MINUTES OF THE COASTAL SHIPPING PROJECT IMPLEMENTATION AND MONITORING COMMITTEE MEETING HELD IN THE CHAMBER OF THE MANAGING DIRECTOR, KERALA STATE MARITIME DEVELOPMENT CORPORATION LIMITED, KOCHI – 16 ON 23.03.2013 AT 11 30 AM Meeting chaired by Shri.K.R Vinothu, Port Officer, Allappuzha PRESENT 1. 2. 3. 4. 5. 6. 7. Capt. Abraham V Kuriakose, Port Officer, Kozhikode Shri. Bijoy Aleyas, Registering Authority Capt. Aswani Prathap. K, Port Officer, Kollam Shri. K.R Vinothu, Port Officer, alappuzha Shri. K.K Rajendran, Managing Director, KSMDCL Shri. V.V Prasad, Port Conservator Capt.Binuvarghese ,Chief examiner Sl. No Issues discussed Decision taken Person doing Date of completion 1 Sanctions from government for providing Rebate in Port Dues and Ship Building Subsidy. Proposals have already been forwarded to Government. The Government Awaiting 2 For availing cargo-subsidy to Stake holders (Ship owners, Cargo owners and disponent owners) To fill and forward the application in the prescribed format Stake holders (Ship owners, Cargo owners and disponent owners) Immediate 3 Providing Sales Check-Post in the ports for hazel free domestic cargo movement. Decided to install Check Post in Ports Port Officer, Kollam Immediate Present Status Awaiting Awaiting Letter issued to Sales tax dept &met the dept officers 4 Container Handling Crane facility in Kollam Port Tender invited for hiring out of Container Handling Crane in Kollam Port D1-Section in Port Directorate Immediate 5 Weigh Bridge facility in Kollam Port Proposal sent to HED for construction of weigh bridge in Kollam Port HED Immediate 6 Other infrastructure development in Kollam Port Immediate action for the commencement of shipping operation Port Officer, Kollam Immediate 7 Container Handling Crane facility in Vizhinjam Port The container handling crane could be hired locally The Purser Vizhinjam & Port Officer Kollam Immediate Coastal Shipping service in the Kerala coast by M/s. LcL Logistics Ltd. To provide Container Shipping Service in the Port Sri. Jaison George, M/s. LcL Logistics Ltd. April 2013 Shipment Operation of 15000 tonne Cargo in Vizhinjam Port through coastal shipping project by M/s. English-Indian Company Prepare and give a schedule of service of Ship Owners to M/s. English-Indian Company Sri. Jaison George, M/s. LcL Logistics Ltd. Incentive benefits to shipping agents for transportation of cargos. 8 40t Container Handling Crane facility in the Port Allow discounts to shipping agents for transportation of cargos by Ship owners. The Ship owners, M/s. Lots Shipping The Ship owners should send a letter to and M/s. Transasia the Director of Ports. Tender invited for hiring out of 40t Container Handling Crane in the Port D1-Section in Port Directorate Bid opened &awarding to M/s Laxmi cranes HED confirmed Will complete in 2 months Rest room & toilet facility work pending Wharf strength not adequate, Study to be conducted by CET completed In progress Immediate completed Within few days. Immediate LC opening &bank guarantee in 3 weeks 9 Labour issues in the Port Labor issues arising from the trade unions during shipment are out of control of Port department and the same has to be handled by the District Authority and Labour Department. The District Collector and Labour Department. Other infrastructure Development in Kozhikode Port Immediate action for the commencement of shipping operation Port Officer, Kozhikode. Immediate Labour charges settled to Rs 190/container in Kollam port Action initiated Immediate completed Prepare a data form for Port facilities in each Port Prepare a data form Filling up of the data form & filing the details of the Port – Alappuzha Sri. K.R. Vinothu 11.02.13 Forward the filled up data to the MME -do- 20.02.13 Filling up of the data form & filing the details of the Port – Vizhinjam Port. Forward the filled up data to the MME Port officer, Kollam 20.02.13 Filling up of the data form & filing the details of the Port – Kollam Port. Forward the filled up data to the MME Port officer, Kollam 20.02.13 Filling up of the data form & filing the details of the Port – Kodungallur Port. Forward the filled up data to the MME P.C. Kodungallur 20.02.13 Filling up of the data form & filing the details of the Port – Beypore Port. Forward the filled up data to the MME Port officer, Kozhikode 20.02.13 Filling up of the data form & filing the details of the Port – Azhikkal Port. Forward the filled up data to the MME Port officer, Kozhikode 20.02.13 Approved list of Cargo owners, Ship owners and Shipping agents Forwarded to MME to publish in the Port Website Do Do Do Do All Port Officers, PC-Kodungallur, Purser-Vizhinjam Do Do Do 01.03.2013 List of documents to be submitted by the Forwarded to MME to publish in the Port Shipping Agents Website 10 11 Prepared PIMC Prepared Fix and publish the rate/fees for container handling at port Forwarded to MME to publish in the Port Website PIMC Number and rate of labours engaged in Port Forwarded to MME to publish in the Port Website All Port Officers, PC-Kodungallur, Purser-Vizhinjam Hiring or purchasing Vessels for coastal shipping operations. The committee has ascertained the feasibility of department owned vessel for the project implementation The committee has ascertained the feasibility of hiring Portable/mobile Weigh Bridge facility in Ports weigh bridge and decided to get the specification of the same. The team leader Sri: K R Vinothu Prepare and furnish the details of each reported that the Data form prepared Port in the proforma. and forwarded to the Port Officers and all members of the committee to furnish the details. The Managing Director, KSMDC reported that the MD and Port Officer, Kollam Prepare proposal for hiring out of visited Mumbai for find out the vessels. possibilities of hiring out the Vessels for coastal shipping operations. They pointed out two vessels for this purpose. 1. “Coastal Line” 2. “Sooryamughi” 01.03.2013 MD, KSMDCL & Port Officer Kollam All Port Officers, PC-Kodungallur, Purser-Vizhinjam & MD KSMDCL Port officers/ PCs of each Port 01.03.2013 Completed Immediate Immediate Immediate Tendered &opening on 27/03/13 Tender to be invited Completed 25.02.2013 Completed MD, KSMDC. 20.02.13 12 The Port Officer, Kozhikode reported that one passenger, ferry Prepare proposal for Ferry/Passenger builder/operator from Mumbai coming operations. to Calicut to discuss about passenger/Ferry operation – Kozhikode to Kollam or Vizhinjam. Port officer, Kkd. Analyzing cost benefit of incentive scheme Cost benefit of incentive scheme as well as Port Officers as well as coastal Shipping Project in the Coastal Shipping project has already Kerala State. discussed and decision taken by Government and it is also informed to all Cargo owners, Ship owners and desponents . Priority measure to be taken for Those who are interested in Coastal shipping Port Officers implementation of Coastal Shipping Project. operating with their own vessels and MD KSMDCL participated in several meetings conducted by Ports Department. On verification we found that the availability and readiness of ship will be delayed due to the various reasons. Expected delay will not less than 3 months as informal by the groups. In order to avoid delay in executing the Coastal Shipping programme / activities. Kerala State Maritime Development Corporation Limited shall be able to undertake the trading activities directly by chartering the vessels in India projected figures for 2 vessels identified on charter basis is given below: a. A container vessel of 160 TEU with gear identified at Bombay with chartered rate is around 1.5 lakhs / day + Taxes, Fuel , Port charges. b. A bulk carrier which can be Meeting with the team in April 2013 Ongoing process and I Month Action ongoing. Action initiated converted into a container vessel of 60TEU or it can be operated as a bulk carrier itself with a capacity of 2753 m3 ( Grain capacity) and its charter rate as around Rs.1 Lakh / day + fuel ( 2.7metre/day and 0.3MT /day DO) In commencing the chartering operation by Kerala State Maritime Development Corporation Limited, the committee is of the opinion that Action by port Dept. financial assistance may be provided to KSMDCL. Analyzing each port total infrastructure facilities in Request immediate action a. On verifying the basic infrastructure at various minor ports, the top priority may be given for procuring container handling crane at Beypore, and Kollam ports b. As a temporary measure hired container handling cranes may be made available at Kollam, Beypore Head Quarters Port ports by the 1st week of April. Dept. 1 Month for Action initiated Pitless weighing scale may be installed at Beypore, Vizhinjam, Kollam ports. c. Weigh bridge has to be constructed urgently at Beypore, Kollam and Vizhinjam ports. Head Quarters Port 1 Month Dept. Preparation of coastal Shipping feasibility Managing Director, KSMDCL to do the MD, KSMDCL report by a competent Chartered necessary feasibility for the operation with 25 Days Action initiated Accountant in Shipping field Chartering a vessel in the support of a consultant in the field Analysis of expenditure involved in the transport of cargo from Kollam to Cochin through sea and road respect to the current data available for chartering the vessel available. Committee suggested making separate calculations for Cochin to Kollam and Cochin to Beypore. MD KSMDCL consulted qualified Chartered Accountants and Logistic support and C&F and necessary inputs collected. Comparative study of converted mini bulk The committee suggested to hire a vessel MD KSMDCL cargo in non – major port with crane to facilitate at all ports till we acquire our own facilities at each port. Possibility study / analysis of bulk cargo in Bulk cargo available at Beypore port. Port Officer non – major project Beypore Total cargo availability in each port Already discussed and details available with PO Kollam Port Officer, Kollam. Status of handling equipments in each port Already evaluated ‘End to End’ solution of transportation of Managing Director, KSMDCL will initiate the MD, KSMDCL cargo at Kollam and Beypore action 13 14 15 Pilot service facilities in each port started , 1 Month Completed started completed evaluated 15 days on confirmation of vessel arrival Directorate of Ports. 1 Month Port officer TVM. Kollam given a proposal at HOMC meeting. At present private pilot services may be arranged in all operating ports (Beypore, Kollam & Vizhinjam) either on contract or permanent basis, Director of Ports may take an appropriate decision in this regard. Feasibility of fuel, water supply at port and Already evaluated Port Officers anchorage Requirement of tugs for bringing ships inside The repair work of one and only one tug Port Officer, Kollam the port and operational crew available at Kollam, MT Padmasree is continuing indefinitely. Urgent action has to be taken to complete the repair work of MT Urgent action Padmasree along with the delivery of new tug under construction. Channel marking buoys installation in Ports 20 Days Installation of channel marking buoys at CME Completed completed 1 Month Various meeting held at KSINC & fund released as per request of KSINC. But the work progress is very slow same to be addressed at government level Supply 16 Customs clearance facility in ports 17 Coastal shipping container vessel tender evaluation Analyzing and empowering all weakened segments in the project Beypore, Kollam, Vizhinjam, Ashtamudi & KDR are still incomplete .To be expedited Status of waving cost recovery charges at Directorate Of Ports. 2 Months Kollam Port is pending with Government. TVM Customs Licence is to be renewed. Prepared a tender evaluation sheet PIMC Completed prepared Immediate availability of vessel, cranes and Directorate of ports, 1 Month providing logistic support Pos and MD KSMDCL &installation by April 2013. Weigh bridge& separate room for customs to be provided. Action ongoing Completed The meeting ended at 1330 Hrs Alappuzha 23.03.2013 K.R. Vinothu. (Team Leader PIMC) Port Officer Alappuzha