Pankaj Kumar

advertisement
Oil and Gas
PANKAJ KUMAR
MOBILE NO: +91-8870467394
E-MAIL ID: pankajkumar_18@yahoo.com
Summary
13 Years of experience in Oil and Gas, 4 years in India and 9 Years in Middle-East
and North African countries. In refinery, NGL, Gas Treatment Plants, Oil Processing
Plant, Gas and Oil Gathering Stations, Well heads. Project Type - Major Turn Around,
Shut Down, Grass Root Projects. Worked in Iran, Qatar, Kuwait, Egypt, Tunisia, Syria,
Algeria, and U.A.E. Worked with EPC Company, Petrofac. Worked with Clients viz,
Total, Qatar Petroleum, Kuwait Oil Company, Apache, British Gas, Petro- Canada,
Anadarko Sonatrach, Cairns India, Shell. B.E. Mechanical, Degree Certificate is
attested by Indian Foreign Ministry and Qatar Embassy.
WORK EXPERIENCE:
 Company: QCON-Shell, Pearl-GTL, Major Turn Around, Qatar
Post
Piping Engineer
Tenure
January 2014 – June 2014
Project
Major Turn Around
Client
Shell, Pearl-GTL
JOB RESPONSIBLITIES:
Responsible for Piping Related Tie-Ins Work Packs
Review of Tie-In Work Packs
a) Assisting Planning Team in Preparing Work Packs.
b) Reviewing of Work Packs.
c) Coordinating with other disciplines and client for resolving engineering
queries, pertaining to Work Packs.
d) Assisting execution team in the execution and providing them technical
assistance.
 Company: Cairn Energy India Limited, Barmer, Brown root
Post
Construction Superintendent- Piping
PANKAJ KUMAR_CV
Page 1 of 9
Oil and Gas
Tenure
May 2012 – October 2013
Project
Mangala Associated Facility Projects
Client
Cairn Energy India Limited
JOB RESPONSIBLITIES:
Responsible for Piping, Structural and Mechanical
e) Coordinating and follow up with supervisors, for piping, structural and
mechanical jobs.
f) Coordinating with other disciplines for inter disciplinary jobs.
g) Coordinating with the safety, for all the works in live area requiring
work permits.
h) Coordinating and follow up with subcontractors.
i) Coordinating with field engineering for Technical Queries related to
drawings, materials, concession request, field issues, etc.
 Company: Petrofac International Limited, Algeria, Grass root,
Post
Field Engineer- Piping
Tenure
January 2010 – APRIL 2012
Project
“Central Processing Facility Lot 1 & 7”
Client
Anadarko & Sonatrach JV
$2.3 Billion
JOB RESPONSIBLITIES:
Responsible for, Under Ground Piping and Above Ground Piping
a) Supervising the fabrication of piping spools for underground piping.
b) Coordinating with civil discipline regarding excavation, access and
trench clearance.
c) Coordinating with the safety discipline for raising the work permit for
the UG piping installation.
d) Supervision of the installation of underground piping.
e) Coordinating with field engineering for Technical Queries related to
drawings, material, procedures, concession request, field issues.
f) Mechanical clearance of the underground piping from QC & Client.
g) Punching and punch list clearance prior to hydro testing.
PANKAJ KUMAR_CV
Page 2 of 9
Oil and Gas
h) Supervision of the installation of aboveground piping.
i) Piping spools and piping component issuance.
j) Continual supervision during the spools erection for correct spool
erection, erection sequence followed, verticality, level or slope(if
mentioned), during erection line is supported, correct item tag erection
material are used(valves, gaskets, stud-bolts), correct primary and
secondary supports are installed.
k) Follow-up with the other discipline(mechanical, tank, ug piping for
inter discipline release note prior piping installation.
l) Supervision of the fabrication of the piping spools at site.
m) Punching and punch list clearance prior to hydro testing for test
package clearance.
n) Follow-up with the sub contractor for the ndt clearance of the test
packages.
o) Daily reporting to my supervisor for daily progress, i.e., construction
manager.
 Company: Petrofac International Limited, Syria,Grass root, $450 million
Post
Field Engineer- Mechanical & Piping
Tenure
May 2009 – November 2009
Project
“Ebla Gas Project GTP, GGS & Well- heads”
Client
Petro Canada
JOB RESPONSIBLITIES:
Responsible for, Unit Piping in the Gathering Center
a) Supervision of the AG piping installation.
b) Continual supervision during the spools erection for correct spool
erection, erection sequence followed, verticality, level or slope , during
erection line is properly supported and secured by temporary supports,
as per iso., erection material are used(valves, gaskets, stud-bolts),
correct primary and secondary supports are installed.
c) Follow-up with the other discipline (civil, mechanical and tanks for
inter discipline release note prior piping installation.
d) Punching and punch list clearance prior to hydro testing for test
package clearance.
e) Follow-up with the sub-contractor for the NDT clearance of the test
packages.
PANKAJ KUMAR_CV
Page 3 of 9
Oil and Gas
f) Hydro testing.
g) Daily reporting to my supervisor for daily progress, i.e., construction
manager.
 Company: Petrofac International Limited, TUNISSIA, Grass root,
Post
Field Engineer- Mechanical & Piping
Tenure
Feb 2009 – April 2009
Project
“Hasdrubal Gas Plant”
Client
British Gas(BG)
$400 million
JOB RESPONSIBLITIES:
Responsible for Mechanical Completion (Piping) Of Gas Conditioning System
a) Punching and punch list clearance of the test packages of the subsystem.
b) Re-instatement of the test packages.
c) Mechanical Completion of the Subsystems (Piping).
d) Daily reporting to my supervisor for daily progress, i.e., construction
manager.

Company: Petrofac International Limited, Egypt, Grass root, $450 million
Post
Field Engineer- Mechanical & Piping
Tenure
June 2008 – Feb 2009
Project
“Salaam Gas Plant, Train-3 & 4 ”
Client
Apache
JOB RESPONSIBLITIES:
Responsible for, Unit Piping
a) Supervision of the installation of aboveground piping.
b) Piping spools and piping component issuance.
c) Continual supervision during the spools erection for correct spool
erection, erection sequence followed, verticality, level or slope(if
mentioned), during erection line is supported, correct item tag erection
PANKAJ KUMAR_CV
Page 4 of 9
Oil and Gas
d)
e)
f)
g)
h)
i)
j)
material are used(valves, gaskets, stud-bolts), correct primary and
secondary supports are installed.
Follow-up with the other discipline (mechanical, tank, ug piping for
inter discipline release note prior piping installation.
Supervision of the fabrication of the piping spools at site.
Preparation of the Hydro Test package.
Punching and punch list clearance prior to hydro testing for test
package clearance.
Follow-up with the sub contractor for the NDT clearance of the test
packages.
Hydro testing.
Daily reporting to my supervisor for daily progress, i.e., construction
manager.
 Company: Petrofac International Ltd., Kuwait, Brown root, $800 million
Post
Field Engineer- Mechanical & Piping
Tenure
August 2006 – March 15, 2007
Project
“Facility Upgrade & Relocation of Underground Process Piping for GC’s & BS’s”
Client
Kuwait Oil Company
JOB RESPONSIBLITIES:
Responsible for, Unit Piping in the Gathering Center – 6 (GC-06).
k) Coordinating with the client and the sub-contractor for daily site
activities.
l) Preparation of the list of material required for the execution of the
available job-front. Co-ordination with the material department for the
issuance of the material.
m) Preparing the list of priority spools and coordinating the same with
fabrication shop, for the prioritized spool fabrication.
n) Follow-up, QA/QC department for the NDT clearance and releasing of
spools.
o) Conducting Daily Tool Box talk and coordinating with our HSE team,
regarding safety issues and Daily Work Permits.
p) Participating in weekly meeting with AMEC and KOC for the release of
flow lines and tanks for the shutdown purpose.
q) Daily reporting to my supervisor for daily progress, i.e., construction
manager.
PANKAJ KUMAR_CV
Page 5 of 9
Oil and Gas
 Company: Petrofac Intenational Limited, Qatar, Brown Root, $450 million
Post
Field Engineer – Piping
Tenure
May 2005 – June 2006
Project
“Rag and Flare Mitigation Integrated Project”,NGL-1/2/3/4
Client
Qatar Petroleum (QP), Qatar
JOB RESPONSIBLITIES:
Responsible for the Unit Piping in the Off-Spec Drum Unit.
a) Mechanical Completion Dossier
i.
Preparation of Dossier files, for all the Sub-systems based on
priority given by our commissioning team.
ii.
Compilation of files based on approved ITP accepted by client.
iii.
Coordinating with all discipline’s engineers and superintendents for
the required certificates.
iv. Coordinating with client for updating the progress.
v.
After the System is ready for handover, final walk through the
system, with the concern discipline’s head and client.
vi. Coordinating with all the discipline’s head for attending all the (A)
punch list before the final submission of the dossiers.
vii.
Submission of the dossiers with number of copies as per the
contract, to the client’s document controller.
viii.
If client have any comments, incorporating the same and resubmit
the dossier.
b) Shutdown Dossiers for the four shutdowns (NGL-1, 2, 3 & 4).
i.
Preparation and compilation of the Pre-shutdown technical
documents.
ii.
Submission of the dossier prior to the shutdowns to the client and
incorporating comments, if any.
c) Daily progress reporting to my supervisor, i.e., superintendent.
 Company: Petrofac International Limited, Iran & UAE, Grass Root, $500 million
Post
Field Engineer- Piping
Tenure
Dec 2003 – April 2005
Project
“Darood Project Onshore Facility and New Plant”, Kharg, Iran
PANKAJ KUMAR_CV
Page 6 of 9
Oil and Gas
Client
Total Elf Fina
JOB RESPONSIBLITIES:
Responsible for the Unit Piping in the Oil Processing Unit.
a)
b)
c)
d)
Punching and punch list clearance for the test packages.
Hydro testing.
Re-instatement.
Coordinating with the vendors for the valve repair and Nitrogen-Helium
Leak Test.
e) Punch list coordination for mechanical and piping disciplines.
f) Providing mechanical assistance to our commissioning team, i.e., nitrogenhelium leak- testing.
g) Daily Progress reporting my supervisor, i.e., Superintendent.
 Company: Punj Lloyd Ltd. and Petrofac Int. Ltd.(JV), Chennai, India, Brown
Root, $180 million
Post
Mechanical Engineer
Tenure
Nov 2002 – Nov 2003
Project
“SRU and VBU- Refinery III Expansion Project”, CPCL, Chennai, India
Client
Engineers India Limited (EIL)
JOB RESPONSIBLITIES:
a) Responsible for AG piping in Sour Water Stripper Unit.
b) A-Punch points clearance prior to hydro testing.
 Company: M/s. Bridge & Roof Co. Ltd., Chennai, India (Govt. of India), Grass Root,
$50 million
Post
Trainee Engineer
Tenure
June 2001 – October 2002
Project
“CDU-Refinery Expansion-III Project”, MRL, Chennai, India
Client
Engineers India Limited (EIL)
PANKAJ KUMAR_CV
Page 7 of 9
Oil and Gas
JOB RESPONSIBILITIES:
a) Responsible for the steel structure, fabrication and erection.
b) Responsible for the fabrication and installation of the Under-ground piping.
 PERSONAL DETAILS:
D.O.B.
SEX
MARITAL STATUS
LANGUAGE KNOWN
PASSPORT NO.
15/06/1980
Male
Married
English, Hindi, Tamil, Persian, Arabic
L3790118 Exp. Year. 2023
 ACADEMIC QUALIFICATION:
Bachelor of Engineering (Degree -Mechanical Engineering)
CERTIFICATE ISSUED
YEAR OF
COMPLETION
UNIVERSITY /
SCHOOL
CLASS
I
I
Bachelor of Engineering (B.E) –
Mechanical
Higher Secondary (+2)
2001
1997
University of
Madras
AGJ HSc. School
State Board of Matriculation(10th)
1995
IG Anglo School
I
Degree Certificate is attested by Indian Foreign Ministry and Qatar Embassy.
Date:
PANKAJ KUMAR_CV
Signature:
Page 8 of 9
Oil and Gas
(Pankaj Kumar)
PANKAJ KUMAR_CV
Page 9 of 9
Download