DREDGING YOUR DOCKS 2014 Organized By CRA Hydrographic Surveyors Orion Marine Group DREDGING YOUR DOCKS 2014 Supported by USCOE Galveston District U. S. Coast Guard Port of Houston Houston Pilots Lone Star Harbor Safety Com. Dredging Cost Presentation Dredging private dock terminals Focus on hydraulic dredging Total project cost to owners Industry standards & requirements Dredging Cost Project Specific Disposal Surveys Permitting Environmental External Cost Impacts •Identifying the scope of work: • Project location • Cubic yards of material • Dredging template • Over-dredge requirements • Type of material •Choosing a Dredge: •Dredge Size •Project Specific requirements •Type of material •Pumping capacity •Location •Schedule • Selecting A DMPA • Federal DMPA • Private DMPA • Uplands • Beneficial Use •Dredge material placement area requirements (DMPA) •DMPA location •DMPA Specific requirements •Pipeline route •Discharge Point •Crossings •Ship Channel – Road •Levee systems •Capacity •Dredge Pipeline Cost • Distance from Project to DMPA • Floating, submerged, & land • Pipeline route • Discharge Point • Crossings - Ship Channel – Road •Dredging Cost Breakdown •Mobilization / Demobilization •Pipeline Cost •Cubic Yard •Unknowns • anomalies, debris, & delays •Disposal Cost • based on gross yardage • management fees • sediment samples DISPOSAL COST •DMPA COST • Disposal Fees • Deposit & Contract Signing • Payment of Gross CY dredged • Sediments Sampling Cost • Management Fees • Application – Consulting DISPOSAL COSTS (per cu/yd.) $10 $8 $6 $4 $2 $0 2000 2005 2007 2009 2012 2015 FUEL COSTS $4.00 $3.00 $2.00 $1.00 $0.00 2001 2003 2005 2007 2012 STRUCTURAL STEEL COSTS (per ton.) $80 $70 $60 $50 $40 $30 $20 $10 $0 2003 2005 2007 2012 Project “A” Project “A” Project “A” Project “B” Project “B” Project “B” PROJECT “A” & “ B” Project “A” 115,000 cy x 8 days = 14,375 cy per dredging day Project “B” 13,000 cy x 5 days = 2,600 CY per dredging day PROJECT “A” & “B” Overview Same dredge spread Pipeline & DMPA Similar dredge template Projects shared the mobilization cost Cost per CY is 5 times for Project “B” than “A” HYDROGRAPHIC SURVEY • • • • Pre-Dredge Survey by Contractor Pre-dredge survey by Third Party Verify, Quantities, Tide Gauge, & intervals Verify survey datum and station #’s • • • Post dredge survey by Surveyor & Contractor Post-Dredge Survey review Pay DMPA & Contractor Permit Requirements • TCEQ Water Quality Certification • USACE Permits •Regulatory •Real Estate • NWP Permits • DMPA Permits EXTERNAL COST • Environmental Impacts • Economic Development • Government Requirements • USACE Regulatory • USACE Real Estate • EPA •TCEQ • Legal – Jones Act DREDGING COST SUMARY •Plan Dredging Activities •Have Permits in Order •Piggy Back off USACE •Share Mobilization Cost with Neighbors •Coordinate DMPA Contracts Early “Not all Dredges are Created Equally” THANK YOU FOR ATTENDING DREDGING YOUR DOCKS 2014