VAN DEN HEEVER v MINISTER OF MINERALS AND ENERGY & OTHERS (unreported, Case No. 2090/2010, Northern Cape High Court, 19 December 2011) Importance Parties Facts The Van den Heever case does not deal with environmental issues directly. However, the question before the court – had Transhex Mynbou Beperk abandoned their rights to mine diamonds on certain properties – could have implications for environmental liability. In this case it was in the interests of Transhex for the court to find that they had not in fact abandoned their rights, as this opened the way for another actor to obtain mining permits. The court found that the rights had not been abandoned because the approval of the Director: Mineral Development had not been obtained. The court situated abandonment within a contractual model, because the initial cause of Transhex Mynbou’s rights was a mineral lease to the properties (even though this was essentially abolished by the Minerals Act). I think this aspect of the judgment is questionable, and that the prima facie intention of the Managing Director in a letter of 2001, excluding the contentious properties from the mining lease, is more persuasive. The case nevertheless raises the question: How and when, legally, has abandonment occurred? And what does this mean for the environmental liabilities of the former mining rights holder? Section 43(1) of the MPRDA, which deals with closure obligations and continuing environmental liability, does not specifically mention “abandonment”. In terms of s 43(3)(a), however, the abandonment of a mining right triggers the need to apply for a closure certificate. Van den Heever is therefore authority for the proposition that such abandonment cannot be effected unilaterally but must be approved by the State, at least where a prior mineral lease with the State has been in place. First Applicant: Gert van den Heever First Respondent: Minister of Minerals and Energy Second Respondent: Director-General, Department of Minerals and Energy Third Respondent: Transhex Mynbou Beperk Fourth Respondent: Transhex Operations (Pty) Ltd Fifth Respondent: Richtersveld Municipality This case relates to a dispute over a permit/right to mine diamonds on two contiguous portions of land on the farm Richtersveld No. 11, Namaqualand, Northern Cape. Van den Heever contended that the third respondent, Transhex Mynbou, had abandoned its rights to mine diamonds on the properties in January 2001. This should have cleared the way for the Minister and DMR to accept Van den Heever’s applications for mining permits to the same properties. Under the Precious Stones Act 73 of 1964, the right to mine and dispose of precious stones was vested in the State. The State was entitled to lease its right to mine and dispose of precious stones, and such a lease in respect of the farm Richtersveld existed between the State and Transhex Mynbou. In terms of the mining lease, the third respondent had the sole right to mine precious stones and could only exercise mining activities on the leased portions to the satisfaction of the (then) Minister of Minerals, Energy and Public Enterprise. Relief Sought Amendments to the mining lease were permissible by consent of the parties. The coming into effect of the Minerals Act 50 of 1991 changed this situation, as it vested the right to mine in the holder of any right to minerals (including precious stones), and not the State. In order to mine, however, the holder of mineral rights had to obtain the necessary authorisation from the State. Section 47(1)(a)(iii) of the Minerals Act ensured the retention of the mining rights that Transhex Mynbou had held under s 21 of the Precious Stones Act. Section 47(1)(f) further provided that the holder of a mining right could abandon the right wholly or in part at any time, by written notice to the Director: Mineral Development. The mineral right is deemed to have lapsed from the date of the notification. In the case of mining permits and rights granted under the Minerals Act, s 11 similarly provided for abandonment of the authorization upon notification to the Director: Mineral Development. In 2001 the Managing Director of Transhex Mynbou wrote to the Director: Mineral Development regarding a “verkleining” (reduction) of the Richtersveld mining area controlled by Transhex Mynbou. This letter noted that Transhex had already for some time been engaged in negotiations with the Richtersveld Municipality regarding various pieces of land which were to be made available for irrigation alongside the Orange River. Agreement had been reached on “handing over” (“oorhandig sal word”) 363,14 hectares of land that formed part of the Richtersveld mining area. The MD accordingly requested the Director: Mineral Development to remove the identified pieces of land from the existing mining area and to register the changes in the Mining Titles Office (“U word dus versoek om die 13 stukke grond, waarvan die omvang in detail deur middle van koördinate op meegande plan gedefineer word, uit die bestaande mynhuurgebied uit to sluit, en die wysiging so by die Mynbriewekantoor in Pretoria to laat registreer”). It appears that at the same time Transhex Mynbou Beperk ceded/assigned/transferred its right to mine minerals on the said properties to Transhex Operations (Pty) Limited, and that the Director: Mineral Development allowed this transfer to be registered in the Mining Titles Office [note: there appears to be an inaccuracy in the judgment at para 1.2]. In April 2008 Van den Heever applied to the Regional Manager for the Northern Cape region for two permits to mine diamonds on pieces of land apparently relinquished through the afore-mentioned abandonment. His applications were rejected on the basis that mining authorizations to the land had already been issued to Transhex Mynbou Beperk and Transhex Operations (Pty) Ltd. The applicant lodged appeals against the decision to dismiss the applications in November 2008, but both were dismissed in March 2010. In 2009 Transhex Operations’ old order mining right was converted into a right under the MPRDA. An order: Declaring that Transhex Mynbou Beperk abandoned its right to mine for minerals on the pieces of contested land; that the cession between Transhex Mynbou Beperk and Transhex Operations (Pty) Ltd was of no force and effect; reviewing and setting aside the decision to Legal Issues Judgment Outcome convert Transhex Operations’ old order rights; reviewing and setting aside the Director-General’s rejection of the applicant’s appeals and referring them back to the Regional Manager for consideration. & Issue 1: Had Transhex Mynbou abandoned its right to mine diamonds on the two pieces of land in question? Judgment: The court agreed that this was the central issue in the case (para 22). Having read the letter that the MD addressed to the Director: Mineral Development, the judge noted that he failed to observe the specific Afrikaans words for “abandon” in the letter (“afstanddoen”). What emerged from the letter itself was rather a request for amendment of the rights (para 23). Counsel for Transhex Mynbou and Transhex Operations also argued that the request for amendment of the rights could not be effected unilaterally, because the notarial mining lease that bound Transhex to the State was a bilateral agreement. The court agreed with this interpretation (para 24), and based on a purposive interpretation of s 47 of the Minerals Act, found that the terms and conditions Transhex Mynbou Beperk enjoyed after the Minerals Act remained the same as in the lease agreement (i.e. the “bilateral” relationship between the parties was preserved). The court also found that the letter could reasonably be interpreted as a request to amend the terms of the mining lease (para 32). He could therefore not agree with Van den Heever’s contention that the letter together with the sketch was sufficient to constitute abandonment. For that to occur, there would have had to be some approval from the Director: Mineral Development on whether the sketch complied with the statutory requirements and was therefore acceptable (paras 33, 37, 39). Based on the judge’s subsequent comments regarding abandonment (see paras 34–36) he appears to have situated abandonment within a contractual scheme and as an act that could not be effected unilaterally. The application was dismissed.