III Estimate Submission

advertisement
Code
00
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
16
Division Name
Bidding Requirements
General Requirements
Administrative Expenses
Temporary Construction
General Operations
Site Work
Concrete (including foundations)
Slab on Grade
Slab on Deck
Rebar
Masonry
Metals
Steel Columns
Steel Beams and Bracing
Steel Deck
Wood & Plastics
Thermal & Moisture Protection
Doors & Windows
Finishes
Specialties
Equipment
Furnishings
Special Construction
Conveying Systems
Mechanical
Electrical
Bonds
Insurance
Taxes
Fee
Estimate Summary
Detailed Cost Percentage
Sq Ft Cost
Projected Cost
7.41%
4.33%
$24.86
$14.53
$6,432,740.00
$3,759,541.00
3.80%
11.09%
$37.19
$3,298,679.00
$9,621,916.00
1.10%
8.87%
$3.69
$29.76
$954,988.00
$7,699,300.00
3.80%
2.46%
3.19%
7.60%
0.46%
2.60%
0.25%
0.79%
0.96%
29.21%
12.08%
$12.73
$8.26
$10.71
$25.51
$1.54
$8.71
$0.84
$2.66
$3.22
$97.99
$40.53
Total Cost
$3,294,603.00
$2,137,232.00
$2,770,080.00
$6,600,315.00
$397,689.00
$2,252,726.00
$218,088.00
$689,233.00
$833,002.00
$25,354,522.00
$10,486,025.00
$86,800,679.00
$1,041,608.15
$520,804.07
$5,208,040.74
$2,170,016.98
$1,422,365.00
$519,662.00
$1,817,514.00
MACH 5
Estimate Summary
AE 472
$737,600.00
$617,400.00
$443,200.00
$1,826,000.00
$5,121,300.00
$752,000.00
1.20%
0.60%
6.00%
2.50%
Total Including bonds,
insurance, taxes and fee
$95,741,148.94
The estimate of the general conditions includes the cost of the project administration,
project equipment, temporary construction and general operations. The administration costs are
broken down into management and supervision, engineering and safety, and office to monitor
and manage the design and construction. The project equipment includes the cost of purchases,
transportation and other miscellaneous expenses. The estimate for temporary construction
includes buildings, utilities, facilities, and protection. Finally, the general operation costs include
permits, bonds, utilities, security, testing, and cleanup.
Structural System
To develop the most accurate take off quantities the provided plans were modeled by MACH 5
Modeling Department using Revit. Given the complexity of the structural system modeling the
structure in 3D is the best method to perform accurate estimations. Using the Revit database of
information a schedule of beams and columns was automatically created. These schedules were
used in conjunction with RS Means to calculate the structural system cost.
III.A.1 | P a g e
Estimate Submission
General Conditions
Time Dependent Durations
Construction on the Material & Life Science Building II is set to begin on October 1, 2008 and
complete by August 1, 2010. The construction schedule is 22 months long or approximately 96
weeks. These durations were used in many of the time dependent line items. The estimated
preconstruction duration is approximately 5.5 months therefore the total preconstruction and
construction duration is 27.5 months. The following chart shows the administrative personnel
and their contributions to this project.
Project Staff
% on Precon
% on Construction
Total % on Job
Resulting Weeks
Project Manager
100
50
60
57.6
Assistant Project Manager
100
50
60
57.6
Superintendent
25
100
85
81.6
Assistant Superintendent
25
100
85
81.6
Assistant Superintendent
25
100
85
81.6
Field Survey/Engineer
25
100
85
81.6
Project Engineer
75
50
55
52.8
Office Engineer
75
50
55
52.8
Field Engineer
25
50
45
43.2
Office Manager
25
50
45
43.2
Timekeeper
25
50
45
43.2
Secretary
25
50
45
43.2
MACH 5
General Conditions
AE 472
The durations for the schedule have been calculated using RS Means Cost Data in conjunction
with industry experienced assumptions. The quantity of material was measured from the
provided building documentation and used with the daily outputs from RS Means Cost Data to
calculate the number of days to complete a task. These calculations can be found in Appendix
A. There will be a significant amount of time dedicated towards the foundation of the building,
approximately 170 days, including excavation, piling and concrete work. However the single
largest amount of time will be taken to install MEP. Finally, the schedule shows the project
completion on July 29.
III.B.2 | P a g e
Estimate Submission
CPM Schedule
GENERAL CONDITIONS
PROJECT: Material & Life Sciences II
OWNER: Chris Magent
Administrative Expense Totals
Labor
Unit Price Burden
Unit
57.6
57.6
81.6
81.6
81.6
81.6
wks
wks
wks
wks
wks
wks
$2,100
$1,600
$1,950
$1,550
$1,550
$1,125
$120,960
$92,160
$159,120
$126,480
$126,480
$91,800
$
$
$
$
$
$
120,960
92,160
159,120
126,480
126,480
91,800
52.8
52.8
43.2
wks
wks
wks
$1,750
$1,300
$1,125
$92,400
$68,640
$48,600
$
$
$
92,400
68,640
48,600
job
job
CSF
job
0.04%
0.04%
$15
job
0.04%
43.2
43.2
43.2
wks
wks
wks
$1,750
$1,005
$365
22
22
month
month
$110
$210
22
22
job
month
month
2587.4
Cost
Material
Unit Price Cost
Qty
0.18%
Total Cost
$ 32,800
$ 32,800
$ 38,811
$ 147,600
$
32,800
$75,600
$43,416
$15,768
$
$
$
75,600
43,416
15,768
$2,420
$4,620
$
$
2,420
4,620
$
$21,450 $
$31,240 $
16,400
21,450
31,240
0.02%
$975
$1,420
$ 1,422,365
III.B.3 | P a g e
Estimate Submission
Code
Description
Administrative Expense
MANAGEMENT & SUPERVISION
1001
Project Manager
1002
Assistant Project Manager
1003
Project Superintendent
1004
Assistant Superintendent
1005
Assistant Superintendent
1006
Field Survey/Engineer
ENGINEERING & SAFETY
1101
Project Engineer
1102
Office Engineer
1103
Field Engineer
1104
Form Detailing
1105
Plan & Schedule
1106
Quality Control
1107
Professional Surveying
1108
Blue Printing
1109
Engineering Equipment
1110
Safety
OFFICE
1201
Office Manager
1202
Timekeeper
1203
Secretarial
1204
Warehousing
1205
Rent
1206
Office Utilities
1207
Job Telephone/Fax
1208
Set up Telephones
1209
Postage
1210
Office Supplies
1211
Furniture & Equipment
1212
Custodial Expense
1213
Public Relations
1214
Travel Expense
1215
Supvisory Subsistence
MACH 5
General Conditions
AE 472
Temporary Construction Totals
22
month
x3
96
SF
$3.91
22
150
3
month
mile
each
$4.50
$1,050
x2
x2
x3
$751
$330
$21,780 $
21,780
$95
$18,240 $
18,991
$76
$3,344
$
$
$
$2.63
$6,805
$ 33,584
$ 162,230
$2,025
$3,150
$26,780
22 mnth $162,230
3,344
2,025
3,150
2587.4
CSF flr
2587.4 CSF flr/mnth
$10.35
$2.85
2587.4
CSF flr
$3.04
$7,866
$10.35
$26,780 $
690
SY
$5.13
$3,540
$2.14
$1,477
100
90
LF
wk
$23.50
$4,700
$44
$1,160
2240
225
LF
SF
$1.61
$3,606
$1.97
$17.90
$4,413
$4,028
$
$
8,019
4,028
10
each
$55
$550
$
550
x2
x2
$
34,645
5,016
$8,800 $ 13,500
$208,800 $ 208,800
$ 519,662
Estimate Submission
Temporary Construction
BUILDINGS
3001
Job Office
3002
Owner/Arch Office
3003
Dry Shacks
3004
Warehouse
3005
Tool Shed
3006
Trailer Transportation
3007
Trailer Setup
3008
Saw Line
INSTALL UTILITIES
3101
Water System
3102
Temp. Power Hookup & Dist.
3103
Temporary Lighting
3104
Install Heating System
3105
Operate Heating System
3106
Telephone/Telex Setup
3107
Job Communications System
SITE FACILITIES
3201
Temporary Roads
3202
Parking
3203
Jobsite Bus
3204
Precast/Panel Yard
3205
Rubbish Chute
3206
Dumpster
3207
Stairs & Ladders
3208
Project Sign
3209
Layout & Batterboard
PROTECTION
3301
Fences
3302
Signs & Barricades
3303
Covered Walks
3304
Temporary Handrails
3305
Fire Protection
3306
Temporary Partitions
MACH 5
General Conditions
AE 472
III.B.4 | P a g e
job
0.50%
$ 410,000
6%
job
1%
$ 820,000
job
0.30%
$ 246,000
22
month
$110
$2,420
$
2,420
22
month
$62
$1,364
$
1,364
22
month
$
15,840
20
day
LS
$
$
4,900
14,818
22
months
258.74
258.74
MSF
MSF
job
$34
$47
0.02%
258.74
MSF
26
2587.4
ton
CSF
x9
$245
$80
$15,840
$4,900
$565
$12,430
$
12,430
$8,797
$12,161
$4.50
$6.61
$1,164
$1,710
$
$
$
9,961
13,871
16,400
$97
$25,098
$3.38
$875
$
25,972
$90
x 90 wks $210,600
$5
$ 210,600
$12,937 $ 12,937
General Operations Totals
Subtotal
$ 1,817,514
$ 3,759,541
General Conditions Total
$ 3,759,541
*NOTES
MSF = thousand square feet
CSF = hundred square feet
SF = square feet
LF = linear feet
SY = square yards
LS = lump sum
III.B.5 | P a g e
Estimate Submission
General Operations
PERMITS LICENSES & TAXES
4001
Building Permit
4002
City Business Tax
4003
State Excise Tax
4004
Sales Tax
4005
Street Use Permit
BOND INSURANCE
4101
Performance Bond
4102
Bond Premium
4103
Broad Form Insurance
4104
Earthquake & Floods Ins.
4105
Liability Insurance
UTILITIES
4201
Operate & Maintain Electrical
4202
Power Bills
4203
Electrical Supplies
4204
Water Bills
4205
Drinking Water
4206
Chemical Toilet
SECURITY & PROTECTION
4301
Security
4302
Flaggers
MAINTAIN FACILITIES
4401
Buildings
4402
Roads
TESTING & INSPECTION
4501
Inspector
4502
Testing
4503
Mockups
4504
Samples
4505
Job Photos
4506
Onsite Video Camera
CLEANUP
4601
Rubbish Removal
4602
Periodic Cleanup
4603
Final Cleanup
4604
Punchlist & Warranty
4605
Clean Streets
4606
Glass Cleaning
4607
Damage Repair
OTHER
4701
Hauling & Freight
4702
Trash Hauling
4703
Environmental Mitigation
4704
Hazardous Material Disposal
MACH 5
General Conditions
AE 472
MACH 5 decided that building a detailed Revit model would be a good approach to get accurate
quantity take offs. (Detailed quantity take off sheets are available upon request to MACH 5). RS
Means Cost Data was used to gather prices for all of the quantities. During this process many
assumptions were made because of the lack of depth in RS Means. These assumptions are noted
in the tables below. The overall price of the super structure of the building is $8,309,800.
Estimate Summary:
Structural Steel Members
Floor and Roof Decking
Concrete Slab on Deck
Concrete Slab on Grade
Reinforced Wire Mesh
Quantity
3103 Pieces and 2803 Tons
159,661 sq ft
5468.5 CY
5,157 CY
312.31 Tons
Cost
$6,954,743
$752,003
$616,421
$737,639.9
$443,229
MACH 5
General Conditions
AE 472
Steel Column Estimate
Total
Length
(decimal)
Quantity
$/ft
Cost
Tonnage
W10X49
17
410.00
$
54.19
$
22,217.90
10.05
W14X43
17
306.00
$
49.88
$
15,263.28
6.58
W14X53
2
54.00
$
61.48
$
3,319.92
1.43
W14X61
163
3,826.00
$
70.76
$
270,727.76
116.69
W14X68
74
1,107.50
$
78.88
$
87,359.60
37.66
W14X74
23
632.00
$
87.37
$
55,217.84
23.38
W14X82
28
718.00
$
95.12
$
68,296.16
29.44
W14X90
160
3,022.00
$
104.40
$
315,496.80
135.99
W14X99
16
210.00
$
114.84
$
24,116.40
10.40
W14X109
8
188.00
$
126.44
$
23,770.72
10.25
W14X120
10
240.00
$
138.96
$
33,350.40
14.40
W14X145
8
136.00
$
168.20
$
22,875.20
9.86
W14X159
10
200.00
$
184.44
$
36,888.00
15.90
W14X176
8
152.00
$
202.18
$
30,731.36
13.38
W14X193
9
156.00
$
223.88
$
34,925.28
15.05
W14X211
5
100.00
$
244.76
$
24,476.00
10.55
W14X257
2
80.00
$
298.12
$
23,849.60
10.28
W14X283
72
1,352.00
$
328.28
$
443,834.56
191.31
W14X311
4
80.00
$
360.76
$
28,860.80
12.44
W14X370
8
144.00
$
429.20
$
61,804.80
26.64
W14X550
16
312.00
$
638.00
$
199,056.00
70.98
TOTAL
TOTAL
1,826,438.38
772.64
TOTAL
660
$
III.B.6 | P a g e
Estimate Submission
Member
Size
Member
Size
Quantity
W8X10
6
W10X49
60
W14X22
89
W14X43
2
W14X68
38
W14X74
Total
Length
(english)
65' - 10 3/32"
Total
Length
(decimal)
Unit Cost
$/ft
Cost
Tonnage
65.84
$
17.65
$
1164' - 10 21/32"
1,164.89
$
62.42
$
72,712.43
28.54
1549' - 10 7/8"
1,549.91
$
33.34
$
51,674.00
17.05
49.41
$
53.20
$
2,628.61
1.06
964' - 10 13/32"
964.87
$
76.63
$
73,937.99
32.81
10
106' - 0 25/32"
106.07
$
88.51
$
9,388.26
3.92
W14X90
50
1255' - 2 23/32"
1,255.23
$
106.14
$
133,230.11
56.49
W14X99
2
<
58' - 6 7/32"
58.52
$
106.14
$
6,211.31
2.90
W14X109
6
^
171' - 11 29/32"
171.99
$
140.29
$
24,128.48
9.37
W14X145
36
*
1318' - 0 31/32"
1,318.08
$
171.10
$
225,523.49
95.56
W14X159
7
*
263' - 8 21/32"
263.72
$
187.62
$
49,479.15
20.97
W14X176
6
*
170' - 7 9/32"
170.61
$
207.68
$
35,432.28
15.01
W14X193
40
*
1133' - 3 11/32"
1,133.28
$
227.74
$
258,093.19
109.36
W14X211
115
*
2541' - 11 3/8"
2,541.95
$
248.98
$
632,894.71
268.18
W14X233
3
*
84' - 10 25/32"
84.90
$
274.94
$
23,342.41
9.89
W14X257
24
*
1128' - 0"
1,128.00
$
303.26
$
342,077.28
144.95
W14X283
22
*
498' - 7 17/32"
498.63
$
333.94
$
166,512.50
70.56
W14X370
6
*
137' - 5 5/32"
137.43
$
436.60
$
60,001.94
25.42
W14X398
14
*
322' - 1 5/32"
322.10
$
469.64
$
151,271.04
64.10
W14X426
4
*
86' - 10 1/4"
86.85
$
502.68
$
43,657.76
18.50
W14X455
5
*
144' - 5 19/32"
144.47
$
536.90
$
77,565.94
32.87
W16X26
29
638' - 0"
638.00
$
33.34
$
21,270.92
8.29
W16x31
37
814' - 0"
814.00
$
39.23
$
31,933.22
12.62
W16X36
10
227' - 4 31/32"
227.42
$
42.49
$
9,663.08
4.09
W18X35
21
422' - 1 9/16"
422.13
$
44.63
$
18,839.66
7.39
W18X40
80
1759' - 10 15/32"
1,759.87
$
50.13
$
88,222.28
35.20
W18X71
1
22' - 0"
22.00
$
90.98
$
2,001.56
0.78
W18X76
30
660' - 0"
660.00
$
90.98
$
60,046.80
25.08
W21X44
716
15608' - 9 1/8"
15,608.76
$
54.13
$
844,902.18
343.39
W21X50
52
1143' - 1 11/16"
1,143.14
$
61.13
$
69,880.15
28.58
W21X68
78
1669' - 0 1/16"
1,669.01
$
81.25
$
135,607.06
56.75
W24X55
403
8830' - 4 1/8"
8,830.34
$
66.44
$
586,687.79
242.83
W24X62
8
440' - 4 17/32"
440.38
$
74.44
$
32,781.89
13.65
W24X68
45
970' - 3 21/32"
970.30
$
80.94
$
78,536.08
32.99
W24X76
43
946' - 0 7/32"
946.02
$
89.94
$
85,085.04
35.95
'
49' - 4 15/16"
1,162.08
0.33
III.B.7 | P a g e
Estimate Submission
Steel Beams and Bracing Estimate
MACH 5
General Conditions
AE 472
W24X84
74
W24X162
4
W27X84
20
W30X90
1,638.48
$
99.07
$
162,324.21
68.82
88.00
$
198.14
$
17,436.32
7.13
466' - 7 23/32"
466.64
$
98.65
$
46,034.04
19.60
6
203' - 10 15/32"
203.87
$
116.16
$
23,681.54
9.17
W36X150
3
93' - 4 1/16"
93.34
$
173.21
$
16,167.42
7.00
W40X149
10
219.40
$
173.21
$
38,002.27
16.35
W40X167
4
88' - 0"
88.00
$
196.29
$
17,273.52
7.35
W44X230
8
176' - 0"
176.00
$
263.29
$
46,339.04
20.24
Special Shapes ~
1638' - 5 25/32"
-
@
88' - 0"
219' - 4 25/32"
MACH 5
General Conditions
AE 472
$/each
HSS10X8X.250
72
$ 1,179.00
$
84,888.00
-
HSS10X8X.3125
2
$ 1,179.00
$
2,358.00
-
HSS12X3X.250
7
$ 1,179.00
$
8,253.00
-
HSS12X6X.500
55
$ 1,179.00
$
64,845.00
-
HSS12X8X.250
2
$ 1,179.00
$
2,358.00
-
HSS12X8X.375
18
$ 1,179.00
$
21,222.00
-
HSS12X8X.500
52
$ 1,179.00
$
61,308.00
-
HSS12X8X.625
2
$ 1,179.00
$
2,358.00
-
HSS12X8X.3125
6
$ 1,179.00
$
7,074.00
-
TOTAL
TOTAL
TOTAL
2443
$5,128,305.03
2,031.07
NOTES:
assume 14x26
assumed 14x90
assume 14X120
assume avg ratio of cost to weight to be 1.18
assume its 2x cost of W24X84
assumed closest W36size
no data for HSS shapes => assume HS12x8x.5x16
Estimate Submission
'
<
^
*
@
~
III.B.8 | P a g e
$
$/Ton
$
Rebar
Weight
Tons
Total
Rebar Cost
Rebar
Price
$/SQ
FT
$
Total
Concrete
Cost
Concrete
Price
Total Deck
Cost
Decking
Price
Volume
$/ Sq
ft
(Revit)
Rebar
Code
Area
Assembly
Floor Assembly Estimate
lb/s
q ft
S1
40,956
1169.26
$4.71
$192,902.76
$2.74
$112,219.44
30.80
$1,405.00
$43,272.47
1.50
S2
58,631
2352.48
$4.71
$276,152.01
$5.01
$293,741.31
39.17
$1,405.00
$55,027.54
1.34
S3
60,074
1946.83
$4.71
$282,948.54
$3.52
$211,460.48
20.69
$1,405.00
$29,069.57
0.69
$617,421.23
90.65
$453,954.98
124.59
$1,425.00
$752,003.31
$127,369.58
159,661
5468.57
Slab 1
165,677
3068.09
-
-
$2.74
Slab 2
5,949
146.9
-
-
$3.52
$20,940.48
6.20
Slab 3
30,136
1116.15
-
-
$5.01
$150,981.36
45.26
Slab 4
11,154
826.19
-
-
$10.02
$111,763.08
45.60
$1,425.00
$737,639.90
221.66
$315,859.42
$1,355,061.13
312.31
$443,229.00
212,916
TOTAL
5157.33
$752,003.31
MACH 5
General Conditions
AE 472
$177,539.47
1.50
$1,425.00
$8,841.85
2.09
$1,425.00
$64,501.59
3.00
$64,976.51
8.18
Estimate Submission
Examples of How Revit was Used for Take Offs
Floor Assemblies from Revit
III.B.9 | P a g e
MACH 5
General Conditions
Example of Detail Level in Revit Model
(includes Bracing and Beams all to proper AISC sizes and standards)
Estimate Submission
AE 472
Structural Column, Beams, and Bracing Above Grade from Revit
III.B.10 | P a g e
MACH 5
General Conditions
Estimate Submission
AE 472
Example of Take-Off of Steel Beams From Revit
III.B.11 | P a g e
Download