Project: Pueblo Viejo Report: BGC Weekly Geotechnical Summary Date: May 25, 2012 to May 31, 2012 The following is a brief summary of the earthwork activities noted by BGC Engineering Inc. (BGC) for the Pueblo Viejo Dominican Corporation (PVDC) Pueblo Viejo project during the period May 25 to May 31, 2012. Weather predominately hot and dry with no rain; no red alerts. 1.0 GENERAL MANAGEMENT AND ADMINISTRATIVE ITEMS: K-122 LL Dam Daily (4 PM) construction co-ordination meetings continued through this period (including HYT, PVDC Construction, Concremat, Epsa Labco, and BGC). Concremat chair the weekly K-122 (LLSD) co-ordination meeting at 5 PM on Thursday and the K122 contract meeting on Wednesdays at 2:30 PM. PVDC-CM chair meeting for ARD Dams 1 and 3 10:30 AM on Wed. THIS WEEK’S ACTIVITIES GENERAL PROGRESS AND NOTES: 2.0 EL LLAGAL TAILINGS STORAGE FACILITY: LL Coffer Dam, Starter Dam and Seepage Recovery Dam Construction Trimming and foundation preparation (LPF zone) o Right Abutment to el. 175 o Left Abutment to 171 m. o Trimming RA DS continued. Foundation approvals: o Right Abut to 173 o Left Abut to 171 Fill placement (LPF) this week was approx.55,300m3 (T&S Data). Fill Type Average Elevation LPF 170 Fine Filter 171 Coarse filter 171 Transition Rock Fill 171 D/S Rock fill 171 U/S Rock Fill 171 U/S Rock Fill shell 171 QA QC summary of activities at LL Starter Dam for the week are included at the end of this report. NCRs. o New - no new NCR’s this week o Remains open NCR 12 -12 – Delay of Rock Fill density test BGC working with EPSA – test started this week NCR 12 – 15 – Timely Reporting of QC Test Results. BGC request update from Epsa Labco and Concremat on the request for additional staff and facilities made by Epsa Labco. o Closed – 0 Water level in the Cofferdam Reservoir was at elev. 139.9 m on May 31. This is a decrease of 2.3 m from last week. The chart attached to this report shows that approx.1.5 million cubic meters of runoff water is currently stored in the reservoir. Total reservoir capacity is approx. 17 million cubic meters at the current dam crest of approx.170 m. Six @ 100 to 125 HP submersible pumps were operated for 6 days this week Permanent water reclaim system ran for 7 days this week discharging with 2 of 3 pumps at a rate of 1150 m3/hr each. Two siphons are available for emergency use. Summary of Pumping Activity PUMP TYPE M3/hr./ea Days/week PVDC Barge (1) 145 6 PVDC Barge (1) 145 6 HYT Sub. 255 6 PVDC Reclaim (2) 1150 7 PVDC Diesel (1) N/A (4) Regular monitoring of seepage at the D/S toe continued. Flow measurements are being tabulated for comparison and trend. Rainfall runoff is adding to discharge. Observations will be maintained. INDRHI inspection on May 25 Rock fill density test was started at the end of this report period LL Seepage Recovery Dam The grouting program was completed on May 19th Fill placement started this week. 2.0 m. of LPF have been placed in the U/S core to aprox... elev. 208m. 1.5 m the D/S blanket was also placed Foundation prep and water control were ongoing. The INDRHI permit to place fill was given this week Field Memo #20 was issued which details the excavation of the LA alluvial soils after the waste dump above is removed. Low Permeability Fill Borrow LPF material was extracted from borrow areas “H, and L” this week. BGC-QA staff visited all borrows currently being utilized or containing stockpiled material (H, H1, I, and L). Epsa Labco QC staff also inspecting borrow. Borrow “I” continued to produce low plastic LPF along with poor mixing Borrow “I” was shut down on May 28 Isolated cases of high moisture content in the LPF borrow are still being detected but are not a major problem to production or quality control at this time. With the hot dry windy weather drying of wet LPF is done quickly PVDC-CM stockpile volume of LPF in Borrow Area “H” and “L” is approx. 35,100 m3; as reported by PVDC this week. Filters and Rockfill Delivery of sand and gravel from Rio Yuna for the production of fine and coarse filter continued this week. BGC continue weekly inspection of Hermanos Yarull aggregate extraction source at the Rio Yuna. No significant changes in the “raw granular product” delivered to El Llagal stockpiles. HYT continue production of fine and coarse filter at El Llagal #2 and Los Bananos. BGC visit the stockpiles on several occasions during the reporting period with Epsa-Labco QC. The “off-site” sources of Cabrera, and Diaz in Cotui continue to deliver fine and coarse filter. Pressa Issa with help from EPSA Labco have been working at producing an in spec product. Filter Source Llagal, Los Bananos Cabrera Diaz Fine (m3) Coarse (m3) 6300* 10100* 5400** 748** 8800** * As reported by HYT. ** As reported by PVDC *** Estimate PVDC’s stockpile report of May 31th, 2012 indicated the following: o Rock fill 52,300m3 o Fine filter 4,280m3 o Coarse filter 57,500m3 o Raw river rock 35,300m3 o LPF 35,100m3 T&S/ Concremat report of June 3rd indicates that: 115,300 m3 of fine filter and 104,800 of coarse filter have been placed in the LL Starter Dam. 3.0 ARD DAM 1 AND BASIN AND SEEPAGE RECOVERY DAM (SRD) ARD Dam 1 - No work related activities. Dam 1 Basin – Two new diesel pumps (2300 gal/min) operating. The water level has dropped by approximately another 2 meters. It is planned to draw the pond down completely and make the final repairs to the liner. PVDC completed the construction of the French drain above the inlet channel at the North side of the basin. Some water is flowing from the drain toward the SRD reservoir. Dam 1 Seepage Recovery Dam - HYT placed material in all zones of the Dam. BGC worked with PVDC-CM and HYT QC to achieve compliance with the drawings and technical specifications. The elevation of the fill placement is as follows: Fill Type Average Elevation masl LPF 143 Fine Filter 143 Coarse Filter 143 Rock Fill 144 Fluor continues working on the installation of the permanent SRD pumping system. Dam 1 Spillway - No work related activities HYT submitted an update on the Deficiency List, including: ( no major change this week) Geomembrane deficiency repairs continue This list is under review by BGC. (approx. 70% of the original items have been addressed by the contractor ) Fluor have not started on the work for the energy dissipation structures at the 3 culvert inlets No work has been started to repair the HR2 ditch. 4.0 ARD DAM 3 AND SEEPAGE RECOVERY DAM (SRD) ARD Dam 3: The work has been going well with good progress; the hot dry weather has helped. The left abutment is still lagging and has needed more resources. PVDC imported 20 more labourers to work this area where a depression has formed. HYT continued placing rock fill material on the upstream and downstream zones of the dam. Summary of fill elevations follows: Fill Type Average Elevation masl LPF 295.5 Fine and Coarse filters 295.6 upstream Rock fill upstream 296 Fine and Coarse filters 295.5 downstream Rock fill downstream 296.1 Dam 3 Cofferdam: One pump (2300 gal/min) required minimally during the day. The water level remains at a low level in the reservoir. Dam 3 SRD: No work related activities. Dam 3 Spillway: HYT continued working on the concrete road crossing / control structure of the emergency spillway. The center portion was poured this week. One lane is complete. NCRs. o Closed – 3 (Dam 3) NCR 12-16 – LPF Fill to FF fill Sequence. NCR 12-17 – Foundation Preparation and contact LPF. NCR 12-18 – Poor surface water Management. 5.0 UM-1 & UM-2; HONDO DAM BGC continue to monitor the existing slope indicators at the Hondo Dam. The trees and scrub vegetation were removed from the dam this week. Additional instrumentation will be installed at the Hondo Dam 6.0 FLUOR PLANT SITE EARTH WORKS BGC assessing the landslide below Lime Kilns. Seepage path into slide area was observed. BGC were requested to assess the slope near the Mill Office on Middle bench. BGC were requested to assess an alternate location for the Bio-Mass Pond. The proposed location is north of the current site and is in a localized area of steeper topography. The BGC assessment is near completion. 7.0 BGC SITE MANPOWER (WEEK ENDING 31, MAY, 2012) Capacity Construction Engineering Contractor Local support Review Engineers Total Personnel Support BGC Equipment Operators Forman Staff Engineers 7 Man Man Days Hours Notes 49 588 2* 11 65 520 2 18 114 1108 31 MAY 2012 VIEW OF LL STARTER DAM LOOKING TO THE EAST. * Secretary SEE NEXT PAGES FOR QA /QC REPORTS AND STORAGE CAPACITY OF LLSD QA /QC REPORT FOR LLSD ( QC BY EPSA LABCO) QA /QC REPORT FOR ARD DAM 1 AND DAM 3 (QC BY HYT) RESERVOIR STORAGE CAPACITY/ STORED WATER GRAPH -- MAY 31,2012