PROJECT STATEMENT OF WORK Boeing BCA Everett Plant Powder Mill Gulch Downgradient Plume Interim Action, Phase 1 Boeing Environment, Health and Safety (EHS) Remediation Group Seattle, WA CONTENTS I. II. III. IV. V. Project Background General Project Requirements General Tasks, Requirements, and Submittals Scope of Work Technical Specifications Attachment 1 – Project Plans Statement of Work i PMG Phase 1 Interim Action PROJECT CONTACTS Boeing (Owner) Boeing Project Manager: Nick Garson 425-269-7866 nick.garson@boeing.com Boeing Everett Plant Contact: Alan Sugino 425-717-6117 alan.k.sugino@boeing.com Boeing Field Manager Dan McCormack 206-290-6558 daniel.c.mccormack@boeing.com Contract Management/ Procurement Agent: Meredith Plumb 425-237-4865 Meredith.G.Plumb@boeing.com Landau Associates (Owner’s Representative) Engineer (Landau Associates): Piper Roelen, P.E. 425-778-0907 425-503-6784 mobile proelen@landauinc.com Biologist (Landau Associates): Steven Quarterman Environmental Project Manager (Landau Associates): Jerry Ninteman, P.E. 425-778-0907 squarterman@landauinc.com 425-778-0907 206-850-4503 mobile jninteman@landauinc.com Statement of Work I-1 PMG Phase 1 Interim Action I. PROJECT BACKGROUND The Boeing Commercial Airplanes (BCA) plant in Everett, Washington is used for the manufacture of 747, 767, 777, and 787 aircraft. Primary construction began in 1968 and was completed in 1969. Additional building and facilities have been constructed since then. The head of Powder Mill Gulch (PMG) is located on the northern end of the Everett Plant property. Tricholoroethylene (TCE) was first detected in PMG groundwater in March 2003 with the installation and sampling of monitoring well EGW075. A phased remedial investigation has been conducted to characterize the nature and extent of the groundwater plume and discharge of contaminated groundwater to surface water in Powder Mill Creek. Based on initial site characterization activities, the TCE source area was identified as an approximately 14,000 square foot (ft2) area centered below the deepest portion of a detention basin at the head of PMG. TCE concentrations in the source area were historically measured as high as 31,000 micrograms per liter (μg/L). An interim action (IA) was completed in 2008 within the source area using in situ electrical resistance heating (ERH) to reduce TCE concentrations in the source area. The objective of the source area IA was to reduce concentrations of TCE in groundwater to below an established remediation level of 500 μg/L. The objective was achieved through most, but not all of the source area through the ERH application. More recent application of contingent and focused bioremediation appears to have successfully achieved the IA objective throughout the source area. The TCE groundwater plume in PMG extends north-northeast from the stormwater detention basin. A portion of the plume discharges to Powder Mill Creek approximately 500 ft north of the detention basin where Powder Mill Creek becomes a perennial gaining stream. The plume continues northward beneath Seaway Boulevard (which bounds the northern edge of Boeing property); onto City of Everett Lot 9, Intermec, and CRISTA Ministries properties; and, ultimately, discharges to Powder Mill Creek at the toe of the plume, beginning approximately 1,000 ft north-northeast of Seaway Boulevard. The plume, defined by TCE concentrations in groundwater greater than the project screening level of 0.49 μg/L, is approximately 2,850 ft in length. TCE has been measured in groundwater at concentrations as high as 2,000 μg/L at wells near Seaway Boulevard, and 1,900 μg/L north of Seaway Boulevard. The plume is present primarily in the upper portion of the Esperance Sand Aquifer, at depths of 4 to 75 ft below ground surface (BGS). A 4-ft-thick silt layer within the Esperance Sand Aquifer is relatively continuous over the length of the plume and serves as a barrier to deeper vertical migration of TCE in the source zone and over most of the downgradient dissolved-phase plume. A relatively impermeable Lawton Clay unit is present approximately 30 ft below the silt. Sampling in Powder Mill Creek and from seeps on the banks and hillsides above the creek have identified concentrations of TCE in Powder Mill Creek up to 38 µg/L (south of Seaway Boulevard) and in seeps up to 530 µg/L (near the toe of the plume). Statement of Work I-2 PMG Phase 1 Interim Action Boeing has agreed to perform a downgradient plume IA to address various elements of contamination in groundwater and surface water. This IA is being performed under the authority and conditions of Amendment No. 5 to Agreed Order No. DE96HS-N274 (Order; Exhibit A1 in Attachment 1 – Project Plans) between The Boeing Company and the Washington State Department of Ecology (Ecology). The downgradient plume IA will include two phases of work: the first on Boeing property, referred to as the “PMG Downgradient Plume Phase 1 IA” (Phase 1 IA); and the second off Boeing property referred to as the “PMG Downgradient Plume Phase 2 IA” (Phase 2 IA). This SOW pertains solely to the Phase 1 IA being conducted on Boeing property. This Phase 1 IA is being conducted to prevent further migration of TCE off of Boeing property and reduce discharge of TCE into Powder Mill Creek through construction and operation of a groundwater extraction and treatment (GET) system. The GET system involves pumping groundwater from extraction wells to create a capture zone to control the migration of TCE-contaminated groundwater, treating the groundwater through air stripping of aqueous-phase volatile organic compounds (VOCs), and discharging treated groundwater to the city of Everett (City) sanitary sewer system. Vapor-phase TCE discharged from the air stripper will be treated through granular activated carbon (GAC). Statement of Work II - 1 PMG Phase 1 Interim Action II. GENERAL PROJECT REQUIREMENTS Upon award of this work, the Contractor shall enter into a binding agreement (Contract) with Boeing (Owner) which shall specify the terms and conditions upon which performance of the Work, specified herein, shall be performed. This section provides general project requirements that shall be observed by the Contractor during performance of work for the duration of the Contract. AGREED ORDER Upon award of this contract, a copy of the Order and Amendment No. 5 will be provided to the Contractor. Contractor is required to provide copies of the Agreed Order to subcontractors, and to provide documentation of this to Owner. CONDUCT OF WORK Coordination Before starting Work, Contractor shall identify to Owner and Engineer an authorized representative who shall have complete authority to represent and to act for Contractor. The authorized representative shall be present at the work site at all times while work is actually in progress or shall have designated an alternate when not present. The authorized representative shall not be removed from the project without notification to Owner and Engineer. Coordination with facility staff, site tenants, property owner representatives, and other onsite contractors shall be made by Contractor through Owner’s onsite representative to assist Contractor with performance of the work with a minimum of interference and inconvenience. Work Hours Standard work hours are 6:30 a.m. to 5:00 p.m., Monday through Friday. Contractor may propose alternative work schedules; however, the proposed work schedule may not be approved if Owner’s representative is not available to be onsite during the proposed work hours. Regulatory Requirements Contractor is responsible for determining requirements and complying with local, state, and federal laws, regulations, and permits that govern the Work. The Contractor shall be aware of applicable or relevant and appropriate requirements for the Work, shall determine the relevance of the regulations to executing the Work in this Contract, and shall comply with all applicable requirements of the regulations in performing the Work. Statement of Work II - 2 PMG Phase 1 Interim Action Sustainable Remediation Practices The Boeing Company is committed to identifying cleanup project opportunities to use natural resources and energy efficiently, reduce negative impacts to the environment, minimize or eliminate pollution at its source, reduce waste to the greatest extent possible and stay abreast of policy, technology and industry standards associated with sustainable practices. This concept of sustainable remediation (SR) can be defined as a remedy or combination of remedies whose net benefit on human health and the environment is maximized through the judicious use of limited resources. SR incorporates sustainable environmental practices into remediation of contaminated sites to increase the environmental, economic and social benefits of a cleanup. This commitment includes using the contracting process to select suppliers who share Boeing’s commitment to SR principles so that remediation work can be performed in a way that reduces adverse impacts to the environment. The following summarizes SR principles that the Contractor shall consider and incorporate as reasonably feasible and applicable during performance of the SOW described herein. Where appropriate, these principals are incorporated into the design plans and technical specifications. Summary of SR Principles and Objectives Contractor will consider the “triple bottom line” for performance of this SOW, including incorporation of efficient, low-impact work practices, procedures, and operations; and use of sustainable materials and products. It is the goal of Boeing’s sustainable remediation program to implement the following objectives in each project to the greatest extent possible: Environmental - Consider environmental effects of remedy implementation and incorporate options to minimize the environmental footprints of a cleanup and conserve natural resources. Economic - Integrate sustainable practices throughout a remediation project’s life cycle, evaluate return on investment. Social - Partner with Boeing business units, regulatory agencies, the public and other stakeholders to identify environmental, land use, health and safety aspects, and economic goals in all phases of remediation projects to develop sustainable remedial alternatives and select final remedies. Core Elements Sustainable practices emphasize the need to more closely evaluate core elements of a cleanup project; compare the site-specific value of conservation benefits gained by different SR strategies; and weigh the environmental trade-offs of potential strategies. Sustainable Remediation addresses five core elements: Energy – Promote efficiency and renewable sources. Statement of Work II - 3 PMG Phase 1 Interim Action Air – Reduce air emissions. Water – Reduce, reuse and protect. Land and Ecosystems – Minimize harm, protect and foster return to ecological, economic, social or other uses. Materials and Waste – Reduce, reuse, recycle; use environmentally responsible products. GENERAL ACCESS REQUIREMENTS The project site area is within Boeing property but outside the security fence of the main facility, and Boeing-provided badges are required for access. The project site area is periodically patrolled by Boeing’s security details and security personnel may query personnel working at the site and ask for identification issued by Boeing. The site is fenced with a locked gate at Seaway Boulevard. Contractor shall provide a padlock to be daisy-chained with Boeing locks. Contractor shall ensure that the gate is locked at the end of each work day. Irregular or Non-Routine Access Access on an irregular basis and during other than established working hours will require prior approval by Owner. Maintenance of Access Contractor shall not obstruct or interfere with access by others to existing facilities adjacent to the project site during the work under this Contract. Vehicle Parking/Idling Contractor’s vehicles shall only park in approved areas. Idling of vehicles and heavy equipment will be limited to 10 minutes or less, excluding daily initial equipment startup/warm up. COORDINATION AND COOPERATION WITH OTHER CONTRACTORS Work by others may be performed in the vicinity of or adjacent to the project site in concurrence with the scheduled performance of the Work under this SOW. Contractor shall coordinate construction work with those other contractors to minimize conflicts and to maintain a cooperative effort in completion of the Work. CONSTRUCTION SCHEDULE REQUIREMENTS Work Flow The work shall be planned, scheduled, and performed to complete the Work within the requirements of this SOW. Contractor shall prepare and maintain a construction Statement of Work II - 4 PMG Phase 1 Interim Action schedule. System startup and full scale operation (i.e., after completion of system testing) shall be on or before August 1, 2012. Work shall be substantially completed by October 30, 2012. Owner may choose to extend this deadline due to circumstances such as weather or extended Ecology or City review periods. Schedule Constraints The following special constraints have been identified as having an impact on the performance of the work. It is not intended to be a comprehensive list of constraints that will result from the execution of the work, but as an aid to Contractor in development of schedules and in executing the work. Additional constraints may exist or develop as a result of required work execution or Contractor’s proposed work methods or sequence. In any event, Contractor is responsible for compliance with the requirements of the various specification sections and the work procedures and protection requirements contained therein, and establishing all constraints associated with the work execution and incorporating them into work schedules and proposed construction activities. Weather events may prevent the Contractor from performing work on certain days because of water entering trench or difficulty controlling surface water flows, or erosion to wetlands or surface water bodies. At the end of work, Contractor’s tools and equipment must remain onsite until Owner/Engineer performs final inspection and gives approval for Contractor to demobilize. PROTECTION OF PROPERTY Contractor shall protect all property within or in the vicinity of the work site. Contractor shall ensure that it is not removed, damaged, destroyed, or prevented from its normal use unless so designated in the SOW. All property adjacent to the work shall be protected including, but not be limited to, protection from construction-generated dust, debris, water, and vibration. Property includes land, utilities, landscaping, markers and monuments, monitoring wells, buildings, structures, site and drainage improvements, and other improvements, whether shown on the Drawings or not. No work shall be conducted in any wetlands or wetland buffer zone, or in the creek or creek buffer zone (shown on the Construction Drawings) unless specifically identified in the Construction Drawings or this scope of work. No work, including the staging of equipment or supplies or any land disturbing activity, shall occur outside the limits shown in the Construction Drawings. No work shall be conducted in restricted areas of the site unless coordinated and approved by Owner. Contractor shall perform a utility locate at least 48 hours prior to any below grade excavation work. Contractor shall be responsible for any damages to existing utilities that are damaged by the Contractor’s work, whether or not those utilities are identified on the Drawings. All utilities that are damaged shall be repaired and restored to their original operation at expense of Contractor. Statement of Work II - 5 PMG Phase 1 Interim Action SPILLS AND HAZARDOUS MATERIALS In the event of a spill or release of a hazardous substance (as designated in 40 CFR 302), pollutant, contaminant, or oil (as governed by the Oil Pollution Act [OPA], 33 USC 2701 et seq.), Contractor shall notify Boeing immediately. Immediate containment actions shall be taken to minimize the effect of any spills or leaks. Cleanup shall be in accordance with applicable federal, state, and local regulations. As directed by Boeing, additional sampling and testing shall be performed to verify that spills have been cleaned up. Spill cleanup and testing shall be done at no additional cost to Boeing. The project shall not use mercury, crystalline silica, lead, cadmium, asbestos, chromium or radioactive material without prior written approval from the Owner. Please note that products labeled as “non-asbestos” may contain asbestos as a minor ingredient and are not allowed in this project. RESPONSIBILITIES In addition to the requirements previously or subsequently indicated in this document, the Contractor is responsible for the following: Completion of the project per the construction schedule. System startup and full scale operation shall be on or before August 1, 2012. Substantial completion of construction is required by no later than October 30, 2012. Providing all labor, equipment, materials, personnel transportation, supervision, and management required to complete the scope of work, including field office, temporary facilities (e.g., portable toilet, lighting), environmental protection, site control and traffic control, grading, trenching, excavation, utility installation, soil handling and dewatering onsite, erosion and sediment control, hauling and disposal of non-contaminated soil and clearing/grubbing debris to designated disposal/recycling facilities, outfall construction, and general system construction. Providing qualified and appropriately trained personnel to complete the scope and comply with the requirements described herein and/or required by law. All site workers that may come in contact with hazardous materials contained in site groundwater must have current 40-hour HAZWOPER training in order to work onsite and the requirement that a HAZWOPER supervisor be available at all times when work is occurring at the site. Providing appropriate personal protective equipment (PPE) for all employees. Contact with contaminated media is not anticipated during construction; however, contaminated groundwater is present beneath the site; therefore, for bidding purposes, assume modified Level “D” PPE (including gloves, Tyveks, and booties) may be necessary for persons performing dewatering tasks or entering excavations that come in contact with groundwater. Appropriately managing stormwater flows, implementing Best Management Practices (BMPs) for environmental and sediment and erosion control protection, and performing associated monitoring. Statement of Work II - 6 PMG Phase 1 Interim Action Maintaining all equipment in good working order. Installing appropriate traffic control measures and barricades around work areas accessible to the public including signs. If necessary, develop traffic control plan for submission to the City, or other appropriate agency. Cooperating with and supporting Owner’s site representatives. Maintain spill clean-up supplies such as absorbent pads and booms in appropriate quantities and at appropriate locations in the work site. Maintaining records and noting deviations from the Construction Drawings to aid and assist with preparation of post-construction as-built drawings. Owner will be responsible for the following: Obtaining environmentally related permits as indicated below. Providing access to the work site (and escorts, as necessary) during normal working hours. Providing construction oversight to ensure compliance with construction provisions and monitoring for potentially hazardous conditions related to site contamination. Preparation of reports for submittal to Ecology. Installation of extraction wells per Washington well installation regulations (borings and well casings completed to ground surface only; i.e., well vaults, pumps, etc. are Contractor’s responsibility). Statement of Work III - 1 PMG Phase 1 Interim Action III. GENERAL TASKS, REQUIREMENTS, AND SUBMITTALS The following required elements of the project shall be followed or completed prior to performance of field activities: PERMITTING For this work, Owner is obtaining a sanitary sewer discharge authorization from the City and a Critical Areas Work Authorization from the City. Contractor shall be responsible for complying with applicable permit conditions associated with this scope of work. Contractor shall apply for and obtain all other necessary and applicable local, state, and federal permits for completion of the work described herein (e.g., building permit, public works permit, side sewer permit, right-of-way permit) including associated submittals. Contractor shall determine what permits are required, apply for permits in a timely manner, diligently pursue securing permits, and comply with any stipulations in the permits. Contractor may request assistance, as necessary, from the Owner or Engineer, but, in all cases, shall be responsible for obtaining permits. Verbally notify the Engineer as soon as possible and provide immediate written notification to the Engineer in the event that a permit cannot be obtained or will likely be obtained with agency stipulations that significantly affect the performance and cost of the work. UTILITY CONNECTIONS Contractor shall be responsible for arranging and coordinating with the local power, telecommunications, and sewer companies/utilities district for appropriate connections and supplying certain applicable equipment and services to allow for hookup of such as needed for the treatment system. Electrical - Contractor shall be responsible for supplying and installing all electrical conduit and junction boxes from the electrical tap point north of Seaway Boulevard (including horizontal boring beneath Seaway Boulevard to tap point) as indicated in the Construction Drawings and Utility Company Drawings and Designs. Snohomish County PUD will provide and install the primary metering cabinet, two transformers, and electrical cable into Contractor installed conduit from tap point to the primary metering cabinet south of Seaway Boulevard and from the primary metering cabinet to the transformers. Contractor shall be responsible for supplying wiring/cable beyond the transformers. Telecommunication - Contractor shall coordinate with local telecommunications company to provide appropriate connection point at the entry to the site along Seaway Boulevard. Telecommunications connection shall be made at the identified connection point along Seaway Boulevard and as indicated in the Construction Drawings or Utility Company Drawings and Designs . Contractor shall install all communication line conduit and wiring from the connection point to the treatment system building and associated equipment and control systems per the Construction Drawings. Statement of Work lII - 2 PMG Phase 1 Interim Action Sewer - Side sewer connection shall be made at and from the identified connection points along the City sanitary sewer line, including appropriate connections, piping, and structures, as indicated in the Construction Drawings, to allow for hookup of such, as, to and from the treatment system. EROSION AND SEDIMENT CONTROL Coverage under the Washington Construction Stormwater General Permit is not required for this project due to the limited area of land that will be disturbed during construction. However, the project is located adjacent to sensitive areas (i.e., Powder Mill Creek, designated jurisdictional wetland, and associated creek and wetland buffer zones). Therefore, Contractor shall implement and maintainappropriate Temporary Erosion and Sediment Control (TESC) measures and best management practices, as prescribed in the Stormwater Management Manual for Western Washington (2005), the City of Everett Stormwater Management Manual, and as shown on Drawing C-3 in all areas disturbed by construction activities. Contractor shall also take appropriate measures to prevent trackout of dirt onto public roads, including construction of a suitable construction entrance at the site entrance at Seaway Boulevard and street cleaning, as needed. All loads of soil or aggregate shall be covered for transport to or from the site. HEALTH AND SAFETY Site work shall be performed in accordance applicable state and federal occupational health and safety regulations. Contractor shall prepare and comply with a health a safety plan that is at least as stringent as the project health and safety plan (Landau Associates 2005). SUBMITTALS Submittal Requirements Two copies of each submittal will be provided by Contractor. All submittals furnished formally shall bear a Contractor’s approval stamp or a certification. The stamp or certification shall be signed by an authorized representative of the Contractor. The Contractor’s stamp or certification on any submittals shall constitute a representation to the Owner and the Engineer that the Contractor has either determined and verified all quantities, dimensions, field construction criteria, materials, catalog numbers and similar data, or that it assumes full responsibility for doing so, and that it has reviewed or coordinated each submittal with the requirements of the Contract Documents. Each submittal shall be accompanied by a transmittal letter that describes the items submitted. The transmittal letter shall be clearly labeled “Phase 1 IA – Boeing/PMG Site” and shall have a submittal number. The first submittal shall have submittal number 001, and subsequent submittals shall be consecutively numbered. The initial version of the submittal shall be identified as “Revision 0,” and subsequent submittals shall be numbered consecutively starting with “Revision 1.” All submittals shall be addressed to the Engineer at the following address: Statement of Work lII - 3 PMG Phase 1 Interim Action Landau Associates 130 2nd Avenue South Edmonds, WA 98020 Attention: Mr. Piper Roelen, P.E., Associate. Electronic submittals may be sent via electronic mail to: proelen@landauinc.com Submittal Review After review of each of Contractor’s submittals, the material will be returned to Contractor marked as follows: 1. “No Exceptions Taken.” Accepted subject to its compatibility with future submittals and additional partial submittals for portions of Work not covered in this submittal. Does not constitute approval or deletion of specified or required items not shown in the partial submittal. 2. “Make Corrections Noted” (No Resubmittals Required). Same as Item 1, except that minor corrections as noted shall be made by Contractor. 3. “Amend and Resubmit.” Rejected because of major inconsistencies or errors. Resolve or correct before next submittal. 4. “Rejected-Resubmit.” Submitted material does not conform to the Contract Documents in a major respect (i.e., wrong size, model, capacity, or material). Within 5 days of receipt of Shop Drawings or manufacturer’s data, the Engineer will return one copy of each drawing and/or data sheet marked to indicate the result of the Engineer’s review. Copies marked “No Exceptions Taken” or “Make Corrections Noted” authorize the Contractor to proceed with construction covered by those Drawings or data sheets with corrections, if any, incorporated. No revision in any way shall be made after a Drawing has been marked “No Exceptions Taken” without resubmitting the Drawing for review. When prints of Drawings have been marked “Amend and Resubmit” or “RejectedResubmit,” the Contractor shall make the necessary corrections and submit required copies. Every revision shall be shown by number, date, and subject in a revision block and, in addition, each revised Drawing shall have its latest revision numbers and items clearly indicated by clouding around the revised areas on the Drawing. Drawings submitted without these indications will be considered nonconforming and will be returned to the Contractor without review. The applicable parts of the requirements specified above for Drawings shall apply equally to design data, catalog cuts, illustrations, printed specifications, draft reports, or any other submittal furnished for review. Specific Project Submittals The following shall be submitted prior to commencement of construction: Statement of Work lII - 4 PMG Phase 1 Interim Action Health and Safety Plan Within 10 calendar days following notice to proceed, Contractor shall submit a worker Health and Safety Plan conforming to the requirements indicated above. Schedule Contractor shall submit the construction schedule within 10 calendar days following notice to proceed. Sequencing/Phasing Plan Within 10 calendar days following notice to proceed, Contractor shall submit a plan presenting a sequencing and phasing plan for preliminary tasks and submittals, clearing and grubbing, grading, utility connections, utility equipment installation, utility conduit/piping trench excavation, sewer connection, utility conduit/piping/wiring installation, treatment system building construction, extraction and treatment system construction, and restoration that optimizes use of the available land area on the property, expedites the work, and minimizes disturbance of land. Changes to sequencing of work presented in Contractor’s approved plan shall only be made with the concurrence of the Engineer. Equipment/Materials List Before beginning onsite work and within 20 days following notice to proceed, Contractor shall submit a list of materials to Engineer for review. The list shall include all items of equipment and material, and the names of the manufacturers and suppliers with whom purchase orders have been placed. Provide sufficient data to precisely identify materials and equipment Contractor proposes to furnish. The list shall include Drawing or Specification references. Engineer will attempt to approve or disapprove of proposed materials/equipment with 3 working days of the submittal. Contractor shall resubmit the above requested information for any equipment or materials that are rejected by the Engineer. Manuals, Instructions, and Certificates Prior to final inspection, Contractor shall submit four (4) complete sets of all manufacturer’s specifications, cut sheets (including major valves and other materials), operations and maintenance manuals, instructions, and certificates to Engineer covering mechanical, electrical, instrumentation, piping items, and other material and equipment provided by the Contractor, as noted in the Drawings and Specifications. These materials shall be provided in 3-ring binder(s) with cover(s) with printed title “Operations and Maintenance Materials,” title of project, and subject matter of binder if multiple binders are required. Place same information on binder spine so as to be legible when standing upright on a bookshelf. Internally subdivide the binder contents with permanent page dividers logically organized; with tab titling clearly printed under reinforced laminated plastic tabs. Include a table of contents for the manual. Provide a directory listing names, addresses, and telephone numbers of Contractor, Subcontractors, and equipment suppliers and manufacturer’s representatives nearest to Statement of Work lII - 5 PMG Phase 1 Interim Action the job site for each major product in the manual. Materials shall be bound in 8-1/2 inch by 11 text pages. Larger sheets shall be folded to 8-1/2 inch by 11 inch size and enclosed in transparent, top entry protective plastic folders. Record Drawings During the progress of the Work, maintain at the site a detailed record of all changes from the layouts and lines and grades, details, or other information shown on the Drawings and on Contractor-furnished drawings and data. Enter the changes on the record drawings promptly, but no later than on a weekly basis, using red, erasable pencil. Have on file current working record drawings showing all changes, associated construction dates, documentation of the Owner’s approval for changes, and documentation of Contractor authorization to execute changes. Contractor shall prepare and submit final mark-up of the Drawings indicating as-built dimensions and any other as-built changes to Drawings. The set of Drawings shall be clean except for red pencil used to indicate the as-built changes. Record drawings shall be submitted within 14 days of completion of the work. Permit Applications Permit applications for the permits identified under “Permitting” subheading above shall be prepared and submitted to the appropriate permitting authority in a timely manner and per the project schedule, allowing sufficient lead time for agency review and approval. Extensions If Contractor is unable to meet the submittal deadlines identified above for any reason, Contractor shall request and extension from the Engineer at least 2 working days prior to, and as far in advance of, the deadline as practicable. The request shall identify the reason why an extension is needed and a proposed revised deadline. PROJECT CLOSEOUT The Contractor warrants the Work delivered under the contract to be free from defects in material or workmanship, and against damage caused prior to final inspection. Unless otherwise specified, this warranty extends for a period of one (1) year from the date of final acceptance. The Contractor shall promptly repair or replace all defective or damaged products or materials delivered under the contract. Prior to requesting final inspection, the Contractor shall submit to Owner and Engineer written certification that the work has been thoroughly inspected by Contractor and is complete in accordance with the Contract Documents. A project closeout punchlist may be used by Contractor, Engineer, and Owner. Statement of Work IV - 1 PMG Phase 1 Interim Action IV. SCOPE OF WORK Contractor shall construct the groundwater extraction and treatment system as shown in the Construction Drawings (Exhibit A2 in Attachment 1 – Project Plans). In the event that discrepancies between this SOW and the Construction Drawings are identified, the Construction Drawings shall take precedence. The discrepancy shall also be identified to the Engineer and/or clarification requested as needed. A summary of the Scope of Work is presented below. SUMMARY The work will consist of constructing all elements of the groundwater extraction system, conveyance system, treatment system and building, and treated water discharge/sewer connection, including all auxiliary electrical and communications systems from the utility connections at Seaway Boulevard and to and from the system components. Contractor shall provide all materials and equipment that are not provided by Owner, as necessary, to produce a fully functional system in accordance with the Construction Drawings and these specifications. The materials that will be provided by the Owner include the lowprofile air stripper and associated blower. The major equipment and materials to be provided by Owner and the Contractor for the Work is provided in schedules on the Drawings. Contractor shall be responsible for installing all equipment, including that equipment provided by Owner. Extraction wells EGW175, EGW182, and EGW183 will be installed by Owner, but all wellhead structures and equipment will be provided and installed by the Contractor. The major elements of the work include, but are not limited to, the following items: Provision and installation of one new well vault, submersible pump, and associated wellhead equipment at well EGW175 Provision and installation of one new well vault, submersible pump, and associated wellhead equipment at well EGW182 Provision and installation of one new well vault, submersible pump, and associated wellhead equipment at well EGW183 Provision and installation of groundwater conveyance piping from extraction wells EGW175, EGW182, and EGW183 to the new treatment system building location Install a side sewer connection to the City sewer line and associated structures Provision and installation of treated groundwater conveyance piping from the new treatment system building location to the side sewer connection to the City sewer line, including associated structures Provide and construct a treatment system building with electrical power, communications (telephone/internet), lighting, heating, a below grade sump Provide, install, and test the following treatment system equipment: o Owner-supplied air stripper o Owner-supplied blower Statement of Work IV - 2 PMG Phase 1 Interim Action o Moisture separator o Duct heater o Granular activated carbon (GAC vessels) and associated manifold o Bridge crane o Temporary water supply o Double-walled temporary holding tank (outside building) Provision and installation of a exterior concrete pad outside treatment system building for temporary holding tank Provision and installation of weather-proof control panel enclosures at EGW175 and EGW182 Provision and installation of system electrical equipment and wiring to all equipment and instrumentation including, but not limited to, below ground electrical conduit and cablesjunction boxes and vaults; and associated breakers and panels Provision and installation of system communication lines including, but not limited to, aboveground communications cables and poles; below ground communications conduit and cables; and control panels Provision and installation of all interconnecting piping and piping supports Provision and installation of interconnecting electrical power wiring and communications wiring all equipment and instrumentation. Trenching (and horizontal boring as necessary) for pipe conveyance, electrical conduit, and communication line conduit, and restoration of natural areas and gravel surfacing along roads Off-site disposal of excess trench spoil Site work including grubbing and clearing, excavation, grading and leveling, subgrade preparation and compaction Pressure testing of lines Startup and testing of systems to ensure proper operation Surveying to determine slopes and elevations as specified Preparation of record drawings to reflect the "as-built" condition. The Work to be accomplished is organized into the general areas listed below: 1. Groundwater Extraction System. Furnish (all materials not provided by Owner), install, startup, and test submersible groundwater extraction pumps for extraction wells EGW175, EGW182, and EGW183. Owner will furnish a 6-inch nominal diameter open-hole drilled wells. Contractor shall install well head vault and 2-inch stainless-steel riser piping for wells and shall install valves and fittings for the well head. Statement of Work IV - 3 PMG Phase 1 Interim Action 2. Groundwater Conveyance Piping. Supply, install, and test the groundwater conveyance piping. New conveyance piping shall consist of 2- and 4-inch diameter conveyance pipe joined to form continuous conveyance of groundwater between individual well vaults (and existing steel piping) and the new treatment system. New groundwater piping shall be constructed of butt-welded high density polyethylene (HDPE) and shall be compatible with TCE and other chlorinated VOCs. Electrical conduit and communication line conduit shall also be routed to the well in the same trench as the conveyance conduit. The Contractor shall supply and install the electrical and communications conduit and cable. Conduit and cable to the extraction wells shall be of the size specified on the electrical drawings and specifications. 3. Building. Prepare site, provide materials, and construct a cement masonry unit (CMU) building with a steel truss roofing system to house the treatment system. The building interior dimensions will be approximately 38 ft long, 20 ft wide, and 13 ft high. Concrete floor to be sloped toward a blind sump with steel grated cover. Building will be provided with heater to keep the building at or above 40°F. Building penetrations required for treatment system components shall be sealed in an aesthetic and water-tight manner. 4. Treatment System. Supply (those materials not provided by Owner), install, and test the treatment system. Contractor will be responsible for coordinating will all utility providers to establish necessary services (i.e., power, telephone). Owner will pay those fees to utilities that are required for provision of new service connections. Contractor will be responsible for connection of services from the point of service provided by the utility companies to the equipment of this Work. Extracted groundwater shall be pumped to the treatment system building and then to the inlet of the air stripper. After treatment in the air stripper, water shall flow by gravity to a polyvinyl chloride (PVC) line, as shown on the Drawings. The Contractor shall connect the air stripper effluent line to piping that allows operation under several configurations as shown on the Drawings: a) to a discharge pump that pumps to the 4-inch HDPE discharge line routed to the sanitary sewer outfall, b) to a discharge pump that pumps to a temporary holding tank outside the building, or c) from the temporary holding tank and returned to the air stripper (via a transfer pump) for additional treatment. Water purposefully or inadvertently discharged to the building sump shall be pumped through 2-inch PVC piping, via a sump pump, to the temporary holding tank. Air exhausted from the air stripper shall be conveyed through an 8-inch steel duct to a moisture separator, duct heater, GAC treatment vessels, and a 10-inch discharge stack through the roof of the new treatment system building. The top of stack shall be at a minimum height of 19 ft above ground surface elevation in the area. Statement of Work IV - 4 PMG Phase 1 Interim Action 5. Discharge/Outfall to Sewer. Install side sewer connection and associated manhole structure for treated groundwater discharge to sanitary sewer. Supply, install, and test the treated water conveyance piping. New conveyance piping shall consist of 4-inch diameter conveyance pipe joined to form continuous conveyance of treated water between the new treatment system and the manhole structure, and 6-inch diameter pipe from the manhole structure to the sanitary sewer outfall. New piping shall be constructed of butt-welded HDPE and shall be compatible with TCE and other chlorinated VOCs.. 6. Instrumentation, Control, and Monitoring (ICM) System. Supply, install, and test a fully programmed and functional ICM system for the treatment equipment and extraction systems, consisting of a Programmable Logic Controllers (PLC), flow meters, pressure indicators, pressure switches, level switches, level alarms, and other miscellaneous elements, as noted on the Drawings. ICM system components to be provided are shown on the Drawings and described in the Technical Specifications. Contractor shall provide and install all required aboveground and underground communications conduit, junction boxes, and wiring to the treatment building, between the well control panels, and the treatment system components. 7. Electrical. Contractor shall provide and install all required aboveground and underground electrical conduit, junction boxes, vaults, and wiring to the treatment building, well vaults, and treatment system components. Statement of Work V-1 PMG Phase 1 Interim Action V. TECHNICAL SPECIFICATIONS The following sections provide technical specifications for applicable elements of work that supplement or augment the specifications provided in the Drawings. This part includes the following Sections: Section 02200 Section 02605 Section 02900 Section 02950 Section 03300 Section 04220 Section 05310 Section 05400 Section 05530 Section 07410 Section 08110 Section 08330 Section 08630 Section 08710 Section 08900 Section 10520 Section 14630 Section 15060 Section 15160 Section 15400 Section 17000 Section 17700 Site Preparation and Earthwork Vaults and Manholes Planting Site Restoration and Rehabilitation Cast-In-Place Concrete Concrete Unit Masonry Steel Decking Cold-Formed Steel Framing Metal Gratings Metal Roof Panels Hollow Metal Doors and Frames Overhead Coiling Doors Metal-Framed Skylights Door Hardware Louvers and Vents Fire Extinguishers Wall Supported Steel Bridge Crane Pipe, Fittings, Valves, and Support Well Equipment Treatment Equipment General Instrumentation, Control, and Monitoring Requirements System Operating Description Statement of Work V-2 PMG Phase 1 Interim Action SECTION 02200 – SITE PREPARATION AND EARTHWORK PART 1 GENERAL 1.1 DESCRIPTION A. 1.2 RELATED SECTIONS A. 1.3 1.4 Provide grubbing and clearing, grading, excavating, backfilling, compaction, removal and disposal of surplus excavated material, and other work associated with meeting established lines and grades, and installation of buried and supported equipment and structures. Division 2: Site Work – all sections. REFERENCES A. ASTM D 422 – Particle Size Analysis of Soil B. ASTM D 2922 – Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods C. ASTM D 3017 – Test Methods for Moisture Content of Soil and SoilAggregate Mixtures D. OSHA E. WSDOT Standard Specifications for Road, Bridge, and Municipal Construction 2010 M 41-10G F. ASTM D 2488 – Practice for Description and Identification of Soils (VisualManual Procedure) G. ASTM D 2487 – Classification of Soils for Engineering Purposes H. Landau Associates. Foundation Design Memorandum. April 27, 2010 I. Western Washington Stormwater Management Manual J. City of Everett Stormwater Management Manual SUBMITTALS A. Submit name of supplier and sample of each type of imported fill for examination by Engineer. Provide materials from same source throughout the work. Site Preparation and Earthwork Section 02200 Statement of Work 1.5 1.6 V-3 PMG Phase 1 Interim Action DELIVERY, STORAGE, AND HANDLING A. Pile delivered and excavated material onsite in a manner that will not endanger the work and that will not obstruct driveways or interfere with facility operations. Take measures to prevent stormwater pollution, including, but not limited to, coir logs surrounding the stockpiles, fabric covers over catch basins, and temporary covers on the piles. Material piles shall only be located in areas specified by the Engineer or Owner. B. Excavated material suitable for use as backfill shall be piled in an orderly manner separately from unsuitable material, at a sufficient distance from the edge of the trench to prevent material from sloughing or sliding back into the trench. C. Excess excavated soils and materials unsuitable for use as backfill shall be placed onsite as directed by the Engineer or Owner. D. Contractor shall, to the maximum extent practicable, transfer excess excavated soil directly into trucks. E. Conduct work in a manner that will cause the least interruption to local business operations. Where local business operations will be impacted by the work being performed, the Contractor shall follow sequence of construction so that local business operations are maintained. COORDINATION A. Notify Engineer at least 5 days before starting excavation. Excavation shall not proceed until Engineer has agreed to same. B. Provide the services of a competent buried utility locating service to identify the location of existing buried utilities within the project site prior to commencing excavation. Mark locations of existing buried utilities and planned location of buried utilities, equipment, and extents of excavation prior to commencing excavation. C. Protect existing pipes, conduits, poles, wires, well casings, or other apparatus that may affect the work, and protect the same, under, over, along or across said work. In case any of said pipes, conduits, poles, wires, or apparatus should be damaged, they shall be repaired by Contractor to the satisfaction of the Engineer, and the expense of such repairs shall be borne by the Contractor. Any damage to existing wells shall be corrected by repair or replacement, by a Washington state licensed well driller approved by Engineer. Contractor shall bear all expenses reasonably related to the repair or replacement of wells, including, but not limited to, the well drillers services and materials, professional oversight and documentation, and sampling and analysis (if necessary). Site Preparation and Earthwork Section 02200 Statement of Work V-4 PMG Phase 1 Interim Action PART 2 PRODUCTS 2.1 STRUCTURAL FILL A. 2.2 NATIVE MATERIAL A. 2.3 2.3 Structural fill is defined as fill used to obtain final grade elevation for footings, earth supported floor slabs, and paved or surfaced areas. Structural fill shall consist of any suitable material that is nonorganic, nonplastic, granular soil corresponding to soil types GW, GP, SW, or SP soils, as designated by Unified Soil Classification System (U.S.C.S.) per ASTM D 2488 and ASTM D 2487. To minimize the quantity of waste soil generated, native soil shall be used as structural fill provided it meets the above requirements and is free of topsoil, organic material, and debris. CDF, as specified in Paragraph 2.03 B of this Section, may be used as structural fill. Recycled material such as crushed concrete is not allowed. Native excavated material free of topsoil or organic matter and any large boulders, rocks, or chunks of consolidated earth that might damage the pipe or structure or present a compaction problem shall be used as backfill material to the extent possible. Rocks larger than 3 inches measured in any direction shall not be used as backfill material. BEDDING MATERIAL A. Gravel: Pipe zone bedding material shall consist of crushed, processed, or naturally occurring granular materials that conform with WSDOT 9-03.12(3). B. Controlled Density Fill (CDF): CDF may be substituted for gravel bedding material in areas with limited access, such as at crossings of existing utility pipes or conduit. CDF shall conform with WSDOT 9-01.2(4). GRAVEL SURFACING A. Gravel surfacing material for the final cover shall be manufactured from ledge rock, talus, or gravel, shall be uniform in quality, and substantially free from wood, roots, bark, and other extraneous material. The material shall conform to the requirements WSDOT 9-03.9(3). B. Contractor may, at its option, utilize an imported, clean, gravel surfacing material with different gradation and quality characteristics than specified above if such material is suitable for its intended use, satisfies the general requirements and intent of this Contract, and is acceptable to the Engineer. C. Material when placed shall also allow ease of foot traffic and small vehicle traffic such as a forklift. Site Preparation and Earthwork Section 02200 Statement of Work V-5 PMG Phase 1 Interim Action PART 3 EXECUTION 3.1 CLEARING, GRUBBING, AND GRADING A. Prior to clearing, grubbing, and grading, wetland buffer and waterway buffer will be flagged or fenced within 50 feet of the project area(s). B. Contractor, in coordination with the Biologist or Engineer, will flag and inventory diameter at breast height and species of trees to be removed. Any trees to be removed are to be replaced at a ratio of 2:1 following completion of construction. The Contractor shall notify the Biologist or Engineer a minimum of five (5) working days in advance of tree inventory. C. Perform clearing, grubbing, and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated work areas. Clearing and grubbing shall only be performed where necessary to safely and effectively perform site grading, trenching, and construction. The limits of the areas to be cleared and grubbed will be marked with high visibility fencing, silt fencing, flags, stakes, tree markings and/or other suitable methods. The limits of clearing and grading shall be verified by the Engineer or Biologist prior to ground disturbance. D. Trees or other materials to be retained or used as habitat features will be flagged and identified by the Engineer or Biologist. The Contractor shall notify the Biologist a minimum of five (5) working days in advance of clearing the site. Trees and other vegetation to be removed will be designated with a different color flag, ribbon or stake. E. Trees, shrubs, and other vegetation designated to remain undisturbed shall be protected from damage throughout the construction period. The Contractor shall be responsible for the repair or replacement of vegetation damaged by the Contractor’s operations. Any superficial damage such as cuts, skins, scrapes or bruises to the bark of protected vegetation shall be carefully trimmed and treated using locally acceptable procedures. 1. Limbs or branches, one half (½”) inches or greater, which are broken or otherwise severed during construction, shall be cut flush at the base of the limb/branch. 2. Roots, one inch (1”) or greater, which are broken or otherwise severed during construction, shall have their ends cut smoothly and perpendicular to the root. 3. Roots exposed during excavation or other operations shall be covered with moist soil to match the previous grades as soon as possible. F. Materials removed during the clearing and grubbing operations will be disposed of offsite as solid waste or recycled/composted. The Contractor is responsible for complying with all applicable local, state or federal regulations when the contract specifies offsite disposal of the materials. Site Preparation and Earthwork Section 02200 Statement of Work V-6 PMG Phase 1 Interim Action G. Site grading shall be performed as shown on the Drawings. Structural fill shall be imported, placed, and compacted as specified in paragraphs 3.03, 3.04, and 3.05 of this section. H. Before and during soil disturbance activities, Contractor shall implement the temporary erosion and stormwater control measures shown on the Drawings and the best management practices. I. Contractor shall recycle construction, demolition, or land clearing (CDL) debris where practical. And report quantities to the Engineer and Owner. These reports must include: 1. A description of all recyclables, non-hazardous waste, and CDL debris removed from the site. 2. The quantity of recyclables and non-hazardous waste removed from the site by weight, for that period. 3. Classification of the recyclables according to the following categories: a. Concrete, asphalt and masonry, b. Clean soil and gravel, c. Metals, d. Stumps and brush, e. Recyclables sorted off site by a third party provider. f. 3.2 EXCAVATION A. The working area of the site shall be cleared of all debris. The clearing limits shall be as marked in the field and shall be kept to the minimum extent needed to accomplish the work. B. Excavation for trenches shall conform to the limits shown on the Drawings. The Contractor shall also prevent surface water from entering the trench. C. Width and Depth: The excavation shall be of such width to permit workmen to satisfactorily install buried structures, and to provide safe working conditions in accordance with federal, state, and local laws and regulations. Trench safety is the sole responsibility of the Contractor, but compliance with OSHA and other applicable regulations is mandatory. Where required to prevent caving of the trench, or by any safety law or regulation such as OSHA, the Contractor shall furnish and install bracing and/or sheeting to protect the excavation. This bracing and/or sheeting shall be removed as trench backfill progresses. Site Preparation and Earthwork Section 02200 Statement of Work 3.3 V-7 PMG Phase 1 Interim Action D. Excavations for vaults and similar structures shall be large enough to provide proper working room. Any over depth excavation shall be backfilled with compacted gravel or other approved material at the Contractor's expense. E. Excavate to bring the required cut areas to rough grade or subgrade in accordance with the drawings within plus or minus 0.10 feet. F. The Contractor shall remove and dispose of all water entering the excavation. Disposal of water shall be done in a manner to prevent erosion or sediment from entering adjacent wetlands or surface water, and in accordance with all applicable laws and regulations. Pumps shall be adequate to maintain a dry trench during the bedding, pipe installation, and initial backfill to an elevation at least one foot above the top of pipe. No backfill may be placed in standing water under any circumstances. G. Dust and storm water control shall be maintained during construction. H. Barricade open excavations to prevent access during nights and weekends and when excavations are not actively being worked. I. Schedule activities to minimize period during which excavations remain open. No excavation shall remain open for a period longer than 5 calendar days without written approval of the Engineer. BACKFILLING A. Compact subgrade to density requirements specified in paragraph 3.04, of this section. B. Remove loose, soft, or wet subgrade soil that cannot be compacted to the specified density. Backfill with structural fill and compact as specified in paragraph 3.04 of this section. C. Employ a placement method that does not disturb or damage existing features or other work. D. Bedding shall be placed in conformance with the details shown on the Drawings to uniformly support the buried structures throughout their length. Before placing any bedding material, the bottom of the trench shall be hand raked ahead of the pipe laying operation to remove stones and lumps which will interfere with smooth and complete bedding of the pipe. After the pipe has been laid and approved for covering, the specified bedding material shall then be placed in layer(s) the full width of the trench, and compacted as indicated in the Drawings and paragraph 3.04 of this section. E. Trenches shall be backfilled above the bedding material, as shown in the Drawings, with suitable material saved from trench excavation. If there is Site Preparation and Earthwork Section 02200 Statement of Work V-8 PMG Phase 1 Interim Action not sufficient suitable material from the excavation, the backfilling of the trench shall be completed utilizing imported backfill. The backfill and/or imported backfill shall be compacted as indicated as indicated in the Drawings and paragraph 3.04 of this section. 3.4 3.5 F. Excavations in existing roadways shall be resurfaced to match pre-existing conditions. G. In freezing weather, prior to terminating the work for the day, loose protective material shall be placed on top of the backfill to prevent freezing and shall be removed prior to subsequent work. Backfill shall not be placed on snow, ice or frozen soil. COMPACTING METHODS A. The fill material shall be compacted at a moisture content within 2% of optimum moisture content. Structural fill and bedding shall be compacted to a firm, unyielding condition within the limits of any pipe trench where the depth of fill over the pipe is less than 12 inches. In areas where subsurface utilities are covered by at least 12 inches of fill and under structures such as the treatment building, catch basins and vaults, compact structural fill to finish paving elevation to at least 95 percent maximum density, as determined by ASTM D 1557. Engineer may have testing done to verify that the requirement for minimum 95% compaction has been achieved. Contractor shall be responsible for any recompaction and re-testing required due to failed compaction testing. B. Field Densities shall be determined by the Sand Cone Method, ASTM D 1556, or the Nuclear Method, ASTM D 2922. At the time of compaction the moisture content of that portion of the backfill material passing a U.S. No. 4 sieve shall be not more than 3 percent above the optimum moisture content as determined by the laboratory tests. C. Place bedding material in layers not exceeding 6 inches loose depth. Place backfill in layers not exceeding 12 inches loose depth. Hand compact bedding material to a distance of 3 inches above the top of pipes prior to using mechanical compacting equipment. D. Avoid contacting any pipe or buried conduit with mechanical compacting equipment. Do not use mechanically-powered compaction equipment directly over pipe or conduits until sufficient backfill has been placed to prevent damage to, or displacement of, the pipe or conduits. TREATMENT SYSTEM AREA A. If necessary following grading and leveling, structural fill shall be placed to raise the treatment system area to the proper elevation indicated on the Drawings. Site Preparation and Earthwork Section 02200 Statement of Work V-9 PMG Phase 1 Interim Action B. Structural fill used for the treatment system area base shall be in accordance with paragraph 2.01A. CDF shall not be substituted for structural fill in the treatment system area. C. Gravel Surfacing: The top layer of gravel surfacing shall be placed in one lift at the treatment system area to provide a minimum of 3 inches depth. This top layer shall be provided to prevent a muddy or dusty ground surface. 1. Moisture condition the gravel surfacing material to or near its optimum moisture content, as determined by ASTM D 1557. Place, grade, and compact gravel surfacing to elevation on the Drawings. Compact granular surfacing to at least 92 percent of its maximum dry density (ASTM D 1557). 3.6 3.7 DISPOSAL OF EXCAVATED MATERIAL A. All excavated soil and debris not used as backfill shall be placed onsite as directed by the Engineer or Owner. B. Asphalt and concrete removed under this Contract shall be transported offsite to a facility licensed to receive the material for either recycling or disposal. C. Submit copies of receipts, weigh tickets, and other documentation verifying that disposal of soils, asphalt, concrete, and other wastes was completed in accordance with this paragraph. FIELD QUALITY CONTROL A. Field inspection and testing will be performed by the Contractor to the satisfaction of the Engineer during the Work. B. Perform compaction testing in accordance with ASTM D 1557, ASTM D 1556, and ASTM D 3017 at two locations, selected by the Engineer, within the limits of the area where the new treatment system concrete pad and building is to be constructed. Compaction testing shall also be conducted along the run of each trench, at locations selected by the Engineer, at no more than 400 ft between testing locations. Compaction testing will not be required in areas where CDF is used as backfill. C. If tests indicate work does not meet specified requirements, remove work, replace, compact, and retest. END OF SECTION Site Preparation and Earthwork Section 02200 Statement of Work V - 10 PMG Phase 1 Interim Action SECTION 02605 – VAULTS AND MANHOLES PART 1 GENERAL 1.1 DESCRIPTION A. 1.2 1.3 The Work of this section includes supply and installation of five underground, precast, concrete vaults and manholes, as shown on the Drawings. RELATED SECTIONS A. Section 02200: Earthwork B. Section 15060: Pipes, Fittings, Valves, and Supports C. Section 15160: Well Equipment SUBMITTALS A. Provide shop drawings for the vaults and all appurtenances. Drawings shall indicate exact dimensions and weight of each unit; dimensions and locations of vault penetrations; design capacities for lifting lugs; and fabrication, handling, and installation procedures. PART 2 PRODUCTS 2.1 PRECAST CONCRETE VAULTS A. Precast concrete vaults for extraction wells EGW175, EGW182, and EGW183, and for the discharge pipe junction, shall be as specified in the Drawings and modified as necessary to accommodate the well vault equipment. Concrete vaults shall include vault accessories, including lids as specified in the Drawings. Precast concrete vaults shall conform to the following: 1. Vault covers shall be water tight and lockable (with padlock), and frames shall be manufactured to withstand AASHTO H-20 loading. 2. Factory Modifications: 10” diameter bottom penetration for well casing, 24” diameter bottom penetration for sump. 3. Open bottom for discharge electrical junction vault B. Precast concrete manhole for the discharge structure adjacent to the side sewer connection shall be as specified in the Drawings. Manhole shall include standard manhole lid. Vaults and Manholes Section 02605 Statement of Work C. 2.2 V - 11 PMG Phase 1 Interim Action Well control panel enclosures for extraction wells EGW175 and EGW182 as specified in the Drawings. GROUT A. Non-shrink grout shall be equivalent to “Masterflow 928” manufactured by Masterbuilders, Inc. PART 3 EXECUTION 3.1 INSTALLATION A. Contractor shall install vaults and manholes per specifications in Drawings. B. The final location of the associated well control panel enclosures shall be flagged by the Contractor and confirmed by the Engineer prior to installation. C. Contractor shall have sole responsibility for coordination of other trades, subcontractors, delivery, off-loading, and all necessary incidental material to accomplish and accurately install vaults and manholes in a timely manner to prevent delay of job progress. D. Contractor shall have sole responsibility for providing adequate equipment and trained personnel to accomplish safe placement of vaults and manholes and ancillary equipment, including the control panel enclosures. E. Vault penetrations for well conduit and drains shall be factory-drilled, saw cut, bored, or cast-in during fabrication or saw cut in the field. Chiseled or jack-hammered penetrations are not acceptable. Final vault pipe penetrations shall be completely filled and patched with non-shrinking cement grout. A trowel or other instrument shall be used to create a finished surface surrounding all pipe penetrations that is smooth and flush with the interior surface of the vault. Seal grout as recommended by the grout manufacturer. Link-Seal® Modular Seals may be substituted for seal grout. F. Special care must be exercised to prevent damage to groundwater extraction well casings or existing utility conduits during excavation for, and setting of, well vaults. Contractor shall repair all damage to well casings and utilities at Contractor’s expense. Any damage to existing wells shall only be corrected by repair or replacement by a Washington state-licensed well driller approved by Engineer. Contractor shall bear all expenses reasonably related to the repair or replacement of wells, including, but not limited to, the well driller’s services and materials, professional oversight and documentation, and sampling and analysis (if necessary). Vaults and Manholes Section 02605 Statement of Work V - 12 PMG Phase 1 Interim Action G. Contractor shall have sole responsibility for setting vaults as shown on the Drawings to provide adequate clearance for the installation of pumps, and other ancillary equipment within the vault. Install vaults to elevations indicated on the Drawings. H. Backfilling around vault shall be accomplished in a uniform and even manner to prevent shifting or misalignment after setting vault. Backfill and compaction shall conform with Section 02200. The completed vault installation shall result in a vault that is level and plumb. I. Install cast iron frame on vault lid by placing a minimum 1/2-inch thick layer of non-shrink grout on the lid within the footprint of the frame. Trowel the grout bed level. Place frame on grout bed and apply firm pressure to seat the frame in the grout. Grout shall completely fill space between the lid and the frame base plate to a thickness of not less than 1/8 inch. Frame shall be accurately centered over the cast opening in the lid. Remove excess grout in the frame/lid opening. Protect frame and lid from damage or movement until grout has initially cured. Place structural fill around and above vault lid and frame and compact using manual compaction equipment. END OF SECTION Vaults and Manholes Section 02605 Statement of Work V - 13 PMG Phase 1 Interim Action SECTION 02900 – PLANTING PART 1 GENERAL 1.1. DESCRIPTION A. This section applies to those items necessary for and incidental to the execution and completion of planting and maintenance for restoration plantings for the wetland and wetland/waterway buffer and other miscellaneous disturbed natural areas.. B. This section applies to those items necessary for and incidental to the execution and completion of planting and maintenance for the restoration plantings for the wetland, wetland/waterway buffer, and other miscellaneous disturbed natural areas. C. A maintenance period shall begin when the initial planting operation has been accepted by the Engineer and extend two full growing seasons following installation. D. In general, restoration plantings should be installed no earlier than October 1 and no later than March 31. However, planting in areas of high erosion potential shall be conducted as soon as practicable E. Caution shall be exercised during excavation, planting, filling, grading, and clean-up to protect existing trees, shrubs, other specified vegetation, and other site features, improvements, structures, and utilities. Removal or destruction of existing plants is prohibited unless specifically authorized by the Engineer or Biologist. The grade shall not be changed nor shall soil be added over the Critical Root Zone (CRZ) of existing plants marked for protection. The CRZ is an area equal to one foot radius for each one inch diameter of a plant measured at diameter breast height (DBH). 1.2 RELATED SECTIONS A. 1.3 Division 2: Site Work – all sections. REFERENCES A. American Standard for Nursery Stock. ANSI Z60.1. current edition. American Nursery and Landscape Association, 1250 I St. NW, Suite 500, Washington, DC 20005. B. The American National Standard for Tree Care Operations, ANSI A300. current edition. International Society of Arboriculture, PO Box 3129, Champaign, IL 61826-3129 Planting Section 02900 Statement of Work C. 1.4 PMG Phase 1 Interim Action All standards shall include the latest additions and amendments as of the date of advertisement for bids. QUALIFICTIONS OF INSTALLER A. The Contractor shall be licensed in the State of Washington, shall have a minimum of 3 years experience, and shall have completed landscaping work similar in material, design, and extent to that indicated for this project and with a record of successful landscape establishment. B. Contractor must be familiar and comply with American Standard for Nursery Stock published by the American Nursery and Landscape Association. 1.5 SUBMITTALS A. Within 30 days of award, Contractor shall submit documentation that specified plant materials have been ordered and secured. A list of supplier names, addresses, phone numbers, and the storage/growing location of the materials shall also be submitted to the Engineer within 30 days of the landscape contractor award. B. If specified materials are unavailable, the Contractor shall notify the Engineer in writing immediately and provide the names and telephone numbers of five suppliers that have been contacted. If substitution is needed, written approval from the Biologist is required. For plants and seeds, local genetics must be confirmed by providing a signed letter to the Engineer. C. Upon completion of the installation of the restoration elements, the Contractor shall provide Engineer with a set of clearly marked Drawings that provide plant quantities and locations within the restoration areas. 1.6 1.7 V - 14 HANDLING AND STORAGE A. Plants must be stored in the manner necessary to accommodate horticultural requirements. Protect plant material stored on site from weather damage, construction activity, and the public. Protect roots by covering with moist soil, mulch, or sawdust. Water as required to keep roots moist. B. Keep plants moist and shaded until the actual time of installation. If bareroot plants are specified, soak roots in water a minimum of 1 hour prior to planting. Before and after planting, immediately saturate the soils in the planting area to prevent capillary stress. PLANT SURVIVAL WARRANTY Planting Section 02900 Statement of Work V - 15 PMG Phase 1 Interim Action A. The Plant Survival Warranty shall include replacement of plants (same size and species shown on the Drawings) that prove to be declining, damaged, dead, or missing. Except for loss due to excessively severe climatological conditions (substantiated by 10-year recorded weather charts), installed plant materials are required to be guaranteed for 2 years against defects and unsatisfactory growth, except for cases of neglect or abuse/damage by others. Plants shall be replaced under plant guarantee conditions. B. It is the responsibility of the Contractor to exercise care when moving plants and other restoration elements to avoid breaking branches, scuffing bark, or breaking roots of existing and new plants. Areas that are damaged or disturbed that are outside of the project limits or not shown on the Drawings shall be restored in kind at no extra cost to Owner. Plant species and quantities of replacement plantings shall be approved by the Biologist prior to installation. PART 2 PRODUCTS 2.1 PLANTS A. Plants shall be provided per planting schedules in the Drawings. B. Plant material shall meet the requirements of the current edition of the American Standard for Nursery Stock, and state and federal laws with respect to plant disease and infestations. Inspection certificates, required by law, shall accompany each and every shipment and shall be submitted to Engineer upon arrival of plant material. C. Plant materials shall be locally grown (western Washington, western Oregon, or western British Columbia), healthy, bushy, in vigorous growing condition, and be accurate in size, name, and variety. Furthermore, plants shall be free from disease, injury, insects, insect eggs, root and other types of weevils, larva, weed roots, and defects such as knots, sun scald, injuries, abrasions, disfigurements, and irregular growth. Local genetics shall be confirmed by a signed letter from the nursery. D. To acclimate plant materials to local conditions, all plant materials used on a project shall be grown continuously outdoors north of the 42nd Latitude (Oregon-California border) from not later than August 1 of the year prior to the time of planting. E. Representative trees must be untied and separated for inspections. Engineer or Biologist reserves the right to refuse any/all plant material any time prior to final acceptance if it is determined that such material does not meet the Specifications as described herein. Plant material with damaged root zones will not be accepted, and shall be replaced at no expense to Planting Section 02900 Statement of Work V - 16 PMG Phase 1 Interim Action the Owner. Rejected materials shall be immediately removed from the project site and replaced at no expense to the Owner. F. The Biologist shall inspect plant materials at the job site for compliance with required standards for plant size and quality prior to planting. This includes, but is not limited to, size and condition of root systems, presence of insects, latent injuries, and defects. Plant requirements are as follows: G. Container Plants (Trees, Shrubs, and Groundcovers): a) Trees shall have uniform branching; single, straight trunks (unless specified as multi-stemmed); and the central leader intact and undamaged. b) No balled or burlapped plants will be used. c) Unless necessary for larger trees, do not stake plants for support. d) Do not prune or top plants before delivery, except as approved by Biologist. e) Protect bark, branches, and root systems from sun scald, drying, sweating, whipping, and other handling and tying damage. f) Do not bend or bind-tie plants in such a manner as to destroy the natural shape. Provide protective covering during delivery. Do not drop plants during delivery. g) Container stock shall be fully rooted but not root-bound. h) The original central leader on tree stock must be healthy and undamaged. i) Plants shall be the size indicated on the Drawings. H. Bare root stock can be substituted for container plants as approved by the Engineer and Biologist. I. Plants must be stored in the manner necessary to accommodate their horticultural requirements. Protect plant material stored on site from weather damage, construction activities, and the public. Keep plants moist and shaded until the actual time of installation. Do not allow any plants to be exposed to freezing temperatures prior to planting. J. Substitutions of plant species or sizes may be permitted based on plant availability, but only with prior written approval by the Biologist. Planting Section 02900 Statement of Work K. 2.2 PMG Phase 1 Interim Action The Biologist shall examine restoration planting materials prior to unloading at the site. Any material not meeting these required Specifications shall be immediately removed from the site and replaced with products specified in the Drawings and these Specifications at no cost to the Owner. Bark Mulch A. 2.3 V - 17 A three inch compacted layer of bark mulch shall be used in a 24-inch diameter ring surrounding all container plants in the Restoration Planting area only. See the Drawings for further information. Fertilizers A. Trees, shrubs, and groundcovers shall be fertilized using one of the following products: 1. Formula 4-2-2 “Transplanter” as manufactured by Pacific Agro Co., with Hercules nitroform and W.R. Grace’s “Magamp” and trace elements. Apply at a rate of: a. Trees: 8 ounces b. Shrubs: 2 ounces c. Groundcovers: 1 ounce 2. Agriform Tablets: Planting tablets, 21-gram size, as manufactured by Agriform International Chemicals, Inc., 20-10-5 analysis. Apply at a rate of: a. Trees: 4 tablets for every foot of rootball diameter b. Shrubs: 3 tablets c. Groundcovers: 1 tablet PART 3 EXECUTION 3.1 PLANTING A. Contractor is to plant trees and shrubs in planting pits as detailed in the Drawings. B. When performing the following work, do not injure the root system. Do not overexcavate planting pit depth; however, overexcavation of planting pit width is desirable. C. Before laying out plant locations, Contractor shall walk the intended planting area with the Biologist to discuss strategies for plant locations. Planting Section 02900 Statement of Work V - 18 PMG Phase 1 Interim Action D. The Contractor shall locate in the field and either stake or lay out actual plants at proposed planting locations prior to planting. Plants shall be placed in a random, natural pattern following placement notes provided in the Plans. On-center (O.C.) spacing called out on the plant schedule indicates an average spacing dimension. For example, if the plan calls for 24 inches O.C., spacing shall vary from 18 to 30 inches O.C., with an average spacing of 24 inches. Biologist shall approve proposed plant locations and layout prior to installation by the Contractor. Any substantial variations from the planting plan will require prior approval by the Biologist. E. Trees shall be handled by the rootball, not by the trunk. Plants shall be installed upright, rotating them to give the best placement to adjacent plants and topography. Hold plant rigidly in position until topsoil has been backfilled and tamped firmly around the ball or roots. F. When the planting pit is backfilled halfway, place the specified quantity of fertilizer and stakes, if necessary, as shown on the Drawings and these Specifications. Evenly space the fertilizer around the perimeter of and immediately adjacent to the root system. Carefully place water and compact planting backfill, filling all voids. Do not injure the root system. G. When the planting pit is three-quarters (3/4) backfilled, fill with water and allow it to soak away. Fill pits with additional topsoil and continue backfilling. Ground bark shall be placed over all tree-planting saucers to a compact depth of 3 inches. Water trees immediately after planting. H. Detailed directions for planting are described as follows (also refer to the Drawings): 1. Container Trees and Shrubs: The following directions, adapted from the International Society of Arboriculture, must be followed for container plantings (see Details on Sheet C-8): a) Dig a shallow, broad planting hole. Make the hole three times the diameter of the root ball but only as deep as the root ball. b) Stockpile excavated soil next to planting pit. The excavated soil will be used for backfill in the planting pit. c) Identify the trunk flare. The trunk flare is where the roots spread at the base of the plant. This point shall be partially visible after the plant has been installed. If the trunk flare is not partially visible, some soil shall be removed from the top of the root ball. d) Place the tree or shrub at the proper height. Before placing the tree or shrub in the hole, check to see that the hole has been dug to the proper depth and no deeper. It is better to plant the tree or shrub a little high, 2 to 3 inches above the base of the trunk flare, than to plant it at or below the original growing level. This planting level will allow for some settling. To avoid damage when setting the tree or Planting Section 02900 Statement of Work V - 19 PMG Phase 1 Interim Action shrub in the hole, always lift the tree or shrub by the root ball and never by the trunk. e) Straighten the tree or shrub in the hole. Before beginning backfilling, view the tree or shrub from several directions to confirm that the tree or shrub is straight. f) Fill the hole gently but firmly. Fill the hole about one-half (½) full and water settle the soil around the base of the root ball. g) Apply fertilizer into planting pit as specified in Section 2.04. h) Fill the remainder of the hole, taking care to firmly pack soil to eliminate air pockets that may cause roots to dry out. To avoid this problem, add the soil a few inches at a time and settle with water. Continue this process until the hole is filled and the tree or shrub is firmly planted. i) Do not stake trees or shrubs unless necessary to keep the tree or shrub straight. a) 2. If bare root stock is to be used in lieu of container plants, all methods for installation of container plants apply with exception of storage and handling of bare root stock, which shall be submitted by Contractor upon request for using bare root stock. I. 3.2 Rectification of Accidental Plant Injury A. 3.3 Immediately (on the day of installation) water all plants thoroughly. Any living woody plant that is damaged during construction shall be treated within 24 hours of occurrence, including wound-shaping treatment, which includes, but is not limited to, evenly cutting broken branches, exposed roots, and damaged tree bark immediately after damage occurs. Injured plants shall be thoroughly watered and additional measures shall be taken, as appropriate, to aid in plant survival, at no cost to Owner. Any plants that are visible harmed such that future growth is jeopardized (such as broken leaders, uprooting, etc.) shall be replaced at no cost to the Owner. SOIL PREPARATION/AMENDMENTS A. Planting Mulch in the form of organic compost shall be used as a topsoil for all planting areas. Section 02900 Statement of Work 3.4 V - 20 PMG Phase 1 Interim Action RESTORE EXISTING NATURAL AREAS A. Existing natural or landscaped areas that are damaged construction shall be restored to their original condition, improvements or modifications are specified for those areas. removed incidental to construction activities shall be replaced at a 2 trees for every tree removed (i.e., 2:1). during unless Trees ratio of B. The Contractor shall exercise care to protect from injury trunks, roots, or branches of any trees or shrubs that are to remain. Any living woody plant that is damaged during construction shall be treated immediately. Any superficial damage such as cuts, skins, scrapes or bruises to the bark of protected vegetation shall be carefully trimmed and treated using locally acceptable procedures. 1. Limbs or branches, one half (½”) inches or greater, which are broken or otherwise severed during construction, shall be cut flush at the base of the limb/branch. 2. Roots, one inch (1”) or greater, which are broken or otherwise severed during construction, shall have their ends cut smoothly and perpendicular to the root. 3. Roots exposed during excavation or other operations shall be covered with moist soil as soon as possible to prevent the roots from drying out. 3.5 IRRIGATION A. 3.6 All plants may require irrigation for a period of time after installation. The Engineer and Biologist will evaluate the environmental conditions of the plating areas and determine what level of effort will be required by Contractor for irrigation. Contractor shall monitor, irrigate, and maintain plants throughout the construction period. During the first year after planting, Contractor shall be responsible for replacement of plants as needed and irrigation of plants for the first growing season (from February 28 to November 20). MAINTENANCE A. This section includes additional maintenance that is not included under the warranty and maintenance for plants. This is expected to include maintenance items authorized in writing by the Owner, as needed after the 2-year warranty period, and other items authorized in writing by the Owner during the 2-year warranty period, including, but not limited to: 1. Correction of Foraging and Browsing: The Contractor shall implement measures to prevent damage of plant material by browsing animals (e.g., deer, beaver, rabbits, mice, voles). Planting Section 02900 Statement of Work V - 21 PMG Phase 1 Interim Action 2. Weeding and Maintenance of Trees and Shrubs: Routine maintenance of trees and shrubs shall be performed. Weed control should be performed by hand removal and/or other approved methods. No mechanical weed trimmers or herbicides will be used after initial site preparation activities. 3. Pruning of Woody Plants – Woody plants shall be pruned only to remove pest infestations. 4. Resetting plants to proper grade and upright position, controlling invasive weed species, and correcting drainage problems, as required. 5. Removal of temporary erosion control. 6. Modifications to the irrigation system to accommodate optimal plant survival. 3.7 B. Contractor shall review maintenance recommendations with the Biologist. C. Contractor has the right to enter the property for inspection and curative treatment of any materials still under warranty during the entire warranty period. Owner is to be notified in advance of any corrective or curative treatment measures so as to arrange for convenient access to the area. D. Contractor shall be responsible for consistent and adequate maintenance and operation of the irrigation system. Contractor shall be responsible for maintenance and repairs during the warranty period. B. At the end of the irrigation period (if needed) and if plant establishment is successful, as determined by Owner’s representative, irrigation will be discontinued. CHECKLIST AND CLOSEOUT A. The Biologist shall verify that all items meet the Specifications listed in this section. Any items that do not meet Specifications will be marked on a checklist for rectification prior to the next phase of work and/or project closeout. If items are to be corrected, a contingency checklist of adaptive management strategies necessary to meet Specifications shall be prepared by the Owner and submitted to the Contractor. After punch list items have been completed by the Contractor, the Owner shall review and revise the checklist to reflect satisfactory completion END OF SECTION Planting Section 02900 Statement of Work V - 22 PMG Phase 1 Interim Action SECTION 02950 – SITE RESTORATION AND REHABILITATION PART 1 GENERAL 1.1 DESCRIPTION A. 1.2 This section describes general site restoration and rehabilitation requirements for areas of the site where Work is substantially completed or will not be actively worked for at least 1 week. RELATED SECTIONS A. All Divisions PART 2 PRODUCTS Not Applicable to This Section PART 3 EXECUTION 3.1 FINISHING AND CLEANUP A. Restore site to pre-construction conditions, where applicable. The entire site shall be cleared of all materials such as construction debris, paper, wood, glass containers, trash, wire, broken concrete, rubble, plastic, fiberglass and other undesirable items as directed by the Engineer. Soil stockpiles shall be removed or spread onsite where approved by the Engineer. B. Finish grade elevations outside of designated cut or fill areas shall be restored to natural grade. C. Gravel roadways shall be graded smooth and aggregate surface restored as needed. D. Contractor shall avoid soil compaction in natural areas. E. Restoration of vegetation in natural areas and within the wetland and wetland/waterwaybuffer (i.e., the treatment system discharge trench and outfall areas, and access paths to piezometers) shall conform to the planting schedule and specifications in the Drawings and Section 02900. Repairs of equipment damage and replacement of vegetation shall be acceptable to the Engineer. The Engineer shall be the sole judge of the need to replace damaged/disturbed vegetation. Leave area in a clean and neat condition. F. Surplus materials, tools, equipment and temporary structures shall be removed by the Contractor. The construction site shall be left clean. Site Restoration and Rehabilitation Section 02950 Statement of Work V - 23 PMG Phase 1 Interim Action END OF SECTION Site Restoration and Rehabilitation Section 02950 Statement of Work V - 24 PMG Phase 1 Interim Action SECTION 03300 - CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.1 SUMMARY A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes. B. Related Sections: 1. Division 31 Section "Earth Moving" for drainage fill under slabs-on-grade. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Design Mixtures: For each concrete mixture. C. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication, bending, and placement. D. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer detailing fabrication, assembly, and support of formwork. 1.3 INFORMATIONAL SUBMITTALS A. Welding certificates. B. Material certificates. C. Material test reports. D. Floor surface flatness and levelness measurements. 1.4 QUALITY ASSURANCE A. Manufacturer Qualifications: A firm experienced in manufacturing readymixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment. 1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities." B. Testing Agency Qualifications: An independent agency qualified according to ASTM C 1077 and ASTM E 329 for testing indicated. Cast-In-Place Concrete Section 03300 Statement of Work V - 25 PMG Phase 1 Interim Action C. Welding Qualifications: Qualify procedures and personnel according to AWS D1.4/D 1.4M, "Structural Welding Code - Reinforcing Steel." D. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents: 1. ACI 301, "Specifications for Structural Concrete," Sections 1 through 5. 2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials." E. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures. PART 2 - PRODUCTS 2.1 FORM-FACING MATERIALS A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints. B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit. 2.2 STEEL REINFORCEMENT A. Reinforcing Bars: ASTM A 615, Grade 60, deformed. B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice. 2.3 CONCRETE MATERIALS A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout the project: 1. Portland Cement: following: ASTM C 150, Type II, gray. Supplement with the a. Fly Ash: ASTM C 618, Class F. b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or 120. B. Normal-Weight Aggregates: ASTM C 33, graded. 1. Maximum Coarse-Aggregate Size: 1-1/2 inches nominal. Cast-In-Place Concrete Section 03300 Statement of Work V - 26 PMG Phase 1 Interim Action 2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement. C. Water: ASTM C 94 and potable. 2.4 ADMIXTURES A. Air-Entraining Admixture: ASTM C 260. B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride. 1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A. 2. Retarding Admixture: ASTM C 494/C 494M, Type B. 3. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D. 4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F. 5. High-Range, Water-Reducing and Retarding Admixture: C 494M, Type G. ASTM C 494/ 6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II. 2.5 VAPOR RETARDERS A. Sheet Vapor Retarder: ASTM E 1745, Class A. recommended adhesive or pressure-sensitive tape. Include manufacturer's B. Sheet Vapor Retarder: Polyethylene sheet, ASTM D 4397, not less than 10 mils thick. 2.6 CURING MATERIALS A. Evaporation Retarder: Waterborne, monomolecular manufactured for application to fresh concrete. film forming, B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry. C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlappolyethylene sheet. D. Water: Potable. E. Clear, Waterborne, Membrane-Forming Curing Compound: Type 1, Class B, dissipating. Cast-In-Place Concrete ASTM C 309, Section 03300 Statement of Work V - 27 PMG Phase 1 Interim Action F. Clear, Waterborne, Membrane-Forming Curing Compound: Type 1, Class B, nondissipating. ASTM C 309, G. Clear, Solvent-Borne, Membrane-Forming Curing and Sealing Compound: ASTM C 1315, Type 1, Class A. 1. VOC Content: Curing and sealing compounds shall have a VOC content of 200 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). H. Clear, Waterborne, Membrane-Forming Curing and Sealing Compound: ASTM C 1315, Type 1, Class A. 1. VOC Content: Curing and sealing compounds shall have a VOC content of 200 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). 2.7 CONCRETE SEALANT A. Carboline® Phenoline® 187 Primer and Finish. 2.8 CONCRETE MIXTURES A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301. B. Cementitious Materials: Use fly ash, pozzolan, ground granulated blastfurnace slag, and silica fume as needed to reduce the total amount of portland cement, which would otherwise be used, by not less than 40 percent. C. Admixtures: Use admixtures according to manufacturer's written instructions. D. Proportion normal-weight concrete mixture as follows: 1. Minimum Compressive Strength: 3500 psi at 28 days. 2. Maximum Water-Cementitious Materials Ratio: 0.45. 3. Slump Limit: 4 inches for concrete with verified slump of 2 to 4 inches (before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch. 4. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent. 2.9 FABRICATING REINFORCEMENT A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice." Cast-In-Place Concrete Section 03300 Statement of Work 2.10 V - 28 PMG Phase 1 Interim Action CONCRETE MIXING A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94, and furnish batch ticket information. 1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes. PART 3 - EXECUTION 3.1 FORMWORK A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads. B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117. C. Chamfer exterior corners and edges of permanently exposed concrete. 3.2 EMBEDDED ITEMS A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. 3.3 VAPOR RETARDERS A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder according to ASTM E 1643 and manufacturer's written instructions. 1. Lap joints 6 inches and seal with manufacturer's recommended tape. 3.4 STEEL REINFORCEMENT A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement. 1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete. 3.5 JOINTS A. General: Construct joints true to line with faces perpendicular to surface plane of concrete. Cast-In-Place Concrete Section 03300 Statement of Work V - 29 PMG Phase 1 Interim Action B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Engineer. C. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated. 3.6 CONCRETE PLACEMENT A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed. B. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation. 1. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301. C. Cold-Weather Placement: Comply with ACI 306.1. D. Hot-Weather Placement: Comply with ACI 301. 3.7 FINISHING FORMED SURFACES A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed-surface irregularities. 1. Apply to concrete surfaces not exposed to view. B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects. Remove fins and other projections that exceed specified limits on formed-surface irregularities. 1. Apply to concrete surfaces exposed to public view. C. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces unless otherwise indicated. Cast-In-Place Concrete Section 03300 Statement of Work 3.8 V - 30 PMG Phase 1 Interim Action FINISHING FLOORS AND SLABS A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces. B. Broom Finish: Apply a broom finish to all concrete slabs. 3.9 CONCRETE PROTECTING AND CURING A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing. B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing. C. Cure concrete according to ACI 308.1, by one or a combination of the following methods: 1. Moisture Curing: seven days. Keep surfaces continuously moist for not less than 2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moistureretaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape. 3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period. a. Removal: After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer. 4. Curing and Sealing Compound: Apply uniformly to floors and slabs indicated in a continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Repeat process 24 hours later and apply a second coat. Maintain continuity of coating and repair damage during curing period. Cast-In-Place Concrete Section 03300 Statement of Work 3.10 V - 31 PMG Phase 1 Interim Action CONCRETE SEALANT A. Contractor shall seal the surfaces of the slab and sump with concrete sealant chemically compatible and resistant to trichloroethylene (at a concentration up to 1,000 parts per billion) and other chlorinated solvents. B. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Carboline C. Applying Sealant: Prepare and mix Phenoline 187 Primer & Finish concrete sealant according to manufacturer's written instructions. Apply primer and finish coat uniformly to floors and sump surfaces with a sprayer according to manufacturer's written instructions. Finish shall be gray. 3.11 CONCRETE SURFACE REPAIRS A. Defective Concrete: Repair and patch defective areas when approved by Engineer. Remove and replace concrete that cannot be repaired and patched to Engineer's approval. 3.12 FIELD QUALITY CONTROL A. Testing and Inspecting: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports. 3.13 PROTECTION OF LIQUID FLOOR TREATMENTS A. Protect liquid floor treatment from damage and wear during the remainder of construction period. Use protective methods and materials, including temporary covering, recommended in writing by liquid floor treatments installer. END OF SECTION Cast-In-Place Concrete Section 03300 Statement of Work V - 32 PMG Phase 1 Interim Action SECTION 04220 - CONCRETE UNIT MASONRY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Concrete masonry units (CMUs) 2. Steel reinforcing bars 3. CMU sealant. 1.2 PRECONSTRUCTION TESTING A. Preconstruction Testing Service: Owner will engage a qualified independent testing agency to perform preconstruction testing indicated below. Retesting of materials that fail to comply with specified requirements shall be done at Contractor's expense. 1. Concrete Masonry Unit Test: For each type of unit required, according to ASTM C 140 for compressive strength. 2. Mortar Test (Property Specification): For each mix required, according to ASTM C 109 for compressive strength. 3. Mortar Test (Property Specification): For each mix required, according to ASTM C 780 for compressive strength. 4. Grout Test (Compressive Strength): For each mix required, according to ASTM C 1019. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: For reinforcing steel. Detail bending and placement of unit masonry reinforcing bars. Comply with ACI 315, "Details and Detailing of Concrete Reinforcement." Show elevations of reinforced walls. 1.4 INFORMATIONAL SUBMITTALS A. Material Certificates: For each type and size of product indicated. For masonry units include material test reports substantiating compliance with requirements. B. Mix Designs: For each type of mortar and grout. Include description of type and proportions of ingredients. Concrete Unit Masonry Section 04220 Statement of Work V - 33 PMG Phase 1 Interim Action 1. Include test reports for mortar mixes required to comply with property specification. Test according to ASTM C 109 for compressive strength, ASTM C 1506 for water retention, and ASTM C 91 for air content. 2. Include test reports, according to ASTM C 1019, for grout mixes required to comply with compressive strength requirement. 1.5 QUALITY ASSURANCE A. Masonry Standard: Comply with ACI 530.1/ASCE 6/TMS 602 unless modified by requirements in the Contract Documents. 1.6 PROJECT CONDITIONS A. Cold-Weather Requirements: Do not use frozen materials or materials mixed or coated with ice or frost. Do not build on frozen substrates. Remove and replace unit masonry damaged by frost or by freezing conditions. Comply with cold-weather construction requirements contained in ACI 530.1/ASCE 6/TMS 602. B. Hot-Weather Requirements: Comply with hot-weather requirements contained in ACI 530.1/ASCE 6/TMS 602. construction PART 2 - PRODUCTS 2.1 MASONRY UNITS, GENERAL A. Defective Units: Referenced masonry unit standards may allow a certain percentage of units to contain chips, cracks, or other defects exceeding limits stated in the standard. Do not use units where such defects will be exposed in the completed Work. B. Fire-Resistance Ratings: Where indicated, provide units that comply with requirements for fire-resistance ratings indicated as determined by testing according to ASTM E 119, by equivalent masonry thickness, or by other means, as acceptable to authorities having jurisdiction. 2.2 CONCRETE MASONRY UNITS A. Shapes: Provide shapes indicated and for lintels, corners, jambs, sashes, movement joints, headers, bonding, and other special conditions. B. CMUs: ASTM C 90. 1. Unit Compressive Strength: Provide units with minimum average net-area compressive strength of 1500 psi. 2. Density Classification: Medium weight. Concrete Unit Masonry Section 04220 Statement of Work 2.3 V - 34 PMG Phase 1 Interim Action CONCRETE MASONRY LINTELS A. General: Provide the following: B. Masonry Lintels: Prefabricated or built-in-place masonry lintels made from bond beam CMUs with reinforcing bars placed as indicated and filled with coarse grout. 2.4 MORTAR AND GROUT MATERIALS A. Portland Cement: ASTM C 150, Type I or II, except Type III may be used for cold-weather construction. Provide natural color or white cement as required to produce mortar color indicated. B. Hydrated Lime: ASTM C 207, Type S. C. Portland Cement-Lime Mix: Packaged blend of portland cement and hydrated lime containing no other ingredients. D. Masonry Cement: ASTM C 91. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Capital Materials Corporation; Flamingo Color Masonry Cement b. Cemex S.A.B. de C.V. c. Essroc, Italcementi Group d. Holcim (US) Inc. e. Lafarge North America Inc. f. Lehigh Cement Company g. National Cement Company, Inc.; Coosa Masonry Cement. E. Mortar Cement: ASTM C 1329. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Lafarge North America Inc. F. Aggregate for Mortar: ASTM C 144 G. Aggregate for Grout: ASTM C 404 H. Cold-Weather Admixture: Nonchloride, noncorrosive, accelerating admixture complying with ASTM C 494/C 494M, Type C, and recommended by manufacturer for use in masonry mortar of composition indicated. Concrete Unit Masonry Section 04220 Statement of Work V - 35 PMG Phase 1 Interim Action 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Euclid Chemical Company (The); Accelguard 80 b. Grace Construction Products, W. R. Grace & Co. - Conn.; Morset c. Sonneborn Products, BASF Aktiengesellschaft; Trimix-NCA. I. Water: Potable. 2.5 REINFORCEMENT A. Uncoated Steel Reinforcing Bars: ASTM A 615or ASTM A 706, Grade 60. 2.6 TIES AND ANCHORS A. Materials: Provide ties and anchors specified in this article that are made from materials that comply with the following unless otherwise indicated. 1. Hot-Dip Galvanized, Carbon-Steel Wire: ASTM A 82; with ASTM A 153, Class B-2 coating. 2. Steel Sheet, Galvanized after Fabrication: Steel, with ASTM A 153, Class B coating. ASTM A 1008, Commercial 3. Steel Plates, Shapes, and Bars: ASTM A 36. B. Anchor Bolts: Headed steel bolts complying with ASTM A 307, Grade A; with ASTM A 563 hex nuts and, where indicated, flat washers; hot-dip galvanized to comply with ASTM A 153, Class C; of dimensions indicated. 2.7 MORTAR AND GROUT MIXES A. General: Do not use admixtures, including pigments, air-entraining agents, accelerators, retarders, water-repellent agents, antifreeze compounds, or other admixtures unless otherwise indicated. 1. Do not use calcium chloride in mortar or grout. 2. For reinforced masonry, use mortar. 3. Add cold-weather admixture (if used) at same rate for all mortar that will be exposed to view, regardless of weather conditions, to ensure that mortar color is consistent. B. Preblended, Dry Mortar Mix: Furnish dry mortar ingredients in form of a preblended mix. Measure quantities by weight to ensure accurate proportions, and thoroughly blend ingredients before delivering to Project site. Concrete Unit Masonry Section 04220 Statement of Work V - 36 PMG Phase 1 Interim Action C. Mortar for Unit Masonry: Comply with ASTM C 270, Property Specification. Provide the following types of mortar for applications stated unless another type is indicated. 1. For reinforced masonry, use Type S. D. Grout for Unit Masonry: Comply with ASTM C 476. 1. Use grout of type indicated or, if not otherwise indicated, of type (fine or coarse) that will comply with Table 1.15.1 in ACI 530.1/ASCE 6/TMS 602 for dimensions of grout spaces and pour height. 2. Proportion grout in accordance with ASTM C 476, Table 1. 3. Provide grout with a slump of 8 to 11 inches as measured according to ASTM C 143. PART 3 - EXECUTION 3.1 TOLERANCES A. Dimensions and Locations of Elements: 1. For dimensions in cross section or elevation do not vary by more than plus 1/2 inch or minus 1/4 inch. 2. For location of elements in plan do not vary from that indicated by more than plus or minus 1/2 inch. 3. For location of elements in elevation do not vary from that indicated by more than plus or minus 1/4 inch in a story height or 1/2 inch total. B. Lines and Levels: 1. For bed joints and top surfaces of bearing walls do not vary from level by more than 1/4 inch in 10 feet or 1/2 inch maximum. 2. For conspicuous horizontal lines, such as lintels, sills, parapets, and reveals, do not vary from level by more than 1/8 inch in 10 feet, 1/4 inch in 20 feet, or 1/2 inch maximum. 3. For vertical lines and surfaces do not vary from plumb by more than 1/4 inch in 10 feet , 3/8 inch in 20 feet, or 1/2 inch maximum. 4. For conspicuous vertical lines, such as external corners, door jambs, reveals, and expansion and control joints, do not vary from plumb by more than 1/8 inch in 10 feet, 1/4 inch in 20 feet , or 1/2 inch maximum. 5. For lines and surfaces do not vary from straight by more than 1/4 inch in 10 feet, 3/8 inch in 20 feet, or 1/2 inch maximum. 3.2 LAYING MASONRY WALLS A. Lay out walls in advance for accurate spacing of surface bond patterns with uniform joint thicknesses and for accurate location of openings, movement- Concrete Unit Masonry Section 04220 Statement of Work V - 37 PMG Phase 1 Interim Action type joints, returns, and offsets. Avoid using less-than-half-size units, particularly at corners, jambs, and, where possible, at other locations. B. Use full-size units without cutting if possible. If cutting is required to provide a continuous pattern or to fit adjoining construction, cut units with motor-driven saws; provide clean, sharp, unchipped edges. Allow units to dry before laying unless wetting of units is specified. Install cut units with cut surfaces and, where possible, cut edges concealed. C. Bond Pattern for Exposed Masonry: Unless otherwise indicated, lay exposed masonry in running bond; do not use units with less than nominal 4-inch horizontal face dimensions at corners or jambs. D. Built-in Work: As construction progresses, build in items specified in this and other Sections. Fill in solidly with masonry around built-in items. E. Fill space between steel frames and masonry solidly with mortar unless otherwise indicated. F. Where built-in items are to be embedded in cores of hollow masonry units, place a layer of metal lath, wire mesh, or plastic mesh in the joint below and rod mortar or grout into core. G. Fill cores in hollow CMUs with grout 24 inches under bearing plates, beams, lintels, posts, and similar items unless otherwise indicated. 3.3 MORTAR BEDDING AND JOINTING A. Lay hollow CMUs as follows: 1. With face shells fully bedded in mortar and with head joints of depth equal to bed joints. 2. With webs fully bedded in mortar in all courses of piers, columns, and pilasters. 3. With webs fully bedded in mortar in grouted masonry, including starting course on footings. 4. With entire units, including areas under cells, fully bedded in mortar at starting course on footings where cells are not grouted. B. Lay solid masonry units with completely filled bed and head joints; butter ends with sufficient mortar to fill head joints and shove into place. Do not deeply furrow bed joints or slush head joints. C. Tool exposed joints slightly concave when thumbprint hard, using a jointer larger than joint thickness unless otherwise indicated. D. Cut joints flush for masonry walls to receive plaster or other direct-applied finishes (other than paint) unless otherwise indicated. Concrete Unit Masonry Section 04220 Statement of Work 3.4 V - 38 PMG Phase 1 Interim Action ANCHORING MASONRY TO CONCRETE A. Anchor masonry to structural steel and concrete where masonry abuts or faces structural steel or concrete to comply with the following: 1. Anchor masonry with pre-installed dowel anchors embedded in concrete. 2. Space anchors as indicated on drawings. 3.5 REINFORCED UNIT MASONRY INSTALLATION A. Temporary Formwork and Shores: Construct formwork and shores as needed to support reinforced masonry elements during construction. 1. Construct formwork to provide shape, line, and dimensions of completed masonry as indicated. Make forms sufficiently tight to prevent leakage of mortar and grout. Brace, tie, and support forms to maintain position and shape during construction and curing of reinforced masonry. 2. Do not remove forms and shores until reinforced masonry members have hardened sufficiently to carry their own weight and other loads that may be placed on them during construction. B. Placing Reinforcement: ASCE 6/TMS 602. Comply with requirements in ACI 530.1/ C. Grouting: Do not place grout until entire height of masonry to be grouted has attained enough strength to resist grout pressure. 1. Comply with requirements in ACI 530.1/ASCE 6/TMS 602 for cleanouts and for grout placement, including minimum grout space and maximum pour height. 2. Limit height of vertical grout pours to not more than 48 inches . D. Sealant: Apply uniformly both exterior and interior faces of all CMU block with Sure Klean® Weather Seal Blok-Guard® & Graffiti Control per manufacturers recommendations. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. b. Prosoco, Inc. 3.6 FIELD QUALITY CONTROL A. Testing and Inspecting: Owner will engage special inspectors to perform tests and inspections and prepare reports. Allow inspectors access to scaffolding and work areas, as needed to perform tests and inspections. Concrete Unit Masonry Section 04220 Statement of Work V - 39 PMG Phase 1 Interim Action Retesting of materials that fail to meet specified requirements shall be done at Contractor's expense. B. Inspections: Level 1 special inspections according to the "International Building Code." 1. Begin masonry construction only after inspectors have verified proportions of site-prepared mortar. 2. Place grout only after inspectors have verified compliance of grout spaces and of grades, sizes, and locations of reinforcement. 3. Place grout only after inspectors have verified proportions of site-prepared grout. C. Testing Prior to Construction: One set of tests. D. Concrete Masonry Unit Test: For each type of unit provided, according to ASTM C 140 for compressive strength. E. Mortar Aggregate Ratio Test (Proportion Specification): provided, according to ASTM C 780. For each mix F. Mortar Test (Property Specification): For each mix provided, according to ASTM C 780. Test mortar for compressive strength. G. Grout Test (Compressive Strength): For each mix provided, according to ASTM C 1019. 3.7 REPAIRING, POINTING, AND CLEANING A. In-Progress Cleaning: Clean unit masonry as work progresses by dry brushing to remove mortar fins and smears before tooling joints. B. Final Cleaning: After mortar is thoroughly set and cured, clean exposed masonry as follows: 1. Test cleaning methods on sample wall panel; leave one-half of panel uncleaned for comparison purposes. 2. Clean concrete masonry by cleaning method indicated in NCMA TEK 8-2A applicable to type of stain on exposed surfaces. 3.8 MASONRY WASTE DISPOSAL A. Waste Disposal as Fill Material: Dispose of clean masonry waste, including excess or soil-contaminated sand, waste mortar, and broken masonry units, by crushing and mixing with fill material as fill is placed. 1. Do not dispose of masonry waste as fill within 18 inches of finished grade. Concrete Unit Masonry Section 04220 Statement of Work V - 40 PMG Phase 1 Interim Action B. Excess Masonry Waste: Remove excess clean masonry waste that cannot be used as fill, as described above, and other masonry waste, and legally dispose of off Owner's property. END OF SECTION Concrete Unit Masonry Section 04220 Statement of Work V - 41 PMG Phase 1 Interim Action SECTION 05310 - STEEL DECKING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Roof deck. 1.2 ACTION SUBMITTALS A. Product Data: For each type of deck, accessory, and product indicated. B. Shop Drawings: 1. Include layout and types of deck panels, anchorage details, reinforcing channels, pans, cut deck openings, special jointing, accessories, and attachments to other construction. 1.3 INFORMATIONAL SUBMITTALS A. Welding certificates. B. Product certificates. C. Evaluation reports. D. Field quality-control reports. 1.4 QUALITY ASSURANCE A. Testing Agency Qualifications: Qualified according to ASTM E 329 for testing indicated. B. Welding Qualifications: Qualify procedures and personnel according to AWS D1.3, "Structural Welding Code - Sheet Steel." 1.5 DELIVERY, STORAGE, AND HANDLING A. Protect steel deck from corrosion, deformation, and other damage during delivery, storage, and handling. B. Stack steel deck on platforms or pallets and slope to provide drainage. Protect with a waterproof covering and ventilate to avoid condensation. Steel Decking Section 05310 Statement of Work V - 42 PMG Phase 1 Interim Action PART 2 - PRODUCTS 2.1 PERFORMANCE REQUIREMENTS A. AISI Specifications: Comply with calculated structural characteristics of steel deck according to AISI's "North American Specification for the Design of Cold-Formed Steel Structural Members." 2.2 ROOF DECK A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Nucor Corp.; Vulcraft Group. 2. Roof Deck, Inc. 3. Verco Manufacturing Co. B. Roof Deck: Fabricate panels, without top-flange stiffening grooves, to comply with "SDI Specifications and Commentary for Steel Roof Deck," in SDI Publication No. 31, and with the following: 1. Galvanized-Steel Sheet: zinc coating. ASTM A 653, Structural Steel (SS), Grade 40 2. Galvanized and Shop-Primed Steel Sheet: ASTM A 653, Structural Steel (SS), Grade 40, G60 zinc coating; cleaned, pretreated, and primed with manufacturer's standard baked-on, rust-inhibitive primer. 3. Deck Profile: As indicated on drawings. 4. Profile Depth: As indicated on drawings. 5. Design Uncoated-Steel Thickness: As indicated on drawings. 2.3 ACCESSORIES A. General: Provide manufacturer's standard accessory materials for deck that comply with requirements indicated. B. Mechanical Fasteners: Corrosion-resistant, low-velocity, power-actuated or pneumatically driven carbon-steel fasteners; or self-drilling, self-threading screws. C. Side-Lap Fasteners: Corrosion-resistant, hexagonal washer head; selfdrilling, carbon-steel screws, No. 10 minimum diameter. D. Flexible Closure Strips: Vulcanized, closed-cell, synthetic rubber. E. Miscellaneous Sheet Metal Deck Accessories: Steel sheet, minimum yield strength of 33,000 psi, not less than 0.0359-inch design uncoated thickness, Steel Decking Section 05310 Statement of Work V - 43 PMG Phase 1 Interim Action of same material and finish as deck; of profile indicated or required for application. F. Flat Sump Plates: Single-piece steel sheet, 0.0747 inch thick, of same material and finish as deck. For drains, cut holes in the field. G. Galvanizing Repair Paint. H. Repair Paint: Manufacturer's standard rust-inhibitive primer of same color as primer. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Install deck panels and accessories according to applicable specifications and commentary in SDI Publication No. 31, manufacturer's written instructions, and requirements in this Section. B. Place deck panels on supporting frame and adjust to final position with ends accurately aligned and bearing on supporting frame before being permanently fastened. Do not stretch or contract side-lap interlocks. C. Place deck panels flat and square and fasten to supporting frame without warp or deflection. D. Cut and neatly fit deck panels and accessories around openings and other work projecting through or adjacent to deck. E. Provide additional reinforcement and closure pieces at openings as required for strength, continuity of deck, and support of other work. F. Comply with AWS requirements and procedures for manual shielded metal arc welding, appearance and quality of welds, and methods used for correcting welding work. G. Mechanical fasteners may be used in lieu of welding to fasten deck. Locate mechanical fasteners and install according to deck manufacturer's written instructions. H. Miscellaneous Roof-Deck Accessories: Install ridge plates, finish strips, end closures, and reinforcing channels according to deck manufacturer's written instructions. Weld or mechanically fasten to substrate to provide a complete deck installation. 1. Weld cover plates at changes in direction of roof-deck panels unless otherwise indicated. Steel Decking Section 05310 Statement of Work V - 44 PMG Phase 1 Interim Action I. Pour Stops and Girder Fillers: Weld steel-sheet pour stops and girder fillers to supporting structure according to SDI recommendations unless otherwise indicated. 3.2 FIELD QUALITY CONTROL A. Testing Agency: inspections. Engage a qualified testing agency to perform tests and B. Field welds will be subject to inspection. C. Testing agency will report inspection results promptly and in writing to Contractor and Architect. D. Remove and replace work that does not comply with specified requirements. E. Additional inspecting, at Contractor's expense, will be performed to determine compliance of corrected work with specified requirements. 3.3 PROTECTION A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on both surfaces of deck with galvanized repair paint according to ASTM A 780 and manufacturer's written instructions. B. Repair Painting: Wire brush and clean rust spots, welds, and abraded areas on both surfaces of prime-painted deck immediately after installation, and apply repair paint. END OF SECTION Steel Decking Section 05310 Statement of Work V - 45 PMG Phase 1 Interim Action SECTION 05400 - COLD-FORMED METAL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Roof trusses. 1.2 PERFORMANCE REQUIREMENTS A. Structural Performance: Provide cold-formed metal framing capable of withstanding design loads within limits and under conditions indicated. 1. Design Loads: As indicated on drawings. 2. Deflection Limits: Design framing systems to withstand design loads without deflections greater than the following: a. Roof Trusses: Vertical deflection of 1/240 of the span. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product and accessory indicated. B. Shop Drawings: Show layout, spacings, sizes, thicknesses, and types of cold-formed metal framing; fabrication; and fastening and anchorage details, including mechanical fasteners. 1. For cold-formed metal framing indicated to comply with design loads, include structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1.4 INFORMATIONAL SUBMITTALS A. Qualification data. B. Welding certificates. C. Product test reports. D. Research/evaluation reports. 1.5 QUALITY ASSURANCE A. Product Tests: Mill certificates or data from a qualified independent testing agency indicating steel sheet complies with requirements. Cold-Formed Metal Framing Section 05400 Statement of Work V - 46 PMG Phase 1 Interim Action B. Welding: Qualify procedures and personnel according to AWS D1.3, "Structural Welding Code--Sheet Steel." C. Fire-Test-Response Characteristics: Where indicated, provide cold-formed metal framing identical to that of assemblies tested for fire resistance per ASTM E 119 by a testing and inspecting agency acceptable to authorities having jurisdiction. D. AISI Specifications and Standards: Comply with AISI's "North American Specification for the Design of Cold-Formed Steel Structural Members" and its "Standard for Cold-Formed Steel Framing - General Provisions." 1. Comply with AISI's "Standard for Cold-Formed Steel Framing - Truss Design." 2. Comply with AISI's "Standard for Cold-Formed Steel Framing - Header Design." E. Comply with AISI's "Standard for Cold-Formed Steel Framing - Prescriptive Method for One and Two Family Dwellings." PART 2 - PRODUCTS 2.1 MATERIALS A. Steel Sheet: ASTM A 1003, Structural Grade, Type H, metallic coated, of grade and coating weight as follows: 1. Grade: As required by structural performance. 2. Coating: G60. 2.2 ROOF TRUSSES A. Roof Truss Members: Manufacturer's standard C-shaped steel sections, of web depths indicated, unpunched, with stiffened flanges. 2.3 FRAMING ACCESSORIES A. Fabricate steel-framing accessories from steel sheet, ASTM A 1003/A 1003M, Structural Grade, Type H, metallic coated, of same grade and coating weight used for framing members, unless otherwise indicated. B. Steel Shapes and Clips: ASTM A 36/A 36M, zinc coated by hot-dip process according to ASTM A 123/A 123M. C. Anchor Bolts: ASTM F 1554, Grade 36, threaded carbon-steel hex-headed bolts and carbon-steel nuts; and flat, hardened-steel washers; zinc coated by hot-dip process according to ASTM A 153, Class C. Cold-Formed Metal Framing Section 05400 Statement of Work V - 47 PMG Phase 1 Interim Action D. Expansion Anchors: Fabricated from corrosion-resistant materials, with capability to sustain, without failure, a load equal to 5 times design load, as determined by testing per ASTM E 488 conducted by a qualified independent testing agency. E. Power-Actuated Anchors: Fastener system of type suitable for application indicated, fabricated from corrosion-resistant materials, with capability to sustain, without failure, a load equal to 10 times design load, as determined by testing per ASTM E 1190 conducted by a qualified independent testing agency. F. Mechanical Fasteners: ASTM C 1513, corrosion-resistant-coated, selfdrilling, self-tapping steel drill screws. 1. Head Type: Low-profile head beneath sheathing, manufacturer's standard elsewhere. 2.4 MISCELLANEOUS MATERIALS A. Galvanizing Repair Paint ASTM A 780. B. Cement Grout: Portland cement, ASTM C 150, Type I; and clean, natural sand, ASTM C 404. Mix at ratio of 1 part cement to 2-1/2 parts sand, by volume, with minimum water required for placement and hydration. C. Shims: Load bearing, high-density multimonomer plastic, nonleaching. D. Sealer Gaskets: Closed-cell neoprene foam, 1/4 inch thick, selected from manufacturer's standard widths to match width of bottom track or rim track members. PART 3 - EXECUTION 3.1 PREPARATION A. Install load bearing shims or grout between the underside of wall bottom track or rim track and the top of foundation wall or slab at stud or joist locations to ensure a uniform bearing surface on supporting concrete or masonry construction. B. Install sealer gaskets to isolate the underside of wall bottom track or rim track and the top of foundation wall or slab at stud or joist locations. 3.2 INSTALLATION, GENERAL A. Install cold-formed metal framing according to AISI's "Standard for ColdFormed Steel Framing - General Provisions" and to manufacturer's written instructions unless more stringent requirements are indicated. Cold-Formed Metal Framing Section 05400 Statement of Work V - 48 PMG Phase 1 Interim Action B. Install cold-formed metal framing and accessories plumb, square, and true to line, and with connections securely fastened. C. Install framing members in one-piece lengths. D. Install temporary bracing and supports to secure framing and support loads comparable in intensity to those for which structure was designed. Maintain braces and supports in place, undisturbed, until entire integrated supporting structure has been completed and permanent connections to framing are secured. E. Do not bridge building expansion and control joints with cold-formed metal framing. Independently frame both sides of joints. F. Install insulation, specified in Division 07 Section "Thermal Insulation," in builtup exterior framing members, such as headers, sills, boxed joists, and multiple studs at openings, that are inaccessible on completion of framing work. G. Fasten hole reinforcing plate over web penetrations that exceed size of manufacturer's standard punched openings. H. Erection Tolerances: Install cold-formed metal framing level, plumb, and true to line to a maximum allowable tolerance variation of 1/8 inch in 10 feet and as follows: 1. Space individual framing members no more than plus or minus 1/8 inch from plan location. Cumulative error shall not exceed minimum fastening requirements of sheathing or other finishing materials. 3.3 TRUSS INSTALLATION A. Install, bridge, and brace trusses according to Shop Drawings and requirements in this Section. B. Truss Spacing: As indicated on drawings. C. Do not alter, cut, or remove framing members or connections of trusses. D. Erect trusses with plane of truss webs plumb and parallel to each other, align, and accurately position at spacings indicated. E. Erect trusses without damaging framing members or connections. F. Align webs of bottom chords and load-bearing studs or continuously reinforce track to transfer loads to structure. Anchor trusses securely at all bearing points. Cold-Formed Metal Framing Section 05400 Statement of Work V - 49 PMG Phase 1 Interim Action G. Install continuous bridging and permanently brace trusses as indicated on Shop Drawings and designed according to LGSEA's Technical Note 551e, "Design Guide for Permanent Bracing of Cold-Formed Steel Trusses." 3.4 FIELD QUALITY CONTROL A. Testing: Owner will engage a qualified independent testing and inspecting agency to perform field tests and inspections and prepare test reports. B. Field and shop welds will be subject to testing and inspecting. C. Testing agency will report test results promptly and in writing to Contractor and Engineer. D. Remove and replace work where test results indicate that it does not comply with specified requirements. E. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements. 3.5 REPAIRS AND PROTECTION A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on fabricated and installed cold-formed metal framing with galvanized repair paint according to ASTM A 780 and manufacturer's written instructions. B. Provide final protection and maintain conditions, in a manner acceptable to manufacturer and installer that ensure that cold-formed metal framing is without damage or deterioration at time of Substantial Completion. END OF SECTION Cold-Formed Metal Framing Section 05400 Statement of Work V - 50 PMG Phase 1 Interim Action SECTION 05530 - METAL GRATINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Metal bar gratings. 1.3 PERFORMANCE REQUIREMENTS A. Delegated Design: Design gratings, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated. B. Structural Performance: Gratings shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated. 1. Floors: Uniform load of 125 lbf/sq. ft. (6.00 kN/sq. m) or concentrated load of 2000 lbf (8.90 kN), whichever produces the greater stress. 2. Limit deflection to L/240 or 1/4 inch (6.4 mm), whichever is less. 1.4 ACTION SUBMITTALS A. Product Data: For the following: 1. Metal bar gratings. B. Shop Drawings: Include plans, sections, details, and attachments to other work. C. Delegated-Design Submittal: For installed products indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1.5 INFORMATIONAL SUBMITTALS A. Qualification Data: For qualified professional engineer. Metal Gratings Section 05530 Statement of Work V - 51 PMG Phase 1 Interim Action B. Mill Certificates: Signed by manufacturers of stainless-steel sheet certifying that products furnished comply with requirements. C. Welding certificates. D. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers certifying that shop primers are compatible with topcoats. 1.6 QUALITY ASSURANCE A. Metal Bar Grating Standards: Comply with [NAAMM MBG 531, "Metal Bar Grating Manual][" and] [NAAMM MBG 532, "Heavy-Duty Metal Bar Grating Manual]." B. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel." 1.7 PROJECT CONDITIONS A. Field Measurements: Verify actual locations of walls and other construction contiguous with gratings by field measurements before fabrication. 1.8 COORDINATION A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another. B. Coordinate installation of anchorages for gratings, grating frames, and supports. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation. PART 2 - PRODUCTS 2.1 FERROUS METALS A. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M. B. Steel Bars for Bar Gratings: ASTM A 36/A 36M ASTM A 1011/A 1011M or ASTM A 1018/A 1018M. or steel strip, C. Wire Rod for Bar Grating Crossbars: ASTM A 510. Metal Gratings Section 05530 Statement of Work 2.2 V - 52 PMG Phase 1 Interim Action MISCELLANEOUS MATERIALS A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy that is welded. B. Low-Emitting Materials: Paints and coatings shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers." C. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPCPaint 20 and compatible with paints specified to be used over it. 2.3 FABRICATION A. Shop Assembly: Fabricate grating sections in shop to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Use connections that maintain structural value of joined pieces. Clearly mark units for reassembly and coordinated installation. B. Cut, drill, and punch material cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces. C. Form from materials of size, thickness, and shapes indicated, but not less than that needed to support indicated loads. D. Fit exposed connections accurately together to form hairline joints. E. Welding: Comply with AWS recommendations and the following: 1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. 2. Obtain fusion without undercut or overlap. 3. Remove welding flux immediately. F. Provide for anchorage of type indicated; coordinate with supporting structure. Fabricate and space the anchoring devices to secure gratings, frames, and supports rigidly in place and to support indicated loads. 2.4 METAL BAR GRATINGS A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the work include, but are not limited to, the following: 1. Grating Pacific, Inc. 2. IKG Industries; a division of Harsco Corporation. Metal Gratings Section 05530 Statement of Work V - 53 PMG Phase 1 Interim Action 3. Marwas Steel Co.; Laurel Steel Products Division. B. Metal Bar Grating: 1. Bearing Bar Spacing: 1-3/16 inches (30 mm) O.C. 2. Bearing Bar Depth: 2 inches (51 mm) 3. Bearing Bar Thickness: 3/16 inch (4.8 mm). 4. Crossbar Spacing: 4 inches (102 mm)] O.C. 5. Steel Finish: Hot-dip galvanized with a coating weight of not less than 1.8 oz./sq. ft. (550 g/sq. m) of coated surface. C. Do not notch bearing bars at supports to maintain elevation. 2.5 GRATING FRAMES AND SUPPORTS A. Frames and Supports for Metal Gratings: Fabricate from metal shapes, plates, and bars of welded construction to sizes, shapes, and profiles indicated and as necessary to receive gratings. Miter and weld connections for perimeter angle frames. Cut, drill, and tap units to receive hardware and similar items. 1. Unless otherwise indicated, fabricate from same basic metal as gratings. B. Galvanize steel frames and supports in the following locations: 1. Interior. 2.6 STEEL FINISHES A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes. B. Finish gratings, frames, and supports after assembly. C. Galvanizing: Hot-dip galvanize items as indicated to comply with ASTM A 153/A 153M for steel and iron hardware and with ASTM A 123/A 123M for other steel and iron products. 1. Do not quench or apply post galvanizing treatments that might interfere with paint adhesion. PART 3 - EXECUTION 3.1 INSTALLATION, GENERAL A. Fastening to In-Place Construction: Provide anchorage devices and fasteners where necessary for securing gratings to in-place construction. Metal Gratings Section 05530 Statement of Work V - 54 PMG Phase 1 Interim Action Include threaded fasteners for concrete and masonry inserts, through-bolts, lag bolts, and other connectors. B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing gratings. Set units accurately in location, alignment, and elevation; measured from established lines and levels and free of rack. C. Provide temporary bracing or anchors in formwork for items that are to be built into concrete or masonry. D. Fit exposed connections accurately together to form hairline joints. 1. Weld connections that are not to be left as exposed joints but cannot be shop welded because of shipping size limitations. Do not weld, cut, or abrade the surfaces of exterior units that have been hot-dip galvanized after fabrication and are for bolted or screwed field connections. E. Attach toeplates to gratings by welding at locations indicated. F. Field Welding: Comply with the following requirements: 1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. 2. Obtain fusion without undercut or overlap. 3. Remove welding flux immediately. G. Corrosion Protection: Coat concealed surfaces of aluminum that will come into contact with grout, concrete, masonry, wood, or dissimilar metals, with a heavy coat of bituminous paint. 3.2 INSTALLING METAL BAR GRATINGS A. General: Install gratings to comply with recommendations of referenced metal bar grating standards that apply to grating types and bar sizes indicated, including installation clearances and standard anchoring details. B. Attach removable units to supporting members with type and size of clips and fasteners indicated or, if not indicated, as recommended by grating manufacturer for type of installation conditions shown. C. Attach nonremovable units to supporting members by welding where both materials are same; otherwise, fasten by bolting as indicated above. 3.3 ADJUSTING AND CLEANING A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with same material as used for shop painting to comply with SSPC-PA 1 requirements for touching up shop-painted surfaces. Metal Gratings Section 05530 Statement of Work V - 55 PMG Phase 1 Interim Action 1. Apply by brush or spray to provide a minimum 2.0-mil (0.05-mm) dry film thickness. B. Touchup Painting: Cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint are specified in Section 099113 "Exterior Painting" and Section 099123 "Interior Painting." C. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780. END OF SECTION Metal Gratings Section 05530 Statement of Work V - 56 PMG Phase 1 Interim Action SECTION 07410 - METAL ROOF PANELS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standing-seam metal roof panels. 2. Metal soffit panels. B. Related Sections: 1. Division 07 Section "Sheet Metal Roofing" for custom-fabricated and onsite, roll-formed sheet metal roofing. 1.2 PERFORMANCE REQUIREMENTS A. Hydrostatic-Head Resistance: No water penetration when tested according to ASTM E 2140. B. Wind-Uplift Resistance: Provide metal roof panel assemblies that comply with UL 580 for wind-uplift-resistance class indicated. 1. Uplift Rating: UL 90. C. FMG Listing: Provide metal roof panels and component materials that comply with requirements in FMG 4471 as part of a panel roofing system and that are listed in FMG's "Approval Guide" for Class 1 or noncombustible construction, as applicable. Identify materials with FMG markings. 1. Hail Resistance: MH. D. Structural Performance: Provide metal roof panel assemblies capable of withstanding the effects of gravity loads and the following loads and stresses within limits and under conditions indicated, based on testing according to ASTM E 1592: 1. Wind Loads: Determine loads based on the following minimum design wind pressures: a. Uniform pressure of 16 lbf/sq. ft., acting inward or outward. 2. Snow Loads: 25 lbf/sq. ft. 3. Deflection Limits: Metal roof panel assemblies shall withstand wind and snow loads with vertical deflections no greater than 1/240 of the span. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product indicated. Metal Roof Panels Section 07410 Statement of Work V - 57 PMG Phase 1 Interim Action B. Shop Drawings: Show fabrication and installation layouts of metal roof panels; details of edge conditions, side-seam and endlap joints, panel profiles, corners, anchorages, trim, flashings, closures, and accessories; and special details. Distinguish between factory- and field-assembled work. C. Samples: For each type of exposed finish required. D. Delegated-Design Submittal: For metal roof panel assembly indicated to comply with performance requirements and design criteria, including analysis data and calculations signed and sealed by the qualified professional engineer responsible for their preparation. 1.4 INFORMATIONAL SUBMITTALS A. Coordination Drawings: Roof plans, drawn to scale, based on input from installers of the items involved. B. Manufacturer Certificates: Signed by manufacturer certifying that roof panels comply with energy performance requirements specified in "Performance Requirements" Article. 1. Submit evidence of meeting performance requirements. C. Product test reports. D. Field quality-control reports. E. Warranties: Samples of special warranties. 1.5 CLOSEOUT SUBMITTALS A. Maintenance data. 1.6 QUALITY ASSURANCE A. Installer Qualifications: manufacturer. 1.7 An employer of workers trained and approved by WARRANTY A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace metal roof panel assemblies that fail in materials or workmanship within specified warranty period. 1. Warranty Period: 5 years from date of Substantial Completion. B. Special Warranty on Panel Finishes: Manufacturer's standard form in which manufacturer agrees to repair finish or replace metal roof panels that show evidence of deterioration of factory-applied finishes within specified warranty period. Metal Roof Panels Section 07410 Statement of Work V - 58 PMG Phase 1 Interim Action 1. Finish Warranty Period: 20 years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 PANEL MATERIALS A. Metallic-Coated Steel Sheet: Restricted flatness steel sheet metallic coated by the hot-dip process and prepainted by the coil-coating process to comply with ASTM A 755/A 755M. 1. Aluminum-Zinc Alloy-Coated Steel Sheet: ASTM A 792, Class AZ50 coating designation, Grade 40; structural quality. 2. Surface: Smooth, flat finish. 3. Concealed Finish: Manufacturer's standard white or light-colored acrylic or polyester backer finish. B. Panel Sealants: 1. Sealant Tape: Pressure-sensitive, 100 percent solids, gray polyisobutylene compound sealant tape with release-paper backing; 1/2 inch wide and 1/8 inch thick. 2. Joint Sealant: ASTM C 920; as recommended in writing by metal roof panel manufacturer. 3. Butyl-Rubber-Based, Solvent-Release Sealant: ASTM C 1311. 2.2 UNDERLAYMENT MATERIALS A. Self-Adhering, High-Temperature Sheet: 30 to 40 mils thick minimum, consisting of slip-resisting, polyethylene-film top surface laminated to layer of butyl or SBS-modified asphalt adhesive, with release-paper backing; cold applied. Provide primer when recommended by underlayment manufacturer. 1. Thermal Stability: Stable after testing at 240 deg F; ASTM D 1970. 2. Low-Temperature Flexibility: ASTM D 1970. Passes after testing at minus 20 deg F; 3. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Carlisle Coatings & Waterproofing Inc., Div. of Carlisle Companies Inc.; CCW WIP 300HT. b. Grace Construction Products; a unit of Grace, W. R. & Co.; Ultra. c. Henry Company; Blueskin PE200 HT. d. Metal-Fab Manufacturing, LLC; MetShield. e. Owens Corning; WeatherLock Metal High Temperature Underlayment. Metal Roof Panels Section 07410 Statement of Work V - 59 PMG Phase 1 Interim Action B. Felts: ASTM D 226, Type II (No. 30), asphalt-saturated organic felts. C. Slip Sheet: application. 2.3 Manufacturer's recommended slip sheet, of type required for MISCELLANEOUS MATERIALS A. Panel Fasteners: Self-tapping screws, bolts, nuts, self-locking rivets and bolts, end-welded studs, and other suitable fasteners designed to withstand design loads. Provide exposed fasteners with heads matching color of metal roof panels by means of plastic caps or factory-applied coating. Provide EPDM, PVC, or neoprene sealing washers. B. Bituminous Coating: Cold-applied asphalt mastic, SSPC-Paint 12, compounded for 15-mil dry film thickness per coat. Provide inert-type noncorrosive compound free of asbestos fibers, sulfur components, and other deleterious impurities. 2.4 STANDING-SEAM METAL ROOF PANELS A. General: Provide factory-formed metal roof panels designed to be installed by lapping and interconnecting raised side edges of adjacent panels with joint type indicated and mechanically attaching panels to supports using concealed clips in side laps. Include clips, cleats, pressure plates, and accessories required for weathertight installation. 1. Steel Panel Systems: Unless more stringent requirements are indicated, comply with ASTM E 1514. 2. Aluminum Panel Systems: Unless more stringent requirements are indicated, comply with ASTM E 1637. 3. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. AEP-Span. 4. Profile: Vertical-rib, snap-joint, as indicated on Drawings. 5. Material: Aluminum-zinc alloy-coated steel sheet, 0.028-inch nominal thickness. a. Exterior Finish: 2-coat fluoropolymer. 6. Clips: a. Material: Stainless steel. 7. Joint Type: As standard with manufacturer. 8. Panel Coverage: 16”. 9. Panel Height: 1½”. Metal Roof Panels Section 07410 Statement of Work 2.5 V - 60 PMG Phase 1 Interim Action METAL SOFFIT PANELS A. General: Provide factory-formed perforated metal soffit panels designed to be installed by lapping and interconnecting side edges of adjacent panels and mechanically attaching through panel to supports using concealed fasteners in side laps. Include accessories required for weathertight installation. B. Metal Soffit Panels: Match profile and material of metal roof panels. 1. Finish: Match finish and color of metal roof panels. 2. Sealant: Factory applied within interlocking joint. 3. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. AEP-Span. 4. Profile: Flush as indicated on Drawings. 5. Material: Same material, finish, and color as metal roof panels. 6. Sealant: Factory applied within interlocking joint. 2.6 ACCESSORIES A. Roof Panel Accessories: Provide components approved by roof panel manufacturer and as required for a complete metal roof panel assembly including trim, copings, fasciae, corner units, ridge closures, clips, flashings, sealants, gaskets, fillers, closure strips, and similar items. Match material and finish of metal roof panels unless otherwise indicated. 1. Closures: Provide closures at eaves and ridges, fabricated of same metal as metal roof panels. 2. Closure Strips: Closed-cell, expanded, cellular, rubber or crosslinked, polyolefin-foam or closed-cell laminated polyethylene; minimum 1-inchthick, flexible closure strips; cut or premolded to match metal roof panel profile. Provide closure strips where indicated or necessary to ensure weathertight construction. 3. Backing Plates: Provide metal backing plates at panel end splices, fabricated from material recommended by manufacturer. B. Flashing and Trim: Formed from same material as roof panels, prepainted with coil coating, minimum 0.018 inch thick. Provide flashing and trim as required to seal against weather and to provide finished appearance. Locations include, but are not limited to, eaves, rakes, corners, bases, framed openings, ridges, fasciae, and fillers. Finish flashing and trim with same finish system as adjacent metal roof panels. C. Gutters: Formed from same material roof panels. Match profile of gable trim, complete with end pieces, outlet tubes, and other special pieces as required. Metal Roof Panels Section 07410 Statement of Work V - 61 PMG Phase 1 Interim Action Fabricate in minimum 96-inch- long sections, of size and metal thickness according to SMACNA's "Architectural Sheet Metal Manual." Furnish gutter supports spaced a maximum of 36 inches O.C., fabricated from same metal as gutters. Provide wire ball strainers of compatible metal at outlets. Finish gutters to match metal roof panels. D. Downspouts: Formed from same material as roof panels. Fabricate in 10foot- long sections, complete with formed elbows and offsets, of size and metal thickness according to SMACNA's "Architectural Sheet Metal Manual." Finish downspouts to match gutters. 2.7 FABRICATION A. Fabricate and finish metal roof panels and accessories at the factory to greatest extent possible, by manufacturer's standard procedures and processes and as necessary to fulfill indicated performance requirements. Comply with indicated profiles and with dimensional and structural requirements. B. Provide panel profile, including major ribs and intermediate stiffening ribs, if any, for full length of panel. C. Fabricate metal roof panel side laps with factory-installed captive gaskets or separator strips that provide a tight seal and prevent metal-to-metal contact, in a manner that will seal weathertight and minimize noise from movements within panel assembly. D. Sheet Metal Accessories: Fabricate flashing and trim to comply with recommendations in SMACNA's "Architectural Sheet Metal Manual" that apply to the design, dimensions, metal, and other characteristics of item indicated. PART 3 - EXECUTION 3.1 PREPARATION A. Substrate Board: Install substrate boards over roof deck on entire roof surface. Attach with substrate-board fasteners. 1. Install substrate board with long joints in continuous straight lines, perpendicular to roof slopes with end joints staggered between rows. Tightly butt substrate boards together. B. Miscellaneous Framing: Install roof panel support members and anchorage according to metal roof panel manufacturer's written instructions. Metal Roof Panels Section 07410 Statement of Work 3.2 V - 62 PMG Phase 1 Interim Action UNDERLAYMENT INSTALLATION A. Self-Adhering Sheet Underlayment: Apply primer if required by manufacturer. Comply with temperature restrictions of underlayment manufacturer for installation. Apply at locations indicated on Drawings, wrinkle free, in shingle fashion to shed water, and with end laps of not less than 6 inches staggered 24 inches between courses. Overlap side edges not less than 3 1/2 inches. Roll laps with roller. Cover underlayment within 14 days. B. Felt Underlayment: Apply at locations indicated on Drawings, in shingle fashion to shed water, and with lapped joints of not less than 2 inches. C. Apply slip sheet over underlayment before installing metal roof panels. D. Install flashings to cover underlayment to comply with requirements specified in Division 07 Section "Sheet Metal Flashing and Trim." 3.3 METAL ROOF PANEL INSTALLATION A. Standing-Seam Metal Roof Panels: Fasten metal roof panels to supports with concealed clips at each standing-seam joint at location, spacing, and with fasteners recommended by manufacturer. 1. Install clips to supports with self-tapping fasteners. 2. Install pressure plates at locations indicated in manufacturer's written installation instructions. 3. Snap Joint: Nest standing seams and fasten together by interlocking and completely engaging factory-applied sealant. 4. Seamed Joint: Crimp standing seams with manufacturer-approved, motorized seamer tool so clip, metal roof panel, and factory-applied sealant are completely engaged. B. Metal Soffit Panels: Provide metal soffit panels full width of soffits. Install panels perpendicular to support framing. 1. Flash and seal panels with weather closures where metal soffit panels meet walls and at perimeter of all openings. 3.4 ACCESSORY INSTALLATION A. General: Install accessories with positive anchorage to building and weathertight mounting and provide for thermal expansion. Coordinate installation with flashings and other components. 1. Install components required for a complete metal roof panel assembly including trim, copings, ridge closures, seam covers, flashings, sealants, gaskets, fillers, closure strips, and similar items. Metal Roof Panels Section 07410 Statement of Work V - 63 PMG Phase 1 Interim Action 2. Flashing and Trim: Comply with performance requirements, manufacturer's written installation instructions, and SMACNA's "Architectural Sheet Metal Manual." Provide concealed fasteners where possible, and set units true to line and level as indicated. Install work with laps, joints, and seams that will be permanently watertight and weather resistant. 3. Provide elbows at base of downspouts to direct water away from building. 3.5 CLEANING A. Remove temporary protective coverings and strippable films, if any, as metal roof panels are installed unless otherwise indicated in manufacturer's written installation instructions. On completion of metal roof panel installation, clean finished surfaces as recommended by metal roof panel manufacturer. Maintain in a clean condition during construction. END OF SECTION Metal Roof Panels Section 07410 Statement of Work V - 64 PMG Phase 1 Interim Action SECTION 08110 - HOLLOW METAL DOORS AND FRAMES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standard hollow metal doors and frames. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: Include elevations, door edge details, frame profiles, metal thicknesses, preparations for hardware, and other details. C. Samples for Initial Selection: For units with factory-applied color finishes. D. Samples for Verification: For each type of exposed finish required. E. Schedule: Prepared by or under the supervision of supplier, using same reference numbers for details and openings as those on Drawings. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Ceco Door Products; an Assa Abloy Group company. 2. Steelcraft; an Ingersoll-Rand company. 2.2 MATERIALS A. Metallic-Coated Steel Sheet: ASTM A 653, Commercial Steel (CS), Type B; with minimum G60 metallic coating. B. Frame Anchors: ASTM A 591, Commercial Steel (CS), 40Z coating designation; mill phosphatized. 1. For anchors built into exterior walls, steel sheet complying with ASTM A 1008/ or ASTM A 1011, hot-dip galvanized according to ASTM A 153, Class B. Hollow Metal Doors and Frames Section 08110 Statement of Work C. Inserts, Bolts, and ASTM A 153/A 153M. V - 65 Fasteners: PMG Phase 1 Interim Action Hot-dip galvanized D. Bituminous Coating: Cold-applied asphalt mastic, compounded for 15-mil dry film thickness per coat. 2.3 according to SSPC-Paint 12, STANDARD HOLLOW METAL DOORS A. General: Comply with ANSI/SDI A250.8. 1. Design: Flush panel. B. Exterior Doors: Face sheets fabricated from metallic-coated steel sheet. Comply with ANSI/SDI A250.8 for level and model and ANSI/SDI A250.4 for physical performance level: 1. Level 2 and Physical Performance Level B (Heavy Duty), Model 1 (Full Flush). C. Hardware Reinforcement: ANSI/SDI A250.6. 2.4 STANDARD HOLLOW METAL FRAMES A. General: Comply with ANSI/SDI A250.8. B. Exterior Frames: Fabricated from metallic-coated steel sheet. 1. Fabricate frames with mitered or coped corners. 2. Fabricate frames as full profile welded unless otherwise indicated. 3. Frames for Level 2 Steel Doors: 16 gauge. C. Hardware Reinforcement: ANSI/SDI A250.6. 2.5 FRAME ANCHORS A. Jamb Anchors: 1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit frame size, not less than 0.042 inch thick, with corrugated or perforated straps not less than 2 inches wide by 10 inches long; or wire anchors not less than 0.177 inch thick. B. Floor Anchors: Formed from same material as frames, not less than 0.042 inch thick, and as follows: 1. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive fasteners. 2. Separate Topping Concrete Slabs: Adjustable-type anchors with extension clips, allowing not less than 2-inch height adjustment. Terminate bottom of frames at finish floor surface. Hollow Metal Doors and Frames Section 08110 Statement of Work 2.6 V - 66 PMG Phase 1 Interim Action FABRICATION A. Tolerances: Fabricate hollow metal work to tolerances indicated in SDI 117. B. Hollow Metal Doors: 1. Exterior Doors: Provide weep-hole openings in bottom of exterior doors. Seal joints in top edges of doors against water penetration. C. Hollow Metal Frames: Where frames are fabricated in sections, provide alignment plates or angles at each joint, fabricated of same thickness metal as frames. 1. Welded Frames: Weld flush face joints continuously; grind, fill, dress, and make smooth, flush, and invisible. 2. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed fasteners unless otherwise indicated. 3. Floor Anchors: Weld anchors to bottom of jambs and mullions with at least four spot welds per anchor. 4. Jamb Anchors: Provide number and spacing of anchors as follows: a. Masonry Type: Locate anchors not more than 18 inches from top and bottom of frame. Space anchors not more than 32 inches O.C. and as follows: 1) 2) Three anchors per jamb from 60 to 90 inches high. Four anchors per jamb from 90 to 120 inches high. D. Hardware Preparation: Factory prepare hollow metal work to receive templated mortised hardware according to the Door Hardware Schedule and templates furnished as specified in Division 08 Section "Door Hardware." 1. Locate hardware as indicated, or if not indicated, according to ANSI/SDI A250.8. 2. Reinforce doors and frames to receive nontemplated, mortised and surface-mounted door hardware. 3. Comply with applicable requirements in ANSI/SDI A250.6 and ANSI/DHI A115 Series specifications for preparation of hollow metal work for hardware. 4. Coordinate locations of conduit and wiring boxes for electrical connections with Division 26 electrical Sections. E. Stops and Moldings: Provide stops and moldings around glazed lites where indicated. Form corners of stops and moldings with butted or mitered hairline joints. 1. Single Glazed Lites: Provide fixed stops and moldings welded on secure side of hollow metal work. Hollow Metal Doors and Frames Section 08110 Statement of Work V - 67 PMG Phase 1 Interim Action 2. Multiple Glazed Lites: Provide fixed and removable stops and moldings so that each glazed lite is capable of being removed independently. 3. Provide fixed frame moldings on outside of exterior and on secure side of interior doors and frames. 4. Provide loose stops and moldings on inside of hollow metal work. 5. Coordinate rabbet width between fixed and removable stops with type of glazing and type of installation indicated. 2.7 STEEL FINISHES A. Prime Finish: Apply manufacturer's standard primer immediately after cleaning and pretreating. 1. Shop Primer: ANSI/SDI A250.10. B. Factory-Applied Paint Finish: ANSI/SDI A250.3. PART 3 - EXECUTION 3.1 INSTALLATION A. Hollow Metal Frames: Comply with ANSI/SDI A250.11. 1. Set frames accurately in position, plumbed, aligned, and braced securely until permanent anchors are set. After wall construction is complete, remove temporary braces, leaving surfaces smooth and undamaged. a. Where frames are fabricated in sections because of shipping or handling limitations, field splice at approved locations by welding face joint continuously; grind, fill, dress, and make splice smooth, flush, and invisible on exposed faces. b. Install frames with removable glazing stops located on secure side of opening. c. Install door silencers in frames before grouting. d. Remove temporary braces necessary for installation only after frames have been properly set and secured. e. Check plumbness, squareness, and twist of frames as walls are constructed. Shim as necessary to comply with installation tolerances. f. Field apply bituminous coating to backs of frames that are filled with grout containing antifreezing agents. 2. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor, and secure with postinstalled expansion anchors. a. Floor anchors may be set with powder-actuated fasteners instead of postinstalled expansion anchors if so indicated and approved on Shop Drawings. Hollow Metal Doors and Frames Section 08110 Statement of Work V - 68 PMG Phase 1 Interim Action 3. Masonry Walls: Coordinate installation of frames to allow for solidly filling space between frames and masonry with grout. 4. Installation Tolerances: Adjust hollow metal door frames for squareness, alignment, twist, and plumb to the following tolerances: a. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a line 90 degrees from jamb perpendicular to frame head. b. Alignment: Plus or minus 1/16 inch, measured at jambs on a horizontal line parallel to plane of wall. c. Twist: Plus or minus 1/16 inch, measured at opposite face corners of jambs on parallel lines, and perpendicular to plane of wall. d. Plumbness: Plus or minus 1/16 inch, measured at jambs at floor. B. Hollow Metal Doors: Fit hollow metal doors accurately in frames, within clearances specified below. Shim as necessary. 1. Non-Fire-Rated Standard Steel Doors: a. Jambs and Head: 1/8 inch plus or minus 1/16 inch. b. Between Edges of Pairs of Doors: 1/8 inch plus or minus 1/16 inch. c. Between Bottom of Door and Top of Threshold: Maximum 3/8 inch. d. Between Bottom of Door and Top of Finish Floor (No Threshold): Maximum 3/4 inch. 3.2 ADJUSTING AND CLEANING A. Final Adjustments: Check and readjust operating hardware items immediately before final inspection. Leave work in complete and proper operating condition. Remove and replace defective work, including hollow metal work that is warped, bowed, or otherwise unacceptable. B. Prime-Coat Touchup: Immediately after erection, sand smooth rusted or damaged areas of prime coat and apply touchup of compatible air-drying, rust-inhibitive primer. C. Metallic-Coated Surfaces: Clean abraded areas and repair with galvanizing repair paint according to manufacturer's written instructions. END OF SECTION Hollow Metal Doors and Frames Section 08110 Statement of Work V - 69 PMG Phase 1 Interim Action SECTION 08330 - OVERHEAD COILING DOORS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Service doors. B. Related Section: 1. Division 05 Section "Metal Fabrications" for miscellaneous steel supports. 1.2 PERFORMANCE REQUIREMENTS A. Structural Performance, Exterior Doors: Exterior overhead coiling doors shall withstand the wind loads, the effects of gravity loads, and loads and stresses within limits and under conditions indicated according to SEI/ASCE 7. 1. Wind Loads: Uniform pressure (velocity pressure) of 20 lbf/sq. ft. (960 Pa), acting inward and outward. B. Windborne-Debris-Impact-Resistance Performance: Provide impactprotective overhead coiling doors that pass missile-impact and cyclicpressure tests when tested according to ASTM E 1886 and ASTM E 1996. 1. Large Missile Test: (9.144 m) of grade. For overhead coiling doors located within 30 feet C. Seismic Performance: Overhead coiling doors shall withstand the effects of earthquake motions determined according to SEI/ASCE 7. 1.3 ACTION SUBMITTALS A. Product Data: accessory. For each type and size of overhead coiling door and B. Shop Drawings: For each installation and for special components not dimensioned or detailed in manufacturer's product data. Include plans, elevations, sections, details, and attachments to other work. 1. Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection. 2. Show locations of replaceable fusible links. 3. Wiring Diagrams: For power, signal, and control wiring. C. Samples: For each exposed product and for each color and texture specified. Overhead Coiling Doors Section 08330 Statement of Work 1.4 V - 70 PMG Phase 1 Interim Action INFORMATIONAL SUBMITTALS A. Seismic Qualification Certificates: For overhead coiling doors, accessories, and components, from manufacturer. B. Oversize Construction Certification: For door assemblies required being firerated and that exceed size limitations of labeled assemblies. 1.5 CLOSEOUT SUBMITTALS A. Maintenance Data. 1.6 QUALITY ASSURANCE A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved for both installation and maintenance of units required for this Project. B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. PART 2 - PRODUCTS 2.1 DOOR CURTAIN MATERIALS AND CONSTRUCTION A. Door Curtains: Fabricate overhead coiling-door curtain of interlocking metal slats, designed to withstand wind loading indicated, in a continuous length for width of door without splices. Unless otherwise indicated, provide slats of thickness and mechanical properties recommended by door manufacturer for performance, size, and type of door indicated, and as follows: 1. Metal Interior Curtain-Slat Facing: face. Match metal of exterior curtain-slat B. Bottom Bar for Service Doors: Consisting of two angles, each not less than 1-1/2 by 1-1/2 by 1/8 inch (38 by 38 by 3 mm) thick; fabricated from metal to match curtain slats and finish. C. Curtain Jamb Guides: Manufacturer's standard angles or channels and angles of same material and finish as curtain slats unless otherwise indicated, with sufficient depth and strength to retain curtain, to allow curtain to operate smoothly, and to withstand loading. Slot bolt holes for guide adjustment. Provide removable stops on guides to prevent over travel of curtain. 1. Removable Posts and Jamb Guides for Counter Doors: Manufacturer's standard. Overhead Coiling Doors Section 08330 Statement of Work 2.2 V - 71 PMG Phase 1 Interim Action HOOD A. General: Form sheet metal hood to entirely enclose coiled curtain and operating mechanism at opening head. Contour to fit end brackets to which hood is attached. Roll and reinforce top and bottom edges for stiffness. Form closed ends for surface-mounted hoods and fascia for any portion of between-jamb mounting that project beyond wall face. Equip hood with intermediate support brackets as required to prevent sagging. 1. Include automatic drop baffle on fire-rated doors to guard against passage of smoke or flame. 2. Exterior-Mounted Doors: Fabricate hood to act as weather protection and with a perimeter sealant-joint-bead profile for applying joint sealant. 2.3 LOCKING DEVICES A. Slide Bolt: Fabricate with side-locking bolts to engage through slots in tracks for locking by padlock, located on both left and right jamb sides, operable from coil side. 2.4 CURTAIN ACCESSORIES A. Weather seals: Equip each exterior door with weather-stripping gaskets fitted to entire perimeter of door for a weather tight installation, unless otherwise indicated. B. Push/Pull Handles: Equip each push-up-operated or emergency-operated door with lifting handles on each side of door, finished to match door. 2.5 COUNTERBALANCING MECHANISM A. General: Counterbalance doors by means of manufacturer's standard mechanism with an adjustable-tension, steel helical torsion spring mounted around a steel shaft and contained in a spring barrel connected to top of curtain with barrel rings. Use grease-sealed bearings or self-lubricating graphite bearings for rotating members. B. Brackets: Manufacturer's standard mounting brackets of either cast iron or cold-rolled steel plate. 2.6 MANUAL DOOR OPERATORS A. Equip door with manufacturer's recommended manual door operator unless another type of door operator is indicated. B. Push-up Door Operation: Design counterbalance mechanism that required lift or pull for door operation does not exceed 25 lbf (111 N). Overhead Coiling Doors Section 08330 Statement of Work V - 72 PMG Phase 1 Interim Action C. Chain-Hoist Operator: Consisting of endless steel hand chain, chain-pocket wheel and guard, and gear-reduction unit with a maximum 25 lbf (111 N) force for door operation. Provide alloy-steel hand chain with chain holder secured to operator guide. D. Crank Operator: Consisting of crank and crank gearbox, steel crank drive shaft, and gear-reduction unit, of type indicated. Size gears to require not more than 25 lbf (111 N) force to turn crank. Fabricate gearbox to be oil tight and to completely enclose operating mechanism. Provide manufacturer's standard crank-locking device. 2.7 DOOR ASSEMBLY A. Service Door: Overhead coiling door formed with curtain of interlocking metal slats. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Cookson Company. b. Overhead Door Corporation. c. Raynor. d. Wayne-Dalton Corp. B. Operation Cycles: Not less than 10,000. C. Door Curtain Material: Aluminum. D. Door Curtain Slats: Flat profile slats of 1-1/4-inch (32-mm). E. Curtain Jamb Guides: Aluminum with exposed finish matching curtain slats. Provide continuous integral wear strips to prevent metal-to-metal contact and to minimize operational noise. F. Hood: Match curtain material and finish. 1. Shape: Round. 2. Mounting: Face of wall. Overhead Coiling Doors Section 08330 Statement of Work V - 73 PMG Phase 1 Interim Action 3. G. Locking Devices: Equip door with slide bolt for padlock. 1. Locking Device Assembly: Both jamb sides locking bars, operable from inside with thumb turn. H. Manual Door Operator: Push-up operation. I. Door Finish: 1. Aluminum Finish: Mill. 2. Factory Prime Finish: Manufacturer's standard color. PART 3 - EXECUTION 3.1 INSTALLATION A. Install overhead coiling doors and operating equipment complete with necessary hardware, anchors, inserts, hangers, and equipment supports; according to manufacturer's written instructions and as specified. B. Fire-Rated Doors: Install according to NFPA 80. C. Smoke-Control Doors: Install according to NFPA 80 and NFPA 105. D. Adjust hardware and moving parts to function smoothly so that doors operate easily, free of warp, twist, or distortion. Lubricate bearings and sliding parts as recommended by manufacturer. Adjust seals to provide weather tight fit around entire perimeter. 3.2 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain overhead coiling doors. END OF SECTION Overhead Coiling Doors Section 08330 Statement of Work V - 74 PMG Phase 1 Interim Action SECTION 08630 - METAL-FRAMED SKYLIGHTS PART 1 - GENERAL 1.1 SUMMARY A. Section includes skylights with metal framing. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: For metal-framed skylights. sections, details, and attachments to other work. Include plans, elevations, C. Samples: For each type of exposed finish. D. Delegated-Design Submittal: For metal-framed skylights indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. 1.3 INFORMATIONAL SUBMITTALS A. Product test reports. B. Field quality-control reports. C. Warranties: Sample of special warranties. 1.4 QUALITY ASSURANCE A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved for installation of metal-framed skylights required for this Project. B. Structural-Sealant Glazing: Comply with recommendations in ASTM C 1401, "Guide for Structural Sealant Glazing," for joint design and quality-control procedures. 1.5 WARRANTY A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of metal-framed skylights that fail in materials or workmanship within specified warranty period. 1. Warranty Period: 10 years from date of Substantial Completion. Metal-Framed Skylights Section 08630 Statement of Work V - 75 PMG Phase 1 Interim Action B. Special Finish Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components on which finishes fail within specified warranty period. Warranty does not include normal weathering. 1. Warranty Period: 20 years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:: 1. Major Industries, Inc.; Auburn Skylights Division. 2. Wasco Products, Inc. 2.2 PERFORMANCE REQUIREMENTS A. General: Metal-framed skylights shall withstand the effects of the following without failure due to defective manufacture, fabrication, installation, or other defects in construction: 1. Structural loads. 2. Thermal movements. 3. Movements of supporting structure. 4. Dimensional tolerances construction. of support system and other adjacent 5. Failure includes, but is not limited to, the following: a. Deflection exceeding specified limits. b. Thermal stresses transferring to building structure. c. Framing members transferring stresses, including those caused by thermal and structural movements to glazing. d. Glazing-to-glazing contact. e. Noise or vibration created by wind and by thermal and structural movements. f. Loosening or weakening of fasteners, attachments, and other components. g. Sealant failure. B. Delegated Design: Design metal-framed skylights, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated. Metal-Framed Skylights Section 08630 Statement of Work V - 76 PMG Phase 1 Interim Action C. Structural Loads: 1. Wind Loads: As indicated on Drawings. 2. Seismic Loads: As indicated on Drawings. D. Deflection criteria of L/175 shall be maximum allowable under design load. E. Lateral Bracing of Framing Members: Compression flanges of flexural members are laterally braced by cross members with minimum depth equal to 50 percent of flexural member that is braced. Glazing does not provide lateral support. F. Air Infiltration: Provide metal-framed skylights with maximum air leakage through fixed glazing and framing areas of 0.06 cfm/sq. ft. of fixed wall area when tested according to ASTM E 283 at a minimum static-air-pressure difference of 6.24 lbf/sq. ft. G. Water Penetration under Static Pressure: Provide metal-framed skylights that do not evidence water penetration through fixed glazing and framing areas when tested according to ASTM E 331 at a minimum static-air-pressure difference of 20 percent of positive wind-load design pressure, but not less than 6.24 lbf/sq. ft. H. Thermal Movements: Provide metal-framed skylights that allow for thermal movements resulting from the following maximum change (range) in ambient and surface temperatures. Base engineering calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss. I. Condensation Resistance: Provide metal-framed skylights with fixed glazing and framing areas having condensation-resistance factor (CRF) of not less than 45 when tested according to AAMA 1503. J. Structural Sealant: Capable of withstanding tensile and shear stresses imposed without failing adhesively or cohesively. When tested for preconstruction adhesion and compatibility, cohesive failure of sealant shall occur before adhesive failure. 2.3 FRAMING SYSTEMS A. Aluminum: Alloy and temper recommended in writing by manufacturer for type of use and finish indicated. 1. Sheet and Plate: ASTM B 209. 2. Extruded Bars, Rods, Profiles, and Tubes: ASTM B 221. 3. Extruded Structural Pipe and Tubes: ASTM B 429. 4. Structural Profiles: ASTM B 308. Metal-Framed Skylights Section 08630 Statement of Work V - 77 PMG Phase 1 Interim Action B. Pressure Caps: Manufacturer's standard aluminum components that mechanically retain glazing. 1. Include snap-on aluminum trim that conceals fasteners. C. Brackets and Reinforcements: Manufacturer's standard high-strength aluminum with nonstaining, nonferrous shims for aligning skylight components. D. Fasteners and Accessories: Manufacturer's standard, corrosion-resistant, nonstaining, nonbleeding fasteners and accessories compatible with adjacent materials. 1. At pressure caps, use ASTM A 193/A 193M stainless-steel screws. 2. Use self-locking devices where fasteners are subject to loosening or turning out from thermal and structural movements, wind loads, or vibration. 3. Reinforce members as required to receive fastener threads. 4. Use exposed fasteners with countersunk Phillips screw heads. E. Anchor Bolts: ASTM A 307, Grade A, galvanized steel. F. Concealed Flashing: Manufacturer's standard, corrosion-resistant, nonstaining, nonbleeding flashing compatible with adjacent materials. G. Exposed Flashing and Closures: Manufacturer's standard aluminum components not less than 0.030 inch thick. H. Framing Gaskets: Manufacturer's standard. I. Framing Sealants: As recommended in writing by manufacturer. J. Corrosion-Resistant Coating: Cold-applied asphalt mastic. 2.4 GLAZING A. Glazing: As specified by manufacturer. B. Spacers, Setting Blocks, and Gaskets: Manufacturer's standard elastomeric types. C. Bond-Breaker Tape: Manufacturer's standard. D. Glazing Sealants: As recommended in writing by manufacturer. 1. Sealants used inside the weatherproofing system shall have a VOC content as indicated when calculated according to 40 CFR 59, Subpart D (EPA Method 24). Metal-Framed Skylights Section 08630 Statement of Work V - 78 PMG Phase 1 Interim Action 2. Sealants used inside the weatherproofing system shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers." 3. Structural Sealant: ASTM C 1184, neutral-curing silicone formulation compatible with system components with which it comes in contact, specifically formulated and tested for use as structural sealant, and approved by structural-sealant manufacturer for use in metal-framed skylights indicated. 4. Weatherseal Sealant: ASTM C 920 for Type S, Grade NS, Class 25, Uses NT, G, A, and O; neutral-curing silicone formulation compatible with structural sealant and other components with which it comes in contact; and recommended in writing by structural- and weatherseal-sealant and metal-framed skylight manufacturers for this use. 2.5 FABRICATION A. Fabricate aluminum components before finishing. B. Fabricate aluminum components that, when assembled, have the following characteristics: 1. Profiles that are sharp, straight, and free of defects or deformations. 2. Accurately fitted joints with ends coped or mitered. 3. Internal guttering systems or other means to drain water passing joints, condensation occurring within framing members, and moisture migrating within skylight to exterior. 4. Physical and thermal isolation of glazing from framing members. 5. Accommodations for thermal and mechanical movements of glazing and framing to maintain required glazing edge clearances. C. Fabricate aluminum sill closures with weep holes and for installation as continuous component. D. Reinforce aluminum components as required to receive fastener threads. E. Factory-Glazed, Metal-Framed Skylights: 1. Factory install glazing to comply with requirements in Division 08 Section "Glazing." 2. Prepare surfaces that will contact structural sealant according to structural-sealant manufacturer's written instructions to ensure compatibility and adhesion. Preparation includes, but is not limited to, cleaning and priming surfaces. F. After fabrication, clearly mark components to identify their locations in Project according to Shop Drawings. Metal-Framed Skylights Section 08630 Statement of Work 2.6 V - 79 PMG Phase 1 Interim Action ALUMINUM FINISHES A. Clear Anodic Finish: AAMA 611, or thicker. B. Color Anodic Finish: AAMA 611, or thicker. C. Baked-Enamel or Powder-Coat Finish: AAMA 2603 except with a minimum dry film thickness of 1.5 mils. 2.7 SOURCE QUALITY CONTROL A. Structural-Sealant Glazing: Perform quality-control procedures complying with ASTM C 1401 recommendations including, but not limited to, material qualification procedures, sealant testing, and fabrication reviews and checks. PART 3 - EXECUTION 3.1 INSTALLATION A. General: 1. Comply with manufacturer's written instructions. 2. Do not install damaged components. 3. Fit joints between aluminum components to produce hairline joints free of burrs and distortion. 4. Rigidly secure nonmovement joints. 5. Install anchors with separators and isolators to prevent metal corrosion and electrolytic deterioration and to prevent impeding movement of moving joints. 6. Seal joints watertight unless otherwise indicated. B. Metal Protection: Where aluminum will contact dissimilar materials, protect against galvanic action by painting contact surfaces with protective coating or by installing nonconductive spacers as recommended in writing by manufacturer for this purpose. C. Install continuous aluminum sill closure with weatherproof expansion joints and locked and sealed corners. Locate weep holes at rafters. D. Install components to drain water passing joints, condensation occurring within framing members, and moisture migrating within skylight to exterior. E. Install components plumb and true in alignment with established lines and elevations. 1. Structural-Sealant Glazing: Metal-Framed Skylights Section 08630 Statement of Work V - 80 PMG Phase 1 Interim Action a. Prepare surfaces that will contact structural sealant according to structural-sealant manufacturer's written instructions to ensure compatibility and adhesion. Preparation includes, but is not limited to, cleaning and priming surfaces. b. Install weatherseal sealant according to weatherseal-sealant manufacturer's written instructions to produce weatherproof joints. Install joint filler behind weatherseal sealant as recommended in writing by weatherseal-sealant manufacturer. F. Erection Tolerances: Install metal-framed skylights to comply with the following maximum tolerances: 1. Alignment: Limit offset from true alignment to 1/32 inch where surfaces abut in line, edge to edge, at corners, or where a reveal or protruding element separates aligned surfaces by less than 3 inches; otherwise, limit offset to 1/8 inch. 2. Location and Plane: Limit variation from true location and plane to 1/8 inch in 12 feet but no greater than 1/2 inch over total length. 3.2 FIELD QUALITY CONTROL A. Testing Agency: inspections. Engage a qualified testing agency to perform tests and 1. Water-Spray Test: Before installation of interior finishes has begun, skylights shall be tested according to AAMA 501.2 and shall not evidence water penetration. B. Repair or remove work where test results and inspections indicate that it does not comply with specified requirements. C. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements. D. Prepare test and inspection reports. END OF SECTION Metal-Framed Skylights Section 08630 Statement of Work V - 81 PMG Phase 1 Interim Action SECTION 08710 - DOOR HARDWARE PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Mechanical door hardware for the following: a. Swinging doors. B. Products furnished, but not installed, under this Section include the products listed below. Coordinating and scheduling the purchase and delivery of these products remain requirements of this Section. 1. Pivots, thresholds, weather stripping, and lock cylinders to be installed under other Sections. 2. Permanent lock cores to be installed by Owner. 1.2 ACTION SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: Details of electrified door hardware. C. Samples: For each exposed product and for each color and texture specified. D. Other Action Submittals: 1. Door Hardware Schedule: Prepared by or under the supervision of Installer, detailing fabrication and assembly of door hardware, as well as installation procedures and diagrams. Coordinate final door hardware schedule with doors, frames, and related work to ensure proper size, thickness, hand, function, and finish of door hardware. a. Content: Include the following information: 1) 2) 3) 4) Identification number, location, hand, fire rating, size, and material of each door and frame. Locations of each door hardware set, cross-referenced to Drawings on floor plans and to door and frame schedule. Complete designations, including name and manufacturer, type, style, function, size, quantity, function, and finish of each door hardware product. Description of electrified door hardware sequences of operation and interfaces with other building control systems. 2. Keying Schedule: Prepared by or under the supervision of Installer, detailing Owner's final keying instructions for locks. Door Hardware Section 08710 Statement of Work 1.3 V - 82 PMG Phase 1 Interim Action MAINTENANCE MATERIAL SUBMITTALS A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1.4 QUALITY ASSURANCE A. Installer Qualifications: Supplier of products and an employer of workers trained and approved by product manufacturers and an Architectural Hardware Consultant who is available during the course of the Work to consult with Contractor, Architect, and Owner about door hardware and keying. B. Keying Conference: Conduct conference at Project site with Owner and/or Engineer. 1.5 DELIVERY, STORAGE, AND HANDLING A. Deliver keys to manufacturer of key control system for subsequent delivery to Owner. B. Deliver keys to Owner by registered mail or overnight package service. 1.6 WARRANTY A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of door hardware that fail in materials or workmanship within specified warranty period. 1. Warranty Period: Three years from date of Substantial Completion, unless otherwise indicated. a. Manual Closers: 10 years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 SCHEDULED DOOR HARDWARE A. Provide door hardware for each door as scheduled on Drawings to comply with requirements in this Section. B. Designations: Requirements for design, grade, function, finish, size, and other distinctive qualities of each type of door hardware are indicated in Part 3 "Door Hardware Schedule" Article. Products are identified by using door hardware designations, as follows: 1. Named Manufacturers' Products: Manufacturer and product designation are listed for each door hardware type required for the purpose of Door Hardware Section 08710 Statement of Work V - 83 PMG Phase 1 Interim Action establishing minimum requirements. Manufacturers' abbreviated in Part 3 "Door Hardware Schedule" Article. names are 2. References to BHMA Designations: Provide products complying with these designations and requirements for description, quality, and function. 2.2 HINGES A. Hinges: BHMA A156.1. Provide template-produced hinges for hinges installed on hollow-metal doors and hollow-metal frames. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Baldwin Hardware Corporation. b. Bommer Industries, Inc. c. Cal-Royal Products, Inc. d. Hager Companies. e. IVES Hardware; an Ingersoll-Rand company. f. Lawrence Hardware Inc. g. McKinney Products Company; an ASSA ABLOY Group company. h. PBB, Inc. i. 2.3 Stanley Commercial Hardware; Div. of The Stanley Works. MECHANICAL LOCKS AND LATCHES A. Strikes: Provide manufacturer's standard strike for each lock bolt or latchbolt complying with requirements indicated for applicable lock or latch and with strike box and curved lip extended to protect frame; finished to match lock or latch. 1. Flat-Lip Strikes: For locks with three-piece antifriction latchbolts, as recommended by manufacturer. 2. Rabbet Front and Strike: Provide on locksets for rabbeted meeting stiles. B. Mortise Locks: BHMA A156.13; Grade 1; stamped steel case with steel or brass parts; Series 1000. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Accurate Lock & Hardware Co. b. Adams Rite Manufacturing Co.; an ASSA ABLOY Group company. c. Arrow USA; an ASSA ABLOY Group company. Door Hardware Section 08710 Statement of Work V - 84 PMG Phase 1 Interim Action d. Best Access Systems; Div. of Stanley Security Solutions, Inc. e. Cal-Royal Products, Inc. f. Corbin Russwin Architectural Hardware; an ASSA ABLOY Group company. g. Falcon Lock; an Ingersoll-Rand company. h. Marks USA. i. PDQ Manufacturing. j. SARGENT Manufacturing Company; an ASSA ABLOY Group company. k. Schlage Commercial Lock Division; an Ingersoll-Rand company. l. 2.4 Yale Security Inc.; an ASSA ABLOY Group company. LOCK CYLINDERS A. Lock Cylinders: Tumbler type, constructed from brass or bronze, stainless steel, or nickel silver. 1. Manufacturer: Same manufacturer as for locking devices. B. Construction Master Keys: Provide cylinders with feature that permits voiding of construction keys without cylinder removal. Provide 10 construction master keys. C. Construction Cores: Provide construction cores that are replaceable by permanent cores. Provide 10 construction master keys. 2.5 KEYING A. Keying System: Factory registered, complying with guidelines in BHMA A156.28, Appendix A. Incorporate decisions made in keying conference. 1. Master Key System: Change keys and a master key operate cylinders. 2. Grand Master Key System: Change keys, a master key, and a grand master key operate cylinders. 3. Great-Grand Master Key System: Change keys, a master key, a grand master key, and a great-grand master key operate cylinders. 4. Existing System: a. Master key or grand master key locks to Owner's existing system. b. Re-key Owner's existing master key system into new keying system. 5. Keyed Alike: Key all cylinders to same change key. B. Keys: Door Hardware Section 08710 Statement of Work V - 85 PMG Phase 1 Interim Action 1. Stamping: Permanently inscribe each key with a visual key control number and include the following notation: 2. Quantity: In addition to one extra key blank for each lock, provide the following: a. Cylinder Change Keys: Three. b. Master Keys: Five. 2.6 OPERATING TRIM A. Operating Trim: BHMA A156.6; stainless steel, unless otherwise indicated. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Burns Manufacturing Incorporated. b. Don-Jo Mfg., Inc. c. Forms + Surfaces. d. Hager Companies. e. Hiawatha, Inc. f. IVES Hardware; an Ingersoll-Rand company. g. Rockwood Manufacturing Company. h. Trimco. 2.7 MECHANICAL STOPS AND HOLDERS A. Wall- and Floor-Mounted Stops: bronze, or aluminum base metal. BHMA A156.16; polished cast brass, 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Architectural Builders Hardware Mfg., Inc. b. Baldwin Hardware Corporation. c. Burns Manufacturing Incorporated. d. Cal-Royal Products, Inc. e. Don-Jo Mfg., Inc. f. Door Controls International, Inc. g. Hager Companies. h. Hiawatha, Inc. i. Door Hardware IVES Hardware; an Ingersoll-Rand company. Section 08710 Statement of Work j. V - 86 PMG Phase 1 Interim Action Rockwood Manufacturing Company. k. Stanley Commercial Hardware; Div. of The Stanley Works. l. 2.8 Trimco. DOOR GASKETING A. Door Gasketing: BHMA A156.22; air leakage not to exceed 0.50 cfm per foot of crack length for gasketing other than for smoke control, as tested according to ASTM E 283; with resilient or flexible seal strips that are easily replaceable and readily available from stocks maintained by manufacturer. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Hager Companies. b. M-D Building Products, Inc. c. National Guard Products. d. Pemko Manufacturing Co.; an ASSA ABLOY Group company. e. Reese Enterprises, Inc. f. Sealeze; a unit of Jason Incorporated. g. Zero International. 2.9 THRESHOLDS A. Thresholds: BHMA A156.21; fabricated to full width of opening indicated. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Hager Companies. b. M-D Building Products, Inc. c. National Guard Products. d. Pemko Manufacturing Co.; an ASSA ABLOY Group company. e. Reese Enterprises, Inc. f. Rixson Specialty Door Controls; an ASSA ABLOY Group company. g. Sealeze; a unit of Jason Incorporated. h. Zero International. Door Hardware Section 08710 Statement of Work 2.10 V - 87 PMG Phase 1 Interim Action FABRICATION A. Fasteners: Provide door hardware manufactured to comply with published templates prepared for machine, wood, and sheet metal screws. Provide screws that comply with commercially recognized industry standards for application intended, except aluminum fasteners are not permitted. Provide Phillips flat-head screws with finished heads to match surface of door hardware, unless otherwise indicated. 1. Concealed Fasteners: For door hardware units that are exposed when door is closed, except for units already specified with concealed fasteners. Do not use through bolts for installation where bolt head or nut on opposite face is exposed unless it is the only means of securely attaching the door hardware. Where through bolts are used on hollow door and frame construction, provide sleeves for each through bolt. 2. Fire-Rated Applications: a. Steel Through Bolts: provided: 1) 2) 3) For the following unless door blocking is Surface hinges to doors. Closers to doors and frames. Surface-mounted exit devices. 3. Spacers or Sex Bolts: For through bolting of hollow-metal doors. 4. Fasteners for Wood Doors: Comply with requirements in DHI WDHS.2, "Recommended Fasteners for Wood Doors." 5. Gasketing Fasteners: Provide noncorrosive fasteners for exterior applications and elsewhere as indicated. 2.11 FINISHES A. Provide finishes complying with BHMA A156.18 as indicated in door hardware schedule. B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping. PART 3 - EXECUTION 3.1 INSTALLATION A. Steel Doors and Frames: For surface applied door hardware, drill and tap doors and frames according to ANSI/SDI A250.6. B. Mounting Heights: Mount door hardware units at heights indicated on Drawings unless otherwise indicated or required to comply with governing regulations. Door Hardware Section 08710 Statement of Work V - 88 PMG Phase 1 Interim Action 1. Standard Steel Doors and Frames: ANSI/SDI A250.8. 2. Custom Steel Doors and Frames: HMMA 831. C. Install each door hardware item to comply with manufacturer's written instructions. Where cutting and fitting are required to install door hardware onto or into surfaces that are later to be painted or finished in another way, coordinate removal, storage, and reinstallation of surface protective trim units with finishing work specified in Division 09 Sections. Do not install surfacemounted items until finishes have been completed on substrates involved. 1. Set units level, plumb, and true to line and location. Adjust and reinforce attachment substrates as necessary for proper installation and operation. 2. Drill and countersink units that are not factory prepared for anchorage fasteners. Space fasteners and anchors according to industry standards. D. Hinges: Install types and in quantities indicated in door hardware schedule but not fewer than the number recommended by manufacturer for application indicated or one hinge for every 30 inches of door height, whichever is more stringent, unless other equivalent means of support for door, such as spring hinges or pivots, are provided. E. Lock Cylinders: Install construction cores to secure building and areas during construction period. F. Key Control System: Tag keys and place them on markers and hooks in key control system cabinet, as determined by final keying schedule. G. Thresholds: Set thresholds for exterior doors and other doors indicated in full bed of sealant complying with requirements specified in Division 07 Section "Joint Sealants." H. Stops: Provide floor stops for doors unless wall or other type stops are indicated in door hardware schedule. Do not mount floor stops where they will impede traffic. I. Perimeter Gasketing: Apply to head and jamb, forming seal between door and frame. J. Door Bottoms: Apply to bottom of door, forming seal with threshold when door is closed. K. Adjustment: Adjust and check each operating item of door hardware and each door to ensure proper operation or function of every unit. Replace units that cannot be adjusted to operate as intended. Adjust door control devices to compensate for final operation of heating and ventilating equipment and to comply with referenced accessibility requirements. Door Hardware Section 08710 Statement of Work 3.2 V - 89 PMG Phase 1 Interim Action FIELD QUALITY CONTROL A. Independent Hardware Consultant: Owner will engage a qualified independent Hardware Consultant to perform inspections and to prepare inspection reports. END OF SECTION Door Hardware Section 08710 Statement of Work V - 90 PMG Phase 1 Interim Action SECTION 08900 - LOUVERS AND VENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Fixed, extruded-aluminum and formed-metal louvers. 2. Wall vents. 1.2 PERFORMANCE REQUIREMENTS A. Delegated Design: Design louvers, including comprehensive engineering analysis by a qualified professional engineer, using structural performance requirements and design criteria indicated. B. Structural Performance: Louvers shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated without permanent deformation of louver components, noise or metal fatigue caused by louver blade rattle or flutter, or permanent damage to fasteners and anchors. 1. Wind Loads: Drawings. Determine loads based on pressures as indicated on C. Louver Performance Ratings: Provide louvers complying with requirements specified, as demonstrated by testing manufacturer's stock units identical to those provided, except for length and width according to AMCA 500-L. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product indicated. 1. For louvers specified to bear AMCA seal, include printed catalog pages showing specified models with appropriate AMCA Certified Ratings Seals. B. Shop Drawings: For louvers and accessories. Include plans, elevations, sections, details, and attachments to other work. Show frame profiles and blade profiles, angles, and spacing. C. Samples: For each type of metal finish required. D. Delegated-Design Submittal: For louvers indicated to comply with structural performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. Louvers and Vents Section 08900 Statement of Work 1.4 V - 91 PMG Phase 1 Interim Action INFORMATIONAL SUBMITTALS A. Product Test Reports: Based on tests performed according to AMCA 500-L. PART 2 - PRODUCTS 2.1 MATERIALS A. Aluminum Extrusions: ASTM B 221, Alloy 6063-T5, T-52, or T6. B. Aluminum Sheet: ASTM B 209, Alloy 3003 or 5005 with temper as required for forming, or as otherwise recommended by metal producer for required finish. C. Galvanized-Steel Sheet: ASTM A 653 G60 zinc coating, mill phosphatized. D. Stainless-Steel Sheet: ASTM A 240/A 240M, Type 304, No. 4 finish. E. Fasteners: Use types and sizes to suit unit installation conditions. 1. For fastening aluminum, use aluminum or 300 series stainless-steel fasteners. 2. For fastening galvanized steel, use hot-dip-galvanized steel or 300 series stainless-steel fasteners. 3. For fastening stainless steel, use 300 series stainless-steel fasteners. 4. For color-finished louvers, use fasteners with heads that match color of louvers. F. Bituminous Paint: ASTM D 1187. 2.2 Cold-applied asphalt emulsion complying with FABRICATION, GENERAL A. Fabricate frames, including integral sills, to fit in openings of sizes indicated, with allowances made for fabrication and installation tolerances, adjoining material tolerances, and perimeter sealant joints. 2.3 WALL VENTS (BRICK VENTS) A. Extruded-Aluminum Wall Vents: 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Air Flow Company, Inc. b. Airolite Company, LLC (The). Louvers and Vents Section 08900 Statement of Work V - 92 PMG Phase 1 Interim Action c. Arrow United Industries; a division of Mestek, Inc. d. Construction Specialties, Inc. e. Dowco Products Group; Safe-Air of Illinois, Inc. f. Greenheck Fan Corporation. g. Hohmann & Barnard, Inc. h. Industrial Louvers, Inc. i. Louvers & Dampers, Inc.; a division of Mestek, Inc. j. Metal Form Manufacturing Inc. k. Nystrom Building Products. l. Reliable Products, Inc. m. Ruskin Company; Tomkins PLC. n. Sunvent Industries; Division of Sylro Sales Corp. o. United Enertech Corp. 2. Provide fixed and operable type louvers of size and design shown. 3. Hand crank operation: Hand crank operator activated by case hardened gears concealed in aluminum housing. Operators shall be removable and located at jambs. Provide one right-handed operator for each louver. 4. Extruded-aluminum louvers and frames, not less than 0.125-inch nominal thickness, assembled by welding; with 18-by-14- mesh, aluminum insect screening on inside face; incorporating weep holes, continuous drip at sill, and integral waterstop on inside edge of sill; of load-bearing design and construction. 2.4 ALUMINUM FINISHES A. Clear Anodic Finish: thicker. AAMA 611, AA-M12C22A41, Class I, 0.018 mm or B. Color Anodic Finish: AAMA 611, AA-M12C22A42/A44, Class I, 0.018 mm or thicker. 2.5 GALVANIZED-STEEL SHEET FINISHES A. Finish louvers after assembly. B. Surface Preparation: Clean surfaces with nonpetroleum solvent so surfaces are free of oil and other contaminants. After cleaning, apply a conversion coating suited to the organic coating to be applied over it. Clean welds, mechanical connections, and abraded areas and repair according to ASTM A 780. Louvers and Vents Section 08900 Statement of Work V - 93 PMG Phase 1 Interim Action C. Baked-Enamel or Powder-Coat Finish: Immediately after cleaning and pretreating, apply manufacturer's standard 2-coat, baked-on finish consisting of prime coat and thermosetting topcoat, with a minimum dry film thickness of 1 mil for topcoat. Comply with coating manufacturer's written instructions for applying and baking to achieve a minimum dry film thickness of 2 mils. PART 3 - EXECUTION 3.1 INSTALLATION A. Locate and place louvers and vents level, plumb, and at indicated alignment with adjacent work. B. Use concealed anchorages where possible. Provide brass or lead washers fitted to screws where required to protect metal surfaces and to make a weathertight connection. C. Provide perimeter reveals and openings of uniform width for sealants and joint fillers, as indicated. D. Repair damaged finishes so no evidence remains of corrective work. Return items that cannot be refinished in the field to the factory and refinish entire unit or provide new units. E. Protect galvanized and nonferrous-metal surfaces that will be in contact with concrete, masonry, or dissimilar metals from corrosion and galvanic action by applying a heavy coating of bituminous paint. END OF SECTION Louvers and Vents Section 08900 Statement of Work V - 94 PMG Phase 1 Interim Action SECTION 10520 - FIRE EXTINGUISHERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes portable, hand-carried fire extinguishers and mounting brackets for fire extinguishers. B. Owner-Furnished Material: Hand-carried fire extinguishers. 1.3 ACTION SUBMITTALS A. Product Data: For each type of product indicated. Include rating and classification, material descriptions, dimensions of individual components and profiles, and finishes for fire extinguisher and mounting brackets. B. Product Schedule: For fire extinguishers. Coordinate final fire extinguisher schedule with mounting bracket schedule to ensure proper fit and function. 1.4 INFORMATIONAL SUBMITTALS A. Warranty: Sample of special warranty. 1.5 CLOSEOUT SUBMITTALS A. Operation and Maintenance Data: maintenance manuals. 1.6 For fire extinguishers to include in QUALITY ASSURANCE A. NFPA Compliance: Fabricate and label fire extinguishers to comply with NFPA 10, "Portable Fire Extinguishers." B. Fire Extinguishers: Listed and labeled for type, rating, and classification by an independent testing agency acceptable to authorities having jurisdiction. 1. Provide fire extinguishers approved, listed, and labeled by FMG. C. Preinstallation Conference: Conduct conference at Project site. Fire Extinguishers Section 10520 Statement of Work V - 95 PMG Phase 1 Interim Action 1. Review methods and procedures related to fire extinguishers including, but not limited to, the following: a. Schedules and coordination requirements. 1.7 COORDINATION A. Coordinate type and capacity of fire extinguishers with fire protection cabinets to ensure fit and function. 1.8 WARRANTY A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace fire extinguishers that fail in materials or workmanship within specified warranty period. 1. Failures include, but are not limited to, the following: a. Failure of hydrostatic test according to NFPA 10. b. Faulty operation of valves or release levers. 2. Warranty Period: Six years from date of Substantial Completion. PART 2 - PRODUCTS 2.1 PORTABLE, HAND-CARRIED FIRE EXTINGUISHERS A. Fire Extinguishers: indicated. Type, size, and capacity for each mounting bracket 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Amerex Corporation. b. Ansul Incorporated; Tyco International Ltd. c. Badger Fire Protection; a Kidde company. d. Buckeye Fire Equipment Company. e. Fire End & Croker Corporation. f. J. L. Industries, Inc.; a division of Activar Construction Products Group. g. Kidde Residential and Commercial Division; Subsidiary of Kidde plc. h. Larsen's Manufacturing Company. i. Moon-American. j. Pem All Fire Extinguisher Corp.; a division of PEM Systems, Inc. k. Potter Roemer LLC. Fire Extinguishers Section 10520 Statement of Work l. V - 96 PMG Phase 1 Interim Action Pyro-Chem; Tyco Safety Products. 2. Valves: Manufacturer's standard. 3. Handles and Levers: Manufacturer's standard. 4. Instruction Labels: Include pictorial marking system complying with NFPA 10, Appendix B and bar coding for documenting fire extinguisher location, inspections, maintenance, and recharging. B. Pressurized, AFFF-Foam Type UL-rated 2-A:10-B:C, 2.6-gal. (10-L) nominal capacity, with AFFF foam in stainless-steel container; with pressure-indicating gage. 2.2 MOUNTING BRACKETS A. Mounting Brackets: Manufacturer's standard galvanized steel, designed to secure fire extinguisher to wall or structure, of sizes required for types and capacities of fire extinguishers indicated, with plated or red baked-enamel finish. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: a. Amerex Corporation. b. Ansul Incorporated; Tyco International Ltd. c. Badger Fire Protection; a Kidde company. d. Buckeye Fire Equipment Company. e. Fire End & Croker Corporation. f. J. L. Industries, Inc.; a division of Activar Construction Products Group. g. Larsen's Manufacturing Company. h. Potter Roemer LLC. B. Identification: Lettering complying with authorities having jurisdiction for letter style, size, spacing, and location. Locate as indicated by Architect. 1. Identify bracket-mounted fire extinguishers with the words "FIRE EXTINGUISHER" in red letter decals applied to mounting surface. a. Orientation: Horizontal. PART 3 - EXECUTION 3.1 EXAMINATION A. Examine fire extinguishers for proper charging and tagging. Fire Extinguishers Section 10520 Statement of Work 1. Remove and extinguishers. V - 97 replace damaged, PMG Phase 1 Interim Action defective, or undercharged fire B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. General: Install fire extinguishers and mounting brackets in locations indicated and in compliance with requirements of authorities having jurisdiction. 1. Mounting Brackets: 54 inches (1372 mm) above finished floor to top of fire extinguisher. B. Mounting Brackets: Fasten mounting brackets to surfaces, square and plumb, at locations indicated. END OF SECTION Fire Extinguishers Section 10520 Statement of Work V - 98 PMG Phase 1 Interim Action SECTION 14630 – WALL SUPPORTED STEEL BRIDGE CRANE PART 1 – GENERAL 1.1 SUMMARY C. Section includes: Wall mounted, steel bridge crane, runways, two (2) movable bridges each with a hoist trolley, and other accessories. D. Related sections: 1. Section 04220 – CONCRETE UNIT MASONRY: CMU walls to receive bridge crane tracks. 1.2 REFERENCES E. American Institute of Steel Construction (AISC): Manual of Steel Construction, Part 5, Specification for Structural Joints Using ASTM A325 or ASTM A490 Bolts. F. American National Standards Institute (ANSI): 1. ANSI B30.11 - Monorails and Underhung Cranes. G. American Society for Testing and Materials (ASTM) Publications: 1. ASTM A36 - Carbon Structural Steel. 2. ASTM A325 - Structural Bolts, Steel, Heat Treated, 120/150 ksi Minimum Tensile Strength. 3. ASTM A490 - Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength. H. American Welding Society (AWS): 4. AWS D1.1 - Structural Welding Code. I. Occupational Safety and Health Administration (OSHA): OSHA Specification 1910.179 - Overhead and Gantry Cranes. Wall-Supported Steel Bridge Crane Section 14630 Statement of Work V - 99 PMG Phase 1 Interim Action J. WAC 296-24-237 Construction, operation and maintenance-Chain and electric hoists. 1.3 PERFORMANCE REQUIREMENTS A. Crane shall provide coverage of rectangular area of size indicated on Drawings and consist of: 1. Two rigid, parallel runway tracks supported on and connected to exterior CMU wall structure. Cranes with more than two runways or with articulating runways are not acceptable. 2. Two rigid single girder bridges moving perpendicular to runways. Double girder bridges and ones with articulating or threaded connections are not acceptable. B. Modular, pre-engineered design: disassembly and relocation. Crane system shall be capable of C. Productivity ratio: Crane shall be designed to manually move load with maximum force of 1/100 load weight. D. Runway and bridge track: Enclosed type limiting dust and dirt collection on rolling surfaces with maximum deflection of 1/450 span based on capacity plus 15 percent for lifting device weight. E. Crane operating temperature: 5 to 200 degrees F. F. Crane shall be designed to withstand: 1. Crane and hoist dead load. 2. Live load capacity for entire system: 4000 pounds. Live load capacity per bridge equal to net rated hook load: 2000 pounds. 3. Inertia forces from crane and load movement. 1.4 SUBMITTALS A. Provide: 1. Product data for crane and accessories. Describe capacities, performance, operation, and applied forces to foundation. 2. Shop drawings showing crane construction and installation details. Wall-Supported Steel Bridge Crane configuration, dimensions, and Section 14630 Statement of Work V - 100 PMG Phase 1 Interim Action 3. Copy of warranty required by Paragraph 1.6 for review by Engineer. 4. Manufacturer's installation instructions. 5. Manufacturer's operation and maintenance manual. 1.5 QUALITY ASSURANCE A. Manufacturer: Company specializing in designing and manufacturing cranes with 25 years successful experience. B. Installer: Company experienced in assembly and installation of cranes with 5 years successful experience and acceptable to crane manufacturer. C. Crane shall be designed, fabricated, and installed in accordance with ANSI B30.11, and OSHA 1910.179. D. Base crane structural design includes full rated load capacity plus 15 percent for hoist and trolley weight and 25 percent impact factor for speed of lifting device and weight of tooling. E. Perform welding by certified operators in accordance with AWS D14.1. F. Bolted connections shall be in accordance with torque tightening procedures specified in AISC Manual, Part 5. G. Clearly label crane with rated load capacity. Place label at height and location easily read from floor level and loading position. 1.6 WARRANTY A. Provide: 1. 5 years warranty for crane to cover defects in materials and workmanship. PART 2 - PRODUCTS 2.1 ACCEPTABLE MANUFACTURERS A. Gorbel, Inc., P.O. Box 593, Fishers, New York 14453-0593; 800-828-0086; www.gorbel.com. 2.2 WALL SUPPORTED STEEL BRIDGE CRANE A. Type: Wall supported runway tracks, all-steel construction, bridge crane, two runways, two bridges moving perpendicular to runways, and equipped with Wall-Supported Steel Bridge Crane Section 14630 Statement of Work V - 101 PMG Phase 1 Interim Action enclosed track, hoist trolley, bumpers, and other accessories; Model No. 4000 lbs capacity GLCSL Trussed Steel Runways, 2000 lbs capacity 15’-0” Track Series Steel Bridge Assemblies as manufactured by Gorbel, Inc. B. Runway length: 19 feet 8 inches. C. Bridge length: 15 feet. D. Construction: Fabricate from ASTM A36 steel sections with finished ends and surfaces. 1. Support structure: Support crane runways from top chord of truss on exterior CMU wall structure. Cut bottom track to fit interior wall to wall dimension leaving vertical truss webs to remain as close to wall as possible (max 6”). 2. Runways: Model GLCSL Vierendeel truss fabricated from square steel tubes and enclosed steel track. a. Track: Enclosed, cold formed, steel box track which serves as bottom cord of runway and permits bridge assembly to ride on lower inside flanges. Fabricate lower running flanges with 2 degrees taper to center trolley within track. Flat, non-centering tracks are not acceptable. b. Splice joint: Splice joints are not acceptable. c. Runway Cantilevers: This is a simple span assembly, there are no cantilevers. 3. Bridge: Track Series Steel Trussed Bridge Assembly single girder, Vierendeel truss fabricated from rectangular steel tubes and enclosed steel box track. a. Track serves as bottom cord of bridge and permits hoist trolley to ride on lower inside flanges. b. Fabricate lower running flanges with 2 degrees taper to center trolley within track. Flat, non-centering tracks are not acceptable. 4. End trucks: Rigid frame end truck designed to ride inside enclosed runway track and connect to and suspend bridge. a. Construction: Stamped steel fabrication with both vertical and horizontal wheels to prevent binding in runway. Designs with welds in tension are not acceptable. Wall-Supported Steel Bridge Crane Section 14630 Statement of Work V - 102 PMG Phase 1 Interim Action b. Wheels: Removable, self-centering wheels with sealed lifetime lubricated bearings. Vertical wheels shall be tapered 2 degrees to match track profile. Non-removable or non-tapered wheels are not acceptable. Duracomp 4® wheel material is preferred. Steel wheels are not acceptable. c. Drop lugs: Provide on both sides of truck to limit truck drop to 1 inch maximum in event of wheel, axle, or load bar failure. d. Connection to the bridge: Provide a rigid connection between bridge and end truck. Articulating connections with threaded hardware are not acceptable. 5. Hoist trolley: Rigid-body trolley designed to ride inside enclosed track of bridge and carry hoist and load. Articulating trolleys are not acceptable. a. Construction: Two-piece stamped steel body with two wheels each side and tapered clevis positioning hoist hook at center of trolley so load weight is evenly distributed to all four trolley wheels. Provide removable clevis pin of type and size determined by manufacturer for specified capacity. Trolleys with non-removable clevis pins are not acceptable. b. Wheels: Removable, self-centering wheels with sealed lifetime lubricated bearings. Vertical wheels shall be tapered 2 degrees to match track profile. Non-removable or non-tapered wheels are not acceptable. Duracomp 4® wheel material is preferred. Steel wheels are not acceptable. . c. Drop lugs: Provide on both sides of trolley to limit trolley drop to 1 inch maximum in event of wheel, axle, or load bar failure. 6. End stops: Molded composite, resilient bumper installed in runway and bridge tracks to prevent end trucks and hoist trolley from rolling out of track. Bolt stops without energy absorbing bumper are not acceptable. 2.3 SHOP FINISHING A. Steam wash steel crane components with iron phosphate solution and apply baked enamel finish. Colors shall be: 4. Support assemblies and runways: Blue. 5. Bridges: Yellow. B. Provide spray cans of matching colors, air-drying paint for field touch-up. Wall-Supported Steel Bridge Crane Section 14630 Statement of Work V - 103 PMG Phase 1 Interim Action PART 3 - EXECUTION 3.1 PREPARATION A. Coordinate provision of crane with: 1. Design and construction of reinforced concrete masonry units as detailed on Drawings and specified in other sections. Ensure that tracks supported on walls have a minimum support length of not less than 6”. Connect to embed plates as detailed in drawings. B. Prior to installation: 1. Verify reinforced concrete masonry unit grout has cured 7 days minimum. Ensure that concrete masonry unit grout has cured 28 days minimum prior to using crane to full capacity. 2. Inventory parts. undamaged. 3.2 Verify all required components are available and INSTALLATION A. Install crane and accessories in accordance with manufacturer's instructions and shop drawings. B. Do not modify crane components in any manner without advance, written approval by crane manufacturer. C. Clearances for moving crane components: 1. 3 inch minimum vertical clearance from any overhead obstruction. 2. 2 inch minimum horizontal clearance from any lateral obstruction. D. Runways: Suspend runways on support structure. Attach as indicated on drawings. 1. Prior to applying proper welds, ensure runways are: a. Level to within plus or minus 1/8 inch. b. Parallel with opposite runway to within plus or minus 1/8 inch in 20 feet. 2. End stops: Bolt stops into runway track. E. Prior to installing bridge, use clean dry cloth to clean inside flanges of runway and bridge tracks. Wall-Supported Steel Bridge Crane Section 14630 Statement of Work V - 104 PMG Phase 1 Interim Action F. Bridge: Lift bridge with end trucks to runways and insert end trucks into open ends of runways. Roll bridge down length of runway. Verify and adjust for smooth travel. G. End stops: Bolt stops into runway track on the festooning end of runways. 3.3 FIELD QUALITY CONTROL A. Move bridge and hoist trolley through entire travel to ensure crane is clear of obstructions and moves freely and smoothly. B. Inspect installed crane. compressed. Verify all bolts are tight and lock washers fully C. Field test crane and accessories for operating functions. Ensure crane movement is smooth and proper. Adjust as required and correct deficiencies. D. Clean surfaces. If necessary, touch-up paint damage, scratches, and blemishes with manufacturer provided matching paint. E. Protect crane from other construction operations. 3.4 DEMONSTRATING AND TRAINING A. Provide demonstration and training session for Owner's representative covering operation and maintenance of free standing work station bridge crane. END OF SECTION Wall-Supported Steel Bridge Crane Section 14630 Statement of Work V - 105 PMG Phase 1 Interim Action SECTION 15060 - PIPE, FITTINGS, VALVES, AND SUPPORT PART 1 GENERAL 1.1 DESCRIPTION A. 1.2 1.3 1.4 1.5 Furnish, deliver, install, and test pipe, tubing, hose, fittings, valves, support, and accessories as shown on Drawings, as specified herein, and as required to completely interconnect equipment for complete and fully functional systems. SUBMITTALS A. Submit data to demonstrate conformance to Specifications requirements. B. Submit field functional and performance test results. QUALIFICATIONS A. Material and equipment furnished under this section shall be of a manufacturer who has been regularly engaged in design and manufacture of the material and equipment for at least 5 years. B. Material and equipment furnished under this section shall demonstrate to satisfaction of Engineer that the quality is equal to material and equipment made by manufacturer specifically named herein, if alternative manufacturer is proposed. DELIVERY, STORAGE, AND HANDLING A. Material and equipment shall be prepared and protected for shipment and shipped in accordance with manufacturer’s instructions. B. Openings and pipe ends shall be covered during shipment, storage, and handling. C. Pipe, fittings, and valves shall be handled in such a manner to prevent scratches, abrasions, impacts, and damage to any coatings. WARRANTY A. Supplier(s) of material and equipment shall warrant them to be free from defects in material and workmanship for at least 12 months from final acceptance. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 106 PMG Phase 1 Interim Action PART 2 PRODUCTS 2.1 GENERAL A. Pipe 1. Material and equipment shall be new, first quality, free from defects, and marked to identify material, manufacturer, and other appropriate data such as thickness for pipe. 2. Pipe and fitting sizes are nominal inside diameter unless otherwise noted. 3. Construct vents and drains using the same material specified for pipe system served by vents and drains, unless indicated otherwise. 4. Pipe and fittings for each type and size pipe system shall, if possible, be supplied by one manufacturer. 5. Acceptance of material shall be subject to strength and quality testing in addition to inspection of completed product. Acceptance of installed pipe systems shall also be based on inspection and leakage tests as specified herein. 6. Raised Face Flanges. When carbon-steel or stainless-steel flanges or flanged valves with raised face will be bolted directly to flat-faced flanged fittings or valves, the raised face shall be removed or spacers approved by the valve or pipe manufacturer shall be installed to allow bearing over 100 percent of the flange area. Some instruments may require raised face flanges. Coordinate and provide raised face flanges as required for process instrumentation. 7. Unless otherwise specified, all pipe systems shall have a nominal design pressure of 150 psig at 70 degrees Fahrenheit. 8. Pipe Markings. All pipe inside building, outside buildings, and in vaults shall be clearly marked with self-adhesive, pre-printed, water-proof labels (or equivalent) to indicate the fluid contained therein and the direction of flow. Markings shall be spaced no less than every 10 feet along the length of each interior pipe run between equipment terminations. For hoses placed within buried conduit, a stamped, stainless steel tag, secured with 18 gauge Type 304 stainless steel wire, shall be placed on each end of the hose to identify the fluid carried by the hose and a self-adhesive marker shall be attached to each end of the hose indicating the direction of flow and respective well number. Labels or tags shall be mounted in such a manner to facilitate operations or maintenance activity. Marking shall conform to the identification key presented on the Drawings. Specifically, pipes shall be marked as follows: Pipes from extraction wells to air stripper in treatment building shall be marked “Groundwater” Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work B. V - 107 PMG Phase 1 Interim Action Water pipes from stripper to outfall shall be marked “Treated Water” Potable water pipes from temporary water supply shall be parked “Potable Water” Air pipes (all) shall be marked “Air” Valves 1. Valves and accessories shall be new, first quality, and free from defects. Valves and accessories of a given type shall be from one manufacturer. 2. Valve sizes are nominal inside diameter unless otherwise specified. 3. Material and equipment shall be marked to identify material, manufacturer, and other appropriate data. 4. Acceptance of material shall be subject to strength and quality testing in addition to inspection of completed product. Acceptance of installed valve systems shall be based on inspection and leakage tests as specified herein. 5. Valves shall be furnished with operators, hand wheels, levers, or other suitable type wrench including handles as specified herein and as shown on Drawings. 6. If valves have flanges, flanges shall have ANSI 150 pound standard drilling. 7. Valve Markings. Valves shall be clearly marked with labels or tags to clearly identify open, closed, or flow direction (for 3-way valves). Labels or tags shall be mounted in such a manner to facilitate operations or maintenance activity. 2.2 PIPE AND FITTINGS A. HDPE. Pipe shall be manufactured from a PE 3608 resin listed with the Plastic Pipe Institute (PPI) as TR-4. The resin material will meet the specifications of ASTM D 3350 with a cell classification of 345464C. Pipe shall have a manufacturing standard of ASTM F 714. Pipe shall be SDR 11 (160 psi WPR) unless otherwise specified on the plans. The pipe shall contain no recycled compounds except that generated in the manufacturer's own plant from resin of the same specification from the same raw material. 1. Butt Fusion Fittings - Fittings shall be PE3608 HDPE, minimum cell classification of 345464C as determined by ASTM D 3350. Molded butt fusion fittings shall have a manufacturing standard of ASTM D 3261. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 108 PMG Phase 1 Interim Action Molded fittings shall have the same pressure rating as the pipe unless otherwise specified on the plans. 2. Electrofusion Fittings - Electrofusion fittings shall not be allowed. 3. Flanged and Mechanical Joint Adapters - Flanged and Mechanical Joint Adapters shall be PE 3608 HDPE, minimum cell classification of 345464C as determined by ASTM D 3350. Flanged and Mechanical Joint Adapters shall have a manufacturing standard of ASTM D 3261. Fittings shall have the same pressure rating as the pipe unless otherwise specified on the plans. B. Steel. Pipe shall be Schedule 40 galvanized or black carbon steel conforming to ASTM A 53, Type E or S, Grade B; API 5L, Grade B; or ASTM A 135, Grade B. Pipes shall be standard weight per ASME B36.10. 1. Steel fittings are defined as a special piece of pipe other than a normal straight section. 2. Elbows, crosses, tees, and reducers are fittings. 3. Fittings shall be butt-welded conforming to ASME B16.9. Material shall be wrought steel conforming to ASTM A 234, Grade WPB. Wall thickness shall be the same as the pipe. C. Polyvinyl choloride (PVC). Pipe shall be Schedule 80 PVC. 1. Unless otherwise specified or shown on the drawings, joints shall be either bell and spigot type with solvent cement bell and spigot. Pipe joints shall be watertight at the pressures specified. 2. Solvent cement joints for PVC pipe and fittings shall be made in accordance with ASTM D 2855 and appendices. 2.3 SUPPORTS A. General. The Contractor shall provide pipe hangers, brackets, saddles, clamps, and other supports, as necessary, to support all dead loads and live loads experienced by the piping and appurtenances. Pipe supports conforming to these requirements shall be supplied whether or not shown on the Drawings. Supports shall be provided at, but not limited to, points of change in direction, each side of valves and fittings, both sides of flexible joints, dead ends, and maximum spacing as defined by this specification. Pipe hangers, brackets, saddles, clamps, and other supports shall be adjustable-type conforming to the requirements of ANSI B31.1, and shall be shop-primed, including all bolts, nuts, and threaded parts. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 109 PMG Phase 1 Interim Action Hangers and supports shall include all hanging and supporting devices shown, specified, or required for pipe lines, apparatus, and equipment other than electrical equipment. The Contractor’s working drawings, as required herein, shall show quantity, type, design, and location of all hangers and supports required under the various Contract items. Hangers and supports shall be hot-dipped galvanized, unless otherwise noted. 1. Where specified or shown, bolts, stud bolts, rods, yokes, and nuts of hangers and supports shall be steel. Bolts shall not be less than 1/2inch in diameter unless otherwise called for on the Drawings. 2. Except where otherwise shown, specified, or required, hangers, supports, anchors, and concrete inserts shall be the standard types as manufactured by Crane Co., Grinnell Co., Fee and Mason manufacturing Co., or approved equal, meeting the requirements specified herein. B. Design. Hangers and supports shall be adequate to maintain the pipe lines, apparatus, and equipment in proper position and alignment under all operating conditions and have springs, where necessary. Where adjustment is noted or required, supports shall be screw-adjustable after installation. C. Supports for PVC Piping. Rigid plastic piping normally shall be supported by the same type of hangers and supports used with steel pipe, except that in no instance shall C-clamp, or other point-bearing supports, be allowed. Riser clamps, if required, shall be full-circumferential type only. Support spacing shall be based on the plastic pipe manufacturer’s recommendations for service conditions, but not more than those noted herein. D. Dissimilar Metals. Where pipe supports contact dissimilar metals, such as copper pipe, a nonconductive, nonabsorbent elastomeric pad of plastic or rubber shall be used to isolate the support from the pipe. E. Spacing of hangers and supports. Pipe support spacing requirements shall be as indicated on the Drawings or as specified by the pipe manufacturer. If not noted elsewhere, the spacing of pipe supports shall not exceed the following: Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 110 PMG Phase 1 Interim Action Maximum Unsupported Pipe Span (ft) PVC or Nominal Pipe Size (inches) Steel Fiberglass 1/2 5 4 3/4 6 4 1 7 4.33 1-1/4 7 4.33 1-1/2 9 4.66 2 10 4.66 2-1/2 11 4 3 12 4.25 2.4 2.5 4 14 5.8 6 17 6.33 8 19 7 10 22 9 12 23 10 14 16 25 27 11 12 SERVICE CONDITIONS A. Location: Everett, WA B. Installation: Below grade in conduit and vaults, above grade exposed, and inside building. C. Ground Water Temperature: 40 to 70 degrees Fahrenheit. D. Ambient Air Temperature Range: 15 to 90 degrees Fahrenheit. E. Relative Humidity of Ambient Air: 50 to 90 percent. PERFORMANCE REQUIREMENTS A. Material and equipment shall meet the following performance requirements when operating at service conditions listed in this section: 1. Material and equipment shall not corrode, deform, crack, become brittle, or otherwise become unserviceable. 2. Material and equipment shall not leak. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 111 PMG Phase 1 Interim Action 3. Material and equipment shall be chemically resistant for intended use. 2.6 SPECIALTIES A. 2.8 In-line instruments and controls. Install in-line instruments and controls specified in Division 17. PIPE INSULATION A. Contractor shall furnish and install closed cell, elastomeric pipe insulation, meeting the requirements of ASTM C-534, Type 1 (tubing) or Type 2 (sheets), ASTM D 1056, SCE 41, and UL 94-5V (Flammability Classification). Insulation shall be not less than 1/2-inch in thickness. Insulation shall cover pipes, fittings, valve bodies, and appurtenances of all outdoor exposed pipe runs, as shown on the drawings. PART 3 EXECUTION 3.1 GENERAL INSTALLATION A. Building Risers Pipes/Conduits: The final location of all conduit and piping risers (as shown on Drawings) in relationship to the building footprint shall be confirmed by the Engineer prior to construction of the building foundation. B. Well Riser Pipe: During the startup of the submersible pump, the torque developed by the motor causes unscrewing torque on right-hand threaded pipe. To safely withstand maximum unscrewing torque with minimum safety factor of 1.5, tighten all threaded joints on the riser pipe to at least 10 ft-lb. per motor horsepower (with a minimum torque load of 10 ft-lb). Wells EGW175 and EGW182 have pump motors with 5 hp, so well riser pipe joints should be tightened to a minimum torque-load of 50 ft-lb). The Contractor shall provide a calibrated torque wrench to verify installation of threaded riser pipe in accordance with these specifications. C. Pipe (General) 1. Install pipe, fittings, valves, recommended by manufacturer. supports, and accessories as 2. Inspect each item carefully before installation. Suspect material or equipment shall not be installed. 3. Cut pipe ends square, reamed, and deburred inside and out to provide a uniform, smooth surface for the jointing process. Remove chips and cutting fluids. 4. Thoroughly clean and dry joining surfaces of each pipe and fitting prior to making connection. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 112 PMG Phase 1 Interim Action 5. Place or erect pipe to accurate line and grade, and support, hang, or brace against movement as required for proper installation. 6. Tighten bolts, nuts, and fittings securely. 7. Reducing fittings shall be used where change in pipe size occurs. Bushings shall not be used unless reducing fittings are not available. Eccentric reducing fittings shall be used wherever necessary to provide for free drainage of pipes. 8. Unless otherwise shown on Drawings, install pipe parallel to structure lines, plumb, and level. 9. Install pipe without springing or forcing pipe in a manner that would set up stresses in pipe, fitting, or connected equipment. 10. Flanged fittings shall be true and perpendicular to axis of pipe. Bolt holes in flange shall straddle vertical centerline of pipe. 11. Where equipment drain connections are provided, they shall be valved, with the drain discharge pipe carried to the nearest floor drain, drain trench, or sump. Drain pipe and valve material shall conform to requirements of system served. 12. Anchor pipe subject to expansion and contraction so that strains are distributed. 13. Sleeves for branches through walls that are not secured with wall seals (if any) shall allow for free side motion of pipe in sleeves. 14. Where necessary to connect to tanks, pumps, and other equipment at the end of pipe runs or branches, materials to make such connections shall be in accordance with this section. 15. Where piping is secured flat to the ground and may be damaged by normal foot traffic, Contractor shall provide and install a protective ramp over the pipe, fabricated either from galvanized steel grating or from 1/4-inch thick galvanized “diamond-plate” steel. D. Valves 1. Inspect valves and accessories carefully before installation. Suspect material or equipment shall not be installed. 2. Remove dirt and foreign matter from valve interior prior to installation. 3. Thoroughly clean joints before joining. 4. Unless otherwise shown, install valves parallel to pipe lines and grades. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 113 PMG Phase 1 Interim Action 5. Snugly install screwed fittings and union nuts. 6. Orient valves to permit easy access to handles or operators and to avoid interference. E. Accessories 1. Install accessories recommendations. in accordance with manufacturer’s 2. Install accessories so parts are easily accessible for maintenance and operation. 3. Install union adjacent to each screwed end accessory. 4. Install valve below each pressure gauge unless otherwise specified. 3.2 PIPE INSTALLATION: SPECIFIC A. Pressurized HDPE Pipe - Fusion: 1. Exercise great care to prevent injury to or scoring of pipe during handling, transport, or storage. Pipe shall not be stored on rough ground. Damaged pipe and fittings shall be repaired or replaced at expense of Contractor at direction of Owner. 2. Place pipe within installation areas at least 24 hours prior to installation to permit temperature equalization. 3. Sections of HDPE pipe should be joined into continuous lengths on the jobsite above ground. The joining method shall be the butt fusion method and shall be performed in strict accordance with the pipe manufacturer's recommendations. The butt fusion equipment used in the joining procedures should be capable of meeting all conditions recommended by the pipe manufacturer, including, but not limited to, temperature requirements of 400-450 degrees Fahrenheit, alignment, and an interfacial fusion pressure of 75 PSI. The butt fusion joining will produce a joint with weld strength equal to or greater than the tensile strength of the pipe itself. 4. Sidewall fusions for connections to outlet piping shall be performed in accordance with HDPE pipe and fitting manufacturer’s specifications. The heating irons used for sidewall fusion shall have an inside diameter equal to the outside diameter of the HDPE pipe being fused. The size of the heating iron shall be ¼ inch larger than the size of the outlet branch being fused. 5. Mechanical joining will be used where the butt fusion method can not be used. Mechanical joining will be accomplished by either using a Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 114 PMG Phase 1 Interim Action HDPE flange adapter with a ductile iron back-up ring or HDPE Mechanical Joint adapter with a ductile iron back-up ring. 6. Socket fusion, hot gas fusion, threading, solvents, and epoxies will not be used to join HDPE pipe. 7. Flanged joints: Bolts and a gasket shall be installed at each flanged joint. Bolts, with washers on each end, shall be installed in each flange hole and nuts shall be tightened snugly. Bolts shall not be forced into place. B. PVC Pipe: 1. Exercise great care to prevent injury to or scoring of pipe during handling, transport, or storage. Pipe shall not be stored on rough ground. Damaged pipe and fittings shall be repaired or replaced at expense of Contractor at direction of Owner. 2. Bell and spigot/fitting joints: Reference marks shall be placed on the spigot/female ends to assist in determining when proper seating depth has been achieved within the joint. 3. Flanged joints: Bolts and a gasket shall be installed at each flanged joint. Bolts, with washers on each end, shall be installed in each flange hole and nuts shall be tightened snugly. Bolts shall not be forced into place. C. Steel Pipe: 1. Screwed joints: a. Coat male threads with joint lubricant seal compound Permatex No. 2, teflon tape or equal. b. Threaded joints shall have connections made metal to metal. 2. Flanged joints: Bolts and a gasket shall be installed at each flanged joint. Bolts, with washers on each end, shall be installed in each flange hole and nuts shall be tightened snugly. Bolts shall not be forced into place. 3. Welded Joints: a. Beveled ends for butt welding shall conform to ASME B16.25. Remove slag by chipping or grinding. Surfaces shall be clean of paint, oil, rust, scale, slag, and other material detrimental to welding. When welding the reverse side, chip out slag before welding. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 115 PMG Phase 1 Interim Action b. Apply full penetration weld to exterior joint of butt welded pipe, fittings, and welding neck flanges. Apply fillet welds to the interior and exterior circumference of the pipe and slip on flanges. Minimum size of fillet weld shall be equal to the steel cylinder thickness. Complete each pass around the entire circumference of the pipe before commencing the next pass. Use electrodes recommended by the pipe fabricator. Do not deposit more than 1/8-inch of throat thickness per pass. The minimum number of passes or beads in the completed weld shall be as follows: Steel Cylinder Thickness (inch) 0.2500 and Less Minimum Number of Passes for Welded Joints 2 Greater than 0.2500 3 c. Use the shielded metal arc welding (SMAW) process for welding. d. Limitations on imperfections in welds shall conform to the requirements in ASME B31.3, Table 341.3.2, and paragraph 341.4 for visual examination. e. Clean each layer of deposited weld metal prior to depositing the next layer of weld metal, including the final pass, by a power-driven wire brush. f. After shop fabrication and prior to shop applied linings and coatings, test each welded joint by the liquid penetrant method. Conform to the requirements specified in ASTM E 165. The materials used shall be either water washable or nonflammable. g. Chip out all defects, reweld, and retest the section affected until it shows no leaks or other defects. D. Hose and Tubing: 1. Install hose and tubing without twists, kinks, excessive bends, or tension. 2. Snugly tighten hose clamps used to secure hose ends. 3.3 CLEANING A. Prior to testing, thoroughly clean inside of each completed pipe system and remove dirt, loose scale, sand, and other foreign material. Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work 3.4 V - 116 PMG Phase 1 Interim Action B. Clean by sweeping, flushing with water, or blowing with compressed air. C. Install temporary strainers, temporarily disconnect equipment, or take other appropriate measures to protect equipment while cleaning pipe and to access otherwise inaccessible areas. FIELD TESTS A. Prior to system startup, pipe and fittings described herein will be inspected by the Engineer for function and for proper level, alignment, and connection. Additional performance tests shall be performed by Contractor as described below: B. Pressurized Liquid Systems – Test for leakage by completely filling with water and pressurizing to 100 psig. Monitor pressure and temperature, and verify reduction in pressure of less than 0.5 psig over 4-hour period when accounting for temperature change of the pressurized fluid. Modify or replace components that fail to meet required performance. Repeat leakage tests until conformance to leakage test requirements specified herein have been fulfilled. C. Gravity Drain Liquid Systems - Test for leakage by completely filling with water to highest point. Monitor water level and verify leakage rate of less than 0.02 gallon per hour per inch diameter per 100 ft of line. Tests shall be conducted over a 24-hour period. Modify or replace components that fail to meet required performance. Repeat leakage tests until conformance to leakage test requirements specified herein have been fulfilled. D. Performance Test (Air Stripper Vent Ducting) – Test air discharge line downstream (on pressure side of blower) for leakage by soaping all ducting within the building while air stripper is operational and examining closely for bubbles. Repair any leaks found and retest. E. Temporarily disconnect gauges or other equipment, or take other appropriate measures to protect equipment from excessive pressure during performance testing. Clean up any water leaked during unsatisfactory testing and repair damage to any material or equipment caused by pressure testing. END OF SECTION Pipe, Fittings, Valves, and Supports Section 15060 Statement of Work V - 117 PMG Phase 1 Interim Action SECTION 15160 - WELL EQUIPMENT PART 1 GENERAL 1.1 DESCRIPTION A. 1. 2 1. 3 General. Provide those materials not provided by the Owner. Install well pumping equipment complete, as indicated on the Drawings and specified herein and appurtenances as necessary to form a complete, installed and operational system. RELATED SECTIONS A. Section 02605: Vaults B. Section 15060: Pipe, Fittings, Valves, and Pipe Supports C. Section 17000: Instrumentation, Control, and Monitoring SUBMITTALS A. Submit system field performance test results. B. Submit all manufacturer’s operations and maintenance manuals, bulletins, spare parts lists, and warranties for equipment supplied by Contractor. PART 2 PRODUCTS 2.1 SUBMERSIBLE PUMPS A. General. Contractor shall provide all associated materials and fittings necessary to construct a complete operating system. B. The submersible electric groundwater extraction pump shall be in accordance with the Drawings. C. Pump shall be manufactured by Grundfos Pumps Corporation. Pump motors shall be manufactured by Franklin Electric. Pump motor size shall be 4-inch, not 6-inch. All wetted components of pumps, pump motors, and motor leads shall be compatible with TCE concentrations up to 20 ppm. Submersible pumps shall be secured with a safety cable. Well Equipment Section 15160 Statement of Work V - 118 PMG Phase 1 Interim Action PART 3 EXECUTION 3.1 INSTALLATION AND START-UP A. 3.2 SYSTEM DESCRIPTION - EXTRACTION PUMP A. 3. 3 Test, startup, and adjust the well equipment. The theory of operation and control system for the groundwater pumping system is provided in Section 17000. EQUIPMENT TESTING A. Field Testing 1. Following completion of the installation and satisfactory start-up of the equipment, the Contractor shall operate each pumping unit to confirm operation in accordance with manufacturer’s recommendations and these specifications. 2. Perform system operational demonstrations and system validation tests in conjunction with the requirements of Section 17000. END OF SECTION Well Equipment Section 15160 Statement of Work V - 119 PMG Phase 1 Interim Action SECTION 15400 - TREATMENT EQUIPMENT PART I GENERAL 1.1 DESCRIPTION A. 1.2 1.3 1.4 RELATED SECTIONS A. Section 15060: Pipe, Fittings, Valves, and Support B. Section 17000: Instrumentation, Control, and Monitoring SUBMITTALS A. Submit functional and performance test results. B. Submit all manufacturer’s operations and maintenance manuals, bulletins, spare parts lists, and warranties for equipment supplied by Contractor. QUALIFICATIONS A. 1.5 Treatment equipment furnished under this section shall be of a manufacturer who has been regularly engaged in design and manufacture of the material and equipment for at least 5 years. DELIVERY, STORAGE, AND HANDLING A. 1.6 Furnish (equipment not provided by Owner), deliver, install, test, and startup treatment equipment as shown on the Drawings, as specified herein, and as required to provide a complete and fully functional treatment process. Equipment and materials furnished under this section shall be prepared and protected for shipment, shipped, and stored until installation per manufacturers’ instructions. GUARANTEE AND WARRANTY A. Suppliers of equipment shall guarantee performance at design conditions. B. Suppliers of equipment and material shall warrant them free of defects in material and workmanship for at least 12 months from initial acceptance. Treatment Equipment Section 15400 Statement of Work V - 120 PMG Phase 1 Interim Action PART 2 PRODUCTS 2.1 GENERAL A. 2.2 2.3 Equipment and materials furnished under this section shall be new. SERVICE CONDITIONS A. Location: Everett, WA B. Installation: Groundwater treatment system sheltered in heated (above 40°F) building. C. Groundwater Temperature: 40 to 70 degrees Fahrenheit. D. Ambient Air Temperature Range: 15 to 90 degrees Fahrenheit. E. Relative Humidity of Ambient Air: 40 to 90 percent PERFORMANCE REQUIREMENTS A. Material and equipment shall meet the following performance requirements when operating at service conditions listed in this section: 1. Material and equipment shall not corrode, deform, crack, become brittle, or otherwise become unserviceable. 2. Material and equipment shall not leak. 3. Material and equipment shall be chemically resistant for intended use. 2.4 SPECIFIC EQUIPMENT A. Air Stripper – Contractor shall coordinate with Engineer and Owner to arrange for delivery of air stripper package from current location in Kent, Washington to new treatment building. Contractor shall pay for all delivery costs. B. Blower – Contractor shall coordinate with Engineer and Owner to arrange for delivery of air stripper package from current location in Kent, Washington to new treatment building. Contractor shall pay for all delivery costs. Treatment Equipment Section 15400 Statement of Work 2.5 PMG Phase 1 Interim Action C. Moisture Separator – Supply unit meeting specifications in Drawings. D. Duct Heater – Supply unit meeting specifications in Drawings. E. Granular Activated Carbon Vessels and Manifold – Supply units meeting specifications in Drawings. TREATMENT SYSTEM BUILDING A. 2.6 V - 121 Contactor shall provide materials and construct new treatment system building per Drawings. Building shall be furnished with locks and shall supply Owner with a minimum of four (4) sets of keys. OTHER EQUIPMENT A. Contractor shall provide all associated electrical, piping, and support equipment even if not specifically included in the drawings or referenced in the specifications, as necessary to provide a fully functional and secure system. B. Contractor shall provide a bridge crane work station system with two mobile bridges per the Drawings. C. Contractor shall provide a temporary water system per the Drawings. D. Contractor shall provide an emergency eyewash/shower station per the Drawings and a hose with hose reel to be mounted inside the treatment system building. PART 3 EXECUTION 3.1 EQUIPMENT INSTALLATION A. Install and connect the treatment system equipment (i.e., air stripper, blower, discharge/transfer pump, temporary holding tank, moisture knockout, duct heater, granular activated carbon vessels); associated piping, ducts, conduits, valves, meters; and building and system appurtenances (i.e., control panels, sump pump, temporary water supply equipment, emergency eyewash and shower) as shown on the Drawings. Because treatment system equipment dimensions may vary from those shown in the Construction Drawings, Engineer shall be consulted on final placement of equipment and associated piping, ducts, and conduits. Treatment Equipment Section 15400 Statement of Work 3.2 V - 122 PMG Phase 1 Interim Action B. Provide and install all interconnecting piping between equipment. Contractor may use structural elements of the building shell to support piping and conduit, provided such support does not exceed building design loads. C. Install all equipment in a manner that allows access to all equipment for operations, maintenance, and monitoring. Contractor shall route pipes to minimize obstruction to foot traffic, and mount pipes to walls in an orderly manner such that valves, sampling ports, and gauges are easily accessible. TESTING A. Functional Tests 1. Perform equipment functional tests per manufacturer’s instructions. B. B. Performance Tests 1. Perform equipment performance tests per manufacturer’s instructions. 2. Perform integrated performance tests per Division 17. END OF SECTION Treatment Equipment Section 15400 Statement of Work V - 123 PMG Phase 1 Interim Action SECTION 17000 - GENERAL INSTRUMENTATION, CONTROL, AND MONITORING REQUIREMENTS PART 1 GENERAL 1.1 1.2 1.3 DESCRIPTION A. This section covers general requirements for furnishing instrumentation, control, and monitoring (ICM) systems complete in every detail for purposes specified and specifies primary elements of process instrumentation, auxiliary equipment and supplies directly related to installation and operation of these primary elements. B. Furnish equipment, material, supplies, and special tools and install ICM system. Ensure conduit runs, signal, and power wiring is consistent with requirements of equipment specified in this section. Perform operational testing of individual systems and complete start up of systems as indicated on Drawings and as specified herein. C. Set up and program Programmable Logic Controllers (PLC) required operational, alarm, and shutdown functions per the Drawings and standard and emergency system operating conditions. RELATED SECTIONS A. Section 15060: Pipe, Fittings, Valves, and Support B. Section 15400: Treatment Equipment C. Section 17700: System Operating Description. QUALITY ASSURANCE A. Manufacturer. Instrumentation and control equipment furnished by Contractor shall be manufactured by a firm regularly and currently engaged in design and manufacture of similar equipment for at least the past 5 years. Equipment furnished shall be new and of current design. B. Equipment/materials of the same type shall be products of the same manufacturer. Capacities of equipment shall not be less than that indicated on Drawings or in Specifications. C. Material and equipment furnished under this section for which an alternative manufacturer is proposed shall be demonstrated to the satisfaction of the Engineer that the quality is equal to the materials and equipment made by the manufacturer specifically named herein. General Instrumentation, Control, and Monitoring Requirements Section 17000 Statement of Work 1.4 General. Contractor shall submit for review and approval shop drawings, material lists, instrument installation and instruction manuals, and other pertinent information to allow verification of compliance with the requirements of this section. Submittals shall be assembled and identified by the specific equipment tag numbers for the primary elements required for this project. DELIVERY, STORAGE, AND HANDLING A. 1.6 PMG Phase 1 Interim Action SUBMITTALS A. 1.5 V - 124 Material and equipment provided by Contractor shall be delivered, stored, and handled in accordance with manufacturer's instructions. GUARANTEE AND WARRANTIES A. Guarantee all Work of Division 17. With respect to instruments and equipment provided by Contractor, guarantee shall cover: 1. Faulty or inadequate design. 2. Improper assembly or erection (includes equipment provided by Owner). 3. Defective workmanship or materials. 4. Leakage, breakage, or other failure not caused by Owner misuse. For equipment bearing manufacturer’s warranty in excess of one year, furnish copy of warranty to Owner with Owner named as beneficiary. PART 2 PRODUCTS 2.1 PRESSURE GAUGES/TRANSMITTERS A. Gauges - Provide for wellheads and in-line pipe vaults (water), blower intake (air), and GAC vessel manifold (air) per Drawings or approved equivalent. Pressure range shall be as shown on the Drawings. Accuracy shall be a minimum of ANSI Grade B (±2 percent of full scale) and shall have dial size of 2-1/2 inches. Gauges shall have a stem mounting, bottom connection. Connections for all gauges shall be 1/4 inch NPT with square wrench flats. Wetted parts shall be corrosion resistant. Cases shall be corrosion resistant and weather proof. B. Transmitter - Provide for wellhead (water) and blower intake (air) per Drawings or approved equivalent. Transmitter shall be compatible with PLC. General Instrumentation, Control, and Monitoring Requirements Section 17000 Statement of Work 2.2 2.3 2.4 A. Water - Provide for wellheads (well discharge conveyance line in vault) and treatment system (intake manifold and discharge to outfall) per Drawings. Flow rate range shall be as shown on the Drawings. Accuracy shall be a maximum ± 1% of measurement over full scale. Flow Display shall have non-resettable totalizer display with indication to ± 1 gallon. Hermetically sealed and waterproof register to prevent condensation or fogging of display. Meter shall transmit output signal compatible with PLC. B. Air - Provide for stripper intake per Drawings or approved equivalent. Flow rate range shall be as shown on the Drawings. Accuracy shall be a maximum ± 1% of measurement over full scale. Flow Display shall have non-resettable totalizer display with indication to ± 1 scfm. Hermetically sealed and waterproof register to prevent condensation or fogging of display. Meter shall transmit output signal compatible with PLC. TEMPERATURE GAUGES/TRANSMITTERS A. Thermometer - Provide for air stripper intake and pre-duct heater per Drawings. Provide compatible thermowell for pressure application at preduct heater location. Temperature range shall be as shown on the Drawings. Accuracy shall be a maximum ± 1 degree Fahrenheit. B. Transmitter – Provide temperature transmitter for post-duct heater per Drawings. Transmitter shall be compatible with PLC. LEVEL TRANSMITTERS/SWITCHES Provide for wells, well vaults, air stripper clearwell, building sump, and holding tank per Drawings. Transmitters shall be compatible with PLC. MOUNTINGS A. 2.6 PMG Phase 1 Interim Action FLOW METERS/TRANSMITTERS A. 2.5 V - 125 Mount and install equipment as indicated. Where not shown, mount field instruments, according to best standard practice, on pipe mounts, pedestal mounts, wall mounts, or other similar means in accordance with supplier’s recommendation. INSTRUMENTATION AND CONTROL A. Instrumentation and control including PLC, control panels, and autocommunications, and user interface, to be provided per Drawings. General Instrumentation, Control, and Monitoring Requirements Section 17000 Statement of Work V - 126 PMG Phase 1 Interim Action PART 3 EXECUTION 3.1 INSPECTION A. 3.2 PREPARATION A. 3.3 3.4 Inspect each instrument and piece of equipment for damage, defects, completeness, and correct operation before installing. Ensure that installation areas are clean and that concrete or other structural operations are completed prior to installing instruments and equipment. Maintain areas in a clean condition during installation operations. INSTRUMENT INSTALLATION, CALIBRATION, AND PROGRAMMING A. Install, connect, calibrate, and functionally test each instrument and related components per manufacturer’s instructions and the Drawings. Instruments and controls shall be installed by, or under the oversight of, a professional electrical systems engineer or technician familiar with remediation system PLC. B. The PLC system and controls shall be programmed by the electrical systems engineer/technician. A logic ladder and a user interface conceptual design, upon which the PLC programming will be based, shall be developed by the electrical system engineer in consultation with the Engineer. The logic ladder shall at a minimum incorporate the system operating conditions described in Section 17400. SYSTEM VALIDATION A. General. Perform system validation of full system including ICM system and including all vendor provided equipment. B. Verify all system switches and shutdowns. Cause malfunctions to sound alarms, or switch to standby, to check system operation. Check systems thoroughly for correct operation. C. Perform system startup and operation for initial “shakedown” period in cooperation with Engineer. At a minimum this system testing shall include, but not be limited to: 1. Potable water shall be used to fill various system components in the treatment building (e.g., air stripper, sump, moisture knockout, temporary holding tank) to test system controls, alarms, and shutoffs). System valves will be configured to test operation and transfer of water in several configurations: General Instrumentation, Control, and Monitoring Requirements Section 17000 Statement of Work V - 127 PMG Phase 1 Interim Action a. Transfer from stripper to sewer outfall (simulated standard operating conditions) b. Transfer from stripper to temporary holding tank c. Transfer from temporary holding tank to stripper (simulated retreatment). 2. Observing startup and short term of continuous operation of blower (e.g., at least 1 hour). 3. Observing startup and short term of continuous operation of each well pump (e.g., at least 10 minutes each). Pumps shall be run independently without other pumps in operation and with all pumps operating simultaneously. The air stripper and blower shall be run simultaneously with discharge routed to temporary holding tank(s). D. During each of these tasks, system components, vaults, valves, meters, piping, ducts, etc. shall be observed for leaks and malfunctions. E. Immediately correct defects and malfunctions disclosed by tests. Use new parts and material as required and approved, and retest. Provide report certifying completion of validation of each instrument system. Report shall indicate calculated system tolerances, verification that system meets these tolerances, and any provisional settings made to devices. F. Testing shall be observed by Engineer. Notify Engineer in writing a minimum of 48 hours prior to proposed date for commencing test. END OF SECTION General Instrumentation, Control, and Monitoring Requirements Section 17000 Statement of Work V - 128 PMG Phase 1 Interim Action SECTION 17700 – SYSTEM OPERATING DESCRIPTION PART 1 GENERAL 1.1 DESCRIPTION A. 1.2 1.3 1.4 This section describes functional requirements of and process for instrumentation, control, and monitoring systems. RELATED SECTIONS A. Section 15400: Treatment Equipment B. Section 17000: Requirements General Instrumentation, Control, and Monitoring SYSTEMS - GENERAL A. This project comprises a groundwater extraction, treatment, and discharge system for Powder Mill Gulch at the Boeing Everett Plant as shown in the Drawings. The groundwater extraction system consists of 3 groundwater extraction wells that are outfitted with submersible pumps that will convey groundwater through a series of interconnecting pipelines to a treatment system. The treatment system features a low-profile air stripper as the fundamental treatment process. Subsystem processes for treatment of groundwater include a discharge pump, temporary holding tank, and transfer pump for testing, temporary storage, and/or retreatment of groundwater; a moisture separator, duct heater, and GAC vapor treatment vessels for the air stream from the air stripper; and other ancillary subsystems. The system will be monitored and controlled by a PLC and associated controls with remote telemetry and communications. B. Intent of the Drawings and this section is to provide ICM system subcontractor a generalized schematic and functional description of how the ICMs are to operate and provide the basis for developing a logic ladder for PLC programming. SUBMITTALS A. General. Contractor shall submit for review and approval the logic ladder and conceptual user interface design upon which PLC programming will be based. Submittal and approval by the engineer of the logic ladder and conceptual user interface design shall not relieve the Contractor in any way of its responsibility to provide a fully functional ICM system as described in this section. System Operation Description Section 17700 Statement of Work 1.5 V - 129 PMG Phase 1 Interim Action SYSTEM DESCRIPTIONS A. General – The following paragraphs describe functional requirements of ICM systems and processes to which they apply. Automatic control of process systems shall be accomplished through use of a PLC and associated controllers. Remote communications to the Operator (i.e., automated signals and alarms to a remote Operator terminal and pager) shall be controlled and performed by the PLC. Operator shall have ability to remotely access the PLC and control certain extraction system and treatment system operations (i.e., extraction pump operation and motor speed, blower operation and motor speed, discharge pump operation and motor speed, duct heater temperature control, and total system startup and shutdown). B. Groundwater Extraction 1. The theory of the operation and control system for each respective extraction system is identical. a. Groundwater shall be pumped from each extraction well by a submersible pump (e.g., P-101) and conveyed to the groundwater treatment system through a series of interconnected pipelines. Quantity of groundwater pumped from each well shall be metered through a magnetic flow meter (e.g., FI/FIT-101). Flow rate shall be indicated locally and transmitted to the PLC (PLC-501) located at the treatment building. Combine flow rate of all wells will also be metered through a magnetic flow meter (FI/FIT-201) at the influent to the air stripper, indicated locally, and transmitted to the PLC. PLC will display flow and totalized flow from each well individually and sum the combined flow rates and flow totals from each extraction well. Groundwater level in each well shall be monitored by a pressure transducer (e.g., LE/LIT-101). Groundwater level shall be transmitted to the PLC and displayed. Pump discharge pressure shall be measured by pressure meters (e.g., PI/PIT-101) at the wellhead, indicated locally, and transmitted to the PLC. PLC will display pump discharge pressure at each well. Pump running time shall be indicated in total cumulative hours at the PLC. b. PLC shall monitor groundwater elevation via pressure transducers in each well (LE/LIT-101, -102, and -103) and control groundwater elevation at each well by signaling each well control panel (e.g., CP-101) located in a CP enclosure proximate to the well (or in the treatment system building for EGW183) to adjust the groundwater extraction rate from each respective well, by modulating the input signal to the variable frequency drive (VFD) and thereby increasing or decreasing the pump speed, to maintain a predetermined groundwater elevation within the extraction well. If groundwater level should fall below preset minimum level and pump speed has been reduced to preset minimum speed, the PLC shall signal pump System Operation Description Section 17700 Statement of Work V - 130 PMG Phase 1 Interim Action shut down after operator adjustable but preset time period. Pump shall remain shut down until groundwater level returns to preset but operator adjustable level above preset minimum level. c. PLC will monitor pump discharge pressure at each well (PI/PIT101, -102, and -103) and send signal to respective CP. Set points for low or high pressure conditions shall be established at PLC and interlocked with CP and operation of pump. Low and high pressure failure signals shall be indicated at PLC, if pressure is below low pressure set point or above high pressure set point. PLC will signal pump shutdown if condition persists after preset but operator adjustable time delay. If pump shutdown is initiated, PLC will remotely communicate condition to Operator. d. The combined flow rate of all wells will be metered through a magnetic flow meter (FI/FIT-201) at the influent to the air stripper, indicated locally, and transmitted to the PLC. PLC will display and totalize flow from each well and sum the combined flow rates from the three extraction wells (total of FI/FIT-101, -102, and -103). PLC shall compare the sum of the flow rates from each individual well to the combined flow rate measured at air stripper influent. If flow rates are not equivalent within a specified tolerance (e.g., if summed flow rate is greater than 5% [plus the rated accuracy of instruments] higher than the combined flow rate at treatment building), a leak in the conveyance line may be present. Pipeline failure (leak) signals shall be indicated at the PLC and remotely communicated to Operator. If condition persists after an operator adjustable but preset time delay, the PLC will signal initiation of system shutdown sequence of the extraction system and treatment system. If shutdown sequence is initiated, PLC will remotely communicate condition to Operator. e. Submersible pump operation shall be identified on a stack light located at the respective well CP enclosure by illumination of a green operating light (e.g., OL-101). Motor overload or other system failures shall be indicated on a red stack light at well control CP enclosure and a main control panel (CP-501) cover by illumination of a red general alarm light (GA). Alarm lights and displays shall remain illuminated or activated until failure is cleared through the PLC user interface (remote or local). C. Air Stripper Treatment Equipment 1. The theory of the operation and control system for the air stripper treatment system is described below. a. The air stripping treatment equipment specified shall treat influent groundwater over a range of flow rates. Air shall be drawn through the low-profile air stripper from the suction side of the positive System Operation Description Section 17700 Statement of Work V - 131 PMG Phase 1 Interim Action displacement blower. The blower motor speed will be controlled through a VFD. The blower is designed to maintain a constant but operator adjustable air to water ratio. As influent groundwater flow rate increases or decreases as measured by FI/FIT-201, PLC shall signal CP-501 to proportionally increase or decrease air flow rate supplied to the stripper, as measured by the air flow meter on the stripper air intake (FI/FIT-301) to maintain a minimum air to water ration of 60:1, by adjusting the blower motor speed through the VFD. Air flow rate supplied to the stripper shall be supplied at a minimum rate of 1800 SCFM and a maximum rate of 3600 SCFM. b. The total groundwater flow rate entering the air stripper, as measured by FI/FIT-201, shall also be monitored by the PLC against a total allowable flow rate into the air stripper (i.e., the maximum design [or empirically demonstrated] groundwater flow rate at which the air stripper can achieve contaminant reductions to less than the regulatory discharge limit). Groundwater flow rates in excess of this value shall signal a system alarm and be remotely communicated to Operator. If condition persists after an operator adjustable but preset time delay, the PLC will signal initiation of system shutdown sequence of the extraction system and treatment system. If shutdown sequence is initiated, PLC will remotely communicate condition to Operator. c. PLC shall monitor water level in the air stripper clear well via an ultrasonic level indicator (LE/LIT-301) and control the water level by adjusting the pumping rate of the discharge pump (P-301) by modulating the input signal to the variable frequency drive (VFD) and, thereby, increasing or decreasing the pump speed to maintain a predetermined operator-controlled level within the air stripper clear well. If the water level should fall below the preset minimum level and pump speed has been reduced to the preset minimum speed, the PLC shall signal pump shutdown after operatoradjustable, but preset, time period. Pump shall remain shut down until groundwater level returns to preset, but operator-adjustable level above the preset minimum level. The air stripper clearwell shall also be equipped with a high-level switch (LSH-301) and lowlevel switch (LSL-301). If water level in clearwell rises or lowers causing either level switch to be triggered, PLC will be signaled. If condition persists after an operator adjustable but preset time delay, the PLC will signal initiation of system shutdown sequence of the extraction system and treatment system. If shutdown sequence is initiated, PLC will remotely communicate condition to Operator. d. Air pressure (vacuum) shall be measured by pressure meter PI/PIT-301 at the blower intake and transmitted to the PLC. PLC will monitor the vacuum. Set points for low or high vacuum conditions shall be established at PLC and interlocked with CP-501 and operation of blower. Low and high vacuum alarms shall be System Operation Description Section 17700 Statement of Work V - 132 PMG Phase 1 Interim Action indicated at PLC and communicated to Operator, if pressure is below low pressure set point or above high pressure set point. PLC will signal blower and extraction system shutdown if condition persists after preset but operator adjustable time delay. If blower shutdown is initiated, PLC will remotely communicate condition to Operator. D. Vapor Treatment Equipment 1. The theory of the operation and control system for the vapor treatment system is described below. a. Moisture Separator – An air moisture separator shall be located inline between the air stripper and blower. Liquid level in the separator shall be controlled by high-, high-high- and low-level float switches (LI/LIT-301). If level in the separator rises causing the high-level float switch to be triggered, the integrated condensate pump will be signaled to evacuate the separator into the building dead-end sump. The condensate pump shall pump until the lowlevel float switch is triggered, signaling the condensate pump to shut off. If the high-high-level switch is triggered, the PLC will be signaled. PLC will signal treatment system and extraction system shutdown if condition persists after preset but operator adjustable time delay. If system shutdown is initiated, PLC will remotely communicate condition to Operator. b. Duct Heater – A duct heater shall be located in-line between the blower and GAC vessels. Air temperature downstream of the duct heater (at the intake to the GAC vessels) shall be measured by TT301. Air temperature shall be transmitted to, displayed, and monitored by the PLC. PLC shall control air temperature entering the GAC vessels by signaling the duct heater temperature controller (TC-301) to adjust the heat input of the duct heater to maintain a predetermined air temperature within the air duct at the GAC vessel intake. c. Vapor Treatment – Air flow through two GAC vessels (GAC-301 and GAC-302) shall be manually controlled with a 6-valve manifold allowing operation in series or parallel configurations. Differential pressure across the vessels shall be monitored manually by pressure gauges PI-301/302/303. E. Other Equipment 1. A description of other equipment and controls associated with the treatment system, treatment system building, or well vaults is described below. System Operation Description Section 17700 Statement of Work V - 133 PMG Phase 1 Interim Action a. Building Sump/Sump Pump/Leak Detection – A dead-end sump shall be located in the treatment building for secondary containment of liquid spills or discharges. The sump will contain level switchs (LE-501) that will trigger a high-level alarm and high-high level switch. If liquid level in the sump rises causing the high-level switch to be triggered, a system alarm will be signaled to the PLC and identified on a red alarm light at CP-501 and remotely to the Operator. If the high-high level switch is triggered, the PLC will be signaled and the PLC shall initiate a shutdown of the extraction system and treatment system. If system shutdown is initiated, PLC will remotely communicate condition to Operator. The sump will also be equipped with a sump pump (P-501). Sump pump shall be manually operated by a hand switch (HS-502) on the sump pump control panel (CP-502). b. Well Vault Sumps/Sump Pumps/Leak Detection – A sump shall be located in each well vault. The sumps will each be equipped with a sump pump controlled by an integrated float switch. Each well vault will also be equipped with a high-level switch (LSH101/102/103). If water level in the vault rises causing the high-level switch to be triggered, an alarm will be signaled to the well control panel which will de-energize all electrical equipment and systems in the well vault and signal the PLC. PLC shall remotely communicate condition to Operator. c. Transfer Pump – A discharge pump (P-401) shall be plumbed between the temporary holding tank and the air stripper groundwater intake piping. The transfer pump shall be operated manually by a hand-off-auto switch located on CP-501. d. Temporary Holding Tank – A temporary holding tank shall be located outside the treatment building and plumbed to the air stripper outfall piping system. The temporary holding tank shall be equipped with a high-level switch (LSH-402). If liquid level in the tank rises causing the high-level switch to be triggered, CP-501 will be signaled to shut down the discharge pump P-301, a system alarm will be signaled on a red alarm light at CP-501, and the PLC will be signaled to communicate the condition remotely to the Operator. e. Potable Water System i. A temporary potable water supply system with tank, pump, and pressure tank shall be located in the treatment building. The system shall be manually controlled. ii. An emergency shower and eyewash station shall be provided in the treatment building. The station shall be plumbed to the potable water supply system. System Operation Description Section 17700 Statement of Work F. V - 134 PMG Phase 1 Interim Action Summary of Controls and Critical Alarms – The following table summarizes system alarms and resulting actions: Control/Critical Alarm Associated Equipment Extraction well groundwater elevation LE/LIT-101, -102, -103 Alter pump motor speed through VFD to maintain level, temporary pump shutoff as necessary. Extraction well pump high/low pressure PI/PIT-101, -102, -103 Shutdown pump if high/low pressure condition persists; signal Operator. Extraction system flow monitoring and comparison (for leak detection) FI/FIT-101, -102, -103; and FI/FIT-201 System shutdown if flow comparison yields loss of flow between wells and air stripper; signal Operator. Submersible pump shutdown OL-101, -102, -103 Air stripper blower flow rate FI/FIT-201 and FI/FIT-301 Air stripper groundwater influent flow rate FI/FIT-201 Alarm and signal operator if maximum flow exceeded. Extraction system shutdown if condition persists; signal Operator. Air stripper clearwell level LE/LIT-301 Alter discharge pump motor speed through VFD to maintain level, temporary pump shutoff, as necessary. Air stripper clearwell high level LSH-301 System shutdown if clearwell high level persists; signal Operator. Air stripper clearwell low level LSL-301 System shutdown if clearwell low level persists; signal Operator. Air stripper high/low vacuum PI/PIT-301 Alarm and signal operator if minimum or maximum vacuum exceeded. System shutdown if condition persists; signal Operator. Moisture separator liquid level LI/LIT-301 Condensate pump signaled to switch on and off by high and low-level switches, respectively. System shutdown if high-high level condition persists; signal Operator. Duct heater air temperature TT-301/TC-301 Alter heat input from duct heater to maintain air temperature; temporary heater shutoff as necessary. Building sump liquid level LE-501 Alarm and signal operator if high level exceeded. System shutdown if high-high level exceeded; signal Operator. Temporary holding tank high level LSH-402 System Operation Description Alarm Result/Action Stack light on control panel illuminate. Alter blower motor speed proportional to influent water flow rate to maintain minimum air to water ratio System shutdown if temporary holding high level exceeded; signal Operator. Section 17700 Statement of Work V - 135 PMG Phase 1 Interim Action PART 2 PRODUCTS 2.1 GENERAL A. Provide per Drawings and Section 17000. PART 3 EXECUTION 3.1 GENERAL A. Coordinate the descriptions in this section with Section 17000 and configure computer and telemetry hardware and software to accomplish the fully integrated and functional supervisory control and data acquisition system specified. END SECTION END OF STATEMENT OF WORK System Operation Description Section 17700 Statement of Work PMG Phase 1 Interim Action ATTACHMENT 1 PROJECT PLANS 1. Agreed Order No. DE96HS-N274 with Amendment Nos. 1 through 5 * 2. Construction Drawings 3. Utility Company Drawings and Designs** * To be provided under separate cover to successful bidder ** To be provided as a bid addendum