Lean as a process improvement tool for infrastructure maintenance Presentation by John Amoore EFRTC Paris 4 October 2012 www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Part One Selection of the most appropriate method for process improvement www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Improving business performance Companies facing increasing competition or other external pressures frequently implement established methods for improving business performance Three of the most commonly applied tools are: o Six Sigma o Theory of constraints o Lean www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Why has Automain selected Lean rather than another or a combination of all three Although there are similar characteristics in these techniques, key defining differences are o Six Sigma (6s) o problem-focused, with a view that process variation is waste. Improved performance through statistical methods (SPC) o Theory of Constraints (ToC) o Understanding the weakest link (bottleneck) in the process chain o Lean o Elimination of all forms of waste – over processing, time, resources etc These methods may be combined into an integrated system LSS-ToC www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Why Lean is preferred There are good reasons for selecting Lean for railway maintenance. Mean Area 68.26% One standard deviation s Six sigma equates to 3.4 defectives per million and is ideal in situations where there is an abundance of data, mathematical tools are appropriate and there is little process variability ToC is concerned with improving the system constraint in a total system approach Lean uses a visualisation approach to reduce waste and minimise the total elapsed time for a process Area 95.44% -1s +1s -2s -3s +2s +3s www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Value stream map and added value The value-stream map of the service we provide (infrastructure capacity at lowest LCC) includes value-added and non-value-added activities Value-added processes are those that meet three criteria the customer is willing to pay for it our action physically changes the infrastructure we work on or contributes to its life it is done right the first time Adding value is another way of saying generating revenue (capacity). If it doesn’t generate revenue then it must add cost, not value Some internet services add value at almost no cost www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission process cycle efficiency (PCE) PCE = Value-Added Time / Total Elapsed Time A Lean process produces a PCE of 25 percent or more. Most business processes are not Lean. One of the main goals of Lean is to increase process velocity. Improving PCE achieves that goal by eliminating non-value-added activities from the process. As IMs migrate towards predictive maintenance, process velocity needs to improve www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Lean plus innovation delivers greatest benefit maintenance process Enter on Plan reduced opportunity for waste possession Return to normal service reduced possession www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Six Sigma or Lean Thinking LEAN THINKING SIX SIGMA VIEW OF WASTE APPLICATION TOOLS FOCUS Variation is waste 1. 2. 3. 4. 5. Define Measure Analyse Improve Control Non value added is waste 1. 2. 3. 4. 5. Identify Value Define Value Stream Determine Flow Define Pull Improve Process Statistics tool set Visualization Problem focused Process flow focused www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Lean and process variation Will LEAN work where there is process variation? Let us examine a generic value stream map for making almost any Pizza. The map may be a standard format having different parameters for ingredients, cooking temperature and cooking time BUT IT WILL STILL IDENTIFY PROCESS WASTE FOR ALL PIZZAS ………..however www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Lean and process variation A value stream map will identify process waste for thick and thin base pizzas and hundreds of sizes and toppings Stock check ingred ients Dispose and reorder Prioritise orders ……..but may produce a disappointing chocolate pudding Preheat oven Form Pizza dough Apply topping To order use dusted peel to apply pizza to stone Bake pizza checking after 5 mins Remove pizza when baked Serve pizza to customer www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Part Two Process improvement in AutoMain www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission The approach o to undertake Structured Observations of the maintenance process o to map out the maintenance and planning processes during Value Stream Mapping (VSM) workshops, quantification of key parameters wherever possible (the duration of the task, the manpower required, the probability of each step occurring right first time etc.) o to produce a Hand Off Diagram Lean provides an opportunity to re-connect management with what is happening at ground level www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Structured Observations Key timings and observations were recorded, and the utilisation of time was subsequently broken down into 5 generic tasks: o confirmation = confirming granting of possession o waiting = waiting for equipment to arrive o communication = phone calls and creation of documentation o tamping = carrying out the tamping activity o transportation = moving of tamping equipment to location This information was then presented in graphical format, along with a summary of the observations made during the course of the visit. www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Value Stream Mapping (VSM) Workshops the planning process is of equal (if not greater) importance: o maintenance needs to be carefully planned to avoid waste – the overall maintenance process will only be efficient if the right machine and staff are sent to the right location at the right time o the move towards predictive maintenance – it is therefore important that the maintenance planning process can react sufficiently quickly to cope with this It was therefore considered important to map out not only a typical maintenance possession, but also the planning process leading up to that possession www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Findings – Structured Observations Shift utilisation (how the tamping crews spent their time) o confirmation 6% to 15% o waiting 7% to 25% o communication 1% to 10% o transportation 17% to 21% o tamping 42% to 50% −a recording run prior to tamping accounted for 9% of the Network Rail possession −the SNCF, Trafikverket and ProRail maintenance was targeted at specific locations within the possession, whereas the Network Rail and DB maintenance was undertaken on a continuous length of track −the number of concurrent processes was different between administrations which potentially increases productivity at the cost of extra manpower and possibility of conflicts www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission NNVA - Necessary Non-Value Added VA - Value Added Totals (Minutes) 360 176 34 150 1. Waiting - Granting of Possession 45 45 2. Waiting - Arrival of Tamper 30 30 3. Pre-shift Brief 59% of the Possession spent on Non Value Added tasks Break down of time utilisation during a planned 6 hour possession on 12/09/2011 4. Tamping Machine Set Up 5. Carry out 'Recording Run' 1,600 M 6. Review 'Recorded Data' and Set up Tamper 7. Tamping Operation Total NVA - Non-Value Added (Waste) Possession Utilisation 5 5 8 8 12. Tamper 'Sweep the possession' (approx - not seen) 11. Waiting for permission to send Tamper 13. Unutilised time 2. Waiting - Arrival of Tamper 1. Waiting Granting of Possession 3. Pre-shift Brief 10. Paperwork and Report Writing 16 16 11 11 150 8. Set Tampers to Travel Positions Utilisation of Available 'Possession Time' 4. Tamping Machine Set Up 9. Check Results of Track levelness 'Traces' 5. Carry out 'Recording Run' 1,600 M 150 2 2 8. Set Tampers to Travel Positions Objective: 9. Check Results of Track levelness 'Traces' 5 5 10. Paperwork and Report Writing 13 11. Waiting for permission to send Tamper 5 5 12. Tamper 'Sweep the possession' (approx - not seen) 30 30 13. Unutilised time 40 40 7. Tamping Operation 6. Review 'Recorded Data' and Set up Tamper 13 Identify the reasons – Why? www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Tamping Process – Value Stream Map Concerns and Improvement Ideas collected from all AutoMain Tamping Experts www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Hand-Off Diagram www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Tamping Process – Value Stream Map 394 Value Stream Map completed for all 5 Automain Partner Organisations Total Improvement opportunities identified www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Tamping Process – Opportunities Stratified No Concern Improvement Idea 114 Tamper given low priority if there is an operational incident 115 Tamper transit route sometimes blocked by late running trains 116 Mismatched understanding of plan between PICOP and Signaller Create access points closer to regularly used signals 117 118 Planners don't take account of location of signals in relation to access points 119 Auto PLB at standard blocking points Stop using Detonators and PLB - Use 'Signal Protection' only 120 IN: Ideas Recorded Strukton Deutsch Network SNCF (Sweden & bahn Holland) Rail x x x x x x x x Category Effort Benefit Rank Standard Planning Procedures H L 0 Problem and Countermeasure L H 3 Training and Communication L H 3 Infrastructure Development H H 2 Standard Planning Procedures L H 3 Standard Operating Procedure L H 3 Standard Operating Procedure L H 3 OUT: - Categorisation - Evaluation - Project Stream Definition www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Tamping Process – Project Stream Definition 1. Planning Systems Development - Largest Opportunity Causation Factors 2. Data Systems Development Key Point: 3. Standard Operations Procedures Why – 59% Nonare Value Added Tasks Opportunities identified: But4. Training and Communications Stratified 7 main Improvements can only be 5. Technical Development realised through Implementation ‘Streams’ for development 7 High Level Project Streams Identified 6. Total Productive Maintenance (TPM) 7. Problem & Countermeasure Systems www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Visualisation of Results www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Ideas and suggestions – VSM Workshops It was suggested that frequent track recording using inservice vehicles would provide the rate of deterioration information necessary to support a more responsive maintenance planning process. But others suggested that trend analysis based on the measurements currently made by dedicated track recording trains is sufficient to predict when maintenance will be required planners have a great deal of skill and experience, it was highlighted that there are no specific software tools available to support decisions for aligning requirements and resources www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Ideas and suggestions – VSM Workshops It was further suggested that maintaining track to a very high quality could reduce the overall deterioration rates. By contrast, more than one workshop suggested that a significant proportion of tamping actually makes track quality worse (as much as 25%). This is a further case for decision support tools www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Opportunities for Lean Approaches o there was a low level of standardisation in terms of infrastructure design (e.g. variable sleeper types and spacing) which further complicates the planning process o there is considerable potential to improve the overall Life Cycle Cost through improvements in the planning stage and decision support tools www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Conclusions The following comments do not apply to all IMs as a number of these practices are already in use by some companies There is scope to reduce the duration of possessions by employing best practice such as using data from track recording cars to calculate vertical and lateral alignment corrections, having multiskilled staff, and enabling adjacent lines to remain open to bidirectional traffic during maintenance. Technological developments that could further enhance productivity include multi-functional high output machines capable of recording and working in either direction, and which minimise set up times on site There is scope to improve the planning of track maintenance, and this appears to have even greater potential to reduce overall possession times than improvements to the actual maintenance processes and technology www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Conclusions Tamping targets based on track lengths maintained may result in unnecessary maintenance activity Longevity and quality of the maintenance may be more appropriate Predictive maintenance based on rate of change of track geometry and other condition data requires a more reactive approach with a shorter interval between planning and implementation Such a targeted approach could increase ballast life, minimise possessions and reduce costs www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Conclusions Lean thinking is an appropriate tool for investigating process improvement for railway infrastructure maintenance Process variation may be accommodated providing that mapping is performed by a team having the necessary knowledge to fully understand the differences, and we do not confuse pizza with chocolate pudding Some IMs involved in this project are extending the implementation of Lean thinking into other maintenance activities www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission Thank you www.automain.eu A Joint Research Project funded under the Seventh Framework Programme (FP7) of the European Commission