AttachmentE - Axthelm Construction

advertisement
PROJECT STATEMENT OF WORK
Boeing BCA Everett Plant
Powder Mill Gulch Downgradient Plume Interim Action, Phase 1
Boeing Environment, Health and Safety (EHS) Remediation Group
Seattle, WA
CONTENTS
I.
II.
III.
IV.
V.
Project Background
General Project Requirements
General Tasks, Requirements, and Submittals
Scope of Work
Technical Specifications
Attachment 1 – Project Plans
Statement of Work
i
PMG Phase 1 Interim Action
PROJECT CONTACTS
Boeing (Owner)
Boeing Project Manager:
Nick Garson
425-269-7866
nick.garson@boeing.com
Boeing Everett Plant Contact:
Alan Sugino
425-717-6117
alan.k.sugino@boeing.com
Boeing Field Manager
Dan McCormack
206-290-6558
daniel.c.mccormack@boeing.com
Contract Management/
Procurement Agent:
Meredith Plumb
425-237-4865
Meredith.G.Plumb@boeing.com
Landau Associates (Owner’s Representative)
Engineer (Landau Associates):
Piper Roelen, P.E.
425-778-0907
425-503-6784 mobile
proelen@landauinc.com
Biologist (Landau Associates):
Steven Quarterman
Environmental Project Manager
(Landau Associates):
Jerry Ninteman, P.E.
425-778-0907
squarterman@landauinc.com
425-778-0907
206-850-4503 mobile
jninteman@landauinc.com
Statement of Work
I-1
PMG Phase 1 Interim Action
I. PROJECT BACKGROUND
The Boeing Commercial Airplanes (BCA) plant in Everett, Washington is used for the
manufacture of 747, 767, 777, and 787 aircraft. Primary construction began in 1968
and was completed in 1969. Additional building and facilities have been constructed
since then. The head of Powder Mill Gulch (PMG) is located on the northern end of the
Everett Plant property.
Tricholoroethylene (TCE) was first detected in PMG groundwater in March 2003 with
the installation and sampling of monitoring well EGW075. A phased remedial
investigation has been conducted to characterize the nature and extent of the
groundwater plume and discharge of contaminated groundwater to surface water in
Powder Mill Creek.
Based on initial site characterization activities, the TCE source area was identified as an
approximately 14,000 square foot (ft2) area centered below the deepest portion of a
detention basin at the head of PMG. TCE concentrations in the source area were
historically measured as high as 31,000 micrograms per liter (μg/L). An interim action
(IA) was completed in 2008 within the source area using in situ electrical resistance
heating (ERH) to reduce TCE concentrations in the source area. The objective of the
source area IA was to reduce concentrations of TCE in groundwater to below an
established remediation level of 500 μg/L. The objective was achieved through most,
but not all of the source area through the ERH application. More recent application of
contingent and focused bioremediation appears to have successfully achieved the IA
objective throughout the source area.
The TCE groundwater plume in PMG extends north-northeast from the stormwater
detention basin. A portion of the plume discharges to Powder Mill Creek approximately
500 ft north of the detention basin where Powder Mill Creek becomes a perennial
gaining stream. The plume continues northward beneath Seaway Boulevard (which
bounds the northern edge of Boeing property); onto City of Everett Lot 9, Intermec, and
CRISTA Ministries properties; and, ultimately, discharges to Powder Mill Creek at the
toe of the plume, beginning approximately 1,000 ft north-northeast of Seaway
Boulevard. The plume, defined by TCE concentrations in groundwater greater than the
project screening level of 0.49 μg/L, is approximately 2,850 ft in length. TCE has been
measured in groundwater at concentrations as high as 2,000 μg/L at wells near Seaway
Boulevard, and 1,900 μg/L north of Seaway Boulevard.
The plume is present primarily in the upper portion of the Esperance Sand Aquifer, at
depths of 4 to 75 ft below ground surface (BGS). A 4-ft-thick silt layer within the
Esperance Sand Aquifer is relatively continuous over the length of the plume and
serves as a barrier to deeper vertical migration of TCE in the source zone and over
most of the downgradient dissolved-phase plume. A relatively impermeable Lawton
Clay unit is present approximately 30 ft below the silt.
Sampling in Powder Mill Creek and from seeps on the banks and hillsides above the
creek have identified concentrations of TCE in Powder Mill Creek up to 38 µg/L (south
of Seaway Boulevard) and in seeps up to 530 µg/L (near the toe of the plume).
Statement of Work
I-2
PMG Phase 1 Interim Action
Boeing has agreed to perform a downgradient plume IA to address various elements of
contamination in groundwater and surface water. This IA is being performed under the
authority and conditions of Amendment No. 5 to Agreed Order No. DE96HS-N274
(Order; Exhibit A1 in Attachment 1 – Project Plans) between The Boeing Company and
the Washington State Department of Ecology (Ecology). The downgradient plume IA
will include two phases of work: the first on Boeing property, referred to as the “PMG
Downgradient Plume Phase 1 IA” (Phase 1 IA); and the second off Boeing property
referred to as the “PMG Downgradient Plume Phase 2 IA” (Phase 2 IA).
This SOW pertains solely to the Phase 1 IA being conducted on Boeing property. This
Phase 1 IA is being conducted to prevent further migration of TCE off of Boeing
property and reduce discharge of TCE into Powder Mill Creek through construction and
operation of a groundwater extraction and treatment (GET) system. The GET system
involves pumping groundwater from extraction wells to create a capture zone to control
the migration of TCE-contaminated groundwater, treating the groundwater through air
stripping of aqueous-phase volatile organic compounds (VOCs), and discharging
treated groundwater to the city of Everett (City) sanitary sewer system. Vapor-phase
TCE discharged from the air stripper will be treated through granular activated carbon
(GAC).
Statement of Work
II - 1
PMG Phase 1 Interim Action
II. GENERAL PROJECT REQUIREMENTS
Upon award of this work, the Contractor shall enter into a binding agreement (Contract)
with Boeing (Owner) which shall specify the terms and conditions upon which
performance of the Work, specified herein, shall be performed.
This section provides general project requirements that shall be observed by the
Contractor during performance of work for the duration of the Contract.
AGREED ORDER
Upon award of this contract, a copy of the Order and Amendment No. 5 will be provided
to the Contractor. Contractor is required to provide copies of the Agreed Order to
subcontractors, and to provide documentation of this to Owner.
CONDUCT OF WORK
Coordination
Before starting Work, Contractor shall identify to Owner and Engineer an authorized
representative who shall have complete authority to represent and to act for Contractor.
The authorized representative shall be present at the work site at all times while work is
actually in progress or shall have designated an alternate when not present. The
authorized representative shall not be removed from the project without notification to
Owner and Engineer.
Coordination with facility staff, site tenants, property owner representatives, and other
onsite contractors shall be made by Contractor through Owner’s onsite representative to
assist Contractor with performance of the work with a minimum of interference and
inconvenience.
Work Hours
Standard work hours are 6:30 a.m. to 5:00 p.m., Monday through Friday. Contractor
may propose alternative work schedules; however, the proposed work schedule may
not be approved if Owner’s representative is not available to be onsite during the
proposed work hours.
Regulatory Requirements
Contractor is responsible for determining requirements and complying with local, state,
and federal laws, regulations, and permits that govern the Work. The Contractor shall
be aware of applicable or relevant and appropriate requirements for the Work, shall
determine the relevance of the regulations to executing the Work in this Contract, and
shall comply with all applicable requirements of the regulations in performing the Work.
Statement of Work
II - 2
PMG Phase 1 Interim Action
Sustainable Remediation Practices
The Boeing Company is committed to identifying cleanup project opportunities to use
natural resources and energy efficiently, reduce negative impacts to the environment,
minimize or eliminate pollution at its source, reduce waste to the greatest extent
possible and stay abreast of policy, technology and industry standards associated with
sustainable practices. This concept of sustainable remediation (SR) can be defined as
a remedy or combination of remedies whose net benefit on human health and the
environment is maximized through the judicious use of limited resources. SR
incorporates sustainable environmental practices into remediation of contaminated sites
to increase the environmental, economic and social benefits of a cleanup.
This
commitment includes using the contracting process to select suppliers who share
Boeing’s commitment to SR principles so that remediation work can be performed in a
way that reduces adverse impacts to the environment.
The following summarizes SR principles that the Contractor shall consider and
incorporate as reasonably feasible and applicable during performance of the SOW
described herein. Where appropriate, these principals are incorporated into the design
plans and technical specifications.
Summary of SR Principles and Objectives
Contractor will consider the “triple bottom line” for performance of this SOW, including
incorporation of efficient, low-impact work practices, procedures, and operations; and
use of sustainable materials and products. It is the goal of Boeing’s sustainable
remediation program to implement the following objectives in each project to the
greatest extent possible:
Environmental - Consider environmental effects of remedy implementation and
incorporate options to minimize the environmental footprints of a cleanup and conserve
natural resources.
Economic - Integrate sustainable practices throughout a remediation project’s life cycle,
evaluate return on investment.
Social - Partner with Boeing business units, regulatory agencies, the public and other
stakeholders to identify environmental, land use, health and safety aspects, and
economic goals in all phases of remediation projects to develop sustainable remedial
alternatives and select final remedies.
Core Elements
Sustainable practices emphasize the need to more closely evaluate core elements of a
cleanup project; compare the site-specific value of conservation benefits gained by
different SR strategies; and weigh the environmental trade-offs of potential strategies.
Sustainable Remediation addresses five core elements:
Energy – Promote efficiency and renewable sources.
Statement of Work
II - 3
PMG Phase 1 Interim Action
Air – Reduce air emissions.
Water – Reduce, reuse and protect.
Land and Ecosystems – Minimize harm, protect and foster return to ecological,
economic, social or other uses.
Materials and Waste – Reduce, reuse, recycle; use environmentally responsible
products.
GENERAL ACCESS REQUIREMENTS
The project site area is within Boeing property but outside the security fence of the main
facility, and Boeing-provided badges are required for access. The project site area is
periodically patrolled by Boeing’s security details and security personnel may query
personnel working at the site and ask for identification issued by Boeing. The site is
fenced with a locked gate at Seaway Boulevard. Contractor shall provide a padlock to
be daisy-chained with Boeing locks. Contractor shall ensure that the gate is locked at
the end of each work day.
Irregular or Non-Routine Access
Access on an irregular basis and during other than established working hours will
require prior approval by Owner.
Maintenance of Access
Contractor shall not obstruct or interfere with access by others to existing facilities
adjacent to the project site during the work under this Contract.
Vehicle Parking/Idling
Contractor’s vehicles shall only park in approved areas. Idling of vehicles and heavy
equipment will be limited to 10 minutes or less, excluding daily initial equipment
startup/warm up.
COORDINATION AND COOPERATION WITH OTHER CONTRACTORS
Work by others may be performed in the vicinity of or adjacent to the project site in
concurrence with the scheduled performance of the Work under this SOW. Contractor
shall coordinate construction work with those other contractors to minimize conflicts and
to maintain a cooperative effort in completion of the Work.
CONSTRUCTION SCHEDULE REQUIREMENTS
Work Flow
The work shall be planned, scheduled, and performed to complete the Work within the
requirements of this SOW. Contractor shall prepare and maintain a construction
Statement of Work
II - 4
PMG Phase 1 Interim Action
schedule. System startup and full scale operation (i.e., after completion of system
testing) shall be on or before August 1, 2012. Work shall be substantially completed by
October 30, 2012. Owner may choose to extend this deadline due to circumstances
such as weather or extended Ecology or City review periods.
Schedule Constraints
The following special constraints have been identified as having an impact on the
performance of the work. It is not intended to be a comprehensive list of constraints
that will result from the execution of the work, but as an aid to Contractor in
development of schedules and in executing the work. Additional constraints may exist
or develop as a result of required work execution or Contractor’s proposed work
methods or sequence. In any event, Contractor is responsible for compliance with the
requirements of the various specification sections and the work procedures and
protection requirements contained therein, and establishing all constraints associated
with the work execution and incorporating them into work schedules and proposed
construction activities.
Weather events may prevent the Contractor from performing work on certain days
because of water entering trench or difficulty controlling surface water flows, or erosion
to wetlands or surface water bodies.
At the end of work, Contractor’s tools and equipment must remain onsite until
Owner/Engineer performs final inspection and gives approval for Contractor to
demobilize.
PROTECTION OF PROPERTY
Contractor shall protect all property within or in the vicinity of the work site. Contractor
shall ensure that it is not removed, damaged, destroyed, or prevented from its normal
use unless so designated in the SOW. All property adjacent to the work shall be
protected including, but not be limited to, protection from construction-generated dust,
debris, water, and vibration. Property includes land, utilities, landscaping, markers and
monuments, monitoring wells, buildings, structures, site and drainage improvements,
and other improvements, whether shown on the Drawings or not. No work shall be
conducted in any wetlands or wetland buffer zone, or in the creek or creek buffer zone
(shown on the Construction Drawings) unless specifically identified in the Construction
Drawings or this scope of work. No work, including the staging of equipment or supplies
or any land disturbing activity, shall occur outside the limits shown in the Construction
Drawings. No work shall be conducted in restricted areas of the site unless coordinated
and approved by Owner.
Contractor shall perform a utility locate at least 48 hours prior to any below grade
excavation work. Contractor shall be responsible for any damages to existing utilities
that are damaged by the Contractor’s work, whether or not those utilities are identified
on the Drawings. All utilities that are damaged shall be repaired and restored to their
original operation at expense of Contractor.
Statement of Work
II - 5
PMG Phase 1 Interim Action
SPILLS AND HAZARDOUS MATERIALS
In the event of a spill or release of a hazardous substance (as designated in 40 CFR
302), pollutant, contaminant, or oil (as governed by the Oil Pollution Act [OPA], 33 USC
2701 et seq.), Contractor shall notify Boeing immediately. Immediate containment
actions shall be taken to minimize the effect of any spills or leaks. Cleanup shall be in
accordance with applicable federal, state, and local regulations. As directed by Boeing,
additional sampling and testing shall be performed to verify that spills have been
cleaned up. Spill cleanup and testing shall be done at no additional cost to Boeing.
The project shall not use mercury, crystalline silica, lead, cadmium, asbestos, chromium
or radioactive material without prior written approval from the Owner. Please note that
products labeled as “non-asbestos” may contain asbestos as a minor ingredient and are
not allowed in this project.
RESPONSIBILITIES
In addition to the requirements previously or subsequently indicated in this document,
the Contractor is responsible for the following:

Completion of the project per the construction schedule. System startup and full
scale operation shall be on or before August 1, 2012. Substantial completion of
construction is required by no later than October 30, 2012.

Providing all labor, equipment, materials, personnel transportation, supervision,
and management required to complete the scope of work, including field office,
temporary facilities (e.g., portable toilet, lighting), environmental protection, site
control and traffic control, grading, trenching, excavation, utility installation, soil
handling and dewatering onsite, erosion and sediment control, hauling and
disposal of non-contaminated soil and clearing/grubbing debris to designated
disposal/recycling facilities, outfall construction, and general system construction.

Providing qualified and appropriately trained personnel to complete the scope
and comply with the requirements described herein and/or required by law. All
site workers that may come in contact with hazardous materials contained in site
groundwater must have current 40-hour HAZWOPER training in order to work
onsite and the requirement that a HAZWOPER supervisor be available at all
times when work is occurring at the site.

Providing appropriate personal protective equipment (PPE) for all employees.
Contact with contaminated media is not anticipated during construction; however,
contaminated groundwater is present beneath the site; therefore, for bidding
purposes, assume modified Level “D” PPE (including gloves, Tyveks, and
booties) may be necessary for persons performing dewatering tasks or entering
excavations that come in contact with groundwater.

Appropriately managing stormwater flows, implementing Best Management
Practices (BMPs) for environmental and sediment and erosion control protection,
and performing associated monitoring.
Statement of Work
II - 6
PMG Phase 1 Interim Action

Maintaining all equipment in good working order.

Installing appropriate traffic control measures and barricades around work areas
accessible to the public including signs. If necessary, develop traffic control plan
for submission to the City, or other appropriate agency.

Cooperating with and supporting Owner’s site representatives.

Maintain spill clean-up supplies such as absorbent pads and booms in
appropriate quantities and at appropriate locations in the work site.

Maintaining records and noting deviations from the Construction Drawings to aid
and assist with preparation of post-construction as-built drawings.
Owner will be responsible for the following:

Obtaining environmentally related permits as indicated below.

Providing access to the work site (and escorts, as necessary) during normal
working hours.

Providing construction oversight to ensure compliance with construction
provisions and monitoring for potentially hazardous conditions related to site
contamination.

Preparation of reports for submittal to Ecology.

Installation of extraction wells per Washington well installation regulations
(borings and well casings completed to ground surface only; i.e., well vaults,
pumps, etc. are Contractor’s responsibility).
Statement of Work
III - 1
PMG Phase 1 Interim Action
III. GENERAL TASKS, REQUIREMENTS, AND SUBMITTALS
The following required elements of the project shall be followed or completed prior to
performance of field activities:
PERMITTING
For this work, Owner is obtaining a sanitary sewer discharge authorization from the City
and a Critical Areas Work Authorization from the City. Contractor shall be responsible
for complying with applicable permit conditions associated with this scope of work.
Contractor shall apply for and obtain all other necessary and applicable local, state, and
federal permits for completion of the work described herein (e.g., building permit, public
works permit, side sewer permit, right-of-way permit) including associated submittals.
Contractor shall determine what permits are required, apply for permits in a timely
manner, diligently pursue securing permits, and comply with any stipulations in the
permits. Contractor may request assistance, as necessary, from the Owner or
Engineer, but, in all cases, shall be responsible for obtaining permits. Verbally notify the
Engineer as soon as possible and provide immediate written notification to the Engineer
in the event that a permit cannot be obtained or will likely be obtained with agency
stipulations that significantly affect the performance and cost of the work.
UTILITY CONNECTIONS
Contractor shall be responsible for arranging and coordinating with the local power,
telecommunications, and sewer companies/utilities district for appropriate connections
and supplying certain applicable equipment and services to allow for hookup of such as
needed for the treatment system.
Electrical - Contractor shall be responsible for supplying and installing all electrical
conduit and junction boxes from the electrical tap point north of Seaway Boulevard
(including horizontal boring beneath Seaway Boulevard to tap point) as indicated in the
Construction Drawings and Utility Company Drawings and Designs. Snohomish County
PUD will provide and install the primary metering cabinet, two transformers, and
electrical cable into Contractor installed conduit from tap point to the primary metering
cabinet south of Seaway Boulevard and from the primary metering cabinet to the
transformers. Contractor shall be responsible for supplying wiring/cable beyond the
transformers.
Telecommunication - Contractor shall coordinate with local telecommunications
company to provide appropriate connection point at the entry to the site along Seaway
Boulevard. Telecommunications connection shall be made at the identified connection
point along Seaway Boulevard and as indicated in the Construction Drawings or Utility
Company Drawings and Designs . Contractor shall install all communication line
conduit and wiring from the connection point to the treatment system building and
associated equipment and control systems per the Construction Drawings.
Statement of Work
lII - 2
PMG Phase 1 Interim Action
Sewer - Side sewer connection shall be made at and from the identified connection
points along the City sanitary sewer line, including appropriate connections, piping, and
structures, as indicated in the Construction Drawings, to allow for hookup of such, as, to
and from the treatment system.
EROSION AND SEDIMENT CONTROL
Coverage under the Washington Construction Stormwater General Permit is not
required for this project due to the limited area of land that will be disturbed during
construction. However, the project is located adjacent to sensitive areas (i.e., Powder
Mill Creek, designated jurisdictional wetland, and associated creek and wetland buffer
zones). Therefore, Contractor shall implement and maintainappropriate Temporary
Erosion and Sediment Control (TESC) measures and best management practices, as
prescribed in the Stormwater Management Manual for Western Washington (2005), the
City of Everett Stormwater Management Manual, and as shown on Drawing C-3 in all
areas disturbed by construction activities. Contractor shall also take appropriate
measures to prevent trackout of dirt onto public roads, including construction of a
suitable construction entrance at the site entrance at Seaway Boulevard and street
cleaning, as needed. All loads of soil or aggregate shall be covered for transport to or
from the site.
HEALTH AND SAFETY
Site work shall be performed in accordance applicable state and federal occupational
health and safety regulations. Contractor shall prepare and comply with a health a
safety plan that is at least as stringent as the project health and safety plan (Landau
Associates 2005).
SUBMITTALS
Submittal Requirements
Two copies of each submittal will be provided by Contractor. All submittals furnished
formally shall bear a Contractor’s approval stamp or a certification. The stamp or
certification shall be signed by an authorized representative of the Contractor. The
Contractor’s stamp or certification on any submittals shall constitute a representation to
the Owner and the Engineer that the Contractor has either determined and verified all
quantities, dimensions, field construction criteria, materials, catalog numbers and similar
data, or that it assumes full responsibility for doing so, and that it has reviewed or
coordinated each submittal with the requirements of the Contract Documents.
Each submittal shall be accompanied by a transmittal letter that describes the items
submitted. The transmittal letter shall be clearly labeled “Phase 1 IA – Boeing/PMG
Site” and shall have a submittal number. The first submittal shall have submittal number
001, and subsequent submittals shall be consecutively numbered. The initial version of
the submittal shall be identified as “Revision 0,” and subsequent submittals shall be
numbered consecutively starting with “Revision 1.”
All submittals shall be addressed to the Engineer at the following address:
Statement of Work
lII - 3
PMG Phase 1 Interim Action
Landau Associates
130 2nd Avenue South
Edmonds, WA 98020
Attention: Mr. Piper Roelen, P.E., Associate.
Electronic submittals may be sent via electronic mail to:
proelen@landauinc.com
Submittal Review
After review of each of Contractor’s submittals, the material will be returned to
Contractor marked as follows:
1. “No Exceptions Taken.” Accepted subject to its compatibility with future
submittals and additional partial submittals for portions of Work not covered in
this submittal. Does not constitute approval or deletion of specified or required
items not shown in the partial submittal.
2. “Make Corrections Noted” (No Resubmittals Required). Same as Item 1, except
that minor corrections as noted shall be made by Contractor.
3. “Amend and Resubmit.” Rejected because of major inconsistencies or errors.
Resolve or correct before next submittal.
4. “Rejected-Resubmit.” Submitted material does not conform to the Contract
Documents in a major respect (i.e., wrong size, model, capacity, or material).
Within 5 days of receipt of Shop Drawings or manufacturer’s data, the Engineer will
return one copy of each drawing and/or data sheet marked to indicate the result of the
Engineer’s review.
Copies marked “No Exceptions Taken” or “Make Corrections Noted” authorize the
Contractor to proceed with construction covered by those Drawings or data sheets with
corrections, if any, incorporated. No revision in any way shall be made after a Drawing
has been marked “No Exceptions Taken” without resubmitting the Drawing for review.
When prints of Drawings have been marked “Amend and Resubmit” or “RejectedResubmit,” the Contractor shall make the necessary corrections and submit required
copies. Every revision shall be shown by number, date, and subject in a revision block
and, in addition, each revised Drawing shall have its latest revision numbers and items
clearly indicated by clouding around the revised areas on the Drawing. Drawings
submitted without these indications will be considered nonconforming and will be
returned to the Contractor without review.
The applicable parts of the requirements specified above for Drawings shall apply
equally to design data, catalog cuts, illustrations, printed specifications, draft reports, or
any other submittal furnished for review.
Specific Project Submittals
The following shall be submitted prior to commencement of construction:
Statement of Work
lII - 4
PMG Phase 1 Interim Action
Health and Safety Plan
Within 10 calendar days following notice to proceed, Contractor shall submit a worker
Health and Safety Plan conforming to the requirements indicated above.
Schedule
Contractor shall submit the construction schedule within 10 calendar days following
notice to proceed.
Sequencing/Phasing Plan
Within 10 calendar days following notice to proceed, Contractor shall submit a plan
presenting a sequencing and phasing plan for preliminary tasks and submittals, clearing
and grubbing, grading, utility connections, utility equipment installation, utility
conduit/piping trench excavation, sewer connection, utility conduit/piping/wiring
installation, treatment system building construction, extraction and treatment system
construction, and restoration that optimizes use of the available land area on the
property, expedites the work, and minimizes disturbance of land.
Changes to sequencing of work presented in Contractor’s approved plan shall only be
made with the concurrence of the Engineer.
Equipment/Materials List
Before beginning onsite work and within 20 days following notice to proceed, Contractor
shall submit a list of materials to Engineer for review. The list shall include all items of
equipment and material, and the names of the manufacturers and suppliers with whom
purchase orders have been placed. Provide sufficient data to precisely identify
materials and equipment Contractor proposes to furnish. The list shall include Drawing
or Specification references. Engineer will attempt to approve or disapprove of proposed
materials/equipment with 3 working days of the submittal. Contractor shall resubmit the
above requested information for any equipment or materials that are rejected by the
Engineer.
Manuals, Instructions, and Certificates
Prior to final inspection, Contractor shall submit four (4) complete sets of all
manufacturer’s specifications, cut sheets (including major valves and other materials),
operations and maintenance manuals, instructions, and certificates to Engineer
covering mechanical, electrical, instrumentation, piping items, and other material and
equipment provided by the Contractor, as noted in the Drawings and Specifications.
These materials shall be provided in 3-ring binder(s) with cover(s) with printed title
“Operations and Maintenance Materials,” title of project, and subject matter of binder if
multiple binders are required. Place same information on binder spine so as to be
legible when standing upright on a bookshelf. Internally subdivide the binder contents
with permanent page dividers logically organized; with tab titling clearly printed under
reinforced laminated plastic tabs. Include a table of contents for the manual. Provide a
directory listing names, addresses, and telephone numbers of Contractor,
Subcontractors, and equipment suppliers and manufacturer’s representatives nearest to
Statement of Work
lII - 5
PMG Phase 1 Interim Action
the job site for each major product in the manual. Materials shall be bound in 8-1/2 inch
by 11 text pages. Larger sheets shall be folded to 8-1/2 inch by 11 inch size and
enclosed in transparent, top entry protective plastic folders.
Record Drawings
During the progress of the Work, maintain at the site a detailed record of all changes
from the layouts and lines and grades, details, or other information shown on the
Drawings and on Contractor-furnished drawings and data. Enter the changes on the
record drawings promptly, but no later than on a weekly basis, using red, erasable
pencil. Have on file current working record drawings showing all changes, associated
construction dates, documentation of the Owner’s approval for changes, and
documentation of Contractor authorization to execute changes.
Contractor shall prepare and submit final mark-up of the Drawings indicating as-built
dimensions and any other as-built changes to Drawings. The set of Drawings shall be
clean except for red pencil used to indicate the as-built changes. Record drawings shall
be submitted within 14 days of completion of the work.
Permit Applications
Permit applications for the permits identified under “Permitting” subheading above shall
be prepared and submitted to the appropriate permitting authority in a timely manner
and per the project schedule, allowing sufficient lead time for agency review and
approval.
Extensions
If Contractor is unable to meet the submittal deadlines identified above for any reason,
Contractor shall request and extension from the Engineer at least 2 working days prior
to, and as far in advance of, the deadline as practicable. The request shall identify the
reason why an extension is needed and a proposed revised deadline.
PROJECT CLOSEOUT
The Contractor warrants the Work delivered under the contract to be free from defects
in material or workmanship, and against damage caused prior to final inspection.
Unless otherwise specified, this warranty extends for a period of one (1) year from the
date of final acceptance.
The Contractor shall promptly repair or replace all defective or damaged products or
materials delivered under the contract.
Prior to requesting final inspection, the Contractor shall submit to Owner and Engineer
written certification that the work has been thoroughly inspected by Contractor and is
complete in accordance with the Contract Documents. A project closeout punchlist may
be used by Contractor, Engineer, and Owner.
Statement of Work
IV - 1
PMG Phase 1 Interim Action
IV. SCOPE OF WORK
Contractor shall construct the groundwater extraction and treatment system as shown in
the Construction Drawings (Exhibit A2 in Attachment 1 – Project Plans). In the event
that discrepancies between this SOW and the Construction Drawings are identified, the
Construction Drawings shall take precedence. The discrepancy shall also be identified
to the Engineer and/or clarification requested as needed. A summary of the Scope of
Work is presented below.
SUMMARY
The work will consist of constructing all elements of the groundwater extraction system,
conveyance system, treatment system and building, and treated water discharge/sewer
connection, including all auxiliary electrical and communications systems from the utility
connections at Seaway Boulevard and to and from the system components. Contractor
shall provide all materials and equipment that are not provided by Owner, as necessary,
to produce a fully functional system in accordance with the Construction Drawings and
these specifications. The materials that will be provided by the Owner include the lowprofile air stripper and associated blower. The major equipment and materials to be
provided by Owner and the Contractor for the Work is provided in schedules on the
Drawings. Contractor shall be responsible for installing all equipment, including that
equipment provided by Owner. Extraction wells EGW175, EGW182, and EGW183 will
be installed by Owner, but all wellhead structures and equipment will be provided and
installed by the Contractor.
The major elements of the work include, but are not limited to, the following items:

Provision and installation of one new well vault, submersible pump, and
associated wellhead equipment at well EGW175

Provision and installation of one new well vault, submersible pump, and
associated wellhead equipment at well EGW182

Provision and installation of one new well vault, submersible pump, and
associated wellhead equipment at well EGW183

Provision and installation of groundwater conveyance piping from extraction wells
EGW175, EGW182, and EGW183 to the new treatment system building location

Install a side sewer connection to the City sewer line and associated structures

Provision and installation of treated groundwater conveyance piping from the
new treatment system building location to the side sewer connection to the City
sewer line, including associated structures

Provide and construct a treatment system building with electrical power,
communications (telephone/internet), lighting, heating, a below grade sump

Provide, install, and test the following treatment system equipment:
o Owner-supplied air stripper
o Owner-supplied blower
Statement of Work
IV - 2
PMG Phase 1 Interim Action
o Moisture separator
o Duct heater
o Granular activated carbon (GAC vessels) and associated manifold
o Bridge crane
o Temporary water supply
o Double-walled temporary holding tank (outside building)

Provision and installation of a exterior concrete pad outside treatment system
building for temporary holding tank

Provision and installation of weather-proof control panel enclosures at EGW175
and EGW182

Provision and installation of system electrical equipment and wiring to all
equipment and instrumentation including, but not limited to, below ground
electrical conduit and cablesjunction boxes and vaults; and associated breakers
and panels

Provision and installation of system communication lines including, but not limited
to, aboveground communications cables and poles; below ground
communications conduit and cables; and control panels

Provision and installation of all interconnecting piping and piping supports

Provision and installation of interconnecting electrical power wiring and
communications wiring all equipment and instrumentation.

Trenching (and horizontal boring as necessary) for pipe conveyance, electrical
conduit, and communication line conduit, and restoration of natural areas and
gravel surfacing along roads

Off-site disposal of excess trench spoil

Site work including grubbing and clearing, excavation, grading and leveling,
subgrade preparation and compaction

Pressure testing of lines

Startup and testing of systems to ensure proper operation

Surveying to determine slopes and elevations as specified

Preparation of record drawings to reflect the "as-built" condition.
The Work to be accomplished is organized into the general areas listed below:
1. Groundwater Extraction System. Furnish (all materials not provided by Owner),
install, startup, and test submersible groundwater extraction pumps for extraction
wells EGW175, EGW182, and EGW183. Owner will furnish a 6-inch nominal
diameter open-hole drilled wells. Contractor shall install well head vault and
2-inch stainless-steel riser piping for wells and shall install valves and fittings for
the well head.
Statement of Work
IV - 3
PMG Phase 1 Interim Action
2. Groundwater Conveyance Piping. Supply, install, and test the groundwater
conveyance piping. New conveyance piping shall consist of 2- and 4-inch
diameter conveyance pipe joined to form continuous conveyance of groundwater
between individual well vaults (and existing steel piping) and the new treatment
system. New groundwater piping shall be constructed of butt-welded high
density polyethylene (HDPE) and shall be compatible with TCE and other
chlorinated VOCs.
Electrical conduit and communication line conduit shall also be routed to the well
in the same trench as the conveyance conduit. The Contractor shall supply and
install the electrical and communications conduit and cable. Conduit and cable
to the extraction wells shall be of the size specified on the electrical drawings and
specifications.
3. Building. Prepare site, provide materials, and construct a cement masonry unit
(CMU) building with a steel truss roofing system to house the treatment system.
The building interior dimensions will be approximately 38 ft long, 20 ft wide, and
13 ft high. Concrete floor to be sloped toward a blind sump with steel grated
cover. Building will be provided with heater to keep the building at or above
40°F. Building penetrations required for treatment system components shall be
sealed in an aesthetic and water-tight manner.
4. Treatment System. Supply (those materials not provided by Owner), install, and
test the treatment system.
Contractor will be responsible for coordinating will all utility providers to establish
necessary services (i.e., power, telephone). Owner will pay those fees to utilities
that are required for provision of new service connections. Contractor will be
responsible for connection of services from the point of service provided by the
utility companies to the equipment of this Work.
Extracted groundwater shall be pumped to the treatment system building and
then to the inlet of the air stripper. After treatment in the air stripper, water shall
flow by gravity to a polyvinyl chloride (PVC) line, as shown on the Drawings. The
Contractor shall connect the air stripper effluent line to piping that allows
operation under several configurations as shown on the Drawings: a) to a
discharge pump that pumps to the 4-inch HDPE discharge line routed to the
sanitary sewer outfall, b) to a discharge pump that pumps to a temporary holding
tank outside the building, or c) from the temporary holding tank and returned to
the air stripper (via a transfer pump) for additional treatment.
Water purposefully or inadvertently discharged to the building sump shall be
pumped through 2-inch PVC piping, via a sump pump, to the temporary holding
tank.
Air exhausted from the air stripper shall be conveyed through an 8-inch steel duct
to a moisture separator, duct heater, GAC treatment vessels, and a 10-inch
discharge stack through the roof of the new treatment system building. The top
of stack shall be at a minimum height of 19 ft above ground surface elevation in
the area.
Statement of Work
IV - 4
PMG Phase 1 Interim Action
5. Discharge/Outfall to Sewer. Install side sewer connection and associated
manhole structure for treated groundwater discharge to sanitary sewer. Supply,
install, and test the treated water conveyance piping. New conveyance piping
shall consist of 4-inch diameter conveyance pipe joined to form continuous
conveyance of treated water between the new treatment system and the
manhole structure, and 6-inch diameter pipe from the manhole structure to the
sanitary sewer outfall. New piping shall be constructed of butt-welded HDPE and
shall be compatible with TCE and other chlorinated VOCs..
6. Instrumentation, Control, and Monitoring (ICM) System. Supply, install, and test
a fully programmed and functional ICM system for the treatment equipment and
extraction systems, consisting of a Programmable Logic Controllers (PLC), flow
meters, pressure indicators, pressure switches, level switches, level alarms, and
other miscellaneous elements, as noted on the Drawings. ICM system
components to be provided are shown on the Drawings and described in the
Technical Specifications. Contractor shall provide and install all required
aboveground and underground communications conduit, junction boxes, and
wiring to the treatment building, between the well control panels, and the
treatment system components.
7. Electrical. Contractor shall provide and install all required aboveground and
underground electrical conduit, junction boxes, vaults, and wiring to the treatment
building, well vaults, and treatment system components.
Statement of Work
V-1
PMG Phase 1 Interim Action
V. TECHNICAL SPECIFICATIONS
The following sections provide technical specifications for applicable elements of work
that supplement or augment the specifications provided in the Drawings.
This part includes the following Sections:
Section 02200
Section 02605
Section 02900
Section 02950
Section 03300
Section 04220
Section 05310
Section 05400
Section 05530
Section 07410
Section 08110
Section 08330
Section 08630
Section 08710
Section 08900
Section 10520
Section 14630
Section 15060
Section 15160
Section 15400
Section 17000
Section 17700
Site Preparation and Earthwork
Vaults and Manholes
Planting
Site Restoration and Rehabilitation
Cast-In-Place Concrete
Concrete Unit Masonry
Steel Decking
Cold-Formed Steel Framing
Metal Gratings
Metal Roof Panels
Hollow Metal Doors and Frames
Overhead Coiling Doors
Metal-Framed Skylights
Door Hardware
Louvers and Vents
Fire Extinguishers
Wall Supported Steel Bridge Crane
Pipe, Fittings, Valves, and Support
Well Equipment
Treatment Equipment
General Instrumentation, Control, and Monitoring Requirements
System Operating Description
Statement of Work
V-2
PMG Phase 1 Interim Action
SECTION 02200 – SITE PREPARATION AND EARTHWORK
PART 1 GENERAL
1.1
DESCRIPTION
A.
1.2
RELATED SECTIONS
A.
1.3
1.4
Provide grubbing and clearing, grading, excavating, backfilling,
compaction, removal and disposal of surplus excavated material, and
other work associated with meeting established lines and grades, and
installation of buried and supported equipment and structures.
Division 2: Site Work – all sections.
REFERENCES
A.
ASTM D 422 – Particle Size Analysis of Soil
B.
ASTM D 2922 – Test Method for Density of Soil and Soil-Aggregate in
Place by Nuclear Methods
C.
ASTM D 3017 – Test Methods for Moisture Content of Soil and SoilAggregate Mixtures
D.
OSHA
E.
WSDOT Standard Specifications for Road, Bridge, and Municipal
Construction 2010 M 41-10G
F.
ASTM D 2488 – Practice for Description and Identification of Soils (VisualManual Procedure)
G.
ASTM D 2487 – Classification of Soils for Engineering Purposes
H.
Landau Associates. Foundation Design Memorandum. April 27, 2010
I.
Western Washington Stormwater Management Manual
J.
City of Everett Stormwater Management Manual
SUBMITTALS
A.
Submit name of supplier and sample of each type of imported fill for
examination by Engineer. Provide materials from same source throughout
the work.
Site Preparation and Earthwork
Section 02200
Statement of Work
1.5
1.6
V-3
PMG Phase 1 Interim Action
DELIVERY, STORAGE, AND HANDLING
A.
Pile delivered and excavated material onsite in a manner that will not
endanger the work and that will not obstruct driveways or interfere with
facility operations. Take measures to prevent stormwater pollution,
including, but not limited to, coir logs surrounding the stockpiles, fabric
covers over catch basins, and temporary covers on the piles. Material
piles shall only be located in areas specified by the Engineer or Owner.
B.
Excavated material suitable for use as backfill shall be piled in an orderly
manner separately from unsuitable material, at a sufficient distance from
the edge of the trench to prevent material from sloughing or sliding back
into the trench.
C.
Excess excavated soils and materials unsuitable for use as backfill shall
be placed onsite as directed by the Engineer or Owner.
D.
Contractor shall, to the maximum extent practicable, transfer excess
excavated soil directly into trucks.
E.
Conduct work in a manner that will cause the least interruption to local
business operations. Where local business operations will be impacted by
the work being performed, the Contractor shall follow sequence of
construction so that local business operations are maintained.
COORDINATION
A.
Notify Engineer at least 5 days before starting excavation. Excavation
shall not proceed until Engineer has agreed to same.
B.
Provide the services of a competent buried utility locating service to
identify the location of existing buried utilities within the project site prior to
commencing excavation. Mark locations of existing buried utilities and
planned location of buried utilities, equipment, and extents of excavation
prior to commencing excavation.
C.
Protect existing pipes, conduits, poles, wires, well casings, or other
apparatus that may affect the work, and protect the same, under, over,
along or across said work. In case any of said pipes, conduits, poles,
wires, or apparatus should be damaged, they shall be repaired by
Contractor to the satisfaction of the Engineer, and the expense of such
repairs shall be borne by the Contractor. Any damage to existing wells
shall be corrected by repair or replacement, by a Washington state
licensed well driller approved by Engineer. Contractor shall bear all
expenses reasonably related to the repair or replacement of wells,
including, but not limited to, the well drillers services and materials,
professional oversight and documentation, and sampling and analysis (if
necessary).
Site Preparation and Earthwork
Section 02200
Statement of Work
V-4
PMG Phase 1 Interim Action
PART 2 PRODUCTS
2.1
STRUCTURAL FILL
A.
2.2
NATIVE MATERIAL
A.
2.3
2.3
Structural fill is defined as fill used to obtain final grade elevation for
footings, earth supported floor slabs, and paved or surfaced areas.
Structural fill shall consist of any suitable material that is nonorganic,
nonplastic, granular soil corresponding to soil types GW, GP, SW, or SP
soils, as designated by Unified Soil Classification System (U.S.C.S.) per
ASTM D 2488 and ASTM D 2487. To minimize the quantity of waste soil
generated, native soil shall be used as structural fill provided it meets the
above requirements and is free of topsoil, organic material, and debris.
CDF, as specified in Paragraph 2.03 B of this Section, may be used as
structural fill. Recycled material such as crushed concrete is not allowed.
Native excavated material free of topsoil or organic matter and any large
boulders, rocks, or chunks of consolidated earth that might damage the
pipe or structure or present a compaction problem shall be used as backfill
material to the extent possible. Rocks larger than 3 inches measured in
any direction shall not be used as backfill material.
BEDDING MATERIAL
A.
Gravel: Pipe zone bedding material shall consist of crushed, processed, or
naturally
occurring
granular
materials
that
conform
with
WSDOT 9-03.12(3).
B.
Controlled Density Fill (CDF): CDF may be substituted for gravel bedding
material in areas with limited access, such as at crossings of existing utility
pipes or conduit. CDF shall conform with WSDOT 9-01.2(4).
GRAVEL SURFACING
A.
Gravel surfacing material for the final cover shall be manufactured from
ledge rock, talus, or gravel, shall be uniform in quality, and substantially
free from wood, roots, bark, and other extraneous material. The material
shall conform to the requirements WSDOT 9-03.9(3).
B.
Contractor may, at its option, utilize an imported, clean, gravel surfacing
material with different gradation and quality characteristics than specified
above if such material is suitable for its intended use, satisfies the general
requirements and intent of this Contract, and is acceptable to the
Engineer.
C.
Material when placed shall also allow ease of foot traffic and small vehicle
traffic such as a forklift.
Site Preparation and Earthwork
Section 02200
Statement of Work
V-5
PMG Phase 1 Interim Action
PART 3 EXECUTION
3.1
CLEARING, GRUBBING, AND GRADING
A.
Prior to clearing, grubbing, and grading, wetland buffer and waterway
buffer will be flagged or fenced within 50 feet of the project area(s).
B.
Contractor, in coordination with the Biologist or Engineer, will flag and
inventory diameter at breast height and species of trees to be removed.
Any trees to be removed are to be replaced at a ratio of 2:1 following
completion of construction. The Contractor shall notify the Biologist or
Engineer a minimum of five (5) working days in advance of tree inventory.
C.
Perform clearing, grubbing, and disposal of trees, snags, logs, brush,
stumps, shrubs, and rubbish from the designated work areas. Clearing
and grubbing shall only be performed where necessary to safely and
effectively perform site grading, trenching, and construction. The limits of
the areas to be cleared and grubbed will be marked with high visibility
fencing, silt fencing, flags, stakes, tree markings and/or other suitable
methods. The limits of clearing and grading shall be verified by the
Engineer or Biologist prior to ground disturbance.
D.
Trees or other materials to be retained or used as habitat features will be
flagged and identified by the Engineer or Biologist. The Contractor shall
notify the Biologist a minimum of five (5) working days in advance of
clearing the site. Trees and other vegetation to be removed will be
designated with a different color flag, ribbon or stake.
E.
Trees, shrubs, and other vegetation designated to remain undisturbed
shall be protected from damage throughout the construction period. The
Contractor shall be responsible for the repair or replacement of vegetation
damaged by the Contractor’s operations. Any superficial damage such as
cuts, skins, scrapes or bruises to the bark of protected vegetation shall be
carefully trimmed and treated using locally acceptable procedures.
1. Limbs or branches, one half (½”) inches or greater, which are broken
or otherwise severed during construction, shall be cut flush at the base
of the limb/branch.
2. Roots, one inch (1”) or greater, which are broken or otherwise severed
during construction, shall have their ends cut smoothly and
perpendicular to the root.
3. Roots exposed during excavation or other operations shall be covered
with moist soil to match the previous grades as soon as possible.
F.
Materials removed during the clearing and grubbing operations will be
disposed of offsite as solid waste or recycled/composted. The Contractor
is responsible for complying with all applicable local, state or federal
regulations when the contract specifies offsite disposal of the materials.
Site Preparation and Earthwork
Section 02200
Statement of Work
V-6
PMG Phase 1 Interim Action
G.
Site grading shall be performed as shown on the Drawings. Structural fill
shall be imported, placed, and compacted as specified in paragraphs 3.03,
3.04, and 3.05 of this section.
H.
Before and during soil disturbance activities, Contractor shall implement
the temporary erosion and stormwater control measures shown on the
Drawings and the best management practices.
I.
Contractor shall recycle construction, demolition, or land clearing (CDL)
debris where practical. And report quantities to the Engineer and Owner.
These reports must include:
1. A description of all recyclables, non-hazardous waste, and CDL debris
removed from the site.
2. The quantity of recyclables and non-hazardous waste removed from
the site by weight, for that period.
3. Classification of the recyclables according to the following categories:
a. Concrete, asphalt and masonry,
b. Clean soil and gravel,
c. Metals,
d. Stumps and brush,
e. Recyclables sorted off site by a third party provider.
f.
3.2
EXCAVATION
A.
The working area of the site shall be cleared of all debris. The clearing
limits shall be as marked in the field and shall be kept to the minimum
extent needed to accomplish the work.
B.
Excavation for trenches shall conform to the limits shown on the Drawings.
The Contractor shall also prevent surface water from entering the trench.
C.
Width and Depth: The excavation shall be of such width to permit
workmen to satisfactorily install buried structures, and to provide safe
working conditions in accordance with federal, state, and local laws and
regulations. Trench safety is the sole responsibility of the Contractor, but
compliance with OSHA and other applicable regulations is mandatory.
Where required to prevent caving of the trench, or by any safety law or
regulation such as OSHA, the Contractor shall furnish and install bracing
and/or sheeting to protect the excavation. This bracing and/or sheeting
shall be removed as trench backfill progresses.
Site Preparation and Earthwork
Section 02200
Statement of Work
3.3
V-7
PMG Phase 1 Interim Action
D.
Excavations for vaults and similar structures shall be large enough to
provide proper working room. Any over depth excavation shall be
backfilled with compacted gravel or other approved material at the
Contractor's expense.
E.
Excavate to bring the required cut areas to rough grade or subgrade in
accordance with the drawings within plus or minus 0.10 feet.
F.
The Contractor shall remove and dispose of all water entering the
excavation. Disposal of water shall be done in a manner to prevent
erosion or sediment from entering adjacent wetlands or surface water, and
in accordance with all applicable laws and regulations. Pumps shall be
adequate to maintain a dry trench during the bedding, pipe installation,
and initial backfill to an elevation at least one foot above the top of pipe.
No backfill may be placed in standing water under any circumstances.
G.
Dust and storm water control shall be maintained during construction.
H.
Barricade open excavations to prevent access during nights and
weekends and when excavations are not actively being worked.
I.
Schedule activities to minimize period during which excavations remain
open. No excavation shall remain open for a period longer than 5
calendar days without written approval of the Engineer.
BACKFILLING
A.
Compact subgrade to density requirements specified in paragraph 3.04, of
this section.
B.
Remove loose, soft, or wet subgrade soil that cannot be compacted to the
specified density. Backfill with structural fill and compact as specified in
paragraph 3.04 of this section.
C.
Employ a placement method that does not disturb or damage existing
features or other work.
D.
Bedding shall be placed in conformance with the details shown on the
Drawings to uniformly support the buried structures throughout their
length. Before placing any bedding material, the bottom of the trench shall
be hand raked ahead of the pipe laying operation to remove stones and
lumps which will interfere with smooth and complete bedding of the pipe.
After the pipe has been laid and approved for covering, the specified
bedding material shall then be placed in layer(s) the full width of the
trench, and compacted as indicated in the Drawings and paragraph 3.04
of this section.
E.
Trenches shall be backfilled above the bedding material, as shown in the
Drawings, with suitable material saved from trench excavation. If there is
Site Preparation and Earthwork
Section 02200
Statement of Work
V-8
PMG Phase 1 Interim Action
not sufficient suitable material from the excavation, the backfilling of the
trench shall be completed utilizing imported backfill. The backfill and/or
imported backfill shall be compacted as indicated as indicated in the
Drawings and paragraph 3.04 of this section.
3.4
3.5
F.
Excavations in existing roadways shall be resurfaced to match pre-existing
conditions.
G.
In freezing weather, prior to terminating the work for the day, loose
protective material shall be placed on top of the backfill to prevent freezing
and shall be removed prior to subsequent work. Backfill shall not be
placed on snow, ice or frozen soil.
COMPACTING METHODS
A.
The fill material shall be compacted at a moisture content within 2% of
optimum moisture content. Structural fill and bedding shall be compacted
to a firm, unyielding condition within the limits of any pipe trench where the
depth of fill over the pipe is less than 12 inches. In areas where
subsurface utilities are covered by at least 12 inches of fill and under
structures such as the treatment building, catch basins and vaults,
compact structural fill to finish paving elevation to at least 95 percent
maximum density, as determined by ASTM D 1557. Engineer may have
testing done to verify that the requirement for minimum 95% compaction
has been achieved. Contractor shall be responsible for any recompaction
and re-testing required due to failed compaction testing.
B.
Field Densities shall be determined by the Sand Cone Method, ASTM D
1556, or the Nuclear Method, ASTM D 2922. At the time of compaction
the moisture content of that portion of the backfill material passing a U.S.
No. 4 sieve shall be not more than 3 percent above the optimum moisture
content as determined by the laboratory tests.
C.
Place bedding material in layers not exceeding 6 inches loose depth.
Place backfill in layers not exceeding 12 inches loose depth. Hand
compact bedding material to a distance of 3 inches above the top of pipes
prior to using mechanical compacting equipment.
D.
Avoid contacting any pipe or buried conduit with mechanical compacting
equipment. Do not use mechanically-powered compaction equipment
directly over pipe or conduits until sufficient backfill has been placed to
prevent damage to, or displacement of, the pipe or conduits.
TREATMENT SYSTEM AREA
A.
If necessary following grading and leveling, structural fill shall be placed to
raise the treatment system area to the proper elevation indicated on the
Drawings.
Site Preparation and Earthwork
Section 02200
Statement of Work
V-9
PMG Phase 1 Interim Action
B.
Structural fill used for the treatment system area base shall be in
accordance with paragraph 2.01A. CDF shall not be substituted for
structural fill in the treatment system area.
C.
Gravel Surfacing: The top layer of gravel surfacing shall be placed in one
lift at the treatment system area to provide a minimum of 3 inches depth.
This top layer shall be provided to prevent a muddy or dusty ground
surface.
1. Moisture condition the gravel surfacing material to or near its optimum
moisture content, as determined by ASTM D 1557. Place, grade, and
compact gravel surfacing to elevation on the Drawings. Compact
granular surfacing to at least 92 percent of its maximum dry density
(ASTM D 1557).
3.6
3.7
DISPOSAL OF EXCAVATED MATERIAL
A.
All excavated soil and debris not used as backfill shall be placed onsite as
directed by the Engineer or Owner.
B.
Asphalt and concrete removed under this Contract shall be transported
offsite to a facility licensed to receive the material for either recycling or
disposal.
C.
Submit copies of receipts, weigh tickets, and other documentation
verifying that disposal of soils, asphalt, concrete, and other wastes was
completed in accordance with this paragraph.
FIELD QUALITY CONTROL
A.
Field inspection and testing will be performed by the Contractor to the
satisfaction of the Engineer during the Work.
B.
Perform compaction testing in accordance with ASTM D 1557, ASTM D
1556, and ASTM D 3017 at two locations, selected by the Engineer, within
the limits of the area where the new treatment system concrete pad and
building is to be constructed. Compaction testing shall also be conducted
along the run of each trench, at locations selected by the Engineer, at no
more than 400 ft between testing locations. Compaction testing will not be
required in areas where CDF is used as backfill.
C.
If tests indicate work does not meet specified requirements, remove work,
replace, compact, and retest.
END OF SECTION
Site Preparation and Earthwork
Section 02200
Statement of Work
V - 10
PMG Phase 1 Interim Action
SECTION 02605 – VAULTS AND MANHOLES
PART 1 GENERAL
1.1
DESCRIPTION
A.
1.2
1.3
The Work of this section includes supply and installation of five
underground, precast, concrete vaults and manholes, as shown on the
Drawings.
RELATED SECTIONS
A.
Section 02200: Earthwork
B.
Section 15060: Pipes, Fittings, Valves, and Supports
C.
Section 15160: Well Equipment
SUBMITTALS
A.
Provide shop drawings for the vaults and all appurtenances. Drawings
shall indicate exact dimensions and weight of each unit; dimensions and
locations of vault penetrations; design capacities for lifting lugs; and
fabrication, handling, and installation procedures.
PART 2 PRODUCTS
2.1
PRECAST CONCRETE VAULTS
A.
Precast concrete vaults for extraction wells EGW175, EGW182, and
EGW183, and for the discharge pipe junction, shall be as specified in the
Drawings and modified as necessary to accommodate the well vault
equipment. Concrete vaults shall include vault accessories, including lids
as specified in the Drawings. Precast concrete vaults shall conform to the
following:
1. Vault covers shall be water tight and lockable (with padlock), and
frames shall be manufactured to withstand AASHTO H-20 loading.
2. Factory Modifications: 10” diameter bottom penetration for well casing,
24” diameter bottom penetration for sump.
3. Open bottom for discharge electrical junction vault
B.
Precast concrete manhole for the discharge structure adjacent to the side
sewer connection shall be as specified in the Drawings. Manhole shall
include standard manhole lid.
Vaults and Manholes
Section 02605
Statement of Work
C.
2.2
V - 11
PMG Phase 1 Interim Action
Well control panel enclosures for extraction wells EGW175 and EGW182
as specified in the Drawings.
GROUT
A.
Non-shrink grout shall be equivalent to “Masterflow 928” manufactured by
Masterbuilders, Inc.
PART 3 EXECUTION
3.1
INSTALLATION
A.
Contractor shall install vaults and manholes per specifications in
Drawings.
B.
The final location of the associated well control panel enclosures shall be
flagged by the Contractor and confirmed by the Engineer prior to
installation.
C.
Contractor shall have sole responsibility for coordination of other trades,
subcontractors, delivery, off-loading, and all necessary incidental material
to accomplish and accurately install vaults and manholes in a timely
manner to prevent delay of job progress.
D.
Contractor shall have sole responsibility for providing adequate equipment
and trained personnel to accomplish safe placement of vaults and
manholes and ancillary equipment, including the control panel enclosures.
E.
Vault penetrations for well conduit and drains shall be factory-drilled, saw
cut, bored, or cast-in during fabrication or saw cut in the field. Chiseled or
jack-hammered penetrations are not acceptable.
Final vault pipe
penetrations shall be completely filled and patched with non-shrinking
cement grout. A trowel or other instrument shall be used to create a
finished surface surrounding all pipe penetrations that is smooth and flush
with the interior surface of the vault. Seal grout as recommended by the
grout manufacturer. Link-Seal® Modular Seals may be substituted for
seal grout.
F.
Special care must be exercised to prevent damage to groundwater
extraction well casings or existing utility conduits during excavation for,
and setting of, well vaults. Contractor shall repair all damage to well
casings and utilities at Contractor’s expense. Any damage to existing
wells shall only be corrected by repair or replacement by a Washington
state-licensed well driller approved by Engineer. Contractor shall bear all
expenses reasonably related to the repair or replacement of wells,
including, but not limited to, the well driller’s services and materials,
professional oversight and documentation, and sampling and analysis (if
necessary).
Vaults and Manholes
Section 02605
Statement of Work
V - 12
PMG Phase 1 Interim Action
G.
Contractor shall have sole responsibility for setting vaults as shown on the
Drawings to provide adequate clearance for the installation of pumps, and
other ancillary equipment within the vault. Install vaults to elevations
indicated on the Drawings.
H.
Backfilling around vault shall be accomplished in a uniform and even
manner to prevent shifting or misalignment after setting vault. Backfill and
compaction shall conform with Section 02200. The completed vault
installation shall result in a vault that is level and plumb.
I.
Install cast iron frame on vault lid by placing a minimum 1/2-inch thick
layer of non-shrink grout on the lid within the footprint of the frame. Trowel
the grout bed level. Place frame on grout bed and apply firm pressure to
seat the frame in the grout. Grout shall completely fill space between the
lid and the frame base plate to a thickness of not less than 1/8 inch.
Frame shall be accurately centered over the cast opening in the lid.
Remove excess grout in the frame/lid opening. Protect frame and lid from
damage or movement until grout has initially cured. Place structural fill
around and above vault lid and frame and compact using manual
compaction equipment.
END OF SECTION
Vaults and Manholes
Section 02605
Statement of Work
V - 13
PMG Phase 1 Interim Action
SECTION 02900 – PLANTING
PART 1 GENERAL
1.1. DESCRIPTION
A.
This section applies to those items necessary for and incidental to the
execution and completion of planting and maintenance for restoration
plantings for the wetland and wetland/waterway buffer and other
miscellaneous disturbed natural areas..
B.
This section applies to those items necessary for and incidental to the
execution and completion of planting and maintenance for the restoration
plantings for the wetland, wetland/waterway buffer, and other
miscellaneous disturbed natural areas.
C.
A maintenance period shall begin when the initial planting operation has
been accepted by the Engineer and extend two full growing seasons
following installation.
D.
In general, restoration plantings should be installed no earlier than
October 1 and no later than March 31. However, planting in areas of high
erosion potential shall be conducted as soon as practicable
E.
Caution shall be exercised during excavation, planting, filling, grading, and
clean-up to protect existing trees, shrubs, other specified vegetation, and
other site features, improvements, structures, and utilities. Removal or
destruction of existing plants is prohibited unless specifically authorized by
the Engineer or Biologist. The grade shall not be changed nor shall soil
be added over the Critical Root Zone (CRZ) of existing plants marked for
protection. The CRZ is an area equal to one foot radius for each one inch
diameter of a plant measured at diameter breast height (DBH).
1.2
RELATED SECTIONS
A.
1.3
Division 2: Site Work – all sections.
REFERENCES
A.
American Standard for Nursery Stock. ANSI Z60.1. current edition.
American Nursery and Landscape Association, 1250 I St. NW, Suite 500,
Washington, DC 20005.
B.
The American National Standard for Tree Care Operations, ANSI A300.
current edition. International Society of Arboriculture, PO Box 3129,
Champaign, IL 61826-3129
Planting
Section 02900
Statement of Work
C.
1.4
PMG Phase 1 Interim Action
All standards shall include the latest additions and amendments as of the
date of advertisement for bids.
QUALIFICTIONS OF INSTALLER
A.
The Contractor shall be licensed in the State of Washington, shall have a
minimum of 3 years experience, and shall have completed landscaping
work similar in material, design, and extent to that indicated for this project
and with a record of successful landscape establishment.
B.
Contractor must be familiar and comply with American Standard for
Nursery Stock published by the American Nursery and Landscape
Association.
1.5
SUBMITTALS
A.
Within 30 days of award, Contractor shall submit documentation that
specified plant materials have been ordered and secured. A list of
supplier names, addresses, phone numbers, and the storage/growing
location of the materials shall also be submitted to the Engineer within 30
days of the landscape contractor award.
B.
If specified materials are unavailable, the Contractor shall notify the
Engineer in writing immediately and provide the names and telephone
numbers of five suppliers that have been contacted. If substitution is
needed, written approval from the Biologist is required. For plants and
seeds, local genetics must be confirmed by providing a signed letter to the
Engineer.
C.
Upon completion of the installation of the restoration elements, the
Contractor shall provide Engineer with a set of clearly marked Drawings
that provide plant quantities and locations within the restoration areas.
1.6
1.7
V - 14
HANDLING AND STORAGE
A.
Plants must be stored in the manner necessary to accommodate
horticultural requirements. Protect plant material stored on site from
weather damage, construction activity, and the public. Protect roots by
covering with moist soil, mulch, or sawdust. Water as required to keep
roots moist.
B.
Keep plants moist and shaded until the actual time of installation. If bareroot plants are specified, soak roots in water a minimum of 1 hour prior to
planting. Before and after planting, immediately saturate the soils in the
planting area to prevent capillary stress.
PLANT SURVIVAL WARRANTY
Planting
Section 02900
Statement of Work
V - 15
PMG Phase 1 Interim Action
A.
The Plant Survival Warranty shall include replacement of plants (same
size and species shown on the Drawings) that prove to be declining,
damaged, dead, or missing. Except for loss due to excessively severe
climatological conditions (substantiated by 10-year recorded weather
charts), installed plant materials are required to be guaranteed for 2 years
against defects and unsatisfactory growth, except for cases of neglect or
abuse/damage by others. Plants shall be replaced under plant guarantee
conditions.
B.
It is the responsibility of the Contractor to exercise care when moving
plants and other restoration elements to avoid breaking branches, scuffing
bark, or breaking roots of existing and new plants. Areas that are
damaged or disturbed that are outside of the project limits or not shown on
the Drawings shall be restored in kind at no extra cost to Owner. Plant
species and quantities of replacement plantings shall be approved by the
Biologist prior to installation.
PART 2 PRODUCTS
2.1
PLANTS
A.
Plants shall be provided per planting schedules in the Drawings.
B.
Plant material shall meet the requirements of the current edition of the
American Standard for Nursery Stock, and state and federal laws with
respect to plant disease and infestations. Inspection certificates, required
by law, shall accompany each and every shipment and shall be submitted
to Engineer upon arrival of plant material.
C.
Plant materials shall be locally grown (western Washington, western
Oregon, or western British Columbia), healthy, bushy, in vigorous growing
condition, and be accurate in size, name, and variety. Furthermore, plants
shall be free from disease, injury, insects, insect eggs, root and other
types of weevils, larva, weed roots, and defects such as knots, sun scald,
injuries, abrasions, disfigurements, and irregular growth. Local genetics
shall be confirmed by a signed letter from the nursery.
D.
To acclimate plant materials to local conditions, all plant materials used on
a project shall be grown continuously outdoors north of the 42nd Latitude
(Oregon-California border) from not later than August 1 of the year prior to
the time of planting.
E.
Representative trees must be untied and separated for inspections.
Engineer or Biologist reserves the right to refuse any/all plant material any
time prior to final acceptance if it is determined that such material does not
meet the Specifications as described herein. Plant material with damaged
root zones will not be accepted, and shall be replaced at no expense to
Planting
Section 02900
Statement of Work
V - 16
PMG Phase 1 Interim Action
the Owner. Rejected materials shall be immediately removed from the
project site and replaced at no expense to the Owner.
F.
The Biologist shall inspect plant materials at the job site for compliance
with required standards for plant size and quality prior to planting. This
includes, but is not limited to, size and condition of root systems, presence
of insects, latent injuries, and defects. Plant requirements are as follows:
G.
Container Plants (Trees, Shrubs, and Groundcovers):
a) Trees shall have uniform branching; single, straight trunks (unless
specified as multi-stemmed); and the central leader intact and
undamaged.
b) No balled or burlapped plants will be used.
c) Unless necessary for larger trees, do not stake plants for support.
d) Do not prune or top plants before delivery, except as approved by
Biologist.
e) Protect bark, branches, and root systems from sun scald, drying,
sweating, whipping, and other handling and tying damage.
f) Do not bend or bind-tie plants in such a manner as to destroy the
natural shape. Provide protective covering during delivery. Do not
drop plants during delivery.
g) Container stock shall be fully rooted but not root-bound.
h) The original central leader on tree stock must be healthy and
undamaged.
i) Plants shall be the size indicated on the Drawings.
H.
Bare root stock can be substituted for container plants as approved by the
Engineer and Biologist.
I.
Plants must be stored in the manner necessary to accommodate their
horticultural requirements. Protect plant material stored on site from
weather damage, construction activities, and the public. Keep plants
moist and shaded until the actual time of installation. Do not allow any
plants to be exposed to freezing temperatures prior to planting.
J.
Substitutions of plant species or sizes may be permitted based on plant
availability, but only with prior written approval by the Biologist.
Planting
Section 02900
Statement of Work
K.
2.2
PMG Phase 1 Interim Action
The Biologist shall examine restoration planting materials prior to
unloading at the site.
Any material not meeting these required
Specifications shall be immediately removed from the site and replaced
with products specified in the Drawings and these Specifications at no
cost to the Owner.
Bark Mulch
A.
2.3
V - 17
A three inch compacted layer of bark mulch shall be used in a 24-inch
diameter ring surrounding all container plants in the Restoration Planting
area only. See the Drawings for further information.
Fertilizers
A.
Trees, shrubs, and groundcovers shall be fertilized using one of the
following products:
1. Formula 4-2-2 “Transplanter” as manufactured by Pacific Agro Co.,
with Hercules nitroform and W.R. Grace’s “Magamp” and trace
elements. Apply at a rate of:
a. Trees: 8 ounces
b. Shrubs: 2 ounces
c. Groundcovers: 1 ounce
2. Agriform Tablets: Planting tablets, 21-gram size, as manufactured by
Agriform International Chemicals, Inc., 20-10-5 analysis. Apply at a
rate of:
a. Trees: 4 tablets for every foot of rootball diameter
b. Shrubs: 3 tablets
c. Groundcovers: 1 tablet
PART 3 EXECUTION
3.1
PLANTING
A.
Contractor is to plant trees and shrubs in planting pits as detailed in the
Drawings.
B.
When performing the following work, do not injure the root system. Do not
overexcavate planting pit depth; however, overexcavation of planting pit
width is desirable.
C.
Before laying out plant locations, Contractor shall walk the intended
planting area with the Biologist to discuss strategies for plant locations.
Planting
Section 02900
Statement of Work
V - 18
PMG Phase 1 Interim Action
D.
The Contractor shall locate in the field and either stake or lay out actual
plants at proposed planting locations prior to planting. Plants shall be
placed in a random, natural pattern following placement notes provided in
the Plans. On-center (O.C.) spacing called out on the plant schedule
indicates an average spacing dimension. For example, if the plan calls for
24 inches O.C., spacing shall vary from 18 to 30 inches O.C., with an
average spacing of 24 inches. Biologist shall approve proposed plant
locations and layout prior to installation by the Contractor. Any substantial
variations from the planting plan will require prior approval by the Biologist.
E.
Trees shall be handled by the rootball, not by the trunk. Plants shall be
installed upright, rotating them to give the best placement to adjacent
plants and topography. Hold plant rigidly in position until topsoil has been
backfilled and tamped firmly around the ball or roots.
F.
When the planting pit is backfilled halfway, place the specified quantity of
fertilizer and stakes, if necessary, as shown on the Drawings and these
Specifications. Evenly space the fertilizer around the perimeter of and
immediately adjacent to the root system. Carefully place water and
compact planting backfill, filling all voids. Do not injure the root system.
G.
When the planting pit is three-quarters (3/4) backfilled, fill with water and
allow it to soak away. Fill pits with additional topsoil and continue
backfilling. Ground bark shall be placed over all tree-planting saucers to a
compact depth of 3 inches. Water trees immediately after planting.
H.
Detailed directions for planting are described as follows (also refer to the
Drawings):
1. Container Trees and Shrubs: The following directions, adapted from
the International Society of Arboriculture, must be followed for
container plantings (see Details on Sheet C-8):
a) Dig a shallow, broad planting hole. Make the hole three times the
diameter of the root ball but only as deep as the root ball.
b) Stockpile excavated soil next to planting pit. The excavated soil will
be used for backfill in the planting pit.
c) Identify the trunk flare. The trunk flare is where the roots spread at
the base of the plant. This point shall be partially visible after the
plant has been installed. If the trunk flare is not partially visible,
some soil shall be removed from the top of the root ball.
d) Place the tree or shrub at the proper height. Before placing the tree
or shrub in the hole, check to see that the hole has been dug to the
proper depth and no deeper. It is better to plant the tree or shrub a
little high, 2 to 3 inches above the base of the trunk flare, than to
plant it at or below the original growing level. This planting level will
allow for some settling. To avoid damage when setting the tree or
Planting
Section 02900
Statement of Work
V - 19
PMG Phase 1 Interim Action
shrub in the hole, always lift the tree or shrub by the root ball and
never by the trunk.
e) Straighten the tree or shrub in the hole. Before beginning
backfilling, view the tree or shrub from several directions to confirm
that the tree or shrub is straight.
f) Fill the hole gently but firmly. Fill the hole about one-half (½) full
and water settle the soil around the base of the root ball.
g) Apply fertilizer into planting pit as specified in Section 2.04.
h) Fill the remainder of the hole, taking care to firmly pack soil to
eliminate air pockets that may cause roots to dry out. To avoid this
problem, add the soil a few inches at a time and settle with water.
Continue this process until the hole is filled and the tree or shrub is
firmly planted.
i) Do not stake trees or shrubs unless necessary to keep the tree or
shrub straight.
a)
2. If bare root stock is to be used in lieu of container plants, all methods
for installation of container plants apply with exception of storage and
handling of bare root stock, which shall be submitted by Contractor
upon request for using bare root stock.
I.
3.2
Rectification of Accidental Plant Injury
A.
3.3
Immediately (on the day of installation) water all plants thoroughly.
Any living woody plant that is damaged during construction shall be
treated within 24 hours of occurrence, including wound-shaping treatment,
which includes, but is not limited to, evenly cutting broken branches,
exposed roots, and damaged tree bark immediately after damage occurs.
Injured plants shall be thoroughly watered and additional measures shall
be taken, as appropriate, to aid in plant survival, at no cost to Owner. Any
plants that are visible harmed such that future growth is jeopardized (such
as broken leaders, uprooting, etc.) shall be replaced at no cost to the
Owner.
SOIL PREPARATION/AMENDMENTS
A.
Planting
Mulch in the form of organic compost shall be used as a topsoil for all
planting areas.
Section 02900
Statement of Work
3.4
V - 20
PMG Phase 1 Interim Action
RESTORE EXISTING NATURAL AREAS
A.
Existing natural or landscaped areas that are damaged
construction shall be restored to their original condition,
improvements or modifications are specified for those areas.
removed incidental to construction activities shall be replaced at a
2 trees for every tree removed (i.e., 2:1).
during
unless
Trees
ratio of
B.
The Contractor shall exercise care to protect from injury trunks, roots, or
branches of any trees or shrubs that are to remain. Any living woody plant
that is damaged during construction shall be treated immediately. Any
superficial damage such as cuts, skins, scrapes or bruises to the bark of
protected vegetation shall be carefully trimmed and treated using locally
acceptable procedures.
1. Limbs or branches, one half (½”) inches or greater, which are broken
or otherwise severed during construction, shall be cut flush at the base
of the limb/branch.
2. Roots, one inch (1”) or greater, which are broken or otherwise severed
during construction, shall have their ends cut smoothly and
perpendicular to the root.
3. Roots exposed during excavation or other operations shall be covered
with moist soil as soon as possible to prevent the roots from drying out.
3.5
IRRIGATION
A.
3.6
All plants may require irrigation for a period of time after installation. The
Engineer and Biologist will evaluate the environmental conditions of the
plating areas and determine what level of effort will be required by
Contractor for irrigation. Contractor shall monitor, irrigate, and maintain
plants throughout the construction period. During the first year after
planting, Contractor shall be responsible for replacement of plants as
needed and irrigation of plants for the first growing season (from February
28 to November 20).
MAINTENANCE
A.
This section includes additional maintenance that is not included under the
warranty and maintenance for plants. This is expected to include
maintenance items authorized in writing by the Owner, as needed after the
2-year warranty period, and other items authorized in writing by the Owner
during the 2-year warranty period, including, but not limited to:
1. Correction of Foraging and Browsing: The Contractor shall implement
measures to prevent damage of plant material by browsing animals
(e.g., deer, beaver, rabbits, mice, voles).
Planting
Section 02900
Statement of Work
V - 21
PMG Phase 1 Interim Action
2. Weeding and Maintenance of Trees and Shrubs: Routine maintenance
of trees and shrubs shall be performed. Weed control should be
performed by hand removal and/or other approved methods. No
mechanical weed trimmers or herbicides will be used after initial site
preparation activities.
3. Pruning of Woody Plants – Woody plants shall be pruned only to
remove pest infestations.
4. Resetting plants to proper grade and upright position, controlling
invasive weed species, and correcting drainage problems, as required.
5. Removal of temporary erosion control.
6. Modifications to the irrigation system to accommodate optimal plant
survival.
3.7
B.
Contractor shall review maintenance recommendations with the Biologist.
C.
Contractor has the right to enter the property for inspection and curative
treatment of any materials still under warranty during the entire warranty
period. Owner is to be notified in advance of any corrective or curative
treatment measures so as to arrange for convenient access to the area.
D.
Contractor shall be responsible for consistent and adequate maintenance
and operation of the irrigation system. Contractor shall be responsible for
maintenance and repairs during the warranty period.
B.
At the end of the irrigation period (if needed) and if plant establishment is
successful, as determined by Owner’s representative, irrigation will be
discontinued.
CHECKLIST AND CLOSEOUT
A.
The Biologist shall verify that all items meet the Specifications listed in this
section. Any items that do not meet Specifications will be marked on a
checklist for rectification prior to the next phase of work and/or project
closeout. If items are to be corrected, a contingency checklist of adaptive
management strategies necessary to meet Specifications shall be
prepared by the Owner and submitted to the Contractor. After punch list
items have been completed by the Contractor, the Owner shall review and
revise the checklist to reflect satisfactory completion
END OF SECTION
Planting
Section 02900
Statement of Work
V - 22
PMG Phase 1 Interim Action
SECTION 02950 – SITE RESTORATION AND REHABILITATION
PART 1 GENERAL
1.1
DESCRIPTION
A.
1.2
This section describes general site restoration and rehabilitation
requirements for areas of the site where Work is substantially completed
or will not be actively worked for at least 1 week.
RELATED SECTIONS
A.
All Divisions
PART 2 PRODUCTS
Not Applicable to This Section
PART 3 EXECUTION
3.1
FINISHING AND CLEANUP
A.
Restore site to pre-construction conditions, where applicable. The entire
site shall be cleared of all materials such as construction debris, paper,
wood, glass containers, trash, wire, broken concrete, rubble, plastic,
fiberglass and other undesirable items as directed by the Engineer. Soil
stockpiles shall be removed or spread onsite where approved by the
Engineer.
B.
Finish grade elevations outside of designated cut or fill areas shall be
restored to natural grade.
C.
Gravel roadways shall be graded smooth and aggregate surface restored
as needed.
D.
Contractor shall avoid soil compaction in natural areas.
E.
Restoration of vegetation in natural areas and within the wetland and
wetland/waterwaybuffer (i.e., the treatment system discharge trench and
outfall areas, and access paths to piezometers) shall conform to the
planting schedule and specifications in the Drawings and Section 02900.
Repairs of equipment damage and replacement of vegetation shall be
acceptable to the Engineer. The Engineer shall be the sole judge of the
need to replace damaged/disturbed vegetation. Leave area in a clean and
neat condition.
F.
Surplus materials, tools, equipment and temporary structures shall be
removed by the Contractor. The construction site shall be left clean.
Site Restoration and Rehabilitation
Section 02950
Statement of Work
V - 23
PMG Phase 1 Interim Action
END OF SECTION
Site Restoration and Rehabilitation
Section 02950
Statement of Work
V - 24
PMG Phase 1 Interim Action
SECTION 03300 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1
SUMMARY
A. Section includes cast-in-place concrete, including formwork, reinforcement,
concrete materials, mixture design, placement procedures, and finishes.
B. Related Sections:
1. Division 31 Section "Earth Moving" for drainage fill under slabs-on-grade.
1.2
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Design Mixtures: For each concrete mixture.
C. Steel Reinforcement Shop Drawings: Placing drawings that detail fabrication,
bending, and placement.
D. Formwork Shop Drawings: Prepared by or under the supervision of a
qualified professional engineer detailing fabrication, assembly, and support of
formwork.
1.3
INFORMATIONAL SUBMITTALS
A. Welding certificates.
B. Material certificates.
C. Material test reports.
D. Floor surface flatness and levelness measurements.
1.4
QUALITY ASSURANCE
A. Manufacturer Qualifications: A firm experienced in manufacturing readymixed concrete products and that complies with ASTM C 94/C 94M
requirements for production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of Ready
Mixed Concrete Production Facilities."
B. Testing Agency Qualifications: An independent agency qualified according to
ASTM C 1077 and ASTM E 329 for testing indicated.
Cast-In-Place Concrete
Section 03300
Statement of Work
V - 25
PMG Phase 1 Interim Action
C. Welding Qualifications: Qualify procedures and personnel according to
AWS D1.4/D 1.4M, "Structural Welding Code - Reinforcing Steel."
D. ACI Publications: Comply with the following unless modified by requirements
in the Contract Documents:
1. ACI 301, "Specifications for Structural Concrete," Sections 1 through 5.
2. ACI 117, "Specifications for Tolerances for Concrete Construction and
Materials."
E. Concrete Testing Service: Engage a qualified independent testing agency to
perform material evaluation tests and to design concrete mixtures.
PART 2 - PRODUCTS
2.1
FORM-FACING MATERIALS
A. Smooth-Formed Finished Concrete: Form-facing panels that will provide
continuous, true, and smooth concrete surfaces.
Furnish in largest
practicable sizes to minimize number of joints.
B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another
approved material. Provide lumber dressed on at least two edges and one
side for tight fit.
2.2
STEEL REINFORCEMENT
A. Reinforcing Bars: ASTM A 615, Grade 60, deformed.
B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing,
supporting, and fastening reinforcing bars and welded wire reinforcement in
place. Manufacture bar supports from steel wire, plastic, or precast concrete
according to CRSI's "Manual of Standard Practice.
2.3
CONCRETE MATERIALS
A. Cementitious Material: Use the following cementitious materials, of the same
type, brand, and source, throughout the project:
1. Portland Cement:
following:
ASTM C 150, Type II, gray. Supplement with the
a. Fly Ash: ASTM C 618, Class F.
b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or
120.
B. Normal-Weight Aggregates: ASTM C 33, graded.
1. Maximum Coarse-Aggregate Size: 1-1/2 inches nominal.
Cast-In-Place Concrete
Section 03300
Statement of Work
V - 26
PMG Phase 1 Interim Action
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in
cement.
C. Water: ASTM C 94 and potable.
2.4
ADMIXTURES
A. Air-Entraining Admixture: ASTM C 260.
B. Chemical Admixtures: Provide admixtures certified by manufacturer to be
compatible with other admixtures and that will not contribute water-soluble
chloride ions exceeding those permitted in hardened concrete. Do not use
calcium chloride or admixtures containing calcium chloride.
1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A.
2. Retarding Admixture: ASTM C 494/C 494M, Type B.
3. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.
4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F.
5. High-Range, Water-Reducing and Retarding Admixture:
C 494M, Type G.
ASTM C 494/
6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.
2.5
VAPOR RETARDERS
A. Sheet Vapor Retarder: ASTM E 1745, Class A.
recommended adhesive or pressure-sensitive tape.
Include manufacturer's
B. Sheet Vapor Retarder: Polyethylene sheet, ASTM D 4397, not less than 10
mils thick.
2.6
CURING MATERIALS
A. Evaporation Retarder:
Waterborne, monomolecular
manufactured for application to fresh concrete.
film
forming,
B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or
kenaf, weighing approximately 9 oz./sq. yd. when dry.
C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlappolyethylene sheet.
D. Water: Potable.
E. Clear, Waterborne, Membrane-Forming Curing Compound:
Type 1, Class B, dissipating.
Cast-In-Place Concrete
ASTM C 309,
Section 03300
Statement of Work
V - 27
PMG Phase 1 Interim Action
F. Clear, Waterborne, Membrane-Forming Curing Compound:
Type 1, Class B, nondissipating.
ASTM C 309,
G. Clear, Solvent-Borne, Membrane-Forming Curing and Sealing Compound:
ASTM C 1315, Type 1, Class A.
1. VOC Content: Curing and sealing compounds shall have a VOC content
of 200 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
H. Clear, Waterborne, Membrane-Forming Curing and Sealing Compound:
ASTM C 1315, Type 1, Class A.
1. VOC Content: Curing and sealing compounds shall have a VOC content
of 200 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
2.7
CONCRETE SEALANT
A. Carboline® Phenoline® 187 Primer and Finish.
2.8
CONCRETE MIXTURES
A. Prepare design mixtures for each type and strength of concrete, proportioned
on the basis of laboratory trial mixture or field test data, or both, according to
ACI 301.
B. Cementitious Materials: Use fly ash, pozzolan, ground granulated blastfurnace slag, and silica fume as needed to reduce the total amount of
portland cement, which would otherwise be used, by not less than 40 percent.
C. Admixtures: Use admixtures according to manufacturer's written instructions.
D. Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength: 3500 psi at 28 days.
2. Maximum Water-Cementitious Materials Ratio: 0.45.
3. Slump Limit: 4 inches for concrete with verified slump of 2 to 4 inches
(before adding high-range water-reducing admixture or plasticizing
admixture, plus or minus 1 inch.
4. Air Content: Do not allow air content of trowel-finished floors to exceed 3
percent.
2.9
FABRICATING REINFORCEMENT
A. Fabricate steel reinforcement according to CRSI's "Manual of Standard
Practice."
Cast-In-Place Concrete
Section 03300
Statement of Work
2.10
V - 28
PMG Phase 1 Interim Action
CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according
to ASTM C 94, and furnish batch ticket information.
1. When air temperature is between 85 and 90 deg F, reduce mixing and
delivery time from 1-1/2 hours to 75 minutes; when air temperature is
above 90 deg F, reduce mixing and delivery time to 60 minutes.
PART 3 - EXECUTION
3.1
FORMWORK
A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to
support vertical, lateral, static, and dynamic loads, and construction loads that
might be applied, until structure can support such loads.
B. Construct formwork so concrete members and structures are of size, shape,
alignment, elevation, and position indicated, within tolerance limits of ACI 117.
C. Chamfer exterior corners and edges of permanently exposed concrete.
3.2
EMBEDDED ITEMS
A. Place and secure anchorage devices and other embedded items required for
adjoining work that is attached to or supported by cast-in-place concrete. Use
setting drawings, templates, diagrams, instructions, and directions furnished
with items to be embedded.
3.3
VAPOR RETARDERS
A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder
according to ASTM E 1643 and manufacturer's written instructions.
1. Lap joints 6 inches and seal with manufacturer's recommended tape.
3.4
STEEL REINFORCEMENT
A. General: Comply with CRSI's "Manual of Standard Practice" for placing
reinforcement.
1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor
retarder before placing concrete.
3.5
JOINTS
A. General: Construct joints true to line with faces perpendicular to surface
plane of concrete.
Cast-In-Place Concrete
Section 03300
Statement of Work
V - 29
PMG Phase 1 Interim Action
B. Construction Joints: Install so strength and appearance of concrete are not
impaired, at locations indicated or as approved by Engineer.
C. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler
strips at slab junctions with vertical surfaces, such as column pedestals,
foundation walls, grade beams, and other locations, as indicated.
3.6
CONCRETE PLACEMENT
A. Before placing concrete, verify that installation of formwork, reinforcement,
and embedded items is complete and that required inspections have been
performed.
B. Deposit concrete continuously in one layer or in horizontal layers of such
thickness that no new concrete will be placed on concrete that has hardened
enough to cause seams or planes of weakness. If a section cannot be placed
continuously, provide construction joints as indicated. Deposit concrete to
avoid segregation.
1. Consolidate placed concrete with mechanical vibrating equipment
according to ACI 301.
C. Cold-Weather Placement: Comply with ACI 306.1.
D. Hot-Weather Placement: Comply with ACI 301.
3.7
FINISHING FORMED SURFACES
A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing
material with tie holes and defects repaired and patched. Remove fins and
other projections that exceed specified limits on formed-surface irregularities.
1. Apply to concrete surfaces not exposed to view.
B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing
material, arranged in an orderly and symmetrical manner with a minimum of
seams. Repair and patch tie holes and defects. Remove fins and other
projections that exceed specified limits on formed-surface irregularities.
1. Apply to concrete surfaces exposed to public view.
C. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar
unformed surfaces adjacent to formed surfaces, strike off smooth and finish
with a texture matching adjacent formed surfaces. Continue final surface
treatment of formed surfaces uniformly across adjacent unformed surfaces
unless otherwise indicated.
Cast-In-Place Concrete
Section 03300
Statement of Work
3.8
V - 30
PMG Phase 1 Interim Action
FINISHING FLOORS AND SLABS
A. General:
Comply with ACI 302.1R recommendations for screeding,
restraightening, and finishing operations for concrete surfaces. Do not wet
concrete surfaces.
B. Broom Finish: Apply a broom finish to all concrete slabs.
3.9
CONCRETE PROTECTING AND CURING
A. General:
Protect freshly placed concrete from premature drying and
excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather
protection and ACI 301 for hot-weather protection during curing.
B. Evaporation Retarder: Apply evaporation retarder to unformed concrete
surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2
lb/sq. ft. x h before and during finishing operations. Apply according to
manufacturer's written instructions after placing, screeding, and bull floating or
darbying concrete, but before float finishing.
C. Cure concrete according to ACI 308.1, by one or a combination of the
following methods:
1. Moisture Curing:
seven days.
Keep surfaces continuously moist for not less than
2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moistureretaining cover for curing concrete, placed in widest practicable width, with
sides and ends lapped at least 12 inches, and sealed by waterproof tape
or adhesive. Cure for not less than seven days. Immediately repair any
holes or tears during curing period using cover material and waterproof
tape.
3. Curing Compound: Apply uniformly in continuous operation by power
spray or roller according to manufacturer's written instructions. Recoat
areas subjected to heavy rainfall within three hours after initial application.
Maintain continuity of coating and repair damage during curing period.
a. Removal: After curing period has elapsed, remove curing compound
without damaging concrete surfaces by method recommended by
curing compound manufacturer.
4. Curing and Sealing Compound: Apply uniformly to floors and slabs
indicated in a continuous operation by power spray or roller according to
manufacturer's written instructions. Recoat areas subjected to heavy
rainfall within three hours after initial application. Repeat process 24
hours later and apply a second coat. Maintain continuity of coating and
repair damage during curing period.
Cast-In-Place Concrete
Section 03300
Statement of Work
3.10
V - 31
PMG Phase 1 Interim Action
CONCRETE SEALANT
A. Contractor shall seal the surfaces of the slab and sump with concrete sealant
chemically compatible and resistant to trichloroethylene (at a concentration up
to 1,000 parts per billion) and other chlorinated solvents.
B. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
1. Carboline
C. Applying Sealant: Prepare and mix Phenoline 187 Primer & Finish concrete
sealant according to manufacturer's written instructions. Apply primer and
finish coat uniformly to floors and sump surfaces with a sprayer according to
manufacturer's written instructions. Finish shall be gray.
3.11
CONCRETE SURFACE REPAIRS
A. Defective Concrete: Repair and patch defective areas when approved by
Engineer. Remove and replace concrete that cannot be repaired and
patched to Engineer's approval.
3.12
FIELD QUALITY CONTROL
A. Testing and Inspecting: Owner will engage a qualified testing and inspecting
agency to perform field tests and inspections and prepare test reports.
3.13
PROTECTION OF LIQUID FLOOR TREATMENTS
A. Protect liquid floor treatment from damage and wear during the remainder of
construction period.
Use protective methods and materials, including
temporary covering, recommended in writing by liquid floor treatments
installer.
END OF SECTION
Cast-In-Place Concrete
Section 03300
Statement of Work
V - 32
PMG Phase 1 Interim Action
SECTION 04220 - CONCRETE UNIT MASONRY
PART 1 - GENERAL
1.1
SUMMARY
A. Section Includes:
1. Concrete masonry units (CMUs)
2. Steel reinforcing bars
3. CMU sealant.
1.2
PRECONSTRUCTION TESTING
A. Preconstruction Testing Service: Owner will engage a qualified independent
testing agency to perform preconstruction testing indicated below. Retesting
of materials that fail to comply with specified requirements shall be done at
Contractor's expense.
1. Concrete Masonry Unit Test: For each type of unit required, according to
ASTM C 140 for compressive strength.
2. Mortar Test (Property Specification): For each mix required, according to
ASTM C 109 for compressive strength.
3. Mortar Test (Property Specification): For each mix required, according to
ASTM C 780 for compressive strength.
4. Grout Test (Compressive Strength): For each mix required, according to
ASTM C 1019.
1.3
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: For reinforcing steel. Detail bending and placement of unit
masonry reinforcing bars. Comply with ACI 315, "Details and Detailing of
Concrete Reinforcement." Show elevations of reinforced walls.
1.4
INFORMATIONAL SUBMITTALS
A. Material Certificates: For each type and size of product indicated. For
masonry units include material test reports substantiating compliance with
requirements.
B. Mix Designs: For each type of mortar and grout. Include description of type
and proportions of ingredients.
Concrete Unit Masonry
Section 04220
Statement of Work
V - 33
PMG Phase 1 Interim Action
1. Include test reports for mortar mixes required to comply with property
specification. Test according to ASTM C 109 for compressive strength,
ASTM C 1506 for water retention, and ASTM C 91 for air content.
2. Include test reports, according to ASTM C 1019, for grout mixes required
to comply with compressive strength requirement.
1.5
QUALITY ASSURANCE
A. Masonry Standard:
Comply with ACI 530.1/ASCE 6/TMS 602 unless
modified by requirements in the Contract Documents.
1.6
PROJECT CONDITIONS
A. Cold-Weather Requirements: Do not use frozen materials or materials mixed
or coated with ice or frost. Do not build on frozen substrates. Remove and
replace unit masonry damaged by frost or by freezing conditions. Comply
with
cold-weather
construction
requirements
contained
in
ACI 530.1/ASCE 6/TMS 602.
B. Hot-Weather Requirements:
Comply with hot-weather
requirements contained in ACI 530.1/ASCE 6/TMS 602.
construction
PART 2 - PRODUCTS
2.1
MASONRY UNITS, GENERAL
A. Defective Units: Referenced masonry unit standards may allow a certain
percentage of units to contain chips, cracks, or other defects exceeding limits
stated in the standard. Do not use units where such defects will be exposed
in the completed Work.
B. Fire-Resistance Ratings: Where indicated, provide units that comply with
requirements for fire-resistance ratings indicated as determined by testing
according to ASTM E 119, by equivalent masonry thickness, or by other
means, as acceptable to authorities having jurisdiction.
2.2
CONCRETE MASONRY UNITS
A. Shapes: Provide shapes indicated and for lintels, corners, jambs, sashes,
movement joints, headers, bonding, and other special conditions.
B. CMUs: ASTM C 90.
1. Unit Compressive Strength: Provide units with minimum average net-area
compressive strength of 1500 psi.
2. Density Classification: Medium weight.
Concrete Unit Masonry
Section 04220
Statement of Work
2.3
V - 34
PMG Phase 1 Interim Action
CONCRETE MASONRY LINTELS
A. General: Provide the following:
B. Masonry Lintels: Prefabricated or built-in-place masonry lintels made from
bond beam CMUs with reinforcing bars placed as indicated and filled with
coarse grout.
2.4
MORTAR AND GROUT MATERIALS
A. Portland Cement: ASTM C 150, Type I or II, except Type III may be used for
cold-weather construction. Provide natural color or white cement as required
to produce mortar color indicated.
B. Hydrated Lime: ASTM C 207, Type S.
C. Portland Cement-Lime Mix: Packaged blend of portland cement and
hydrated lime containing no other ingredients.
D. Masonry Cement: ASTM C 91.
1. Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a. Capital Materials Corporation; Flamingo Color Masonry Cement
b. Cemex S.A.B. de C.V.
c. Essroc, Italcementi Group
d. Holcim (US) Inc.
e. Lafarge North America Inc.
f. Lehigh Cement Company
g. National Cement Company, Inc.; Coosa Masonry Cement.
E. Mortar Cement: ASTM C 1329.
1. Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a. Lafarge North America Inc.
F. Aggregate for Mortar: ASTM C 144
G. Aggregate for Grout: ASTM C 404
H. Cold-Weather Admixture: Nonchloride, noncorrosive, accelerating admixture
complying with ASTM C 494/C 494M, Type C, and recommended by
manufacturer for use in masonry mortar of composition indicated.
Concrete Unit Masonry
Section 04220
Statement of Work
V - 35
PMG Phase 1 Interim Action
1. Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a. Euclid Chemical Company (The); Accelguard 80
b. Grace Construction Products, W. R. Grace & Co. - Conn.; Morset
c. Sonneborn Products, BASF Aktiengesellschaft; Trimix-NCA.
I. Water: Potable.
2.5
REINFORCEMENT
A. Uncoated Steel Reinforcing Bars: ASTM A 615or ASTM A 706, Grade 60.
2.6
TIES AND ANCHORS
A. Materials: Provide ties and anchors specified in this article that are made
from materials that comply with the following unless otherwise indicated.
1. Hot-Dip Galvanized, Carbon-Steel Wire: ASTM A 82; with ASTM A 153,
Class B-2 coating.
2. Steel Sheet, Galvanized after Fabrication:
Steel, with ASTM A 153, Class B coating.
ASTM A 1008, Commercial
3. Steel Plates, Shapes, and Bars: ASTM A 36.
B. Anchor Bolts: Headed steel bolts complying with ASTM A 307, Grade A; with
ASTM A 563 hex nuts and, where indicated, flat washers; hot-dip galvanized
to comply with ASTM A 153, Class C; of dimensions indicated.
2.7
MORTAR AND GROUT MIXES
A. General: Do not use admixtures, including pigments, air-entraining agents,
accelerators, retarders, water-repellent agents, antifreeze compounds, or
other admixtures unless otherwise indicated.
1. Do not use calcium chloride in mortar or grout.
2. For reinforced masonry, use mortar.
3. Add cold-weather admixture (if used) at same rate for all mortar that will
be exposed to view, regardless of weather conditions, to ensure that
mortar color is consistent.
B. Preblended, Dry Mortar Mix: Furnish dry mortar ingredients in form of a
preblended mix.
Measure quantities by weight to ensure accurate
proportions, and thoroughly blend ingredients before delivering to Project site.
Concrete Unit Masonry
Section 04220
Statement of Work
V - 36
PMG Phase 1 Interim Action
C. Mortar for Unit Masonry: Comply with ASTM C 270, Property Specification.
Provide the following types of mortar for applications stated unless another
type is indicated.
1. For reinforced masonry, use Type S.
D. Grout for Unit Masonry: Comply with ASTM C 476.
1. Use grout of type indicated or, if not otherwise indicated, of type (fine or
coarse) that will comply with Table 1.15.1 in ACI 530.1/ASCE 6/TMS 602
for dimensions of grout spaces and pour height.
2. Proportion grout in accordance with ASTM C 476, Table 1.
3. Provide grout with a slump of 8 to 11 inches as measured according to
ASTM C 143.
PART 3 - EXECUTION
3.1
TOLERANCES
A. Dimensions and Locations of Elements:
1. For dimensions in cross section or elevation do not vary by more than plus
1/2 inch or minus 1/4 inch.
2. For location of elements in plan do not vary from that indicated by more
than plus or minus 1/2 inch.
3. For location of elements in elevation do not vary from that indicated by
more than plus or minus 1/4 inch in a story height or 1/2 inch total.
B. Lines and Levels:
1. For bed joints and top surfaces of bearing walls do not vary from level by
more than 1/4 inch in 10 feet or 1/2 inch maximum.
2. For conspicuous horizontal lines, such as lintels, sills, parapets, and
reveals, do not vary from level by more than 1/8 inch in 10 feet, 1/4 inch in
20 feet, or 1/2 inch maximum.
3. For vertical lines and surfaces do not vary from plumb by more than 1/4
inch in 10 feet , 3/8 inch in 20 feet, or 1/2 inch maximum.
4. For conspicuous vertical lines, such as external corners, door jambs,
reveals, and expansion and control joints, do not vary from plumb by more
than 1/8 inch in 10 feet, 1/4 inch in 20 feet , or 1/2 inch maximum.
5. For lines and surfaces do not vary from straight by more than 1/4 inch in
10 feet, 3/8 inch in 20 feet, or 1/2 inch maximum.
3.2
LAYING MASONRY WALLS
A. Lay out walls in advance for accurate spacing of surface bond patterns with
uniform joint thicknesses and for accurate location of openings, movement-
Concrete Unit Masonry
Section 04220
Statement of Work
V - 37
PMG Phase 1 Interim Action
type joints, returns, and offsets. Avoid using less-than-half-size units,
particularly at corners, jambs, and, where possible, at other locations.
B. Use full-size units without cutting if possible. If cutting is required to provide a
continuous pattern or to fit adjoining construction, cut units with motor-driven
saws; provide clean, sharp, unchipped edges. Allow units to dry before laying
unless wetting of units is specified. Install cut units with cut surfaces and,
where possible, cut edges concealed.
C. Bond Pattern for Exposed Masonry: Unless otherwise indicated, lay exposed
masonry in running bond; do not use units with less than nominal 4-inch
horizontal face dimensions at corners or jambs.
D. Built-in Work: As construction progresses, build in items specified in this and
other Sections. Fill in solidly with masonry around built-in items.
E. Fill space between steel frames and masonry solidly with mortar unless
otherwise indicated.
F. Where built-in items are to be embedded in cores of hollow masonry units,
place a layer of metal lath, wire mesh, or plastic mesh in the joint below and
rod mortar or grout into core.
G. Fill cores in hollow CMUs with grout 24 inches under bearing plates, beams,
lintels, posts, and similar items unless otherwise indicated.
3.3
MORTAR BEDDING AND JOINTING
A. Lay hollow CMUs as follows:
1. With face shells fully bedded in mortar and with head joints of depth equal
to bed joints.
2. With webs fully bedded in mortar in all courses of piers, columns, and
pilasters.
3. With webs fully bedded in mortar in grouted masonry, including starting
course on footings.
4. With entire units, including areas under cells, fully bedded in mortar at
starting course on footings where cells are not grouted.
B. Lay solid masonry units with completely filled bed and head joints; butter ends
with sufficient mortar to fill head joints and shove into place. Do not deeply
furrow bed joints or slush head joints.
C. Tool exposed joints slightly concave when thumbprint hard, using a jointer
larger than joint thickness unless otherwise indicated.
D. Cut joints flush for masonry walls to receive plaster or other direct-applied
finishes (other than paint) unless otherwise indicated.
Concrete Unit Masonry
Section 04220
Statement of Work
3.4
V - 38
PMG Phase 1 Interim Action
ANCHORING MASONRY TO CONCRETE
A. Anchor masonry to structural steel and concrete where masonry abuts or
faces structural steel or concrete to comply with the following:
1. Anchor masonry with pre-installed dowel anchors embedded in concrete.
2. Space anchors as indicated on drawings.
3.5
REINFORCED UNIT MASONRY INSTALLATION
A. Temporary Formwork and Shores: Construct formwork and shores as
needed to support reinforced masonry elements during construction.
1. Construct formwork to provide shape, line, and dimensions of completed
masonry as indicated. Make forms sufficiently tight to prevent leakage of
mortar and grout. Brace, tie, and support forms to maintain position and
shape during construction and curing of reinforced masonry.
2. Do not remove forms and shores until reinforced masonry members have
hardened sufficiently to carry their own weight and other loads that may be
placed on them during construction.
B. Placing Reinforcement:
ASCE 6/TMS 602.
Comply
with
requirements
in
ACI 530.1/
C. Grouting: Do not place grout until entire height of masonry to be grouted has
attained enough strength to resist grout pressure.
1. Comply with requirements in ACI 530.1/ASCE 6/TMS 602 for cleanouts
and for grout placement, including minimum grout space and maximum
pour height.
2. Limit height of vertical grout pours to not more than 48 inches .
D. Sealant: Apply uniformly both exterior and interior faces of all CMU block with
Sure Klean® Weather Seal Blok-Guard® & Graffiti Control per manufacturers
recommendations.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a.
b. Prosoco, Inc.
3.6
FIELD QUALITY CONTROL
A. Testing and Inspecting: Owner will engage special inspectors to perform
tests and inspections and prepare reports. Allow inspectors access to
scaffolding and work areas, as needed to perform tests and inspections.
Concrete Unit Masonry
Section 04220
Statement of Work
V - 39
PMG Phase 1 Interim Action
Retesting of materials that fail to meet specified requirements shall be done at
Contractor's expense.
B. Inspections: Level 1 special inspections according to the "International
Building Code."
1. Begin masonry construction only after inspectors have verified proportions
of site-prepared mortar.
2. Place grout only after inspectors have verified compliance of grout spaces
and of grades, sizes, and locations of reinforcement.
3. Place grout only after inspectors have verified proportions of site-prepared
grout.
C. Testing Prior to Construction: One set of tests.
D. Concrete Masonry Unit Test: For each type of unit provided, according to
ASTM C 140 for compressive strength.
E. Mortar Aggregate Ratio Test (Proportion Specification):
provided, according to ASTM C 780.
For each mix
F. Mortar Test (Property Specification): For each mix provided, according to
ASTM C 780. Test mortar for compressive strength.
G. Grout Test (Compressive Strength): For each mix provided, according to
ASTM C 1019.
3.7
REPAIRING, POINTING, AND CLEANING
A. In-Progress Cleaning: Clean unit masonry as work progresses by dry
brushing to remove mortar fins and smears before tooling joints.
B. Final Cleaning: After mortar is thoroughly set and cured, clean exposed
masonry as follows:
1. Test cleaning methods on sample wall panel; leave one-half of panel
uncleaned for comparison purposes.
2. Clean concrete masonry by cleaning method indicated in NCMA TEK 8-2A
applicable to type of stain on exposed surfaces.
3.8
MASONRY WASTE DISPOSAL
A. Waste Disposal as Fill Material: Dispose of clean masonry waste, including
excess or soil-contaminated sand, waste mortar, and broken masonry units,
by crushing and mixing with fill material as fill is placed.
1. Do not dispose of masonry waste as fill within 18 inches of finished grade.
Concrete Unit Masonry
Section 04220
Statement of Work
V - 40
PMG Phase 1 Interim Action
B. Excess Masonry Waste: Remove excess clean masonry waste that cannot
be used as fill, as described above, and other masonry waste, and legally
dispose of off Owner's property.
END OF SECTION
Concrete Unit Masonry
Section 04220
Statement of Work
V - 41
PMG Phase 1 Interim Action
SECTION 05310 - STEEL DECKING
PART 1 - GENERAL
1.1
SUMMARY
A. Section Includes:
1. Roof deck.
1.2
ACTION SUBMITTALS
A. Product Data: For each type of deck, accessory, and product indicated.
B. Shop Drawings:
1. Include layout and types of deck panels, anchorage details, reinforcing
channels, pans, cut deck openings, special jointing, accessories, and
attachments to other construction.
1.3
INFORMATIONAL SUBMITTALS
A. Welding certificates.
B. Product certificates.
C. Evaluation reports.
D. Field quality-control reports.
1.4
QUALITY ASSURANCE
A. Testing Agency Qualifications: Qualified according to ASTM E 329 for testing
indicated.
B. Welding Qualifications: Qualify procedures and personnel according to
AWS D1.3, "Structural Welding Code - Sheet Steel."
1.5
DELIVERY, STORAGE, AND HANDLING
A. Protect steel deck from corrosion, deformation, and other damage during
delivery, storage, and handling.
B. Stack steel deck on platforms or pallets and slope to provide drainage.
Protect with a waterproof covering and ventilate to avoid condensation.
Steel Decking
Section 05310
Statement of Work
V - 42
PMG Phase 1 Interim Action
PART 2 - PRODUCTS
2.1
PERFORMANCE REQUIREMENTS
A. AISI Specifications: Comply with calculated structural characteristics of steel
deck according to AISI's "North American Specification for the Design of
Cold-Formed Steel Structural Members."
2.2
ROOF DECK
A. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
1. Nucor Corp.; Vulcraft Group.
2. Roof Deck, Inc.
3. Verco Manufacturing Co.
B. Roof Deck: Fabricate panels, without top-flange stiffening grooves, to comply
with "SDI Specifications and Commentary for Steel Roof Deck," in SDI
Publication No. 31, and with the following:
1. Galvanized-Steel Sheet:
zinc coating.
ASTM A 653, Structural Steel (SS), Grade 40
2. Galvanized and Shop-Primed Steel Sheet: ASTM A 653, Structural Steel
(SS), Grade 40, G60 zinc coating; cleaned, pretreated, and primed with
manufacturer's standard baked-on, rust-inhibitive primer.
3. Deck Profile: As indicated on drawings.
4. Profile Depth: As indicated on drawings.
5. Design Uncoated-Steel Thickness: As indicated on drawings.
2.3
ACCESSORIES
A. General: Provide manufacturer's standard accessory materials for deck that
comply with requirements indicated.
B. Mechanical Fasteners: Corrosion-resistant, low-velocity, power-actuated or
pneumatically driven carbon-steel fasteners; or self-drilling, self-threading
screws.
C. Side-Lap Fasteners: Corrosion-resistant, hexagonal washer head; selfdrilling, carbon-steel screws, No. 10 minimum diameter.
D. Flexible Closure Strips: Vulcanized, closed-cell, synthetic rubber.
E. Miscellaneous Sheet Metal Deck Accessories: Steel sheet, minimum yield
strength of 33,000 psi, not less than 0.0359-inch design uncoated thickness,
Steel Decking
Section 05310
Statement of Work
V - 43
PMG Phase 1 Interim Action
of same material and finish as deck; of profile indicated or required for
application.
F. Flat Sump Plates: Single-piece steel sheet, 0.0747 inch thick, of same
material and finish as deck. For drains, cut holes in the field.
G. Galvanizing Repair Paint.
H. Repair Paint: Manufacturer's standard rust-inhibitive primer of same color as
primer.
PART 3 - EXECUTION
3.1
INSTALLATION, GENERAL
A. Install deck panels and accessories according to applicable specifications and
commentary in SDI Publication No. 31, manufacturer's written instructions,
and requirements in this Section.
B. Place deck panels on supporting frame and adjust to final position with ends
accurately aligned and bearing on supporting frame before being permanently
fastened. Do not stretch or contract side-lap interlocks.
C. Place deck panels flat and square and fasten to supporting frame without
warp or deflection.
D. Cut and neatly fit deck panels and accessories around openings and other
work projecting through or adjacent to deck.
E. Provide additional reinforcement and closure pieces at openings as required
for strength, continuity of deck, and support of other work.
F. Comply with AWS requirements and procedures for manual shielded metal
arc welding, appearance and quality of welds, and methods used for
correcting welding work.
G. Mechanical fasteners may be used in lieu of welding to fasten deck. Locate
mechanical fasteners and install according to deck manufacturer's written
instructions.
H. Miscellaneous Roof-Deck Accessories: Install ridge plates, finish strips, end
closures, and reinforcing channels according to deck manufacturer's written
instructions. Weld or mechanically fasten to substrate to provide a complete
deck installation.
1. Weld cover plates at changes in direction of roof-deck panels unless
otherwise indicated.
Steel Decking
Section 05310
Statement of Work
V - 44
PMG Phase 1 Interim Action
I. Pour Stops and Girder Fillers: Weld steel-sheet pour stops and girder fillers
to supporting structure according to SDI recommendations unless otherwise
indicated.
3.2
FIELD QUALITY CONTROL
A. Testing Agency:
inspections.
Engage a qualified testing agency to perform tests and
B. Field welds will be subject to inspection.
C. Testing agency will report inspection results promptly and in writing to
Contractor and Architect.
D. Remove and replace work that does not comply with specified requirements.
E. Additional inspecting, at Contractor's expense, will be performed to determine
compliance of corrected work with specified requirements.
3.3
PROTECTION
A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on
both surfaces of deck with galvanized repair paint according to ASTM A 780
and manufacturer's written instructions.
B. Repair Painting: Wire brush and clean rust spots, welds, and abraded areas
on both surfaces of prime-painted deck immediately after installation, and
apply repair paint.
END OF SECTION
Steel Decking
Section 05310
Statement of Work
V - 45
PMG Phase 1 Interim Action
SECTION 05400 - COLD-FORMED METAL FRAMING
PART 1 - GENERAL
1.1
SUMMARY
A. This Section includes the following:
1. Roof trusses.
1.2
PERFORMANCE REQUIREMENTS
A. Structural Performance: Provide cold-formed metal framing capable of
withstanding design loads within limits and under conditions indicated.
1. Design Loads: As indicated on drawings.
2. Deflection Limits: Design framing systems to withstand design loads
without deflections greater than the following:
a. Roof Trusses: Vertical deflection of 1/240 of the span.
1.3
ACTION SUBMITTALS
A. Product Data: For each type of product and accessory indicated.
B. Shop Drawings: Show layout, spacings, sizes, thicknesses, and types of
cold-formed metal framing; fabrication; and fastening and anchorage details,
including mechanical fasteners.
1. For cold-formed metal framing indicated to comply with design loads,
include structural analysis data signed and sealed by the qualified
professional engineer responsible for their preparation.
1.4
INFORMATIONAL SUBMITTALS
A. Qualification data.
B. Welding certificates.
C. Product test reports.
D. Research/evaluation reports.
1.5
QUALITY ASSURANCE
A. Product Tests: Mill certificates or data from a qualified independent testing
agency indicating steel sheet complies with requirements.
Cold-Formed Metal Framing
Section 05400
Statement of Work
V - 46
PMG Phase 1 Interim Action
B. Welding:
Qualify procedures and personnel according to AWS D1.3,
"Structural Welding Code--Sheet Steel."
C. Fire-Test-Response Characteristics: Where indicated, provide cold-formed
metal framing identical to that of assemblies tested for fire resistance per
ASTM E 119 by a testing and inspecting agency acceptable to authorities
having jurisdiction.
D. AISI Specifications and Standards: Comply with AISI's "North American
Specification for the Design of Cold-Formed Steel Structural Members" and
its "Standard for Cold-Formed Steel Framing - General Provisions."
1. Comply with AISI's "Standard for Cold-Formed Steel Framing - Truss
Design."
2. Comply with AISI's "Standard for Cold-Formed Steel Framing - Header
Design."
E. Comply with AISI's "Standard for Cold-Formed Steel Framing - Prescriptive
Method for One and Two Family Dwellings."
PART 2 - PRODUCTS
2.1
MATERIALS
A. Steel Sheet: ASTM A 1003, Structural Grade, Type H, metallic coated, of
grade and coating weight as follows:
1. Grade: As required by structural performance.
2. Coating: G60.
2.2
ROOF TRUSSES
A. Roof Truss Members: Manufacturer's standard C-shaped steel sections, of
web depths indicated, unpunched, with stiffened flanges.
2.3
FRAMING ACCESSORIES
A. Fabricate
steel-framing
accessories
from
steel
sheet,
ASTM A 1003/A 1003M, Structural Grade, Type H, metallic coated, of same
grade and coating weight used for framing members, unless otherwise
indicated.
B. Steel Shapes and Clips: ASTM A 36/A 36M, zinc coated by hot-dip process
according to ASTM A 123/A 123M.
C. Anchor Bolts: ASTM F 1554, Grade 36, threaded carbon-steel hex-headed
bolts and carbon-steel nuts; and flat, hardened-steel washers; zinc coated by
hot-dip process according to ASTM A 153, Class C.
Cold-Formed Metal Framing
Section 05400
Statement of Work
V - 47
PMG Phase 1 Interim Action
D. Expansion Anchors: Fabricated from corrosion-resistant materials, with
capability to sustain, without failure, a load equal to 5 times design load, as
determined by testing per ASTM E 488 conducted by a qualified independent
testing agency.
E. Power-Actuated Anchors: Fastener system of type suitable for application
indicated, fabricated from corrosion-resistant materials, with capability to
sustain, without failure, a load equal to 10 times design load, as determined
by testing per ASTM E 1190 conducted by a qualified independent testing
agency.
F. Mechanical Fasteners:
ASTM C 1513, corrosion-resistant-coated, selfdrilling, self-tapping steel drill screws.
1. Head Type: Low-profile head beneath sheathing, manufacturer's standard
elsewhere.
2.4
MISCELLANEOUS MATERIALS
A. Galvanizing Repair Paint ASTM A 780.
B. Cement Grout: Portland cement, ASTM C 150, Type I; and clean, natural
sand, ASTM C 404. Mix at ratio of 1 part cement to 2-1/2 parts sand, by
volume, with minimum water required for placement and hydration.
C. Shims: Load bearing, high-density multimonomer plastic, nonleaching.
D. Sealer Gaskets: Closed-cell neoprene foam, 1/4 inch thick, selected from
manufacturer's standard widths to match width of bottom track or rim track
members.
PART 3 - EXECUTION
3.1
PREPARATION
A. Install load bearing shims or grout between the underside of wall bottom track
or rim track and the top of foundation wall or slab at stud or joist locations to
ensure a uniform bearing surface on supporting concrete or masonry
construction.
B. Install sealer gaskets to isolate the underside of wall bottom track or rim track
and the top of foundation wall or slab at stud or joist locations.
3.2
INSTALLATION, GENERAL
A. Install cold-formed metal framing according to AISI's "Standard for ColdFormed Steel Framing - General Provisions" and to manufacturer's written
instructions unless more stringent requirements are indicated.
Cold-Formed Metal Framing
Section 05400
Statement of Work
V - 48
PMG Phase 1 Interim Action
B. Install cold-formed metal framing and accessories plumb, square, and true to
line, and with connections securely fastened.
C. Install framing members in one-piece lengths.
D. Install temporary bracing and supports to secure framing and support loads
comparable in intensity to those for which structure was designed. Maintain
braces and supports in place, undisturbed, until entire integrated supporting
structure has been completed and permanent connections to framing are
secured.
E. Do not bridge building expansion and control joints with cold-formed metal
framing. Independently frame both sides of joints.
F. Install insulation, specified in Division 07 Section "Thermal Insulation," in builtup exterior framing members, such as headers, sills, boxed joists, and
multiple studs at openings, that are inaccessible on completion of framing
work.
G. Fasten hole reinforcing plate over web penetrations that exceed size of
manufacturer's standard punched openings.
H. Erection Tolerances: Install cold-formed metal framing level, plumb, and true
to line to a maximum allowable tolerance variation of 1/8 inch in 10 feet and
as follows:
1. Space individual framing members no more than plus or minus 1/8 inch
from plan location. Cumulative error shall not exceed minimum fastening
requirements of sheathing or other finishing materials.
3.3
TRUSS INSTALLATION
A. Install, bridge, and brace trusses according to Shop Drawings and
requirements in this Section.
B. Truss Spacing: As indicated on drawings.
C. Do not alter, cut, or remove framing members or connections of trusses.
D. Erect trusses with plane of truss webs plumb and parallel to each other, align,
and accurately position at spacings indicated.
E. Erect trusses without damaging framing members or connections.
F. Align webs of bottom chords and load-bearing studs or continuously reinforce
track to transfer loads to structure. Anchor trusses securely at all bearing
points.
Cold-Formed Metal Framing
Section 05400
Statement of Work
V - 49
PMG Phase 1 Interim Action
G. Install continuous bridging and permanently brace trusses as indicated on
Shop Drawings and designed according to LGSEA's Technical Note 551e,
"Design Guide for Permanent Bracing of Cold-Formed Steel Trusses."
3.4
FIELD QUALITY CONTROL
A. Testing: Owner will engage a qualified independent testing and inspecting
agency to perform field tests and inspections and prepare test reports.
B. Field and shop welds will be subject to testing and inspecting.
C. Testing agency will report test results promptly and in writing to Contractor
and Engineer.
D. Remove and replace work where test results indicate that it does not comply
with specified requirements.
E. Additional testing and inspecting, at Contractor's expense, will be performed
to determine compliance of replaced or additional work with specified
requirements.
3.5
REPAIRS AND PROTECTION
A. Galvanizing Repairs: Prepare and repair damaged galvanized coatings on
fabricated and installed cold-formed metal framing with galvanized repair
paint according to ASTM A 780 and manufacturer's written instructions.
B. Provide final protection and maintain conditions, in a manner acceptable to
manufacturer and installer that ensure that cold-formed metal framing is
without damage or deterioration at time of Substantial Completion.
END OF SECTION
Cold-Formed Metal Framing
Section 05400
Statement of Work
V - 50
PMG Phase 1 Interim Action
SECTION 05530 - METAL GRATINGS
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to
this Section.
1.2
SUMMARY
A. Section Includes:
1. Metal bar gratings.
1.3
PERFORMANCE REQUIREMENTS
A. Delegated Design: Design gratings, including comprehensive engineering
analysis by a qualified professional engineer, using performance
requirements and design criteria indicated.
B. Structural Performance: Gratings shall withstand the effects of gravity loads
and the following loads and stresses within limits and under conditions
indicated.
1. Floors: Uniform load of 125 lbf/sq. ft. (6.00 kN/sq. m) or concentrated load
of 2000 lbf (8.90 kN), whichever produces the greater stress.
2. Limit deflection to L/240 or 1/4 inch (6.4 mm), whichever is less.
1.4
ACTION SUBMITTALS
A. Product Data: For the following:
1. Metal bar gratings.
B. Shop Drawings: Include plans, sections, details, and attachments to other
work.
C. Delegated-Design Submittal: For installed products indicated to comply with
performance requirements and design criteria, including analysis data signed
and sealed by the qualified professional engineer responsible for their
preparation.
1.5
INFORMATIONAL SUBMITTALS
A. Qualification Data: For qualified professional engineer.
Metal Gratings
Section 05530
Statement of Work
V - 51
PMG Phase 1 Interim Action
B. Mill Certificates: Signed by manufacturers of stainless-steel sheet certifying
that products furnished comply with requirements.
C. Welding certificates.
D. Paint Compatibility Certificates: From manufacturers of topcoats applied over
shop primers certifying that shop primers are compatible with topcoats.
1.6
QUALITY ASSURANCE
A. Metal Bar Grating Standards: Comply with [NAAMM MBG 531, "Metal Bar
Grating Manual][" and] [NAAMM MBG 532, "Heavy-Duty Metal Bar Grating
Manual]."
B. Welding Qualifications: Qualify procedures and personnel according to
AWS D1.1/D1.1M, "Structural Welding Code - Steel."
1.7
PROJECT CONDITIONS
A. Field Measurements: Verify actual locations of walls and other construction
contiguous with gratings by field measurements before fabrication.
1.8
COORDINATION
A. Coordinate selection of shop primers with topcoats to be applied over them.
Comply with paint and coating manufacturers' written recommendations to
ensure that shop primers and topcoats are compatible with one another.
B. Coordinate installation of anchorages for gratings, grating frames, and
supports. Furnish setting drawings, templates, and directions for installing
anchorages, including sleeves, concrete inserts, anchor bolts, and items with
integral anchors, that are to be embedded in concrete or masonry. Deliver
such items to Project site in time for installation.
PART 2 - PRODUCTS
2.1
FERROUS METALS
A. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.
B. Steel Bars for Bar Gratings:
ASTM A 36/A 36M
ASTM A 1011/A 1011M or ASTM A 1018/A 1018M.
or
steel
strip,
C. Wire Rod for Bar Grating Crossbars: ASTM A 510.
Metal Gratings
Section 05530
Statement of Work
2.2
V - 52
PMG Phase 1 Interim Action
MISCELLANEOUS MATERIALS
A. Welding Rods and Bare Electrodes: Select according to AWS specifications
for metal alloy that is welded.
B. Low-Emitting Materials: Paints and coatings shall comply with the testing and
product requirements of the California Department of Health Services'
"Standard Practice for the Testing of Volatile Organic Emissions from Various
Sources Using Small-Scale Environmental Chambers."
C. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPCPaint 20 and compatible with paints specified to be used over it.
2.3
FABRICATION
A. Shop Assembly: Fabricate grating sections in shop to greatest extent
possible to minimize field splicing and assembly. Disassemble units only as
necessary for shipping and handling limitations. Use connections that
maintain structural value of joined pieces. Clearly mark units for reassembly
and coordinated installation.
B. Cut, drill, and punch material cleanly and accurately. Remove burrs and ease
edges to a radius of approximately 1/32 inch (1 mm) unless otherwise
indicated. Remove sharp or rough areas on exposed surfaces.
C. Form from materials of size, thickness, and shapes indicated, but not less
than that needed to support indicated loads.
D. Fit exposed connections accurately together to form hairline joints.
E. Welding: Comply with AWS recommendations and the following:
1. Use materials and methods that minimize distortion and develop strength
and corrosion resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
F. Provide for anchorage of type indicated; coordinate with supporting structure.
Fabricate and space the anchoring devices to secure gratings, frames, and
supports rigidly in place and to support indicated loads.
2.4
METAL BAR GRATINGS
A. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the work
include, but are not limited to, the following:
1. Grating Pacific, Inc.
2. IKG Industries; a division of Harsco Corporation.
Metal Gratings
Section 05530
Statement of Work
V - 53
PMG Phase 1 Interim Action
3. Marwas Steel Co.; Laurel Steel Products Division.
B. Metal Bar Grating:
1. Bearing Bar Spacing: 1-3/16 inches (30 mm) O.C.
2. Bearing Bar Depth: 2 inches (51 mm)
3. Bearing Bar Thickness: 3/16 inch (4.8 mm).
4. Crossbar Spacing: 4 inches (102 mm)] O.C.
5. Steel Finish: Hot-dip galvanized with a coating weight of not less than 1.8
oz./sq. ft. (550 g/sq. m) of coated surface.
C. Do not notch bearing bars at supports to maintain elevation.
2.5
GRATING FRAMES AND SUPPORTS
A. Frames and Supports for Metal Gratings: Fabricate from metal shapes,
plates, and bars of welded construction to sizes, shapes, and profiles
indicated and as necessary to receive gratings. Miter and weld connections
for perimeter angle frames. Cut, drill, and tap units to receive hardware and
similar items.
1. Unless otherwise indicated, fabricate from same basic metal as gratings.
B. Galvanize steel frames and supports in the following locations:
1. Interior.
2.6
STEEL FINISHES
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal
Products" for recommendations for applying and designating finishes.
B. Finish gratings, frames, and supports after assembly.
C. Galvanizing:
Hot-dip galvanize items as indicated to comply with
ASTM A 153/A 153M
for
steel
and
iron
hardware
and
with
ASTM A 123/A 123M for other steel and iron products.
1. Do not quench or apply post galvanizing treatments that might interfere
with paint adhesion.
PART 3 - EXECUTION
3.1
INSTALLATION, GENERAL
A. Fastening to In-Place Construction:
Provide anchorage devices and
fasteners where necessary for securing gratings to in-place construction.
Metal Gratings
Section 05530
Statement of Work
V - 54
PMG Phase 1 Interim Action
Include threaded fasteners for concrete and masonry inserts, through-bolts,
lag bolts, and other connectors.
B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required
for installing gratings. Set units accurately in location, alignment, and
elevation; measured from established lines and levels and free of rack.
C. Provide temporary bracing or anchors in formwork for items that are to be
built into concrete or masonry.
D. Fit exposed connections accurately together to form hairline joints.
1. Weld connections that are not to be left as exposed joints but cannot be
shop welded because of shipping size limitations. Do not weld, cut, or
abrade the surfaces of exterior units that have been hot-dip galvanized
after fabrication and are for bolted or screwed field connections.
E. Attach toeplates to gratings by welding at locations indicated.
F. Field Welding: Comply with the following requirements:
1. Use materials and methods that minimize distortion and develop strength
and corrosion resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove welding flux immediately.
G. Corrosion Protection: Coat concealed surfaces of aluminum that will come
into contact with grout, concrete, masonry, wood, or dissimilar metals, with a
heavy coat of bituminous paint.
3.2
INSTALLING METAL BAR GRATINGS
A. General: Install gratings to comply with recommendations of referenced
metal bar grating standards that apply to grating types and bar sizes
indicated, including installation clearances and standard anchoring details.
B. Attach removable units to supporting members with type and size of clips and
fasteners indicated or, if not indicated, as recommended by grating
manufacturer for type of installation conditions shown.
C. Attach nonremovable units to supporting members by welding where both
materials are same; otherwise, fasten by bolting as indicated above.
3.3
ADJUSTING AND CLEANING
A. Touchup Painting: Immediately after erection, clean field welds, bolted
connections, and abraded areas of shop paint, and paint exposed areas with
same material as used for shop painting to comply with SSPC-PA 1
requirements for touching up shop-painted surfaces.
Metal Gratings
Section 05530
Statement of Work
V - 55
PMG Phase 1 Interim Action
1. Apply by brush or spray to provide a minimum 2.0-mil (0.05-mm) dry film
thickness.
B. Touchup Painting: Cleaning and touchup painting of field welds, bolted
connections, and abraded areas of shop paint are specified in
Section 099113 "Exterior Painting" and Section 099123 "Interior Painting."
C. Galvanized Surfaces: Clean field welds, bolted connections, and abraded
areas and repair galvanizing to comply with ASTM A 780.
END OF SECTION
Metal Gratings
Section 05530
Statement of Work
V - 56
PMG Phase 1 Interim Action
SECTION 07410 - METAL ROOF PANELS
PART 1 - GENERAL
1.1
SUMMARY
A. Section Includes:
1. Standing-seam metal roof panels.
2. Metal soffit panels.
B. Related Sections:
1. Division 07 Section "Sheet Metal Roofing" for custom-fabricated and onsite, roll-formed sheet metal roofing.
1.2
PERFORMANCE REQUIREMENTS
A. Hydrostatic-Head Resistance: No water penetration when tested according to
ASTM E 2140.
B. Wind-Uplift Resistance: Provide metal roof panel assemblies that comply
with UL 580 for wind-uplift-resistance class indicated.
1. Uplift Rating: UL 90.
C. FMG Listing: Provide metal roof panels and component materials that comply
with requirements in FMG 4471 as part of a panel roofing system and that are
listed in FMG's "Approval Guide" for Class 1 or noncombustible construction,
as applicable. Identify materials with FMG markings.
1. Hail Resistance: MH.
D. Structural Performance: Provide metal roof panel assemblies capable of
withstanding the effects of gravity loads and the following loads and stresses
within limits and under conditions indicated, based on testing according to
ASTM E 1592:
1. Wind Loads: Determine loads based on the following minimum design
wind pressures:
a. Uniform pressure of 16 lbf/sq. ft., acting inward or outward.
2. Snow Loads: 25 lbf/sq. ft.
3. Deflection Limits: Metal roof panel assemblies shall withstand wind and
snow loads with vertical deflections no greater than 1/240 of the span.
1.3
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
Metal Roof Panels
Section 07410
Statement of Work
V - 57
PMG Phase 1 Interim Action
B. Shop Drawings: Show fabrication and installation layouts of metal roof
panels; details of edge conditions, side-seam and endlap joints, panel
profiles, corners, anchorages, trim, flashings, closures, and accessories; and
special details. Distinguish between factory- and field-assembled work.
C. Samples: For each type of exposed finish required.
D. Delegated-Design Submittal: For metal roof panel assembly indicated to
comply with performance requirements and design criteria, including analysis
data and calculations signed and sealed by the qualified professional
engineer responsible for their preparation.
1.4
INFORMATIONAL SUBMITTALS
A. Coordination Drawings: Roof plans, drawn to scale, based on input from
installers of the items involved.
B. Manufacturer Certificates: Signed by manufacturer certifying that roof panels
comply with energy performance requirements specified in "Performance
Requirements" Article.
1. Submit evidence of meeting performance requirements.
C. Product test reports.
D. Field quality-control reports.
E. Warranties: Samples of special warranties.
1.5
CLOSEOUT SUBMITTALS
A. Maintenance data.
1.6
QUALITY ASSURANCE
A. Installer Qualifications:
manufacturer.
1.7
An employer of workers trained and approved by
WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer
agrees to repair or replace metal roof panel assemblies that fail in materials
or workmanship within specified warranty period.
1. Warranty Period: 5 years from date of Substantial Completion.
B. Special Warranty on Panel Finishes: Manufacturer's standard form in which
manufacturer agrees to repair finish or replace metal roof panels that show
evidence of deterioration of factory-applied finishes within specified warranty
period.
Metal Roof Panels
Section 07410
Statement of Work
V - 58
PMG Phase 1 Interim Action
1. Finish Warranty Period: 20 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1
PANEL MATERIALS
A. Metallic-Coated Steel Sheet: Restricted flatness steel sheet metallic coated
by the hot-dip process and prepainted by the coil-coating process to comply
with ASTM A 755/A 755M.
1. Aluminum-Zinc Alloy-Coated Steel Sheet: ASTM A 792, Class AZ50
coating designation, Grade 40; structural quality.
2. Surface: Smooth, flat finish.
3. Concealed Finish: Manufacturer's standard white or light-colored acrylic
or polyester backer finish.
B. Panel Sealants:
1. Sealant Tape:
Pressure-sensitive, 100 percent solids, gray
polyisobutylene compound sealant tape with release-paper backing; 1/2
inch wide and 1/8 inch thick.
2. Joint Sealant: ASTM C 920; as recommended in writing by metal roof
panel manufacturer.
3. Butyl-Rubber-Based, Solvent-Release Sealant: ASTM C 1311.
2.2
UNDERLAYMENT MATERIALS
A. Self-Adhering, High-Temperature Sheet: 30 to 40 mils thick minimum,
consisting of slip-resisting, polyethylene-film top surface laminated to layer of
butyl or SBS-modified asphalt adhesive, with release-paper backing; cold
applied. Provide primer when recommended by underlayment manufacturer.
1. Thermal Stability: Stable after testing at 240 deg F; ASTM D 1970.
2. Low-Temperature Flexibility:
ASTM D 1970.
Passes after testing at minus 20 deg F;
3. Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a. Carlisle Coatings & Waterproofing Inc., Div. of Carlisle Companies Inc.;
CCW WIP 300HT.
b. Grace Construction Products; a unit of Grace, W. R. & Co.; Ultra.
c. Henry Company; Blueskin PE200 HT.
d. Metal-Fab Manufacturing, LLC; MetShield.
e. Owens Corning; WeatherLock Metal High Temperature Underlayment.
Metal Roof Panels
Section 07410
Statement of Work
V - 59
PMG Phase 1 Interim Action
B. Felts: ASTM D 226, Type II (No. 30), asphalt-saturated organic felts.
C. Slip Sheet:
application.
2.3
Manufacturer's recommended slip sheet, of type required for
MISCELLANEOUS MATERIALS
A. Panel Fasteners: Self-tapping screws, bolts, nuts, self-locking rivets and
bolts, end-welded studs, and other suitable fasteners designed to withstand
design loads. Provide exposed fasteners with heads matching color of metal
roof panels by means of plastic caps or factory-applied coating. Provide
EPDM, PVC, or neoprene sealing washers.
B. Bituminous Coating:
Cold-applied asphalt mastic, SSPC-Paint 12,
compounded for 15-mil dry film thickness per coat. Provide inert-type
noncorrosive compound free of asbestos fibers, sulfur components, and other
deleterious impurities.
2.4
STANDING-SEAM METAL ROOF PANELS
A. General: Provide factory-formed metal roof panels designed to be installed
by lapping and interconnecting raised side edges of adjacent panels with joint
type indicated and mechanically attaching panels to supports using concealed
clips in side laps. Include clips, cleats, pressure plates, and accessories
required for weathertight installation.
1. Steel Panel Systems: Unless more stringent requirements are indicated,
comply with ASTM E 1514.
2. Aluminum Panel Systems: Unless more stringent requirements are
indicated, comply with ASTM E 1637.
3. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. AEP-Span.
4. Profile: Vertical-rib, snap-joint, as indicated on Drawings.
5. Material: Aluminum-zinc alloy-coated steel sheet, 0.028-inch nominal
thickness.
a. Exterior Finish: 2-coat fluoropolymer.
6. Clips:
a. Material: Stainless steel.
7. Joint Type: As standard with manufacturer.
8. Panel Coverage: 16”.
9. Panel Height: 1½”.
Metal Roof Panels
Section 07410
Statement of Work
2.5
V - 60
PMG Phase 1 Interim Action
METAL SOFFIT PANELS
A. General: Provide factory-formed perforated metal soffit panels designed to
be installed by lapping and interconnecting side edges of adjacent panels and
mechanically attaching through panel to supports using concealed fasteners
in side laps. Include accessories required for weathertight installation.
B. Metal Soffit Panels: Match profile and material of metal roof panels.
1. Finish: Match finish and color of metal roof panels.
2. Sealant: Factory applied within interlocking joint.
3. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. AEP-Span.
4. Profile: Flush as indicated on Drawings.
5. Material: Same material, finish, and color as metal roof panels.
6. Sealant: Factory applied within interlocking joint.
2.6
ACCESSORIES
A. Roof Panel Accessories: Provide components approved by roof panel
manufacturer and as required for a complete metal roof panel assembly
including trim, copings, fasciae, corner units, ridge closures, clips, flashings,
sealants, gaskets, fillers, closure strips, and similar items. Match material and
finish of metal roof panels unless otherwise indicated.
1. Closures: Provide closures at eaves and ridges, fabricated of same metal
as metal roof panels.
2. Closure Strips: Closed-cell, expanded, cellular, rubber or crosslinked,
polyolefin-foam or closed-cell laminated polyethylene; minimum 1-inchthick, flexible closure strips; cut or premolded to match metal roof panel
profile. Provide closure strips where indicated or necessary to ensure
weathertight construction.
3. Backing Plates: Provide metal backing plates at panel end splices,
fabricated from material recommended by manufacturer.
B. Flashing and Trim: Formed from same material as roof panels, prepainted
with coil coating, minimum 0.018 inch thick. Provide flashing and trim as
required to seal against weather and to provide finished appearance.
Locations include, but are not limited to, eaves, rakes, corners, bases, framed
openings, ridges, fasciae, and fillers. Finish flashing and trim with same finish
system as adjacent metal roof panels.
C. Gutters: Formed from same material roof panels. Match profile of gable trim,
complete with end pieces, outlet tubes, and other special pieces as required.
Metal Roof Panels
Section 07410
Statement of Work
V - 61
PMG Phase 1 Interim Action
Fabricate in minimum 96-inch- long sections, of size and metal thickness
according to SMACNA's "Architectural Sheet Metal Manual." Furnish gutter
supports spaced a maximum of 36 inches O.C., fabricated from same metal
as gutters. Provide wire ball strainers of compatible metal at outlets. Finish
gutters to match metal roof panels.
D. Downspouts: Formed from same material as roof panels. Fabricate in 10foot- long sections, complete with formed elbows and offsets, of size and
metal thickness according to SMACNA's "Architectural Sheet Metal Manual."
Finish downspouts to match gutters.
2.7
FABRICATION
A. Fabricate and finish metal roof panels and accessories at the factory to
greatest extent possible, by manufacturer's standard procedures and
processes and as necessary to fulfill indicated performance requirements.
Comply with indicated profiles and with dimensional and structural
requirements.
B. Provide panel profile, including major ribs and intermediate stiffening ribs, if
any, for full length of panel.
C. Fabricate metal roof panel side laps with factory-installed captive gaskets or
separator strips that provide a tight seal and prevent metal-to-metal contact,
in a manner that will seal weathertight and minimize noise from movements
within panel assembly.
D. Sheet Metal Accessories: Fabricate flashing and trim to comply with
recommendations in SMACNA's "Architectural Sheet Metal Manual" that
apply to the design, dimensions, metal, and other characteristics of item
indicated.
PART 3 - EXECUTION
3.1
PREPARATION
A. Substrate Board: Install substrate boards over roof deck on entire roof
surface. Attach with substrate-board fasteners.
1. Install substrate board with long joints in continuous straight lines,
perpendicular to roof slopes with end joints staggered between rows.
Tightly butt substrate boards together.
B. Miscellaneous Framing: Install roof panel support members and anchorage
according to metal roof panel manufacturer's written instructions.
Metal Roof Panels
Section 07410
Statement of Work
3.2
V - 62
PMG Phase 1 Interim Action
UNDERLAYMENT INSTALLATION
A. Self-Adhering Sheet Underlayment: Apply primer if required by manufacturer.
Comply with temperature restrictions of underlayment manufacturer for
installation. Apply at locations indicated on Drawings, wrinkle free, in shingle
fashion to shed water, and with end laps of not less than 6 inches staggered
24 inches between courses. Overlap side edges not less than 3 1/2 inches.
Roll laps with roller. Cover underlayment within 14 days.
B. Felt Underlayment: Apply at locations indicated on Drawings, in shingle
fashion to shed water, and with lapped joints of not less than 2 inches.
C. Apply slip sheet over underlayment before installing metal roof panels.
D. Install flashings to cover underlayment to comply with requirements specified
in Division 07 Section "Sheet Metal Flashing and Trim."
3.3
METAL ROOF PANEL INSTALLATION
A. Standing-Seam Metal Roof Panels: Fasten metal roof panels to supports with
concealed clips at each standing-seam joint at location, spacing, and with
fasteners recommended by manufacturer.
1. Install clips to supports with self-tapping fasteners.
2. Install pressure plates at locations indicated in manufacturer's written
installation instructions.
3. Snap Joint: Nest standing seams and fasten together by interlocking and
completely engaging factory-applied sealant.
4. Seamed Joint: Crimp standing seams with manufacturer-approved,
motorized seamer tool so clip, metal roof panel, and factory-applied
sealant are completely engaged.
B. Metal Soffit Panels: Provide metal soffit panels full width of soffits. Install
panels perpendicular to support framing.
1. Flash and seal panels with weather closures where metal soffit panels
meet walls and at perimeter of all openings.
3.4
ACCESSORY INSTALLATION
A. General:
Install accessories with positive anchorage to building and
weathertight mounting and provide for thermal expansion. Coordinate
installation with flashings and other components.
1. Install components required for a complete metal roof panel assembly
including trim, copings, ridge closures, seam covers, flashings, sealants,
gaskets, fillers, closure strips, and similar items.
Metal Roof Panels
Section 07410
Statement of Work
V - 63
PMG Phase 1 Interim Action
2. Flashing and Trim:
Comply with performance requirements,
manufacturer's written installation instructions, and SMACNA's
"Architectural Sheet Metal Manual." Provide concealed fasteners where
possible, and set units true to line and level as indicated. Install work with
laps, joints, and seams that will be permanently watertight and weather
resistant.
3. Provide elbows at base of downspouts to direct water away from building.
3.5
CLEANING
A. Remove temporary protective coverings and strippable films, if any, as metal
roof panels are installed unless otherwise indicated in manufacturer's written
installation instructions. On completion of metal roof panel installation, clean
finished surfaces as recommended by metal roof panel manufacturer.
Maintain in a clean condition during construction.
END OF SECTION
Metal Roof Panels
Section 07410
Statement of Work
V - 64
PMG Phase 1 Interim Action
SECTION 08110 - HOLLOW METAL DOORS AND FRAMES
PART 1 - GENERAL
1.1
SUMMARY
A. Section Includes:
1. Standard hollow metal doors and frames.
1.2
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: Include elevations, door edge details, frame profiles, metal
thicknesses, preparations for hardware, and other details.
C. Samples for Initial Selection: For units with factory-applied color finishes.
D. Samples for Verification: For each type of exposed finish required.
E. Schedule: Prepared by or under the supervision of supplier, using same
reference numbers for details and openings as those on Drawings.
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
1. Ceco Door Products; an Assa Abloy Group company.
2. Steelcraft; an Ingersoll-Rand company.
2.2
MATERIALS
A. Metallic-Coated Steel Sheet: ASTM A 653, Commercial Steel (CS), Type B;
with minimum G60 metallic coating.
B. Frame Anchors:
ASTM A 591, Commercial Steel (CS), 40Z coating
designation; mill phosphatized.
1. For anchors built into exterior walls, steel sheet complying with
ASTM A 1008/ or ASTM A 1011, hot-dip galvanized according to
ASTM A 153, Class B.
Hollow Metal Doors and Frames
Section 08110
Statement of Work
C. Inserts, Bolts, and
ASTM A 153/A 153M.
V - 65
Fasteners:
PMG Phase 1 Interim Action
Hot-dip
galvanized
D. Bituminous Coating:
Cold-applied asphalt mastic,
compounded for 15-mil dry film thickness per coat.
2.3
according
to
SSPC-Paint 12,
STANDARD HOLLOW METAL DOORS
A. General: Comply with ANSI/SDI A250.8.
1. Design: Flush panel.
B. Exterior Doors: Face sheets fabricated from metallic-coated steel sheet.
Comply with ANSI/SDI A250.8 for level and model and ANSI/SDI A250.4 for
physical performance level:
1. Level 2 and Physical Performance Level B (Heavy Duty), Model 1 (Full
Flush).
C. Hardware Reinforcement: ANSI/SDI A250.6.
2.4
STANDARD HOLLOW METAL FRAMES
A. General: Comply with ANSI/SDI A250.8.
B. Exterior Frames: Fabricated from metallic-coated steel sheet.
1. Fabricate frames with mitered or coped corners.
2. Fabricate frames as full profile welded unless otherwise indicated.
3. Frames for Level 2 Steel Doors: 16 gauge.
C. Hardware Reinforcement: ANSI/SDI A250.6.
2.5
FRAME ANCHORS
A. Jamb Anchors:
1. Masonry Type: Adjustable strap-and-stirrup or T-shaped anchors to suit
frame size, not less than 0.042 inch thick, with corrugated or perforated
straps not less than 2 inches wide by 10 inches long; or wire anchors not
less than 0.177 inch thick.
B. Floor Anchors: Formed from same material as frames, not less than 0.042
inch thick, and as follows:
1. Monolithic Concrete Slabs: Clip-type anchors, with two holes to receive
fasteners.
2. Separate Topping Concrete Slabs:
Adjustable-type anchors with
extension clips, allowing not less than 2-inch height adjustment.
Terminate bottom of frames at finish floor surface.
Hollow Metal Doors and Frames
Section 08110
Statement of Work
2.6
V - 66
PMG Phase 1 Interim Action
FABRICATION
A. Tolerances: Fabricate hollow metal work to tolerances indicated in SDI 117.
B. Hollow Metal Doors:
1. Exterior Doors: Provide weep-hole openings in bottom of exterior doors.
Seal joints in top edges of doors against water penetration.
C. Hollow Metal Frames: Where frames are fabricated in sections, provide
alignment plates or angles at each joint, fabricated of same thickness metal
as frames.
1. Welded Frames: Weld flush face joints continuously; grind, fill, dress, and
make smooth, flush, and invisible.
2. Provide countersunk, flat- or oval-head exposed screws and bolts for
exposed fasteners unless otherwise indicated.
3. Floor Anchors: Weld anchors to bottom of jambs and mullions with at
least four spot welds per anchor.
4. Jamb Anchors: Provide number and spacing of anchors as follows:
a. Masonry Type: Locate anchors not more than 18 inches from top and
bottom of frame. Space anchors not more than 32 inches O.C. and as
follows:
1)
2)
Three anchors per jamb from 60 to 90 inches high.
Four anchors per jamb from 90 to 120 inches high.
D. Hardware Preparation: Factory prepare hollow metal work to receive
templated mortised hardware according to the Door Hardware Schedule and
templates furnished as specified in Division 08 Section "Door Hardware."
1. Locate hardware as indicated, or if not indicated, according to
ANSI/SDI A250.8.
2. Reinforce doors and frames to receive nontemplated, mortised and
surface-mounted door hardware.
3. Comply with applicable requirements in ANSI/SDI A250.6 and
ANSI/DHI A115 Series specifications for preparation of hollow metal work
for hardware.
4. Coordinate locations of conduit and wiring boxes for electrical connections
with Division 26 electrical Sections.
E. Stops and Moldings: Provide stops and moldings around glazed lites where
indicated. Form corners of stops and moldings with butted or mitered hairline
joints.
1. Single Glazed Lites: Provide fixed stops and moldings welded on secure
side of hollow metal work.
Hollow Metal Doors and Frames
Section 08110
Statement of Work
V - 67
PMG Phase 1 Interim Action
2. Multiple Glazed Lites: Provide fixed and removable stops and moldings
so that each glazed lite is capable of being removed independently.
3. Provide fixed frame moldings on outside of exterior and on secure side of
interior doors and frames.
4. Provide loose stops and moldings on inside of hollow metal work.
5. Coordinate rabbet width between fixed and removable stops with type of
glazing and type of installation indicated.
2.7
STEEL FINISHES
A. Prime Finish: Apply manufacturer's standard primer immediately after
cleaning and pretreating.
1. Shop Primer: ANSI/SDI A250.10.
B. Factory-Applied Paint Finish: ANSI/SDI A250.3.
PART 3 - EXECUTION
3.1
INSTALLATION
A. Hollow Metal Frames: Comply with ANSI/SDI A250.11.
1. Set frames accurately in position, plumbed, aligned, and braced securely
until permanent anchors are set. After wall construction is complete,
remove temporary braces, leaving surfaces smooth and undamaged.
a. Where frames are fabricated in sections because of shipping or
handling limitations, field splice at approved locations by welding face
joint continuously; grind, fill, dress, and make splice smooth, flush, and
invisible on exposed faces.
b. Install frames with removable glazing stops located on secure side of
opening.
c. Install door silencers in frames before grouting.
d. Remove temporary braces necessary for installation only after frames
have been properly set and secured.
e. Check plumbness, squareness, and twist of frames as walls are
constructed. Shim as necessary to comply with installation tolerances.
f. Field apply bituminous coating to backs of frames that are filled with
grout containing antifreezing agents.
2. Floor Anchors: Provide floor anchors for each jamb and mullion that
extends to floor, and secure with postinstalled expansion anchors.
a. Floor anchors may be set with powder-actuated fasteners instead of
postinstalled expansion anchors if so indicated and approved on Shop
Drawings.
Hollow Metal Doors and Frames
Section 08110
Statement of Work
V - 68
PMG Phase 1 Interim Action
3. Masonry Walls: Coordinate installation of frames to allow for solidly filling
space between frames and masonry with grout.
4. Installation Tolerances: Adjust hollow metal door frames for squareness,
alignment, twist, and plumb to the following tolerances:
a. Squareness: Plus or minus 1/16 inch, measured at door rabbet on a
line 90 degrees from jamb perpendicular to frame head.
b. Alignment: Plus or minus 1/16 inch, measured at jambs on a
horizontal line parallel to plane of wall.
c. Twist: Plus or minus 1/16 inch, measured at opposite face corners of
jambs on parallel lines, and perpendicular to plane of wall.
d. Plumbness: Plus or minus 1/16 inch, measured at jambs at floor.
B. Hollow Metal Doors: Fit hollow metal doors accurately in frames, within
clearances specified below. Shim as necessary.
1. Non-Fire-Rated Standard Steel Doors:
a. Jambs and Head: 1/8 inch plus or minus 1/16 inch.
b. Between Edges of Pairs of Doors: 1/8 inch plus or minus 1/16 inch.
c. Between Bottom of Door and Top of Threshold: Maximum 3/8 inch.
d. Between Bottom of Door and Top of Finish Floor (No Threshold):
Maximum 3/4 inch.
3.2
ADJUSTING AND CLEANING
A. Final Adjustments:
Check and readjust operating hardware items
immediately before final inspection. Leave work in complete and proper
operating condition. Remove and replace defective work, including hollow
metal work that is warped, bowed, or otherwise unacceptable.
B. Prime-Coat Touchup: Immediately after erection, sand smooth rusted or
damaged areas of prime coat and apply touchup of compatible air-drying,
rust-inhibitive primer.
C. Metallic-Coated Surfaces: Clean abraded areas and repair with galvanizing
repair paint according to manufacturer's written instructions.
END OF SECTION
Hollow Metal Doors and Frames
Section 08110
Statement of Work
V - 69
PMG Phase 1 Interim Action
SECTION 08330 - OVERHEAD COILING DOORS
PART 1 - GENERAL
1.1
SUMMARY
A. Section includes:
1. Service doors.
B. Related Section:
1. Division 05 Section "Metal Fabrications" for miscellaneous steel supports.
1.2
PERFORMANCE REQUIREMENTS
A. Structural Performance, Exterior Doors: Exterior overhead coiling doors shall
withstand the wind loads, the effects of gravity loads, and loads and stresses
within limits and under conditions indicated according to SEI/ASCE 7.
1. Wind Loads: Uniform pressure (velocity pressure) of 20 lbf/sq. ft. (960
Pa), acting inward and outward.
B. Windborne-Debris-Impact-Resistance Performance:
Provide impactprotective overhead coiling doors that pass missile-impact and cyclicpressure tests when tested according to ASTM E 1886 and ASTM E 1996.
1. Large Missile Test:
(9.144 m) of grade.
For overhead coiling doors located within 30 feet
C. Seismic Performance: Overhead coiling doors shall withstand the effects of
earthquake motions determined according to SEI/ASCE 7.
1.3
ACTION SUBMITTALS
A. Product Data:
accessory.
For each type and size of overhead coiling door and
B. Shop Drawings: For each installation and for special components not
dimensioned or detailed in manufacturer's product data. Include plans,
elevations, sections, details, and attachments to other work.
1. Detail equipment assemblies and indicate dimensions, weights, loads,
required clearances, method of field assembly, components, and location
and size of each field connection.
2. Show locations of replaceable fusible links.
3. Wiring Diagrams: For power, signal, and control wiring.
C. Samples: For each exposed product and for each color and texture specified.
Overhead Coiling Doors
Section 08330
Statement of Work
1.4
V - 70
PMG Phase 1 Interim Action
INFORMATIONAL SUBMITTALS
A. Seismic Qualification Certificates: For overhead coiling doors, accessories,
and components, from manufacturer.
B. Oversize Construction Certification: For door assemblies required being firerated and that exceed size limitations of labeled assemblies.
1.5
CLOSEOUT SUBMITTALS
A. Maintenance Data.
1.6
QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is
trained and approved for both installation and maintenance of units required
for this Project.
B. Electrical Components, Devices, and Accessories: Listed and labeled as
defined in NFPA 70, by a qualified testing agency, and marked for intended
location and application.
PART 2 - PRODUCTS
2.1
DOOR CURTAIN MATERIALS AND CONSTRUCTION
A. Door Curtains: Fabricate overhead coiling-door curtain of interlocking metal
slats, designed to withstand wind loading indicated, in a continuous length for
width of door without splices. Unless otherwise indicated, provide slats of
thickness and mechanical properties recommended by door manufacturer for
performance, size, and type of door indicated, and as follows:
1. Metal Interior Curtain-Slat Facing:
face.
Match metal of exterior curtain-slat
B. Bottom Bar for Service Doors: Consisting of two angles, each not less than
1-1/2 by 1-1/2 by 1/8 inch (38 by 38 by 3 mm) thick; fabricated from metal to
match curtain slats and finish.
C. Curtain Jamb Guides: Manufacturer's standard angles or channels and
angles of same material and finish as curtain slats unless otherwise indicated,
with sufficient depth and strength to retain curtain, to allow curtain to operate
smoothly, and to withstand loading. Slot bolt holes for guide adjustment.
Provide removable stops on guides to prevent over travel of curtain.
1. Removable Posts and Jamb Guides for Counter Doors: Manufacturer's
standard.
Overhead Coiling Doors
Section 08330
Statement of Work
2.2
V - 71
PMG Phase 1 Interim Action
HOOD
A. General: Form sheet metal hood to entirely enclose coiled curtain and
operating mechanism at opening head. Contour to fit end brackets to which
hood is attached. Roll and reinforce top and bottom edges for stiffness.
Form closed ends for surface-mounted hoods and fascia for any portion of
between-jamb mounting that project beyond wall face. Equip hood with
intermediate support brackets as required to prevent sagging.
1. Include automatic drop baffle on fire-rated doors to guard against passage
of smoke or flame.
2. Exterior-Mounted Doors: Fabricate hood to act as weather protection and
with a perimeter sealant-joint-bead profile for applying joint sealant.
2.3
LOCKING DEVICES
A. Slide Bolt: Fabricate with side-locking bolts to engage through slots in tracks
for locking by padlock, located on both left and right jamb sides, operable
from coil side.
2.4
CURTAIN ACCESSORIES
A. Weather seals: Equip each exterior door with weather-stripping gaskets fitted
to entire perimeter of door for a weather tight installation, unless otherwise
indicated.
B. Push/Pull Handles: Equip each push-up-operated or emergency-operated
door with lifting handles on each side of door, finished to match door.
2.5
COUNTERBALANCING MECHANISM
A. General: Counterbalance doors by means of manufacturer's standard
mechanism with an adjustable-tension, steel helical torsion spring mounted
around a steel shaft and contained in a spring barrel connected to top of
curtain with barrel rings. Use grease-sealed bearings or self-lubricating
graphite bearings for rotating members.
B. Brackets: Manufacturer's standard mounting brackets of either cast iron or
cold-rolled steel plate.
2.6
MANUAL DOOR OPERATORS
A. Equip door with manufacturer's recommended manual door operator unless
another type of door operator is indicated.
B. Push-up Door Operation: Design counterbalance mechanism that required lift
or pull for door operation does not exceed 25 lbf (111 N).
Overhead Coiling Doors
Section 08330
Statement of Work
V - 72
PMG Phase 1 Interim Action
C. Chain-Hoist Operator: Consisting of endless steel hand chain, chain-pocket
wheel and guard, and gear-reduction unit with a maximum 25 lbf (111 N)
force for door operation. Provide alloy-steel hand chain with chain holder
secured to operator guide.
D. Crank Operator: Consisting of crank and crank gearbox, steel crank drive
shaft, and gear-reduction unit, of type indicated. Size gears to require not
more than 25 lbf (111 N) force to turn crank. Fabricate gearbox to be oil tight
and to completely enclose operating mechanism. Provide manufacturer's
standard crank-locking device.
2.7
DOOR ASSEMBLY
A. Service Door: Overhead coiling door formed with curtain of interlocking metal
slats.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Cookson Company.
b. Overhead Door Corporation.
c. Raynor.
d. Wayne-Dalton Corp.
B. Operation Cycles: Not less than 10,000.
C. Door Curtain Material: Aluminum.
D. Door Curtain Slats: Flat profile slats of 1-1/4-inch (32-mm).
E. Curtain Jamb Guides: Aluminum with exposed finish matching curtain
slats. Provide continuous integral wear strips to prevent metal-to-metal
contact and to minimize operational noise.
F. Hood: Match curtain material and finish.
1. Shape: Round.
2. Mounting: Face of wall.
Overhead Coiling Doors
Section 08330
Statement of Work
V - 73
PMG Phase 1 Interim Action
3.
G. Locking Devices: Equip door with slide bolt for padlock.
1. Locking Device Assembly: Both jamb sides locking bars, operable from
inside with thumb turn.
H. Manual Door Operator: Push-up operation.
I. Door Finish:
1. Aluminum Finish: Mill.
2. Factory Prime Finish: Manufacturer's standard color.
PART 3 - EXECUTION
3.1
INSTALLATION
A. Install overhead coiling doors and operating equipment complete with
necessary hardware, anchors, inserts, hangers, and equipment supports;
according to manufacturer's written instructions and as specified.
B. Fire-Rated Doors: Install according to NFPA 80.
C. Smoke-Control Doors: Install according to NFPA 80 and NFPA 105.
D. Adjust hardware and moving parts to function smoothly so that doors operate
easily, free of warp, twist, or distortion. Lubricate bearings and sliding parts
as recommended by manufacturer. Adjust seals to provide weather tight fit
around entire perimeter.
3.2
DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's
maintenance personnel to adjust, operate, and maintain overhead coiling
doors.
END OF SECTION
Overhead Coiling Doors
Section 08330
Statement of Work
V - 74
PMG Phase 1 Interim Action
SECTION 08630 - METAL-FRAMED SKYLIGHTS
PART 1 - GENERAL
1.1
SUMMARY
A. Section includes skylights with metal framing.
1.2
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: For metal-framed skylights.
sections, details, and attachments to other work.
Include plans, elevations,
C. Samples: For each type of exposed finish.
D. Delegated-Design Submittal: For metal-framed skylights indicated to comply
with performance requirements and design criteria, including analysis data
signed and sealed by the qualified professional engineer responsible for their
preparation.
1.3
INFORMATIONAL SUBMITTALS
A. Product test reports.
B. Field quality-control reports.
C. Warranties: Sample of special warranties.
1.4
QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is
trained and approved for installation of metal-framed skylights required for
this Project.
B. Structural-Sealant Glazing: Comply with recommendations in ASTM C 1401,
"Guide for Structural Sealant Glazing," for joint design and quality-control
procedures.
1.5
WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer
agrees to repair or replace components of metal-framed skylights that fail in
materials or workmanship within specified warranty period.
1. Warranty Period: 10 years from date of Substantial Completion.
Metal-Framed Skylights
Section 08630
Statement of Work
V - 75
PMG Phase 1 Interim Action
B. Special Finish Warranty: Manufacturer's standard form in which manufacturer
agrees to repair or replace components on which finishes fail within specified
warranty period. Warranty does not include normal weathering.
1. Warranty Period: 20 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1
MANUFACTURERS
A. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following::
1. Major Industries, Inc.; Auburn Skylights Division.
2. Wasco Products, Inc.
2.2
PERFORMANCE REQUIREMENTS
A. General: Metal-framed skylights shall withstand the effects of the following
without failure due to defective manufacture, fabrication, installation, or other
defects in construction:
1. Structural loads.
2. Thermal movements.
3. Movements of supporting structure.
4. Dimensional tolerances
construction.
of
support
system
and
other
adjacent
5. Failure includes, but is not limited to, the following:
a. Deflection exceeding specified limits.
b. Thermal stresses transferring to building structure.
c. Framing members transferring stresses, including those caused by
thermal and structural movements to glazing.
d. Glazing-to-glazing contact.
e. Noise or vibration created by wind and by thermal and structural
movements.
f. Loosening or weakening of fasteners, attachments, and other
components.
g. Sealant failure.
B. Delegated Design: Design metal-framed skylights, including comprehensive
engineering analysis by a qualified professional engineer, using performance
requirements and design criteria indicated.
Metal-Framed Skylights
Section 08630
Statement of Work
V - 76
PMG Phase 1 Interim Action
C. Structural Loads:
1. Wind Loads: As indicated on Drawings.
2. Seismic Loads: As indicated on Drawings.
D. Deflection criteria of L/175 shall be maximum allowable under design load.
E. Lateral Bracing of Framing Members: Compression flanges of flexural
members are laterally braced by cross members with minimum depth equal to
50 percent of flexural member that is braced. Glazing does not provide lateral
support.
F. Air Infiltration: Provide metal-framed skylights with maximum air leakage
through fixed glazing and framing areas of 0.06 cfm/sq. ft. of fixed wall area
when tested according to ASTM E 283 at a minimum static-air-pressure
difference of 6.24 lbf/sq. ft.
G. Water Penetration under Static Pressure: Provide metal-framed skylights that
do not evidence water penetration through fixed glazing and framing areas
when tested according to ASTM E 331 at a minimum static-air-pressure
difference of 20 percent of positive wind-load design pressure, but not less
than 6.24 lbf/sq. ft.
H. Thermal Movements: Provide metal-framed skylights that allow for thermal
movements resulting from the following maximum change (range) in ambient
and surface temperatures.
Base engineering calculations on surface
temperatures of materials due to both solar heat gain and nighttime-sky heat
loss.
I. Condensation Resistance: Provide metal-framed skylights with fixed glazing
and framing areas having condensation-resistance factor (CRF) of not less
than 45 when tested according to AAMA 1503.
J. Structural Sealant: Capable of withstanding tensile and shear stresses
imposed without failing adhesively or cohesively.
When tested for
preconstruction adhesion and compatibility, cohesive failure of sealant shall
occur before adhesive failure.
2.3
FRAMING SYSTEMS
A. Aluminum: Alloy and temper recommended in writing by manufacturer for
type of use and finish indicated.
1. Sheet and Plate: ASTM B 209.
2. Extruded Bars, Rods, Profiles, and Tubes: ASTM B 221.
3. Extruded Structural Pipe and Tubes: ASTM B 429.
4. Structural Profiles: ASTM B 308.
Metal-Framed Skylights
Section 08630
Statement of Work
V - 77
PMG Phase 1 Interim Action
B. Pressure Caps:
Manufacturer's standard aluminum components that
mechanically retain glazing.
1. Include snap-on aluminum trim that conceals fasteners.
C. Brackets and Reinforcements:
Manufacturer's standard high-strength
aluminum with nonstaining, nonferrous shims for aligning skylight
components.
D. Fasteners and Accessories: Manufacturer's standard, corrosion-resistant,
nonstaining, nonbleeding fasteners and accessories compatible with adjacent
materials.
1. At pressure caps, use ASTM A 193/A 193M stainless-steel screws.
2. Use self-locking devices where fasteners are subject to loosening or
turning out from thermal and structural movements, wind loads, or
vibration.
3. Reinforce members as required to receive fastener threads.
4. Use exposed fasteners with countersunk Phillips screw heads.
E. Anchor Bolts: ASTM A 307, Grade A, galvanized steel.
F. Concealed Flashing:
Manufacturer's standard, corrosion-resistant,
nonstaining, nonbleeding flashing compatible with adjacent materials.
G. Exposed Flashing and Closures:
Manufacturer's standard aluminum
components not less than 0.030 inch thick.
H. Framing Gaskets: Manufacturer's standard.
I. Framing Sealants: As recommended in writing by manufacturer.
J. Corrosion-Resistant Coating: Cold-applied asphalt mastic.
2.4
GLAZING
A. Glazing: As specified by manufacturer.
B. Spacers, Setting Blocks, and Gaskets: Manufacturer's standard elastomeric
types.
C. Bond-Breaker Tape: Manufacturer's standard.
D. Glazing Sealants: As recommended in writing by manufacturer.
1. Sealants used inside the weatherproofing system shall have a VOC
content as indicated when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
Metal-Framed Skylights
Section 08630
Statement of Work
V - 78
PMG Phase 1 Interim Action
2. Sealants used inside the weatherproofing system shall comply with the
testing and product requirements of the California Department of Health
Services' "Standard Practice for the Testing of Volatile Organic Emissions
from Various Sources Using Small-Scale Environmental Chambers."
3. Structural Sealant: ASTM C 1184, neutral-curing silicone formulation
compatible with system components with which it comes in contact,
specifically formulated and tested for use as structural sealant, and
approved by structural-sealant manufacturer for use in metal-framed
skylights indicated.
4. Weatherseal Sealant: ASTM C 920 for Type S, Grade NS, Class 25,
Uses NT, G, A, and O; neutral-curing silicone formulation compatible with
structural sealant and other components with which it comes in contact;
and recommended in writing by structural- and weatherseal-sealant and
metal-framed skylight manufacturers for this use.
2.5
FABRICATION
A. Fabricate aluminum components before finishing.
B. Fabricate aluminum components that, when assembled, have the following
characteristics:
1. Profiles that are sharp, straight, and free of defects or deformations.
2. Accurately fitted joints with ends coped or mitered.
3. Internal guttering systems or other means to drain water passing joints,
condensation occurring within framing members, and moisture migrating
within skylight to exterior.
4. Physical and thermal isolation of glazing from framing members.
5. Accommodations for thermal and mechanical movements of glazing and
framing to maintain required glazing edge clearances.
C. Fabricate aluminum sill closures with weep holes and for installation as
continuous component.
D. Reinforce aluminum components as required to receive fastener threads.
E. Factory-Glazed, Metal-Framed Skylights:
1. Factory install glazing to comply with requirements in Division 08 Section
"Glazing."
2. Prepare surfaces that will contact structural sealant according to
structural-sealant manufacturer's written instructions to ensure
compatibility and adhesion. Preparation includes, but is not limited to,
cleaning and priming surfaces.
F. After fabrication, clearly mark components to identify their locations in Project
according to Shop Drawings.
Metal-Framed Skylights
Section 08630
Statement of Work
2.6
V - 79
PMG Phase 1 Interim Action
ALUMINUM FINISHES
A. Clear Anodic Finish: AAMA 611, or thicker.
B. Color Anodic Finish: AAMA 611, or thicker.
C. Baked-Enamel or Powder-Coat Finish: AAMA 2603 except with a minimum
dry film thickness of 1.5 mils.
2.7
SOURCE QUALITY CONTROL
A. Structural-Sealant Glazing: Perform quality-control procedures complying
with ASTM C 1401 recommendations including, but not limited to, material
qualification procedures, sealant testing, and fabrication reviews and checks.
PART 3 - EXECUTION
3.1
INSTALLATION
A. General:
1. Comply with manufacturer's written instructions.
2. Do not install damaged components.
3. Fit joints between aluminum components to produce hairline joints free of
burrs and distortion.
4. Rigidly secure nonmovement joints.
5. Install anchors with separators and isolators to prevent metal corrosion
and electrolytic deterioration and to prevent impeding movement of
moving joints.
6. Seal joints watertight unless otherwise indicated.
B. Metal Protection: Where aluminum will contact dissimilar materials, protect
against galvanic action by painting contact surfaces with protective coating or
by installing nonconductive spacers as recommended in writing by
manufacturer for this purpose.
C. Install continuous aluminum sill closure with weatherproof expansion joints
and locked and sealed corners. Locate weep holes at rafters.
D. Install components to drain water passing joints, condensation occurring
within framing members, and moisture migrating within skylight to exterior.
E. Install components plumb and true in alignment with established lines and
elevations.
1. Structural-Sealant Glazing:
Metal-Framed Skylights
Section 08630
Statement of Work
V - 80
PMG Phase 1 Interim Action
a. Prepare surfaces that will contact structural sealant according to
structural-sealant manufacturer's written instructions to ensure
compatibility and adhesion. Preparation includes, but is not limited to,
cleaning and priming surfaces.
b. Install weatherseal sealant according to weatherseal-sealant
manufacturer's written instructions to produce weatherproof joints.
Install joint filler behind weatherseal sealant as recommended in
writing by weatherseal-sealant manufacturer.
F. Erection Tolerances: Install metal-framed skylights to comply with the
following maximum tolerances:
1. Alignment: Limit offset from true alignment to 1/32 inch where surfaces
abut in line, edge to edge, at corners, or where a reveal or protruding
element separates aligned surfaces by less than 3 inches; otherwise, limit
offset to 1/8 inch.
2. Location and Plane: Limit variation from true location and plane to 1/8
inch in 12 feet but no greater than 1/2 inch over total length.
3.2
FIELD QUALITY CONTROL
A. Testing Agency:
inspections.
Engage a qualified testing agency to perform tests and
1. Water-Spray Test: Before installation of interior finishes has begun,
skylights shall be tested according to AAMA 501.2 and shall not evidence
water penetration.
B. Repair or remove work where test results and inspections indicate that it does
not comply with specified requirements.
C. Additional testing and inspecting, at Contractor's expense, will be performed
to determine compliance of replaced or additional work with specified
requirements.
D. Prepare test and inspection reports.
END OF SECTION
Metal-Framed Skylights
Section 08630
Statement of Work
V - 81
PMG Phase 1 Interim Action
SECTION 08710 - DOOR HARDWARE
PART 1 - GENERAL
1.1
SUMMARY
A. Section includes:
1. Mechanical door hardware for the following:
a. Swinging doors.
B. Products furnished, but not installed, under this Section include the products
listed below. Coordinating and scheduling the purchase and delivery of these
products remain requirements of this Section.
1. Pivots, thresholds, weather stripping, and lock cylinders to be installed
under other Sections.
2. Permanent lock cores to be installed by Owner.
1.2
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: Details of electrified door hardware.
C. Samples: For each exposed product and for each color and texture specified.
D. Other Action Submittals:
1. Door Hardware Schedule: Prepared by or under the supervision of
Installer, detailing fabrication and assembly of door hardware, as well as
installation procedures and diagrams. Coordinate final door hardware
schedule with doors, frames, and related work to ensure proper size,
thickness, hand, function, and finish of door hardware.
a. Content: Include the following information:
1)
2)
3)
4)
Identification number, location, hand, fire rating, size, and
material of each door and frame.
Locations of each door hardware set, cross-referenced to
Drawings on floor plans and to door and frame schedule.
Complete designations, including name and manufacturer,
type, style, function, size, quantity, function, and finish of each
door hardware product.
Description of electrified door hardware sequences of operation
and interfaces with other building control systems.
2. Keying Schedule: Prepared by or under the supervision of Installer,
detailing Owner's final keying instructions for locks.
Door Hardware
Section 08710
Statement of Work
1.3
V - 82
PMG Phase 1 Interim Action
MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged
with protective covering for storage and identified with labels describing
contents.
1.4
QUALITY ASSURANCE
A. Installer Qualifications: Supplier of products and an employer of workers
trained and approved by product manufacturers and an Architectural
Hardware Consultant who is available during the course of the Work to
consult with Contractor, Architect, and Owner about door hardware and
keying.
B. Keying Conference: Conduct conference at Project site with Owner and/or
Engineer.
1.5
DELIVERY, STORAGE, AND HANDLING
A. Deliver keys to manufacturer of key control system for subsequent delivery to
Owner.
B. Deliver keys to Owner by registered mail or overnight package service.
1.6
WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer
agrees to repair or replace components of door hardware that fail in materials
or workmanship within specified warranty period.
1. Warranty Period: Three years from date of Substantial Completion,
unless otherwise indicated.
a. Manual Closers: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1
SCHEDULED DOOR HARDWARE
A. Provide door hardware for each door as scheduled on Drawings to comply
with requirements in this Section.
B. Designations: Requirements for design, grade, function, finish, size, and
other distinctive qualities of each type of door hardware are indicated in Part 3
"Door Hardware Schedule" Article. Products are identified by using door
hardware designations, as follows:
1. Named Manufacturers' Products: Manufacturer and product designation
are listed for each door hardware type required for the purpose of
Door Hardware
Section 08710
Statement of Work
V - 83
PMG Phase 1 Interim Action
establishing minimum requirements.
Manufacturers'
abbreviated in Part 3 "Door Hardware Schedule" Article.
names
are
2. References to BHMA Designations: Provide products complying with
these designations and requirements for description, quality, and function.
2.2
HINGES
A. Hinges:
BHMA A156.1. Provide template-produced hinges for hinges
installed on hollow-metal doors and hollow-metal frames.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Baldwin Hardware Corporation.
b. Bommer Industries, Inc.
c. Cal-Royal Products, Inc.
d. Hager Companies.
e. IVES Hardware; an Ingersoll-Rand company.
f. Lawrence Hardware Inc.
g. McKinney Products Company; an ASSA ABLOY Group company.
h. PBB, Inc.
i.
2.3
Stanley Commercial Hardware; Div. of The Stanley Works.
MECHANICAL LOCKS AND LATCHES
A. Strikes: Provide manufacturer's standard strike for each lock bolt or latchbolt
complying with requirements indicated for applicable lock or latch and with
strike box and curved lip extended to protect frame; finished to match lock or
latch.
1. Flat-Lip Strikes: For locks with three-piece antifriction latchbolts, as
recommended by manufacturer.
2. Rabbet Front and Strike: Provide on locksets for rabbeted meeting stiles.
B. Mortise Locks: BHMA A156.13; Grade 1; stamped steel case with steel or
brass parts; Series 1000.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Accurate Lock & Hardware Co.
b. Adams Rite Manufacturing Co.; an ASSA ABLOY Group company.
c. Arrow USA; an ASSA ABLOY Group company.
Door Hardware
Section 08710
Statement of Work
V - 84
PMG Phase 1 Interim Action
d. Best Access Systems; Div. of Stanley Security Solutions, Inc.
e. Cal-Royal Products, Inc.
f. Corbin Russwin Architectural Hardware; an ASSA ABLOY Group
company.
g. Falcon Lock; an Ingersoll-Rand company.
h. Marks USA.
i.
PDQ Manufacturing.
j.
SARGENT Manufacturing Company; an ASSA ABLOY Group
company.
k. Schlage Commercial Lock Division; an Ingersoll-Rand company.
l.
2.4
Yale Security Inc.; an ASSA ABLOY Group company.
LOCK CYLINDERS
A. Lock Cylinders: Tumbler type, constructed from brass or bronze, stainless
steel, or nickel silver.
1. Manufacturer: Same manufacturer as for locking devices.
B. Construction Master Keys: Provide cylinders with feature that permits voiding
of construction keys without cylinder removal. Provide 10 construction master
keys.
C. Construction Cores: Provide construction cores that are replaceable by
permanent cores. Provide 10 construction master keys.
2.5
KEYING
A. Keying System:
Factory registered, complying with guidelines in
BHMA A156.28, Appendix A.
Incorporate decisions made in keying
conference.
1. Master Key System: Change keys and a master key operate cylinders.
2. Grand Master Key System: Change keys, a master key, and a grand
master key operate cylinders.
3. Great-Grand Master Key System: Change keys, a master key, a grand
master key, and a great-grand master key operate cylinders.
4. Existing System:
a. Master key or grand master key locks to Owner's existing system.
b. Re-key Owner's existing master key system into new keying system.
5. Keyed Alike: Key all cylinders to same change key.
B. Keys:
Door Hardware
Section 08710
Statement of Work
V - 85
PMG Phase 1 Interim Action
1. Stamping: Permanently inscribe each key with a visual key control
number and include the following notation:
2. Quantity: In addition to one extra key blank for each lock, provide the
following:
a. Cylinder Change Keys: Three.
b. Master Keys: Five.
2.6
OPERATING TRIM
A. Operating Trim: BHMA A156.6; stainless steel, unless otherwise indicated.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Burns Manufacturing Incorporated.
b. Don-Jo Mfg., Inc.
c. Forms + Surfaces.
d. Hager Companies.
e. Hiawatha, Inc.
f. IVES Hardware; an Ingersoll-Rand company.
g. Rockwood Manufacturing Company.
h. Trimco.
2.7
MECHANICAL STOPS AND HOLDERS
A. Wall- and Floor-Mounted Stops:
bronze, or aluminum base metal.
BHMA A156.16; polished cast brass,
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Architectural Builders Hardware Mfg., Inc.
b. Baldwin Hardware Corporation.
c. Burns Manufacturing Incorporated.
d. Cal-Royal Products, Inc.
e. Don-Jo Mfg., Inc.
f. Door Controls International, Inc.
g. Hager Companies.
h. Hiawatha, Inc.
i.
Door Hardware
IVES Hardware; an Ingersoll-Rand company.
Section 08710
Statement of Work
j.
V - 86
PMG Phase 1 Interim Action
Rockwood Manufacturing Company.
k. Stanley Commercial Hardware; Div. of The Stanley Works.
l.
2.8
Trimco.
DOOR GASKETING
A. Door Gasketing: BHMA A156.22; air leakage not to exceed 0.50 cfm per foot
of crack length for gasketing other than for smoke control, as tested according
to ASTM E 283; with resilient or flexible seal strips that are easily replaceable
and readily available from stocks maintained by manufacturer.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Hager Companies.
b. M-D Building Products, Inc.
c. National Guard Products.
d. Pemko Manufacturing Co.; an ASSA ABLOY Group company.
e. Reese Enterprises, Inc.
f. Sealeze; a unit of Jason Incorporated.
g. Zero International.
2.9
THRESHOLDS
A. Thresholds: BHMA A156.21; fabricated to full width of opening indicated.
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Hager Companies.
b. M-D Building Products, Inc.
c. National Guard Products.
d. Pemko Manufacturing Co.; an ASSA ABLOY Group company.
e. Reese Enterprises, Inc.
f. Rixson Specialty Door Controls; an ASSA ABLOY Group company.
g. Sealeze; a unit of Jason Incorporated.
h. Zero International.
Door Hardware
Section 08710
Statement of Work
2.10
V - 87
PMG Phase 1 Interim Action
FABRICATION
A. Fasteners: Provide door hardware manufactured to comply with published
templates prepared for machine, wood, and sheet metal screws. Provide
screws that comply with commercially recognized industry standards for
application intended, except aluminum fasteners are not permitted. Provide
Phillips flat-head screws with finished heads to match surface of door
hardware, unless otherwise indicated.
1. Concealed Fasteners: For door hardware units that are exposed when
door is closed, except for units already specified with concealed fasteners.
Do not use through bolts for installation where bolt head or nut on
opposite face is exposed unless it is the only means of securely attaching
the door hardware. Where through bolts are used on hollow door and
frame construction, provide sleeves for each through bolt.
2. Fire-Rated Applications:
a. Steel Through Bolts:
provided:
1)
2)
3)
For the following unless door blocking is
Surface hinges to doors.
Closers to doors and frames.
Surface-mounted exit devices.
3. Spacers or Sex Bolts: For through bolting of hollow-metal doors.
4. Fasteners for Wood Doors: Comply with requirements in DHI WDHS.2,
"Recommended Fasteners for Wood Doors."
5. Gasketing Fasteners:
Provide noncorrosive fasteners for exterior
applications and elsewhere as indicated.
2.11
FINISHES
A. Provide finishes complying with BHMA A156.18 as indicated in door hardware
schedule.
B. Protect mechanical finishes on exposed surfaces from damage by applying a
strippable, temporary protective covering before shipping.
PART 3 - EXECUTION
3.1
INSTALLATION
A. Steel Doors and Frames: For surface applied door hardware, drill and tap
doors and frames according to ANSI/SDI A250.6.
B. Mounting Heights: Mount door hardware units at heights indicated on
Drawings unless otherwise indicated or required to comply with governing
regulations.
Door Hardware
Section 08710
Statement of Work
V - 88
PMG Phase 1 Interim Action
1. Standard Steel Doors and Frames: ANSI/SDI A250.8.
2. Custom Steel Doors and Frames: HMMA 831.
C. Install each door hardware item to comply with manufacturer's written
instructions. Where cutting and fitting are required to install door hardware
onto or into surfaces that are later to be painted or finished in another way,
coordinate removal, storage, and reinstallation of surface protective trim units
with finishing work specified in Division 09 Sections. Do not install surfacemounted items until finishes have been completed on substrates involved.
1. Set units level, plumb, and true to line and location. Adjust and reinforce
attachment substrates as necessary for proper installation and operation.
2. Drill and countersink units that are not factory prepared for anchorage
fasteners. Space fasteners and anchors according to industry standards.
D. Hinges: Install types and in quantities indicated in door hardware schedule
but not fewer than the number recommended by manufacturer for application
indicated or one hinge for every 30 inches of door height, whichever is more
stringent, unless other equivalent means of support for door, such as spring
hinges or pivots, are provided.
E. Lock Cylinders: Install construction cores to secure building and areas during
construction period.
F. Key Control System: Tag keys and place them on markers and hooks in key
control system cabinet, as determined by final keying schedule.
G. Thresholds: Set thresholds for exterior doors and other doors indicated in full
bed of sealant complying with requirements specified in Division 07 Section
"Joint Sealants."
H. Stops: Provide floor stops for doors unless wall or other type stops are
indicated in door hardware schedule. Do not mount floor stops where they
will impede traffic.
I. Perimeter Gasketing: Apply to head and jamb, forming seal between door
and frame.
J. Door Bottoms: Apply to bottom of door, forming seal with threshold when
door is closed.
K. Adjustment: Adjust and check each operating item of door hardware and
each door to ensure proper operation or function of every unit. Replace units
that cannot be adjusted to operate as intended. Adjust door control devices
to compensate for final operation of heating and ventilating equipment and to
comply with referenced accessibility requirements.
Door Hardware
Section 08710
Statement of Work
3.2
V - 89
PMG Phase 1 Interim Action
FIELD QUALITY CONTROL
A. Independent Hardware Consultant:
Owner will engage a qualified
independent Hardware Consultant to perform inspections and to prepare
inspection reports.
END OF SECTION
Door Hardware
Section 08710
Statement of Work
V - 90
PMG Phase 1 Interim Action
SECTION 08900 - LOUVERS AND VENTS
PART 1 - GENERAL
1.1
SUMMARY
A. Section Includes:
1. Fixed, extruded-aluminum and formed-metal louvers.
2. Wall vents.
1.2
PERFORMANCE REQUIREMENTS
A. Delegated Design: Design louvers, including comprehensive engineering
analysis by a qualified professional engineer, using structural performance
requirements and design criteria indicated.
B. Structural Performance: Louvers shall withstand the effects of gravity loads
and the following loads and stresses within limits and under conditions
indicated without permanent deformation of louver components, noise or
metal fatigue caused by louver blade rattle or flutter, or permanent damage to
fasteners and anchors.
1. Wind Loads:
Drawings.
Determine loads based on pressures as indicated on
C. Louver Performance Ratings: Provide louvers complying with requirements
specified, as demonstrated by testing manufacturer's stock units identical to
those provided, except for length and width according to AMCA 500-L.
1.3
ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
1. For louvers specified to bear AMCA seal, include printed catalog pages
showing specified models with appropriate AMCA Certified Ratings Seals.
B. Shop Drawings: For louvers and accessories. Include plans, elevations,
sections, details, and attachments to other work. Show frame profiles and
blade profiles, angles, and spacing.
C. Samples: For each type of metal finish required.
D. Delegated-Design Submittal: For louvers indicated to comply with structural
performance requirements and design criteria, including analysis data signed
and sealed by the qualified professional engineer responsible for their
preparation.
Louvers and Vents
Section 08900
Statement of Work
1.4
V - 91
PMG Phase 1 Interim Action
INFORMATIONAL SUBMITTALS
A. Product Test Reports: Based on tests performed according to AMCA 500-L.
PART 2 - PRODUCTS
2.1
MATERIALS
A. Aluminum Extrusions: ASTM B 221, Alloy 6063-T5, T-52, or T6.
B. Aluminum Sheet: ASTM B 209, Alloy 3003 or 5005 with temper as required
for forming, or as otherwise recommended by metal producer for required
finish.
C. Galvanized-Steel Sheet: ASTM A 653 G60 zinc coating, mill phosphatized.
D. Stainless-Steel Sheet: ASTM A 240/A 240M, Type 304, No. 4 finish.
E. Fasteners: Use types and sizes to suit unit installation conditions.
1. For fastening aluminum, use aluminum or 300 series stainless-steel
fasteners.
2. For fastening galvanized steel, use hot-dip-galvanized steel or 300 series
stainless-steel fasteners.
3. For fastening stainless steel, use 300 series stainless-steel fasteners.
4. For color-finished louvers, use fasteners with heads that match color of
louvers.
F. Bituminous Paint:
ASTM D 1187.
2.2
Cold-applied
asphalt
emulsion
complying
with
FABRICATION, GENERAL
A. Fabricate frames, including integral sills, to fit in openings of sizes indicated,
with allowances made for fabrication and installation tolerances, adjoining
material tolerances, and perimeter sealant joints.
2.3
WALL VENTS (BRICK VENTS)
A. Extruded-Aluminum Wall Vents:
1. Manufacturers: Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Air Flow Company, Inc.
b. Airolite Company, LLC (The).
Louvers and Vents
Section 08900
Statement of Work
V - 92
PMG Phase 1 Interim Action
c. Arrow United Industries; a division of Mestek, Inc.
d. Construction Specialties, Inc.
e. Dowco Products Group; Safe-Air of Illinois, Inc.
f. Greenheck Fan Corporation.
g. Hohmann & Barnard, Inc.
h. Industrial Louvers, Inc.
i.
Louvers & Dampers, Inc.; a division of Mestek, Inc.
j.
Metal Form Manufacturing Inc.
k. Nystrom Building Products.
l.
Reliable Products, Inc.
m. Ruskin Company; Tomkins PLC.
n. Sunvent Industries; Division of Sylro Sales Corp.
o. United Enertech Corp.
2. Provide fixed and operable type louvers of size and design shown.
3. Hand crank operation: Hand crank operator activated by case hardened
gears concealed in aluminum housing. Operators shall be removable and
located at jambs. Provide one right-handed operator for each louver.
4. Extruded-aluminum louvers and frames, not less than 0.125-inch nominal
thickness, assembled by welding; with 18-by-14- mesh, aluminum insect
screening on inside face; incorporating weep holes, continuous drip at sill,
and integral waterstop on inside edge of sill; of load-bearing design and
construction.
2.4
ALUMINUM FINISHES
A. Clear Anodic Finish:
thicker.
AAMA 611, AA-M12C22A41, Class I, 0.018 mm or
B. Color Anodic Finish: AAMA 611, AA-M12C22A42/A44, Class I, 0.018 mm or
thicker.
2.5
GALVANIZED-STEEL SHEET FINISHES
A. Finish louvers after assembly.
B. Surface Preparation: Clean surfaces with nonpetroleum solvent so surfaces
are free of oil and other contaminants. After cleaning, apply a conversion
coating suited to the organic coating to be applied over it. Clean welds,
mechanical connections, and abraded areas and repair according to
ASTM A 780.
Louvers and Vents
Section 08900
Statement of Work
V - 93
PMG Phase 1 Interim Action
C. Baked-Enamel or Powder-Coat Finish: Immediately after cleaning and
pretreating, apply manufacturer's standard 2-coat, baked-on finish consisting
of prime coat and thermosetting topcoat, with a minimum dry film thickness of
1 mil for topcoat. Comply with coating manufacturer's written instructions for
applying and baking to achieve a minimum dry film thickness of 2 mils.
PART 3 - EXECUTION
3.1
INSTALLATION
A. Locate and place louvers and vents level, plumb, and at indicated alignment
with adjacent work.
B. Use concealed anchorages where possible. Provide brass or lead washers
fitted to screws where required to protect metal surfaces and to make a
weathertight connection.
C. Provide perimeter reveals and openings of uniform width for sealants and
joint fillers, as indicated.
D. Repair damaged finishes so no evidence remains of corrective work. Return
items that cannot be refinished in the field to the factory and refinish entire
unit or provide new units.
E. Protect galvanized and nonferrous-metal surfaces that will be in contact with
concrete, masonry, or dissimilar metals from corrosion and galvanic action by
applying a heavy coating of bituminous paint.
END OF SECTION
Louvers and Vents
Section 08900
Statement of Work
V - 94
PMG Phase 1 Interim Action
SECTION 10520 - FIRE EXTINGUISHERS
PART 1 - GENERAL
1.1
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 01 Specification Sections, apply to
this Section.
1.2
SUMMARY
A. Section includes portable, hand-carried fire extinguishers and mounting
brackets for fire extinguishers.
B. Owner-Furnished Material: Hand-carried fire extinguishers.
1.3
ACTION SUBMITTALS
A. Product Data: For each type of product indicated. Include rating and
classification, material descriptions, dimensions of individual components and
profiles, and finishes for fire extinguisher and mounting brackets.
B. Product Schedule: For fire extinguishers. Coordinate final fire extinguisher
schedule with mounting bracket schedule to ensure proper fit and function.
1.4
INFORMATIONAL SUBMITTALS
A. Warranty: Sample of special warranty.
1.5
CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data:
maintenance manuals.
1.6
For fire extinguishers to include in
QUALITY ASSURANCE
A. NFPA Compliance: Fabricate and label fire extinguishers to comply with
NFPA 10, "Portable Fire Extinguishers."
B. Fire Extinguishers: Listed and labeled for type, rating, and classification by
an independent testing agency acceptable to authorities having jurisdiction.
1. Provide fire extinguishers approved, listed, and labeled by FMG.
C. Preinstallation Conference: Conduct conference at Project site.
Fire Extinguishers
Section 10520
Statement of Work
V - 95
PMG Phase 1 Interim Action
1. Review methods and procedures related to fire extinguishers including,
but not limited to, the following:
a. Schedules and coordination requirements.
1.7
COORDINATION
A. Coordinate type and capacity of fire extinguishers with fire protection cabinets
to ensure fit and function.
1.8
WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer
agrees to repair or replace fire extinguishers that fail in materials or
workmanship within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Failure of hydrostatic test according to NFPA 10.
b. Faulty operation of valves or release levers.
2. Warranty Period: Six years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1
PORTABLE, HAND-CARRIED FIRE EXTINGUISHERS
A. Fire Extinguishers:
indicated.
Type, size, and capacity for each mounting bracket
1. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Amerex Corporation.
b. Ansul Incorporated; Tyco International Ltd.
c. Badger Fire Protection; a Kidde company.
d. Buckeye Fire Equipment Company.
e. Fire End & Croker Corporation.
f. J. L. Industries, Inc.; a division of Activar Construction Products Group.
g. Kidde Residential and Commercial Division; Subsidiary of Kidde plc.
h. Larsen's Manufacturing Company.
i.
Moon-American.
j.
Pem All Fire Extinguisher Corp.; a division of PEM Systems, Inc.
k. Potter Roemer LLC.
Fire Extinguishers
Section 10520
Statement of Work
l.
V - 96
PMG Phase 1 Interim Action
Pyro-Chem; Tyco Safety Products.
2. Valves: Manufacturer's standard.
3. Handles and Levers: Manufacturer's standard.
4. Instruction Labels: Include pictorial marking system complying with
NFPA 10, Appendix B and bar coding for documenting fire extinguisher
location, inspections, maintenance, and recharging.
B. Pressurized, AFFF-Foam Type UL-rated 2-A:10-B:C, 2.6-gal. (10-L) nominal
capacity, with AFFF foam in stainless-steel container; with pressure-indicating
gage.
2.2
MOUNTING BRACKETS
A. Mounting Brackets: Manufacturer's standard galvanized steel, designed to
secure fire extinguisher to wall or structure, of sizes required for types and
capacities of fire extinguishers indicated, with plated or red baked-enamel
finish.
1. Manufacturers:
Subject to compliance with requirements, available
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the following:
a. Amerex Corporation.
b. Ansul Incorporated; Tyco International Ltd.
c. Badger Fire Protection; a Kidde company.
d. Buckeye Fire Equipment Company.
e. Fire End & Croker Corporation.
f. J. L. Industries, Inc.; a division of Activar Construction Products Group.
g. Larsen's Manufacturing Company.
h. Potter Roemer LLC.
B. Identification: Lettering complying with authorities having jurisdiction for letter
style, size, spacing, and location. Locate as indicated by Architect.
1. Identify bracket-mounted fire extinguishers with the words "FIRE
EXTINGUISHER" in red letter decals applied to mounting surface.
a. Orientation: Horizontal.
PART 3 - EXECUTION
3.1
EXAMINATION
A. Examine fire extinguishers for proper charging and tagging.
Fire Extinguishers
Section 10520
Statement of Work
1. Remove and
extinguishers.
V - 97
replace
damaged,
PMG Phase 1 Interim Action
defective,
or
undercharged
fire
B. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.2
INSTALLATION
A. General: Install fire extinguishers and mounting brackets in locations
indicated and in compliance with requirements of authorities having
jurisdiction.
1. Mounting Brackets: 54 inches (1372 mm) above finished floor to top of
fire extinguisher.
B. Mounting Brackets: Fasten mounting brackets to surfaces, square and
plumb, at locations indicated.
END OF SECTION
Fire Extinguishers
Section 10520
Statement of Work
V - 98
PMG Phase 1 Interim Action
SECTION 14630 – WALL SUPPORTED STEEL BRIDGE CRANE
PART 1 – GENERAL
1.1
SUMMARY
C. Section includes: Wall mounted, steel bridge crane, runways, two (2)
movable bridges each with a hoist trolley, and other accessories.
D. Related sections:
1. Section 04220 – CONCRETE UNIT MASONRY: CMU walls to receive
bridge crane tracks.
1.2
REFERENCES
E. American Institute of Steel Construction (AISC):
Manual of Steel
Construction, Part 5, Specification for Structural Joints Using ASTM A325 or
ASTM A490 Bolts.
F. American National Standards Institute (ANSI):
1. ANSI B30.11 - Monorails and Underhung Cranes.
G. American Society for Testing and Materials (ASTM) Publications:
1. ASTM A36 - Carbon Structural Steel.
2. ASTM A325 - Structural Bolts, Steel, Heat Treated, 120/150 ksi Minimum
Tensile Strength.
3. ASTM A490 - Structural Bolts, Alloy Steel, Heat Treated, 150 ksi
Minimum Tensile Strength.
H. American Welding Society (AWS):
4. AWS D1.1 - Structural Welding Code.
I. Occupational Safety and Health Administration (OSHA): OSHA Specification
1910.179 - Overhead and Gantry Cranes.
Wall-Supported Steel Bridge Crane
Section 14630
Statement of Work
V - 99
PMG Phase 1 Interim Action
J. WAC 296-24-237 Construction, operation and maintenance-Chain and
electric hoists.
1.3
PERFORMANCE REQUIREMENTS
A. Crane shall provide coverage of rectangular area of size indicated on
Drawings and consist of:
1. Two rigid, parallel runway tracks supported on and connected to exterior
CMU wall structure. Cranes with more than two runways or with
articulating runways are not acceptable.
2. Two rigid single girder bridges moving perpendicular to runways. Double
girder bridges and ones with articulating or threaded connections are not
acceptable.
B. Modular, pre-engineered design:
disassembly and relocation.
Crane system shall be capable of
C. Productivity ratio: Crane shall be designed to manually move load with
maximum force of 1/100 load weight.
D. Runway and bridge track: Enclosed type limiting dust and dirt collection on
rolling surfaces with maximum deflection of 1/450 span based on capacity
plus 15 percent for lifting device weight.
E. Crane operating temperature: 5 to 200 degrees F.
F. Crane shall be designed to withstand:
1. Crane and hoist dead load.
2. Live load capacity for entire system: 4000 pounds.
Live load capacity per bridge equal to net rated hook load: 2000 pounds.
3. Inertia forces from crane and load movement.
1.4
SUBMITTALS
A. Provide:
1. Product data for crane and accessories.
Describe capacities,
performance, operation, and applied forces to foundation.
2. Shop drawings showing crane
construction and installation details.
Wall-Supported Steel Bridge Crane
configuration,
dimensions,
and
Section 14630
Statement of Work
V - 100
PMG Phase 1 Interim Action
3. Copy of warranty required by Paragraph 1.6 for review by Engineer.
4. Manufacturer's installation instructions.
5. Manufacturer's operation and maintenance manual.
1.5
QUALITY ASSURANCE
A. Manufacturer: Company specializing in designing and manufacturing cranes
with 25 years successful experience.
B. Installer: Company experienced in assembly and installation of cranes with 5
years successful experience and acceptable to crane manufacturer.
C. Crane shall be designed, fabricated, and installed in accordance with ANSI
B30.11, and OSHA 1910.179.
D. Base crane structural design includes full rated load capacity plus 15 percent
for hoist and trolley weight and 25 percent impact factor for speed of lifting
device and weight of tooling.
E. Perform welding by certified operators in accordance with AWS D14.1.
F. Bolted connections shall be in accordance with torque tightening procedures
specified in AISC Manual, Part 5.
G. Clearly label crane with rated load capacity. Place label at height and
location easily read from floor level and loading position.
1.6
WARRANTY
A. Provide:
1. 5 years warranty for crane to cover defects in materials and
workmanship.
PART 2 - PRODUCTS
2.1
ACCEPTABLE MANUFACTURERS
A. Gorbel, Inc., P.O. Box 593, Fishers, New York 14453-0593; 800-828-0086;
www.gorbel.com.
2.2
WALL SUPPORTED STEEL BRIDGE CRANE
A. Type: Wall supported runway tracks, all-steel construction, bridge crane, two
runways, two bridges moving perpendicular to runways, and equipped with
Wall-Supported Steel Bridge Crane
Section 14630
Statement of Work
V - 101
PMG Phase 1 Interim Action
enclosed track, hoist trolley, bumpers, and other accessories; Model No.
4000 lbs capacity
GLCSL Trussed Steel Runways, 2000 lbs capacity 15’-0” Track Series Steel
Bridge Assemblies as manufactured by Gorbel, Inc.
B. Runway length: 19 feet 8 inches.
C. Bridge length: 15 feet.
D. Construction: Fabricate from ASTM A36 steel sections with finished ends
and surfaces.
1. Support structure: Support crane runways from top chord of truss on
exterior CMU wall structure. Cut bottom track to fit interior wall to wall
dimension leaving vertical truss webs to remain as close to wall as
possible (max 6”).
2. Runways: Model GLCSL Vierendeel truss fabricated from square steel
tubes and enclosed steel track.
a. Track: Enclosed, cold formed, steel box track which serves as
bottom cord of runway and permits bridge assembly to ride on lower
inside flanges. Fabricate lower running flanges with 2 degrees taper
to center trolley within track. Flat, non-centering tracks are not
acceptable.
b. Splice joint: Splice joints are not acceptable.
c. Runway Cantilevers: This is a simple span assembly, there are no
cantilevers.
3. Bridge: Track Series Steel Trussed Bridge Assembly single girder,
Vierendeel truss fabricated from rectangular steel tubes and enclosed
steel box track.
a. Track serves as bottom cord of bridge and permits hoist trolley to
ride on lower inside flanges.
b. Fabricate lower running flanges with 2 degrees taper to center trolley
within track. Flat, non-centering tracks are not acceptable.
4. End trucks: Rigid frame end truck designed to ride inside enclosed
runway track and connect to and suspend bridge.
a. Construction: Stamped steel fabrication with both vertical and
horizontal wheels to prevent binding in runway. Designs with welds in
tension are not acceptable.
Wall-Supported Steel Bridge Crane
Section 14630
Statement of Work
V - 102
PMG Phase 1 Interim Action
b. Wheels: Removable, self-centering wheels with sealed lifetime
lubricated bearings. Vertical wheels shall be tapered 2 degrees to
match track profile. Non-removable or non-tapered wheels are not
acceptable. Duracomp 4® wheel material is preferred. Steel wheels
are not acceptable.
c. Drop lugs: Provide on both sides of truck to limit truck drop to 1 inch
maximum in event of wheel, axle, or load bar failure.
d. Connection to the bridge: Provide a rigid connection between bridge
and end truck. Articulating connections with threaded hardware are
not acceptable.
5. Hoist trolley: Rigid-body trolley designed to ride inside enclosed track of
bridge and carry hoist and load. Articulating trolleys are not acceptable.
a. Construction: Two-piece stamped steel body with two wheels each
side and tapered clevis positioning hoist hook at center of trolley so
load weight is evenly distributed to all four trolley wheels. Provide
removable clevis pin of type and size determined by manufacturer for
specified capacity. Trolleys with non-removable clevis pins are not
acceptable.
b. Wheels: Removable, self-centering wheels with sealed lifetime
lubricated bearings. Vertical wheels shall be tapered 2 degrees to
match track profile. Non-removable or non-tapered wheels are not
acceptable. Duracomp 4® wheel material is preferred. Steel wheels
are not acceptable.
.
c. Drop lugs: Provide on both sides of trolley to limit trolley drop to 1
inch maximum in event of wheel, axle, or load bar failure.
6. End stops: Molded composite, resilient bumper installed in runway and bridge
tracks to prevent end trucks and hoist trolley from rolling out of track. Bolt stops
without energy absorbing bumper are not acceptable.
2.3
SHOP FINISHING
A. Steam wash steel crane components with iron phosphate solution and apply
baked enamel finish. Colors shall be:
4. Support assemblies and runways: Blue.
5. Bridges: Yellow.
B. Provide spray cans of matching colors, air-drying paint for field touch-up.
Wall-Supported Steel Bridge Crane
Section 14630
Statement of Work
V - 103
PMG Phase 1 Interim Action
PART 3 - EXECUTION
3.1
PREPARATION
A. Coordinate provision of crane with:
1. Design and construction of reinforced concrete masonry units as detailed
on Drawings and specified in other sections. Ensure that tracks
supported on walls have a minimum support length of not less than 6”.
Connect to embed plates as detailed in drawings.
B. Prior to installation:
1. Verify reinforced concrete masonry unit grout has cured 7 days
minimum. Ensure that concrete masonry unit grout has cured 28 days
minimum prior to using crane to full capacity.
2. Inventory parts.
undamaged.
3.2
Verify all required components are available and
INSTALLATION
A. Install crane and accessories in accordance with manufacturer's instructions
and shop drawings.
B. Do not modify crane components in any manner without advance, written
approval by crane manufacturer.
C. Clearances for moving crane components:
1. 3 inch minimum vertical clearance from any overhead obstruction.
2. 2 inch minimum horizontal clearance from any lateral obstruction.
D. Runways: Suspend runways on support structure. Attach as indicated on
drawings.
1. Prior to applying proper welds, ensure runways are:
a. Level to within plus or minus 1/8 inch.
b. Parallel with opposite runway to within plus or minus 1/8 inch in 20
feet.
2. End stops: Bolt stops into runway track.
E. Prior to installing bridge, use clean dry cloth to clean inside flanges of runway
and bridge tracks.
Wall-Supported Steel Bridge Crane
Section 14630
Statement of Work
V - 104
PMG Phase 1 Interim Action
F. Bridge: Lift bridge with end trucks to runways and insert end trucks into open
ends of runways. Roll bridge down length of runway. Verify and adjust for
smooth travel.
G. End stops: Bolt stops into runway track on the festooning end of runways.
3.3
FIELD QUALITY CONTROL
A. Move bridge and hoist trolley through entire travel to ensure crane is clear of
obstructions and moves freely and smoothly.
B. Inspect installed crane.
compressed.
Verify all bolts are tight and lock washers fully
C. Field test crane and accessories for operating functions. Ensure crane
movement is smooth and proper. Adjust as required and correct deficiencies.
D. Clean surfaces. If necessary, touch-up paint damage, scratches, and
blemishes with manufacturer provided matching paint.
E. Protect crane from other construction operations.
3.4
DEMONSTRATING AND TRAINING
A. Provide demonstration and training session for Owner's representative
covering operation and maintenance of free standing work station bridge
crane.
END OF SECTION
Wall-Supported Steel Bridge Crane
Section 14630
Statement of Work
V - 105
PMG Phase 1 Interim Action
SECTION 15060 - PIPE, FITTINGS, VALVES, AND SUPPORT
PART 1 GENERAL
1.1
DESCRIPTION
A.
1.2
1.3
1.4
1.5
Furnish, deliver, install, and test pipe, tubing, hose, fittings, valves,
support, and accessories as shown on Drawings, as specified herein, and
as required to completely interconnect equipment for complete and fully
functional systems.
SUBMITTALS
A.
Submit data to demonstrate conformance to Specifications requirements.
B.
Submit field functional and performance test results.
QUALIFICATIONS
A.
Material and equipment furnished under this section shall be of a
manufacturer who has been regularly engaged in design and manufacture
of the material and equipment for at least 5 years.
B.
Material and equipment furnished under this section shall demonstrate to
satisfaction of Engineer that the quality is equal to material and equipment
made by manufacturer specifically named herein, if alternative
manufacturer is proposed.
DELIVERY, STORAGE, AND HANDLING
A.
Material and equipment shall be prepared and protected for shipment and
shipped in accordance with manufacturer’s instructions.
B.
Openings and pipe ends shall be covered during shipment, storage, and
handling.
C.
Pipe, fittings, and valves shall be handled in such a manner to prevent
scratches, abrasions, impacts, and damage to any coatings.
WARRANTY
A.
Supplier(s) of material and equipment shall warrant them to be free from
defects in material and workmanship for at least 12 months from final
acceptance.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 106
PMG Phase 1 Interim Action
PART 2 PRODUCTS
2.1
GENERAL
A. Pipe
1. Material and equipment shall be new, first quality, free from defects, and
marked to identify material, manufacturer, and other appropriate data such
as thickness for pipe.
2. Pipe and fitting sizes are nominal inside diameter unless otherwise noted.
3. Construct vents and drains using the same material specified for pipe
system served by vents and drains, unless indicated otherwise.
4. Pipe and fittings for each type and size pipe system shall, if possible, be
supplied by one manufacturer.
5. Acceptance of material shall be subject to strength and quality testing in
addition to inspection of completed product. Acceptance of installed pipe
systems shall also be based on inspection and leakage tests as specified
herein.
6. Raised Face Flanges. When carbon-steel or stainless-steel flanges or
flanged valves with raised face will be bolted directly to flat-faced flanged
fittings or valves, the raised face shall be removed or spacers approved by
the valve or pipe manufacturer shall be installed to allow bearing over 100
percent of the flange area. Some instruments may require raised face
flanges. Coordinate and provide raised face flanges as required for
process instrumentation.
7. Unless otherwise specified, all pipe systems shall have a nominal design
pressure of 150 psig at 70 degrees Fahrenheit.
8. Pipe Markings. All pipe inside building, outside buildings, and in vaults
shall be clearly marked with self-adhesive, pre-printed, water-proof labels
(or equivalent) to indicate the fluid contained therein and the direction of
flow. Markings shall be spaced no less than every 10 feet along the length
of each interior pipe run between equipment terminations. For hoses
placed within buried conduit, a stamped, stainless steel tag, secured with
18 gauge Type 304 stainless steel wire, shall be placed on each end of
the hose to identify the fluid carried by the hose and a self-adhesive
marker shall be attached to each end of the hose indicating the direction
of flow and respective well number. Labels or tags shall be mounted in
such a manner to facilitate operations or maintenance activity. Marking
shall conform to the identification key presented on the Drawings.
Specifically, pipes shall be marked as follows:

Pipes from extraction wells to air stripper in treatment building shall be
marked “Groundwater”
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
B.
V - 107
PMG Phase 1 Interim Action

Water pipes from stripper to outfall shall be marked “Treated Water”

Potable water pipes from temporary water supply shall be parked
“Potable Water”

Air pipes (all) shall be marked “Air”
Valves
1. Valves and accessories shall be new, first quality, and free from
defects. Valves and accessories of a given type shall be from one
manufacturer.
2. Valve sizes are nominal inside diameter unless otherwise specified.
3. Material and equipment shall be marked to identify material,
manufacturer, and other appropriate data.
4. Acceptance of material shall be subject to strength and quality testing
in addition to inspection of completed product. Acceptance of installed
valve systems shall be based on inspection and leakage tests as
specified herein.
5. Valves shall be furnished with operators, hand wheels, levers, or other
suitable type wrench including handles as specified herein and as
shown on Drawings.
6. If valves have flanges, flanges shall have ANSI 150 pound standard
drilling.
7. Valve Markings. Valves shall be clearly marked with labels or tags to
clearly identify open, closed, or flow direction (for 3-way valves).
Labels or tags shall be mounted in such a manner to facilitate
operations or maintenance activity.
2.2
PIPE AND FITTINGS
A.
HDPE. Pipe shall be manufactured from a PE 3608 resin listed with the
Plastic Pipe Institute (PPI) as TR-4. The resin material will meet the
specifications of ASTM D 3350 with a cell classification of 345464C. Pipe
shall have a manufacturing standard of ASTM F 714. Pipe shall be
SDR 11 (160 psi WPR) unless otherwise specified on the plans. The pipe
shall contain no recycled compounds except that generated in the
manufacturer's own plant from resin of the same specification from the
same raw material.
1. Butt Fusion Fittings - Fittings shall be PE3608 HDPE, minimum cell
classification of 345464C as determined by ASTM D 3350. Molded butt
fusion fittings shall have a manufacturing standard of ASTM D 3261.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 108
PMG Phase 1 Interim Action
Molded fittings shall have the same pressure rating as the pipe unless
otherwise specified on the plans.
2. Electrofusion Fittings - Electrofusion fittings shall not be allowed.
3. Flanged and Mechanical Joint Adapters - Flanged and Mechanical
Joint Adapters shall be PE 3608 HDPE, minimum cell classification of
345464C as determined by ASTM D 3350. Flanged and Mechanical
Joint Adapters shall have a manufacturing standard of ASTM D 3261.
Fittings shall have the same pressure rating as the pipe unless
otherwise specified on the plans.
B.
Steel. Pipe shall be Schedule 40 galvanized or black carbon steel
conforming to ASTM A 53, Type E or S, Grade B; API 5L, Grade B; or
ASTM A 135, Grade B. Pipes shall be standard weight per ASME B36.10.
1. Steel fittings are defined as a special piece of pipe other than a normal
straight section.
2. Elbows, crosses, tees, and reducers are fittings.
3. Fittings shall be butt-welded conforming to ASME B16.9. Material shall
be wrought steel conforming to ASTM A 234, Grade WPB. Wall
thickness shall be the same as the pipe.
C.
Polyvinyl choloride (PVC). Pipe shall be Schedule 80 PVC.
1. Unless otherwise specified or shown on the drawings, joints shall be
either bell and spigot type with solvent cement bell and spigot. Pipe
joints shall be watertight at the pressures specified.
2. Solvent cement joints for PVC pipe and fittings shall be made in
accordance with ASTM D 2855 and appendices.
2.3
SUPPORTS
A.
General. The Contractor shall provide pipe hangers, brackets, saddles,
clamps, and other supports, as necessary, to support all dead loads and
live loads experienced by the piping and appurtenances. Pipe supports
conforming to these requirements shall be supplied whether or not shown
on the Drawings. Supports shall be provided at, but not limited to, points
of change in direction, each side of valves and fittings, both sides of
flexible joints, dead ends, and maximum spacing as defined by this
specification.
Pipe hangers, brackets, saddles, clamps, and other
supports shall be adjustable-type conforming to the requirements of ANSI
B31.1, and shall be shop-primed, including all bolts, nuts, and threaded
parts.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 109
PMG Phase 1 Interim Action
Hangers and supports shall include all hanging and supporting devices
shown, specified, or required for pipe lines, apparatus, and equipment
other than electrical equipment. The Contractor’s working drawings, as
required herein, shall show quantity, type, design, and location of all
hangers and supports required under the various Contract items. Hangers
and supports shall be hot-dipped galvanized, unless otherwise noted.
1. Where specified or shown, bolts, stud bolts, rods, yokes, and nuts of
hangers and supports shall be steel. Bolts shall not be less than
1/2inch in diameter unless otherwise called for on the Drawings.
2. Except where otherwise shown, specified, or required, hangers,
supports, anchors, and concrete inserts shall be the standard types as
manufactured by Crane Co., Grinnell Co., Fee and Mason
manufacturing Co., or approved equal, meeting the requirements
specified herein.
B.
Design. Hangers and supports shall be adequate to maintain the pipe
lines, apparatus, and equipment in proper position and alignment under all
operating conditions and have springs, where necessary. Where
adjustment is noted or required, supports shall be screw-adjustable after
installation.
C.
Supports for PVC Piping. Rigid plastic piping normally shall be supported
by the same type of hangers and supports used with steel pipe, except
that in no instance shall C-clamp, or other point-bearing supports, be
allowed. Riser clamps, if required, shall be full-circumferential type only.
Support spacing shall be based on the plastic pipe manufacturer’s
recommendations for service conditions, but not more than those noted
herein.
D.
Dissimilar Metals. Where pipe supports contact dissimilar metals, such as
copper pipe, a nonconductive, nonabsorbent elastomeric pad of plastic or
rubber shall be used to isolate the support from the pipe.
E.
Spacing of hangers and supports. Pipe support spacing requirements
shall be as indicated on the Drawings or as specified by the pipe
manufacturer. If not noted elsewhere, the spacing of pipe supports shall
not exceed the following:
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 110
PMG Phase 1 Interim Action
Maximum Unsupported Pipe Span (ft)
PVC or
Nominal Pipe Size
(inches)
Steel
Fiberglass
1/2
5
4
3/4
6
4
1
7
4.33
1-1/4
7
4.33
1-1/2
9
4.66
2
10
4.66
2-1/2
11
4
3
12
4.25
2.4
2.5
4
14
5.8
6
17
6.33
8
19
7
10
22
9
12
23
10
14
16
25
27
11
12
SERVICE CONDITIONS
A.
Location: Everett, WA
B.
Installation: Below grade in conduit and vaults, above grade exposed, and
inside building.
C.
Ground Water Temperature: 40 to 70 degrees Fahrenheit.
D.
Ambient Air Temperature Range: 15 to 90 degrees Fahrenheit.
E.
Relative Humidity of Ambient Air: 50 to 90 percent.
PERFORMANCE REQUIREMENTS
A.
Material and equipment shall meet the following performance
requirements when operating at service conditions listed in this section:
1. Material and equipment shall not corrode, deform, crack, become
brittle, or otherwise become unserviceable.
2. Material and equipment shall not leak.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 111
PMG Phase 1 Interim Action
3. Material and equipment shall be chemically resistant for intended use.
2.6
SPECIALTIES
A.
2.8
In-line instruments and controls. Install in-line instruments and controls
specified in Division 17.
PIPE INSULATION
A.
Contractor shall furnish and install closed cell, elastomeric pipe insulation,
meeting the requirements of ASTM C-534, Type 1 (tubing) or Type 2
(sheets), ASTM D 1056, SCE 41, and UL 94-5V (Flammability
Classification). Insulation shall be not less than 1/2-inch in thickness.
Insulation shall cover pipes, fittings, valve bodies, and appurtenances of
all outdoor exposed pipe runs, as shown on the drawings.
PART 3 EXECUTION
3.1
GENERAL INSTALLATION
A.
Building Risers Pipes/Conduits: The final location of all conduit and piping
risers (as shown on Drawings) in relationship to the building footprint shall
be confirmed by the Engineer prior to construction of the building
foundation.
B.
Well Riser Pipe: During the startup of the submersible pump, the torque
developed by the motor causes unscrewing torque on right-hand threaded
pipe. To safely withstand maximum unscrewing torque with minimum
safety factor of 1.5, tighten all threaded joints on the riser pipe to at least
10 ft-lb. per motor horsepower (with a minimum torque load of 10 ft-lb).
Wells EGW175 and EGW182 have pump motors with 5 hp, so well riser
pipe joints should be tightened to a minimum torque-load of 50 ft-lb). The
Contractor shall provide a calibrated torque wrench to verify installation of
threaded riser pipe in accordance with these specifications.
C.
Pipe (General)
1. Install pipe, fittings, valves,
recommended by manufacturer.
supports,
and
accessories
as
2. Inspect each item carefully before installation. Suspect material or
equipment shall not be installed.
3. Cut pipe ends square, reamed, and deburred inside and out to provide
a uniform, smooth surface for the jointing process. Remove chips and
cutting fluids.
4. Thoroughly clean and dry joining surfaces of each pipe and fitting prior
to making connection.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 112
PMG Phase 1 Interim Action
5. Place or erect pipe to accurate line and grade, and support, hang, or
brace against movement as required for proper installation.
6. Tighten bolts, nuts, and fittings securely.
7. Reducing fittings shall be used where change in pipe size occurs.
Bushings shall not be used unless reducing fittings are not available.
Eccentric reducing fittings shall be used wherever necessary to provide
for free drainage of pipes.
8. Unless otherwise shown on Drawings, install pipe parallel to structure
lines, plumb, and level.
9. Install pipe without springing or forcing pipe in a manner that would set
up stresses in pipe, fitting, or connected equipment.
10. Flanged fittings shall be true and perpendicular to axis of pipe. Bolt
holes in flange shall straddle vertical centerline of pipe.
11. Where equipment drain connections are provided, they shall be valved,
with the drain discharge pipe carried to the nearest floor drain, drain
trench, or sump. Drain pipe and valve material shall conform to
requirements of system served.
12. Anchor pipe subject to expansion and contraction so that strains are
distributed.
13. Sleeves for branches through walls that are not secured with wall seals
(if any) shall allow for free side motion of pipe in sleeves.
14. Where necessary to connect to tanks, pumps, and other equipment at
the end of pipe runs or branches, materials to make such connections
shall be in accordance with this section.
15. Where piping is secured flat to the ground and may be damaged by
normal foot traffic, Contractor shall provide and install a protective
ramp over the pipe, fabricated either from galvanized steel grating or
from 1/4-inch thick galvanized “diamond-plate” steel.
D.
Valves
1. Inspect valves and accessories carefully before installation. Suspect
material or equipment shall not be installed.
2. Remove dirt and foreign matter from valve interior prior to installation.
3. Thoroughly clean joints before joining.
4. Unless otherwise shown, install valves parallel to pipe lines and
grades.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 113
PMG Phase 1 Interim Action
5. Snugly install screwed fittings and union nuts.
6. Orient valves to permit easy access to handles or operators and to
avoid interference.
E.
Accessories
1. Install
accessories
recommendations.
in
accordance
with
manufacturer’s
2. Install accessories so parts are easily accessible for maintenance and
operation.
3. Install union adjacent to each screwed end accessory.
4. Install valve below each pressure gauge unless otherwise specified.
3.2
PIPE INSTALLATION: SPECIFIC
A.
Pressurized HDPE Pipe - Fusion:
1. Exercise great care to prevent injury to or scoring of pipe during
handling, transport, or storage. Pipe shall not be stored on rough
ground. Damaged pipe and fittings shall be repaired or replaced at
expense of Contractor at direction of Owner.
2. Place pipe within installation areas at least 24 hours prior to installation
to permit temperature equalization.
3. Sections of HDPE pipe should be joined into continuous lengths on the
jobsite above ground. The joining method shall be the butt fusion
method and shall be performed in strict accordance with the pipe
manufacturer's recommendations. The butt fusion equipment used in
the joining procedures should be capable of meeting all conditions
recommended by the pipe manufacturer, including, but not limited to,
temperature requirements of 400-450 degrees Fahrenheit, alignment,
and an interfacial fusion pressure of 75 PSI. The butt fusion joining will
produce a joint with weld strength equal to or greater than the tensile
strength of the pipe itself.
4. Sidewall fusions for connections to outlet piping shall be performed in
accordance with HDPE pipe and fitting manufacturer’s specifications.
The heating irons used for sidewall fusion shall have an inside
diameter equal to the outside diameter of the HDPE pipe being fused.
The size of the heating iron shall be ¼ inch larger than the size of the
outlet branch being fused.
5. Mechanical joining will be used where the butt fusion method can not
be used. Mechanical joining will be accomplished by either using a
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 114
PMG Phase 1 Interim Action
HDPE flange adapter with a ductile iron back-up ring or HDPE
Mechanical Joint adapter with a ductile iron back-up ring.
6. Socket fusion, hot gas fusion, threading, solvents, and epoxies will not
be used to join HDPE pipe.
7. Flanged joints: Bolts and a gasket shall be installed at each flanged
joint. Bolts, with washers on each end, shall be installed in each flange
hole and nuts shall be tightened snugly. Bolts shall not be forced into
place.
B.
PVC Pipe:
1. Exercise great care to prevent injury to or scoring of pipe during
handling, transport, or storage. Pipe shall not be stored on rough
ground. Damaged pipe and fittings shall be repaired or replaced at
expense of Contractor at direction of Owner.
2. Bell and spigot/fitting joints: Reference marks shall be placed on the
spigot/female ends to assist in determining when proper seating depth
has been achieved within the joint.
3. Flanged joints: Bolts and a gasket shall be installed at each flanged
joint. Bolts, with washers on each end, shall be installed in each flange
hole and nuts shall be tightened snugly. Bolts shall not be forced into
place.
C.
Steel Pipe:
1. Screwed joints:
a. Coat male threads with joint lubricant seal compound Permatex No.
2, teflon tape or equal.
b. Threaded joints shall have connections made metal to metal.
2. Flanged joints: Bolts and a gasket shall be installed at each flanged
joint. Bolts, with washers on each end, shall be installed in each flange
hole and nuts shall be tightened snugly. Bolts shall not be forced into
place.
3. Welded Joints:
a. Beveled ends for butt welding shall conform to ASME B16.25.
Remove slag by chipping or grinding. Surfaces shall be clean of
paint, oil, rust, scale, slag, and other material detrimental to
welding. When welding the reverse side, chip out slag before
welding.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 115
PMG Phase 1 Interim Action
b. Apply full penetration weld to exterior joint of butt welded pipe,
fittings, and welding neck flanges. Apply fillet welds to the interior
and exterior circumference of the pipe and slip on flanges.
Minimum size of fillet weld shall be equal to the steel cylinder
thickness. Complete each pass around the entire circumference of
the pipe before commencing the next pass. Use electrodes
recommended by the pipe fabricator. Do not deposit more than
1/8-inch of throat thickness per pass. The minimum number of
passes or beads in the completed weld shall be as follows:
Steel Cylinder Thickness
(inch)
0.2500 and Less
Minimum Number of Passes
for Welded Joints
2
Greater than 0.2500
3
c. Use the shielded metal arc welding (SMAW) process for welding.
d. Limitations on imperfections in welds shall conform to the
requirements in ASME B31.3, Table 341.3.2, and paragraph 341.4
for visual examination.
e. Clean each layer of deposited weld metal prior to depositing the
next layer of weld metal, including the final pass, by a power-driven
wire brush.
f. After shop fabrication and prior to shop applied linings and
coatings, test each welded joint by the liquid penetrant method.
Conform to the requirements specified in ASTM E 165. The
materials used shall be either water washable or nonflammable.
g. Chip out all defects, reweld, and retest the section affected until it
shows no leaks or other defects.
D.
Hose and Tubing:
1. Install hose and tubing without twists, kinks, excessive bends, or
tension.
2. Snugly tighten hose clamps used to secure hose ends.
3.3
CLEANING
A.
Prior to testing, thoroughly clean inside of each completed pipe system
and remove dirt, loose scale, sand, and other foreign material.
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
3.4
V - 116
PMG Phase 1 Interim Action
B.
Clean by sweeping, flushing with water, or blowing with compressed air.
C.
Install temporary strainers, temporarily disconnect equipment, or take
other appropriate measures to protect equipment while cleaning pipe and
to access otherwise inaccessible areas.
FIELD TESTS
A.
Prior to system startup, pipe and fittings described herein will be inspected
by the Engineer for function and for proper level, alignment, and
connection. Additional performance tests shall be performed by Contractor
as described below:
B.
Pressurized Liquid Systems – Test for leakage by completely filling with
water and pressurizing to 100 psig. Monitor pressure and temperature,
and verify reduction in pressure of less than 0.5 psig over 4-hour period
when accounting for temperature change of the pressurized fluid. Modify
or replace components that fail to meet required performance. Repeat
leakage tests until conformance to leakage test requirements specified
herein have been fulfilled.
C.
Gravity Drain Liquid Systems - Test for leakage by completely filling with
water to highest point. Monitor water level and verify leakage rate of less
than 0.02 gallon per hour per inch diameter per 100 ft of line. Tests shall
be conducted over a 24-hour period. Modify or replace components that
fail to meet required performance. Repeat leakage tests until conformance
to leakage test requirements specified herein have been fulfilled.
D.
Performance Test (Air Stripper Vent Ducting) – Test air discharge line
downstream (on pressure side of blower) for leakage by soaping all
ducting within the building while air stripper is operational and examining
closely for bubbles. Repair any leaks found and retest.
E.
Temporarily disconnect gauges or other equipment, or take other
appropriate measures to protect equipment from excessive pressure
during performance testing. Clean up any water leaked during
unsatisfactory testing and repair damage to any material or equipment
caused by pressure testing.
END OF SECTION
Pipe, Fittings, Valves, and Supports
Section 15060
Statement of Work
V - 117
PMG Phase 1 Interim Action
SECTION 15160 - WELL EQUIPMENT
PART 1 GENERAL
1.1
DESCRIPTION
A.
1. 2
1. 3
General. Provide those materials not provided by the Owner. Install well
pumping equipment complete, as indicated on the Drawings and specified
herein and appurtenances as necessary to form a complete, installed and
operational system.
RELATED SECTIONS
A.
Section 02605: Vaults
B.
Section 15060: Pipe, Fittings, Valves, and Pipe Supports
C.
Section 17000: Instrumentation, Control, and Monitoring
SUBMITTALS
A.
Submit system field performance test results.
B.
Submit all manufacturer’s operations and maintenance manuals, bulletins,
spare parts lists, and warranties for equipment supplied by Contractor.
PART 2 PRODUCTS
2.1
SUBMERSIBLE PUMPS
A.
General. Contractor shall provide all associated materials and fittings
necessary to construct a complete operating system.
B.
The submersible electric groundwater extraction pump shall be in
accordance with the Drawings.
C.
Pump shall be manufactured by Grundfos Pumps Corporation. Pump
motors shall be manufactured by Franklin Electric. Pump motor size shall
be 4-inch, not 6-inch. All wetted components of pumps, pump motors, and
motor leads shall be compatible with TCE concentrations up to 20 ppm.
Submersible pumps shall be secured with a safety cable.
Well Equipment
Section 15160
Statement of Work
V - 118
PMG Phase 1 Interim Action
PART 3 EXECUTION
3.1
INSTALLATION AND START-UP
A.
3.2
SYSTEM DESCRIPTION - EXTRACTION PUMP
A.
3. 3
Test, startup, and adjust the well equipment.
The theory of operation and control system for the groundwater pumping
system is provided in Section 17000.
EQUIPMENT TESTING
A.
Field Testing
1. Following completion of the installation and satisfactory start-up of the
equipment, the Contractor shall operate each pumping unit to confirm
operation in accordance with manufacturer’s recommendations and
these specifications.
2. Perform system operational demonstrations and system validation
tests in conjunction with the requirements of Section 17000.
END OF SECTION
Well Equipment
Section 15160
Statement of Work
V - 119
PMG Phase 1 Interim Action
SECTION 15400 - TREATMENT EQUIPMENT
PART I GENERAL
1.1
DESCRIPTION
A.
1.2
1.3
1.4
RELATED SECTIONS
A.
Section 15060: Pipe, Fittings, Valves, and Support
B.
Section 17000: Instrumentation, Control, and Monitoring
SUBMITTALS
A.
Submit functional and performance test results.
B.
Submit all manufacturer’s operations and maintenance manuals, bulletins,
spare parts lists, and warranties for equipment supplied by Contractor.
QUALIFICATIONS
A.
1.5
Treatment equipment furnished under this section shall be of a
manufacturer who has been regularly engaged in design and manufacture
of the material and equipment for at least 5 years.
DELIVERY, STORAGE, AND HANDLING
A.
1.6
Furnish (equipment not provided by Owner), deliver, install, test, and startup treatment equipment as shown on the Drawings, as specified herein,
and as required to provide a complete and fully functional treatment
process.
Equipment and materials furnished under this section shall be prepared
and protected for shipment, shipped, and stored until installation per
manufacturers’ instructions.
GUARANTEE AND WARRANTY
A.
Suppliers of equipment shall guarantee performance at design conditions.
B.
Suppliers of equipment and material shall warrant them free of defects in
material and workmanship for at least 12 months from initial acceptance.
Treatment Equipment
Section 15400
Statement of Work
V - 120
PMG Phase 1 Interim Action
PART 2 PRODUCTS
2.1
GENERAL
A.
2.2
2.3
Equipment and materials furnished under this section shall be new.
SERVICE CONDITIONS
A.
Location: Everett, WA
B.
Installation: Groundwater treatment system sheltered in heated (above
40°F) building.
C.
Groundwater Temperature: 40 to 70 degrees Fahrenheit.
D.
Ambient Air Temperature Range: 15 to 90 degrees Fahrenheit.
E.
Relative Humidity of Ambient Air: 40 to 90 percent
PERFORMANCE REQUIREMENTS
A.
Material and equipment shall meet the following performance
requirements when operating at service conditions listed in this section:
1. Material and equipment shall not corrode, deform, crack, become
brittle, or otherwise become unserviceable.
2. Material and equipment shall not leak.
3. Material and equipment shall be chemically resistant for intended use.
2.4
SPECIFIC EQUIPMENT
A.
Air Stripper – Contractor shall coordinate with Engineer and Owner to
arrange for delivery of air stripper package from current location in Kent,
Washington to new treatment building. Contractor shall pay for all delivery
costs.
B.
Blower – Contractor shall coordinate with Engineer and Owner to arrange
for delivery of air stripper package from current location in Kent,
Washington to new treatment building. Contractor shall pay for all delivery
costs.
Treatment Equipment
Section 15400
Statement of Work
2.5
PMG Phase 1 Interim Action
C.
Moisture Separator – Supply unit meeting specifications in Drawings.
D.
Duct Heater – Supply unit meeting specifications in Drawings.
E.
Granular Activated Carbon Vessels and Manifold – Supply units meeting
specifications in Drawings.
TREATMENT SYSTEM BUILDING
A.
2.6
V - 121
Contactor shall provide materials and construct new treatment system
building per Drawings. Building shall be furnished with locks and shall
supply Owner with a minimum of four (4) sets of keys.
OTHER EQUIPMENT
A.
Contractor shall provide all associated electrical, piping, and support
equipment even if not specifically included in the drawings or referenced in
the specifications, as necessary to provide a fully functional and secure
system.
B.
Contractor shall provide a bridge crane work station system with two
mobile bridges per the Drawings.
C.
Contractor shall provide a temporary water system per the Drawings.
D.
Contractor shall provide an emergency eyewash/shower station per the
Drawings and a hose with hose reel to be mounted inside the treatment
system building.
PART 3 EXECUTION
3.1
EQUIPMENT INSTALLATION
A.
Install and connect the treatment system equipment (i.e., air stripper,
blower, discharge/transfer pump, temporary holding tank, moisture
knockout, duct heater, granular activated carbon vessels); associated
piping, ducts, conduits, valves, meters; and building and system
appurtenances (i.e., control panels, sump pump, temporary water supply
equipment, emergency eyewash and shower) as shown on the Drawings.
Because treatment system equipment dimensions may vary from those
shown in the Construction Drawings, Engineer shall be consulted on final
placement of equipment and associated piping, ducts, and conduits.
Treatment Equipment
Section 15400
Statement of Work
3.2
V - 122
PMG Phase 1 Interim Action
B.
Provide and install all interconnecting piping between equipment.
Contractor may use structural elements of the building shell to support
piping and conduit, provided such support does not exceed building
design loads.
C.
Install all equipment in a manner that allows access to all equipment for
operations, maintenance, and monitoring. Contractor shall route pipes to
minimize obstruction to foot traffic, and mount pipes to walls in an orderly
manner such that valves, sampling ports, and gauges are easily
accessible.
TESTING
A.
Functional Tests
1. Perform equipment functional tests per manufacturer’s instructions.
B.
B. Performance Tests
1. Perform equipment performance tests per manufacturer’s instructions.
2. Perform integrated performance tests per Division 17.
END OF SECTION
Treatment Equipment
Section 15400
Statement of Work
V - 123
PMG Phase 1 Interim Action
SECTION 17000 - GENERAL INSTRUMENTATION, CONTROL,
AND MONITORING REQUIREMENTS
PART 1 GENERAL
1.1
1.2
1.3
DESCRIPTION
A.
This section covers general requirements for furnishing instrumentation,
control, and monitoring (ICM) systems complete in every detail for
purposes specified and specifies primary elements of process
instrumentation, auxiliary equipment and supplies directly related to
installation and operation of these primary elements.
B.
Furnish equipment, material, supplies, and special tools and install ICM
system. Ensure conduit runs, signal, and power wiring is consistent with
requirements of equipment specified in this section. Perform operational
testing of individual systems and complete start up of systems as
indicated on Drawings and as specified herein.
C.
Set up and program Programmable Logic Controllers (PLC) required
operational, alarm, and shutdown functions per the Drawings and
standard and emergency system operating conditions.
RELATED SECTIONS
A.
Section 15060: Pipe, Fittings, Valves, and Support
B.
Section 15400: Treatment Equipment
C.
Section 17700: System Operating Description.
QUALITY ASSURANCE
A.
Manufacturer. Instrumentation and control equipment furnished by
Contractor shall be manufactured by a firm regularly and currently
engaged in design and manufacture of similar equipment for at least the
past 5 years. Equipment furnished shall be new and of current design.
B.
Equipment/materials of the same type shall be products of the same
manufacturer. Capacities of equipment shall not be less than that
indicated on Drawings or in Specifications.
C.
Material and equipment furnished under this section for which an
alternative manufacturer is proposed shall be demonstrated to the
satisfaction of the Engineer that the quality is equal to the materials and
equipment made by the manufacturer specifically named herein.
General Instrumentation, Control, and Monitoring Requirements
Section 17000
Statement of Work
1.4
General. Contractor shall submit for review and approval shop drawings,
material lists, instrument installation and instruction manuals, and other
pertinent information to allow verification of compliance with the
requirements of this section. Submittals shall be assembled and identified
by the specific equipment tag numbers for the primary elements required
for this project.
DELIVERY, STORAGE, AND HANDLING
A.
1.6
PMG Phase 1 Interim Action
SUBMITTALS
A.
1.5
V - 124
Material and equipment provided by Contractor shall be delivered, stored,
and handled in accordance with manufacturer's instructions.
GUARANTEE AND WARRANTIES
A.
Guarantee all Work of Division 17. With respect to instruments and
equipment provided by Contractor, guarantee shall cover:
1. Faulty or inadequate design.
2. Improper assembly or erection (includes equipment provided by
Owner).
3. Defective workmanship or materials.
4. Leakage, breakage, or other failure not caused by Owner misuse. For
equipment bearing manufacturer’s warranty in excess of one year,
furnish copy of warranty to Owner with Owner named as beneficiary.
PART 2 PRODUCTS
2.1
PRESSURE GAUGES/TRANSMITTERS
A.
Gauges - Provide for wellheads and in-line pipe vaults (water), blower
intake (air), and GAC vessel manifold (air) per Drawings or approved
equivalent. Pressure range shall be as shown on the Drawings. Accuracy
shall be a minimum of ANSI Grade B (±2 percent of full scale) and shall
have dial size of 2-1/2 inches. Gauges shall have a stem mounting,
bottom connection. Connections for all gauges shall be 1/4 inch NPT with
square wrench flats. Wetted parts shall be corrosion resistant. Cases shall
be corrosion resistant and weather proof.
B.
Transmitter - Provide for wellhead (water) and blower intake (air) per
Drawings or approved equivalent. Transmitter shall be compatible with
PLC.
General Instrumentation, Control, and Monitoring Requirements
Section 17000
Statement of Work
2.2
2.3
2.4
A.
Water - Provide for wellheads (well discharge conveyance line in vault)
and treatment system (intake manifold and discharge to outfall) per
Drawings. Flow rate range shall be as shown on the Drawings. Accuracy
shall be a maximum ± 1% of measurement over full scale. Flow Display
shall have non-resettable totalizer display with indication to ± 1 gallon.
Hermetically sealed and waterproof register to prevent condensation or
fogging of display. Meter shall transmit output signal compatible with PLC.
B.
Air - Provide for stripper intake per Drawings or approved equivalent.
Flow rate range shall be as shown on the Drawings. Accuracy shall be a
maximum ± 1% of measurement over full scale. Flow Display shall have
non-resettable totalizer display with indication to ± 1 scfm. Hermetically
sealed and waterproof register to prevent condensation or fogging of
display. Meter shall transmit output signal compatible with PLC.
TEMPERATURE GAUGES/TRANSMITTERS
A.
Thermometer - Provide for air stripper intake and pre-duct heater per
Drawings. Provide compatible thermowell for pressure application at preduct heater location. Temperature range shall be as shown on the
Drawings. Accuracy shall be a maximum ± 1 degree Fahrenheit.
B.
Transmitter – Provide temperature transmitter for post-duct heater per
Drawings. Transmitter shall be compatible with PLC.
LEVEL TRANSMITTERS/SWITCHES
Provide for wells, well vaults, air stripper clearwell, building sump, and
holding tank per Drawings. Transmitters shall be compatible with PLC.
MOUNTINGS
A.
2.6
PMG Phase 1 Interim Action
FLOW METERS/TRANSMITTERS
A.
2.5
V - 125
Mount and install equipment as indicated. Where not shown, mount field
instruments, according to best standard practice, on pipe mounts,
pedestal mounts, wall mounts, or other similar means in accordance with
supplier’s recommendation.
INSTRUMENTATION AND CONTROL
A.
Instrumentation and control including PLC, control panels, and autocommunications, and user interface, to be provided per Drawings.
General Instrumentation, Control, and Monitoring Requirements
Section 17000
Statement of Work
V - 126
PMG Phase 1 Interim Action
PART 3 EXECUTION
3.1
INSPECTION
A.
3.2
PREPARATION
A.
3.3
3.4
Inspect each instrument and piece of equipment for damage, defects,
completeness, and correct operation before installing.
Ensure that installation areas are clean and that concrete or other
structural operations are completed prior to installing instruments and
equipment. Maintain areas in a clean condition during installation
operations.
INSTRUMENT INSTALLATION, CALIBRATION, AND PROGRAMMING
A.
Install, connect, calibrate, and functionally test each instrument and
related components per manufacturer’s instructions and the Drawings.
Instruments and controls shall be installed by, or under the oversight of, a
professional electrical systems engineer or technician familiar with
remediation system PLC.
B.
The PLC system and controls shall be programmed by the electrical
systems engineer/technician.
A logic ladder and a user interface
conceptual design, upon which the PLC programming will be based, shall
be developed by the electrical system engineer in consultation with the
Engineer. The logic ladder shall at a minimum incorporate the system
operating conditions described in Section 17400.
SYSTEM VALIDATION
A.
General. Perform system validation of full system including ICM system
and including all vendor provided equipment.
B.
Verify all system switches and shutdowns. Cause malfunctions to sound
alarms, or switch to standby, to check system operation. Check systems
thoroughly for correct operation.
C.
Perform system startup and operation for initial “shakedown” period in
cooperation with Engineer. At a minimum this system testing shall
include, but not be limited to:
1. Potable water shall be used to fill various system components in the
treatment building (e.g., air stripper, sump, moisture knockout,
temporary holding tank) to test system controls, alarms, and shutoffs).
System valves will be configured to test operation and transfer of water
in several configurations:
General Instrumentation, Control, and Monitoring Requirements
Section 17000
Statement of Work
V - 127
PMG Phase 1 Interim Action
a. Transfer from stripper to sewer outfall (simulated standard
operating conditions)
b. Transfer from stripper to temporary holding tank
c. Transfer from temporary holding tank to stripper (simulated
retreatment).
2. Observing startup and short term of continuous operation of blower
(e.g., at least 1 hour).
3. Observing startup and short term of continuous operation of each well
pump (e.g., at least 10 minutes each).
Pumps shall be run
independently without other pumps in operation and with all pumps
operating simultaneously. The air stripper and blower shall be run
simultaneously with discharge routed to temporary holding tank(s).
D.
During each of these tasks, system components, vaults, valves, meters,
piping, ducts, etc. shall be observed for leaks and malfunctions.
E.
Immediately correct defects and malfunctions disclosed by tests. Use new
parts and material as required and approved, and retest. Provide report
certifying completion of validation of each instrument system. Report shall
indicate calculated system tolerances, verification that system meets
these tolerances, and any provisional settings made to devices.
F.
Testing shall be observed by Engineer. Notify Engineer in writing a
minimum of 48 hours prior to proposed date for commencing test.
END OF SECTION
General Instrumentation, Control, and Monitoring Requirements
Section 17000
Statement of Work
V - 128
PMG Phase 1 Interim Action
SECTION 17700 – SYSTEM OPERATING DESCRIPTION
PART 1 GENERAL
1.1
DESCRIPTION
A.
1.2
1.3
1.4
This section describes functional requirements of and process for
instrumentation, control, and monitoring systems.
RELATED SECTIONS
A.
Section 15400: Treatment Equipment
B.
Section 17000:
Requirements
General
Instrumentation,
Control,
and
Monitoring
SYSTEMS - GENERAL
A.
This project comprises a groundwater extraction, treatment, and discharge
system for Powder Mill Gulch at the Boeing Everett Plant as shown in the
Drawings. The groundwater extraction system consists of 3 groundwater
extraction wells that are outfitted with submersible pumps that will convey
groundwater through a series of interconnecting pipelines to a treatment
system. The treatment system features a low-profile air stripper as the
fundamental treatment process. Subsystem processes for treatment of
groundwater include a discharge pump, temporary holding tank, and
transfer pump for testing, temporary storage, and/or retreatment of
groundwater; a moisture separator, duct heater, and GAC vapor treatment
vessels for the air stream from the air stripper; and other ancillary
subsystems. The system will be monitored and controlled by a PLC and
associated controls with remote telemetry and communications.
B.
Intent of the Drawings and this section is to provide ICM system
subcontractor a generalized schematic and functional description of how
the ICMs are to operate and provide the basis for developing a logic
ladder for PLC programming.
SUBMITTALS
A.
General. Contractor shall submit for review and approval the logic ladder
and conceptual user interface design upon which PLC programming will
be based. Submittal and approval by the engineer of the logic ladder and
conceptual user interface design shall not relieve the Contractor in any
way of its responsibility to provide a fully functional ICM system as
described in this section.
System Operation Description
Section 17700
Statement of Work
1.5
V - 129
PMG Phase 1 Interim Action
SYSTEM DESCRIPTIONS
A.
General – The following paragraphs describe functional requirements of
ICM systems and processes to which they apply. Automatic control of
process systems shall be accomplished through use of a PLC and
associated controllers. Remote communications to the Operator (i.e.,
automated signals and alarms to a remote Operator terminal and pager)
shall be controlled and performed by the PLC. Operator shall have ability
to remotely access the PLC and control certain extraction system and
treatment system operations (i.e., extraction pump operation and motor
speed, blower operation and motor speed, discharge pump operation and
motor speed, duct heater temperature control, and total system startup
and shutdown).
B.
Groundwater Extraction
1. The theory of the operation and control system for each respective
extraction system is identical.
a. Groundwater shall be pumped from each extraction well by a
submersible pump (e.g., P-101) and conveyed to the groundwater
treatment system through a series of interconnected pipelines.
Quantity of groundwater pumped from each well shall be metered
through a magnetic flow meter (e.g., FI/FIT-101). Flow rate shall be
indicated locally and transmitted to the PLC (PLC-501) located at
the treatment building. Combine flow rate of all wells will also be
metered through a magnetic flow meter (FI/FIT-201) at the influent
to the air stripper, indicated locally, and transmitted to the PLC.
PLC will display flow and totalized flow from each well individually
and sum the combined flow rates and flow totals from each
extraction well. Groundwater level in each well shall be monitored
by a pressure transducer (e.g., LE/LIT-101). Groundwater level
shall be transmitted to the PLC and displayed. Pump discharge
pressure shall be measured by pressure meters (e.g., PI/PIT-101)
at the wellhead, indicated locally, and transmitted to the PLC. PLC
will display pump discharge pressure at each well. Pump running
time shall be indicated in total cumulative hours at the PLC.
b. PLC shall monitor groundwater elevation via pressure transducers
in each well (LE/LIT-101, -102, and -103) and control groundwater
elevation at each well by signaling each well control panel (e.g.,
CP-101) located in a CP enclosure proximate to the well (or in the
treatment system building for EGW183) to adjust the groundwater
extraction rate from each respective well, by modulating the input
signal to the variable frequency drive (VFD) and thereby increasing
or decreasing the pump speed, to maintain a predetermined
groundwater elevation within the extraction well. If groundwater
level should fall below preset minimum level and pump speed has
been reduced to preset minimum speed, the PLC shall signal pump
System Operation Description
Section 17700
Statement of Work
V - 130
PMG Phase 1 Interim Action
shut down after operator adjustable but preset time period. Pump
shall remain shut down until groundwater level returns to preset but
operator adjustable level above preset minimum level.
c. PLC will monitor pump discharge pressure at each well (PI/PIT101, -102, and -103) and send signal to respective CP. Set points
for low or high pressure conditions shall be established at PLC and
interlocked with CP and operation of pump. Low and high pressure
failure signals shall be indicated at PLC, if pressure is below low
pressure set point or above high pressure set point. PLC will signal
pump shutdown if condition persists after preset but operator
adjustable time delay. If pump shutdown is initiated, PLC will
remotely communicate condition to Operator.
d. The combined flow rate of all wells will be metered through a
magnetic flow meter (FI/FIT-201) at the influent to the air stripper,
indicated locally, and transmitted to the PLC. PLC will display and
totalize flow from each well and sum the combined flow rates from
the three extraction wells (total of FI/FIT-101, -102, and -103). PLC
shall compare the sum of the flow rates from each individual well to
the combined flow rate measured at air stripper influent. If flow
rates are not equivalent within a specified tolerance (e.g., if
summed flow rate is greater than 5% [plus the rated accuracy of
instruments] higher than the combined flow rate at treatment
building), a leak in the conveyance line may be present. Pipeline
failure (leak) signals shall be indicated at the PLC and remotely
communicated to Operator. If condition persists after an operator
adjustable but preset time delay, the PLC will signal initiation of
system shutdown sequence of the extraction system and treatment
system. If shutdown sequence is initiated, PLC will remotely
communicate condition to Operator.
e. Submersible pump operation shall be identified on a stack light
located at the respective well CP enclosure by illumination of a
green operating light (e.g., OL-101). Motor overload or other
system failures shall be indicated on a red stack light at well control
CP enclosure and a main control panel (CP-501) cover by
illumination of a red general alarm light (GA). Alarm lights and
displays shall remain illuminated or activated until failure is cleared
through the PLC user interface (remote or local).
C.
Air Stripper Treatment Equipment
1. The theory of the operation and control system for the air stripper
treatment system is described below.
a. The air stripping treatment equipment specified shall treat influent
groundwater over a range of flow rates. Air shall be drawn through
the low-profile air stripper from the suction side of the positive
System Operation Description
Section 17700
Statement of Work
V - 131
PMG Phase 1 Interim Action
displacement blower. The blower motor speed will be controlled
through a VFD. The blower is designed to maintain a constant but
operator adjustable air to water ratio. As influent groundwater flow
rate increases or decreases as measured by FI/FIT-201, PLC shall
signal CP-501 to proportionally increase or decrease air flow rate
supplied to the stripper, as measured by the air flow meter on the
stripper air intake (FI/FIT-301) to maintain a minimum air to water
ration of 60:1, by adjusting the blower motor speed through the
VFD. Air flow rate supplied to the stripper shall be supplied at a
minimum rate of 1800 SCFM and a maximum rate of 3600 SCFM.
b. The total groundwater flow rate entering the air stripper, as
measured by FI/FIT-201, shall also be monitored by the PLC
against a total allowable flow rate into the air stripper (i.e., the
maximum design [or empirically demonstrated] groundwater flow
rate at which the air stripper can achieve contaminant reductions to
less than the regulatory discharge limit). Groundwater flow rates in
excess of this value shall signal a system alarm and be remotely
communicated to Operator. If condition persists after an operator
adjustable but preset time delay, the PLC will signal initiation of
system shutdown sequence of the extraction system and treatment
system. If shutdown sequence is initiated, PLC will remotely
communicate condition to Operator.
c. PLC shall monitor water level in the air stripper clear well via an
ultrasonic level indicator (LE/LIT-301) and control the water level by
adjusting the pumping rate of the discharge pump (P-301) by
modulating the input signal to the variable frequency drive (VFD)
and, thereby, increasing or decreasing the pump speed to maintain
a predetermined operator-controlled level within the air stripper
clear well. If the water level should fall below the preset minimum
level and pump speed has been reduced to the preset minimum
speed, the PLC shall signal pump shutdown after operatoradjustable, but preset, time period. Pump shall remain shut down
until groundwater level returns to preset, but operator-adjustable
level above the preset minimum level. The air stripper clearwell
shall also be equipped with a high-level switch (LSH-301) and lowlevel switch (LSL-301). If water level in clearwell rises or lowers
causing either level switch to be triggered, PLC will be signaled. If
condition persists after an operator adjustable but preset time
delay, the PLC will signal initiation of system shutdown sequence of
the extraction system and treatment system. If shutdown sequence
is initiated, PLC will remotely communicate condition to Operator.
d. Air pressure (vacuum) shall be measured by pressure meter
PI/PIT-301 at the blower intake and transmitted to the PLC. PLC
will monitor the vacuum. Set points for low or high vacuum
conditions shall be established at PLC and interlocked with CP-501
and operation of blower. Low and high vacuum alarms shall be
System Operation Description
Section 17700
Statement of Work
V - 132
PMG Phase 1 Interim Action
indicated at PLC and communicated to Operator, if pressure is
below low pressure set point or above high pressure set point. PLC
will signal blower and extraction system shutdown if condition
persists after preset but operator adjustable time delay. If blower
shutdown is initiated, PLC will remotely communicate condition to
Operator.
D.
Vapor Treatment Equipment
1. The theory of the operation and control system for the vapor treatment
system is described below.
a. Moisture Separator – An air moisture separator shall be located inline between the air stripper and blower. Liquid level in the
separator shall be controlled by high-, high-high- and low-level float
switches (LI/LIT-301). If level in the separator rises causing the
high-level float switch to be triggered, the integrated condensate
pump will be signaled to evacuate the separator into the building
dead-end sump. The condensate pump shall pump until the lowlevel float switch is triggered, signaling the condensate pump to
shut off. If the high-high-level switch is triggered, the PLC will be
signaled. PLC will signal treatment system and extraction system
shutdown if condition persists after preset but operator adjustable
time delay. If system shutdown is initiated, PLC will remotely
communicate condition to Operator.
b. Duct Heater – A duct heater shall be located in-line between the
blower and GAC vessels. Air temperature downstream of the duct
heater (at the intake to the GAC vessels) shall be measured by TT301. Air temperature shall be transmitted to, displayed, and
monitored by the PLC. PLC shall control air temperature entering
the GAC vessels by signaling the duct heater temperature
controller (TC-301) to adjust the heat input of the duct heater to
maintain a predetermined air temperature within the air duct at the
GAC vessel intake.
c. Vapor Treatment – Air flow through two GAC vessels (GAC-301
and GAC-302) shall be manually controlled with a 6-valve manifold
allowing operation in series or parallel configurations. Differential
pressure across the vessels shall be monitored manually by
pressure gauges PI-301/302/303.
E.
Other Equipment
1. A description of other equipment and controls associated with the
treatment system, treatment system building, or well vaults is
described below.
System Operation Description
Section 17700
Statement of Work
V - 133
PMG Phase 1 Interim Action
a. Building Sump/Sump Pump/Leak Detection – A dead-end sump
shall be located in the treatment building for secondary containment
of liquid spills or discharges. The sump will contain level switchs
(LE-501) that will trigger a high-level alarm and high-high level
switch. If liquid level in the sump rises causing the high-level switch
to be triggered, a system alarm will be signaled to the PLC and
identified on a red alarm light at CP-501 and remotely to the
Operator. If the high-high level switch is triggered, the PLC will be
signaled and the PLC shall initiate a shutdown of the extraction
system and treatment system. If system shutdown is initiated, PLC
will remotely communicate condition to Operator. The sump will
also be equipped with a sump pump (P-501). Sump pump shall be
manually operated by a hand switch (HS-502) on the sump pump
control panel (CP-502).
b. Well Vault Sumps/Sump Pumps/Leak Detection – A sump shall be
located in each well vault. The sumps will each be equipped with a
sump pump controlled by an integrated float switch. Each well
vault will also be equipped with a high-level switch (LSH101/102/103). If water level in the vault rises causing the high-level
switch to be triggered, an alarm will be signaled to the well control
panel which will de-energize all electrical equipment and systems in
the well vault and signal the PLC. PLC shall remotely communicate
condition to Operator.
c. Transfer Pump – A discharge pump (P-401) shall be plumbed
between the temporary holding tank and the air stripper
groundwater intake piping. The transfer pump shall be operated
manually by a hand-off-auto switch located on CP-501.
d. Temporary Holding Tank – A temporary holding tank shall be
located outside the treatment building and plumbed to the air
stripper outfall piping system. The temporary holding tank shall be
equipped with a high-level switch (LSH-402). If liquid level in the
tank rises causing the high-level switch to be triggered, CP-501 will
be signaled to shut down the discharge pump P-301, a system
alarm will be signaled on a red alarm light at CP-501, and the PLC
will be signaled to communicate the condition remotely to the
Operator.
e. Potable Water System
i. A temporary potable water supply system with tank, pump, and
pressure tank shall be located in the treatment building. The
system shall be manually controlled.
ii. An emergency shower and eyewash station shall be provided in
the treatment building. The station shall be plumbed to the
potable water supply system.
System Operation Description
Section 17700
Statement of Work
F.
V - 134
PMG Phase 1 Interim Action
Summary of Controls and Critical Alarms – The following table
summarizes system alarms and resulting actions:
Control/Critical Alarm
Associated Equipment
Extraction well
groundwater elevation
LE/LIT-101, -102, -103
Alter pump motor speed through VFD to
maintain level, temporary pump shutoff as
necessary.
Extraction well pump
high/low pressure
PI/PIT-101, -102, -103
Shutdown pump if high/low pressure condition
persists; signal Operator.
Extraction system flow
monitoring and comparison
(for leak detection)
FI/FIT-101, -102, -103;
and FI/FIT-201
System shutdown if flow comparison yields
loss of flow between wells and air stripper;
signal Operator.
Submersible pump shutdown
OL-101, -102, -103
Air stripper blower flow rate
FI/FIT-201 and FI/FIT-301
Air stripper groundwater
influent flow rate
FI/FIT-201
Alarm and signal operator if maximum flow
exceeded. Extraction system shutdown if
condition persists; signal Operator.
Air stripper clearwell level
LE/LIT-301
Alter discharge pump motor speed through
VFD to maintain level, temporary pump shutoff,
as necessary.
Air stripper clearwell
high level
LSH-301
System shutdown if clearwell high level
persists; signal Operator.
Air stripper clearwell low level
LSL-301
System shutdown if clearwell low level
persists; signal Operator.
Air stripper high/low vacuum
PI/PIT-301
Alarm and signal operator if minimum or
maximum vacuum exceeded. System
shutdown if condition persists; signal Operator.
Moisture separator liquid level
LI/LIT-301
Condensate pump signaled to switch on and
off by high and low-level switches,
respectively. System shutdown if high-high
level condition persists; signal Operator.
Duct heater air temperature
TT-301/TC-301
Alter heat input from duct heater to maintain air
temperature; temporary heater shutoff as
necessary.
Building sump liquid level
LE-501
Alarm and signal operator if high level
exceeded. System shutdown if high-high level
exceeded; signal Operator.
Temporary holding
tank high level
LSH-402
System Operation Description
Alarm Result/Action
Stack light on control panel illuminate.
Alter blower motor speed proportional to
influent water flow rate to maintain minimum air
to water ratio
System shutdown if temporary holding high
level exceeded; signal Operator.
Section 17700
Statement of Work
V - 135
PMG Phase 1 Interim Action
PART 2 PRODUCTS
2.1
GENERAL
A.
Provide per Drawings and Section 17000.
PART 3 EXECUTION
3.1
GENERAL
A.
Coordinate the descriptions in this section with Section 17000 and
configure computer and telemetry hardware and software to accomplish
the fully integrated and functional supervisory control and data acquisition
system specified.
END SECTION
END OF STATEMENT OF WORK
System Operation Description
Section 17700
Statement of Work
PMG Phase 1 Interim Action
ATTACHMENT 1
PROJECT PLANS
1. Agreed Order No. DE96HS-N274 with Amendment Nos. 1 through 5 *
2. Construction Drawings
3. Utility Company Drawings and Designs**
* To be provided under separate cover to successful bidder
** To be provided as a bid addendum
Download