Alaska Sustainable Salmon Fund Statement of Work I. Project Title: Matanuska-Susitna Borough Fish Passage Restoration II. Project Number: 44720 III. Principal Investigator Gillian O’Doherty, Habitat Biologist III Alaska Department of Fish and Game (ADF&G), Sport Fish Division (SF)/RTS 333 Raspberry Road Anchorage, AK 99518 Phone (907) 267-2146 Email: gillian.odoherty@alaska.gov PCSRF Objective: HP&R Co-Principal Investigators Jim Jensen, Acting O&M Division Manager Department of Public Works Operations and Maintenance Matanuska-Susitna Borough (MSB) 350 Dahlia Ave. Palmer, AK 99645 Phone: (907) 745-9817 Email: james.jenson@matsugov.us Bill Rice, PE, Habitat Restoration Branch Chief US Fish and Wildlife Service (USFWS) 605 W. 4th Ave., Ste. G-61 Anchorage, AK 99501 Phone: (907) 271-1798 Email: william_rice@fws.gov IV. Project Period: 4/1/13 – 11/30/15 V. Project Description 1. Synopsis This project will address ten fish passage barriers identified and prioritized by ADF&G during a 2009 comprehensive assessment of the Matanuska-Susitna Borough (MSB). The projects include four red-rated barriers that block the most upstream salmon habitat on MSB-owned roads, one failing culvert that is delivering sediment into a salmon spawning stream, and all of the red-rated barriers on Oil Well Road. In total, the project will restore or improve fish passage to 50.057 km of stream habitat, including 28.621 km of catalogued anadromous habitat and 393 ha of lake habitat, for the benefit of Chinook, coho, and sockeye salmon. 2. Introduction MSB Fish Passage Restoration 44720 Page 1 of 8 2/8/2016 Juvenile anadromous fish, such as Chinook, coho, and sockeye salmon, spend up to three years in fresh water during which they must move up and downstream or between watersheds to access favorable habitat. Improperly installed culverts and other fish passage barriers reduce or eliminate access to these preferred habitats, particularly for juvenile, small, and weak swimming fish. The MSB is one the most populous and rapidly growing areas of Alaska; one consequence of such growth has been the rapid construction of local road networks. The salmon and trout produced in MSB streams support commercial, sport, and recreational fishing industries and contribute in excess of several hundred million dollars to the Southcentral Alaska economy. ADF&G identified and assessed over 580 road stream crossing sites for fish passage throughout the MSB between 2009 and 2011 under AKSSF project 45878, Mat-Su Basin Fish Passage Inventory. The resulting data was used to select the sites included in this project. Priority was given to sites that open large amounts of upstream habitat; are on systems that support Chinook salmon or are on tributaries to documented Chinook salmon streams; and that open entire watersheds. Ten crossings were selected for replacement based on these criteria and available funds. In 2012, in an effort to improve fish passage on MSB-owned roads, the MSB Assembly approved $500,000 for stream crossing replacement projects. This project will combine MSB, AKSSF, and other funds to improve fish passage in five priority systems: Goose Creek, Meadow Creek, Montana Creek, Willow Creek, and Moose/Kroto creeks. This project is a partnership between the MSB, USFWS, and ADF&G. The USFWS and ADF&G will review and approve designs; the MSB will oversee construction and contract for the engineering, project management, and construction; and ADF&G will provide post-project monitoring, collect and disseminate information on the projects to the public via the ADF&G Fish Resource Monitor website at http://gis.sf.adfg.state.ak.us/FlexMaps/fishresourcemonitor.html, and conduct public information workshops. Survey and design work will begin in 2013 as well as construction for projects that have designs previously funded by USFWS. Construction on the remaining projects will begin in 2014 and 2015. 3. Locations Site: Cameo Road and Goose Creek (ADFG #20501173) Latitude: 61.42235 N Longitude: 149.91904 W Site: Willow Creek Parkway and Shirley Lake, a tributary to Willow Creek (ADFG #20501238) Latitude: 61.75812 N Longitude: 150.10677 W Site: Montana Creek Road and Buddy Creek, a tributary to Montana Creek (ADFG #20501471) Latitude: 62.13629 N Longitude: 149.9403 W Site: Sawyer’s Shady Road and Buddy Creek, a tributary to Montana Creek (ADFG #20501526) Latitude: 62.14034 N Longitude: 149.9866 W MSB Fish Passage Restoration 44720 Page 2 of 8 2/8/2016 Site: Crystal Lake Road and Long Lake to Rainbow Lake, tributary to Willow Creek. (ADFG #20501182) Latitude: 61.70733 N Longitude: 150.0852 W Site: Oil Well Road and Moose Creek Tributary #1 (ADFG #20501403) Latitude: 62.28352 N Longitude: 150.42371 W Site: Oil Well Road and Moose Creek Tributary #2 (ADFG #20501404) Latitude: 62.23786 N Longitude: 150.43933 W Site: Oil Well Road and Moose Creek Tributary #3 (ADFG #20501473) Latitude: 62.18156 N Longitude: 150.51703 W Site: Oil Well Road and Kroto Creek Tributary (ADFG #20501472) Latitude: 62.10631 N Longitude: 150.52565 W Site: Beaver Lake Road and Meadow Creek (ADFG #20501435) Latitude: 61.56269 N Longitude: 149.82533 W 4. AKSSF Objective 1B-2 VI. Objectives 1. Project Objectives Restore unimpeded fish passage to 50.057 km of stream habitat, including 28.621 km of catalogued anadromous habitat and 393 ha of lake habitat, by replacing ten documented fish passage barriers with stream simulation crossings 2. Methods At each of the selected sites, detailed engineering drawings and a contractor work plan will be developed and reviewed by the MSB, USFWS, and ADF&G. Upon approval of the engineering design, all permit applications necessary for project implementation will be submitted for review and approval by the MSB. Concurrently, a request for project bids and quotations will be developed from which a contractor will be hired by the MSB. The contractor will remove the existing culvert, install the stream simulation design developed to achieve the identified objective, and complete stream bank stabilization work, if needed. ADF&G and USFWS will carry out site visits during construction and post-project monitoring to ensure compliance to the original design plan and document fish utilization of the new culvert. All culvert designs will be stream simulation, a method of constructing crossings that mimics natural channel dimensions and processes through the culverted reach in order to maintain similar passage conditions to those in the adjacent channel. These crossings are also more stable and less prone to bank scour, channel incision, or sediment accretion at a rate greater than the rest of the channel. Additionally, stream simulation culverts are widely accepted both in Alaska and elsewhere as the preferred method in constructing small road stream culvert crossings for aquatic organism passage. A variety of guidelines for stream simulation type crossings have been produced in recent years; this project will largely follow the guidelines within the U.S. Forest Service stream simulation publication “An ecological approach to providing passage for aquatic organisms at road-stream crossings” (2008). This approach is based on selecting an appropriate reference reach and basing the design on specific measurements taken there. MSB Fish Passage Restoration 44720 Page 3 of 8 2/8/2016 To the extent practical, the final designs will conform to the following guidelines: Size: The diameter of the culvert will be at least 20% greater than the stream’s natural ordinary high water (OHW) width. For narrow channels with wide floodplains, additional overflow culverts are considered. Gradient: The culvert gradient will be within 1% of the natural stream gradient. Embeddedness: Culverts will be embedded no less than 20% below the naturally projected bed scour depth and no more than 40% of the diameter of the pipe. Substrate: Culverts will be back-filled with the same size and size fraction of sediment as the naturally occurring stream sediment but be dynamically stable up to the 50-year flood event. Low Flow Channel: Care should be given to mimic stream conditions during low flow conditions such that the low flow channel within the culvert has similar depth and velocity to the natural stream. Often this requires utilizing substrate to mimic the stream bank lines within the culverts. Capacity: The culverts will pass a 100-year storm flow at less than 100% of the culvert’s height. This allows for passage of other watershed products (large wood, debris, and substrate) during extremely high flows. Channel: Stable stream banks upstream and downstream of the crossing will be maintained or constructed to prevent scour and sedimentation. This project will seek designs that are predicted not to fail when subjected to natural perturbations, primarily floods. Therefore success will also be measured by the ability of the structure to transport and replace sediment during a 100-year flood event. Embedded culverts will have a minimum of 20% of the barrel diameter placed below the natural stream gradient and be dynamically stable up to the 50-year flood event to allow sediment to be mobilized and replaced during 100-year flood events. This ensures that if the in-pipe substrate is flushed out, it will be replaced with upstream sediment flushed in. After construction, ADF&G will survey the sites using its standard criteria for assessing juvenile passage at stream crossings. The criteria for a stream simulation type crossing are based on the hydrologic characteristics of the stream through the road prism being consistent with the natural stream conditions in adjacent reaches. ADF&G bases the classification primarily on the following three criteria used to rank the crossings for passage: (1) Slope: Channel slope through the crossing should be +/- 1% of natural stream gradient (2) Perch: No perch (or fall at culvert outlet) (3) Constriction: At ordinary high water there should be no constriction of the stream channel by the crossing ADF&G will post all post-construction monitoring data on the Fish Resource Monitor website along with information on the design and construction of the replacement project to aid other practitioners. This includes design drawings and other project specific information. MSB Fish Passage Restoration 44720 Page 4 of 8 2/8/2016 VII. Benefits This project will enhance salmonid habitat in the MSB by restoring free and clear movement of juvenile salmonids at ten road crossings. Restoring unimpeded fish passage will increase the availability of productive upstream habitats (including wetlands) to rearing juveniles. In addition, sizing the culverts to pass debris and sediment as well as water during 100-year flood events will greatly reduce the likelihood of catastrophic road failures introducing large volumes of sediment into streams. VIII. Products, Milestones, and Timelines May 2013 – December 2013: Carry out survey work on first subset of culverts; select project engineering consultant; prepare engineering plans, drawings, and contractor bid package April 2013 – March 2014: Initiate permit reviews and coordinate project review (right of way, permitting, maintenance, and engineering) May – December 2014: Begin construction of first set of culverts and carry out survey and design work on remaining culverts August 1 – September 30, 2014: Carry out post construction surveys on 2014 projects April 2013 – March 2015: Conduct project permit reviews and coordinate project review for second year of construction May – September 2015: Complete construction August 1 – September 30, 2015: Carry out post construction surveys on 2015 projects October 1, 2015 – November 2015: Complete post construction monitoring, update the Fish Resource Monitor website, and post information on design and construction on the ADF&G website December 2015: Provide final report to AKSSF IX. Budget Summary 100 Personnel 200 Travel 300 Contractual 400 Supplies 500 Equipment Subtotal 600 Indirect Total Total $13,200 $2,340 $1,080,000 $0 $0 $1,095,540 $2,176 $1,097,716 This project funds the following entities: ADF&G: $17,716 MSB: $1,080,000 ADF&G Budget ADF&G MSB Fish Passage Restoration 44720 Total Page 5 of 8 2/8/2016 100 Personnel 200 Travel 300 Contractual 400 Supplies 500 Equipment Subtotal 600 Indirect @ 14% Total $13,200 $2,340 $0 $0 $0 $15,540 $2,176 $17,716 ADF&G Budget Narrative: Line 100: Personnel ($13,200) Mark Eisenman, SF Habitat Biologist I, will conduct post project monitoring and update the ADF&G website: 2 months @ $6,600 = $13,200 Line 200: Travel ($2,340) Project oversight: $500 lodging (4 nights @ $125/night) + $480 per diem (8 days @ $60/day) = $980 Post project monitoring: $500 lodging (2 nights @ $125/night x 2 people) + $360 per diem (3 days @ $60/day x 2 people) = $860 Transportation to sites (fuel): $500 Line 600: indirect ($2,176) ADF&G’s federally negotiated indirect rate through June 30, 2013 is 14.41% excluding equipment and pass-through funds; however, indirect will be recovered at a reduced rate of 14% for this project. MSB Budget MSB 100 Personnel 200 Travel 300 Contractual 400 Supplies 500 Equipment Total Total $0 $0 $1,080,000 $0 $0 $1,080,000 7/9/14: Informal revision to MSB budget MSB will shift approximately $10,000 from Line 300 Contractual to Line 200 Travel to pay the per diem costs of a (separately funded) Borough employee to travel to and from the project construction site for the performance of onsite inspections. MSB Budget Narrative: Line 300: Contractual ($1,080,000) MSB Fish Passage Restoration 44720 Page 6 of 8 2/8/2016 Survey, design, and engineering: ADFG # Culvert 20501403 Moose Creek Tributary Red 1 20501404 Moose Creek Tributary Red 2 20501473 Moose Creek Tributary Red 3 Total Road Oil Well Road Oil Well Road Oil Well Road Design and engineering $40,000 $40,000 $40,000 $120,000 Construction: ADFG # Culvert 20501173 Goose Creek 20501182 Rainbow Lake to Long Lake 20501471 Buddy Creek 20501526 20501435 20501403 20501404 20501473 20501472 Total IX. Buddy Creek Meadow Creek Moose Creek Tributary Red 1 Moose Creek Tributary Red 2 Moose Creek Tributary Red 3 Kroto Creek Tributary Road Cameo Road Crystal Lake Road Katahdin Street Sawyer's Shady Street Beaver Lake Rd Oil Well Road Oil Well Road Oil Well Road Oil Well Road Construction $20,000 $100,000 $50,000 $200,000 $150,000 $80,000 $140,000 $140,000 $80,000 $960,000 Match Budget MSB Match (35%) 100 Personnel 200 Travel 300 Contractual 400 Supplies 500 Equipment Total Total $0 $0 $384,201 $0 $0 $384,201 MSB Match Budget Narrative: Line 300: Contractual ($384,201) Survey, design and engineering: ADFG # 20501238 Culvert Road Willow Creek Parkway Shirley Lake Outlet MSB Fish Passage Restoration 44720 Page 7 of 8 Design & engineering $50,000 2/8/2016 20501182 20501526 20501472 Total Rainbow Lake to Long Lake Buddy Creek Kroto Creek Tributary Construction: ADFG # Culvert 20501173 Goose Creek 20501238 Total Road Cameo Road Willow Creek Parkway Shirley Lake Outlet MSB Fish Passage Restoration 44720 Crystal Lake Road Sawyer's Shady Street Oil Well Road Page 8 of 8 $50,000 $40,000 $24,201 $ 164,201 Construction $30,000 $190,000 $220,000 2/8/2016