SECTION 202 REMOVAL OF STRUCTURES, OBSTRUCTIONS, SURFACING, AND MISCELLANEOUS ITEMS 202.01 DESCRIPTION This work consists of demolishing, removing, salvaging, and disposing of items not designated to remain, salvaging designated materials, and backfilling resulting cavities. 202.02 EQUIPMENT Reserved 202.03 MATERIALS Reserved 202.04 CONSTRUCTION REQUIREMENTS A. General. Replace items designated for salvage that are lost or damaged by work activities with new items that meet the appropriate specifications at no additional cost to the Department. Remove existing bituminous and concrete surfaces to a joint or saw a full-depth vertical cut along the entire length of the butt joint. Backfill and compact cavities within the embankment area as specified in Section 203.04 E.2, “Compaction Control, Type A”. Backfill and compact cavities outside the embankment area to the same level as the surrounding undisturbed ground. Before backfilling, break remaining concrete slabs for drainage. B. Removal of Bridges and Box Culverts. Remove existing substructures to one foot below the existing stream bottom, and remove those parts outside the stream to one foot below final ground surface. If bridge elements are designated for salvage, match mark the elements and transport them to the location specified in the contract. C. Removal of Pipe Conduit. Dispose of unsuitable or excess excavation at an approved location. D. Removal of Bituminous, Concrete, and Aggregate Materials. If designated as salvage material, ensure the material is not contaminated with dirt or other deleterious material. Remove all reinforcing steel, dowel bars, and tie bars from the existing concrete pavement. Do not stockpile the reinforcing steel, dowel bars, and tie bars within the ROW. At the end of each day provide a smooth transition between areas where pavement has been removed and areas from which traffic can enter the removal area. E. Removal of Manholes and Inlets. Remove manholes or inlets by removing the casting, rings, barrel and base; plug or cap the existing lines; and backfill to grade. 202.05 METHOD OF MEASUREMENT The Engineer will measure as specified in Section 109.01, “Measurement of Quantities” and as follows: The Engineer will measure removal of pipe conduit along the top of the pipe. The Engineer will not measure flared end sections. Flared end section will be considered part of the pipe. The Engineer will include the reinforcing steel in the total weight when the Department pays for removal of concrete pavement by the ton. 202.06 BASIS OF PAYMENT Pay Item Removal of Structure Removal of Structure-Site __ Removal of Structures and Obstructions Removal of Box Culvert Removal of Concrete-Site __ Removal of Concrete Removal of Concrete Pavement Removal of Pavement Removal of _________ Surfacing Remove & Salvage Base &Surfacing Removal & Salvage of __________ Surfacing Removal & Salvage Culverts, All Types & Sizes Removal of End Sections, All Types & Sizes Removal of Culvert, All types and Sizes Removal of Pipe All, Types & Sizes Removal of Curb & Gutter Saw Concrete Saw Bituminous Surfacing-Full Depth Removal of Manholes Removal of Inlets Removal of Catch Basins Removal of ____________ Pay Unit Each, Lump Sum Lump Sum Lump Sum Each, Lump Sum Lump Sum Lump Sum, Square Yard, Cubic Yard, Ton Square Yard Square Yard, Ton Square Yard, Cubic Yard, Ton Ton Square Yard, Cubic Yard, Ton Linear Foot Each Linear Foot Linear Foot Linear Foot Linear Foot Linear Foot Each Each Each Each, Lump Sum, Linear Foot, Square Yard, Cubic Yard, Ton Include the cost for excavation and disposal of excess excavation for removal of pipe conduit in the price bid for “Removal of Pipe All Types & Sizes”. Such payment is full compensation for furnishing all materials, equipment, labor, and incidentals to complete the work as specified.