Permit to Work - DRAFT - QUT - Health, Safety and Environment

advertisement
Procedure
Permit to Work - DRAFT
1. Purpose
The purpose of this procedure is to establish and specify requirements for the application of a permit to work
system within QUT. This is to assist in the planning, scheduling and control of specified tasks which have a
high level of risk and /or include simultaneous or non-routine work. The permit system ensures appropriate
controls are in place prior to undertaking work.
2. Scope
This procedure and associated work instructions apply to all activities undertaken by QUT staff, students and
contractors when conducting ‘high risk’ work or other specified tasks which require review and approval by
an authorised person.
This procedure does not apply to activities on QUT campuses or other sites which are conducted entirely
within an area over which a third party has management control.
3. Definitions
For detailed terms and definitions, refer to the HSE Glossary.
4. Permit systems
Where an activity introduces sufficient risk to persons, equipment or facilities through the nature of the work,
or the complexity of the work environment, review and approval of the work practice must be undertaken
prior to work commencing. This will be done through the use of a work permit which:
defines the scope of the job;
identifies the hazards and HSE risks of the job;
details and records agreed control measures to mitigate the identified risks; and
provide a written authorisation to conduct the work from a QUT Permit Officer.
Permits are generally associated with activities specified as ‘high risk’ by legislation and include but are not
limited to:
Fire alarm isolation;
Hot work;
Energy isolation;
Working in confined spaces;
Working at heights and roof access; and
Working with asbestos.
Example permits for high risk activities are attached to the applicable HSE Procedures.
Activities other than those specified as ‘high risk’ may also necessitate the use of permits and these would
be identified through the conduct of a detailed risk assessment as part of activity planning. These may
include activities where:
the planned work is outside the scope of what would be considered ‘routine’; and
the location of the work introduces variable which elevate the risk; or
the risk is increased due to activity in adjacent locations.
Permits for such activities should be developed on an as required basis by the relevant faculty, institute or
division in consultation with the Department of HSE.
1
Last modified: 6 February 2016
Document1
Permit to Work - DRAFT
5. Authority to issue permits
Were required, permits to work may only be issued by specified ‘High Risk Permit Officers’ (Permit Officers),
following their review and approval of the planned work.
Permit officers may only issue permits for high risk work tasks for which they are qualified and authorised.
Faculties, Institutes and Divisions are responsible for defining internal permit officer requirements and
ensuring that these persons are appropriately skilled and qualified to enable them to perform this function.
Where known or planned work does not warrant the maintenance of specific permit officers, permit officers
from other faculties, institutes or divisions may be requested to review work plans and issue permits for high
risk work. Such support is subject to capacity constraints of the permit officer and management approval.
The QUT Department of HSE is responsible for ensuring that permit officer information is made available
across the university through the QUT intranet; however, Faculties, Institutes and Divisions are responsible
for ensuring the currency of the permit officer information provided.
6. Planning
All tasks involving high risk work require detailed planning to ensure the effective identification and
management of risk and to ensure that the work is conducted in a manner so as to not adversely affect other
areas or activities.
The requirement for the issue of a work permit should be identified during the planning stage for a task and
this is supported by the conduct of either a detailed risk assessment or a QUT Risk Check.
Planning must identify the potential for the issue and management of multiple concurrent permits within the
same work area and consider how the risks associated with these tasks will be managed.
Risk assessment and QUT risk check
All high risk work activities, regardless of task, process, equipment or environment must be the subject of a
detailed risk assessment and recorded in the applicable risk register.
Prior to commencing any work and independent of any requirement for a permit, all high risk work tasks must
be subject to a daily analysis of the task and inspection of the work environment by applying the QUT Risk
Check process.
Work Instructions
Where particular high risk tasks are conducted as part of routine activities, or conducted with sufficient
frequency, faculties / institutes / divisions should develop work instructions to detail the method for the
undertaking the work task. These must be specific to the work environment and the high risk work task being
undertaken, address risks and incorporate relevant controls identified through the risk assessment.
Where an approved work instruction exists, detailed risk assessments for each occurrence are not required.
Additionally, the existence and application of a current work instruction may remove the requirement for high
risk work to be conducted under a permit. Further detail on where this may be relevant is located in
procedures and work instructions for applicable high risk activities.
7. Permit issue process
Compilation of the permit
Prior to their approval and issue, permits should be compiled by the person who is going to conduct the
work. If compiled by someone other than person conducting the work, that person must have some level of
management control over the activity (E.g. supervisor of the person conducting the work).
If specific technical qualifications are required for the compilation of the permit (and / or completion of the
work), these will be specified through applicable procedures, work instructions or other direction.*
* Note - If compiled by someone other than person conducting the work, that person must brief the person
conducting the work on the issues risks and controls to be applied prior to any work commencing.
2
Last modified: 6 February 2016
Document1
Permit to Work - DRAFT
Compilation of permits must include a review of existing procedures, risk assessments and / or work
instructions that address the planned work. In addition to detailing the nature and scope of the task, the
hazards, risks and associated controls specified in these documents must be reflected in the permit.
Approval and issue
On receipt of the permit, the permit officer must review the nature and scope of the task, the adequacy of
planned risk controls as well as the potential impact on activities, areas or persons adjacent to the work.
If satisfied that identified risks will be adequately controlled, the permit officer shall approve the work.
Permit officers may elect to issue permits for periods greater than 1 day where the work is being conducted
over consecutive days.* Such approvals must reflect the nature of the work and the assessed level of risk.
* Note - Permits issued for durations greater than 1 day do not diminish the requirement for persons
conducting the work to conduct a daily analysis of the task and inspection of the work environment.
Management of multiple permits
Where work involves multiple and combined high risk tasks (eg hot work at height or in a confined space),
the permit officer(s) must consult as part of the approval process and ensure that the cumulative effects of
the high risk tasks are identified and managed.
Where work involves multiple, yet stand-alone high risk tasks within the same vicinity, the person with
management control of the work shall ensure that the respective tasks do not adversely affect each other.
Withdrawal
Permits may be withdrawn by permit officers at any time where they identify:
unsafe work practices or deviation from specified risk controls; or
significant changes to the work environment outside those considered in the issue of the permit
Records retention
Faculties, Institutes and Divisions must ensure that copies of permits are retained for record keeping
purposes.
8. Responsibilities
Managers/supervisors
For high risk work practices conducted in areas within their influence or control, managers and supervisors at
all levels are responsible for:
ensuring that such work practices are subject to detailed risk assessments and recorded in applicable
risk registers;
ensuring that work permits are sought and issued in accordance with this and other applicable
procedures; and
ensuring that completed work permits are retained for record keeping purposes.
Person conducting high risk work
Persons conducting high risk work are responsible for:
undertaking the necessary planning for the conduct of the high risk work task;
obtaining a work permit in accordance with this and other relevant procedures, or where determined by a
detailed risk assessment;
conducting a daily risk check and ensuring that all controls specified in the work permit are in place and
maintained throughout the task;
operating equipment in accordance with manufacturer’s instructions;
wearing PPE appropriate for the work being conducted;
stopping the work if it becomes unsafe or a serious incident occurs; and
reporting any incidents or conditions that affected their ability to conduct the work as planned.
3
Last modified: 6 February 2016
Document1
Permit to Work - DRAFT
Permit Officers
Permit Officers authorised for approving specified high risk work are responsible for:
reviewing plans for the conduct of the work (where required) and verifying the effectiveness of identified
controls;
providing advice to managers, supervisors and persons conducting high risk work on safe work
practices;
monitoring high risk work to ensure that it does not / will not impact on other work on the site and equally
that other work will not affect the safety of those doing the high risk work;
approving high risk work tasks through the issue of work permits; and
conducting inspections, where considered appropriate, of approved high risk work tasks to ensure that
the work is being conducted in accordance with the requirements of the permit.
Contractors
Contractors conducting high risk work for or on behalf of QUT shall apply the requirements outlined in this
procedure.
Contractors they may seek approval from the QUT person commissioning the work to use their own permit
forms, if it can be demonstrated that the QUT permit is not suitable for the work being conducted. In such
cases, the permit must still be approved and issued by a QUT permit officer.
9. Associated documentation
Guidance Information
Procedures
HSE PRO – Risk management
HSE PRO – Hot work
HSE PRO – Working at height
HSE PRO – Confined space entry
Forms
Lists
10.
Document history
Title:
Document Number:
Author:
Document Owner:
Review Interval:
Version Number
Paragraph
Description
4
Last modified: 6 February 2016
Document1
Date
Approved by
Download