Developer Obligations - Frequently Asked Questions (FAQ’s) 1. What are Developer Obligations? Developer obligations are contributions sought from developers (in kind or financial) to mitigate any pressure their development may have on existing infrastructure and facilities. This is to ensure that existing residents are not disadvantaged. Developer obligations must relate to the impact of the proposed development. They cannot be sought for existing deficiencies. 2. What is draft Supplementary Guidance? The emerging Moray Local Development Plan (LDP) sets out the strategy for the development and use of land in Moray. The LDP contains policies and land designations to guide development. Supplementary guidance expands upon policies set out within the LDP to assist in their consistent interpretation and implementation. Policy IMP3 Developer Obligations sets out a commitment to prepare supplementary guidance on developer obligations. The draft supplementary guidance sets out the developer obligations process, the infrastructure and facilities requirements that the Council will seek for different types of development, and the assessment methodologies that will be used to calculate the level of contribution required. In summary, the draft guidance sets out that contributions will be sought for education (pre-school, primary, secondary, further), transport, community, sports and recreational facilities, cemeteries, healthcare (GP surgeries, dental practices, community pharmacies), town centre improvements, environmental and access improvements and waste. The draft guidance includes a list of the infrastructure and facilities that are likely to be required and their contribution rate for each Associated School Group (ASG), e.g. Forres Academy. This is to help provide clarity and certainty to the development industry and communities over what will be sought from a new development. Any infrastructure or facilities proposed through the consultation that meet the tests set by the Scottish Government (outlined below) and are deliverable will be included within the relevant ASG list in the finalised supplementary guidance. This means that the Council would seek a contribution towards this requirement from relevant new development. However, where a developer is concerned that the viability of their development may be undermined by the application of developer obligations, and this is accepted by the Council then the Council will need to prioritise the infrastructure and facilities that obligations are sought for. For further information about development viability please see question 4. 3. What can Developer Obligations be sought for? Developer obligations can be sought for capital costs, e.g. construction works. They cannot be sought for revenue costs, e.g. maintenance and running costs such as utility bills. Developer obligations can be sought where there is a need to provide additional facilities (or increase the capacity of an existing facility) to accommodate residents from the new development. The following examples illustrate where the existing capacity of a community, sports or recreational facility may be increased to accommodate additional residents (and usage): Reconfiguration of a village hall to accommodate additional community space (e.g. conversion of a store room to crèche); Floodlighting for sports pitches to allow them to be used for longer periods of time and by a larger range of user groups; Provision of toilets/changing facilities associated with an existing sports pitch to enable them to be more widely used; Improving the drainage and surfacing of sports pitches to bring them back into use; Making premises Disabilities Discrimination Act (DDA) compliant (e.g. sports pavilions, village halls) where it would allow more residents to use the facility. It is important to be realistic about what is achievable when seeking contributions and ensure these are related to the impact of the proposed development. Where a relatively small scale of development is likely to take place in a town or village, it is unlikely that sufficient contributions will be generated for larger projects. The Council will avoid seeking contributions that will result in a slow accumulation of funds as these are unlikely to be spent because monies can only be held for a limited number of years and are an administrative burden to the Council. 4. Do developer obligations impact on a development’s viability? Developer obligations must be reasonable to ensure that Moray remains an attractive area to develop in and to encourage economic growth. Developer obligations should be factored into the proposed developments financial appraisal from the outset. In exceptional circumstances, the developer will be able to demonstrate to the Council in a viability statement how the application of developer obligations will render a development unviable on a confidential basis. This statement will be assessed by a third party at the developer’s expense. Where the Council accepts this position, the obligations and their respective levels may be negotiated and varied. This may include reviewing the timing or phasing of paying financial contributions to assist the financial viability of a development. In these circumstances, the Council will need to prioritise those infrastructure and facility requirements that obligations will be sought for. This prioritisation will be established with the finalised Supplementary Guidance and reported to a further meeting of the Planning & Regulatory Services Committee for approval. 5. How will developer obligations be secured? Remittance of financial contributions can be undertaken through the provision of an upfront payment (Section 69 agreement) prior to the release of the Planning Decision Notice or by entering into a Section 75 agreement (also referred to as a Planning Obligation). A Section 75 legal agreement is likely to be required for larger obligations to secure these through phased payments and in perpetuity with each successor in title. 6. What criteria or tests are applied when seeking Developer Obligations? The Scottish Government set strict criteria (or tests) that must be met when the Council seek developer obligations. All of these tests must be met. The tests (and an example of each for explanation purposes) are set out below: TEST Necessary to make the proposed development acceptable in planning terms; EXAMPLE Without the proposed infrastructure or facility there would be a shortfall in provision and this would have an adverse impact on existing residents, e.g. where a primary school is at capacity a contribution will need to be sought to accommodate additional pupils arising from a new development. Serve a planning purpose and where, it is possible to identify infrastructure provision requirements in advance, should relate to development plans; The proposed sports facility (e.g. football pitch) satisfies the open space requirements set out in the LDP. The supplementary guidance including the infrastructure and facility requirements set out in the ASG lists provide this information in advance. TEST Relate to the proposed development either as a direct consequence of the development or arising from the cumulative impact of development in the area; Fairly and reasonably relate in scale and kind to the proposed development; and, Be reasonable in all other respects. EXAMPLE Direct: The proposed development will generate x primary school pupils and therefore x contribution will be necessary to build an extension to the local school to accommodate the additional pupils. The contribution will not be used to compensate for an existing lack of facilities at the local school. Cumulative: A number of individual developments will place additional pressure on key junctions on the road network and the developer will need to carry out works at these junctions or provide a contribution towards mitigation works to negate their impact. Scale: Where a proposed housing development results in a 10% increase in the population of a town or village the development is taking place in, then only 10% of the total cost of the proposed facility should be sought. Kind: The infrastructure or facility that the contribution is being sought for should be appropriate to the type of development, e.g. a business development will not generate any primary or secondary school pupils therefore it is not appropriate to seek contributions towards education facilities. The developer obligation will not mitigate any existing impact that is present prior to development of the site. The application of the contribution will not undermine the viability of the development. 7. Can a developer appeal against a Developer Obligation? Yes. Similar to a planning application refusal, a developer has the right to seek to modify or discharge (i.e. appeal) a planning obligation. If the Council is considered to have acted unreasonably in seeking the contribution, the Council may have costs awarded against them. 8. Do Developer Obligations have to be spent within a specified time period? The Council will generally endeavour to spend the funds received for appropriate infrastructure and facilities within 10 years of the date when planning permission is implemented or for those applications where phased payments are received within 10 years of the date of the final payment, unless otherwise stated. Contributions not spent by the end of the relevant period will be refunded to the developer with interest. 9. Can developer obligations be match-funded? Yes. Developer obligations may be used to attract match funding from other sources to further enhance the facility the funds are being sought for, which will potentially provide a greater return to the community. 10. What is a constituted community group? A constituted community group is run on a voluntary basis and it is set up as an organisation in its own right with a management committee, constitution and its own bank account. The most common types of constituted groups formed within the community and voluntary sector include: associations (e.g. community associations), trusts (e.g. grant-making organisation), and companies limited by guarantee (e.g. charitable company). 11. What is a project delivery plan? A project delivery plan should define the project, set out the business case (including capital and revenue costs), identify key milestones/timeline for delivery, define responsibilities/project management, and show that stakeholder analysis has been carried out. 12. What happens next? Following the consultation, any proposed infrastructure or facilities will be assessed against the tests set out above. Those that are considered to satisfy all of the tests and are with an existing constituting body with a project delivery plan will be included within the ASG list of infrastructure and facility requirements in the finalised supplementary guidance. This means that a contribution could be sought for this requirement from related new development. All comments and a response will be reported back to the Planning and Regulatory Services Committee along with the finalised Supplementary Guidance and revised ASG lists for approval. Should the finalised guidance be approved, it will become part of the Moray LDP and be used in the determination of planning applications.