Lean Six Sigma Improve Phase Tollgate Review Lean Six Sigma DMAIC Tools and Activities Review Project Charter Validate High-Level Value Stream Map and Scope Voice of the Customer & Voice of the Business Validate Problem Statement and Goals Validate Financial Benefits Create Communication Plan Select and Launch Team Develop Project Schedule Complete Define Tollgate Validate Define Project Charter Voice of the Customer Value Stream Map Flow Identify Key Input, Process and Output Metrics Operational Definitions Develop Data Collection Plan Validate Measurement System Collect Baseline Data Determine Process Capability Complete Measure Tollgate Develop Measure and Kano Analysis SIPOC Map Project Valuation/ROIC Analysis Tools RACI and Quad Charts Stakeholder Analysis Communication Plan Effective Meeting Tools Inquiry and Advocacy Skills Time Lines, Milestones, and Gantt Charting Pareto Analysis Value Stream Mapping Process Cycle Efficiency/Little’s Law Operational Definitions Data Collection Plan Statistical Sampling Measurement System Analysis (MSA) Gage R&R Kappa Studies Control Charts Spaghetti Diagrams Histograms Normality Test Process Capability Analysis Identify Root Causes Reduce List of Potential Root Causes Confirm Root Cause to Output Relationship Estimate Impact of Root Causes on Key Outputs Prioritize Root Causes Value-Add Analysis Takt Rate Analysis Quick Wins Statistical Analysis Complete Analyze Tollgate Analyze Process Constraint ID and Takt Time Analysis Cause & Effect Analysis FMEA Hypothesis Tests/Conf. Intervals Simple & Multiple Regression ANOVA Components of Variation Conquering Product and Process Complexity Queuing Theory Develop Potential Solutions Evaluate, Select, and Optimize Best Solutions ‘To-Be’ Value Stream Map(s) Develop and Implement Pilot Solution Implement 5s Program Develop Full Scale Implementation Plan Cost/Benefit Analysis Benchmarking Complete Improve Tollgate Develop Develop SOP’s, Training Plan & Process Controls Implement Solution and Ongoing Process Measurements Confirm Attainment of Project Goals Identify Project Replication Opportunities Training Complete Control Tollgate Transition Project to Process Owner Improve Replenishment Pull/Kanban Stocking Strategy Process Flow Improvement Process Balancing Analytical Batch Sizing Total Productive Maintenance Design of Experiments (DOE) Solution Selection Matrix Piloting and Simulation Work Control System Setup reduction Pugh Matrix Pull System Control Mistake-Proofing/ Zero Defects Operating Procedures (SOP’s) Process Control Plans Visual Process Control Tools MGPP Statistical Process Controls (SPC) Solution Replication Visual Workplace Metrics Project Transition Model Team Feedback Session Standard Kaizen Events Targeted in Measure to Accelerate Results International Standards for Lean Six Sigma 2 Analyze Overview Hypothesis Tests Example: ANOVA Example: ANOVA Example: Chi Squared Example: Pareto Factor (x) Tested Value Add Analysis - Current State p Value Location Part vs. No Part Department Region Observations/Conclusion 0.030 Significant factor - 1 hour driving time from DC to Baltimore office causes ticket cycle time to generally be longer for the Baltimore site 0.004 Significant factor - on average, calls requiring parts have double the cycle time (22 vs 43 hours) 0.000 Significant factor - Department 4 has digitized addition of customer info to ticket and less human intervention, resulting in fewer errors n/a South region accounted for 59% of the defects due to their manual process and distance from the parts warehouse Takt Tim e = 55 Task Time (seconds) Hypothesis Test (ANOVA, 1 or 2 sample t - test, Chi Squared, Regression, Test of Equal Variance, etc) Value-Add Analysis Effect Root cause: Effect Root cause: Effect 40 20 0 2 3 4 CVA Time 5 6 Task # BVA Time 7 8 9 10 NVA Time Tools Used Root Cause / Effect Root cause: 60 1 Describe any other observations about the root cause (x) data 80 Value Add Analysis One-Way ANOVA Two-Way ANOVA Pareto Plots Simple Linear Regression Multiple Regression Test for Equal Variance Scatter Plots C&E Matrix Complexity Cause & Effect Diagram Kaizen/Quick Wins FMEA Control/Impact Chart T-Test Other Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 3 To-Be Process Map Client Mgr Client HR Notify HR of employee exit date Avg. Cycle time = 0 days Places information into HR EXIT database Utilize web tool to submit a delete request to vendor Client Contact NT Admin Access database daily Avg. Cycle time = 1 day Create Work Request Email Vendor Avg. Cycle time = 1 day Delete account Admin closes work request and manager notified Avg. Cycle time = 1 day Avg. Cycle time = 1 day Admin Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 4 Quick Win Documentation Template Process Name: __________________ Process Lead: ___________________ Process Owner: ______________________ Start Date: ______________ Process Area: ________________________ Stop Date: ______________ 1. 2. 3. 4. 5. 6. Root Cause: _________________________________________________ Obvious Solution: __________________________________________ Low or No Cost: __________________________________________ 5s 4-Step Setup Reduction Low Risk: ________________________________________________ Inventory Reduction Implementation Plan: ______________________________________________ MSA Improvements Stakeholder (s) Approval: ___________________________________________ Price reductions Reduced DOWNTIME Benefits: (NVA steps or work) __________________________________________________________ Pull System __________________________________________________________ Kaizen events Other __________________________________________________________ Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 5 FMEA Example Document delay of not scheduled Received delivery User forgot to update system 7 and send document 3 Call user to escalate issue New RPN New Detection # New Occurance # Current Control New Severity # Causes of Failure Target Actual Date Recommended Completion Action Action Responsibility Date Completed Ima N. Charge, Automate system Program settings for Manager 7 147 missing field 9/30/2005 10/20/2005 7 1 1 7 values and auto Joe Schmoe, send Process Mgr RPN Item/ Process Step Potential Potential Failure Failure Mode Effects Detection # Occurrence # Risk Analysis recommended actions (Key Speaking Points) Rating Index Total Current RPN Risk Severity # Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 6 Value Stream Map (VSM) Future State Information Flow Sources of Value Supplier Customer <Step1> <Step3> <Step3> 1 2 1 ? ? ? ? ? Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 7 Business Impact State financial impact of future project leverage opportunities Separate “hard or Type 1” from “soft Type 2 or 3” dollars Annual Estimate Type 1: ? Type 2: ? Type 3: ? Replicated Estimate • • • Type 1: ? Type 2: ? Type 3: ? 1: ? 2: ? 3: ? • • • Type 1: ? Type 2: ? Type 3: ? Type 1: ? • Type 2: ? • Type 3: ? • • • • Type 1: ? Type 2: ? Type 3: ? • • • Type 1: ? Type 2: ? Type 3: ? • • • Type 1: ? Type 2: ? Type 3: ? • • • Type 1: ? Type 2: ? Type 3: ? Revenue Enhancement • • • Expenses Reduction • Type • Type • Type Loss Reduction • Cost Avoidance Total Savings Type 1: ? • Type 2: ? • Type 3: ? Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 8 Business Impact Details Type 1: Describe the chain of causality that shows how you determined the Type 1 savings. (tell the story with cause–effect relationships, on how the proposed change should create the desired financial result (savings) in your project ) Show the financial calculation savings and assumptions used. Type 2: Describe the chain of causality that shows how you determined the Type 2 savings. (tell the story with cause–effect relationships, on how the proposed change should create the desired financial result (savings) in your project ) Show the financial calculation savings and assumptions used. Assumption #1 (i.e. source of data, clear Operational Definitions?) Assumption #2 (i.e. hourly rate + incremental benefit cost + travel) Assumption #1 (i.e. Labor rate used, period of time, etc…) Assumption #2 (i.e. contractor hrs or FTE, source of data, etc…) Describe the Type 3 Business Impact(s) areas and how these were measured Assumption #1 (i.e. project is driven by the Business strategy?) Assumption #2 (i.e. Customer service rating, employee moral, etc…) Other Questions Stakeholders agree on the project’s impact and how it will be measured in financial terms? What steps were taken to ensure the integrity & accuracy of the data? Has the project tracking worksheet been updated? Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 9 Current Status Key actions completed Issues Lessons learned Communication, team building, organizational activities Lean Six Sigma Project Status and Planning Deliverables/Tasks Completed last week Upcoming Deliverables/Tasks - 2 weeks out Comment Due Revised Due For deliverables due thru: Actions Scheduled for next 2 Weeks Deliverable/Action Who Due Revised Due Commen Current Issues and Risks Who Due Revised Due Recomm Issue/Risk Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 10 Next Steps Key actions Planned Lean Six Sigma Tool use Questions to answer Barrier/risk mitigation activities Lean Six Sigma Project Issue Log No. Description/Recommendation Status Open/Closed/Hold Last Revised: Revised Due Due Date Resp Comments / Resolution Date 1 2 3 4 5 6 7 8 9 10 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 11 Improve Summary Vital X (root cause) Proof of Causation Practical Solution (process change Operating to address X) Tolerances for X Eliminate process - Place accountability n/a on Client HR for information placed into new database. Client IT need to reverify all exit data received from Client HR Average delay between reception of information from Client HR until it reaches NT Admin or general admin E-mail vendor's contract with Client The SLA has a range of 35 business days for the completion of a delete request E-mail vendor instituted new web interface for all add/delete requests, vastly improving request processing time. 1 - 2 days E-mail vendor's contract with Client The SLA has a range of 35 business days for the completion of a delete request E-mail vendor instituted new web interface for all add/delete requests, vastly improving request processing time. 1 - 2 days Solution Selection Criteria How the solution was determined: • What was the solution selection tool used? • What project management tools were used? • Cost/benefit analysis? • Include any other tools or methods used Pilot and Implementation Plan 1. 2. 3. 4. 5. ? ? ? ? ? Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 12 Sign Off I concur that the Improve phase was successfully completed on MM/DD/YYYY I concur the project is ready to proceed to next phase: Analyze Enter Name Here Green Belt/Black Belt Enter Name Here Enter Name Here Sponsor / Process Owner Financial Representative Enter Name Here Deployment Champion Enter Name Here Master Black Belt Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 13 Tollgate Reviews Backup Slides D M A I C Project Charter Financial Impact Problem/Goal Statement Problem: Describe problem in non-technical terms Statement should explain why project is important; why working on it is a priority Goal: Goals communicate “before” and “after” conditions Shift mean, variance, or both? Should impact cost, time, quality dimensions Express goals using SMART criteria Specific, Measurable, Attainable, Resource Requirements, Time Boundaries Explain leverage and strategic implications (if any) Team State financial impact of project Expenses Investments (inventory, capital, A/R) Revenues Separate “hard” from “soft” dollars State financial impact of leverage opportunities (future projects) Tollgate Review Schedule PES Name Project Executive Sponsor (if different from PS) PS Name Project Sponsor/Process Owner DC Name Deployment Champion GB/BB Name Green Belt/Black Belt MBB Name Master Black Belt Core Team Role % Contrib. LSS Training Team Member 1 SME XX YB Team Member 2 TM XX GB Team Member 3 SME XX PS Extended Team Team Member 1 BFM XX Not Trained Team Member 2 IT XX Not Trained Tollgate Scheduled Revised Define: XX/XX/XX Measure: XX/XX/XX XX/XX/XX Analyze: XX/XX/XX XX/XX/XX Improve: XX/XX/XX XX/XX/XX Control: XX/XX/XX XX/XX/XX Review high-level schedule milestones here: Phase Completions Tollgate Reviews Complete XX/XX/XX XX/XX/XX XX/XX/XX XX/XX/XX XX/XX/XX Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 15 Measure Overview Process Capability I -M R C h a r t o f D e l i v e r y T i m e 40 U C L= 3 7 . 7 0 I n d iv id u a l V a lu e CTQ: ? Unit (d) or Mean (c): ? Defect (d) or St. Dev. (c): ? PCE%: ? DPMO (d): ? Sigma (Short Term): ? Sigma (Long Term):? MSA Results: show the percentage result of the GR&R, AR&R or other MSA carried out in the project 35 _ X= 2 9 .1 3 30 25 LC L= 2 0 . 5 6 20 1 28 55 82 109 136 163 190 217 244 O b s e r v a tio n U C L= 1 0 . 5 3 10.0 M o v in g R a n g e Graphical Analysis 7.5 5.0 __ M R = 3.22 2.5 0.0 LC L= 0 1 28 55 82 109 136 163 190 217 244 O b s e r v a tio n Root Cause / Quick Win Root cause: Quick Win #1 Root cause: Quick Win #2 Root cause: Quick Win #3 Tools Used Detailed process mapping MSA Value Stream Mapping Data Collection Planning Basic Statistics Process Capability Histograms Time Series Plot Probability Plot Pareto Analysis Operational Def. 5s Pull Control Charts Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 16 Analyze Tollgate Checklist Has the team examined the process and identified potential bottlenecks, disconnects and redundancies that could contribute to the problem statement? Deliverables: Has the team analyzed data about the process and its performance to help stratify the problem, understand reasons for variation in the process, and generate hypothesis as to the root causes of the current process performance? Prioritized List of Validated Root Causes Has an evaluation been done to determine whether the problem can be solved without a fundamental recreation of the process? Has the decision been confirmed with the Project Sponsor? Has the team investigated and validated (or devalidated) the root cause hypotheses generated earlier, to gain confidence that the “vital few” root causes have been uncovered? Does the team understand why the problem (the Quality, Cycle Time or Cost Efficiency issue identified in the Problem Statement) is being seen? Has the team been able to identify any additional ‘Quick Wins’? Have learnings to-date required modification of the Project Charter? If so, have these changes been approved by the Project Sponsor and the Key Stakeholders? Have any new risks to project success been identified, added to the Risk Mitigation Plan, and a mitigation strategy put in place? List of Potential Root causes Additional “Quick Wins”, if applicable Refined Charter, as necessary Updated Risk Mitigation Plan Deliverables Uploaded to Central Storage Location or Deployment Management System Tollgate Review Has the team identified the key factors (critical X’s) that have the biggest impact on process performance? Have they validated the root causes? International Standards for Lean Six Sigma 17 17 Improve Tollgate Checklist What techniques were used to generate ideas for potential solutions? What narrowing and screening techniques were used to further develop and qualify potential solutions? What evaluation criteria were used to select a recommended solution? Do proposed solutions address all the identified root causes, at least the most critical? Were the solutions verified with the Project Sponsor and Stakeholders? Has an approval been received to implement? Was a pilot run to test the solution? What was learned? What modifications made? Has the team seen evidence that the root causes of the initial problems have been addressed during the pilot? What are the expected benefits? Has the team considered potential problems and unintended consequences (FMEA) of the solution and developed preventive and contingency actions to address them? Has the proposed solution been documented, including process participants, job descriptions and if applicable, their estimated time commitment to support the process? Has the team developed an implementation plan? What is the status? Have changes been communicated to all the appropriate people? Has the team been able to identify any additional ‘Quick Wins’? Have ‘learning's’ to-date required modification of the Project Charter? If so, have these changes been approved by the Project Sponsor and the Key Stakeholders? Have any new risks to project success been identified and added to the Risk Mitigation Plan? Deliverables: Prioritized List of Solutions “To-Be” Value Stream Map(s) Pilot Plan & Results Approved Solution and Detailed Implementation Plan Additional “Quick Wins”, if applicable Refined Charter, as necessary Updated Risk Mitigation Plan Deliverables Uploaded to Central Storage Location or Deployment Management System Tollgate Review Has the team developed improvement solutions for the critical X’s, piloted the solution and verified that the solution will solve the problem? International Standards for Lean Six Sigma 18 Control Tollgate Checklist Has the team prepared all the essential documentation for the improved process, including revised/new Standard Operating Procedures (SOP’s), a training plan and a process control system? Has the necessary training for process owners/operators been performed? Have the right measures been selected, and documented as part of the Process Control System, to monitor performance of the process and the continued effectiveness of the solution? Has the metrics briefing plan/schedule been documented? Who owns the measures? Has the Process Owner’s job description been updated to reflect the new responsibilities? What happens if minimum performance is not achieved? Has the solution been effectively implemented? Has the team compiled results data confirming that the solution has achieved the goals defined in the Project Charter? Has the Benefits Realization Schedule been verified by the Financial Representative? Has the process been transitioned to the Process Owner, to take over responsibility for managing continuing operations? Do they concur with the control plan? Has a final Storyboard documenting the project work been developed? Has the team forwarded other issues/opportunities, which were not able to be addressed, to senior management? Have “lessons learned” been captured? Have replication opportunities been identified and communicated? Has the hard work and successful efforts of our team been celebrated? Deliverables: SOP’s Training Plan Process Control System Benefits Realization Schedule, validated by Financial Representative Validated Solution Replication/ Standardization Plan Lessons Learned Transitioned Project Project Risk Performance Deliverables Uploaded to Central Storage Location or Deployment Management System Tollgate Review Has the team implemented the solution, and a control plan to insure the process is robust to change? International Standards for Lean Six Sigma 19 Lean Six Sigma DMAIC Improvement Process Define Define the opportunity from both the customer and business perspective Measure Understand the baseline process performance Analyze Identify the critical X factors and root causes impacting process performance Improve Develop solutions linked to critical x’s Control Implement solutions & control plan Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 20 Evaluating Solutions Against Criteria (Optional) Example: Independent Solutions Solutions Solution A % Contribution of Root Cause to Process Deficiency 250 100% Root Cause #1 40% 200 80% 150 60% 100 40% 50 20% 0 0% Root Cause #2 25% Root Cause #3 20% Root Cause #4 10% 80% Solution B 20% Solution C 30% 80% 100% Solution D Solution E 20% 5% #1 #2 #3 #4 Root Causes Solution A = a 32% reduction in defects (80% of 40%) Solution B = a 21% reduction in defects (20% of 25% + 80% of 20%)=(5%+16%) Solution C = a 17.5% reduction in defects (30% of 25% + 100% of 10%)=(7.5%+10%) Implementing Solutions A & B achieve a 53% reduction in defects. (Assumes no interaction effects of the solutions) Original goal is a 50% reduction. Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 21 Design of Experiments (DOE) Results (Optional) M a i n E f f e c ts P l o t ( d a ta m e a ns ) f o r M e a n T rain in g D o llars 60 Je t s 45 Mean of Mean 30 15 0 -1 1 -1 1 E m p lo y e e s 60 % O v e rb o o k e d 45 30 15 0 -1 1 -1 1 The number of Employees is the biggest driver for Mean Time Late P a r e to C h a r t o f th e S ta n d a r d i z e d E f f e c ts ( r e s p o n s e is M e a n , A lp h a = .0 5 ) 2 .6 C BD D Te rm CD A AB Pareto Chart for Mean Time Late B AC 0 50 100 150 200 S t a n d a r d iz e d Ef f e c t 250 N am e A T ra in in g D o lla rs B J e ts C E m p lo y e e s D % O v e rb o o k e d P 0.000 0.573 0.676 0.000 0.088 0.591 0.788 0.619 0.591 0.066 0.359 Employee is the only statistically significant factor for Mean besides the constant term. All other main effects & 2-way interactions have a p-value > 0.05. Ymean=f(x) equation is: Ymean = -27.97(Employee) + 29.64 BC AD F a cto r Fractional Factorial Fit: Response = Mean Estimated Effects and Coefficients for Mean (coded units) Term Effect Coef SE Coef T Constant 29.64 0.08610 344.22 Training 0.10 0.05 0.08610 0.60 Jets -0.08 -0.04 0.08610 -0.44 Employee -55.93 -27.97 0.08610 -324.81 % Overbo 0.36 0.18 0.08610 2.11 Training*Jets -0.10 -0.05 0.08610 -0.57 Training*Employee 0.05 0.02 0.08610 0.28 Training*% Overbo 0.09 0.05 0.08610 0.53 Jets*Employee 0.10 0.05 0.08610 0.57 Jets*% Overbo -0.40 -0.20 0.08610 -2.34 Employee*% Overbo 0.17 0.09 0.08610 1.01 300 350 Number of Employees is the only significant factor for Mean - Time Late Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 22 Pugh (Selection) Matrix (Optional) Pugh Matrix Importance Rating Benchmark Option Alternative 1 Alternative 2 Alternative 3 Alternative 4 Alternative 5 Solution Alternatives Criteria 1 4 + S + + - - Criteria 2 2 S - S + + + Criteria 3 3 - + - + S S Criteria 4 2 + S + + - + Criteria 5 5 S - S S + S Criteria 6 6 - - - - - - Criteria 7 10 + + + + + + Criteria 8 8 S S S S S S Criteria 9 5 - - - - - - Criteria 10 6 + + - + + + Concept Selection Legend Better + Same S Worse - Key Criteria Sum of Positives 4 3 3 6 4 4 Sum of Negatives 3 4 4 2 4 3 Sum of Sames 3 3 3 2 2 3 Weighted Sum of Positives 22 19 16 27 23 20 Weighted Sum of Negatives 14 18 20 11 17 15 8 1 -4 16 6 5 Totals Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 23 Benefit-Effort Matrix (Optional) Benefit Highly Desirable Opportunities Projects in upper left are the most desirable projects. High 16 7 1 8 12 Potentially Desirable Opportunities Projects in the upper right are potentially desirable, but usually require more analysis to ensure good decision making. 3 Med 4 17 13 9 10 Low 6 14 11 5 Low 15 Med 2 High “Potential Quick Hits” Possibility for Kaizen event or small GB project Least Desirable Opportunities Projects in the lower right are the least desirable. Effort Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 24 Stakeholder Analysis (Optional) Stakeholder Analysis 4 3 3 2 2 1 1 1 Strongly Against Moderately Against Neutral 1 0 Moderately Supportive Strongly Supportive Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 25 Influence Strategy (Optional) Influence Strategy Stakeholder Issues/Concerns Identify "Wins" Influence Strategy Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 26 Measurement Systems Analysis (MSA) (Optional) Reported by : Gage Tolerance: name: Date Misc: of study : Gage R&R Measurement system is acceptable with the Total % Contribution <10% Response by Part % Contribution Percent % Study Var 10.00 9.75 50 9.50 0 Gage R&R Repeat Reprod 1 Part-to-Part 2 3 R Chart by Operator 1 2 3 0.10 5 6 7 8 9 10 Response by Operator UCL=0.1073 10.00 9.75 _ R=0.0417 0.05 4 Part 9.50 0.00 LCL=0 1 2 Operator Xbar Chart by Operator 1 10.00 9.75 2 3 Operator * Part Interaction 3 UCL=9.8422 __ X=9.7996 LCL=9.7569 Operator 10.00 Average Number of Distinct Categories = 7 Components of Variation 100 Sample Range Study Var %Study Var Source StdDev (SD) (6 * SD) (%SV) Total Gage R&R .039870 0.23922 19.22 Repeatability 0.023594 0.14156 11.38 Reproducibility 0.032140 0.19284 15.50 Operator 0.018488 0.11093 8.91 Operator*Part 0.026290 0.15774 12.68 Part-To-Part 0.203531 1.22118 98.13 Total Variation 0.207399 1.24439 100.00 Gage R&R (ANOVA) for Response Sample Mean %Contribution Source VarComp (of VarComp) Total Gage R&R 0.0015896 3.70 Repeatability 0.0005567 1.29 Reproducibility 0.0010330 2.40 Operator 0.0003418 0.79 Operator*Part 0.0006912 1.61 Part-To-Part 0.0414247 96.30 Total Variation 0.0430143 100.00 9.50 1 2 9.75 3 9.50 1 2 3 4 5 6 Part 7 8 9 10 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 27 Pull System (Optional) 1. Always pull stock from bin with GREEN card if it is there. 2. Store/supply room replaces stocked items and switches RED card to items just replaced. 3. The cards are attached to magnetic strip labels (for ease of movement for resizing). Bin 1 Order Cards Bin1Bin 1 2 Bin 1 Bin 2 Bin 1 Bin 2 Bin 2-Bin Mailbox Bin Bin 1 1 Bin Bin 2 2 Bin 1 Bin 2 Bin 1 B in 2 Bin 1 Bin 2 Bin 1Bin 2 Bin 1 Bin 1 Bin 2 Bin 1 Bin 1Bin 2 Bin 1 Bin 2 Bin 1 Bin 2 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 28 Setup Reduction (Optional) Setup Documentation Worksheet MACHINE: DOCUMENTOR: DATE: PAGE 1 OF 1 SEQ # START TIME 1 0 2 ELAPSED TIME INT Shut down machine :30 :30 0:30 Get change parts 3:00 3 3:30 Remove change parts from machine 3:30 3:30 4 7:00 Place new change parts on machine 3:30 3:30 5 10:30 Return change parts to storage 3:00 6 13:30 Load material onto machine 1:00 1:00 7 14:30 Generate test piece :30 :30 8 15:00 Measure and inspect 2:00 2:00 9 17:00 Adjust dies 1:00 1:00 10 18:00 Generate test piece :30 :30 11 18:30 Measure and inspect 1:30 1:30 12 20:00 Generate first good piece 1:00 1:00 EVENT TOTAL TIME THIS PAGE: 21:00 TOTAL TIME ALL PAGES: 21:00 EXT 3:00 3:00 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 29 PDCA (Optional) Plan: ? ? Do: ? ? Check: ? ? Act: ? ? ? Plan ? Do ? Check ? Act Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 30 5s (Optional) Sort ? ? Set Order ? ? Shine ? ? Standardize ? ? Sustain ? ? 5s FORM IDENTIFICATION ITEM NAME TAG NUMBER TAGGED BY TAG DATE CLASSIFICATION o RAW MATERIAL o TOOLS o FURNITURE o WIP o SUPPLIES o OFFICE MATERIAL o o EQUIPMENT o BOOKS/MAGAZINES FINISHED GOOD QUANTITY o OTHER (EXPLAIN) CELL / AREA REASON o UNNECESSARY o LEFTOVER MATERIAL o DEFECTIVE o UNKNOWN o NON-URGENT o OTHER (EXPLAIN) DISPOSITION REQUIRED o DISCARD o TRANSFER o o LONG-TERM STORAGE o OTHER (EXPLAIN) IN-CELL STORAGE o REDUCE ACTION TAKEN ACTION DESCRIPTION APPROVED BY DATE NEW LOCATION NEW CELL / AREA Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 31 Kaizen (Optional) Monday Typical Kaizen Weekly Schedule Tuesday Wednesday 8AM Mid-Week Review Measure Typical Kaizen Weekly ScheduleWeekly Calendar Status Thursday Finalize Pre-Event Prep 10AM Implement Improvements Future State Des (Present State Analysis) Perform Process Participant Training Implement Improvements XX/XX Pre-work 12PM Lunch 3. Gather Data (Demand, Quality, Headcount, WIP, Downtime, Overtime, Safety, Before Pics) Lunch Finalize Future State Complete Training on Std Work Tweak Design Final Presentation Analyze 1. Review Scope, Goals, Objectives, and Deliverables With Senior Staff 2. Select Team Leader 2A. Select Team Members 2B. Inform Team Members Friday Future State Des Lunch Lunch Lunch and Celebration 4. Set Meeting Rooms, Food, Develop Team Tool Box Kaizen Kickoff XX/XX Monday 2PM 1. Kaizen Kickoff (Senior Staff Representative) 2. Kaizen Training (Lean Principles) & Specialized for Project Lean/Kaizen Training Analyze Specialized Training Idea Effort/Impact 3. Review Project Scope, Goals (SMART), Deliverables with Team 5. Train Team Members in Timestudy Basics and Begin Observation and Data Gathering Perform Process Participant Training Idea Prioritization 4. Assign Tasks for Process Observations, Timestudies, 5-S, Spaghetti Charts, Takt Time Chart Future State Design 4PM Tweak Design Measure XX/XX Tuesday Create and Implement Standard Work Implement Improvements Brainstorm Ideas Measure Future State Calculate Actual Benefits (Present State Analysis) 1. Complete Present State Analysis Using All Appropriate Data Process Part Design Review 2. Brainstorm Based on Goals & Objectives, Ergonomics, Safety, & Waste Elimination 6PM 3. Create Future State Analysis and Action Plan Create Final Presentation 4. Team Lead and Consultant Review FSA With Senior Staff 5 Launch Sub-Teams and Complete Plan Step 1 XX/XX Wednesday 1. Complete Action Plan Time 2. Train Process Participants in New Process Activity 1-1 3. Fine-tune New Process and Take After Digital Pics Step 2 Step 3 Time Time Activity 2-1 Activity 3-1 Time Time Time Activity 1-2 Activity 2-2 Step 4 Time Activity 4-1 Step 5 Time Activity 5-1 Step 6 Time Activity 6-1 4. Retime and Compare to Goals, Objectives XX/XX Thursday 1. Run New Process and Assess Effectiveness 2. Calculate Improvements in Cycle Time, WIP, Cost Savings, Etc. 3. Complete New Takt Time Cycle Time Bar Chart and Create 30 Day Follow-up List 4. Complete New Standard Operating Procedure 5. Prepare Presentation, Assign Presenters XX/XX Friday 1. Practice Presentation 2. Present to Senior Staff 2A. Set 30 Day Follow-up 3. Celebration Luncheon and or event 2B. Create Final Report & Monitor Results Time Time Time Activity 4-2 Activity 5-2 Activity 6-2 Time Time Time Time Time Activity 1-3 Activity 2-3 Activity 4-3 Activity 5-3 Time Time Time Time Activity 1-4 Activity 2-4 Activity 4-4 Time Time Time Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 32 Benchmark Analysis (Optional) CTQ Process Capability (X/Y) Benchmark Gap / Opportunity Source Assumptions Risks Based on the information above, what is the performance objective*? • Reduce defects by % • Reduce long-term DPMO from to . • Improve short-term Z from to . *If you do not benchmark, performance standards are based on: • For a process with 3 sigma level, decrease % defects by 10x. • For a process with > 3 sigma level, decrease % defects by 2x. • Other….please explain (corporate mandate, compliance/legal, VOC data, etc) Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 33 e ntim 4.0 Enter Key Slide Take Away (Key Point) Here ic Pr e r de Re rL la tio ea ns d Ti hi m p Ne e M w an Pr ag od em uc en tD t ev el op m Br en an Pr t od d Im uc ag tO e ffe rin Pr g ox Br im ea ity dt h to Cu st om er Sp ec i CTQ Importance al O % De liv Co er y m pl et e W O rd ar er ra nt y Re tu In rn ve s nt or y Tu Co rn s rre ct In vo ic e O Key Buying Factor Analysis (Optional) Company Comp 1 International Standards for Lean Six Sigma Comp 2 Comp 3 10.0 9.0 8.0 7.0 6.0 5.0 34 Pilot Plan (Optional) Pilot Test Hand-Chek/ Hot-Chek Interface Test Description • • • • Check-in Verification Test • • • • • Check-in Validation Test • • • Sample Check-in Data entered in Hand-Chek device Sample Data Sets Transmitted to Hot-Chek System – All Hotel Floors, All Hotel Rooms Confirmation Data Received from Hot-Chek to HandChek Device – All Hotel Floors &Rooms • Sample Guest Data Entered in Hot-Chek System (variety of room requirements) “Guests” (Hotel Employees) Walked Through Check-in Process (90% Pre-Registered, 10% Non-PreRegistered) Volume Stress Test – Simulated Arrival 20 Guests in a “Tour Bus” Process Measurements recorded via Observer (see Design Scorecard); “Guest” Observations Recorded. • 25 Guests invited to experience hotel check-in Guests “pre-registered” with their room requirements in Hot-Chek system. Guests Walked Through Check-in Process (90% PreRegistered, 10% Non-Pre-Registered) Process Measurements recorded via Observer (see Design Scorecard) Guests Debriefed Following Experience. • • • • • • • • • Success Criteria Test Team Schedule Data Set Entry Accuracy < 3.4 DPMO Data Time < 6 Sec Data Transmission/ Accuracy < 3.4 DPMO SB, plus HotChek tech rep Start 3/1 Complete 3/3 Data Set Entry Accuracy < 3.4 DPMO Data Set Entry Time < 6 Seconds Data Set Transmission/ Reception Accuracy < 3.4 DPMO Design Scorecard CCRs SB, + 6 Check-in Staff Start 3/6 Complete 3/7 Data Set Entry Accuracy < 3.4 DPMO Data Set Entry Time < 6 Seconds Data Set Transmission/ Reception Accuracy < 3.4 DPMO Design Scorecard CCRs SB, + 6 Check-in Staff Start 3/10 Complete 3/10 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 35 Verify Pilot Results (Optional) Measurement Plan: Plan Target Measure Pilot x CTQs Process time 1 minute 0.5 min. CTQs Data Transmission Accuracy < 3.4 DPMO 100 DPMO Pilot Observations: s Comments 0.05 min. 1) Data Reception Weak – 12th Floor, SW Rooms 2) Data Entry Sequence Confusing GAP Analysis/Root Causes: 1) Insufficient radio transceivers, 12th Floor 2) Order of questions confusing staff Follow-up Actions: 1) Add four more radio transceivers 2) Resequence guest questions Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 36 Summarizing Pilot Conclusions (Optional) Once all the pilot data has been collected and the results verified, the team can determine the next steps toward solution implementation. Only after an objective and comprehensive assessment of the pilot can responsible “next step” decisions be made. Some questions a team should ask upon the completion of a pilot to help guide them toward identification of the proper next steps are: Did pilot have anticipated results? Was the plan for conducting the pilot effective? What improvements can we make to the solution? Can the solution be implemented “as-is”? Should it be? Can the solution remain in place at the pilot location? What lessons learned and best practices can we apply during solution implementation? Did the solution achieve the required design goals? Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 37 Kaizen Action Workout (Optional) Planning Execution Before ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? Graphical Analysis Root Causes / Quick Wins Root cause: Quick Root cause: Quick Win #1 Win #2 Root cause: Quick After ? ? ? ? ? ? ? ? ? ? Win #3 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 38 Technical-Political-Cultural TPC Analysis (Optional) Technical-Political-Cultural (TPC) Analysis Sources Of Resistance Definition Causes Of Resistance Rating Examples Technical Political Cultural Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 39 Multi-Generational Project Plan (Optional) MGPP Gen1 Gen2 Gen3 Target Date Vision Key Functionality Technology Requirements Target Customers Metrics Dependencies Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 40 Cost/Benefit Analysis (Optional) Identify the various solution options Describe the Type 1 solution $ gained from the expected process improvement Calculate the total cost of ownership to fully implement the solution Cost/Benefit Analysis Financial Benefits: First 12 months after Budget Increase Implementation Expense Reduction Loss Avoidance Other Total Benefits Financial Cost: Labor Pre-Implementation & Technology first 12 months after Materials Other Total Cost Cost/Benefit Solution A Solution B Solution C $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Enter Key Slide Take Away (Key Point) Here International Standards for Lean Six Sigma 41