DRAINAGE PLAN for Proposed Cement Factory,Clarendon. Volume: 932 Folio:447 Prepared for: The Owner May 2010 1 Introduction .................................................................................................... 1 1.1 Background ............................................................................................ 1 1.2 Objectives of the report........................................................................... 1 1.3 Methodology ........................................................................................... 1 2 Description of Development ........................................................................... 1 2.1 The Catchments ..................................................................................... 3 2.2 Soils ........................................................................................................ 5 2.3 Meteorology ............................................................................................ 5 2.4 Anecdotal Evidence of Historical Flooding Events (Hurricane Ivan) ....... 5 2.5 Limitations of Hydrologic Analysis .......................................................... 7 3 Proposed Drainage Infrastructure .................................................................. 7 3.1 Drain Sizing Guidelines .......................................................................... 7 3.2 Hydrology ............................................................................................... 7 3.2.1 SCS Method .................................................................................... 7 3.2.2 Curve numbers ................................................................................ 7 3.3 Hydraulics ............................................................................................... 8 3.3.1 Methodology .................................................................................... 8 3.3.2 Hydraulic Analysis of the proposed site ........................................... 8 4 Conclusions and Recommendations ........................................................... 10 4.1 Conclusions .......................................................................................... 10 4.2 Recommendations ................................................................................ 10 2 1 Introduction 1.1 Background The proposed site is located approximately 4 km east of Freetown and 6 Km south south east of Old Harbour, Clarendon. It is the site for the proposed cement factory with a volume of 932 and a folio of 447. The site is bordered to the north Highway 2000 and bordered to the west by the HIPRO FEEDS factory. Please see Figure 1.1 which shows the location of the proposed site. Figure 1.1. Map shows location of proposed site. 1 1.2 Objectives of the report The Client is desirous of developing a drainage plan as requested by the National Works Agency. This drainage plan examined the flow of stormwater which will be conducted through the site. The goals of this report are as follows: To outline the flows expected to be generated from the proposed site. To design preliminary drainage works for the site. 1.3 Methodology The methodology adopted to complete these goals are as follows: Field investigations to determine past flooding and rainfall runoff event effects. Hydrological analysis of the associated catchments Hydraulic analysis of the existing and proposed drains and drainage features Prepare engineering analysis, designs and drawings for preliminary drainage infrastructure. 2 Description of Development The site at present is has a gentle slope from north to south with the site elevation ranging from 23.5 m to 14m. The site receives an earth drain at the north end approximately 2m wide and 2.7 m deep which runs through the centre of the proposed site. Investigations of the site topography as well as anecdotal information revealed that the drain is unable to contain the stormwater which is expected from even the 2 year return period and so ponding in several low spots on the site occurs. Please see Figure 2.1 which shows an overview of the site, the existing earth drain and proposed layout of the factory. 1 Figure 2.1. Overview of site showing existing earth drain and factory layout 2 2.1 The Catchments It was crucial for us to delineate the catchments associated with the site so that we could deduce the rainfall runoff flows expected to reach the site. The area of concern has several catchments which are generally bounded by the natural topography. From the site visit it was evident that in its existing form, the land is drained via overland sheet flow to the earth drain travelling through the site as well as the low spots. The catchments associated with the site have an overall area of 223 HA. The catchments associated with subdivision one have moderate slopes reaching a summit of 39 m above mean sea level north of the site. Please see Figure 2.2A which shows the catchments associated with the site. 3 Figure 2.2A. Map shows associated catchment area. 4 2.2 Soils The soil types as described in the “GIS data sets obtained from the Meteorological Service of Jamaica for the area contained by the main catchments are clay loam and sandy loam. These soils are rapidly draining soils having a high propensity for landslides. 2.3 Meteorology The meteorological data for the catchment was obtained from the Intensity Duration Frequency Curves data set analysed by the Meteorological Service of Jamaica. Please see Table 2. Return Periods Predicted Rainfall Intensity 2 5 10 94 140 170 50 236 mm/24hrs Table 2.1. Table shows predicted rainfall intensity for different return periods at the Bodles Station Bodles is approximately 2km, north of the proposed site. The rainfall extremal data was obtained for the 50 year return period as instructed by the NWA guidelines for designing internal drainage and was found to be 236 mm/24hrs. 2.4 Anecdotal Evidence (Hurricane Ivan) of Historical Flooding Events To supplement meteorological data, information regarding historical rainfall events was obtained by conducting interviews with present residents in the area. On speaking to 5 residents in the area, it was concluded that the proposed sites had no historical flooding events even during severe weather systems such as Hurricane Ivan in 2004 and Hurricane Dean in 2007. It was the general consensus that all the rainfall runoff tended to travel over land and on the existing roads to the existing earth drain. It should be noted however that there are no residents directly adjacent to the site and so they could not speak for what happens on the property. A preliminary hydrologic analysis was conducted to conclude whether the existing drain could handle the expected flows from catchment. The analysis revealed that the existing drain could not handle the expected flows for even the 2 year event however the closest residents interviewed (less than 1km from site) had no recollection of flooding in past storm events. Please see Table 2.1 which shows the calculations. 5 Input Parameters Area Mannings Coefficient for land Lengths Main stream length, L Secondary length Distance from outlet to centroid, Lc Elevations Lower elevation Upper elevation Upper elevation-catchment ridge Slope Main channel slope Catchment slope Ct Cp Runoff Coefficient, C Curve Number, CN Values Box Channel Length of main channel Slope Mannings Coefficient Width Depth Depth + freeboard R P A Velocity Flow Tt Hydrology Time of concentration Time entry Overland/shallow flow, Tt (NCCS revised) User switch (Box = 1, V = 2, Trapezoidal =3; Pipe = 4) Time of travel in main channel Values 1426 0.67% 0.015 2.000 2.500 3.13 0.7 7 5 4.3 21.74 0.091 Units m 0.083 0.042 1 0.091 hours hours 0.22 hours Units 2,233,733 m 2 0.035 783.2 m m m 14.00 23.50 39.50 m m m 1426 904 0.7% 1.1% 1.50 0.17 70% 87 Tc m m m m m 2 m m/s 3 m /sec hours hours Rainfall-24 hours ( 1 in ARI year return period) 94 mm/24hours Rainfall Intensity 41 mm/hour Rainfall Intensity for Tc 7.83 3 m /sec 25.34 Table 2.1. Calculations of the capacity of the existing drain and the expected flow from the 2 year rainfall event. Effective Runoff Rate 6 2.5 Limitations of Hydrologic Analysis It is important to note that there was insufficient topographic information with respect to the earth drain upstream of the site and so the true elevation of the invert of the gully was not known. Given this limitation, as well as limited site topographic data, topographic data from the12 500 map series was used in the analysis. A detailed site specific topographic survey as well as a survey of the earth drain upstream is recommended so that an accurate hydrologic and flood plain analysis can be conducted. It is possible that depressions upstream which during rainfall events, act as ponds could significantly decrease the peak flow downstream and so may explain why flooding is not recalled at the site. 3 Proposed Drainage Infrastructure 3.1 Drain Sizing Guidelines The drainage for the project was designed according to specific guidelines set out in the Ministry of Transport and Works Guidelines for Drainage review of Subdivisions and Development Applications (May 2007). Some of these guidelines are as follows: The return period to be used for flood control is 1 in 50 year. The internal diameter of sewer or drainage pipes must not be smaller than 450 mm The freeboard in all drains must be at least 25% of the depth of channel 3.2 Hydrology The hydrology was analyzed using the Natural Resources Conservation Service (NRCS) Method for generating peak flow. This method incorporates selecting a single curve number to describe the runoff land and soil conditions. For the analysis a type III distribution curve was used. 3.2.1 SCS Method SCS method is an empirical model for rainfall runoffs which is based on the potential for the soil to absorb a certain amount of moisture. On the basis of field observations, this potential storage S (millimeters or inches) was related to a 'curve number' CN which is a characteristic of the soil type, land use and the initial degree of saturation known as the antecedent moisture condition. 3.2.2 Curve numbers The curve number used in the SCS method was extracted from the recommended set of values given in the ‘Stormwater Collection Systems Design Handbook’ – written by Larry W. Mays, PH.D., PE., P.H. 7 The selected curve number was 87 for the type of soil and the observed land use corroborated by that stated in the “Soil and Land-Use Surveys” for Clarendon. 3.3 Hydraulics 3.3.1 Methodology The hydraulics was approached using a steady state analysis. The hydraulics was programmed using the Manning’s Equation for the design of an open channel (v-drain), a box drain and drain pipes. The Manning’s equation is one of the most commonly used equations governing open channel flow. The Manning’s equation is an empirical equation that applies to uniform flow in open channels and is a function of the channel velocity, flow area and channel slope. Where: Q = Flow Rate, (ft3/s) v = Velocity, (ft/s) A = Flow Area, (ft2) n = Manning’s Roughness Coefficient R = Hydraulic Radius, (ft) S = Channel Slope, (ft/ft) 3.3.2 Hydraulic Analysis of the proposed site The proposed plan is to redirect the route of the existing earth drain to a proposed open U-drain which will run along the northern boundary in a westerly direction to the western boundary of the site. The drain will then continue south along the western boundary to the southwest corner of the site before discharge into an existing culvert which will have to be upgraded. The site will then be graded to drain via overland sheet flow to internal drainage to be designed once the construction of the plant begins, and ultimately discharged to the Open Udrain being proposed along the western boundary. The proposed catchment is expected to generate a flow of 79.22 cubic metres per second for the 1 in 50 year event. The proposed U-drain will therefore be 8.6 m wide and 1.9m deep with a slope of 0.67% in order to handle the expected flow. Please see Table 3.1 which shows the calculations. 8 Table 3.1 Calculation of proposed drain size for the 50 year return period. Input Parameters Values Units 2 Area 2,233,733 m Mannings Coefficient for land 0.035 Lengths Main stream length, L 1426 m Secondary length 904 m Distance from outlet to centroid, Lc 783.2 m Elevations Lower elevation 14.00 m Upper elevation 23.50 m Upper elevation-catchment ridge 39.50 m Slope Main channel slope 0.7% Catchment slope 1.1% Ct 1.50 Cp 0.17 Runoff Coefficient, C 70% Curve Number, CN 87 Box Channel Length of main channel Slope Mannings Coefficient Width Depth Depth + freeboard R P A Velocity Flow Tt Hydrology Time of concentration Time entry Overland/shallow flow, Tt (NCCS revised) User switch (Box = 1, V = 2, Trapezoidal =3; Pipe = 4) Time of travel in main channel Values 1426 0.67% 0.015 8.600 1.500 1.88 1.1 11.6 12.9 5.8 75.35 0.068 Units m 0.083 0.042 1 0.068 hours hours Tc 0.19 hours Rainfall-24 hours ( 1 in ARI year return period) 236 mm/24hours Rainfall Intensity 128 mm/hour Rainfall Intensity for Tc 20.32 Effective Runoff Rate 79.22 9 m m m m m 2 m m/s 3 m /sec hours hours 3 m /sec The proposed drain will discharge into an existing culvert in the wouthwest corner of the site. The culvert will need to be upgraded to a box culvert of similar dimensions (8.6 m wide by 1.9m deep) to handle the 50 year return event. 4 Conclusions and Recommendations 4.1 Conclusions The following could be concluded from the analysis conducted to date: The Catchments associated with the site are primarily bounded by the natural topography in the area. Presently the site is drained by overland sheet flow to the existing earth drain which runs through the site. Anecdotal information retrieved on the site visit from 5 residents in the surrounding areas showed that there are no historical flood events on the site. 4.2 Recommendations The following are our recommendations based on the analysis and design conducted: A detailed topographic survey of the proposed site and the earth drain upstream should be conducted to confirm the expected flows reaching the site. A flood plain analysis should be conducted before internal drainage infrastructure as well as design floor levels are concluded. Use the proposed drainage infrastructure to conduct the flow out of the site Site should be graded to encourage runoff to proposed drainage infrastructure. Supplementary Paragraph An earth drain presently runs in a southerly direction from as far north as Bodles Agricultural Research Station, under Highway 2000 via a culvert before crossing the proposed site. Please see drawing attached. The catchment associated with this drain is approximately 223 HA and is denoted by the broken blue line on the drawing. During a rainfall event, water travels via over land sheet flow to the earth drain which conducts the water through the proposed site before discharge into a culvert located in the south west corner of the site. The expected runoff rate of rainfall during a 50 year storm event is 79.22 m3/s as stated in the drainage report. The direction of flow is denoted on the drawing by the magenta arrows. 10 11