC
V0G 1Y0
Phone:
(250) 362 - 5052
Email: Info@kast.com
www.Kast .com
1|P a g e
RFP No. 1516-01-MIDAS-DD
Appendix A- Project Scope Definition: Detailed Design
1.0
GENERAL
This document was prepared by KAST to provide a summary description of the Scope of Services for
Detailed Design required by an Engineering/Design Consultant firm. This document is to work in
conjunction with KAST Request for Proposals Document RFP 1516-01-MIDAS-DD. In the event of any
conflicts or discrepancies between documents, RFP No. 1516-01-MIDAS-DD is to take precedence.
1.1
MIDAS Project Description
MIDAS is an applied research, commercialization and digital fabrication training facility in Trail, B.C.,
focused on the metallurgical sector that exists in the region surrounding the Teck Trail Operations
smelter. MIDAS makes recent advances in manufacturing technology (including 3D Printing)
accessible to West Kootenay companies, entrepreneurs and students.
MIDAS Goals:
 Support entrepreneur development and the commercialization of applied, market-relevant
research in the metallurgic industry;
 Expand local small and medium-sized companies’ strengths in collaborating, adopting
technology, and creating new and marketable products;
 Promote skills training opportunities in digital fabrication and metallurgical technology for
entrepreneurs, company personnel and students.
MIDAS Activities:
 Public access to an MIT-certified digital fabrication laboratory, or “Fab Lab”, and to
metallurgy-specific equipment provided by Fenix Advanced Materials;
 Technical training in metallurgical science and digital fabrication;
 Organized research and development (R&D) of commercial applications for metals and
materials derived from Teck smelter by-products;
 Business coaching;
 Facilitating co-work and collaboration, hosting workshops and events.
MIDAS is a partnership between the Kootenay Association for Science & Technology (KAST) - a nonprofit society active in the West Kootenay since 1998 - and industry partner Fenix Advanced
Materials, which produces high-purity metals for the semiconductor market. Fenix Advanced
Materials’ operations are underway at 2950 Highway Drive in the areas labelled “Tenant 103” and
“Tenant 104” on Appendix F- MIDAS Facility OVERALL Site Battery Limits, Construction Area
The Government of Canada has provided basic financial support for MIDAS capital expenditure on
digital fabrication laboratory equipment, including installation, to enhance the region’s existing
expertise in rapid prototyping, advanced manufacturing and 3D printing.
There is an expectation that MIDAS will be self-sustaining by 2019. In order to achieve this goal,
significant and paid community membership and ongoing use of the MIDAS facility is essential.
Appendix A- Project Scope Definition: Detailed Design
1-1 | P a g e
1.2
Renovation Project Objective
The objective of this renovation project is to provide at MIDAS an MIT-certified digital fabrication
laboratory or “Fab Lab” for instruction purposes and community and corporate use, along with space
for research and development work related to the metallurgical sector. The MIDAS facility will also
include a communal working, learning and events space or “Learning Centre”. Modifications to the
existing facility at 2950 Highway Drive are required to include and/or improve the following:
1.
2.
3.
4.
Building Exterior
General Building Area Interior
Office and Meeting Room Area
Electronics & Printing Area and Learning Centre Area:
a. Learning Centre: communal work space with capacity to host instruction
sessions and conferences/events
b. Electronics & Printing Area: laser cutter, 3D printing, 3D scanning and
electronics work area
5. Work Shop & Materials Storage Area: wood working, metal working, molding and
casting work spaces, along with a materials storage area and storage space for MIDAS
user projects.
1.3
MIDAS Facility Area Breakdown
For the purposes of the renovation project, the MIDAS facility has been divided as shown on the
Appendix F- MIDAS Facility OVERALL Site Battery Limits, Construction Area and Appendix C- MIDAS
Facility Drawing (CAD), Rev A((which is missing Area 00 and portions of Area 10).
Area #
00
10
Area Description
General Building – Exterior
General Building – Interior
20
30
40
Office and Meeting Room Area
Learning Centre
Electronics and Printing
50
Work Shop & Materials Storage
Area Includes
Façade, Windows/Doors, Signage, Awning
Hallways, Bathrooms, Electrical Room, HVAC,
Janitorial, Future Expansion Areas, Kitchen
Reception, Offices 101-106, Meeting Room
Co-work space, conference & events space
Laser Cutter, 3D Printing, 3D Scanning and
Electronics work spaces
Wood working, Metal working, Molding and
Casting work spaces. Materials Storage space.
Storage space for MIDAS user projects.
Appendix A- Project Scope Definition: Detailed Design
1-2 | P a g e
1.4
1.4.1
Procurement Plan
Purchasing Plan
KAST will order all office furnishings, computers, equipment and tools for MIDAS users to ensure
that the project meets its MIT certification, and installation timeframe.
For details of equipment to be installed and located at the MIDAS facility, please refer to the
appended Appendix B- MIDAS Equipment List. Contractors will supply any material or
equipment not specifically labeled on Appendix B- MIDAS Equipment List as owner-supplied.
1.4.2
Contracting Plan
KAST will issue contracts that will be managed by the MIDAS Project Director during the Design
and Construction Execution phases. The MIDAS Project Director is a KAST representative, and
the contractor’s sole point of contact.
As part of the Detailed Design phase, the Engineering Consultant will be requested to provide
Scopes of Work (SOW) to allow KAST to request pricing from contractors. The Engineering
Consultant will provide tendering and construction support as necessary and at the request of
the MIDAS Project Director.
At this time KAST expects the following major contracts:

Consultant Detailed Design Contract

Demolition and Construction Contracts (4):
o
Work Shop Area Modifications: This lump sum contract will include the demolition
and construction to create the wood working, metal working, molding and casting
work spaces, along with a materials storage area and storage space for MIDAS user
projects.
o
Electronics, Printing and Learning Centre Area Modifications: This lump sum
contract will included the demolition and construction to create the laser cutter, 3D
printing, 3D scanning and electronics work area; and the Learning Centre area - a
communal work space with capacity to host instruction sessions and
conferences/events.
o
Fire Suppression System Modifications: This will be a lump sum contract to include
the design, supply and construct for the modifications to the existing fire
suppressions system to accommodate the new facility.
Appendix A- Project Scope Definition: Detailed Design
1-3 | P a g e
o
Safety Plan and Safety Training: This will be a time and materials contract to include
the design of a comprehensive Safety Plan for the MIDAS facility, personnel and
users, and deliver professional and periodic safety training in the new facility.
Access and modifications to the General Building-Interior Area 10 are likely required, and are
outstanding subject to Detailed Design phase outcomes. These modifications will be added to the
above construction contracts as is necessary and appropriate.
For each of the construction contracts, it is expected that a General Contractor will be awarded the
work, and will be assigned as the Prime Contractor.
Minor modifications to the Office and Meeting Room Area, and to the Building Exterior will be
completed on a time and materials basis at a timeframe convenient to the users of that space.
1.5
Design Criteria
1.5.1
CODES, STANDARDS, ACTS AND REGULATIONS
The design, materials, fabrication and construction shall comply with the latest editions of the
codes, standards, acts and regulations listed below:















1.5.2
Workers’ Compensation Board of British Columbia, “Occupational Health and Safety
Regulation”
British Columbia Building Code
British Columbia Plumbing Code
British Columbia Electrical Code
British Columbia Fire Code
NFPA – National Fire Protection Association
ULC – Underwriters Laboratory of Canada
ASHRAE – American Society of Heating, Refrigeration, and Air Conditioning Engineers
SMACNA – Sheet Metal and Air Conditioning Contractors National Association
CSA – Canadian Standards Association
NEMA – National Electrical Manufacturers Association
ANSI – American National Standards Institute
CISC – Canadian Institute of Steel Construction
http://www.fabfoundation.org/fab-labs/fab-lab-criteria/
BC Environmental Management Act: Temporary Materials Storage: Division 2
GENERAL SITE CONDITIONS
The site is located in Trail, British Columbia. The “authority having jurisdiction” in this area is the
Regional District of Kootenay Boundary (RDKB).
Appendix A- Project Scope Definition: Detailed Design
1-4 | P a g e
Site conditions are as per the BC Building Code.
1.5.3
LIGHTING
All new lighting is to be LED, budget permitting.
Target Illumination Levels are as follows:
Task Categories
Workstations
Emergency Lighting
All Areas
1.5.4
Illumination Levels in LUX
300
10
100
SAFETY:
As a space intended for community use and training, the safety of MIDAS users and personnel is
a critical design consideration. The space will be used by the public with only basic supervision
and training. All possible safety considerations are to be included in the Design Consultant’s
submission to protect users.
A formal Safety Plan will be prepared for MIDAS, and Safety Training implemented for MIDAS
personnel. This work is outside the scope of this Design Consult.
Exit signage is required as per regulations (1.5.1)
Fire protection must be upgraded to meet requirements of building end use.
1.5.5
DESIGN OVERVIEW PER BREAKDOWN AREA
1.5.5.1.
Building Exterior (00)
The building exterior is located at 2950 Highway Drive in Trail, BC.
The building exterior will be cosmetically upgraded to represent MIDAS with professionalism and
a sense of welcome. Signage consistent with the MIDAS brand (to be determined) will be created
and installed on the awning, signpost and exterior facing frosted doors. Some basic parking and
wayfinding signage for MIDAS members and visitors will be created and installed.
The building exterior should be used as a significant opportunity to publically celebrate major
financial contributions to the MIDAS project.
Appendix A- Project Scope Definition: Detailed Design
1-5 | P a g e
1.5.5.2.
General Building Area (10)
The building will be shared between anchor tenant Fenix Advanced Materials and MIDAS, with
room for future expansion. A current tenant (Area 40, Tenant 101, Tenant 118 on Appendix FMIDAS Facility OVERALL Site Battery Limits, Construction Area will vacate the facility by
December 1, 2015.
General Building Areas accessible by MIDAS and relevant to this Design Consult include hallways,
the electrical room and the building’s existing HVAC system.
Other General Building Areas include a kitchen, several bathrooms and a janitorial space.
1.5.5.3.
Office and Meeting Room Area (20)
The Office and Meeting Room Area is to be the primary entry point for MIDAS business,
partner/sponsor and research & development interactions, and so design should represent
MIDAS with professionalism and a sense of welcome.
The Office and Meeting Room Area provides a physical opportunity to celebrate the
achievements of the facility and involved businesses and members, partners, financial
supporters, and to promote a consistent marketing presence or MIDAS brand.
The Office and Meeting Room Area will be shared by Fenix Advanced Materials, Community
Futures of Greater Trail, KAST and graduate interns on R&D assignment. It provides a gathering
area, reception space (101) and offices (102-106) requiring broadband connectivity, cosmetic
and marketing upgrades.
A Meeting Room (107) requires separation from the gathering space (100) and an office (106),
broadband connectivity and meeting/presentation technology installation.
The paint and colour scheme is to match that selected for the Learning Centre.
Furnishings are to be selected by KAST.
1.5.5.4.
Learning Centre (30)
The Learning Centre is a communal work space with the capacity to host instruction sessions and
conferences/events. It requires broadband connectivity and cutting edge meeting/presentation
technology.
The Learning Centre design should facilitate co-work and collaboration, with significant
attention paid to friendly acoustics, enabling both productive work and comfortable
Appendix A- Project Scope Definition: Detailed Design
1-6 | P a g e
conversation. The paint and colour scheme is to be designed for this end use and desired “feel”,
and carried through to the Office and Meeting Room Area for design and brand consistency.
A soundproof booth for private phone calls will be installed, with computer workstations and
internet connection.
Furnishings will be supplied by KAST. Furnishings should be on castors and moveable.
To facilitate event hosting/catering, the Learning Centre is to include a stainless steel sink with
hot and cold water, a dishwasher, counter space, and basic cupboards/drawers for dishes.
Windows and a double-sized glass door between the Learning Centre (30) and the Electronics,
3D Printing, 3D Scanning area (40) will ensure that the two areas feel like a joined space, and
that interesting work in the Electronics, 3D Printing, 3D Scanning area can be viewed from the
Learning Centre, but that scheduled instruction in the Learning Centre does not disrupt and is
not disrupted by work in the Electronics, 3D Printing, 3D Scanning area.
Figure 1. Conceptual example of Learning Centre Space from MIT.
Appendix A- Project Scope Definition: Detailed Design
1-7 | P a g e
1.5.5.5.
Electronics, 3D Printing and Learning Centre Area (40):
The Electronics, 3D Printing and 3D Scanning Area will be accessed by MIDAS users for creation and testing of
projects. It is relatively clean work and interesting to observe. This type of work will be a major focus of the
teaching activities in the adjacent Learning Centre, and it is expected that there will be a visual and physical
flow of MIDAS users between the two spaces, though with restriction of physical and audio flow-through
possible during teaching sessions, conferences and events.
Users of the Electronics, 3D Printing and 3D Scanning Area will require streamlined access to the Work Shop
and Materials Storage Areas (50).
The floor layout of the Electronics, 3D Printing, 3D Scanning Area is to include working area for fixed tools as
per Appendix B- MIDAS Equipment List and Appendix C- MIDAS Facility Drawing.
Electrically, the area should have isolated circuits for all major equipment to allow uninterrupted use. Work
benches are to have 4 plex GCIF protected 20 AMP plugs and high speed internet connections located every
meter along their length.
The Electronics, 3D Printing and 3D Scanning Area is to be designed for public use and teaching, and user
safety considerations are paramount: a power key for the area is required to control power by reception
(Office and Meeting Room Area 20, reception space 101) personnel to minimize potential unauthorized usage
outside of supervised hours. An emergency stop button is to be located at each door, with appropriate
signage. It will cut power to all equipment in the room when pushed.
Work benches with easy-to-clean heat resistant surfaces and shelving are required minimally as follows:
1. Electronics Area: two 1 M X 5 M work benches with shelving above one
2. 3D Printing Area: one 1 M X 4 M work benches with shelving below
3. Laser: one 1M X 2M work bench
Appendix A- Project Scope Definition: Detailed Design
1-8 | P a g e
Figure 2. Conceptual example of Electronics Space from MIT.
Appendix A- Project Scope Definition: Detailed Design
1-9 | P a g e
Figure 3. Conceptual example of 3D Printing Space from MIT.
Appendix A- Project Scope Definition: Detailed Design
1-10 | P a g e
Figure 4. Conceptual example of Laser Space from MIT.
Appendix A- Project Scope Definition: Detailed Design
1-11 | P a g e
1.5.5.6.
Workshop Area & Materials Storage(50)
Rolling work benches will be required to maximize wood and metal workshop space as much as is practical.
These work benches should also be available for Electronic, 3D Printing use (section 1.5.5.5) as space suitable
for large project assembly is constrained in that area.
Electrically, the wood working and metal working areas areas should have isolated circuits for all major
equipment listed above to allow uninterrupted use. Work benches are to have 4 plex GCIF protected 20 AMP
plugs at every meter along length.
Wood working and metals working areas are to each include compressed air piping connections at each
workstation and piece of fixed piece of equipment (see Appendix C- MIDAS Facility Drawing). Connections are
to be quick-connect system similar to that standardly used in wood working shops. One connection per
workstation and two 50’ retractable air hoses are required. Two stations in each area are to be capable to be
used simultaneously.
As a space intended for public use and teaching, design for safety is imperative. A power key for the entire
workshop area is required to control power by reception (Office and Meeting Room Area 20, reception space
101) personnel to minimize potential unauthorized usage outside of supervised hours. An emergency stop
button is to be located at each door, with appropriate signage. It will cut power to all equipment in the room
when pushed.
The Workshop area is broken into four distinct geographical sections:
Wood Working Shop:
Effective dust collection is imperative in the wood working shop. The woodworking area is to contain the
fugitive dust emissions to the rest of the building through negative pressure of the area and the use of a
localized dust collection system. Air quality is to be maintained through fresh air exchanges as much as
possible to minimize the cost of filtration units. All openings are to have a door or vinyl curtains to aid in
containment.
Localized dust collection system is to have ducts running to each workstation for major dust-generating
equipment. Dust collection system is to be capable of being turned on through actuation of a tool or manual
switch at workstation. Localized dust collection system should be sized so that the Shopbot and two (2) tool
work stations can be in use at a given time. Disposal of dust: ensure capability to remove manually without it
having to be transferred from one container to another.
The preference is for the dust collection unit and a necessary air compressor unit to be located in the
Delivery Bay/Materials Storage area with appropriate connections to the Workshop Area including the
Shopbot enclosure.
Molding and Casting Area:
Appendix A- Project Scope Definition: Detailed Design
1-12 | P a g e
This work space is to include a stainless steel counter with an inset sink with hot and cold water, a fume hood
vented to outside, and a convection hood. The size of the counter is to be a minimum of 1m X 5m. Under
counter is to be open shelving for storage of heavy items. This area should be separated from other work
areas using a vinyl curtain.
Figure 5. Conceptual example of Molding Space from MIT.
Metal Working shop:
The safety shower station should be located in the metal working shop. This area should be discrete from the
molding and casting area for safety reasons.
Materials and Project Storage:
Capacity for materials and project storage is to be located in the delivery bay adjoining the Metal Working
Area. This Material and Project Storage Area is to include the following:
1.
2.
3.
4.
5.
6.
Air Compressor for supplying air to tools in the wood working and metal working shops
Dust Collection Unit servicing Shopbot enclosure and wood working shop
Shelving/Storage system for raw materials, specifications per MIDAS Project Director
A large safe secured to the floor in the room for valuable materials
Lockers for storage of projects by MIDAS users
Material Movement Systems Storage:
a. dollies
b. rolling A frame
7. Computer workstation with internet connection for inventory management.
Appendix A- Project Scope Definition: Detailed Design
1-13 | P a g e
2.0
SCOPE OF FACILITIES BY AREA/DISCIPLINE
2.1
Area 00: General Building – Exterior
2.1.1
Civil, Structural and Architectural
The scope in this area includes:








Clean and refurbish awning
Supply and install MIDAS advertising as required onto awning
Supply and install MIDAS signage as required onto signpost
Pressure wash front of exterior building
Wash all windows interior and exterior
Source and install parking and wayfinding signage as required
Assess loading ramp drainage effectiveness
Canvas and advise on external lighting requirements
2.2
Area 10: General Building – Interior
2.2.1
Site Preparation (Demolition and Relocation - all Disciplines)
The scope in this area includes:

2.2.2
Remove and dispose of temporary divider door in N-S corridor adjacent to Learning Centre
Area (Area 30). Appendix F- MIDAS Facility OVERALL Site Battery Limits, Construction Area
for area designations.
Civil, Structural and Architectural
There is no Civil, Structural and Architectural scope of work for this area.
2.2.3
Mechanical and HVAC:
The scope in this area includes:

Assess and document HVAC impact in this area
Appendix A- Project Scope Definition: Detailed Design
2-14 | P a g e
2.2.4
Piping
The scope in this area includes:

2.2.5
Assess and document sprinkler system impact in this area.
Electrical and Instrumentation
The scope in this area includes:



Install owner-supplied internet fiber infrastructure, connection panel and distribution centre
in Electrical Room. Recommend Cat 5E Ethernet cable to electrical termination point and
office internet drops
Replace light bulbs (LED preferred if lumen count attainable per 1.5.3)
Assess and document exit signage per safety requirements
2.3
Area 20: MIDAS Office and Meeting Room Space
2.3.1
Site Preparation (Demolition and Relocation - all Disciplines)
The scope in this area includes:


2.3.2
Civil, Structural and Architectural









2.3.3
Remove and dispose of existing ceiling tiles in T-Bar Ceiling
Remove door between office 106 and meeting room 107
Install meeting technology as per MIDAS Project Director recommendations
Clean carpets, walls and interior windows
Supply and install new ceiling tiles in T-Bar Ceiling
Supply and install wall-sized magnetized promotional board behind reception desk (101)
Supply and install glass door to separate MIDAS Meeting Room (107) from MIDAS Gathering
Area (100)
Infill and paint rough opening from door removal between office 106 and meeting room 107
Supply and install cabinet for secure MIDAS Keybox in Reception (101)
Install office furnishings, computers, screens and projectors as required
Interior painting to match design scheme of Learning Centre
Mechanical and HVAC:
The scope in this area includes:
Appendix A- Project Scope Definition: Detailed Design
2-15 | P a g e

2.3.4
Clean ductwork and service office HVAC unit
Piping
The scope in this area includes:

2.3.5
Assess and document sprinkler system impact in this area.
Electrical and Instrumentation
The scope in this area includes:



2.4
2.4.1
Supply and install high-speed internet drops for each of the desk locations (101-106) and
gathering area (100)
Supply and Install internet/telecom connections for meeting room (107) per MIDAS Project
Director recommendations re meeting technology
Replace light bulbs in all offices
Area 30: MIDAS Conference and Learning Centre
Site Preparation (Demolition and Relocation - all Disciplines)
The scope in this area includes:




2.4.2
Disconnect and remove wiring to panel for electrical located in dividing wall
Remove and dispose of dividing wall up to column line
Remove and replace frosting on exterior doors with MIDAS advertising/wayfinding signage
as required
Disconnect and remove installed wall-mounted HVAC system
Civil, Structural and Architectural
The scope in the area includes:







Refinish end of wall left raw after wall demolition
Clean carpets
Install computer workstations, desks, and other office furnishings
Paint interior of room to colors as selected by Midas Project Director
Reinforce wall at location where presentation technology will be mounted, as necessary and
per MIDAS Project Director recommendations re presentation technology
Supply and install counter top and cupboards for coffee area
Scope and suggest best location for plumbed coffee station: sink and dishwasher
Appendix A- Project Scope Definition: Detailed Design
2-16 | P a g e

2.4.3
Construct 10’ x 10’ soundproof closed room for phone calls in Area 30 Learning Centre
Mechanical and HVAC:
The scope in this area includes:

2.4.4
Supply and install HVAC system for rooms as required to maintain a comfortable work
environment
Piping
The scope in this area includes:


2.4.5
Supply and install sink with hot and cold water
Supply and install dishwasher with hot and cold water
Electrical and Instrumentation
The scope in this area includes:





Supply and install retractable high-speed internet and power connections located in the
ceiling for movable workstations. Document cost and viability of channeling connections in
the floor versus hanging from the ceiling
Supply and install internet/telecom connections for presentation area
Mount presentation technology, as necessary and per MIDAS Project Director
recommendations re presentation technology
Supply and install speaker/microphone system per MIDAS Project Director
recommendations re audio technology
Supply and install replacement light bulbs as required to get room to function
2.5
Area 40: Electronics and Printing
2.5.1
Site Preparation (Demolition and Relocation - all Disciplines)
The scope in this area includes:



Create rough openings for new windows and glass doors to be located in the dividing wall
between the Learning Centre (Area 30) and Electronics Area (Area 40)
Disconnect and remove wiring to panel for electrical located in dividing wall that will be
disturbed during installation of the above windows and doors
Remove frosting on exterior doors
Appendix A- Project Scope Definition: Detailed Design
2-17 | P a g e

2.5.2
Remove double door to interior hall for replacement with a single door (per Appendix CMIDAS Facility Drawing (CAD), Rev A specifications)
Civil, Structural and Architectural
The scope in this area includes:






2.5.3
Supply and install windows and double glass doors in the dividing wall between the Learning
Centre (Area 30) and Electronics Area (Area 40)
Clean carpets
Supply and install 10M of 1M deep work benches with under-cabinet storage. See Appendix
C- MIDAS Facility Drawing (CAD), Rev A
Supply and install 2 shelves for tool storage (3M long X 0.38M deep)
Paint interior of room to colors as selected by MIDAS Project Director
Supply and install rolling workbench (per Appendix C- MIDAS Facility Drawing)
Mechanical and HVAC:
The scope in this area includes:

2.5.4
Refurbish – or, if required, supply and install - HVAC system for room as required to maintain
comfortable work environment
Piping
There is no piping scope of work for this area.
2.5.5
Electrical and Instrumentation
The scope in this area includes:





Supply and install high-speed internet and power connections for 6 computer workstations
for electronics area.
Supply and install 8 GCIF 20 Amp power taps (with 4 outlets each) for electronics area at
workbench height for long workbench along West wall (per Appendix C- MIDAS Facility
Drawing specifications)
Supply 4 GCIF 20 Amp power taps (with 4 outlets each) to shorter rolling workbench along
East wall (per Appendix C- MIDAS Facility Drawing specifications, Area 40)
Supply and install task lighting above all workbenches, so working area receives lumens per
1.5.3
2 x 220 volt single phase required for Laser Cutter (per Appendix C- MIDAS Facility Drawing
specifications)
Appendix A- Project Scope Definition: Detailed Design
2-18 | P a g e




Install owner-supplied user equipment as per Appendix B- MIDAS Equipment List and
Appendix C- MIDAS Facility Drawing).
Install power key system for the area, controlled by Office and Meeting Room Area (20)
Reception Space 101
Install an emergency stop button at each door, with appropriate signage. It will cut power to
all equipment in the room when pushed
Install entrance login security system for Electronics and Printing area to manage member
access as selected by MIDAS Project Director
2.6
Workshops and Materials Storage
2.6.1
Site Preparation (Demolition and Relocation - all Disciplines)
The scope in this area includes:















2.6.2
Disconnect, make safe, and remove wiring to panel for electrical being removed or being
rendered obsolete
Remove, salvage, and store doors for re-use per Appendix C- MIDAS Facility Drawing
(CAD), Rev A. Retain doors to corridors
Remove and dispose of all dividing walls (cinderblock, wood or metal studs) in area,
excluding floor-to-ceiling dividing wall between metal shop and wood shop, excluding walls
surrounding Shopbot room
Remove and dispose of all light fixtures
Remove and dispose of ductwork. Penetrations to the exterior of building to remain with 1M
of ducting attached
Remove and dispose of staircase
Remove and dispose of fans
Remove and store tiles from drop ceiling for replacement of damaged tiles in office space.
Remove and dispose of T-Bar drop ceilings
Create 3M X 3M rough opening in divider wall between metal workshop and woodworking
shop
Remove and dispose of all hangers and conduit not in use
Remove and dispose of obsolete piping
Remove electrical connections and panel from dividing wall between kitchen and
woodworking area. Power from this area is to come from new panel
Remove carpeting in the woodworking area
Remove and salvage windows from Shopbot enclosure
Civil, Structural and Architectural
The scope in this area includes:
Appendix A- Project Scope Definition: Detailed Design
2-19 | P a g e















2.6.3
Infill hole left after door removal between kitchen and the wood working area
Prepare isolated double offset insulated enclosure for Shopbot with double door access
allowing for entrance of large materials. Doors to the Shotbot room are to contain windows
for monitoring machine by users without opening doors. The room is to be designed to
contain noise when the Shopbot is running. This room is to be serviced with dust collection
and sprinklers. The room is also to contain a computer workstation with an internet drop.
Install salvaged windows in ShopBot enclosure Appendix C- MIDAS Facility Drawing
Supply and install shelving suitable for in-use tools in Shopbot enclosure
Drywall ceilings over existing tile
Complete drywall of remaining dividing wall between wood working and metal working
areas
Supply and install three 3M X 3M Vinyl Strip Doors between:

Metal Working Area and Woodworking Area

Molding & Casting Area and Woodworking Area

Materials Storage Area and Metal Working Area
Supply and install walls, ceiling over tool room as indicated on Appendix C- MIDAS Facility
Drawing. Install doors to tool room from both the wood working and metal working shops
Supply and install tool storage shelving in tool room
Review soundness of pillar (see Image 3 in Appendix D- MIDAS Facility Photos and as
indicated on Appendix C- MIDAS Facility Drawing Area 50 with notation to assess
support) in metal working area, and assess replacement options.
Supply and install lock-able project storage cabinets for electronics and 3D printing projects
in Materials Storage Area, minimum 0.35M wide X 3M long X 2M high
Supply and install shelving for materials storage
Supply and install locked “gun” safe for secure material storage
Seal and paint concrete flooring
Paint all interior of all areas to colors as specified by MIDAS Project Director
Mechanical and HVAC:
The scope in this area includes:








Install 1 Cabinet-style Fume Hood (see Appendix D- MIDAS Facility Photos image #2) and one
overhead Fume Hood.
Install owner-supplied wood working, metal working and molding & casting equipment as
per Appendix B- MIDAS Equipment List and Appendix C- MIDAS Facility Drawing.
Supply and install all necessary ducting for Fume Hoods
Assess HVAC system; supply and install all necessary ductwork for HVAC system
Supply and install Exhaust Air/Filtration system for wood working shop
Install owner-supplied dust collection unit in materials storage area
Supply and install dust collection ducting with necessary vent connections in wood working
shop and Shopbot enclosure
Service gas unit heater in Metal Working shop
Appendix A- Project Scope Definition: Detailed Design
2-20 | P a g e

2.6.4
Supply and install rolling workbenches in shops as space permits
Piping
The scope in this area includes:







2.6.5
Salvage or replace sprinkler in Shopbot enclosure
Assess and document sprinkler system impact in this area
Install air compressor system in materials storage area, including water separator system
and appropriate piping
Supply and install air compressor piping to all shop equipment as necessary. Wood working
and metals working areas are to each include compressed air piping connections at each
workstation and piece of fixed piece of equipment. Connections are to be quick-connect
system similar to that standardly used in wood working shops. One connection per
workstation and two 50’ retractable air hoses are required. Two stations in each area are to
be capable to be used simultaneously
Supply and install hot water and cold water piping for sinks, and equipment as necessary
Supply and install sinks in wood working, molding & casting area, and metal working shop
Supply and install an emergency shower in the metal working shop, and eyewash stations in
both wood working and metal working shops
Electrical and Instrumentation
The scope in this area includes:








Install entrance login security system for workshop area to manage member access per
MIDAS Project Director specifications
Supply and install LED lighting for shop and work spaces per 1.5.3.
Supply and install required power for equipment as per Appendix B- MIDAS Equipment List
and Appendix C- MIDAS Facility Drawing, including plan for power expansion.
Supply and install GCIF power outlets for tools. Electrically, the wood working area should
have isolated circuits for all major equipment per Appendix B- MIDAS Equipment List and
Appendix C- MIDAS Facility Drawing (CAD), Rev A to allow un-interrupted use. Work
benches are to have 4 plex GCIF protected 20 AMP plugs located every meter along length
Supply and install retractable GCIF power drops around room for power tools
Supply and install high-speed internet and power connections for 2 computer workstations:
in Materials Storage Area for inventory purposes, and in Shopbot area
Supply and install a power key for the Shop area: required to control power by operations to
minimize potential un-authorized usage outside of supervised hours
Supply and install an emergency stop button at each shop door, with appropriate signage. It
will cut power to all equipment in the room when pushed
Appendix A- Project Scope Definition: Detailed Design
2-21 | P a g e
3.0
MIDAS PROJECT SCHEDULE
A preliminary Project Schedule is attached Appendix E- MIDAS Construction Timeline, Level 1.
This schedule is in development at present and includes the anticipated major milestones related
to the modifications of the facility.
4.0
DETAILED DESIGN CONSULTANT SCOPE OF SERVICES
4.1.1
Engineering/Design Consultant Battery Limits
The engineering consultant is responsible for the design within the following areas as shown on
Appendix C- MIDAS Facility Drawing (CAD), Rev A:
1. Area 00: General Building – Exterior, only assessment and recommendations on exterior
lighting and loading ramp drainage
2. Area 30: Conference and Learning Centre
3. Area 40: Electronics and Printing
4. Area 50: Work Shop and Materials Storage
The engineering consultant is not responsible for any design within the following areas as shown
on Appendix F- MIDAS Facility OVERALL Site Battery Limits, Construction Area:
1. Area 00: General Building – Exterior, excepting assessment and recommendations on
exterior lighting and loading ramp drainage
2. Area 10: General Building – Interior
3. Area 20: Office and Meeting Room Area
Please note the design of wall or roof penetrations, HVAC, fire suppression, internet and
electrical are considered to part of the Scope of Facilities for where the equipment it attaches to
resides.
4.1.2
Included:
The intent of the Engineering/Design Consultant is to adequately describe the construction,
including the issue of any necessary drawings, so that lump sum construction and demolition
contracts can be let and see minimal cost increases. The methodology to be used by the
consultant is to be that of bare bones documents requirements for execution of construction to
limit the costs of engineering.
The Engineering/Design Consultant services for this package will include, but is not limited to,
the following minimum activities:
Appendix A- Project Scope Definition: Detailed Design
4-22 | P a g e
1. Complete a Kick-off Meeting and attend bi-monthly meetings with Owner (MIDAS
Project Director) until completion of detailed design services.
2. Complete meeting minutes for any meetings with owner or other stakeholders.
3. Provide report in a standard template via email to Owner on a weekly basis that
includes scope worked on in the week, a budget update, identification of any critical
issues, and work planned for the coming week.
4. Work with the owner to refine and Issue For Design (IFD) the preliminary
documentation provided for building renovations. Consultant is to provide cost-effective
recommendations to the Owner based on previous experience of requirements for
similar facilities.
5. Create electrical single line and panel schedules for existing building services.
6. Field measure and create overall floor plan of the existing building.
7. Develop and issue proposed MIDAS floor plan for the facility as the first deliverable for
Owner approval, prior to creating any other drawings.
8. Develop Issued for Construction (IFC) drawings for all disciplines, as required, that are
needed for construction or building applications.
9. Contract and manage Hazardous Materials survey if required by code for renovation.
10. Act as the Coordinating Registered Professional and apply for building permit(s) with
Regional District of Kootenay Boundary (RDKB) on behalf of the Owner. Fees associated
with application and permit are the responsibility of the Owner and will be covered by
Owner directly with RDKB.
11. Work with Owner to specify electrical needs to meet regulation requirements,
requirements of equipment listed in Appendix B- MIDAS Equipment List, requirement
for future equipment expansion as per Appendix C- MIDAS Facility Drawing and
desired building end use.
12. Work with Owner to specify fume hoods and ventilation system needs to meet
regulation requirements.
13. Work with Owner to specify HVAC requirements of existing system and required
modifications of system to meet regulation requirements.
14. Work with Owner to assess and document existing fire suppression system enabling
procurement of a fire suppression contractor to meet regulation requirements and
building end use.
15. Provide Scope of Work Documents for each construction contract (see 1.4.2).
16. Provide Issue for Review (IFR) at 60% of Design, Issued for Approval (IFA ) at 90% of
Design, and Issued for Construction (IFC) for floor plans, elevations, electrical single
line(s), electrical layout, panel schedule.
17. Provide Scope of Work documents and specifications for Owner approval at 95% of
Completion and at Issue for Construction.
18. Develop color scheme for MIDAS project in consultation with the owner and provide
samples in color board. Color scheme is to be used throughout.
19. Provide National Master Specifications (NMS) sections to specify materials and
construction requirements.
20. Provide Class B estimate for demolition and construction portion of project. Owner will
provide costs of equipment and other associated Owner’s costs to be included.
Appendix A- Project Scope Definition: Detailed Design
4-23 | P a g e
21. Have contractor(s) complete Condition Assessments of building equipment to be reused, and provide report with required maintenance for determination of path forward
by owner.
22. Review contractor-supplied shop drawings as requested by Owner.
23. Provide construction and tender support as requested by the Owner.
24. Final deliverables are to be PDF and AutoCAD compatible file and, if used, an electronic
copy of the 3D model.
4.1.3
Not Included:
Engineering/Design Consultant services for this package are not to include the following:
1. Drawings or specifications for the layout or modifications to the office area.
4. Drawings or specifications for the layout or modifications to the building exterior except
as where design breaches interior walls or ceiling to outside or visually impacts building
exterior, and excepting assessment and recommendations on exterior lighting and
loading ramp drainage
2. Design and specification of the internet system. Consultant is required to design for
internet connection locations within responsible areas only.
3. Determination and specification of Owner-supplied equipment, except in as the
electrical or HVAC requirements of that equipment will render install prohibitively
expensive or breach regulatory requirements. Issues of this nature are to be discussed
with the Owner for an Owner decision as to the path forward.
4. Procurement, Project Management, Construction Management, Cost Control.
5. Construction Record Drawings.
6. Providing exterior building elevations.
Appendix A- Project Scope Definition: Detailed Design
4-24 | P a g e
Download