Attachment-D.-

advertisement
Attachment D. Environmental Mitigation and Monitoring Plan (EMMP) for DOWA Demonstration Farm
Subproject/Grant
Activity
1. Finalizing facilities
layout
2. Staking perimeter
of each component
1. Level land
(approximately
30000 square
meter)
2. Install drip
irrigation system –
laying buried pipes,
installing heads
Potential Environmental
Impact
Planning and Design
None
NA
None
Mitigation Measure
NA
Construction and Handover
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful grading of the
construction site such that water is not allowed to
run off the site into adjacent drainages, agricultural
fields or inhabited areas. Where excavated soils are
stored onsite, adequate measures will be
implemented to control runoff, including covering
exposed soils, construction of settling basins, or
erection of erosion control barriers surrounding
stored soil.
Worker safety
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots and hard hats).
Soil erosion
Soil erosion
Monitoring
Indicator
Frequency of
Monitoring
Responsible
Party
Cost
NA
NA
NA
NA
NA
NA
NA
NA
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
Weekly
RADP-S
I. Visual
Inspection of
workers/work
site
Weekly
RADP-S
Weekly
RADP-S
Mitigation Measure 2: Develop & implement a
worker site safety plan; PPE; enforce and monitor
the site safety plan.
2. Review of
safety plan
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of the
Construction site such that water is not allowed to
run off the site into adjacent drainages, agricultural
fields or inhabited areas. Where excavated soils are
stored onsite, adequate measures will be
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
Subproject/Grant
Activity
Potential Environmental
Impact
Worker safety
Mitigation Measure
implemented to control runoff, including covering
exposed soils, construction of settling basins, or
erection of erosion control barriers surrounding
stored soil.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan, train workers in the use of
PPE; enforce and monitor the site safety plan.
3. Installation of
two PVC water tank
with concrete floor
and foundation
Soil erosion
Construction solid waste
disposal
Noise
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
Monitoring
Indicator
I. Visual
Inspection of
workers/work
site
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
1. Visual
inspection of
work site
2. Review of
waste removal/
transport logs
1. Complaints
from residents
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Worker safety
Mitigation Measure
 In populated areas, avoid work early in the
morning, in the evening and overnight
 Engineering noise control – reduce noise from
machines and equipment; relocate noisy
equipment by isolating them within
enclosures, erecting sound barriers, reducing
kinetic or potential energy and regularly
maintaining machines and equipment;
 Use quiet running machinery and equipment
when available in the market, such as
generators and compressors. Provide hearing
protectors for workers who are exposed to
excessive noise and ensure that they are worn
at all times. Install warning signs in areas with
excessive noise to remind workers that hearing
protectors must be worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
personal protection equipment; enforce and
monitor the site safety plan.
4. Erect
greenhouses (4) –
land leveling,
erecting Steel
structure, installing
plastic sheeting
outer shell
Construction solid waste
disposal
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Monitoring
Indicator
and
management
Frequency of
Monitoring
Responsible
Party
2. Visual (aural)
inspection of
equipment at
work site
I. Visual
Inspection of
workers/work
site
Weekly
RADP-S
Weekly
RADP-S
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
work site
2. Review of
waste removal/
transport logs
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Noise
Worker safety
5. Construction of
approximately 782
m gravel paths
inside the farm
Soil erosion
Mitigation Measure
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
 Use quiet running machinery and equipment
when available in the market, including
generators and compressors. Provide hearing
protectors for workers who are exposed to
excessive noise and ensure that they are worn
at all times. Install warning signs in areas with
excessive noise to remind workers that hearing
protectors must be worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Monitoring
Indicator
1. Complaints
from facility
residents and
management
Frequency of
Monitoring
Weekly
Responsible
Party
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Visual (aural)
inspection of
equipment at
work site
I. Visual
Inspection of
workers/work
site
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
2. Review of
safety plan
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Construction solid waste
disposal
Noise
Worker safety
Mitigation Measure
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
Use quiet running machinery and equipment when
available in the market, including generators and
compressors. Provide hearing protectors for
workers who are exposed to excessive noise and
ensure that they are worn at all times. Install
warning signs in areas with excessive noise to
remind workers that hearing protectors must be
worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Monitoring
Indicator
for signs of soil
erosion off site
1. Visual
inspection of
work site
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
waste removal/
transport logs
1. Complaints
from residents
area and
management
2. Visual (aural)
inspection of
equipment at
work site
I. Visual
Inspection of
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Mitigation Measure
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
6. Installation of
approximately 1160
m ,90 cm underground irrigation
pipe for pumping
canal water to
purposed farm with
a pump house and
pump
Soil erosion
Construction solid waste
disposal
Noise
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
Monitoring
Indicator
workers/work
site
Frequency of
Monitoring
Responsible
Party
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
1. Visual
inspection of
work site
Weekly
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
waste removal/
transport logs
1. Complaints
from residents
area and
management
2. Visual (aural)
inspection of
equipment at
work site
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Worker safety
Mitigation Measure
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
Use quiet running machinery and equipment when
available in the market, including generators and
compressors. Provide hearing protectors for
workers who are exposed to excessive noise and
ensure that they are worn at all times. Install
warning signs in areas with excessive noise to
remind workers that hearing protectors must be
worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
7. Development of
two 80 m borehole
water wells,
diameter of well
shall be 12 inches
and 6 inches casing
pipe shell be
installed.
Soil erosion
Construction solid waste
disposal
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
Monitoring
Indicator
I. Visual
Inspection of
workers/work
site
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
1. Visual
inspection of
work site
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Noise
Worker safety
Mitigation Measure
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
Use quiet running machinery and equipment when
available in the market, including generators and
compressors. Provide hearing protectors for
workers who are exposed to excessive noise and
ensure that they are worn at all times. Install
warning signs in areas with excessive noise to
remind workers that hearing protectors must be
worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
Monitoring
Indicator
2. Review of
waste removal/
transport logs
1. Complaints
from residents
area and
management
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Weekly
RADP-S
2. Visual (aural)
inspection of
equipment at
work site
I. Visual
Inspection of
workers/work
site
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
Cost
Subproject/Grant
Activity
8. Installation of
Training, Office,
bathrooms and
storage facilities at
the farm from 40
feet containers. All
facilities will be
install on 10cm
poured concrete.
Potential Environmental
Impact
Soil erosion
Construction solid waste
disposal
Noise
Mitigation Measure
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
Use quiet running machinery and equipment when
available in the market, including generators and
compressors. Provide hearing protectors for
workers who are exposed to excessive noise and
ensure that they are worn at all times. Install
warning signs in areas with excessive noise to
Monitoring
Indicator
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
Frequency of
Monitoring
Weekly
Responsible
Party
RADP-S
1. Visual
inspection of
work site
Weekly
RADP-S
Weekly
RADP-S
2. Review of
waste removal/
transport logs
1. Complaints
from residents
area and
management
2. Visual (aural)
inspection of
equipment at
work site
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Worker safety
Mitigation Measure
remind workers that hearing protectors must be
worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
9. Installation of
solar powered
electrical system for
the well and farm
facilities such as
pumps, fans,
exhaust, lights,
switches, coolers,
wiring and all other
necessary electrical
works
Worker safety
10. Construction of
Livestock facility for
two cows with an
outside concrete
floor, shed,
graveling, fencing,
and electrical,
plumbing and other
necessary work.
Soil erosion
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Monitoring
Indicator
I. Visual
Inspection of
workers/work
site
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
I. Visual
Inspection of
workers/work
site
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Construction solid waste
disposal
Noise
Worker safety
Mitigation Measure
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
Use quiet running machinery and equipment when
available in the market, including generators and
compressors. Provide hearing protectors for
workers who are exposed to excessive noise and
ensure that they are worn at all times. Install
warning signs in areas with excessive noise to
remind workers that hearing protectors must be
worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
Monitoring
Indicator
1. Visual
inspection of
work site
Frequency of
Monitoring
Weekly
Responsible
Party
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
waste removal/
transport logs
1. Complaints
from residents
area and
management
2. Visual (aural)
inspection of
equipment at
work site
I. Visual
Inspection of
workers/work
site
2. Review of
safety plan
Cost
Subproject/Grant
Activity
11.Installation of
model pack house
and storage area –
land, pouring
concrete pad and
installation of
electricity and
plumbing
Potential Environmental
Impact
Soil erosion
Construction solid waste
disposal
Noise
Mitigation Measure
Mitigation Measure 1: Impacts due to soil erosion
will be mitigated by careful Grading of Construction
site such that water is not allowed to run off the
site into adjacent drainages, agricultural fields or
inhabited areas. Where excavated soils are stored
onsite, adequate measures will be implemented to
control runoff, including covering exposed soils,
construction of settling basins, or erection of
erosion control barriers surrounding stored soil.
Mitigation Measure 1: Solid waste shall be stored
in a secure and sanitary on site facility, and shall be
transported off site and disposed of in an approval
solid waste disposal facility. To the extent possible,
organic waste shall be composted or otherwise
used in a productive manner (e.g. livestock fodder)
and all inorganic waste with a market value shall be
recycled.
Mitigation Measure 1: Ensure that all processes,
machines and equipment used will implement one
or more of the following measures:
 In populated areas, we will avoid work early in
the morning, in the evening and overnight
 Engineering noise control, e.g., modifying
noisy processes, machines and equipment,
relocating noisy processes or isolating them
within enclosures, erecting sound barriers,
reducing kinetic or potential energy and
regularly maintaining machines and
equipment;
Use quiet running machinery and equipment when
available in the market, including generators and
compressors. Provide hearing protectors for
Monitoring
Indicator
3. Visual
inspection of
worker safety
training
1. Visual
inspection of
site and
adjacent areas
for signs of soil
erosion off site
1. Visual
inspection of
work site
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Weekly
RADP-S
Weekly
RADP-S
2. Review of
waste removal/
transport logs
1. Complaints
from residents
area and
management
2. Visual (aural)
inspection of
equipment at
work site
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Worker safety
Mitigation Measure
workers who are exposed to excessive noise and
ensure that they are worn at all times. Install
warning signs in areas with excessive noise to
remind workers that hearing protectors must be
worn.
Mitigation Measure 1: Insure that all workers are
provided with appropriate PPE (e.g. gloves,
goggles, boots, and hard hats).
Mitigation Measure 2: Develop and implement a
worker site safety plan; train workers in the use of
PPE; enforce and monitor the site safety plan.
Monitoring
Indicator
I. Visual
Inspection of
workers/work
site
Frequency of
Monitoring
Responsible
Party
Weekly
RADP-S
Quarterly
RADP-S
Quarterly
RADP-S
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
1. Irrigating crops
Groundwater
withdrawal
2. Applying fertilizer
and pesticides to
crops
Groundwater
contamination
Operation
Mitigation Measure 1: To the extent possible
obtain data regarding pre-intervention (e.g.
baseline) groundwater quantities and withdrawal
rates to determine a sustainable withdrawal rate
for irrigation system operation.
Mitigation Measure 1: Apply fertilizers in the
amounts specified for the particular crops. Do not
overuse fertilizers.
Mitigation Measure 2: Apply pesticides to specific
crops (timing and quality) as specified in the
USAID/Afghanistan PERSUAP
1. Liters of
water
withdrawn from
groundwater
well
1. Quantity of
fertilizer used
(for each
different
fertilizer type)
2. Quantity of
pesticide used
(for each
different
pesticide type)
Cost
Subproject/Grant
Activity
Potential Environmental
Impact
Worker safety
Mitigation Measure
Mitigation Measure 1: Assure that workers
applying pesticides are trained in the proper/safe
application of those specific pesticides and use the
appropriate personal safety equipment as specified
in the USAID/Afghanistan PERSUAP.
Monitoring
Indicator
3. Visual
inspection of
pesticide
application logs
to determine
timing of
application
I. Visual
Inspection of
workers/work
site
Frequency of
Monitoring
Responsible
Party
Quarterly
RADP-S
Monthly
RADP-S
2. Review of
safety plan
3.animal Manure
Management
Groundwater
Contamination
Mitigation Measure 1: Store animal Manure in
Manure area on time, Apply manure in the
amounts specified for the particular crops and soil.
Do not overuse manure.
3. Visual
inspection of
worker safety
training
1.Quantity of
Manure used
for crops and
soil
2. Visual
inspection of
Manure storage
and application
Worker safety
Mitigation Measure 1: Assure that workers store
and applying manure are trained in the proper,
store/safe application of manure use the
appropriate personal safety equipment.
. Visual
Inspection of
workers/work
site
Cost
Subproject/Grant
Activity
4. Weeding fields
None anticipated
Potential Environmental
Impact
None
NA
Decommissioning
Mitigation Measure
Monitoring
Indicator
2. Review of
safety plan
3. Visual
inspection of
worker safety
training
NA
Frequency of
Monitoring
NA
Responsible
Party
NA
Cost
NA
Download