Change Order No. 9 Cover Letter

advertisement
Date:
September 16, 2010
To:
Oklahoma City Zoological Trust
From:
Dwight Scott, Executive Director/CEO
Re:
Change Order #9 for Asia, Project #MZ-0044
Location:
Oklahoma City Zoological Park
Purpose:
This change order covers the changes made from:
P.R. #55 Provides below grade roof drain collection to storm
sewer as requested by zoo staff following the bid. This should
prevent erosion below the elephant barn and allow the vegetation
to grow in quicker
P.R .#56 Rev. #2. Installs a fire truck turnaround near the haybarn
as requested by the fire marshall to obtain the occupancy permit.
The fire truck turnaround around was not included in the bid set
because during two meetings with the City prior to bidding, the fire
marshall reviewed the plans and found no objections at the time.
P.R. #56 is value engineered from a grass pave drive, to the
concrete drive as shown.
P.R. #58 Changes the elephant hot wire detail from a copper
stanchion to fiberglass stanchions, and provides a third energizer
requested by the staff following bidding to run each paddock
independently. These changes are recommended by Gallagher
the hot wire MFG, and results in a credit back to the zoo.
P.R. #60 Reroutes fire protection piping out of the elephant
community stall, where they would have been within reach.
P.R. #62 Rev. Provides Elephant House roof flashing, gutters,
downspouts and associated wood theme work furouts as
requested by zoo staff following the bid. This should prevent
erosion below and allow the vegetation to grow in more quickly.
P.R. #67 Provides natural cut stone rock retaining walls at the
switchback to prevent erosion and increase the ease of planting
as requested by horticultural staff following the bid set. This
proposal request is value engineered from rockwork retaining
walls.
P.R. #68 Roughs in PVC and EMT conduit for a future
communications system. Was originally going to be owner
provided, but considering work in the area was taking place, it
makes sense to do it now.
P.R. #70 Provides electrical service from the Thai Demonstration
Pavilion to the electric gate operators on the northwest side of the
museum.
P.R. #71 Provides access doors in the utility rocks for the hose
bibbs located in the elephant exhibit areas. The hose bibbs are
inset into the rockwork, the access doors are for the vacuum
breakers which are required by code.
P.R. #72 runs gas piping to the emergency generator and split
system furnace unit at the mezzanine office, which was left out of
the bid set.
Background:
Refer to the attached from Lippert Bros, Inc., for backup
documentation of the above descriptions
Previous Action:
Change Orders #1,#2, #3, #4, #5, #6, #7, & #8
Architect:
Torre Design Consortium, Ltd.
Contractor:
Lippert Bros. Inc.
Change Order #9
Prepared By:
Lippert Bros., Inc.
Contract Price:
Original Contract Amount:
Previous Change Orders:
Contract Sum to Date:
Change Order # 9 Amount:
$12,658,000.00
$425,595.00
$13,083,595.00
$ 108,553.00
% Increase over Original:
New Contract Amount:
Time Extension:
C.O. #1
C.O. #2
C.O. #3
C.O. #4
C.O.#5
C.O.#6
C.O.#7
C.O.#8
C.O. #9
.2334%
.3041%
.1016%
-.6426%
.1782%
.1671%
2.5385%
.4816%
.8575%
Total
4.2197%
$13,192,148.00
0 days Base Bid
0 days Alt #2
(Time extension for PR #55,56,58, 62,68,70,71,72 to be agreed upon at a later date)
Source of Funds:
Zoo Sales Tax
Review:
Lippert Bros., Inc., Zoo Staff, Municipal Counselor, City of
Oklahoma City Staff.
Recommendation:
Staff Recommends Approval of Change Order #9
The Architect, City Staff and the Contractor have reviewed these items and determined
that the approval of these items will benefit the City, Oklahoma City Zoological Park
staff, and the citizens of Oklahoma who will use the facility.
The above and foregoing is hereby reviewed the _____ day of ____________, 2010 and
the undersigned agree to perform the work at the price indicated.
ATTEST:
___________________________
LIPPERT BROS., INC.
__________________________
The above and foregoing is hereby submitted for approval this ____ day
of______________________, 2010.
_________________________________
Architect of Record
The prices for Change Order #9 have been established by negotiation and appear to be
fair and reasonable. The following recommend approval:
_______________________________
Dwight Scott, Executive Director
The amount contained in the above change order complies with 61 O.S. Section 21.
APPROVED as to form and legality this ____ day of ________________, 2010.
__________________________
Assistant Municipal Counselor
APPROVED:
By the Oklahoma City Zoological Trust this____ day of _________, 2010.
_____________________
Secretary
_____________________
Chairman
Download