-1- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 NORTHERN TERRITORY DEPARTMENT OF MINES AND ENERGY MINING MANAGEMENT PLAN (MMP) STRUCTURE GUIDE FOR EXTRACTIVE OPERATIONS ADVISORY NOTE INSTRUCTIONS ON THE USE OF THIS DOCUMENT An Authorisation for Extractive Activities can only be issued on the completion and acceptance of a MMP. An MMP is required for new projects, when operations change significantly from the previous plan or on an annual report basis for each active Extractive Area. This Advisory Note contains instructions and some examples of environmental management issues for consideration in the preparation of an MMP. Each section contains examples of issues which may be relevant to an extractive operation. The operator should assess which are relevant to their site, or whether other factors need consideration, but are not listed here. The commitments to continuous improvement should have a defined objective and completion date placed on them so that there is a measurable time frame. An Extractive Operations MMP Template is available, if required, on the department’s website at: www.minerals.nt.gov.au/mineralsforms#mining THIS ADVISORY NOTE AND PLAN IS NOT TO BE TAKEN AS A DEFINITIVE RESPONSE TO THE DEPARTMENTS REPORTING REQUIREMENTS BUT SHOULD BE UTILISED BY OPERATORS AS A BASIS TO THE DEVELOPMENT OF A PROJECT-SPECIFIC MINING MANAGEMENT PLAN (MMP) THAT INCORPORATES A PROGRAM OF CONTINUOUS IMPROVEMENT. Page 1 of 19 -2- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 CONTENTS AMENDMENTS 1.0 OPERATOR DETAILS 1.1 ORGANISATIONAL STRUCTURE / CHART 1.2 WORKFORCE 2.0 PROJECT DETAILS 2.1 MAP OF SITE LOCATION AND LAYOUT 2.2 HISTORY OF DEVELOPMENT AND CURRENT STATUS 2.3 PROPOSED ACTIVITIES 2.4 OTHER RELEVANT INFORMATION 3.0 CURRENT PROJECT SITE CONDITIONS 4.0 ENVIRONMENTAL MANAGEMENT SYSTEM / PLAN 4.1 ENVIRONMENTAL POLICY AND RESPONSIBILITIES 4.2 LEGAL AND OTHER REQUIREMENTS 4.3 OBJECTIVES AND TARGETS 4.4 IDENTIFICATION OF ENVIRONMENTAL ASPECTS AND IMPACTS 4.5 MANAGEMENT OF IDENTIFIED ENVIRONMENTAL IMPACTS 4.6 INDUCTION AND TRAINING 4.7 IDENTIFIED STAKEHOLDERS AND CONSULTATION 4.8 EMERGENCY PROCEDURES AND INCIDENT REPORTING 4.9 ENVIRONMENTAL AUDITS AND INSPECTIONS 4.10 DOCUMENTATION 4.11 ENVIRONMENTAL PERFORMANCE REPORTING 5.0 REHABILITATION AND CLOSURE PLAN 5.1 STATUS OF CURRENT REHABILITATION 5.2 COSTING OF CLOSURE ACTIVITIES 6.0 PERFORMANCE OBJECTIVES APPENDICES Attachment A – EXAMPLE SITE LAYOUT MAP Attachment B – EXAMPLE SITE LOCATION MAP Attachment C – GLOSSARY OF TERMS 3 4 4 4 5 5 5 6 6 7 8 8 8 9 9 11 12 12 12 12 12 13 14 15 15 15 16 17 18 18 Page 2 of 19 -3- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 AMENDMENTS As per Section 41(2) of the Mining Management Act, an MMP reviewed and amended under Section 41(1)(a) is to clearly identify amendments made. These changes can be outlined in a table, as per the example below. Table 1. Example of amendments made. Section Section 1.1 – Organisational Structure / Chart Section 2.0 - Project Details Section 4.6 – Identification of Environmental Aspects and Impacts Amendment Change in organisational structure. Additional title to be included in Authorisation. A new potential impact identified, as a result of change in procedure/process. Page 3 of 19 -4- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 1.0 OPERATOR DETAILS This section should provide operator details including: Name of operator or company (as per Australian Securities and Investment Commission (ASIC) if applicable) Key contacts (i.e. senior on site personnel, site manager) Postal and street address Phone/fax/email contact details 1.1 ORGANISATIONAL STRUCTURE / CHART This section should include an organisational structure chart or particulars of the organisations structure, as per Section 40(e) of the Mining Management Act. See example below. Site Manager Plant Operator Health, Safety & Environmental Officer Contractors Figure 1. Sample organisational chart. 1.2 WORKFORCE The following information should be provided: Number in workforce Number of contractors Any relevant socio-economic aspects e.g. source of labour, contractors/employees Work descriptions Page 4 of 19 -5- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 2.0 PROJECT DETAILS This section should provide details of the proposed extractive project including: Project name Location in context of distance to nearest town/major features/roads Mining interest/s (i.e. titles) Title holder/s NOTE: if operator is not the title holder, a Nomination of Operator form should be completed by the title holder, appointing the operator for the site – this is a requirement under section 10 of the Mining Management Act. 2.1 MAP OF SITE LOCATION AND LAYOUT Provide a legible and detailed site location map and site diagram with the following information: Lease boundaries Site access Tracks (including proposed tracks) Easements - above or below ground electrical cables, gas pipelines, water pipelines, telephone Existing topographic features Areas to be cleared Undisturbed areas/areas of existing vegetation Infrastructure (site office, workshops, plant) locations Drillhole/costean locations Pit locations Target areas Waterways Buffer zones Rehabilitated areas Sensitive areas Cultural/heritage zones (sacred sites) Hydrocarbon/hazardous chemical storage area/s NOTE: All maps must include a scale, date of drawing, orientation (i.e. North point), contours and be able to be overlaid on the previous site plan. 2.2 HISTORY OF DEVELOPMENT AND CURRENT STATUS The MMP is a backward and forward looking document for ongoing operations and should provide details of previous extractive activities carried out in the last twelve months under a current Authorisation. This information may be included in the form of a table and should include: Total amount extracted during the last twelve months Total amount proposed for extraction in the last MMP Total area cleared/disturbed during the last twelve months Total area proposed for clearing in the last MMP This section should also outline any previous site activities that are to be accounted for under the plan e.g. any previous mining/exploration or rehabilitation completed by previous operators. If Page 5 of 19 -6- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 known, a brief outline of any historical mining or exploration carried out in the area could also be provided here. A summary of the size and number of existing disturbances and site infrastructure should also be included to assist in the calculation of security (i.e. pit area (ha), stockpile areas (ha), fuel storage area (m²), area of haul roads (length x width), etc.) 2.3 PROPOSED ACTIVITIES This section must detail the proposed activities for the next twelve months. This may include, but is not limited to: Target material/material reserves Amount proposed for extraction Details of the extractive program (i.e. clearing, stripping, excavation) Methods to be used (e.g. screening, crushing, washing) Method of excavation/machinery to be used Size and number of disturbances (e.g. costeans, pits, stockpile areas, etc.) Depth of pits Details of exploration activities if applicable (i.e. drilling) Km of track clearing/construction Size of camp area required This information may be included in the form of a table. 2.4 OTHER RELEVANT INFORMATION This section should include any other information relevant to the operation that has not been included in this structure guide. For instance, refer to Attachment D (Site Specific Practices) of the Structure Guide. Page 6 of 19 -7- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 3.0 CURRENT PROJECT SITE CONDITIONS This information is requested to allow the Department to gain an understanding of the current site conditions and to accurately assess risks. Maps at appropriate scales may also be used to illustrate current site conditions. Information that should be provided here includes: Geology (i.e. outline of ore or material resource, soil description and geological characterisation of the area) Hydrology (i.e. surface water flows onto and out of the site area, surface and groundwater quality, groundwater occurrence locally, location of bores, and any present/planned uses or users of surface water and groundwater) Flora and fauna (i.e. identification of any rare and endangered species, description of any feral animals and weed species at the site, outline of flora and fauna native to the area, and any flora and fauna of cultural significance) Information may be sourced from the NT Department of Natural Resources, Environment, the Arts and Sport (NRETAS) (http://www.nt.gov.au/nreta/) and the Commonwealth Department of the Environment, Water, Heritage and the Arts, Environmental Reporting Tool (http://www.environment.gov.au/apps/boobook/mapservlet?app=ert) Land use (i.e. pastoral, freehold, traditional Aboriginal ownership, parks and reserves, mining, communities and townships) Historical, Aboriginal, Heritage sites (i.e. identification of historical, Aboriginal, and/or heritage sites that may be affected by the proposed activities) This information could be supported by documentation such as results of an inspection of the Register of Sacred Sites maintained by the Aboriginal Areas Protection Authority. NOTE: Information regarding the above topics may be sourced from the NRETAS (http://www.nt.gov.au/nreta/nretasmaps/). Reference to any reports/studies undertaken should also be included. Page 7 of 19 -8- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 4.0 ENVIRONMENTAL MANAGEMENT SYSTEM / PLAN Companies with a structured EMS and EMP may attach this to the MMP. 4.1 ENVIRONMENTAL POLICY AND RESPONSIBILITIES An environmental policy sets the direction for management of the environment. By providing a framework for setting and reviewing environmental objectives and targets, it describes the expectations of top management (and the rest of the organisation) for environmental performance. An environmental policy should contain three basic commitments: Compliance with all applicable legal requirements, and with other requirements to which the organisation subscribes relating to its environmental aspects. Prevention of pollution. Continual improvement. The company’s environmental policies and commitments should be outlined here. Also: Who is the person responsible for implementing environmental management? 4.2 LEGAL AND OTHER REQUIREMENTS This section should include a list of current applicable legislation, permits and conditions under which the project will be operated. List may include, but is not limited to: Mining Management Act Mining Management Regulations Mining Act Weeds Management Act Bushfires Act Australasia Railway (Special Provisions) Act Heritage Conservation Act NT Aboriginal Sacred Sites Act Native Title Act Aboriginal Land Rights (Northern Territory) Act Environment Protection & Biodiversity Conservation Act Workplace Health and Safety Act Waste Management and Pollution Control Act Reporting requirements such as those for; production statistics; employment/injury and safety statistics; frequency of water quality reporting Lease conditions Authorisation conditions This section should also include any other (non-statutory) requirements related to the establishment and implementation of the operator’s environmental management system. For example, land use agreements, pastoral agreements, pre-eminent practices, Land Council agreements, and agreements with other Authorised operators on site (if relevant). Page 8 of 19 -9- ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 4.3 OBJECTIVES AND TARGETS Objectives are the overall goals arising from the environmental policy. Targets are the performance requirements that arise from the objectives and that need to be set and met to achieve those goals. Objectives and targets should be Specific, Measurable, Achievable, Realistic and Timely (SMART) and should be reviewed regularly to determine if they are being achieved and to set new targets. Detail the organisations environmental objectives and targets taking into account legal and other requirements and views of stakeholders. A specific end land use objective must also be stated here. Table 2. Examples of objectives and targets. Objective Reduce the use of water in production Increase the revegetation success of rehabilitation Target Achieve a 10% reduction in water by 2011. Increase the active seeding of areas by 5% by 2011. 4.4 IDENTIFICATION OF ENVIRONMENTAL ASPECTS AND IMPACTS This section should identify actual and potential environmental aspects and impacts associated with the site and proposed activities. As defined by ISO14001:2004: Environmental aspects are the elements of an organisations activities or products or services that can interact with the environment (i.e. stripping/clearing, fuel storage, vehicles and machinery, etc) Environmental impacts are any change to the environment, whether adverse or beneficial, wholly or partially resulting from an organisation’s environmental aspects. Things to consider when identifying aspects of an organisation: What activities interface with the environment in a way that could cause an impact? What resources, materials, and energy do we use? Are there emissions to the air, water, land? Do we generate wastes? Does our infrastructure interact with the environment? What activities might lead to an accidental release? (e.g. storage of chemicals) Some questions to consider when evaluating impacts: Are the impacts actual or potential? Are they beneficial or damaging to the environment? What is the magnitude or degree of the impact? What is the frequency or likelihood of these impacts? What is the duration and geographic area? Which parts of the environment might be affected? A risk assessment should be conducted to determine the likelihood and severity of the identified impacts and the degree to which the impact needs managing. Refer to Figure 2 for a sample risk matrix. Risk ratings should be taken into account in Section 4.5 - Management of Identified Environmental Impacts. Page 9 of 19 - 10 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 Table 3. Examples of environmental aspects and impacts related to extractive activities. Aspect Impact Risk Rating Loss of native flora and fauna Erosion Loss of habitat Contamination of groundwater and surface water Loss of resource Introduction of weeds Local dust pollution Impacts on flora and fauna communities Clearing/construction of haul roads Mining of sand, gravel, etc Crushing/processing 3 (moderate risk) 8 (high risk) 5 (moderate risk) Driving between sites/tenements Spread of weeds/pests 5 (moderate risk) Emissions Degradation of air quality 5 (moderate risk) Fuel Storage Hydrocarbon leak/spill – contamination of soil, surface and ground water 6 (high risk) Outline the procedures in place for identifying impacts i.e. workplace inspections, risk assessment, etc. KEY Critical Risk High Risk Moderate Risk Low Risk CONSEQUENCE (C) Low Little to no impact Medium High Medium term -ve impact Irreversible or long term – ve impact 4 7 9 2 5 8 1 3 6 LIKELIHOOD (L) High >75% Chance event will occur in life of plan Medium 25%<>75% Chance event will occur in life of plan Low <25% Chance event will occur in life of plan Figure 2. Sample risk matrix and key. Page 10 of 19 - 11 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 4.5 MANAGEMENT OF IDENTIFIED ENVIRONMENTAL IMPACTS For the actual and potential environmental impacts identified in Section 4.4, management measures for both the prevention and remediation of these impacts need to be devised. This section must address management of water, invasive species, flora and fauna, hydrocarbons and hazardous materials, waste, noise and air, and cultural and heritage sites. Category Water Management Identified Environmental Impact/s Management (Prevention) Management (Remediation) Monitoring E.g. Erosion. E.g. Poor water quality at creek downstream from site. E.g. Minimise extent of cleared areas. E.g. Sediment traps (provide details and location). E.g. Revegetate cleared/disturbed areas to provide soil stability. E.g. Weekly field readings of turbidity. E.g. Weekly visual inspections of the site. Invasive Species Management Flora and Fauna Management Waste Management Noise and Air Quality Management Culture and Heritage Management Hazardous Materials and Hydrocarbon Management NOTE: Rows should be added/deleted where necessary. Page 11 of 19 - 12 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 4.6 INDUCTION AND TRAINING This information should include the following: Overview of environmental training and education process e.g. Induction, meetings. Outline of environmental issues covered in the induction. Is additional training required or carried out? E.g. weed identification, emergency response training, etc. 4.7 IDENTIFIED STAKEHOLDERS AND CONSULTATION This should include an outline of interested parties and their connection. This may include: Lease owner Land owner / occupiers Land claimants Neighbours and communities Tenement manager/s Government departments Shareholders Adjacent operators (i.e. sharing of haul roads) Outline the consultation process undertaken with the underlying landowners. Describe how end land use objectives and rehabilitation are discussed and agreed to with the underlying landowner. Describe the consultation process with the identified stakeholders on site related issues. Consultation should also be carried out with other Operators in the area which may be impacted. 4.8 EMERGENCY PROCEDURES AND INCIDENT REPORTING This section should, at a minimum, give an outline of the procedures followed in the event of an environmental emergency and how incidents are reported. What environmental emergency procedures have been developed? E.g. hydrocarbon spills. Formal procedures should be attached as an appendix to this plan as supporting documentation. Provide an overview of management of environmental incidents and identified hazards. Describe the companies incident reporting procedure both internal and external (i.e. environmental incidents must be reported to the Department as soon as practicable as per section 29 of the Mining Management Act). 4.9 ENVIRONMENTAL AUDITS AND INSPECTIONS Environmental audits and inspections should be carried out at regular intervals to assess the company’s environmental performance at the site. Have any environmental audits or inspections been carried out or are planned to be done? What frequency are audits/inspections carried out? What were the findings of any reviews? How are issues/problems identified? 4.10 DOCUMENTATION All objectives, targets, policies, responsibilities, procedures and environmental performance should be documented. Page 12 of 19 - 13 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 Documentation should be available to staff and the department Outline where the above information is stored and who is responsible for review All documents referenced in the MMP should be included as appendices 4.11 ENVIRONMENTAL PERFORMANCE REPORTING Factors for consideration: Results of monitoring programs should be presented e.g. water, noise, dust, weeds, erosion, etc Pollution and waste management and minimisation progress Progress made against environmental targets Progress towards achieving revegetation and closure objectives Page 13 of 19 - 14 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 5.0 REHABILITATION AND CLOSURE PLAN For each disturbance type listed, detail rehabilitation activities to be conducted including details of infilling, replacement of topsoil, revegetation techniques, ripping/scarification, etc. A schedule of proposed works needs to be provided. Closure objectives/targets should be provided, which reflect end land use objectives/agreements. Detail how rehabilitation success will be monitored e.g. in terms of water, erosion, vegetation, weeds, stabilisation, etc. NOTE: Department Advisory notes are available online for general guidance however these are not statutory requirements and should be assessed for appropriateness for individual sites. Advisory notes are reviewed regularly and may change. If referencing this material it must be attached to the MMP for assessment against the site and proposed disturbance. Disturbance Pits Proposed Rehabilitation Activities E.g. Backfilling of pit – 3,750m³ of infill material. Replace topsoil. Rip disturbed area and allow vegetation to naturally regenerate. Schedule (Timing) E.g. 50 x 50 metre area to be rehabilitated on completion of extraction of all viable material (prior to onset of wet season). Closure Objectives / Targets Monitoring and Remediation E.g. All mined areas closed out prior to onset of wet season. E.g. Visual monitoring of rehabilitation and erosion. If erosion is occurring and rehabilitation is unsuccessful, direct seeding may be required and drainage works. Haul roads/tracks Stockpile area/s Sediment traps/dams Workshops/sheds Offices/demountables Fuel storage area Other Page 14 of 19 - 15 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 5.1 STATUS OF CURRENT REHABILITATION This section should provide information on the amount of area disturbed and rehabilitated, per tenement, over the reportable period. Outstanding rehabilitation should also be outlined. This may be supported with a site map of the current status of rehabilitation. 5.2 COSTING OF CLOSURE ACTIVITIES As per Section 43 of the Mining Management Act, a security is required by the Minister as a condition of an Authorisation. As per Section 40 of the Mining Management Act, determine a costing for closure activities as per the Department Security Calculation spreadsheet (available on the website at www.minerals.nt.gov.au/mineralsforms#mining) or equivalent. Members of the Extractive Industry Association (EIA) may use the Department endorsed EIA Security Calculation Tool, which can be obtained from the EIA committee. Costing should cover issues such as: Removal of infrastructure and contamination (i.e. contaminated soils) Earthmoving Ripping Revegetation, including costs of materials Drainage works (i.e. sediment control) Infilling of sumps Post closure (i.e. weed management, mobilisation/demobilisation of plant and machinery) Details of calculations, including units of measure and cost per unit of measure used, should be included e.g. ripping (ha) at $/ha. The DoR Security calculation spreadsheet, if used, should be appended to the plan. 6.0 PERFORMANCE OBJECTIVES Performance objectives are a list of proposed improvements to environmental management issues on site. The objectives should include a measurable outcome (i.e. meeting a specific level), the time frame in which it will be completed (i.e. by when) and the person responsible for ensuring it is completed (i.e. a specific person). Page 15 of 19 - 16 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 APPENDICES Any other document(s) referred to in the MMP should be included in the Appendix, such as: Copies of approvals may be included in an Appendix. Copies of monitoring reports to meet statutory requirements may be included in an Appendix. Copies of rehabilitation agreements. Copies of AAPA search results. Page 16 of 19 - 17 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 Attachment A – EXAMPLE SITE LAYOUT MAP N EMP1234 EMP5678 Figure 1. Site layout map. LEGEND Haul Road Disturbed Areas Rehabilitated Areas Stockpile Areas Title Boundary Drainage Line Infrastructure Area Sensitive Vegetation Page 17 of 19 - 18 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 AA7-027 Attachment B – EXAMPLE SITE LOCATION MAP N DARWIN Figure 2. Site location map Attachment C – GLOSSARY OF TERMS TERM Audit CEO Contractor Critical Incidents Emergency Response MEANING Means any systematic investigation or appraisal of procedures or operations for the purpose of determining conformity with prescribed procedures. Means the Chief Executive Officer, within the meaning of the Public Sector Employment and Management Act, of the Agency administering this Act. Means a person who under a contract performs work or supplies a service in connection with an exploration activity on a site. Means an event on a mining site that has the potential to cause a significant adverse effect on the environment. A plan for the minimisation of environmental harm in the event of an emergency. Page 18 of 19 - 19 - ADVISORY NOTE EXTRACTIVE OPERATIONS MINING MANAGEMENT PLAN Sections 35(3), 40 of the Mining Management Act Minerals and Energy February 2010 Employee Environment Environmental Aspects Environmental Impacts Hazardous Material Issues MMA MSDS Objective Operator Plant Serious Accidents Target AA7-027 Means a person employed by a company. Means land, air, water, organisms and ecosystems on a site and includes: the well-being of humans; structures made or modified by humans; the amenity values of the site; and economic, cultural and social conditions The elements of an organisations activities or products or services that can interact with the environment. Any change to the environment, whether adverse or beneficial, wholly or partially resulting from an organisation’s environmental aspects. A substance having properties capable of having adverse affects on the environment. An important topic of discussion or point in question i.e. management of risk. Mining Management Act. Material Safety Data Sheet. It is provided by manufacturer or supplier of hazardous materials, and describes the properties and nature of the material. Overall environmental goal, consistent with the environmental policy, than an organisation sets itself to achieve. Means the operator for a mining site referred to in Mining Management Act section 10. Includes machinery, pressure vessels, equipment, appliances, implements, scaffolding and tools, any component of the plant and anything fitted or connected to the plant. Means an event on a site that causes material environmental harm. A detailed performance requirement, applicable to the organisation, that arises from the environmental objectives and that needs to be set and met in order to achieve those objectives. Page 19 of 19