DRAFT STATEMENT OF COMMON GROUND ON FLOOD RISK AND SURFACE WATER DRAINAGE PINS Ref: APP/D0515/A/14/2210915/NWF Fenland D.C. Ref F/YR13/0714/O Appeal by Showfields Limited Erection of up to 249 dwellings with associated infrastructure, vehicular and pedestrian access, public open space and associated flood mitigation works. Land North of Whittlesey, East of East Delph, Whittlesey, Cambridgeshire. Introduction 1. This Statement of Common Ground (SCG) relates to an appeal under section 78 of the Town and Country Planning Act 1990 (as amended) by Showfields Ltd and considers matters relating to flood risk and surface water drainage. It provides the areas of common ground between the Environment Agency, Showfields Limited, Fenland District Council and North Level Internal Drainage Board. 2. The Government's policy with regard to flood risk in the context of planning is set out in the National Planning Policy Framework (NPPF), published on 27 March 2012. Paragraphs 100 to 104 of NPPF set out a sequential and risk based approach to be adopted at all levels of planning. Paragraph 100 of NPPF covers the requirement to consider flood risk from all sources and states that ‘inappropriate development in areas at risk of flooding should be avoided by directing development away from areas at highest risk, but where development is necessary, making it safe without increasing flood risk elsewhere.’ 3. NPPF is supported by Planning Practice Guidance (NPPG) which is web based guidance, last updated on 6 March 2014. 4. Schedule 5 of the Town and Country Planning (Development Management Procedure) (England) Order 2010 identifies the Environment Agency, as a consultee under Article 16 on applications, other than minor development, which is to be carried out on land –(ze) (i) in an areas within Flood Zone 2 or Flood Zone 3; or (ii) in an area within Flood Zone 1 which has critical drainage problems and which has 1 been notified for the purpose of this provision to the local planning authority by the Environment Agency, and (zf) any development on land exceeding 1 hectare or more. 5. The Environment Agency's role as statutory consultee for flood risk is to ensure that the technical requirements of NPPF in relation to coastal and fluvial flood risk and surface water drainage are adequately considered in any planning application. This is generally done through providing comments to the Local Planning Authority (LPA) on the Flood Risk Assessment (FRA) submitted with the planning application. A FRA must be provided for all sites within Flood Zones (FZ) 2 and 3 or where the site area is greater than 1 ha. t. In this instance, the Environment Agency is a party to the SOCG as statutory consultee to assist the Inspector on flood risk matters at the Inquiry but is not a Rule 6 party as we have no objection to the development subject to appropriate conditions being imposed It is not part of the Environment Agency’s role to determine whether it is necessary to apply the sequential test in accordance with paragraphs 100 to 104 of the NPPF,,or to determine whether this test has been met. This role lies with the LPA in this case Fenland District Council. 6. The development site lies on the edge of the North Level Internal Drainage District. The North Level Internal Drainage Board (IDB) is a drainage authority with permissive powers to manage water levels within their district. They undertake works to reduce flood risk to people and property and manage water levels to meet local needs. They also provide advice and direction to local authorities and developers as part of the Town and Country Planning process. Site Location 7. The site comprises a series of fields (or parts of fields) on the northern edge of Whittlesey extending from East Delph (B1040), across to land to the north of Moorhen Road. The site is bounded by existing development to the south and the Whittlesey Washes to the north. The application site location plan shows the area proposed for development edged in red. Operation of Whittlesey Washes and Flood Levels 8. The Whittlesey Washes Flood Storage Reservoir lies to the south of the River Nene, east of Peterborough. It plays an important part in helping to reduce the risk of 2 flooding in Peterborough and the surrounding area during combined high tides and river flows. It is designated a reservoir under the Reservoir Act 1975. 9. The reservoir is approximately 20km long and up to 1.4km wide in places. It covers an area of approximately 1,450 hectares, reducing flood risk principally to Peterborough. The Washes reduces risks to hundreds of properties, as well as roads, railways and more than 8,000 hectares of farmland in the fenland area to the south east of Peterborough. 10. Flood water is stored on the Washes when high river levels cannot be released downstream due to high tides when the tidal sluice gates at the Dog-in-aDoublet Sluice are closed. This is when the river is ‘tide-locked’. High flows from the River Nene are diverted into Morton’s Leam through Stanground Sluice. When the capacity of Moreton’s Leam is exceeded, water flows in to the Washes and is contained by the South Barrier Bank and the Cradge Bank (separates the River Nene from the Washes). The River Nene continues to flow and in extreme flood events water from the River Nene also flows in to the Washes over the Cradge Bank which forms the southern bank of the River Nene. 11. As the tide recedes, water is released from the reservoir and back into the River Nene from the eastern end of the Washes via the Rings End tidal sluice. The equivalent of 14,000 Olympic‐sized pools of flood water can be temporarily stored on the Washes. A diagram showing this can be found in Appendix A 12. The lowest crest level of the South Barrier bank is 5.2m AOD. For a length north of Whittlesey, the South Barrier Bank is not required as ground levels are higher than in the surrounding fens. The Cradge bank, to the east of the Dog in a Doublet is set at 4.3 m AOD. In extreme flooding scenarios where a prolonged series of high tides coincides with very high river flows the River Nene and the Washes can reach a level above the Cradge Bank. The Environment Agency have determined that the maximum level of storage that can be achieved in the Washes before flooding large portions of Whittlesey and the surrounding fens is 5m AOD. There are however some lower lying residential areas to the north of Whittlesey which could potentially flood before the maximum level of storage is reached. The Environment Agency have used the 5.0m AOD level as defining the extent of the flood storage and the Whittlesey Washes. 3 13. The rate at which the Washes fill and drain down depends on both the river and tide conditions. The Washes may fill when high flows in the River Nene exceed the discharge capacity of the Dog in a Doublet sluice even in low tide conditions or where relatively normal river flows are restricted by reduced discharge through the Dog in a Doublet sluice by high tides. The duration of high river flows or high tides will also have an effect. 14. There are a multitude of different hydrological scenarios such that defining the probability associated with each (or cumulatively) would require highly complex statistical analysis of joint probabilities. However, as discussed further in paragraph 18 the extent of the area designated as flood storage is considered to be functional flood plain for planning purposes. Consequently joint probabilities have not been considered further in relation to development planning. 15. In summary, the designated functional floodplain is defined by the physical maximum capacity of the Reservoir. It is recognised that the full extent will only be used in extreme events although the frequency of this use may increase as a result of the impacts of climate change. 16. The flood levels contained within the FRA, provided by the Environment Agency in 2011, are ‘in-channel’ levels based on a downstream tidal boundary set at Mean High Water Springs (which is loosely an average of the high tides when the tidal range is at its greatest). The model simulations from which these water levels are derived provide a reasonable prediction of the water levels which will be achieved during fluvial floods of the defined scenarios. The predictions are within acceptable fluvial modelling tolerances but do not fully simulate all possible flooding scenarios. 17. The Environment Agency is currently carrying out improvements to the length of the South Barrier Bank to maintain its structural integrity as required following the latest reservoir safety inspection. These works involve strengthening the bank by reshaping the slope of the bank and placing extra material at the base. This will not affect the standard of protection offered by the Washes and has no implications on the development site as the South Barrier Bank is not present at this location. 4 Flood Map for Planning (Rivers and Sea) 18. The Environment Agency has a suite of flood maps including the Flood Map for Planning (Rivers and Sea). This shows the Flood Zones as set out in the National Planning Policy Framework (NPPF). 19. In this case the Nene Washes to the north of the appeal site is considered to be Flood Zone 3b, Functional Floodplain. The level defining the boundary between Flood Zone 3b and Flood Zone 1 is 5.0mAOD. 20. The Flood Risk Assessment for the site, in Figure 4.1.1 shows the original flood map for the site which the Environment Agency provided in 2011. At this time the extent of storage of Whittlesey Washes and hence FZ3 was plotted on the 5 metre contour on the Ordnance Survey (OS) 1:10,000 scale map. 21. In 2012 a flood map challenge was made to the Environment Agency based on the site specific topographic survey. The challenge aimed to demonstrate that the OS 5 metre contour was coarse and did not represent site specific levels in sufficient detail. 22. The Environment Agency compared the topographic survey to the their latest survey undertaken using LIDAR (Light Detection and Ranging) which is a commonly accepted technique for delivering highly accurate height data (ground levels). It was found that both surveys gave the similar results and the flood map was changed based on the LIDAR data. This is now shown on the published flood map for planning (rivers and sea). 23. The agreed extent of the 5.0mAOD contour is shown in the FRA as Figure FRA02 revD. Sequential test 24. The NPPF sets out the requirement to apply a sequential test when determining if development is appropriate in areas of flood risk. Paragraph 100 of the NPPF advises that Local Plans should apply a sequential, risk-based approach to the location of development, and to that extent, the LPA carries out a sequential test. For individual applications, NPPG advises that it is for the applicant to present sequential test information in an appropriate site specific FRA. NPPG contains guidance on the level of detail in the CHECKLIST(paragraph 068 Reference ID: 7068-20140306). The NPPG, paragraph 034, Reference ID: 7-034-2013-0306 states 5 that the developer should justify with evidence to the LPA what area of search has been used when making the application. The role of the LPA is to consider whether a sequential and exception test is required and whether this has been carried out satisfactorily. 25. The Environment Agency’s position of non-objection on the technical accuracy of the flood risk assessment does not prejudice the LPA’s requirement for and assessment of any sequential test. NPPF Paragraphs 102 and 103 set out that the sequential test applies to the flood zone designation before the exception test is applied. 26. The Sequential test covers all forms of flooding as set out in Local Plan policy LP14 and in various references in NPPG. 27. The Environment Agency informs the exception test process by advising on the accuracy of the flood risk assessment on safety issues, mitigating and managing risks to others. 28. The outcome of the sequential test is not agreed and is a subject of this appeal.Environment Agency agrees with the FRA, and accordingly does not advises the LPA that the development will not increase flood risk elsewhere. poses safety risks. In the case of this development, the LPA considers that the sequential test should be applied. The appellant considers that the sequential test is of no practical purpose as the entirety of the development will be in FZ1. The Development proposal 29. It is agreed that drawing FRA02 Revision D shows the site specific extent of FZ3b and in line with the published flood map for planning (rivers and sea). 30. In order to rationalise the development potential for the site, the FRA proposes (section 4.11) reprofiling of the site with floodplain compensation on a level for level, volume for volume basis. It is agreed that this would involve raising ground levels in the north and west of the site out of FZ3b (functional flood plain)and lowering ground levels on a central parcel of land to bring this compensatory land into the Whittlesey Washes. -It is agreed that this technical solution which is acceptable to the EA in both technical and practical terms, would ensure that postdevelopment, no built development would be located in FZ3 (that is lower than the 5 metre contour) and all built development would be entirely with FZ1. There with will 6 be no volume of storage lost within the Whittlesey Washes and therefore the development would not give rise to increased risk of flooding elsewhere. The technical and practical feasibility of the flood compensation works has been agreed with the Environment Agency. This agreement does not imply that the proposal is acceptable in respect of planning policy or negate the requirement for the sequential test. Other Matters 31. The Environment Agency has not considered the desirability of public open space, highways or private curtilage flooding - FDC considers this to be their role, as informed by relevant advisors. Whilst the EA advises that it is principally tasked with avoiding significant risks of internal flooding, the EA can advise LPAs where flooding of external space may remain a risk. The EA and FDC agree that it is for the LPA to assess the acceptability of the impacts of flooding in relation to material considerations such as private amenity space, public amenity space, utilities, transport, access for disabled persons and landscaping. Signed Environment Agency................................................. Fenland District Council............................................. North Level Internal Drainage Board.......................... Showfields Limited...................................................... 7