Mordialloc Creek Dredging Program Outline 2011 - 2012 Contents 1. 2. 3. 4. 5. 6. 7. Background Program Scope Stakeholders Program Pre-conditions Funding Arrangements Related works program Sustainable Management Plan 1. Background • Natural tidal creek • Heavily modified by channels, revetments, training walls. • Was the natural outlet of the Carrum Swamp • Historic boat harbour • Upstream now more estuarine condition Dredging history • Melbourne Water performed dredging in the past • No significant dredging in section A since 1997 • Section B was last done in 2000 • Some maintenance dredging since 2000 Mordialloc Village • Important Council focus – Mordialloc Master Plan • Structure plan for the area – Historic fishing village and boat harbour – Commercial and recreational hub Mordialloc Creek • Responsible Agencies – Melbourne Water – City of Kingston – Parks Victoria – Dept Sustainability & Environment – EPA Victoria • Affected Agencies – Victrack – Vic Roads Mordialloc Creek (cont) • Melbourne Water Responsibilities – Manage and monitor the health of rivers, creeks and wetlands – Manage the regional drainage system – Provide a safe level of flood protection – Regulate works on rivers and creeks – Make sure urban development is safe and meets flood and environment standards. Mordialloc Creek (cont) • Kingston CC Responsibilities – Be the Committee of Management for the nominated Crown Land • • • • • Manage the reserve Develop the reserve Enter into contracts Enter into tenure arrangements Enforce regulations 2. Program Scope • PHASE 1 – Lambert Island Section • Tasks • Tender & Contract • Consents & Approvals • PHASE 2 – Sections A, B & C • Tasks • Tender & Contract Dredging Tasks • Method • Barge mounted bucket excavator • Partially dewatered in a hopper barge • Cationic polymer added to trap ASS and pollutants • Floating silt curtain to trap plume • Timing to avoid fish breeding times • Class C contaminated silt disposal to landfill Dredging Sections Channel Profiles 3. Stakeholders • Community – Residents – Mordialloc Creek Community – Commercial Operators – Village Traders’ Group • Agencies – DSE – MW – PV 4. Program Preconditions • Stage 1 – Consent from DSE – Consent from EPA Victoria • Stage 2 – Funding from State Government – Sustainable Management Plan – MOU joint management with PV and MW 5. Funding Arrangements • Stage 1 – City of Kingston • Stage 2 – State Government – City of Kingston (related or ancillary works) 6. Related Works • • • • • Mooring pole replacements Landings & Jetties Revetments, walls Slipways Other – Wave barriers (PV) – Training walls (PV) – Structure / Master plan items 7. Sustainable Master Plan • Precondition for 10 year consent • Will look at sustainable dredging practice • Will look at sustainable funding arrangements • KCC + MW + PV joint plan • May set rules on boat size / operation