Appendix E Completed Mitigation Projects

advertisement
Appendix E
Completed Mitigation Projects
Completed Mitigation Projects
Alachua County
Fire Rescue Headquarters and Stations
Project Description
A wind retrofit project to reenforce window and door
openings at the Fire Rescue
Headquarters building and 3 fire
stations. Project enhances
protection of public safety
equipment in these buildings.
Fire stations and Headquarters
are listed critical facilities.
Project Costs
Total Costs:
$ 48,525
Federal Share: $ 36,772
Local Share: $ 11,753
Funding Source: HMGP
Project Timeline
Completed July 2008.
Alachua County
Sheriff Admin Building and CCC/EOC Building
Project Description
A wind retrofit project to add
shutters to window and door
openings at the ASO
Administration building and
upgrade the existing system on
the CCC/EOC building. Project
enhances protection of public
safety equipment in these
buildings. ASO Admin building
and the CC/EOC are listed critical
facility.
Project Costs
Total Costs: $ 125,640
Federal Share: $ 94,230
County Share: $ 31,410
Funding Source: PDM Grant
Project Timeline
Completed September 2011.
City of Alachua
Project Description
Lincoln Gardens Drainage
Project. Enhancement of storm
water management system to
address flooding and erosion.
Installation of roadway curb and
guttering, additional storm water
inlets, and right-of-way
stabilization [grading and
installation of sod].
Project Costs
Total Costs:
$ 351,070
Federal Share: $ 263,300
City Share:
$ 87,770
Project Timeline
Phase 1 Planning and Design:
October 2006 – July 2008
Phase 2 Construction:
August 2009 – April 2010
Funding Source: HMGP
Project Description
Mulberry Landing Drainage
Improvements. Installation of
drainage pipe and inlet
structures to address historic
flooding.
Project Costs
Total Costs:
$ 51,850
Federal Share: $ 38,888
Local Share: $ 12,962
Project Timeline
Phase 1 Planning and Design:
October 2006 – August 2008
Phase 2 Construction:
August 2009 – April 2010
Funding Source: HMGP
Project Description
Wastewater Treatment Plant
Access Road Drainage
Improvements. Installation of
drainage pipe and regarding of
roadside swales to enhance
water conveyance. The City of
Alachua Wastewater Treatment
Plan is a listed critical facility.
Project Costs
Total Costs:
$ 48,852
Federal Share: $ 36,718
Local Share: $ 12,134
Project Timeline
Phase 1 Planning and Design:
April 2007 – November 2008
Phase 2 – Construction:
August 2009 – May 2010
Funding Source: HMGP
City of Archer
Project Description
Storm water Management
System Enhancement.
Expansion of an existing storm
water retention basin.
Project Costs
Total Costs: $ 54,713
Funding Source: CDBG
Project Timeline
Project completed August 2011
Download