Attachment 3 Charlotte Area Transit System (CATS) CityLYNX Gold Line Phase 2 Project Charlotte, NC Baseline Cost Estimate Table 1 - BCE by Standard Cost Category Applicable Line Items Only YOE Dollars Total (X000) 10 GUIDEWAY & TRACK ELEMENTS (route miles) 19,575,657 10.01 Guideway: At-grade exclusive right-of-way 0 10.02 Guideway: At-grade semi-exclusive (allows cross-traffic) 0 10.03 Guideway: At-grade in mixed traffic 10.04 Guideway: Aerial structure 10.05 Guideway: Built-up fill 0 10.06 Guideway: Underground cut & cover 0 10.07 Guideway: Underground tunnel 0 10.08 Guideway: Retained cut or fill 0 10.09 Track: Direct fixation 0 10.10 Track: Embedded 10.11 Track: Ballasted 10.12 Track: Special (switches, turnouts) 10.13 Track: Vibration and noise dampening 0 5,249,791 12,145,322 0 2,180,544 0 20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 3,009,540 20.01 At-grade station, stop, shelter, mall, terminal, platform 3,009,540 20.02 Aerial station, stop, shelter, mall, terminal, platform 0 20.03 Underground station, stop, shelter, mall, terminal, platform 0 20.04 Other stations, landings, terminals: Intermodal, ferry, trolley, etc. 0 20.05 Joint development 0 20.06 Automobile parking multi-story structure 0 20.07 Elevators, escalators 0 30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 0 30.01 Administration Building: Office, sales, storage, revenue counting #DIV/0! 30.02 Light Maintenance Facility #DIV/0! 30.03 Heavy Maintenance Facility #DIV/0! 30.04 Storage or Maintenance of Way Building #DIV/0! 30.05 Yard and Yard Track #DIV/0! 40 SITEWORK & SPECIAL CONDITIONS 28,004,286 40.01 Demolition, Clearing, Earthwork 4,420,026 40.02 Site Utilities, Utility Relocation 12,973,213 40.03 40.04 40.05 40.06 40.07 40.08 Haz. mat'l, contam'd soil removal/mitigation, ground water treatments Environmental mitigation, e.g. wetlands, historic/archeologic, parks Site structures including retaining walls, sound walls Pedestrian / bike access and accommodation, landscaping Automobile, bus, van accessways including roads, parking lots Temporary Facilities and other indirect costs during construction 50 SYSTEMS 208,604 0 160,340 991,720 3,603,865 5,646,519 22,675,493 50.01 Train control and signals 50.02 Traffic signals and crossing protection 1,058,253 50.03 Traction power supply: substations 11,117,815 50.04 Traction power distribution: catenary and third rail 9,487,451 50.05 Communications 167,467 50.06 Fare collection system and equipment 111,190 50.07 Central Control Construction Subtotal (10 - 50) 60 ROW, LAND, EXISTING IMPROVEMENTS 60.01 60.02 Purchase or lease of real estate Relocation of existing households and businesses 733,317 0 73,264,977 1,201,415 1,201,415 0 70 VEHICLES (number) 40,886,578 70.01 Light Rail 37,510,622 70.02 Heavy Rail 0 70.03 Commuter Rail 0 70.04 Bus 0 70.05 Other 0 70.06 Non-revenue vehicles 0 70.07 Spare parts 3,375,956 80 PROFESSIONAL SERVICES (applies to Cats. 10-50) 23,564,385 80.01 Project Development 16,713,177 80.02 Engineering (not applicable to Small Starts) 80.03 Project Management for Design and Construction 1,658,155 80.04 Construction Administration & Management 1,842,394 80.05 Professional Liability and other Non-Construction Insurance 0 80.06 Legal; Permits; Review Fees by other agencies, cities, etc. 51,178 80.07 Surveys, Testing, Investigation, Inspection 80.08 Start up Subtotal (10 - 80) 90 UNALLOCATED CONTINGENCY Subtotal (10 - 90) 100 FINANCE CHARGES Total Project Cost (10 - 100) 0 740,601 2,558,881 138,917,355 11,082,645 150,000,000 0 150,000,000 Attachment 3 Charlotte Area Transit System (CATS) CityLYNX Gold Line Phase 2 Project Charlotte, NC Baseline Cost Estimate Table 2 - Inflated Cost to Year of Expenditure Base Year Base Year Dollars w/o Dollars Contingency Allocated (X000) Contingency (X000) Base Year Dollars TOTAL (X000) Inflation Factor YOE Dollars TOTAL (X000) 2,144,634 17,775,289 1.1013 19,575,657 171,886 2,714,111 1.1088 3,009,540 0 0 0 #DIV/0! 0 40 SITEWORK & SPECIAL CONDITIONS 23,136,794 2,638,445 25,775,239 1.0865 28,004,286 50 SYSTEMS 18,828,481 1,972,765 20,801,246 1.0901 22,675,493 920,575 230,144 1,150,719 1.0441 1,201,415 70 VEHICLES (number) 34,335,000 3,433,500 37,768,500 1.0826 40,886,578 80 PROFESSIONAL SERVICES (applies to Cats. 10-50) 23,022,161 0 23,022,161 1.0236 23,564,385 10,129,370 1.0941 11,082,645 0 #DIV/0! 0 139,136,635 1.0781 150,000,000 10 GUIDEWAY & TRACK ELEMENTS (route miles) 15,630,654 20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 2,542,226 30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 60 ROW, LAND, EXISTING IMPROVEMENTS 90 UNALLOCATED CONTINGENCY 100 FINANCE CHARGES Total Project Cost (10 - 100) Attachment 3 Charlotte Area Transit System (CATS) CityLYNX Gold Line Phase 2 Project Charlotte, NC Baseline Cost Estimate Table 3 - BCE by Source of Funding Total Project Cost in YOE Dollars (X000) 10 GUIDEWAY & TRACK ELEMENTS (route miles) Double Federal 5309 Federal Other Check Total Small Starts (X000) 19,575,657 Local 19,575,657 9,787,829 9,787,829 3,009,540 1,504,770 1,504,770 0 0 0 0 40 SITEWORK & SPECIAL CONDITIONS 28,004,286 28,004,286 14,002,143 14,002,143 50 SYSTEMS 22,675,493 22,675,493 11,337,747 11,337,747 1,201,415 1,201,415 600,708 600,708 70 VEHICLES (number) 40,886,578 40,886,578 20,443,289 20,443,289 80 PROFESSIONAL SERVICES (applies to Cats. 10-50) 23,564,385 23,564,385 11,782,193 11,782,193 90 UNALLOCATED CONTINGENCY 11,082,645 11,082,645 5,541,322 5,541,322 0 0 0 0 150,000,000 150,000,000 75,000,000 20 STATIONS, STOPS, TERMINALS, INTERMODAL (number) 3,009,540 30 SUPPORT FACILITIES: YARDS, SHOPS, ADMIN. BLDGS 60 ROW, LAND, EXISTING IMPROVEMENTS 100 FINANCE CHARGES Total Project Cost (10 - 100) 0 75,000,000 Sources of Federal Funding and Matching Share Ratios Federal 5309 New Starts Federal Other (please specify sources...) Total Costs Attributed to Source of Funds (X000) Federal/ Local Matching Ratio within Source All Federal Funds (X000) Local Funds (X000) 150,000,000 50/50 75,000,000 75,000,000 75,000,000 75,000,000 0 150,000,000 Overall Federal Share of Project 50.00% New Starts Share of Project 50.00% Attachment 3A Charlotte Area Transit System (CATS) CityLYNX Gold Line Phase 2 Project Charlotte, NC Baseline Cost Estimate Scope and Activity Description Scope Code ALI Code Scope and Activity Line Item Descriptions Federal 5309 Small Starts Qty Total Federal % Federal Local Total 2.58 50.00% 9,788 9,788 21 50.00% 1,505 1,505 Federal Other Federal Local Project Totals Total Federal Local Total 19,576 0 9,788 9,788 19,576 3,010 0 1,505 1,505 3,010 14010 140110 GUIDEWAY & TRACK ELEMENTS 14020 140220 STATIONS, STOPS, TERMINALS, INTERMODAL 14030 140330 SUPPORT FACILITIES, YARDS, SHOPS, ADMIN. BLDGS. #DIV/0! 0 0 0 0 0 0 0 14040 140440 SITEWORK & SPECIAL CONDITIONS 50.00% 14,002 14,002 28,004 0 14,002 14,002 28,004 14050 140550 SYSTEMS 50.00% 11,338 11,338 22,675 0 11,338 11,338 22,675 14060 140660 ROW, LAND, EXISTING IMPROVEMENTS 50.00% 601 601 1,201 0 601 601 1,201 50.00% 20,443 20,443 40,887 0 20,443 20,443 40,887 14070 VEHICLES 7 13.13.20 Light Rail Cars 13.__.__ 14080 140880 PROFESSIONAL SERVICES 50.00% 11,782 11,782 23,564 0 11,782 11,782 23,564 14090 140990 UNALLOCATED CONTINGENCY 50.00% 5,541 5,541 11,083 0 5,541 5,541 11,083 14100 141010 FINANCE CHARGES #DIV/0! 0 0 0 0 0 0 0 50.00% 75,000 75,000 150,000 0 75,000 75,000 150,000 Total Project Cost (10 - 100) 0 0