Africa’s Time for ACTION PIDA Rolling-Out the PAP African Development Bank Group 17th UPDEA Congress, Tunisia AfDB Dr. J. Moulot AfDB, dept. ONRI Interconnecting, integrating and transforming a continent Programme for Infrastructure Development in Africa Overview of Presentation 1 •PIDA Priority Action Plan 2 •Projects synopsis 3 •Implementation Issues 1 PAP-Energy Investment Cost: $40.3 bn Inga Hydro Phase 1 6,000 ECCAS Central African Interconnection 10,500 ECCAS Great Millennium Renaissance Dam 8,000 COMESA/ IGAD Batoka Dam 2,800 COMESA EAC Ruzizi III Dam 450 COMESA EAC Rusumo Falls Dam 360 COMESA EAC Uganda-Kenya Petroleum Products Pipeline 150 COMESA EAC North Africa Transmission Nigeria -Algeria Pipeline 1,200 AMU N/A UMA ECOWAS North South Power Transmission Corridor 6,000 COMESA EAC SADC IGAD Nphamda -Nkuwa Dam 2,400 SADC Lesotho HWP Phase II -hydropower component 800 SADC Sambagalou Dam 300 ECOWAS West African Power Transmission Corridor Kaleta Dam II Central 1,200 ECOWAS Eastern Northern Northern, Western Southern Western 179 ECOWAS 2 PAP vs. Regions and Project Types Cost in Million USD Total:40.3 billion TYPE PROJECTS 25,000 Western 4% Central 41% Million USD Southern 23% 20,000 15,000 10,000 Eastern 29% Northern 3% 5,000 0 Series1 Generation Transmission O&G Pipeline 21,289 18,900 150 3 PIDA Priority Action Plan 2020 Energy 15 items USD 40 bn The energy infrastructure program focuses on major hydroelectric projects and interconnects the power pools to meet the forecast increase in demand. One regional petroleum products pipeline is also included. 4 Overview of Presentation 1 •PIDA Priority Action Plan 2 •Projects synopsis 3 •Implementation Issues 5 GREAT MILLENNIUM RENAISSANCE DAM Cost (Million USD) 8,000 REC Involved COMESA/IGAD Beneficiary countries Technical Organizations Objectives Expected Results Project Challenges Ethiopia, Nile Basin Countries Ethiopian Electric Company / Nile Basin, EAPP Develop a 5,250 MW plant increase capacity of EEPCO six-fold (750 MW at present) Supply Ethiopian and export EAPP market Capacity of EEPCO to O&M commercially and financially plant Mobilization of financing: Some US$ 3 billion are still needed Issuance of local bonds a challenge Coordinate Generation with development of complementary transmission and distribution Consensus building with neighboring countries (Sudan, Egypt) Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 6 NORTH SOUTH POWER TRANSMISSION CORRIDOR Cost (Million USD) 6,000 REC Involved COMESA/EAC/SADC/IGAD Beneficiary countries Technical Organizations Kenya, Ethiopia, Tanzania, Zimbabwe, South Africa SAPP Objectives Transport energy of Great Millennium Renaissance Dam 8,000 km line from Egypt through Sudan, South Sudan, Ethiopia , Kenya, Malawi, Mozambique, Zambia, Zimbabwe to South Africa Cooperation/Agreements among participating countries No regional entity for Overall project development, operation and Maintenance Establishment of Cross Regional SPV Inter-regional interconnection between EAPP and SAPP Expected Results Project Challenges Malawi, Mozambique, Zambia, Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 7 NPHAMDA – NKUWA HP-DAM Cost (Million USD) 2,400 REC Involved SADC Beneficiary countries Technical Organizations Mozambique, Zambezi basin Mphanda Nkuwa Hydro-Electric Company, SAPP Objectives Export on the SAPP market Expected Results Hydroelectric power plant with a capacity of 1,500 MW Project Challenges Completion of financing plan Project structure needs to minimize risk profile and attract commercial financing Negotiation of off-take agreements ( South-Africa: Local or Hard currency?; Capacity of Energy off-take TOP contract?) High Currency Risks and hydrology risks Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 8 LESOTHO HWP PHASE II - HYDROPOWER COMPONENT Cost (Million USD) 2,400 REC Involved SADC Beneficiary countries Technical Organizations Objectives Expected Results Lesotho, South Africa, Orange-Senqu River Basin Lesotho Highlands Water Commission, SAPP IWRM to provide energy to Lesotho and water transfer to SA and ensures the water security of South Africa’s Gauteng province Lesotho Highlands Water Project Phase II consists of two separate components – a) the construction of Polihali Dam and transfer to tunnel to Katse dam, and b) the Kobong pump storage scheme hydroelectricity scheme. Project Challenges Proposed 1,200 MW pumped storage component new challenge from Phase I Financing for preparation of the pumped storage component Risks mitigation for the pumped storage component. Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 9 INGA- HYDROPOWER PHASE 1 Cost (Million USD) 6,000 REC Involved ECCAS Beneficiary countries Technical Organizations Objectives Expected Results Project Challenges DRC, Congo River Countries CAPP Contribute to energy security and Increase energy trade between DRC, Zambia and South Africa as well as DRC and Congo River Countries To Develop 4,200 MW capacity run of river hydropower station on the Congo river with eight turbines Final structure for project development yet to be established Weak capacity of SNEL as developer Large financial package not sustainable by National interest alone Power Off-take yet to be agreed Political risk of DRC Minimizing contingent liability on GODRC’s balance sheet Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 10 CENTRAL AFRICAN INTERCONNECTION Cost (Million USD) 10,500 REC Involved ECCAS Beneficiary countries Technical Organizations Objectives Expected Results Project Challenges South Africa, Angola, Gabon, Namibia, Ethiopia CAPP Develop the transmission lines associated to the Inga Site (Inga 3 and Grand Inga) 3,800 km line from DRC to South Africa through Angola, Gabon, Namibia and to the North to Eq. Guinea, Cameroon and Chad • Coordinated development of generation and transmission • Close Coordination between GoDRC and Regional Organization Establishment of single entity SPV for development /operation of Line Regional approach to reduce transit risks Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 11 SAMBAGALOU HP DAM Cost (Million USD) 300 REC Involved ECOWAS Beneficiary countries Technical Organizations Objectives Expected Results Project Challenges Senegal, OMVG countries (Senegal, Guinea, Guinea Bissau, Gambia) EBID To provide power to the OMVG Member States 128 MW of hydropower capacity, 930 km from the mouth of the Gambia River to supply Senegal, Guinea, Guinea Bissau and Gambia The project structure is still undecided. (PPP, IFI, Public Financing) Financial sustainability of Dam unproven The role of Kaleta Dam in project structure uncertain The political support at OMVG and WAPP level is strong; Country political commitment of the countries changing over time Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 12 WEST AFRICAN POWER TRANSMISSION CORRIDOR Cost (Million USD) 1,200 REC Involved ECOWAS Beneficiary countries Technical Organizations Guinea,Guinea Bissau, Gambia, Sierra Leone, Liberia, Côte d’ivoire, Ghana Objectives Expected Results Project Challenges WAPP, OMVS Ensure transmission between the countries and transport regional energy to ECOWAS countries 2,000 km line along the coast connecting with the existing Ghana Nigeria line with a capacity of 1,000 MW Coordination between WAPP, OMVS and the Governments The lack of a single point of responsibility creditworthiness of the power sector in Guinea Bissau, Guinea and The Gambia not established Establishment of single entity SPV for development /operation of Line Link sufficient generation capacities in Guinea and Cote d’Ivoire Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 13 NORTH AFRICA TRANSMISSION Cost (Million USD) 1,200 REC Involved UMA Beneficiary countries Technical Organizations Objectives Expected Results Project Challenges Morocco, Algeria, Tunisia, Libya, Egypt COMELEC Ensure transmission between the countries and transport regional energy to UMA countries 2,700 km line from Morocco to Egypt through Algeria, Tunisia and Libya Clarify role of COMELEC and the Governments Establish Trade frameworks and develop Agreements for the exchanges Regional versus National power market development advantages Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 14 BATOKA GORGE HP DAM Cost (Million USD) 2800 REC Involved COMESA/EAC Beneficiary countries Zambia/Zimbabwe Zambezi basin Technical Organizations EAPP/ Zambesi River Authority Objectives Expected Results To increase generation capacity and reduce reliance on electricity imports and improve generation mix construction of a 181 meter gravity dam; installation of 800 MW (4 x 200 MW units) for both Zimbabwe and Zambia. Transmission lines Project Challenges Mandate of Zambesi River Authority (ZRA) to raise financing or implement capital projects Special Purpose Vehicle to raise financing and implement the project yet to be created Poor Creditworthiness of participating utilities, ZESA and ZESCO Zimbabwe government classification with IFIs as defaulting Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 15 RUZZIZI III Cost (Million USD) 450 REC Involved COMESA/EAC Beneficiary countries Rwanda/DRC Technical Organizations CEPGL, EGL Objectives Share power between Rwanda, Burundi and DRC promoted by CEPGL and develop local renewable energy as well as regulation of water basin Expected Results Hydroelectric plant with a capacity of 145 MW Project Challenges Resources limitation of EGL for needs of the project The studies were launched to review the interconnection of South Kivu and North Kivu and their interface with the CEPGL interconnected network. Finalization of Establishment of a Basin Authority, necessary Finalized selection of preferered investors for PPP Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 16 RUSUMO FALLS Cost (Million USD) 360 REC Involved COMESA/EAC Beneficiary countries Technical Organizations Objectives Expected Results Project Challenges Nile River Basin Countries NELSAP Provide inexpensive electricity and improve energy security in the region • dam and hydro-electric power station of about 61 MW on the Kagera River at Rusumo Falls; • Power lines connecting the power plant to the electricity grids of Burundi, Rwanda and Tanzania. • Power sharing agreement between Burundi, Rwanda and Tanzania • Environmental issues related to flooding (could affect wetlands downstream, including in the Akagera National Park) Reservoir have a negligible effect on net evaporation Issues: Updated Status of Project; Roles of Utility, RECs and Power Pool 17 Overview of Presentation 1 •PIDA Priority Action Plan 2 •Projects synopsis 3 •Implementation Issues 18 Roles of Utilities and Power Pools Influencing, Making Commitments , Acting together… Projects Fiches Commitments and Needs - Update - Package - Capacity needs - Fill gaps (physical and soft) - Reforms needs Funding + Actions - Tariffs - Project Preparation - Creditworthiness - Maintenance and Operation A time for action MERCI OBRIGADO THANK YOU شكرا 20