March 15, 2015 Mr. Eric Desmarais Energy Facility Siting Analyst Oregon Department of Energy 625 Marion St, NE Salem, Oregon 97301 Dear Mr. Desmarais: I am requesting a Contested Case hearing regarding the proposed order for Summit Ridge Wind Farm, Amendment No. 1 1. Issues Being Contested: EFSC erred in Acceptance of the amendment request over 5 mos. after the deadline for filing it had passed. The request for Amendment No. 1 needed to be submitted by Feb. 18, 2014 according to the EFSC rules. It was not submitted until August 15, 2014. The applicant failed to show good cause for the delay as required by 345-0270030(1). EFSC erred in considering a lack of need for the electricity being generated as this is specifically excluded from EFSC jurisdiction by ORS 469.501. Per OAR 345022-0000 the council cannot waive any applicable state statute. 2. DOE and the EFSC are not allowed to consider whether or not there is a need for the energy which will be generated by the Summit Ridge Wind Farm. The statutes are clear in the exclusion of need as a consideration in eligibility determinations for wind developments. An amended site certificate has the same legal standing as the original site certificate and the amendment to extend the start date of construction constitutes a general reopener. The EFSC cannot rely on arguments that there was no purchaser for the electricity which would be generated to base a decision regarding whether or not there is just cause for the applicant’s untimely request for an extension in the start date for this project. All the information contained in section 1.2 of the application for amendment, paragraphs 1 through 3 and paragraph 6 relate to the fact that the developer had been unable to find a purchaser for the energy they will generate. None of this information has relevance to or can be considered in a determination of “good cause”. Even if it were not excluded from consideration by statute and rule, the circumstance the developer found themselves in is no different than most of the developers who currently have site certificates, but have not initiated construction. The information in section 1.2, paragraphs 4 and 5 relating to the costs associated with the start of construction do not support a determination of good cause because these are not costs that occur until the developer actually decides to start the construction process. They are not costs that occur due to the applicant filing an amendment request and are not costs which would have to occur prior to the filing of the amendment request and thus are not relevant to a good cause determination.. The only costs the developer must assume are the costs of payments to the landowners and the cost of submitting and processing the application for amendment. Other developers who have no purchaser for their electricity assume the costs of filing for an amendment and pay the landowners until such time as they are ready to start construction. They meet the required timelines and process amendment requests with the same issues that this developer has. These are not circumstances which justify a determination of good cause to request an amendment over 5 months after the mandatory date for doing so. Unless the agreements this developer has with their landowners are significantly different than those of other developers, they can cancel their agreements with the landowners with a simple notice. This has been done by other developers. In addition, unless this developer can prove that their payments to landowners are substantially more than other developers, there is nothing unusual about a developer making payments to landowners during extensions of the start dates for construction. It is done all the time. A determination of good cause requires a set of circumstances that are substantially different than the norm and outside the control of the applicant. Nothing in this situation meets the test for a determination of good cause and nothing prevented the applicant from filing their request on time. The EFSC does not have the authority to accept excuses relating to a lack of a purchaser for their product as justification for failing to follow the rules. The statute clearly removes this issue from EFSC consideration. There is nothing in the “just cause” argument given by the applicant that constitutes unusual or extraordinary circumstances outside the control of the applicant. For the above reasons, I am requesting that a contested case be provided due to the fact that the actions taken by the EFSC do not comply with the statute. Need is not an issue EFSC is allowed to consider and even if they were able to consider it, there is nothing unique about a developer not having a purchaser for their electricity that would preclude them from meeting the timeframes required by rule. There is no justification for a determination of good cause when the circumstances are the same as virtually every other developer who is timely in their requests. Sincerely,