Phase 2: Route Refinement Stakeholder Engagement in Greece West 1 INTRODUCTION 1.1 THIS REPORT This report presents the stakeholder engagement process undertaken as part of the route refinement process of the Trans Adriatic Pipeline Project (TAP) in Greece. The route refinement process was undertaken between October 2010 and April 2011 and included three main field trips to the study area: in November and December 2010 and February 2011 as part of the route appraisal fieldwork, and in July 2011 to disclose the preferred pipeline route to national, regional and local authority stakeholders. The SEP (Greece) has been divided into six phases, each with slightly different objectives for consultation and engagement. Table 1.1 summarises the phases of the SEP Greece and the progress to date. Table 1.1 Phases of the SEP Greece and Progress to Date Engagement Phase Phase 1: pre-Scoping Phase 2: Route Refinement (alternative route selection) Phase 3: ESIA Scoping Phase 4: Main ESIA Phase 5: ESIA Finalization and Disclosure Phase 6: Ongoing Engagement Status Compete Complete Planned Planned Planned Planned As presented in Table 1.1, the route refinement process is the second phase of consultation for the TAP Project in Greece. The first phase involved high level consultation with national authorities, and phases 3 to 5 will be conducted during scoping, the main ESIA and ESIA disclosure. 1.2 OBJECTIVES OF STAKEHOLDER ENGAGEMENT DURING ROUTE SELECTION The overall objectives of stakeholder engagement during the route refinement process were to introduce the proposed project to stakeholders and gather information pertinent to the route selection process. The information collected was used to complement and verify information obtained from a desktop study and included the identification of social, environmental and cultural sensitivities and the level of support or opposition from stakeholders towards the project. The specific objectives of Route Refinement Stakeholder Engagement are the following: Stage 1: Notification to Authorities and Engagement with Key Stakeholders (November 2010 – February 2011) • Introduce the work of the Project team. • Explain TAP’s sustainability and stakeholder engagement approach. • Provide an overview of the field work. • Check completeness of the stakeholder groups identified. • Request their support during implementation of field activities. • Gain an understanding of the local population (local administration, demographics, presence of vulnerable groups, land use, livelihoods, etc. and any specific issues at the local level). • Discuss key issues and answer stakeholder questions to the extent possible at this stage of development of the Project. Stage 2: Verification Activities (July 2011) • Inform about the preferred route. • Validate the results of the route refinement report with the administrations and communities affected by the selected base case. • Disclose the results of the assessment with stakeholders. • Discuss any concerns stakeholders have about the preferred route. 1.3 STUDY AREA The TAP pipeline will commence in Greece near Thessaloniki1 and head west to the boarder of Albania. The pipeline will then cross Albania and the Adriatic Sea and end in Italy. Within Greece, it will run from Thessaloniki to the Greek-Albanian border in the municipality of Kastoria. The Alternative Route Selection Appraisal of the two main alternatives under consideration crosses two administrative regions in Greece which are outlined below and shown in Figure 1.1: • Central Macedonia at the eastern end; and • Western Macedonia up to the Albanian border. Figure 1.1 1 Route Refinement Study Area Please note that at the time this report was developed, TAP had not yet decided to expand the project further to the Greek-Turkish border in the East. At the beginning of the route refinement process (end of 2010) the two regions were administered through a number of prefectures and municipalities. However, political and administrative changes in Greece resulted in the prefectures being repealed and the number of municipalities reduced. This was achieved by merging and altering the existing boundaries. This process was referred to as Kallikratis and took effect as of January 2011. The regional boundaries remained unaffected by these changes. 2 APPROACH TO ROUTE REFINEMENT ENGAGEMENT 2.1 KEY CONSIDERATIONS In preparing our approach to stakeholder engagement during the alternative route selection process (Phase Two), the following factors were considered: • Geographic context: a 2 km corridor from each route alternative was used as the study area and defined the administrative divisions to be engaged as well as the settlements close to the route. The alternative corridors cross two Regions and 14 municipalities. • Stage of the Project: As this is an alternatives assessment process, not all municipalities/settlements located in the 2 km corridor will be finally affected by the project. It was therefore considered necessary to design the consultation process such that expectations and / or apprehension at the community level were not unnecessarily raised. • Level of activity in the field: Several specialists undertook activities in the local area at the same time during the field surveys. It was therefore necessary to ensure that the relevant authorities were aware and were supportive of this activity. • Compliance with EBRD Standards: Engagement activities were undertaken in line and compliance with EBRD standards and TAP’s corporate requirements. • Missing or unreliable data from the desktop study: Available information was collected and considered during the desktop study. Missing information or information from unreliable sources was noted and verified where possible by contacting relevant stakeholders and/ or consulting local subcontractors. 2.2 STAKEHOLDER IDENTIFICATION AND PRIORITISATION According to EBRD definition, stakeholders are individuals or groups that are (i) affected or likely to be affected (both directly and indirectly) by the Project (“affected parties”) or (ii) may have an interest in the Project (“other interested parties”). In view of the objectives of each phase of the engagement it is then important to define what level of engagement is appropriate for each group in that specific phase. These stakeholders are identified based on their likely interest in and influence over the project within at the specific phase. The list of stakeholders to be contacted during route refinement was detailed in the Action Plan for Route Refinement field activities and is summarized in the following paragraphs. 3 STAGE 1: NOTIFICATION TO AUTHORITIES AND ENGAGEMENT WITH KEY STAKEHOLDERS 3.1 OVERVIEW Stage 1 stakeholder engagement initially focused on the national, regional and prefecture level. It was then extended to all municipalities and to a sample of settlements within the route alternatives corridor. The following information was disclosed to all stakeholders met: • Presentation of TAP, its stakeholders and commitment to high international standards and EBRD requirements. • Overall stakeholder engagement and ESIA process schedule. • Objectives, study area and timing of the route refinement. The disclosure was supported by a presentation, which was distributed to the participants at the meetings. The maps of the route alternatives at scale 1:100,000 and 1:25,000 were shown and analysed with the participants. Figure 3.1 Meeting with Stakeholders - Molocha Settlement 3.2 LEVELS OF ENGAGEMENT 3.2.1 National Level Stakeholders The set of national level stakeholders engaged during route refinement is listed in Table 3.1. The engagement was initiated through a written communication to inform stakeholders about TAP project its status and the plan for fieldwork and to request data for the baseline studies, where applicable. A meeting was organized with most of these organizations between November and December 2010. Table 3.1 National Level Stakeholders Stakeholder Group(s) Departments/ Position Ministry of Environment, Energy & Climate Change Ministry of Defence Ministry of Culture Deputy Minister for Energy issues Ministry of Regional Development and Competitiveness Ministry of Infrastructure, Transport and Networks Ministry of Foreign Affairs Public Power Corporation Egnatia Highway S.A. Regulatory Authority for Energy DESFA - Natural Gas System Operator Engagement Informed Met Director of Prehistoric and Classical Antiquities. Department of Large Projects 29th Ephorate of Prehistoric & Classical Antiquities – Florina 30th Ephorate of Prehistoric & Classical Antiquities - Eani 16th Ephorate of Byzantine Antiquities – Kastoria General Secretary of Investments General Secretary √ √ √ √ √ √ √ √ √ √ √ √ √ Secretary General for International Economic√ Relations & Development Cooperation Mines Engineering and Development √ Department Mining area Dirachiou 89 Mining area Kifissou PPC Lignite Centre of West Macedonia - Ptolemaida High Voltage Power Lines Department √ Thessaloniki Department √ √ Managing Director Technical Departments (identified by the Managing Director) √ √ √ √ Stakeholder Group(s) Departments/ Position Inspectorate of Mines North Greece Director of Inspectorate of Mines North Greece and Engineers (Thessaloniki) Institute of Geological and Mineral Exploration 3.2.2 Engagement Informed Met √ √ √ Regional and Municipal Authorities After an administrative reform that entered into force in January 2011 and is referred to as Kallikratis, Greek public administration was reorganised under two main levels: regions and municipalities. The intermediate administrative level between regions and municipalities, that was called prefectures, was repealed by the reform. The reorganisation and redistribution of roles and responsibilities between the remaining administrative levels is still on-going. When TAP started to engage with the administrative units in November 2010, prefectures were still in place. It was decided to include them in the stakeholder engagement program in order to gather the baseline data that they held before they were repealed. The following table lists the regions and municipalities crossed by the route and respective municipal capital cities. It also indicates the corresponding regional entities names, which were prefectures before Kallikratis. These were all included in the route refinement stakeholder engagement program carried out between October 2010 and February 2011. Table 3.2 Regions and Municipalities in the Study Area Region Regional Entity (ex Prefectures) Thessaloniki Imathia Central Macedonia Pella Kozani West Macedonia Region Kastoria Florina Municipalities Capital City Chalkidona Alexandreia Veroia Naousa Edessa Skydra Pella Kozani Voio Eordea Kastoria Orestida Nestorio Amyntaio Koufalia Alexandreia Veroia Naousa Edessa Skydra Giannitsa Kozani Siatista Ptolemaida Kastoria Argos Orestiko Nestorio Amyntaio In addition, the Regional Development Agency of West Macedonia (ANKO) was met and informed about the project. 3.2.3 Settlements A sample of settlements was engaged during the field survey in February 2011 to introduce the project to the local community and collect community level socio-economic baseline along the different alternatives and potential re- routings. The guiding criteria used to identify settlements within the 2 km study corridor that were visited were: • distance from the corridor centreline: the settlements within a 500 m corridor were prioritized; and • distribution of settlements along the whole route in order to provide a broadly representative understanding of the whole study area crossed by all alternatives sections considered. Meetings were held with heads of settlement in each of the settlements listed in Table 3.3. Based on the interviews with settlement heads, settlement profiles were compiled. Table 3.3 List of Villages Engaged by Municipality Municipality Municipality Capital Chalkidona Alexandreia Amyntaio Koufalia Alexandreia Amyntaio Edessa Eordea Kastoria Edessa Ptolemaida Kastoria Kozani Kozani Naousa Nestorio Naousa Nestorio Orestidos Argos Orestiko Pella Skydra Veroia Giannitsa Skydra Veroia Voio Siatista Stakeholder Engagement at Village level Sklithron Xinon Neron Anatolikon Chiliodendron Klesoura Akontion (not interviewed but visited, abandoned village) Voskoxwrion Agios Charalampos Kalamia Mavrodendrion Polla Nera Dipotamia Pentavrissos Militsa Ammoudara Aspron Palea Likogianni Patris Aliakmon Mikrokastron Molocha 3.2.4 NGOs Three environmental NGOs were engaged and informed about the project as key informants on the environmental and biodiversity values of the area and of the sensitivity of the communities towards new developments. Arcturos was identified as the major NGO operating in the area, the Hellenic Ornithological Society is a key informant for data on the natural environment and the Club of Friends of the Environment was indicated and invited by the Municipality in Kastoria. A wider NGO engagement is foreseen in the subsequent phases of the disclosure and consultation. 3.3 CONSULTATION OUTCOMES Generally municipalities engaged indicated that they would welcome the pipeline through their municipality in order to realise potential benefits associated with the project. In particular expectations were expressed about compensation for land easement and acquisition and the possibility to receive and use gas in the region. A thorough consultation mainly with the Public Power Corporation was dedicated to addressing the issue of lignite mines and their potential crossing (see Figure 3.3). It was confirmed that the selected alternatives are not interfering with areas of development of lignite mines. A summary of the main local issues collected along the different alternatives is provided in Figure 3.3 which also locates these issues on the map. The issues identified during stakeholder engagement feed into the route refinement process and ESIA studies and will be addressed through re- routing or identification of appropriate mitigation measures, subject to further consultations and disclosure. A summary of the issues identified and actions to be undertaken to follow up is provided in Table 3.4. Table 3.4 Main Issues Identified during Route Refinement Stakeholder Engagement Issue Description Issue Stakeholder Group Proposed Follow up Action Underground irrigation channels Alexandreia The agricultural area of Alexandreia is served by a vast irrigation system, installed 1-2.5 m below ground level functioning between April and October. Alexandreia Municipality Take into account the irrigation system and its seasonality for construction and reinstatement planning to minimize interference. Include in route refinement reporting. Further evaluate through ESIA. Information shared with technical team to include in route refinement reporting if appropriate. Further evaluate through ESIA. Wind farms on Vermio mountain A large wind farm project is proposed by ENTEKA – ACCIONA on the peaks of Vermio (at heights up to 2400 m). The estimated location for the proposed 528MW wind farm has been identified between the city of Kato Gramatikon and southwards towards the city of Kato Vermion. Industrial park planned A 200 ha industrial park has been and road in construction discussed for the area south of PollaNera. The road Naousa – Veroia – Patrida – Skydra has been partially constructed (till Patrida) while another part remains in blueprints. Project ran out of financing several years ago and is viewed as unlikely to continue soon. Wind farm projects and Wind farm projects are planned in the urban expansion at Municipality of Veroia (Altenative S0), Veroia directly along Section 11. Expansion of Veroia has occurred (Sections 11 and 12). As such re-routings 5 and 6 are considered a good alternative to avoid conflict. Crossing of PerdikkasFurther urbanization is planned along Ptolemaida road the road Perdikkas-Ptolemaida (Alternative N2) north of Ptolemaida. No urban plans are available for the area but according to the Greek Law the land along national roads is considered “constructible”. Wind farms at A windfarm project is being discussed Anatolikon for the area along the ridge near the village of Anatolikon (Alternative N1). The EIA was not yet submitted. District heating Kozani is heated by district heating from power plants north of the pipeline- three pipes cross under the road and the intended pipeline route. Edessa Municipality Skydra Further evaluate plans for industiral development through ESIA. Follow up with municipalities for road route plans. Information shared with technical team to include in route refinement reporting if appropriate. Further evaluate through ESIA. Eordea Municipality Include in route refinement reporting. Further evaluate through ESIA. Anatolikon Village, Eordea Municipality Verify position and stage of development of the project during ESIA studies. Information shared with technical team to include in route refinement reporting if appropriate. Further evaluate through ESIA. Kozani Municipality Issue Description Issue Industrial area DrepanonMavrodenndrion An industrial area is planned along the road between Drepanon and Mavrodendrion on the Alternative S0. Army camps Army camps are located at Mavrodendrion village (Alternative S1) and Nea Nikopolis village (Alternateive S0) in the municipality of Kozani. Underground water pipe Underground pipes bringing water from a dam in the southwest to the city of Siatistra and other major population centres in the municipality cross both southern pipeline routes. Underground irrigation An underground irrigation scheme scheme was indicated in the area between the village of Molocha and the river Aliakmonas. Water supply reservoir Underground water pipes from a Pentalofos reservoir in Pentaolofos (south west from the study area) supply Siatista, Aliakmon, Mikrokastron and others in the area crossing Alternative S0. Stakeholder Group Include in route refinement reporting. Further evaluate through ESIA. Mavrodendrion village, Nea Nikopolis Village Further evaluate through ESIA. Continue communication with the military on potential military sites along the route. Consider this information Voio Municipality in technical reports. Obtain the route plans of the water pipes at a later project stage. Molocha Village Located on S1Alternative. Siatista town, Aliakmon village, Mikrokastron village Cultural heritage findings Potential archaeological findings directly on the Alternative S0 corridor between Pentavrissos and Ipsilo. Orestida Municipality Mink farms Approximately four mink farms are located along Section 2 of the route. These are an important source of employment and income for villages in the area. Minks are reportedly sensitive to noise and could be impacted during construction activities. Municipalities officials identified several potential archaeological sites, including one along S0 near Pentavrissos that is not on the existing CH map. Kastoria Municipality Cultural heritage sites Proposed Follow up Action Information shared with technical team to include in route refinement reporting if appropriate. Further evaluate through ESIA. Information shared with cultural heritage team. to include in route refinement reporting if appropriate. Further evaluate through ESIA. Further evaluate through ESIA. Information shared with cultural heritage team to include in route refinement reporting if appropriate.