BID PROTESTS: THE COSTS ARE REAL, BUT THE BENEFITS OUTWEIGH THEM Daniel I. Gordon* [Note for student editors: Will you insert a table of contents and format the headings of the article consistent with PCLJ’s procedures?] * 1 TABLE OF CONTENTS I. INTRODUCTION.............................................. 2 II. ADMINISTRATIVE AND JUDICIAL VENUES FOR FILING PROTESTS IN THE U.S. FEDERAL SYSTEM................................... 3 III. SPREAD OF THE PROTEST PROCESS OUTSIDE THE U.S............. 6 IV. CORRECTING MISPERCEPTIONS ABOUT PROTEST STATIISTICS....... 8 A. Protests are rare events............................. 9 B. It is rare for a protester to win a protest, and even rarer for a winning protester to go on to obtain the contract at issue in the protest.................... 16 V. COSTS OF THE PROTEST PROCESS............................. 20 VI. Benefits of the Protest Process.......................... 32 VII. Conclusion: The Costs are Overstated, and the Benefits Outweigh Them............................................ 35 I. INTRODUCTION This article discusses the benefits and costs of bid protests—legal challenges by a bidder to the way the Government has conducted a procurement.1 In the U.S. federal procurement system, bid protests have existed since the 1920s,2 and criticism arguing that they are more trouble than they are worth has been around for nearly that long.3 The article explains why, in the author’s view, the benefits of the bid protest system See James F. Nagle & Adam K. Lasky, A Practitioner’s Road Map to GAO Bid Protests, 30 CONSTR. LAW, no. 5, Winter 2010, at 5. 2 See id. 1 3 2 substantially outweigh the burdens that it imposes on the procurement system. II. ADMINISTRATIVE AND JUDICIAL VENUES FOR FILING PROTESTS IN THE U.S. FEDERAL SYSTEM It was in the U.S. that the first litigation leading to what came to be recognized as a bid protest decision took place.4 In 1924, a company filed a complaint with the then-new General Accounting Office (“GAO”),5 alleging that the officials of the Panama Canal had written specifications for a truck that were “wired” to a particular brand name and that unfairly precluded the complaining firm from fair consideration for the contract.6 GAO, after some internal hesitation, decided to consider the complaint as part of the office’s responsibility to ensure that funds appropriated by Congress were lawfully spent—what is referred to as GAO’s account settlement function.7 GAO ultimately agreed with the protesting firm.8 See Comptroller General McCarl to the Governor, the Panama Canal, 5 Comp. Gen. 712, A-11259 (Mar. 9, 1926). 5 Effective July 7, 2004, the GAO's legal name became the Government Accountability Office. See GAO Human Capital Reform Act of 2004, Pub. L. 108-271, § 8(a), 118 Stat. 811 (2004). 6 5 Comp. Gen. 712, 713. 7 In the Beginning: The Earliest Bid Protests Filed with the US General Accounting Office, 13 PUBLIC PROCUREMENT L. REV. 5 (2004); Daniel I. Gordon, Annals of Accountability: The First Published Bid Protest Decision, 39 PROCUREMENT LAWYER, no. 2, Winter 2004, at 11.. 8 5 Comp. Gen. 712, 713. 4 3 In the course of the ensuing decades, handling bid protests became a routine function of GAO’s Office of General Counsel.9 Some protests involved pre-award challenges by potential offerors to solicitation terms;10 the majority were post-award challenges by firms that had competed for a contract, contesting the award to another offeror.11 For many years, courts did not consider bid protests, so that GAO (and the contracting agencies themselves) represented the only place to file a protest.12 Then, for three decades after the decision of the U.S. Court of Appeals for the District of Columbia Circuit in Scanwell,13 U.S. district courts had bid protest jurisdiction, until that jurisdiction “sunset” in 2001.14 From the enactment of CICA in 198415 until its jurisdiction was ended through section 5101 of the Clinger Cohen Act of 1996,16 Pub. L. No. 104-106, there was another administrative forum with jurisdiction over some protests, those related to information See William E. Kovacic, Procurement Reform and the Choice o Forum in Bid Protest Disputes, 9 ADMIN. L. REV. AM. U. 461, 470 (1995) 10 See, e.g., New York Tel. Co. v. Sec’y of Army, 67 F. Supp. 18, 19 (D.D.C. 1986) 9 11 12 Scanwell Labs., Inc. v. United States, 424 F.2d 859 (D.C. Cir. 1970). 14 The Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320, § 12, 110 Stat. at 3874, provided for the District Court jurisdiction to sunset on January 1, 2001. 13 15 16 4 technology, and that was the General Services Administration’s Board of Contract Appeals, the GSBCA.17 In addition, a statutory change in 1996 meant that the Court of Federal Claims,18 which had only pre-award protest jurisdiction for many years, was given post-award jurisdiction as well.19 The result is that, for more than a decade now, the only places outside the contracting agency where disappointed bidders have been able to protest are GAO and the Court of Federal Claims.20 From time to time there are differences between GAO and the Court, with respect to both process and outcomes.21 The author views occasional differences between two fora as inevitable, and that is particularly the case here, where one forum is administrative and the other is judicial. In any event, having two fora hearing bid protests may be healthy for the procurement system. While the discussion below regarding the costs and benefits of protests to the procurement system is 17 The Court of Federal Claims was previously called the United States Claims Court prior to Congress’s enactment of the Federal Courts Administration Act of 1992, Pub. L. No. 102-572, 106 Stat. 4506, 4516. Also, Prior to Congress’s enactment of the Federal Courts Improvement Act of 1982, Pub. L. No. 97-164, 96 Stat. 25, 42, the court generally existed as the United States Court of Claims, Trial Division. 19 Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320, section 12(d). [Note to student editors: Should we refer back to the citation in the earlier footnote?] 18 20 21 5 focused on GAO, the analysis should apply, at least in broad terms, to the Court of Federal Claims as well. III. SPREAD OF THE PROTEST PROCESS OUTSIDE THE U.S. Before turning to that analysis, it is worth looking outside the U.S., because the protest process has been receiving substantial attention around the world.22 More than ever in the past, a protest system has come to be seen as a required part of a good public procurement system.23 For example, in every free trade agreement that the U.S. has negotiated over the past 20 years, there has been a provision requiring our trading partners to have a protest mechanism.24 In Canada, for instance, the Canadian International Trade Tribunal was created to satisfy the requirement of NAFTA, the North America Free Trade Agreement, that each partner have a protest forum.25 Similarly, the World 22 It should be noted that the term “protest” (or “bid protest”) is rarely used outside the United States; instead, what we would call protests are called ”challenges,” “domestic review procedures,” “remedies,” or simply ”complaints.” 23 24 http://www.international.gc.ca/trade-agreements-accordscommerciaux/agr-acc/nafta-alena/bereczky.aspx?view=d: “Article 1017 of the NAFTA calls for the promotion of “fair, open and impartial procurement procedures,” whereby “each party shall adopt and maintain bid challenge procedures for procurement covered” in accordance with a variety of principles, including that of “establish[ing] or designat[ing] a reviewing authority with no substantial interest in the outcome of procurements to receive bid challenges and make findings and recommendations concerning them.” As a result, the Canadian government established the Canadian International Trade Tribunal (CITT). NEEDS CITE. The tribunal’s mandate is to receive complaints and 25 6 Trade Organization’s Agreement on Government Procurement (GPA) includes a provision requiring WTO members that accede to it to have a protest forum (called a domestic review procedure).26 In addition, there is a protest provision in Chapter VIII of the model procurement law of the United Nations Commission on International Trade Law (UNCITRAL).27 Perhaps most interesting is the attention that protests have received over the past 20 years in the European Union (“E.U.”). Not mentioned in the EU’s Public Procurement Directives,28 protests were first addressed by the European Commission in what is known as the Remedies Directive.29 Initially issued in 1989,30 the Remedies Directive was revised in 2007.31 The Remedies Directive has had an enormous impact, to conduct the necessary investigation to see whether the procurement project challenged falls outside the respectable limits of the NAFTA procurement procedures and to provide for remedies where procedural breaches occur.” NEEDS CITE. 26 See Article XX of the existing GPA and Article XVIII of the 2011 revised version, which is to come into effect shortly. http://www.ustr.gov/sites/default/files/GPA%20113%20Decision%20o n%20the%20outcomes%20of%20the%20negotiations%20under%20Article%2 0XXIV%207.pdf 27 See Challenge Proceedings, Chapter VIII, UNCITRAL Model Law on Public Procurement (2011). http://www.uncitral.org/pdf/english/texts/procurem/mlprocurement-2011/ML_Public_Procurement_A_66_17_E.pdf. 28 See Preamble, Council Directive 89/665/EEC (1989). 29 See Preamble, Council Directive 89/665/EEC (1989). 30 Id. 31 See Directive 2007/66/EC of the European Parliament and of the Council (2007). 7 requiring all member states to have a protest forum,32 and a good number of EU member states have recently seen a significant increase in the number of protests being filed (whether that is a positive or a negative development is a separate question).33 The Court of Justice of the European Union has issued decisions that have reshaped the protest process in the E.U., in particular, through the Alcatel decision34 that led to the requirement (codified in Article 2a of the 2007 revision to the Remedies Directive) that there be a “standstill” period (typically 10 days) between the announcement of the apparent winner of the competition for a contract and the signing of the contract, in order to allow potential protesters to file before the contract is actually awarded.35 IV. CORRECTING MISPERCEPTIONS ABOUT PROTEST STATIISTICS In the circle of people who are interested in federal procurement, there are a number of misperceptions about protest statistics that should be addressed, since they can taint judgments about the benefits and costs of protests. In particular, even people quite familiar with the federal See id. at Article 1, Scope and Availability of Review Procedures. 33 JEREMY GLOVER, CHALLENGING THE TENDER PROCESS- WHAT IS THE EFFECT OF RECENT CASE LAW? 10 (2009). 34 Case C-81/98, Alcatel Austria AG and Others, Siemens AG Österreich and Sag-Schrack Anlagentechnik AG v Bundesministerium für Wissenschaft und Verkehr, I-7708 (2009). 35 See Article 2(a), Standstill period, Directive 2007/66/EC of the European Parliament and of the Council, (2007). 32 8 acquisition system believe that protests are more common than they really are, and they often believe, inaccurately, that protesters frequently use the protest process to win contracts. A. Protests are rare events The frequency or rarity of protests needs to be judged in context in order for the judgment to be sensible. If a contracting officer is asked whether, in the procurements she or he has worked on over the prior 3 years, protests were frequent, an affirmative answer is often provided; but if one asks how many procurements the contracting officer has worked on during that period, that number often dwarfs the number of protests. Put another way, while the numerator (the absolute number of protests) is important, the denominator (the total number of procurements) is critical to a determination of whether protests can reasonably be said to be frequent. In assessing the frequency of bid protests in the federal procurement system, there are difficulties with both the denominator and the numerator – respectively, the number of federal procurements that occur each year, and the number of protests filed each year. Regarding the denominator, perhaps surprisingly, there are not good statistics on the number of federal procurements that occur each year. Any such count would need to include, not only the number of contracts awarded, but also any task and delivery 9 orders awarded that can be protested. The latter includes all orders placed under the GSA Federal Supply Schedule and orders issued under multiple-awarded indefinite-delivery, indefinitequantity contracts, where the orders have a value above $10 million.36 A recent RAND Corporation study of Air Force procurements that were protested to GAO indicated that approximately 20,000 contracts with a value above $25,000 were awarded by the Air Force in 2008, representing approximately $63 billion.37 Since overall procurement spending in 2008 was over $500 billion (eight times the amount spent by the Air Force alone),38 that would suggest that the overall number of contracts awarded was approximately 160,000. The author suspects that the number is low and that a better estimate, including FSS orders and ID/IQ orders above $10 million, would probably substantially exceed 250,000. For the purpose of the analysis in this paper, it will be assumed that the total number of federal contracts and protestable orders awarded in a year is 200,000. The Fiscal Year (FY) 2008 National Defense Authorization Act (NDAA), NEEDS CITE, amended FASA, NEEDS CITE, to grant GAO jurisdiction to hear protests concerning task or delivery orders valued at more than $10 million. See Pub. L. No. 110-181, 122 Stat. 3, 237 (2008). [Note to Student editors: Please update the citation to also include references to the FY 2011 and FY2012 NDAAs, which extended the jurisdiction past the sunset period] 36 37 http://www.rand.org/content/dam/rand/pubs/technical_reports/2012 /RAND_TR883.pdf at 12. 38 10 With respect to the numerator – the number of protests filed—there has been confusion, for reasons that can be clarified here. One challenge has been a methodological anomaly that is worth explaining. Since the days when protest filings were tracked on 3” x 5” cards, GAO has used a methodology that can cause people to believe that protest numbers are higher than they actually are. When a company files a protest challenging the terms of a solicitation, GAO assigns it a docket number, referred to as a “B number,” since it begins with a “B” – for example, B-123456.39 If the protester later learns new information that constitutes a new ground of protest and files a supplemental protest of that same solicitation’s terms, GAO will docket that as B-123456.2.40 If another potential offeror also protests the solicitation’s terms, GAO will docket its protest as B-123456.3, and if that firm supplements its protest, that will be docketed as B-123456.4.41 However those pre-award protests are resolved, once the agency awards a contract, a losing competitor may file a protest, which GAO will docket as B-123456.5 and, if there is a supplemental protest once the protester sees the agency report, that will be docketed as B123456.6.42 And finally, if another losing competitor files a 39 40 41 42 11 protest and then supplements it, they will be docketed as B123456.7 and B-123456.8, respectively.43 Overall, GAO’s statistics will indicate eight protests, even though only one procurement has been protested. While eight protests of one procurement would be unusual, having two protests is routine, and three would not be out of the ordinary. What that means is that, when GAO reports the number of protests filed in a year, that number substantially overstates the number of procurements protested. For Fiscal Year (FY) 2008, for example, while GAO reported 1,652 cases filed,44 elsewhere GAO reported that 1,027 procurements were protested in that period.45 In other words, GAO indicated that, on average, there are approximately 1.6 docket numbers assigned (“cases filed”) for each protested procurement. Assuming that this ratio is stable over time, it would mean that the 2,353 “cases 43 GAO’s reported number of cases filed apparently also includes requests for reconsideration of a prior GAO decision as well as requests for reimbursement of costs, since either such request would be assigned the same B number as the related protest (in the example used in the text here, a request for reconsideration of the decision on the protests of the award would be docketed as B-123456.9 and a subsequent request by the two protesters that their protest costs be reimbursed would be docketed as B123456.10 and B-123456.11. 45 Cf. B-401197 (supra note XX) at 7, fig. 1, and GAO’s GAO Bid Protest Annual Report to the Congress for Fiscal Year 2008, B158766, Dec. 22, 2008. 44 12 filed” in FY 201146 represented approximately 1,470 protested procurements. While the number of federal procurements was probably not the same in FY 2008 and FY 2011, if we assume, for the sake of simplicity and since this is only a rough estimate, that there were 200,000 procurements in each of those two years, that would suggest that 0.51 percent of procurements were protested in FY 2008 and 0.7 percent were protested in FY 2011. In other words, between 99.3 and 99.5 percent of procurements were not protested. This calculation has been confirmed through the recent RAND study mentioned above.47 In that study, researchers at the RAND Corporation found that, in the Air Force, “[t]he number of [GAO] protests as a percentage of total contract awards fell fairly steadily from about 1.7 percent in 1995 to 0.5 percent in 2008.”48 That is to say, as of 2008, 99.5 percent of Air Force procurements went forward without being protested to GAO. Even if GAO protests of some other agencies’ procurements were twice as common as for the Air Force (and there is no reason to assume U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-12-199SP, BID PROTEST STATISTICS FOR FISCAL YEARS 2007-2011 4 (2011). 46 47 F. Camm, M.E. Chenoweth, T. Light, M.A. Lorell, J.C. Graser, P. Lewis and R. Rudavsky, Government Accountability Office Bid Protests in Air Force Source Selections, in American Bar Association Section of Public Contract Law, “The Changing Budgetary Environment: Legal and Fiscal Challenges in Federal Procurement,” from the ABA Annual Meetings in Chicago (August 2012), at 3. 48 13 that that is the case), it would still be true that 99 percent of their procurements went forward without being protested to GAO. While the RAND study refers to GAO protests, including the Court of Federal Claims would not alter the picture, since the Court receives fewer than one-tenth the number of protests each year that GAO receives.49 And while protesters can file protests within the Air Force and statistics on the number of those “agency-level protests” are not available, there is no reason to believe that they would increase the total percentage of protested Air Force procurements much above 0.5 percent. It is, of course, true that very high-dollar procurements are much more likely to be protested—the higher the dollar value, the greater the likelihood of a protest. For a company that loses the competition for a $100 million contract, with all the bid and proposal costs that competing entails, the additional cost of filing a protest may seem minimal, so that filing a protest can be very tempting. That does not change the overall picture, however, especially since very high-dollar procurements are themselves few in number: protests are rare. What about the mantra we often hear about increases in protest numbers? It is true that GAO has reported a substantial Thus, the Court received 79 protests in FY 2008. http://www.crowell.com/files/2011-Bid-Protests-Trends-andDevelopments.pdf 49 14 increase in the number of cases filed over the past few years,50 but even if the numbers doubled, from 0.5 percent of procurements to a full percent, it would still mean that something like 99 percent of procurements are not protested. In terms of absolute numbers, GAO has reported that the number of protests rose from 1,327 in FY 2006 to 2,353 in FY 2011, an increase of more than 70 percent.51 Adjusted to eliminate the overcounting explained above,52 that would represent an increase from approximately 830 to approximately 1,470 protested procurements (representing the same percentage increase). During that same period, however, federal procurement spending increased from $432 billion in FY 2006 to $537 billion in FY 2011.53 Put another way, in FY 2006, there were approximately 1.92 protests for each billion in federal procurement spending, while in FY 2011, there were 2.74 protests per billion. Those figures are similar to the ones that GAO provided in a congressional report in 2009, when it stated that the number of protested procurements per billion dollars in Department of Defense contract spending ranged from 1.4 to 1.9 during the 50 U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-12-199SP, BID PROTEST STATISTICS FOR FISCAL YEARS 2007-2011 4 (2011). 51 supra note 50 at 4;supra note 49, at 4. 52 53 Source: usaspending.gov. 15 period FY 2004 to FY 2008.54 While the FY 2011 figure reflects an increase, the number of protests for each billion in federal procurement spending is still extremely low: fewer than three protests for each billion dollars that the government spends on contracts. B. It is rare for a protester to win a protest, and even rarer for a winning protester to go on to obtain the contract at issue in the protest. Here again, GAO’s methodology risks misleading observers. GAO reports a “sustain” rate that has ranged (that is, the rate at which GAO rules in favor of the protester and sustains the protest), over the past 5 years, from 16 to 27 percent.55 sounds like protesters do fairly well. That For better or for worse, the full picture is not so favorable to protesters. First, the sustain rate has been dropping nearly consistently over the past 5 years, falling from 27 percent in FY 2007 to 16 percent in FY 2011.56 Second, the sustain rate is calculated only among the cases for which GAO issues a merits decision, as GAO explains in its annual reports.57 That means that, in FY 2010, for example, GAO did not sustain 19 percent of 2,299 cases – it sustained 19 54 U.S. GOV’T ACCOUNTABILITY OFFICE, REPORT TO CONGRESS ON BID PROTESTS INVOLVING DEFENSE PROCUREMENTS 10 (2009). 55 U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-12-520SP, GAO BID PROTEST OVERVIEW 2 (2011). 56 U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-12-199SP, BID PROTEST ANNUAL REPORT TO THE CONGRESS FOR FISCAL YEAR 2011, at 4 (2011). 57 Id. 16 percent of 441 merit decisions.58 Third, that percentage is distorted by the methodology of counting multiple B numbers separately, because protests that are sustained typically have more B numbers than protests that are denied.59 Thus, for FY 2010, GAO reported 441 merit decisions, of which 82 were reported as sustained protests.60 A count of the actual decisions (counting each decision as one, even if it resolves two or more B numbers) shows that there were actually 277 (not 441) decisions, of which 45 (not 82) were sustained.61 That represents a 16 percent sustain rate (not 19 percent). Thus far, this analysis means that, among the hundreds of thousands of federal procurements that occurred in FY 2010, there were only 45 where GAO sustained protests. The next stage, though, offers even worse news for protesters, and it is surprising how little is reported about it. What happened in those 45 procurements, after GAO sustained the protests? Did the protester that was successful in the GAO litigation succeed in obtaining the contract? The answer: Rarely. The FY 2010 numbers have been selected here for further study, because enough time should have passed for final action in the Id. This presumably derives from protesters’ filing more supplemental protests in sustained protests, for whatever reason. 60 GAO-12-199SP at 4. 58 59 61 17 procurement to be available. That said, discovering the final action can be challenging, because information on what ultimately happened in each one of the sustained protests is not readily available, but enough is known to give a fairly clear picture of protesters often winning at GAO but nonetheless not receiving the contested contracts.62 In four of the 45 cases, GAO did not recommend any corrective action in the protested procurement, either because the contract had already been performed or for other reasons.63 In an additional three cases, GAO did recommend corrective action in the procurement, but the agency explicitly declined to follow GAO’s recommendation.64 In another case, the agency cancelled the solicitation entirely (for reasons, and with impact, unclear).65 In 16 additional cases (more than one third of all the protests sustained in FY 2010) , GAO recommended corrective action, the agency followed GAO’s recommendation, but the agency then confirmed award to the GAO does not track information on which company ultimately receives a contract after GAO has sustained a protest. The author, working with student research assistants at the George Washington University Law School, has been endeavoring to obtain information for the post-protest outcome of each of the 45 sustained FY 2010 protests, and the results to date are set out in the text here. The effort to track down every case continues through Freedom of Information Act requests to the respective agencies. 63 Note, though, that two of those four cases involved protests of public-private competitions, where the federal employees’ representative won the protest and may have been satisfied that no further competition was to be held. 62 64 65 18 same company as before (or awarded to a third company, neither the earlier awardee or the protester).66 In only four cases identified to date did the protester ultimately obtain the contested contract.67 While the ultimate outcome has yet been determined in the remaining 17 procurements,68 this much is clear: winning a protest is far from ensuring that a protester will win the contract it is seeking. Experienced practitioners may point out that GAO reports a high “effectiveness rate” that would suggest that the picture is far better than this for protesters. That “effectiveness rate,” which was reported as 42 percent for FY 2010,69 combines the sustained protests described above as well as cases where agencies took voluntary “corrective action,” without action by GAO, so that GAO closed its files without a decision.70 There is no publicly available information on that large universe of protests where GAO was told that the protester “obtain[ed] some form of relief,” as GAO writes in a footnote to its annual report.71 In particular, there is no way to know whether the protesters ultimately obtained the contracts at issue, and discovering the outcome in each of the affected procurement 66 67 68 GAO-12-199SP at 4. U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-13-162SP, BID PROTEST ANNUAL REPORT TO THE CONGRESS FOR FISCAL YEAR 2012, at 5 (2012). 71 Id. 69 70 19 would challenge even the most diligent researchers, since GAO does not publicly disclose any information about the cases that it closes due to agencies’ voluntary corrective action.72 There is, however, no obvious reason that an agency is more likely to award a contract to a protester whose case ends without a GAO decision than the agency would after GAO rules in the protester’s favor. V. COSTS OF THE PROTEST PROCESS A key component of the harm of the protest process is the delay that protests cause. Even when a protest is denied, it holds up the acquisition.73 In particular, when a protester files in time to trigger the automatic stay under CICA,74 the agency will be required to hold off on awarding the contract (for pre-award protests) or to direct the contractor to stop work (for post-award protests).75 That automatic stay can last up to 100 days,76 which is longer than the automatic suspension of a procurement in any other country’s protest system, at least among the many systems that the author has reviewed.77 Even if GAO dismisses a protest, whether because it was untimely filed U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-13-2SP, PERFORMANCE ACCOUNTABILITY REPORT FISCAL YEAR 2012, at 46 (2012). 73 31 U.S.C. § 3553(c)(1) (2006). 72 AND 74 75 31 U.S.C. § 3553(c), (d). 76 Need to add cite to at least one foreign system and the length of its stay. 77 20 or because the protester does not qualify as an ‘interested party’ with standing to protest,78 can take several weeks, and even the most promptly dismissed protests may trigger a CICA stay that is in place for at least a few days.79 In short, the CICA stay does disrupt procurements. The discussion above makes clear, however, that the CICA stay applies to only a tiny percentage of federal procurements, so that any harm caused by the CICA stay is also more limited than might initially appear. In FY 2011, as noted early, approximately 1,470 procurements were protested to GAO.80 While specific information is not publicly available, not all of those 1,470 protested procurements would have been stayed. Only protests filed within specified deadlines trigger a CICA stay,81 and at least some of those 1,470 protests were either untimely filed (indeed, timeliness is one of GAO’s most common bases for dismissing protests82) and even some of the timely-filed protests may have been filed too late to trigger a CICA stay. For example, a protest filed 6 to 10 days after a debriefing will usually be timely for GAO’s filing purposes, but it will not 78 79 80 U.S. GOV’T ACCOUNTABILITY OFFICE, GAO-12-199SP, BID PROTEST STATISTICS FISCAL YEARS 2007-2011 4 (2011). FOR 81 Dismissals of Bid Protests at the General Accounting Office, THE PROCUREMENT LAWYER, Vol. 37, No. 2 (Winter 2002) at 16. 82 21 trigger a CICA stay, because a protest must be filed within 5 days of a debriefing to trigger a stay.83 Moreover, the fact that a protest has triggered the CICA stay does not mean that the procurement will be on hold for 100 days. Most protests are resolved well before the 100th day, the maximum length of CICA’s automatic stay.84 In 2009, GAO reported to Congress that it consistently closed more than half of all protests within 30 days.85 While that report related to protests of DoD procurements,86 there is no reason to believe that protests of civilian agency procurements (which are fewer in number than DoD protests)87 take longer for GAO to close. The stay may end because the protester has withdrawn the protest, or because GAO has dismissed the case.88 When the agency takes corrective action, that also ends the stay, but, of course, the corrective action itself will generally delay progress in the procurement.89 Even for the minority of protests that go to published decisions – which means that they form the group of protests for which the stay remains in place the longest time – 83 84 85 86 87 31 U.S.C. § 3553(d)(4)(B). Supra note 54, at 5. Id. at 10. Id. at 5. Needs cite. 88 89 22 GAO reports that, on average, the decision is issued before the 80th day.90 Not only is the delay caused by the CICA stay shorter than it may appear – when a delay, even a relatively short one, could cause harm, CICA provides a mechanism for agencies to move forward with the procurement while the protest is still pending.91 This “override” mechanism is available to agencies, and is used, although information on the frequency of overrides is not readily available.92 The truly long delays – disrupting the procurement for many months – occur when GAO issues a decision sustaining a protest and the agency then implements GAO’s recommendation, which typically calls for the agency to re-do at least part of the competition for the contract.93 however, is quite small: The universe of such cases, as explained above, there are only a few dozen sustained protests in a year (as noted above, there were 45 procurements in which GAO sustained protests in FY 2010),94 and, of those, some did not lead to delay in the 90 Couldn’t find this 91 For FY 2002, the last year that GAO included information on overrides in its annual report on protests, GAO reported that, with respect to the 1,101 protests filed that year, there were 71 instances of agencies’ using their override authority to move forward with the procurement, notwithstanding the protest. http://gao.gov/assets/100/93966.pdf 93 31 U.S.C. § 3554(b)(1)(B). 92 94 23 procurement after GAO issued its decision, either because the decision did not contain a recommendation for corrective action or because the agency declined to follow GAO’s recommendation.95 That leaves a relatively small number of procurements – almost certainly fewer than 40 out of the 200,000 estimate used here for each year’s procurements – in which there is substantial delay due to a successful protest.96 In the author’s view, there is adequate justification for a substantial delay in a procurement where GAO has found that the agency violated procurement law and that the violation harmed the protester. In any event, again in the author’s view, any delay that the agency’s unlawful action has caused cannot fairly be blamed on the protest system. Critics of the protest system may also view as a cost of the protest system GAO’s recommendation that protesters be reimbursed the costs of filing and pursuing their protests, including their attorney fees.97 That situation arises only when GAO finds that a protest is meritorious—meaning, again, that the contracting agency violated procurement law to the detriment of the protester—so that (1) at issue are only a small number of protests each year and (2) those cases are ones where the 95 96 31 U.S.C. § 3554(c)(1)(A)-(B); see also KATE MANUEL & MOSHE SCHWARTZ, CONG. RESEARCH SERV., REPORT NO. R40228, GAO BID PROTESTS: AN OVERVIEW OF TIME FRAMES AND PROCEDURES n.100 at 15 (June 30, 2011). 97 24 protest system has identified unlawful action by the government.98 In the author’s view, reimbursing protesters for their action as “private attorneys general” is justified.99 In any event, the reimbursable rates for attorney fees in those situations are now capped, except for small business protesters.100 That said, critics point to abuse of the protest system in particular contexts as causes for concern. Specifically, there are persistent complaints that abuse arises in the form of “frivolous” protests, and the author has often heard calls for imposing sanctions on firms that file frivolous protests.101 In the 2009 report to Congress mentioned earlier, GAO responded to questions from the House Armed Services Committee to address frivolous protests filed in connection with DoD procurements.102 Compare Takota Corp.-Costs, B-299600 et al., 2007 CPD ¶ 171, at 3 (Comp. Gen. Sept. 18, 2007)(finding no need to award attorney fees because Coast Guard complied with regulations by swiftly correcting solicitation) with Advanced Envtl. Solutions, Inc.-Costs, B296136 et al., 2005 CPD ¶ 121 at 2-3 (Comp. Gen. June 20, 2005)(finding attorney fees should be awarded because agency unduly delayed taking corrective action on meritorious protest). 99 Scanwell Lab., Inc. v. Shaffer, 424 F.2d 859, 864 (D.C. Cir. 1970). 100 31 U.S.C. § 3554 (c)(2). 101 Robert S. Metzger & Daniel A. Lyons, A Critical Reassessment of the GAO Bid-Protest Mechanism, 6 WIS. L. REV. 1225, 1240 (2007); see also Jonathan R. Canton, Note, Bid Protests and Procurement Reform: The Case for Leaving Well Enough Alone, 27 PUB. CON. L.J. 155, 172 (1997)(recounting proposed regulations aimed at preventing frivolous protests). 102 Supra note 54, at 14. 98 25 GAO pointed out that the fact that a protest was denied or even dismissed did not mean that it was frivolous; instead, GAO expressed the view that only a protest filed in bad faith should be viewed as frivolous.103 GAO reported that it did not categorize protests as frivolous and therefore had no data on the number of frivolous protests.104 It did point out that contracting agencies rarely assert that protests are frivolous.105 In a footnote, GAO reported that the last reported decision noting that an agency characterized a protest as frivolous had been in 1996 and that, in that case, the agency subsequently acknowledged that the evaluation scheme used in the protested procurement was flawed.106 In its 2009 report, GAO pointed to its practice of promptly dismissing protests as indicating that there was no problem with frivolous protests that needed to be solved.107 GAO also expressed concern that any effort to impose sanctions on frivolous protests (such as by imposing a fine or requiring the protester to reimburse the government for costs incurred in defending against the protest) would risk “the unintended consequence of harming the federal procurement system by discouraging participation in federal contracting and, in turn, 103 104 105 106 107 Id. at 13. Id. at 12. Id. Id. Id. at 2. 26 limiting competition.”108 GAO also pointed out that penalties could not properly be imposed on “frivolous” protesters without adding a new layer of litigation, in which GAO would need to determine whether the protester had filed its protest in bad faith.109 Besides the burden that would place on GAO, distracting it from its focus on resolving protests as quickly as possible, that new layer of litigation could impose additional costs on agencies and protesters, and the burden of those additional costs might fall disproportionately heavily on small businesses and protesters not represented by counsel, who may have protested in good faith, even if they acted with a misunderstanding of the facts or the law.110 Those who allege that some protesters abuse of the system sometimes point to one scenario in particular: situations where a service contractor has lost the competition for a follow-on Id. Id. at 13. 110 Id. ((U.S. GOV’T ACCOUNTABILITY OFFICE, B-401197, REPORT TO CONGRESS ON BID PROTESTS INVOLVING DEFENSE PROCUREMENTS 13 (2009).))It is worth noting that protesters have only limited information about what happened during a procurement at the time that the strict time limits require them to decide whether to file a protest. Many agencies disclose to firms that lost competitions for contract only the bare minimum required by law. See Federal Acquisition Regulation section 15.506. It is often only through the protest process that protesters (or at least their counsel) learn in detail why they lost the competition for a contract. While review of the full agency record may eventually demonstrate that some initial protests are without merit, in other cases, review of the entire file discloses that the protests are, indeed, meritorious. 108 109 27 contract and then files a protest in order to continue working during the period of the CICA stay.111 This concern may be legitimate, although the extent of the problem is not clear. The concern would be particularly great if (1) many protests were found to have been filed by service-contract incumbents who had lost the competitions for the follow-on contracts and (2) their protests were completely without merit, but (3) GAO was so slow in resolving the protests that the incumbent was able to continue to perform well after its contract had been due to expire. The author is not aware of data supporting those three statements. The appropriate response, in any event, would appear to be to press GAO to continue (or intensify) its efforts to resolve the protests promptly – not to create a new round of litigation about the imposition of sanctions, and certainly not to limit or abolish vendors’ right to have an independent body consider their claims of unlawful action by the contracting agency. The final category of alleged abuse of the protest system is composed of sequential protests – that is, situations where a protester loses a protest at GAO and then protests at the Court 11131 U.S.C. §3553(d)(3)(C); see also Keeton Corrections, Inc., v. United States, 59 Fed. Cl. 753, 754-55 (2007); Robert S. Metzger & Daniel A. Lyons, A Critical Reassessment of the GAO Bid-Protest Mechanism, 6 WIS. L. REV. 1225, 1239 (2007). 28 of Federal Claims.112 Presumably, the situation could be made to sound worse by imagining a case in which a firm protests first to the contracting agency, then to GAO, then to the Court of Federal Claims, and finally to the Federal Circuit.113 This scenario is, however, an instance of imagining the hypothetical, with no evidence of the nightmarish pattern ever actually occurring.114 Indeed, if it did occur, it is not clear that the procurement would be disrupted, since there might be no CICA stay at GAO,115 and the courts would certainly have discretion not to impose a preliminary injunction.116 While there are some protesters who start at GAO and then go to the Court of Federal Claims,117 the numbers are so small (certainly fewer than 50 in a year) and the evidence that the procurements have been held up so thin (again, there is no automatic right to a stay at the Court), that this cannot legitimately be seen as a significant cost of the bid protest system. In fact, the Court occasionally 11228 U.S.C. § 1491(b)(1)(granting the Court of Federal Claims subject matter jurisdiction over bid protest claims); 5 U.S.C. § 706(2)(A)(establishing the standard of review for hearing bid protest claims); see also Axiom Resource Management, Inc. v. United States, 564 F.3d 1374, 1381 (Fed. Cir. 2009); Michael J. Schaengold et al., Choice of Forum for Federal Government Contract Bid Protests, 18 FED. CIR. B. J. 243, 318 (2009). 113 114 115 116 117 29 reaches a different outcome than did GAO,118 which suggests, if nothing else, that the protest was not frivolous. Another concern about the cost of the protest system relates to what might be called its indirect impact. Fear of protests is often given as the explanation for contracting officers’ preference for certain courses of action over others.119 In particular, contracting officers are said to be acting to avoid bid protests when they decide that a contract should be awarded to the low-priced technically acceptable (LPTA) proposal, rather than to allow a tradeoff.120 The author has never seen data that would indicate how often contracting officers actually decide to name LPTA as the award criterion in a solicitation for this reason, nor how often source selection officials avoid making tradeoffs in the award decision, even when permitted by the terms of the solicitation, in order to avoid protests. If the phenomenon is common, it is unfortunate, since discretion to make tradeoffs is a positive option in the U.S. procurement system. Similarly, the author has heard for many years that some contracting officers prefer to make award based on initial proposals, rather than to conduct discussions, because they fear that conducting discussions with offerors will increase the 118 119 120 30 likelihood of a bid protest, and increase the protester’s chances of prevailing, if a protest is filed. Again, that would represent a loss, since the ability to conduct discussions with offerors is a good feature of our acquisition system, which few systems around the world have.121 As with excessive reliance on LPTA award criteria, we lack data about how common it is for contracting officers to award based on initial proposals merely to reduce the likelihood of a successful protest. In both situations, the author is skeptical that there is any good reason to try to “protest-proof” an acquisition in this way, especially in light of how rare protests are, and how exceedingly rare successful protests are. Moreover, neither using LPTA as the basis for award, nor making award based on initial proposals, without conduct discussions, will, in fact, ensure that no protest will be held, as GAO and Court of Federal Claims decisions ruling on protests of LPTA awards and initialproposal awards will testify.122 That said, it must be recognized that in both areas, and potentially in others as well, it is quite possible that the fear of protests – whether justifiable or not – is harming the acquisition system by driving bad decisions. To mitigate that harm, efforts need to be made to improve the knowledge of contracting officers about 121 122 31 the rarity of protests and the fact that making LPTA or initialproposals awards will not prevent protests, as well as the benefit to the government of using tradeoffs and discussions as means to obtain a better deal for the taxpayers. VI. BENEFITS OF THE PROTEST PROCESS As noted above, countries around the world are developing bid protest systems, and such systems have become, or are fast becoming, part of the norm for good government in the acquisition arena.123 That can be attributed to several benefits associated with protests. First, protests introduce a relatively low-cost form of accountability into the acquisition system by providing disgruntled participants a forum for airing their complaints.124 Protesting firms decide which procurements are to be investigated – if no one protests, neither GAO nor the Court of Federal Claims will look into the procurement; if someone does protest, they will (at least if the protest passes the procedural hurdles, such as timeliness).125 While reliance on audits by government officials would also provide accountability into the workings of the procurement system, it may be more efficient to focus on the procurements where a participant is dissatisfied by the government agency’s conduct, and that is 123 124 125 32 what the “private attorney general” model of a protest provides.126 In blunt terms, if no one is dissatisfied with the way the government conducted a procurement, it may not be a wise use of auditors’ time to investigate it. Second, by being directly responsive to participants’ complaints, protests can increase potential bidders’ confidence in the integrity of the procurement process, and therefore lead more players to participate, thus increasing competition. Increasing competition, in turn, can translate into bidders offering lower prices, higher quality, or both, to the contracting agency.127 Third, protests can increase the public’s confidence in the integrity of the public procurement process. While the public only rarely focuses on public contracting, having the protest process mentioned in the press—as happened when The Boeing Company successfully protested the Air Force’s award of the tanker contract to Northrop Grumman—may, it can be hoped, raise the public’s trust in the fairness of the government’s acquisition system and the way it spends taxpayer funds.128 Fourth, because protests are a known avenue for complaints, their availability empowers those in contracting agencies who face pressure to act improperly. Thus, if a contracting officer 126 127 128 The Boeing Company, B-311344 et seq., June 18, 2008. 33 is pressed by users within the agency to award a sole-source contract to a favored firm, the contracting officer—who may lack the bureaucratic clout to resist the pressure—can point to the risk of a successful protest as the reason to follow the statutory and regulatory requirements for competition. Fifth, protest decisions, because they are public, and have been released publicly since GAO issued the first one in 1926,129 provide a high level of transparency into what is happening in the federal procurement system. While, in theory, databases such as the federal procurement data system should provide transparency into the system,130 protests can often provide more useful information than databases. This is particularly the case where protests demonstrate how problematic certain issues are. For example, when GAO sustained a significant number of protests challenging the way agencies were conducting public/private competitions under OMB Circular A-76 in the 1990s, that highlighted the importance of improving the way those competitions were conducted, ultimately leading to revisions to the Circular as well as the creation of the congressionally-chartered Commercial Activities Panel.131 129 130 Commercial Activities Panel, Improving the Sourcing Decisions of the Government: Final Report, April 2002. Appendix D of the report summarizes GAO bid protest decisions arising from public/private competitions under OMB Circular A-76. 131 34 Similarly, it was GAO’s sustaining of a number of protests alleging organizational conflicts of interest that focused attention with the procurement world on this area, and ultimately led to congressional and regulatory action.132 Finally, the fact that protest decisions are published and widely read by practitioners brings an additional benefit: they provide guidance, particularly to agency counsel and attorneys representing potential protesters, as well as, of course, to their clients. for decades: To give just one example, which has been true any corporate counsel who follows GAO bid protest decisions knows how strictly GAO applies the “late is late” rule, so that counsel will ensure that people in the company appreciate the importance of getting bids in on time.133 VII. CONCLUSION: THE COSTS ARE OVERSTATED, AND THE BENEFITS OUTWEIGH THEM As explained above, the costs that bid protests impose on the acquisition system are often misunderstood and therefore overstated, in terms of the frequency of protests, the length of time that they last, and the risk that the agency’s choice of contractor will be overturned in the process.134 Moreover, the benefits of the protest system may not be fully appreciated, as See Daniel I. Gordon, Organizational Conflicts of Interest: A Growing Integrity Challenge, 35 PUB. CONT. L.J. 1 (2005), and cases cited therein. 132 133 134 35 is the fact that the United States is required by its international trade agreements to have a protest system.135 Whatever costs protests impose on the procurement system are outweighed, at least in the author’s view, by the benefits that protests bring, in terms of transparency, accountability, education, and protection of the integrity of the U.S. federal acquisition system. 135 36