Chapter 10 Monitoring and Information Systems Jason C. H. Chen, Ph.D. Professor of MIS School of Business Administration Gonzaga University Spokane, WA 99258 chen@jepson.gonzaga.edu Dr. Chen, Special Topic: Project Management 1 Project Management Dr. Chen, Special Topic: Project Management Figure Project Triangle (Project Management Trade-offs) Cost [budget] Time [schedule] The center of project triangle is QUALITY Scope [performance] The objective of the PM is to define project’s scope realistically and ultimately deliver quality of product/service on time, on budget and within scope. Dr. Chen, Special Topic: Project Management Project Management versus Process Management “Ultimately, the parallels between process and project management give way to a fundamental difference: process management seeks to eliminate variability whereas project management must accept variability because each project is unique.” Elton, J. & J. Roe. “Bringing Discipline to Project Management” Harvard Business Review Dr. Chen, Special Topic: Project Management Terms • Monitoring - Collecting, recording, and reporting information concerning any and all aspects of project performance • Controlling - Uses the data supplied by monitoring to bring actual performance into compliance with the plan • Evaluation - Judgments regarding the quality and effectiveness of project performance Dr. Chen, Special Topic: Project Management The Planning–Monitoring–Controlling Cycle • We mainly want to monitor: – Time (schedule) – Cost (budget) – Scope (project performance) • Closed-loop system – Revised plans and schedules following corrective actions Dr. Chen, Special Topic: Project Management Project Authorization and Expenditure Control System Information Flow Dr. Chen, Special Topic: Project Management Figure 10-1 Designing the Monitoring System • Identify key factors to be controlled: – – – • Scope Cost Time Information to be collected must be identified. Dr. Chen, Special Topic: Project Management Designing the Monitoring System Continued • Do not want to avoid collecting necessary data because it is hard to get. • Do not want to collect too much data. • The next step is to design a reporting system that gets the data to the proper people in a timely and understandable manner. Dr. Chen, Special Topic: Project Management Data Collection • Once we know the data we want, we need to decide how to collect it. • Should the data be collected after some event? – Order and/or precedence • Should it be collected on a regular basis? • Are there any special forms needed for data collection? Dr. Chen, Special Topic: Project Management Data/Information … BAD information is WORSE than ... NO ________information. Dr. Chen, Special Topic: Project Management Attributes of Data/Information Quality We realize that a firm needs better information to survive and prosper. Therefore, high quality information products have to be provided to management. Dr. Chen, Special Topic: Project Management Attributes of Data/Information Quality Dr. Chen, Special Topic: Project Management Much Data Involves • • • • • Frequency counts Raw numbers Subjective numeric ratings Indicators Verbal measures Dr. Chen, Special Topic: Project Management Information Needs and Reporting • Everyone should be tied into the reporting system – see order management slide • Reports should address each level • Not at same depth and frequency for every level – Lower-level needs detailed information – Senior management levels need overview (i.e., summarized) reports • Report frequency is typically high at low levels and less frequent at higher levels Dr. Chen, Special Topic: Project Management The Reporting Process • • • • Reports must contain relevant data. Must be issued frequently. Should be available in time for control. Distribution of project reports depends on interest – For senior management, may be few milestones (what is it?) – For project manager, there may be many critical points Dr. Chen, Special Topic: Project Management Gantt Chart critical vs. non-critical Milestone (for “Design” phase) Shows time estimates of tasks A milestone represents an event or condition that marks the completion of a group of related tasks or the completion of a phase of the project. If any activity on critical path delayed, the overall project time will be increased Dr. Chen, Special Topic: Project Management Benefits of Detailed and Timely Reports • Mutual understanding of the goals • Awareness of the progress of parallel activities • Understanding the relationship of tasks • Early warning signals of problems • Minimizing the confusion • Higher visibility to top management • Keeping client up to date Dr. Chen, Special Topic: Project Management Report Types • • • • Routine - Reports that are issued on a regular basis or each time the project reaches a milestone Exception - Reports that are generated when an usual condition occurs or as an informational vehicle when an unusual decision is made Special Analysis - Reports that result from studies commissioned to look into unexpected problems All are linked to data (database, knowledge base etc.) Dr. Chen, Special Topic: Project Management Meetings • • • • Reports do not have to be written They can be delivered verbally in meetings Projects have too many meetings The trick is to keep them to as few as possible Dr. Chen, Special Topic: Project Management Meeting Rules • • • • • Use meetings to make group decisions Start and end on time and have an agenda Do your homework before the meeting Take minutes (what is minutes?) Avoid attributing remarks to individuals in minutes • Avoid overly formal rules of procedure • Call meeting for serious problems Dr. Chen, Special Topic: Project Management Common Reporting Problems • Too much detail • Poor interface between the data/procedures of the project and the information system of the parent company • Poor correspondence between the planning process and the monitoring process Dr. Chen, Special Topic: Project Management Earned Value Analysis • A valuable technique for monitoring overall project performance is earned value. • One way is by using an aggregate performance measure called earned value. • Have covered monitoring parts – Timing and coordination between individual tasks is important • Must also monitor performance of entire project – Crux of matter should not be overlooked Dr. Chen, Special Topic: Project Management The Earned Value Chart and Calculations • The Earned Value Chart and Calculations – The key element of the earned value technique is the measurement of progress in addition to cost and schedule. – If progress is not measured, then data about cost and schedule is meaningless because the PM does not know what resulted from the expenditures. Dr. Chen, Special Topic: Project Management The Earned Value Chart and Calculations (cont.) • Actual against baseline ignores the amount of work accomplished • Earned value incorporates work accomplished • Multiply the “estimated percent work complete” for each task by the “planned cost” • Only need percent complete estimate for tasks currently in progress. Dr. Chen, Special Topic: Project Management Rules to Aid in Estimating Percent Completion • 50-50 rule – Taking credit for 50% complete when the task begins and the other 50% when the task ends (50-50 estimate). • 0-100 percent rule – Taking no credit for progress until the task completes (0-100 rule). Dr. Chen, Special Topic: Project Management Rules to Aid in Estimating Percent Completion • Critical input use rule – Taking credit for progress based on the use of a critical input. This works only if the process consuming the input is reliable and well defined. • Proportionality rule – Taking credit for progress based on either the percent of the budget that has been expended or the percent of the elapsed time that has gone by (proportionality rule). Dr. Chen, Special Topic: Project Management The Earned Value Chart EAC = ETC + AC Dr. Chen, Special Topic: Project Management Figure 10-6 Variances • Variances can help analyze a project 1. A negative variance is bad 2. Cost and schedule variances are calculated as the earned value minus some other measure • Will look at some of the more common ones CV = EV – AC Dr. Chen, Special Topic: Project Management Cost Variance (CV) • CV = EV – AC • EV: earned value • AC: actual cost of the work • Negative variance indicates a cost overrun • Magnitude depends on the costs Dr. Chen, Special Topic: Project Management Schedule Variance (SV) • SV = EV – PV • PV: planned value (the cost of the work we scheduled to be performed to date) • Negative variance indicates you are behind schedule • Measured using costs Dr. Chen, Special Topic: Project Management Time Variance (TV) • TV = ST – AT • ST: time scheduled for the work that has been performed • AT: actual time used to perform • Negative variance indicates you are behind schedule TV = SV / slope Slope = PV / Days Dr. Chen, Special Topic: Project Management Indices • Cost Performance Index CPI = EV/AC • Schedule Performance Index SPI = EV/PV • Time Performance Index TPI = ST/AT • Cost Schedule Index CSI = EV2/(AC)(PV) Dr. Chen, Special Topic: Project Management Summary on Variances and Indices CV = EV – AC CV: cost variance EV: earned value AC: actual cost of the work SV = EV – PV SV: schedule variance PV: planned value (the cost of the work we scheduled to be performed to date) TV = ST – AT TV: time variance ST: time scheduled for the work that has been performed AT: actual time used to perform Dr. Chen, Special Topic: Project Management • Cost Performance Index CPI = EV/AC • Schedule Performance Index SPI = EV/PV • Time Performance Index TPI = ST/AT • Cost Schedule Index CSI = EV2/(AC)(PV) TV = SV / slope Slope = PV / Days “To complete” and “At Completion” • Project manager reviewing what is complete and what remains • Final cost and final completion date are moving targets • The project manager compiles these into a to complete forecast • Actual + forecast = final date and cost at completion Dr. Chen, Special Topic: Project Management ETC and EAC ETC = (BAC + EV)/CPI EAC = ETC + AC where, ETC = Estimated cost to complete BAC = Budget at completion EV = Earned value CPI = Cost performance index EAC = Estimated cost at completion AC = Amount expended to date (actual cost) Dr. Chen, Special Topic: Project Management Milestone Reporting • Reports that are created when a project reaches a major milestone • They are designed to keep everyone up-todate on project status • For executives and clients, these may be the only reports they receive Dr. Chen, Special Topic: Project Management Computerized PMIS (Project Management Information Systems) • Real projects are often large – Hundreds of tasks – Thousands of work units • Reporting is clearly a job for the computer • Project management information systems were one of the earlier applications • Initially focus was on scheduling • Now it includes, earned values, variances, and more Dr. Chen, Special Topic: Project Management PMIS Errors • • • • • Computer paralysis Information overload Project isolation Computer dependence PMIS misdirection Dr. Chen, Special Topic: Project Management Creating a Project Budget WBS Project Plan Scheduling • Top-down • Bottom-up Dr. Chen, Special Topic: Project Management Budgeting The budget is a plan that identifies the resources, goals and schedule that allows a firm to achieve those goals VIDEO • VIDEO: • 7. An_Introduction_to_the_Earned_Value_M easurement_System(15m) • 8. Value_Driven_Project_Mgt(9m28s) Dr. Chen, Special Topic: Project Management Problem 1: ($000) Month 22 CV SV AC $540 $(5) $12 PV EV $523 $535 Unfavorable Favorable EV: earned value AC: actual cost of the work Dr. Chen, Special Topic: Project Management CV = EV – AC SV = EV – PV Negative variances are unfavorable. Problem 2: ($000) Month AC 5 $34 CV $5 CPI 1.15 SV $(3) SPI 0.93 PV $42 EV $39 Favorable CV = EV – AC CPI = EV/AC SV = EV – PV SPI = EV/PV Unfavorable Negative variances are unfavorable. If an index is less than one, the variance is unfavorable. PV: planned value (the cost of the work we scheduled to be performed to date) Dr. Chen, Special Topic: Project Management Problem 3: ($000) Day 70 CV CPI SV SPI CSI TV AC $78 $3 1.04 $(3) 0.96 1.00 (2.50) PV $84 EV $81 Favorable Unfavorable On target Days delayed CSI = (CPI)(SPI) TV = SV / slope Slope = PV / Days CSI is on target because the unfavorable SV is offset by the favorable CV. TV predicts that the project is 2.5 days behind schedule given the estimated EV. Dr. Chen, Special Topic: Project Management Problem 4: ($000) Month AC 17 $350 CV $(50) CPI 0.86 SV $(175) SPI 0.63 CSI 0.54 PV $475 EV $300 Unfavorable Unfavorable Unfavorable Cost Performance Index CPI = EV/AC Schedule Performance Index SPI = EV/PV Time Performance Index TPI = ST/AT Cost Schedule Index CSI = EV2/(AC)(PV) Dr. Chen, Special Topic: Project Management This project is seriously delayed (SPI) and also over budget (CV). Problem 5: ($000) Month 10 CV CPI SV SPI CSI AC $23 $(3) 0.87 $3 1.18 1.03 PV $17 EV $20 Unfavorable Favorable Favorable This project is ahead of schedule, but has an unfavorable CV. Dr. Chen, Special Topic: Project Management Problem 6: ($000) Day 65 CV CPI SV SPI CSI TV AC = $550 AC PV EV $550 $735 $678 $128 Favorable 1.23 $(57) Unfavorable 0.92 1.13 Favorable (5.00) Days behind Day 65 CV CPI SV SPI CSI TV AC = $750 AC PV EV $750 $735 $678 $(72) Unfavorable 0.90 $(57) Unfavorable 0.92 0.83 Unfavorable (5.00) Days behind The first step is to estimate EV. Starting with TV, we solve to determine SV. Once SV is known, EV can be determined because the PV was given. In problem 6, changing the AC value only affects cost-related measures and indices. The SV and SPI are unaffected by a change in AC. Dr. Chen, Special Topic: Project Management Problem 7: ($000) CV CPI SV SPI CSI AC $10.0 $(1.6) 0.84 $(3.6) 0.70 0.59 PV $12.0 EV $8.4 Unfavorable Unfavorable Unfavorable In this problem, EV = 70% PV. This client is probably upset because the CSI suggests that this project is likely to be delayed and to cost more than originally planned. Dr. Chen, Special Topic: Project Management