EU Emissions Trading Scheme Guidance to Operators on the requirements for installations to achieve the highest applicable monitoring tiers (as defined within Commission Decision 2004/156/EC - Monitoring and Reporting Guidelines) Guidance to Operators of Offshore Installations (Incorporating Frequently Asked Questions) February 2007 Version 2 – Feb 2007 Page 1 CONTENTS 1 INTRODUCTION 3 1.1 1.2 3 3 PURPOSE BACKGROUND 2 Monitoring Tiers 4 3 Demonstration of Cost-benefits 5 Appendix 1 Offshore Sector Combustion Activities Version 2 – Feb 2007 7 Page 2 1 INTRODUCTION 1.1 PURPOSE The purpose of this guidance is to assist Operators with interpretation of the requirements of the EU Emissions Trading Scheme (EU ETS) with regard to achieving the highest standard of monitoring for carbon dioxide emissions, as prescribed in the EU Monitoring and Reporting Guidelines1 (the ‘M&R Guidelines’). It should be noted that this guidance relates specifically to the M&R Guidelines as published in Commission Decision 2004/156/EC, and will only apply to Phase I of the EU ETS. A revision of the M&R Guidelines has been published for Phase II of the EU ETS. This guidance identifies the requirements for determining each variable during Phase I of the EU ETS. This guidance also incorporates a revised draft of the “Frequently Asked Questions” prepared by the DTI for Phase I Monitoring, Reporting and Verification for Offshore Facilities. 1.2 BACKGROUND Activity specific guidelines are set out in Annexes II to XI of the M&R Guidelines, and include specific methodologies for determining the variables - activity data, emission factors, oxidation or conversion factors. For each methodology, there are one or more approaches to determining these variables. These different approaches are referred to as ‘tiers’. The increasing numbering of the tiers, from Tier 1 upwards, reflects increasing levels of accuracy, with the highest numbered tier being the preferred tier. Equivalent tiers are referred to using the same tier number and a specific alphabetic character (e.g. Tiers 2a and 2b). For those activities where alternative calculation methods are provided, an operator can only change from one method to the other if it can be demonstrated to the satisfaction of the Competent Authority that such a change will lead to a more accurate monitoring and reporting of the emissions. Section 4.2.2.1.4 of the M&R Guidelines requires that the highest tier approach shall be used by all operators to determine all variables for all sources within an installation for monitoring and reporting purposes. However, if it can be demonstrated to the satisfaction of the Competent Authority that the highest tier approach is technically not feasible, or will lead to unreasonably high costs, then operators may use the next lower tier for that variable. The selected tier will therefore reflect the highest level of accuracy that is technically feasible and does not lead to unreasonably high costs. The operator may apply different approved tiers to determine the variables - activity data, emission factors, oxidation or conversion factors - used within a single calculation. The appropriate tier for each variable will be subject to approval by the Competent Authority. 1 Commission Decision of 29 January 2004 establishing guidelines for the monitoring and reporting of greenhouse gas emissions pursuant to Directive 2003/87/EC of the European Parliament and of the Council (2004/156/EC) Version 2 – Feb 2007 Page 3 2 Monitoring Tiers A table presenting the highest tier requirements to be achieved for the monitoring of all major fuels and materials (see Box 1), together with indicative timescales for achievement of the relevant tier, is appended at Appendix 1. Box 1 ‘Major sources, including major streams of fuels and materials are those which, if ranked in order of their decreasing magnitude, cumulatively contribute at least 95% to the total annual emissions of the installation. Minor sources are those emitting 2.5 ktonnes or less per year, or those that contribute 5% or less to the total annual emissions of an installation, whichever is the highest in terms of absolute emissions. For those minor sources jointly emitting 0.5 ktonnes or less per year, or those that contribute less than 1% of total annual emissions of an installation, whichever is the highest in terms of absolute emissions, the operator of an installation may apply a de minimis approach for monitoring and reporting, using his own no-tier estimation method, subject to the approval of the competent authority.’ (Source: Section 4.2.2.1.4 of the M&R Guidelines) For minor or de minimis sources, an operator should still aim to apply the highest tier practicable, i.e. if an operator uses a metering device to meet the highest tiers identified for a major source, then the Competent Authority would normally also expect this to be applied for minor and de minimis sources. The guidance provided within the table is without prejudice to an operator’s justification that to apply the highest tiers identified would not be technically feasible or would lead to unreasonably high costs. Some guidance on how an operator might assess whether the cost of a potential improvement is either reasonable or unreasonable, by evaluating the costs and benefits of an improvement, is provided in Section 3. An operator may also determine carbon dioxide emissions using continuous emission measurement systems (CEMS) for each source, using standardised or accepted methods approved by the Competent Authority, providing that using CEMS achieves greater accuracy than the calculation of emissions using the highest tiers identified. Details of the requirements for CEMS can be found in Annex I, Sections 4.2.3, 4.3.2, and 7.2 of the M&R Guidelines). Operators should note that, in accordance with Annex I, Section 4.2.3.1 of the M&R Guidelines, emissions determined using CEMS must be corroborated by a supporting calculation of emissions applying the highest tiers identified. Monitoring of emissions using CEMS is not discussed further within this guidance. Version 2 – Feb 2007 Page 4 3 Demonstration of Cost-benefits In order to demonstrate how reasonable or unreasonable the costs of implementing a measure(s) to meet the highest tiers identified would be, an operator should evaluate the costs of implementing measures to improve metering, sampling and/or analytical accuracy against the benefits obtained. Such analysis is often referred to as a cost-benefit analysis. Section 4.2.2.1.4 of the M&R Guidelines states that: ‘The highest tier approach shall be used by all operators to determine all variables for all sources within an installation for monitoring and reporting purposes. Only if it is shown to the satisfaction of the competent authority that the highest tier approach is technically not feasible or will lead to unreasonably high costs, may a next lower tier be used for that variable within a monitoring methodology.’ Accordingly, for all major fuel or material streams, the highest tier approach must be used in all circumstances unless this can be demonstrated to be technically not feasible or will lead to unreasonably high costs. (For minor and de minimis sources, lower tiers may be applied subject to approval from the Competent Authority). Demonstration of how reasonable the costs of implementing improvement measures are should be set out in a cost-benefit analysis similar to the general approach outlined in Figure 1. Stage 1 Quantify the costs of meeting the tier requirement Stage 2 Quantify the benefits of meeting the tier requirement Stage 3 Compare the costs and benefits Figure 1 Key stages of a cost-benefit analysis A description of each of these stages is provided below. Stage 1 Quantify the costs of meeting the required monitoring tier The costs should include the capital expenditure (purchase costs) and installation and maintenance costs. If the proposed equipment (e.g. a metering device) is a replacement for an existing device (e.g. a less accurate metering device), then the maintenance costs of the new equipment must be off-set against the cost of maintaining and calibrating the current equipment. Where there is more than one technical option, the operator may select the most cost-effective measures for evaluation, i.e. those options that meet the operator’s requirements at the lowest overall cost. Stage 2 Quantify the benefits of achieving an increased accuracy The benefits should be monetised, by assessing the value of carbon dioxide allowances involved in achieving greater accuracy. For example, following an evaluation of suppliers and equipment, an operator has selected a new meter to replace his current fuel gas oil flow meter. The new meter has a manufacturer guaranteed accuracy of ±0.5% fsd, whereas the existing meter has an accuracy of ±4% fsd. Installation of the new meter would enable the operator to move from activity data Tier 2b to Tier 4b. The cost of the replacement meter is £1500 including purchase and installation costs. The marginal costs of maintaining and calibrating the new meter are considered to be £0, as these costs should be similar to those for the current meter. The current meter and its replacement are for measuring gas oil use in a boiler house that is expected to give rise to around 5000 tonnes of carbon dioxide per annum. Accordingly the amount of CO2 associated with the improvement in accuracy is given by: (4 – 0.5)/100 x 5000 = 175 tonnes Version 2 – Feb 2007 Page 5 The value of this carbon dioxide will vary with trading volumes and market demand for allowances. However, a low price could be expected to be around Є10/tonne, or about £7/tonne, of CO 2. A high price could be considered to be around Є40/tonne, or about £27/tonne, which is the mandatory penalty that must be paid by an operator if there are insufficient allowances in a trading account to cover the amount of carbon dioxide emitted and reported for a given year during Phase I. Accordingly the value of the carbon dioxide allowances potentially affected in a single year can be considered and calculated as a range given by: (175 x £7) to (175 x £27) i.e. £1225 to £4725 Stage 3 Compare the costs and the benefits (taking account of uncertainties) In this stage the cost of implementing the measure is compared with the monetised benefits. Accordingly, from the example above: The cost of moving from Tier 2b to Tier 4b is £1500 The monetised benefits range from a low estimate of £1225 to a high estimate of £4725. This range reflects the uncertainty in the assessment of the benefits. Accordingly, in this example, as the implementation cost is only marginally greater than the lowest estimate of the value of the allowances, and only about a third of the highest estimate, the cost of achieving the higher tier would be considered to be reasonable, particularly if the benefits are multiplied over the expected lifetime of the new meter. It should be noted that this is a very simplistic example, and is provided for guidance only. An operator may wish to consider other factors in the analysis, such as the remaining life of the existing meter and its residual asset value, and the anticipate life of the installation. For example, if a meter was shortly due for replacement, because it was close to the end of its useful life, then only the marginal cost of replacement should be considered i.e. the difference in the purchase and installation costs for an identical meter and the more accurate meter. However, if the existing meter was fairly new, then its remaining asset value could also be added to the replacement costs, unless the meter could be sold or usefully used elsewhere within the installation. It is not the purpose of this guidance to identify the specific point within a range of monetised benefits at which an improvement cost might be considered to be reasonable. It is for the operator to provide his/her recommendation, together with a justification. The Competent Authority will then assess each case on its merits, taking account of any wider circumstances relating to the operator’s proposal, for example the standards that are already applied at similar installations, and the verifier comments and recommendations. Version 2 – Feb 2007 Page 6 Appendix 1 Offshore Sector Combustion Activities: Tier Requirements See also Annex II of M&R Guidelines Combustion Activities Variable Highest tier Requirement Expectations Activity data Tier 4b or 3b Liquid fuels Liquid fuels Generally, Tier 4b applies to the use of most liquid fuels in combustion activities. For the offshore sector: Where liquid fuel constitutes a major source, Tier 4b should be achieved unless it would not be technically feasible or would lead to unreasonably high costs. Tier 4b requires that fuel purchase is metered, applying metering devices with a maximum permissible uncertainty of less than ± 1.0% for the metering process. Fuel consumption is calculated using a mass balance approach based on the quantity of fuel purchased and the difference in the quantity of stock held over a period of time. Compliance can be achieved by measuring fuel purchase and/or consumption using appropriate metering devices with an accuracy of better than ±1%, and by accurate determination of fuel stocks. Full implementation of requirements for offshore installations in 2006, unless otherwise agreed with DTI. Implementation of any necessary improvements by 01/01/2007, or a date notified to and agreed with the DTI. Where liquid fuel constitutes a minor source, Tier 3b should be achieved. Tier 3b requires that fuel purchase is metered, applying metering devices with a maximum permissible uncertainty of less than ± 2.0% for the metering process. Fuel consumption is calculated using a mass balance approach based on the quantity of fuel purchased and the difference in the quantity of stock held over a period of time. Compliance can be achieved through the use of appropriate metering equipment on the supplying vessel and the maintenance of accurate supply and stock records and the determination and recording of all non-fuel use (e.g. diesel used in wells). As the metering equipment on the supplying vessel is used for fiscal and costing purposes, it can be assumed that the maximum permissible uncertainty is less than ± 1.0% for the metering process. Version 2 – Feb 2007 Page 7 Combustion Activities Variable Highest tier Requirement Expectations Activity Data Tier 4a or 3a Gaseous fuels Gaseous fuels Generally, Tier 4a or 3a applies to the use of most gaseous fuels in combustion activities. For the offshore sector: For large volume users of gaseous fuels (CO2 emissions of greater than 500,000 tonnes per annum), Tier 4a should be achieved unless it would not be technically feasible or would lead to unreasonably high costs. Tier 4a requires that fuel consumption is metered without intermediate storage before combustion in the installation, applying metering devices resulting in a maximum permissible uncertainty of less than ±1.5% for the metering process. Fiscal gas meters can be supplied and installed to statutory standards, and calibrated to an accuracy of around ±1% Full implementation of requirements for offshore installations in 2006, unless otherwise agreed with DTI. Implementation of any necessary improvements by 01/01/2007, or a date notified to and agreed with the DTI. For lower volume users of gaseous fuels, Tier 3a should be achieved. Tier 3a requires that fuel consumption is metered without intermediate storage before combustion in the installation, applying metering devices resulting in a maximum permissible uncertainty of less than ± 2.5% for the metering process. Compliance can be achieved through the use of appropriate metering equipment, the implementation of appropriate service and calibration schedules for metering equipment and the accurate determination and recording of all non-fuel use (e.g. flare pilot and purge). It is recognised that, in most cases, it will be difficult to justify the costs and disruption that would be imposed by upgrading meters from Tier 3a to 4a, compared to the marginal increase in metering accuracy. In this context, it should also be noted that any sub-meters installed, for example to quantify gas take-off for flare, would have to be taken into consideration during any upgrade. Depending on the proportion of gas being metered, technical feasibility and reasonable cost, the Competent Authority would normally expect sub-meters to meet the specified accuracy for the identified tier. Version 2 – Feb 2007 Page 8 Combustion Activities Variable Emission Factor and Net Calorific Value (NCV) Highest tier Requirement Expectations Tier 3 Liquid fuels Liquid fuels Tier 3 applies to the use of liquid fuels in combustion activities. For the offshore sector: Tier 3 should be achieved unless it would not be technically feasible or would lead to unreasonably high costs. Tier 3 requires that the net calorific value representative of each batch of fuel used on an installation is measured by the operator, a contracted laboratory or the fuel supplier, in accordance with relevant CEN standards, ISO standards or National standards. Where no applicable standards exist, procedures should be carried out in accordance with any relevant draft standards or industry best practice guidelines. Tier 3 also requires that there should be representative sampling of the fuel, and subsequent analysis by a laboratory certified to ISO17025 for the determination of calorific values and carbon content. Operators should use the UKOOA emission factor, and the NCV detailed in the DEFRA emission factor spreadsheet. It is recognised that, for the vast majority of offshore installations, Tier 3 would entail unreasonably high costs. Tier 2 is therefore considered to be appropriate, and this can be achieved by using the UKOOA emission factor (3.2tonnes CO2/per tonne diesel). The NCV should be recorded as detailed in the DEFRA emission factor spreadsheet (43.32GJ/tonne). Version 2 – Feb 2007 Page 9 Combustion Activities Variable Emission Factor and Net Calorific Value (NCV) Highest tier Tier 3 Requirement Expectations Gaseous fuels Gaseous fuels Tier 3 applies to the use of gaseous fuels in combustion activities. For the offshore sector: Full implementation of requirements for offshore installations in 2006, unless otherwise agreed with DTI. For all users of gaseous fuels, Tier 3 should be achieved unless it would not be technically feasible or would lead to unreasonably high costs. Tier 3 requires that the net calorific value representative of each batch of fuel used on an installation is measured by the operator, a contracted laboratory or the fuel supplier, in accordance with relevant CEN standards, ISO standards or National standards. Where no applicable standards exist, procedures should be carried out in accordance with any relevant draft standards or industry best practice guidelines. Tier 3 also requires that there should be representative sampling of the fuel, and subsequent analysis by a laboratory certified to ISO17025 for the determination of calorific values and carbon content. For the offshore sector to achieve Tier 3, it is recommended that the minimum sampling frequency for installations with a homogeneous gas supply (i.e. there is documented evidence of stable composition) should be once per quarter, and that the minimum sampling frequency for installations with a heterogeneous gas supply (i.e. there is documented evidence of fluctuating composition, for example if the installation serves a number of fields and the composition varies with production from each field) should be once per month. It is further recommended that a representative number of samples should be analysed on each sampling occasion, and that the analyses should be undertaken using an appropriate measuring device (e.g. gas chromatograph), with calibration and maintenance underpinned by an organisation accredited to ISO 17025 to provide such a service. This organisation may be an external third party or an internal service provider. Additional sampling should be undertaken if there is a change in fuel type (e.g. a new field is brought on stream, significantly change the fuel gas composition), prior to recommencing the appropriate minimum sampling frequency. Non-accredited in-house analyses are considered to be acceptable for the routine analyses, but wherever possible they should be backed-up by less frequent calibration analyses undertaken by an ISO17025 accredited laboratory. The minimum frequency of such analyses should be once per year, although it may be necessary to undertake more frequent analyses if there is a heterogeneous gas supply or there are significant discrepancies between the in-house and calibration analyses. Where there is good agreement between the in-house and calibration analyses, the results of the in-house analyses may be used in the calculation of the NCV and emission factor. Where there is poor agreement, the minimum frequency of the calibration analyses should be once per quarter, and the results of the calibration analyses should be used in the calculation of the NCV and emission factor. In all cases, the operator will need to develop a robust sampling and analysis programme, to provide evidence that the samples taken are representative of the “batch” of fuel burned and that the sample handling and storage procedures for calibration analyses do not lead to sample degradation. The operator will also need to provide details of the comparison between the in-house and calibration analyses, and the quality checks required under Section 7.3 of the M&R Guidelines. Version 2 – Feb 2007 Page 10 Combustion Activities Variable Highest tier Oxidation factors 1 Requirement Expectations Liquid and gaseous fuels Liquid and gaseous fuels Tier 1 is the only applicable tier for liquid and gaseous fuels Operators should use an oxidation factor of 0.995. For the offshore sector: Offshore operators should use an oxidation factor of 0.995, as required by the EU ETS M&R Guidelines. Version 2 – Feb 2007 Page 11