Tender No.: 7559/07 PART 1 GENERAL 1.1 GENERAL .1 1.2 Section 02242 Turbidity Barriers Page 1 The Contractors operations will be subject to the maximum allowable increase in total suspended solids (Max-TSS) within the watercourse. DEFINITIONS .1 “Instream” means those parts of the bed and banks of a water body that are both with and without terrestrial vegetation. .2 “Max-TSS” means the maximum allowable increase of total suspended solids in the watercourse from the levels at the compliance point downstream of the turbidity control structure from those immediately upstream of the worksite containment. .3 “Visually Conspicuous Plume” means a plume of suspended solids that can be visually observed in the watercourse. .4 “Normal Construction Activity” means any construction activity that will not cause elevated turbidity levels, and no visual indications of elevated turbidity levels. .5 “Scheduled Construction Activity” means any planned activity that can be expected to result in additional turbidity in the watercourse, including the installation and removal of cofferdams, silt curtains, placing of riprap in the water, grading, etc. .6 “Accidental Occurrence” means any situation, beyond the Contractor’s control, that results in elevated turbidity levels in excess of the specified compliance limits, including situations like the unexpected breaching of a cofferdam due to flood conditions exceeding the design levels. 1.3 SAMPLING AND TESTING (QUALITY CONTROL AND QUALITY ASSURANCE) .1 Perform all sampling and testing of total suspended solids as specified herein. .2 Provide copies of the results of all sampling and testing in a daily summary format. Upon completion of Construction Activities, submit a final report containing all sampling and testing data. .3 The Minister will carry out random quality assurance inspection as a means to monitor the Contractor’s quality control program. Assist and cooperate with the Minister during the collection of water quality samples. .4 Prior to the start of construction, carry out sufficient testing to determine the normally occurring linear relationship between total suspended solids Section 02242 Turbidity Barriers Page 2 Tender No.: 7559/07 concentration and turbidity in the watercourse. Pay services of a qualified laboratory to determine the relationship. .5 Take at least 15 test samples and establish the linear relationship. Follow the procedures outlined in www.transportation.alberta.ca, Environmental Management. .6 During construction, perform the following: 1.4 .1 Measure the suspended solids in Nephelometric Turbidity Units (NTU) accurate to within 2%. .2 Convert NTU into mg/l using the industry standard method. .3 Measure upstream and downstream NTU levels within 30 minutes of each other, unless there is a sediment release (see monitoring frequency below). .4 Take one measurement at one-half the depth of the watercourse for watercourses less than one metre in depth. For watercourses greater than one metre in depth, take two measurements, one at 20% depth and one at 80% depth of the watercourse. SAMPLING FREQUENCY .1 Perform total suspended solid sampling at the following frequency: Site Condition Monitoring Frequency Normal Construction Activities During instream work, sample twice a day, at intervals more than eight hours apart, both at the upstream background site and all specified downstream compliance sites(1). Scheduled Construction Activities and Accidental Occurrences During daylight hours, sample as frequently as possible, and as directed by the Minister, at the upstream background site and the specified downstream compliance sites until total suspended solids (TSS) levels have returned to acceptable background limits. Note(1): With prior approval of the Minister, testing frequency may be reduced if the Contractor’s environmental controls are determined to be effective at controlling turbidity to less than 5 mg/l in excess of normal background levels for a period of five consecutive days. Section 02242 Turbidity Barriers Page 3 Tender No.: 7559/07 1.5 COMPLIANCE POINT LOCATIONS .1 Monitor the total suspended solids at the following compliance point locations: Type of Watercourse Downstream Compliance Point Distance 1 (1) Downstream Compliance Point Distance 2 Downstream Compliance Point Distance 3 Ponded systems such as lakes, pools, wetlands and similar other waterbodies where velocities are less than 0.5 m/s The lesser of 30 m, or the maximum surface dimension of the waterbody. Samples must be taken 30 m apart around the circumference of the turbidity barrier. 20 m (dependent on the size of the waterbody). Samples must be taken 30 m apart around the circumference of the turbidity barrier. 20 m (dependent on the size of the waterbody). Samples must be taken 30 m apart around the circumference of the turbidity barrier. Wetted streams less than 10 m wide 1 stream width downstream (1) 2 stream widths downstream (1) 3 stream widths downstream (1) Wetted streams between 10 m and 30 m wide 30 m downstream (1) 60 m downstream (1) 90 m downstream (1) Wetted streams greater than 30 m but less than 60 m wide 60 m downstream (1) 120 m downstream (1) 180 m downstream (1) Wetted streams greater than 60 m wide 90 m downstream (1) 180 m downstream (1) 270 m downstream (1) Note (1): If there is a plume then measure total suspended solids at various locations across the watercourse, in accordance with the following: 1. Take samples from the middle of the plume. 2. Take samples as close to the source of the plume as possible (within safety limits). 3. If the watercourse is less than 5 m wide then only one measurement is required across the stream width. Take measurement within the plume. 4. If the watercourse is greater than 5 m wide, measurement must be taken at a minimum of three locations across the watercourse; within the plume, halfway across the channel, and 2/3 of the channel width measured from the bank closest to the point where the discharge originated. Section 02242 Turbidity Barriers Page 4 Tender No.: 7559/07 1.6 MAXIMUM ALLOWABLE INCREASE OF TOTAL SUSPENDED SOLIDS .1 Visual Limits .1 .2 In the event that a Visually Conspicuous Plume does exist, cease all activities which will have the potential to generate sediment in the watercourse. Compliance Criteria .1 Criteria are set by the Canadian Council of Ministers of the Environment Guidelines. .2 Utilize equipment, labour and procedures in a manner that ensures the maximum allowable levels of suspended solids are maintained at or below the following levels: Site Conditions Compliance Criteria – (MAX-TSS in Excess of Normal Background Levels) Contractor Action if TSS exceeds the Compliance Criteria Normal Construction Activity 5 mg/l in excess of normal background levels is continuously allowed (2) Notify the Minister immediately. Cease all instream work and immediately initiate remedial works. If compliance criteria is exceeded for 2 or more hours, follow the Contractor Actions for Accidental Occurrences and/or Scheduled Construction activities. Accidental Occurrences 150 mg/l not exceeding 2 hours in duration and at no time exceeding 250 mg/l (3) Notify the Minister immediately. Cease all in-stream work and immediately initiate remedial works. If compliance criteria is exceeded for 2 or more hours, notify authorities for Regulatory Requirements in accordance with the Environmental Management System Manual. Section 02242 Turbidity Barriers Page 5 Tender No.: 7559/07 Scheduled Construction Activities When background levels are less than or below 250 mg/l (2) 1. A maximum increase of 25 mg/l 2. 5 mg/l for a 30 day period 3. 25 mg/l for a 24 hour period 4. At no time are 250 mg/l to be exceeded When background levels are above 250 mg/l 1. TSS may be increased by 10% above background levels for a 24 hour period 2. TSS may be increased by 2% above background levels for a 30 day period Note (2): Note (3): 1.7 Notify the Minister immediately. Cease all in-stream work and immediately initiate remedial works. Complete the Scheduled Construction activities in an 8 hour day or cease all instream works until TSS levels return to acceptable limits. If compliance criteria is exceeded for 2 or more hours, notify authorities for Regulatory Requirements in accordance with the Environmental Management System Manual. The Canadian Council of Ministers of the Environment Suggested guideline for Accidental Occurrences .3 Notify the Minister at least 48 hours prior to the start of any Scheduled Construction Activity. .4 In the event of an Accidental Occurrence that results in a Visually Conspicuous Plume of sediment, immediately notify the Minister and undertake any mitigative actions necessary to comply with the specified compliance criteria. SUBMITTALS .1 Provide the following submittals: .2 Shop Drawings of the turbidity barriers detailing the components and the material specifications of the components, 15 days prior to commencement of the Work. Provide a turbidity barriers system that has been designed and stamped by a professional Engineer registered with the Association of Professional Engineers, Geologists and Geophysicists of Alberta or a specialist in such Work authorized by the Minister. .3 Turbidity Control Execution Plan outlining the location of the turbidity barriers, the method of installation, anchorage details, maintenance and inspection procedures, the removal and storage procedures and contingency plans in case of a breach in the turbidity curtain, 15 days prior to commencement of the Work. .4 Final report referred to in 1.3.2. Section 02242 Turbidity Barriers Page 6 Tender No.: 7559/07 PART 2 PRODUCTS – NOT USED PART 3 EXECUTION 3.1 INSTALLATION .1 Install provisions for turbidity control at the Travers Inlet site during all periods of construction that may impact the quality of water in Travers Reservoir including at least the following: .1 .2 Initial construction of the cofferdam. Placement of riprap and bedding material. .2 Install the temporary turbidity barrier system in accordance with the turbidity control execution plan. .3 Remove the turbidity barriers during the periods they are not required. END OF SECTION