Yankee Airforce Museum, Van Buren Twp
MDOT’s Mission
Providing the highest quality
integrated transportation services
for economic benefit and improved
quality of life.
Introduction
 I-96 freeway originally opened in 1971
 Has served community for over 40 years
 Has exceeded its service life
Meeting Purpose
 Update design progress
 Decision to close the freeway
 Review Construction Staging
 Obtain input on corridor aesthetics
(landscaping, colors, etc.)
 Gather input on potential
project/construction impacts
How Did We Get Here?
On March 1, 2012, MDOT hosted the first public
meeting to present:
 General project information
 Eleven different options for maintaining traffic during
construction, including the preference on whether to
close the freeway or keep lanes open through the work
zone
How Did We Get Here?
 More than 1,700
people responded to a
survey asking which
options were preferred:
TO OPEN or TO CLOSE
the freeway during
construction
 56 percent of
respondents preferred
full closure, favoring
minimized construction
duration
What We are Doing
MDOT is working with the following stakeholders to
mitigate reconstruction concerns, including but not
limited to:
 Wayne County
 City of Livonia
 Redford Township
 Detroit Water and Sewer Department
 Various School Districts
 Business Owners
 Residents
What We are Doing
Rebuild / Upgrade
 Road Reconstruction
 Bridge Repairs
 Geometric Upgrades
 Drainage
 Freeway Lighting
 Signing
 Landscaping
Project Scope
Rebuild / Upgrade
 Seven miles of eight-lane freeway
• Six full-service interchanges
• On and off ramps serving businesses and residential areas
 37 Bridges
• Bridge work scopes range from minor rehabilitation to
replacement
Project Scope
 Freeway Lighting
Rebuild / Upgrade
• New lights will last longer and require less maintenance
• LED lamp options under evaluation
 Aesthetic Treatments for:
•
•
•
•
•
Barriers, bridges, retaining walls, and mainline shoulders
Bridge fencing
Service drive fencing and paving
Paint color selections for new/existing structures
Right‐of‐way landscape plantings
Project Scope
Rebuild / Upgrade
 Maintaining Traffic/Access to Freeway and Local
System
• Detour around project site for through-traffic
o I-94 to south
o I-696 to north
o Westbound connection at M-39 (Southfield Freeway)
o Eastbound connection at I-275
Project Scope
Rebuild / Upgrade
 Maintaining Traffic/Access to Freeway and
Local System
• Local access across I-96 during Bridge
Repair/Reconstruction
o 31 of 37 bridges will be closed at various periods for
construction
o Six of 37 bridges will have partial closures
o MDOT will ensure that no two adjacent bridges will be closed
at the same time. As such, detours will be less impactful.
Project Scope
Rebuild / Upgrade
 Relocate changeable message signs as needed
 Improve vertical clearance under at bridges and
update freeway design
 Minimize impacts on existing walls
Project Scope
Design Challenges
 Improve on and off ramp access to local roads
 Improve drainage on the freeway
 Flatten freeway side slopes
Project Schedule
Next Steps
 Third Public Meeting will be held in mid-2013
• Present complete plan for construction, upcoming
timelines and more details
• Continue to work with business owners, residents
and motorists to address any concerns regarding the
project
Contact Information
 Ways to voice your opinion:
• Project email address: MDOT-96fix@michigan.gov
• Facebook: www.facebook.com/96fix
• Twitter: www.twitter.com/96fix
• Web site: www.96fix.com
• MDOT Taylor TSC :
6510 Telegraph Road, Taylor MI 48180
Phone: 313-375-2400
Questions?
Customer Service is Important
Please take our customer survey:
www.michigan.gov/mdot
17
Download